Loading...
HomeMy WebLinkAboutCherry Street DevelopmentCI �_RRY STREET DEVELOPME" " Cost: $525,000 funded through Community Development Block Grant Utilities: Sewer is already done, water and hydrants will be included. May possibly include new streetlights. Timeframe: Will not be out to bid until the end of 1999. Construction will begin in the spring. Acquisition: City was authorized to acquire land at the October 14th City Council meeting including 19 right of ways and two easements Development: Between 2"d and Boyett-acquiring property from both sides Between 2nd and College Main -acquiring property from the North Side Between College Main and Tauber -acquiring property from the North Side Development will include curb and gutter, no sidewalks are budgeted but are built into the design for construction at a later date -budget permitting, street width will be 29 feet (standard) Engineering will be requesting bids for both asphalt and concrete