HomeMy WebLinkAbout03-22-12-02 - Resolution - 03/22/2012 RESOLUTION NO.03 12. - O2
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF COLLEGE STATION,
TEXAS, APPROVING A CONSTRUCTION CONTRACT FOR A TRANSMISSION
LINE TIE AND DISTRIBUTION IMPROVEMENTS AT THE CSU SWITCH STATION
SUBSTATION AND AUTHORIZING THE EXPENDITURE OF FUNDS.
WHEREAS, the City of College Station, Texas, solicited bids for the construction of a
transmission line tie with Entergy Texas, Inc. and additional Distribution improvements at the
CSU Switch Station substation; and
WHEREAS, the selection of Pike Electric, LLC is being recommended as the lowest responsible
bidder for the construction of a transmission line tie with Entergy Texas, Inc. and additional
Distribution improvements at the CSU Switch Station substation; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF COLLEGE STATION,
TEXAS:
PART 1: That the City Council hereby finds that Pike Electric, LLC is the lowest
responsible bidder.
PART 2: That the City Council hereby approves a total bonded contract with Pike
Electric, LLC for $2,661,428.90 which includes City furnished material in
the amount of $1,161,196.00 and Contractor furnished material,
equipment and labor in the amount of $1,500,232.90 required for the
construction of a transmission line tie with Entergy Texas, Inc. and
additional Distribution improvements at the CSU Switch Station
substation.
PART 3: That the funding for this Contract plus owner furnished materials shall be
as budgeted from the College Station Utilities Capital Improvement Fund,
Electric Department, in the amount of $2,661,428.90.
PART 4: That this resolution shall take effect immediately from and after its passage.
ADOPTED this 2.2, day of M( CA1 , A.D. 2012