RESOLUTION NO. 11-20-2006-13.07
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF COLLEGE STATION,
TEXAS, APPROVING A CONSTRUCTION CONTRACT FOR THE SPRING CREEK
SUBSTATION PROJECT AND AUTHORIZING THE EXPENDITURE OF FUNDS.
WHEREAS, the City of College Station, Texas, solicited bids for the construction phase of the
Spring Creek Substation Project; and
WHEREAS, the selection of Gulf States, Inc., is being recommended as the lowest responsible
bidder for the construction services related to Spring Creek Substation; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF COLLEGE STATION,
TEXAS:
PART 1:
That the City Council hereby finds that Gulf States, Inc., is the lowest
responsible bidder.
PART 2:
That the City Council hereby approves the contract with Gulf States, Inc.,
for $3,642,800. for the labor, materials and equipment required for the
improvements related the Spring Creek Substation Project.
PART 3:
That the funding for this Contract shall be as budgeted from the Capital
Improvement Fund, Electric Department, in the amount of $3,642,800.
PART 4:
That this resolution shall take effect immediately from and after its passage.
ADOPTED this 20th day of November, A.D. 2006.
C f)t\h..H'
CONNIE HOOKS, City Secretary
APPROVED:
~~4l
ATTEST:
BEN WHITE, Mayor Pro Tern
APPROVED:
~)/>_?"'2 _:.-.~eu Uy' '~e;(g;M,'D~~("""\-/)'-;:';! l?
. /2"7~ ~7~uthe~t~lth """P'9telt -'~- / Wj
&V ~---;;.... ~.,.' - ->,-""'~----,- ~~_-L::.,",,-z-~.
,. ..;:/
City Attorney