WHEREAS, the City expects to pay expenditures in connection with the design, planning,
acquisition and construction of the projects described on Exhibit "A" hereto (collectively, the "Project")
prior to the issuance of obligations by the City in connection with the financing of the Project from available
funds;
WHEREAS, the City finds, considers, and declares that the reimbursement of the City for the
payment of such expenditures will be appropriate and consistent with the lawful objectives of the City and,
as such, chooses to declare its intention, in accordance with the provisions of Section 1.150-2 of the
Treasury Regulations, to reimburse itself for such payments at such time as it issues obligations to finance
the Project;
THEREFORE, BE IT RESOL YEO BY THE CITY COUNCIL OF THE CITY OF COLLEGE
STATION, TEXAS THAT:
Section 1. The City reasonably expects it will incur debt, as one or more series of obligations,
with an aggregate maximum principal amount not to exceed $34,740,000, for the purpose of paying the
aggregate costs of the Project.
Section 2. All costs to be reimbursed pursuant hereto wi II be capital expenditures. No tax-exempt
obligations will be issued by the City in furtherance of this Statement after a date which is later than 18
months after the later of (1) the date the expenditures are paid or (2) the date on which the property, with
respect to which such expenditures were made, is placed in service.
Section 3. The foregoing notwithstanding, no tax-exempt obligation will be issued pursuant to
this Statement more than three years after the date any expenditure which is to be reimbursed is paid.
PASSED AND APPROVED THIS 25th DAY OF February, 2019.
�
ATTEST:
(Seal)
Exhibit "A"
The projects to be financed that are the subject of this Statement are:
Lick Creek Wastewater Treatment Plant Capacity Expansion
This debt associated with this debt reimbursement resolution is for the construction of the Lick Creek
Wastewater Treatment Plant (LCWWTP) Capacity Expansion project. Some of the major plant
components included in the design include a new coarse screening structure for lift station protection with
an associated screenings building; an expansion of the influent lift station and odor control systems;
expansion of the existing head works to include additional fine screens, grit removal, grease handling
improvements, odor control, and evaluation of overall headworks effectiveness; expanded aeration basins
and blowers, master planned for future nutrient removal with the design assumption that the basins will be
conventional activated sludge sized and arranged for future biological nutrient removal and potential
uprating; and the addition of new secondary clarifiers and improvements to the existing clarifiers to
reduce short circuiting.
The overall result of this project will result in a 3 million gallons per day (MGD) expansion of
LCWWTP. This expansion is required to meet the TCEQ permit requirements as development continues
within the Lick Creek sewer shed, based on the City of College Station's 2016 Wastewater Master Plan.
This project will increase the capacity of LCWWTP from 2 MGD to 5 MGD.
The total project estimate has been revised to $40,740,000 and it is anticipated that debt will be used to
fund the project in its entirety. The project was previously issued a debt reimbursement resolution of
$6,000,000 on 23 February 2017. This additional debt reimbursement resolution is intended to cover the
remaining expenditures of the entire project.