HomeMy WebLinkAbout12-10-09-2w - Resolution - 12/10/2009RESOLUTION NO. 12- 10 -09 -2w
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF COLLEGE STATION,
TEXAS, APPROVING A CONSTRUCTION CONTRACT FOR THE DOWLING ROAD
SUBSTATION PROJECT AND AUTHORIZING THE EXPENDITURE OF FUNDS.
WHEREAS, the City of College Station, Texas, solicited bids for the construction phase of the
Dowling Road Substation Project; and
WHEREAS, the selection of Re -Con Company is being recommended as the lowest responsible
bidder for the construction services related to Dowling Road Substation; now, therefore,
BE IT RESOLVED BY THE CITY COUNCIL OF THE CITY OF COLLEGE STATION,
TEXAS:
PART 1: That the City Council hereby finds that Re -Con Company is the lowest
responsible bidder.
PART 2: That the City Council hereby approves the contract with Re -Con Company
for $2,975,960.21 for the labor, materials and equipment required for the
improvements related the Dowling Road Substation Project, plus owner
furnished material of $1,785,536.00, for a total bonded project
requirement of $4,761,496.21.
PART 3: That the funding for this Contract shall be as budgeted from the Capital
Improvement Fund, Electric Division, in the amount of $2,975,960.21.
PART 4: That this resolution shall take effect immediately from and after its passage.
ADOPTED this 10th day of December , A.D. 2009.