March 28, 1984
MEMORANDUM
TO: Robert Nash, Dalsan Properties
Gary Schuberth, Schuberth, Rodrigues Valdes, Inc.
John Olsen, Jerry Bishop & Associates, Inc.
FROM: Project Review Committee:
Al Mayo, Director of Planning
David Pullen, City Engineer
Roy Kelly, P &Z Representative
Other Staff:
Jane Kee, Zoning Official
Kim Johnson, Ass't. Zoning Official
Rick Ploeger, City Forester
Harry Davis, Fire Marshal
Cathy Locke, Ass't. City Attorney
Joe Guidry, Electrical Superintendent
Jim McCord, Elec. Power Engrs.
Shirley Volk, Planning Technician
SUBJECT: Parking Lot Plan - College Station Retail Center - 84 -407
The P.R.C. met on this date to review the above mentioned project, and recom-
mends approval with the following conditions:*
(1) Correct the dimension lines to match the drawings.
(2) There are 134 parking spaces plus those designated as being for handicapped
persons on this site plan. Please correct notes to reflect correct numbers.
(3) Dumpster pads must be at grade rather than 6" above grade as indicated.
(4) Compliance with the provided P,R.C. Drainage Statement is required.
(5) Dimension all islands.
(6) Check with Traffic Engineer John Black and Zoning Official Jane Kee
regarding size and location of directional signs.
(7) It has been suggested that there be a Development Agreement reached between
the Developer and the City regarding uses and required parking for these
uses. Please set up an appointment with the City Planner and the Legal
Department to discuss.
(8) Dumpster location must be as directed by the Director of Public Services
(Alfred Miller).
(9) Landscaping:
(a) Suggest an alternate shrubbery or groundcover to be used on the
slope to the creek.as a means of erosion control.
(b) Suggest relocation of oaks along Texas Avenue further into the
property to help maintain the sight distance triangle, and to
prevent interference with utility lines.
(c) Calculate the points in notes on the site plan.
(d) Show square footage of entire site; landscaping points are
figured two ways.
(e) Indicate all locations of Indian Hawthorne.
...Continued on Page 2
P.R.C. Report - 84 -407
page 2
March 28, 1984
(10) The screen fence between this project and the adjacent residential
development will not be required due to the size and location of
the flood plain.
(11) A 6" raised curb is required around all edges of all parts of all
paved areas without exception. (To include islands, planting areas,
access ways, dumpster locations, utility pads, etc.) Curb detail
to be approved by the City Engineer. No exceptions will be made
for areas indicated on site plan as "reserved for future parking."
SUBMIT FIVE (5) COPIES OF REVISED SITE PLAN TO DIRECTOR OF PLANNING FOR
REVIEW AND APPROVAL PRIOR TO ISSUANCE OF BUILDING PERMIT.
sjv
♦�� City of College Station
POST OFFICE BOX 9960 1101 TEXAS AVENUE
\ / COLLEGE STATION, TEXAS 77840 -2499
March 28, 1984
MEMORANDUM
To: Batten-Blackburn
c/o Phil Blackburn
FROM: Project Review Committee:
Al Mayo, Director of Planning
David Pullen, City Engineer
Roy Kelly, P &Z Representative
Other Staff:
Harry Davis, Fire Marshal
Joe Guidry, Electrical Superintendent
Jane Kee, Zoning Official
Kim Johnson, Ass't, Zoning Official
Shirley Volk, Planning Technician
SUBJECT: Professional Car Services - Lot 23 Block 16 SWV Sec 3 - 84 -409
The P.R.C. met on this date to review the above mentioned project and will
set another date to review it again when the following changes have been
made:
(1) Based on verbal information given by the applicant at the meeting, the
number of required parking spaces is 28 plus the 8 service bays. Show
the dimensions and square footage of the building and also that of the
service area so exact determination of required number of spaces can
be made.
(2) Show the required 8 ft. setback from the property line to the curbing
of the parking area.
(3) There must be a 15 ft. separation between buildings or the buildings
must be constructed with 4 hour fire walls (no penetration) if lot
line construction is used.
(4) The addition of an island is required at the northwest corner of the
parking lot.
(5) Locate the dumpster pad as directed by the Director of Public Services.
Dumpster pad (12' x 12') should be at grade, with screening but no gates.
(6) Indicate dimensions of the island at the northeast corner of the building.
(7) Show location of sign; include elevations; all subject to approval by
the Zoning Official. Applicant verbally indicated the sign will be on
or near the property line and will be shared by both businesses.
(8) Landscaping must be in compliance with the Landscaping Ordinance, which
was furnished.
(9) A 6" raised curb is required around all edges of all parts of all paved
areas without exception. (To include islands, planting areas, access ways,
dumpster locations, utility pads, etc.) Curb detail to be approved by the
City Engineer. No exceptions will be made for areas indicated on site
plan as "reserved for future parking."
Submit 5 revised copies of site plan to Planning Department for further review
and approval.
sjv
♦�� City of College Station
POST OFFICE BOX 9960 1101 TEXAS AVENUE
\ / COLLEGE STATION, TEXAS 77840 -2499
March 29, 1984
PRESUBMISSION CONFERENCE
TO: Tim David Chinn, Kling Engineering,�,,,
FROM: Al Mayo, Director of Planning k
David Pullen, City Engineer
Harry Davis, Fire Marshal
Joe Guidry, Electrical Superintendent
Shirley Volk, Planning Technician
SUBJECT: Preliminay Plat - Rainbow Acres 2nd Installment - 204.420 A. (84 -303)
A Presubmission Conference was held on March 28th to review the above mentioned
plat, and staff recommends approval with the following conditions *:
(1) A 20 foot utility easement will be required along the rear property
line of each lot.
(2) A variance will be required for Lots 3, 4, 5 Block 7 regarding the 50 foot
frontage on these lots at the end of the cul -de -sac. Ordinance requires
100 foot frontage on lots with this type of configuration. Staff will
recommend denial of this variance.
(3) A variance will be required regarding the 60 foot R.O.W. for streets.
The City requires 70 foot right -of -ways but the County requires only
60 foot right -of -ways. Staff will recommend approval of this variance.
(4) Staff suggests the acreage of each lot to be shown on this plat.
-;Any changes to an approved plat must be cleared through the Office of the
Director of Planning.
Submit 10 copies and a master copy of this plat to the Planning Department
by 5 P.M. on April 13th to be on the P &Z agenda April 19th.
sjv