HomeMy WebLinkAboutFY 2009-2010 Capital Improvements Program Budgetwww.cstx.gov City of College Station CAPITAL IMPROVEMENTS PROGRAM BUDGET FOR FISCAL YEAR 2010 OCTOBER 1, 2009 to SEPTEMBER 30, 2010 Home of Texas A&M University ® TABLE OF CONTENTS Executive Summary ............................................................................................................. 1 General Government Capital Improvement Projects Streets, Traffic, Sidewalks and Trails ........................................................................ 11 Street Rehabilitation Projects ................................................................... 17 Street Extension Projects ......................................................................... 24 Street TxDOT Projects ............................................................................. 46 Traffic Projects ......................................................................................... 49 Sidewalks and Trails ................................................................................ 64 Parks and Recreation Projects .................................................................................. 77 Wolf Pen Creek Parks and Recreation Projects ....................................... 102 General Government Facilities and Technology ..................................................... 105 Public Facilities ......................................................................................... 108 Technology Projects .................................................................................. 119 Drainage Utility ........................................................................................................ 129 Convention Center .................................................................................................. 139 Special Revenue Capital Improvement Projects Parkland Dedication ................................................................................................ 143 Enterprise Funds Capital Improvement Projects Electric Service ........................................................................................................ 171 Water Service .......................................................................................................... 175 Production Projects ................................................................................ 180 Distribution ............................................................................................. 203 Rehabilitation Projects ........................................................................... 221 TABLE OF CONTENTS Wastewater Service ........................................................................................... 235 Collection ........................................................................................... 240 Rehabilitation Projects ...................................................................... 249 Treatment .......................................................................................... 251 Brazos Valley Solid Waste Management Agency .............................................. 279 Estimated Operations and Maintenance (O&M) Costs General Government Capital Improvement Projects O&M Costs. .......................... 298 Special Revenue Capital Improvement Projects O&M Costs .................................. 299 Enterprise Funds Capital Improvement Projects O&M Costs .................................. 300 Index by Project/Work Order Name .................................................................................... 301 Index by Project/Work Order Number ................................................................................. 303 Fiscal Year 2009 – 2010   Capital Improvements Program Budget  Executive Summary  The following is the annual City of College Station Capital Improvements Program (CIP) Budget document. The CIP budget provides the framework for capital improvement projects to be conducted in the 2010 fiscal year that begins October 1, 2009 and ends on September 30, 2010. On an annual basis, the City of College Station prepares a five-year Capital Improvements Program (CIP). The CIP is presented for City Council review as part of the annual budget process. The program consolidates all anticipated capital needs for which funding authorization exists, while separating the projects into several sections depending on the services provided and the respective funding source. Once the budget is approved by the City Council, the assigned project managers manage their respective projects with budgetary oversight from the Office of Budget and Strategic Planning and the Finance Department. Summary capital project schedules have been included in the annual College Station Approved Budget; however, this CIP budget document permits greater communication among City staff, administration, Council and citizens regarding capital projects. Areas of enhanced information conveyed within this document include individual project detail pages and corresponding maps, where applicable. The project sheets detail the project number, project manager, funding source(s), description of purpose and need, funding per year and category, and the estimated impact, if any, on future operating budgets. The maps provide citizens and officials a greater understanding of the scope and the impact of the specific projects through the illustration of the planned action. The projects presented in this document are grouped according to major funding source. For example, projects for which the major funding source is the Streets Capital Improvement Projects Fund are included in the Streets, Traffic, Sidewalks and Trails section of the document. A number of projects included in this document have multiple funding sources. The project sheets for these projects include an expenditure summary for each funding source as well as a combined expenditure summary that reflects the total projected expenditures for the project. The project sheets for projects with multiple funding sources are included in the section of the CIP document that reflects the project’s primary funding source. CAPITAL PROJECTS FUNDING The City operates under the laws of the State of Texas and the City of College Station's Home Rule Charter. Two categories of capital expenditures are defined by the City. The first category of capital expenditure is for major capital projects. Major capital projects are projects that cost more than $50,000 and provide a fixed asset or equipment that has a useful life of three years or more. The second category of capital expenditure is for minor capital projects. Minor capital projects are projects that cost more than $5,000 and less than $50,000 and provide a fixed asset or equipment that has a useful life of three years or more. The approved Capital Improvements Budget for FY10 totals $53,210,063 for all funds that include capital projects. This budget amount does not, however, reflect all projected capital expenditures for FY10. In the case of projects for which funds have already been approved and budgeted, the City may continue to spend money to complete these projects without including the projected FY10 expense as a new appropriation. The project budgets that have been appropriated carry forward until the project is complete. Only portions of the projects that have not been previously appropriated are included as new appropriations in the FY10 budget. The total projected to be spent in FY10 on capital projects including both new appropriations as well as existing appropriations is approximately $89,000,000. The City only has legal authority to issue General Obligation (GO) debt after a successful citizen referendum. GO debt is debt that obligates the City to repay the issue with ad valorem tax revenues. The City uses GO debt for the acquisition and development of parks and recreation facilities; rights-of-way acquisition; construction of arterial streets; reconstruction of major arterial streets; and for public buildings such as City offices, libraries, swimming pools and other general use facilities. The most recent General Obligation bond election was held in November of 2008. Voters approved $76,950,000 in General Obligation Bond (GOB) authorization to be issued over 7-years for streets, traffic, and fire station projects, the Library expansion project, and parks projects including an addition at the Lincoln Center and the Lick Creek Park Nature Center. In November 2003, the citizens of College Station approved $38,405,000 in GOB authorization for street, traffic, police and fire station projects, the City Center project, and parks projects including the second phase of Veterans Park. A small amount of the 2003 GOB debt remains to be issued. 1 In FY09, the City issued $3,335,000 in GOB debt for various General Government capital projects. Of this, $1,050,000 was issued for street, traffic and sidewalk projects. This included $455,000 for traffic signal and safety improvement projects. An additional $100,000 was issued for oversize participation projects. These funds will be used toward building increased capacity into the streets that are being constructed by developers. $100,000 will be used for various sidewalk improvements throughout the City. $270,000 was issued for the design of the Victoria Avenue extension and $125,000 was issued for the design of the hike and bike trail completion. In addition, $1,535,000 was issued for Park projects. This included $200,000 for the skate park design, $515,000 for the construction of the Creek View neighborhood park, $500,000 for the purchase of land for neighborhood parks and $320,000 for improvements to various neighborhood parks throughout the City. Finally, $750,000 in GOB debt was issued for the design of Fire Station #6. This fire station will serve the busy University Drive corridor. The FY10 Approved Budget includes the projected issuance of $16,440,500 in GO’s. Included is $9,672,500 for street, sidewalk, traffic and transportation projects. This includes $1,080,000 for street oversize participation projects. These funds will be used toward building increased capacity into the streets that are being constructed by developers. An additional $100,000 has been included for sidewalk improvements throughout the City and $100,000 is included for new traffic signal projects. $5,707,500 is projected for the phase II construction of Barron Road from Decatur Drive to William D. Fitch Parkway. An additional $1,700,000 is projected to be used toward the construction of Victoria Avenue extension. Victoria Avenue will be extended from Southern Plantation Drive and will be connected with William D. Fitch Parkway (SH 40). $370,000 is projected for the design of the Penberthy extension. This project will extend Penberthy Boulevard from the Luther Street / Jones Butler intersection across A&M property to the George Bush Drive / Penberthy Boulevard intersection. $500,000 is included to be issued for land acquisition and construction related to the hike and bike trail completion. Funds will be used to construct the Bee Creek West/South project which has been identified by the Hike and Bike Task Force. Finally, $115,000 is estimated to be issued for the purchase of right-of-way along Rock Prairie Road West to provide for future widening. FY10 GOB debt in the amount of $1,586,000 is projected for Parks projects. This includes $720,000 for the construction of a skate park. An additional $500,000 is included for the purchase of land for neighborhood parks. $270,000 is estimated to be issued for improvements to various neighborhood parks throughout the City. The proposed improvements include a walking loop at Anderson Park and a running surface at Brothers Pond Park. Additionally, $96,000 is included for the design of improvements at Beachy Central Park. These include a new concession complex and restroom building. Facility projects for which debt is projected to be issued in FY10 include Fire Station #6 in the amount of $4,000,000. This fire station will serve the University Drive corridor. Debt for the design and construction of the station is scheduled to be issued over three fiscal years. $250,000 is scheduled to be issued for design of City Hall facility improvements. Finally, $932,000 is projected to be issued for the design of the library expansion. Construction is expected to occur in FY11 and FY12. The City has statutory authority, and City Council policy allows for the use of non-voter authorized debt instruments such as certificates of obligation and contract obligations (generally referred to as CO's). City Council policy allows the City to use such instruments for capital items such as the following: • The purchase and replacement of major computer systems and other technology-based items that have useful lives of not more than ten years. • The purchase and replacement of major equipment items such as fire fighting equipment. The City has, however, developed policies and procedures to provide almost all of this equipment without issuing debt. • The purchase of land and development of land for economic development uses. In FY09, the City issued $31,315,000 in CO debt. Included was $3,250,000 for a variety of General Government Capital projects. $540,000 was included for construction costs related to completion of the new City cemetery. The cemetery was completed in FY09. Funds in the amount of $70,000 were issued for the purchase of a new scheduling system for the Police Department. $2,490,000 was included for the replacement of the City’s 800 MHz radio system. The current total budget for this project is $4,885,000. The additional funds for the project came from funds set aside in the Equipment Replacement Fund for the replacement of the radio system. In addition, $150,000 was issued for a Fiber Optic Infrastructure project. This project will support the installation of fiber optic cable to continue expansion of the city's network to new buildings and facilities, and to permit the connection of existing facilities that are not currently on the network. 2 CO debt was also issued for the Convention Center project. A total of $3,200,000 was issued for this project. $2,600,000 was for a portion of the land cost of this project. The additional cost of the land was paid for with Hotel Tax funds. Additionally, $600,000 was issued for the design of the Convention Center project. In addition to the CO debt issued for General Government projects, $10,240,000 in CO debt was issued for the construction of the new Brazos Valley Solid Waste Management Agency (BVSWMA) landfill. However, as the City of Bryan has 50% ownership in BVSWMA, it is anticipated that the City of Bryan will issue debt in FY10 for half of this amount. It is proposed that half of the CO debt previously issued by the City of College Station will be used for BVSWMA and the remaining half will be used by the City of College Station’s Water, Wastewater and/or Electric Utilities to fund capital projects. It is projected that the debt service on the debt issued for the landfill will be paid from tipping fees and other revenue generated by the landfill. Utility debt service will be paid with revenue generated by the Utilities. $14,475,000 in CO debt was issued for Utility projects. Utility Revenue Bond debt is typically used for the Utility projects. However, based on the recommendations from the City’s financial advisors, and due to the marketability of the bonds as well as the volatility of the bond market, CO debt was issued for these projects in FY09. $6,975,000 was issued for Electric projects and $7,500,000 was issued for Water projects. Finally, $150,000 was issued to cover debt issuance costs. The FY10 Approved Budget includes the issue of $425,000 in CO debt for General Government projects. The amount includes $150,000 for a Server Consolidation project. This project provides additional hardware to accommodate the increasing demands for additional electronic storage and the software to better manage the data. The hardware upgrades will permit a doubling of the current storage allotted to each employee. In addition, $220,000 is projected to be issued for a Fiber Optic Infrastructure project. This project will support the installation of fiber optic cable to continue expansion of the city's network to new buildings and facilities, and to permit the connection of existing facilities that are not currently on the network. Finally, $55,000 is projected to be issued for the CAD hardware operating system upgrade. This project will change the server hardware, and replace the operating system used from AIX (UNIX) to a Windows based system. This change will enable greater support, less expensive hardware, and greater flexibility. Combined Utility Revenue Bonds are traditionally issued to provide for capital expansion and replacements for the various utility services. In FY10, either Utility Revenue Bonds or Certificates of Obligation will be issued for Utility capital projects. Funds in the amount of $12,025,000 are estimated for Water capital projects and funds in the amount of $7,600,000 are estimated for Wastewater capital projects. GOVERNMENTAL CAPITAL PROJECTS   Below are descriptions of the governmental capital projects included in the FY10 Approved Budget. The funds expended on these projects are considered significant and nonroutine. STREETS, TRAFFIC, SIDEWALKS AND TRAIL CAPITAL PROJECTS  Street Rehabilitation Projects  In FY10, funds in the amount of $1,684,013 are included for the Tauber and Stasney street rehabilitation project. These streets are located in the Northgate area. The project includes the rehabilitation of Tauber Street and Stasney Street from University Drive to Cherry Street as well as the design and construction of new sidewalks on College Main. The project also includes the water and wastewater line rehabilitation. Funds in the amount of $417,225 are also projected in FY10 for other rehabilitation projects that may arise in the Northgate area. These funds reflect the balance of the Church Avenue rehabilitation project, which came in under budget. The construction funds for these Northgate area rehabilitation projects were authorized as part of the 2003 GO bond election. Street Extension Projects  $12,793,835 is the estimated expenditure included in the FY10 Approved Budget for various street extension and widening projects. Funds in the amount of $1,700,000 are included for the extension of Holleman Drive. This project calls for Holleman Drive to be extended from Jones Butler Road to FM 2818. An estimated $807,061 is included for extension of Discovery Drive. $1,704,313 is projected for the extension of Victoria Avenue. Victoria Avenue will be extended from Southern Plantation Drive to connect with William D. Fitch Parkway (SH 40), aligning with the existing Victoria Avenue on the south side of William D. Fitch Parkway (SH 40). The roadway will be a major collector consisting of two travel lanes and a center turn lane with bike lanes, sidewalks, landscaping and storm drainage. An estimated $360,865 is projected for the extension of Penberthy Boulevard. The project extends Penberthy Boulevard from the Luther Street / Jones Butler intersection across A&M property to the George Bush Drive / Penberthy Boulevard intersection. The project includes an 3 equestrian crossing to accommodate University operations and a traffic signal will be installed at the George Bush Drive and Penberthy Boulevard intersection. The approved budget also includes $989,110 for the Rock Prairie Road Widening project. These funds will be used for design and right-of-way acquisition costs related to the future widening of Rock Prairie Road. Construction funds are not included in the project budget. $115,000 is the projected FY10 expenditure for the Rock Prairie Road West right-of-way project. This project includes the purchase of additional right-of-way from State Highway 6 to Normand Drive to provide for the future widening of that section of Rock Prairie Road. In addition, $5,707,500 is projected for the phase II of construction to Barron Road from Decatur Drive to William D. Fitch Parkway. This project will upgrade Barron Road from a two lane rural highway to a four lane road with sidewalks, raised center median, landscaping, storm sewers and street lighting. $882,695 has been included for the completion of phase II of the widening of William D. Fitch Parkway. This project will widen William D. Fitch Parkway between Pebble Creek Parkway and Rock Prairie Road. Finally, $527,291 is included for other street extension projects that may arise or for projects that may go over budget. These funds came from the Dartmouth Extension project which was completed under budget. Street TxDOT Projects  $596,399 is the estimated FY10 expenditure streetscaping along Texas Avenue. This streetscaping follows the completion of the TxDOT Texas Avenue Widening project. Traffic Projects  The FY10 Approved Budget includes an estimated $670,272 for new traffic signal projects and traffic signal communication projects. Included is an estimated $615,587 for new signals throughout the City. A signal warrant study was recently completed, the results of which have indicated the need for new signals at the following locations: William D. Fitch Parkway (SH 40) at Barron Road, William D. Fitch Parkway (SH 40) at Arrington Road, Texas Avenue at Krenek Tap Road, George Bush East at Dominik and SH30 at Copperfield. These are proposed to be the locations of the next new signals. In addition, $54,685 is included in the budget for traffic signal communication projects. These projects support traffic signal connectivity as well as other City data and voice services. Sidewalks and Trail Projects  The City of College Station has worked over the years to ensure adequate transportation infrastructure for pedestrians and bicyclists. The City has an adopted sidewalk and bike loop plan. $318,488 is the projected expenditure for the completion of the City’s bike loop. This project will consist of signed bike routes, on-street bike lanes, and off-street bike paths to link the Texas A&M campus, City of College Station parks and local housing areas. In addition, the project will include improvements for pedestrians and bicyclists at the Longmire/FM 2818 intersection. A portion of the expenditures for the Bike Loop project will be reimbursed by TxDOT as part of an Intermodal Surface Transportation Efficiency Act (ISTEA) grant received by the City. Also included in the FY10 Approved Budget is an estimated $249,550 for City of College Station Beautification Improvements. This project includes the addition of trees and other beautification improvements along the University Drive and Highway 6 entrance point. As new development occurs, sidewalks are an important aspect that must be considered. In FY10, $100,000 is included for sidewalk improvements throughout the City. Finally, $500,000 is included for the completion of the hike and bike trail as identified by the Hike and Bike Task Force. PARKS AND RECREATION CAPITAL PROJECTS  In FY10, funds in the amount of $2,285,840 are estimated for Parks and Recreation capital improvement projects. Included is $140,840 for field redevelopment projects. A portion of the funds will be used for replacement and repairs to numerous athletic facilities throughout the City. Items include drinking fountains, shade covers, light and base replacement, as well as fence and bleacher repairs. Remaining funds will be used for turf repair on other athletic parks. The funds for these projects are collected from the fees paid by players and teams from both City leagues and outside user groups. The funds are used to pay for replacement items and facility upgrades at City athletic facilities. Funds in the amount of $464,000 are estimated in FY10 for the completion of Creek View neighborhood park. This park will be constructed adjacent to Creek View Elementary. $270,000 is estimated to be issued for improvements to various neighborhood parks throughout the City. The proposed improvements include improvements at Emerald Forest Park, a walking loop at Anderson Park and a running surface at Brothers Pond Park. $815,000 is estimated for the construction of a skate park. An additional $500,000 is included for the purchase of land for neighborhood parks. Finally, $96,000 is included for the design of improvements at Beachy Central Park. These include a new concession complex and restroom building. 4 GENERAL GOVERNMENT AND CAPITAL EQUIPMENT CAPITAL PROJECTS  General government and capital equipment projects are planned assets that have value to more than one specific area of City operations. The two main divisions within this category are public facilities and technology projects. In FY10, it is projected that $6,009,409 will be spent on public facility projects. Included in this amount is $660,000 for design and improvements of City Hall facilities. $4,200,000 is estimated for the construction of Fire Station #6. Fire Station #6 will serve the busy University Drive corridor. Funds in the amount of $932,000 have been included for the expansion of the Larry J. Ringer library. It is estimated that the library will be expanded by approximately 15,000 square feet with an additional 16,000 square feet of parking. $20,000 is included for the purchase of library books. The funds for the purchase of these books come from donations collected for this purpose. Finally, $197,409 is included for other facility projects that may arise or for projects that may go over budget. These funds came from the Fire Station #3 relocation project which was completed under budget. The FY10 Approved Budget also includes a projected expenditure of $4,436,257 for technology projects. An estimated expenditure of $3,900,000 has been included for the replacement of the City’s 800 MHz radio system. A portion of the budget for this project ($2,310,000) came from the Equipment Replacement Fund where they were set aside for this purpose. The remainder will come from CO’s. The City, along with a number of local entities, was awarded a federal grant that will help fund a County-wide radio system. The funds received for this project will be used toward the City’s portion of the system. $110,000 is projected for the Wireless Infrastructure project which will provide funds for the installation of equipment that will allow wireless access by City employees at various locations throughout the City. $150,000 is projected for Server Consolidation. This project provides additional hardware to accommodate the increasing demands for additional electronic storage and the software to better manage the data. The hardware upgrades will permit a doubling of the current storage allotted to each employee. $221,000 is projected for a Fiber Optic Infrastructure project. This project will support the installation of fiber optic cable to continue expansion of the city's network to new buildings and facilities, and to permit the connection of existing facilities that are not currently on the network. A projected $55,000 is included for the CAD hardware operating system upgrade project. The current CAD operating system was installed in 2003. This project will change the server hardware, and replace the operating system used from AIX (UNIX) to a Windows based system. This change will enable greater support, less expensive hardware, and greater flexibility. Finally, $257 is projected for miscellaneous IT projects. These funds reflect remaining balances of closed projects for which debt was issued. DRAINAGE PROJECTS  Drainage capital projects are funded by revenue generated through a drainage utility fee that is collected from residential and commercial utility users. The FY10 drainage capital projects budget includes a projected expenditure of $1,762,099 for capital improvements. Significant projects include a projected $1,048,200 for Bee Creek IV and V. This project is for storm drainage improvements to the flow capacity of Bee Creek Tributary “A.” These improvements include bank stabilization from Brothers Boulevard to Longmire Drive. $463,899 is projected for Greenways land acquisition throughout the City. The City’s Greenways Master Plan calls for future trail development in urban and suburban greenways. $200,000 is included for Minor Drainage Improvement projects. These funds are used for minor unscheduled drainage projects that arise throughout the fiscal year. $50,000 is included for Stormwater Mapping projects. These funds will be used for mapping of the City’s stormwater infrastructure. CONVENTION CENTER CAPITAL PROJECTS The Convention Center Fund accounts for the receipt and expenditure of funds received by the City for the operation and maintenance of a convention center. In FY10, there is budgeted expenditure of $750,000 in the Convention Center Fund. $376,385 is budgeted for convention center project expenditures. $100,000 of which is for the completion of a study that will provide recommendations as to the feasibility of a new convention center. In addition, funds in the amount of $276,385 have been included for future design costs. $223,615 is included for the debt service payment that will cover the debt that has been issued to date toward the land and design of the convention center. These funds will be transferred to the debt service fund out of which the debt service payment will be made. In addition, funds in the amount of $150,000 have been estimated for maintenance costs related to the Chimney Hill property on which the convention center will be built. These expenses will be offset by lease revenue received from existing tenants.   SPECIAL REVENUE CAPITAL PROJECTS Below are descriptions of the special revenue capital projects included in the FY10 Approved Budget. The funds expended on these projects are considered significant and nonroutine. Parkland Dedication Capital Improvement Projects The Parkland Dedication Funds account for the receipt and expenditure of funds received by the City from residential land developers who dedicate land, or money in lieu of land, for use in the development of neighborhood parks in residential 5 areas. The projects in the Parkland Dedication Capital Improvement Projects Funds are funded using the dedicated parkland funds. Parkland dedication funds must be used for the development of parks within the zone to which the funds are dedicated. In FY10, appropriations in the amount of $861,138 are included in the budget. Total expenditures are estimated at $1,060,918 for projects that are anticipated to be completed in the various park zones. Funds in the amount of $12,500 are included for improvements at Parkway Park. $167,780 is projected in Zone 6 for the development of Southwest Park. This park will have amenities found in typical neighborhood parks such as a playground, walks and picnic tables. $53,000 is the estimated FY10 expenditure for phase III of John Crompton Park and $63,000 is projected for improvements at Emerald Forest Park. Additional funds are projected in a number of Park zones but have not yet been obligated to specific projects. These funds will be obligated to specific projects within these zones throughout the fiscal year as the projects arise. Funds not used in the fiscal year will carry over to future fiscal years. UTILITY CAPITAL PROJECTS Below are descriptions of the utility capital projects included in the FY10 Approved Budget. The funds expended on these projects are considered significant and nonroutine. Electric Capital Projects  $8,932,210 is the approved appropriation for electric capital projects in FY10. As the electric capital projects are considered competitive matter under Texas Senate Bill No. 7, details of these projects cannot be outlined in this summary, but have been provided to the City Council. Water Capital Projects In FY10, $12,948,894 is the approved new appropriation for water capital projects. Water production projects include an estimated FY10 expenditure of $13,285,000. This includes $4,500,000 for construction of phase I of the Parallel Wellfield Collection Line. This water line will run parallel to the existing water line which is currently operating at maximum capacity. The parallel line will increase system capacity. $1,000,000 is included for the purchase of land for future well sites. As capacity needs grow, the City is preparing for the construction of new wells. A component of this is the land acquisition for new future wells. Also included in the FY10 Approved Budget are funds in the amount of $4,875,000 for the construction of Well #8 and funds in the amount of $2,000,000 for construction of the Well #8 Collection Line. The additional capacity is required to meet Texas Commission on Environmental Quality (TCEQ) regulations for pumping capacity to match the projected population. $400,000 is included for the design of the high service water pump improvements. This project will replace the existing high service pumps #3 and #4 with higher capacity fixed speed pumps. This project is in response to analysis of the water system capacities in relation to TCEQ requirements. An additional $400,000 is included for the removal, inspection, and rehabilitation of the pumps and motors for two Simsboro water wells. The pumps in these two wells have reached their expected service life and need to be inspected and rehabilitated. $110,000 is projected for the completion of the Supervisory Control and Data Acquisition (SCADA) system replacement. SCADA is a system that allows for computerized control over plant operations and remote facilities. This project will replace the control equipment that has exceeded its useful life. Funds in the amount of $5,134,824 are projected to be expended on Distribution projects in FY10. This includes $100,000 of general oversize participation (OP) funds. These funds are used to help meet future capacity needs by oversizing water lines above the minimum size required to serve a development. $2,650,000 is included in the FY10 budget for construction on the Reclaimed Water project. This is a multi-phase project to deliver irrigation water to major users in College Station. Phase I includes delivery of reclaimed water to Veterans Park. $865,759 is the projected FY10 expenditure for the Wellborn Widening project. This project was for the relocation of water lines outside of future pavement areas in conjunction with Wellborn Widening. A final phase is expected to be completed in FY10. A portion of the expenditures for this project will be reimbursed by TxDOT. It is estimated that $2,930,408 will be received over the next two fiscal years. 80% estimated to be received in FY10 and the balance in FY11 following the completion of the project. $127,007 is included for the design of the Barron Road water line extension. This project is for the installation of water lines along Barron Road. Construction is estimated for FY11. A projected expenditure of $366,000 is included for land acquisition related to the construction of water lines in annexed areas along Raymond Stotzer West. This project will provide water to areas along Raymond Stotzer West. $150,000 is included for the relocation and improvements to water lines along Barron Road from Decatur Drive to William D. Fitch Parkway. In addition, $217,500 is included for water line improvements along Victoria Avenue. These last two projects will be completed in conjunction with the corresponding street extension projects. $25,000 is included for the land acquisition related to the project that will provide a connection of the 24” water line at Graham Road to the 24” water line at Barron Road. This is needed for the proper operation of the distribution system. An estimated $299,500 is included for land acquisition related to the relocation of the water line for TxDOT's future widening of University Drive East. Water lines will 6 need to be relocated into an easement outside of the right-of-way. A portion of the funds expended on this project will be eligible for reimbursement from TxDOT. Finally, $334,058 is included for the William D. Fitch East project. This project is for the installation of a water line to serve the annexed area along William D. Fitch Parkway. Construction is estimated to be completed in FY10. Rehabilitation projects included in the FY10 Approved Budget include $120,000 for the adjustments to water lines that will occur as part of the Bee Creek IV and V drainage project which will provide storm drainage improvements to the flow capacity of Bee Creek Tributary "A." An estimate of $77,688 is included for the replacement of water lines along Tauber Street and Stasney Street. This project is being completed in connection with the Streets rehabilitation project. The existing infrastructure is being replaced and capacity should increase as a result. $1,436,866 is projected for the South Knoll/The Glade project. This project is for the replacement of water lines in the area bounded by Haines, Southwest Parkway, Glade and Langford. These aging lines were identified in a 2003 water study as in need of replacement. In addition, $1,267,823 has been estimated for the Southwood 5-7 project. This project is for the replacement of water lines in an area bounded by Southwest Parkway, Harvey Mitchell Parkway, Welsh and Shadowood. Contingency in the amount of $150,000 has been included in the FY10 Approved Budget. These funds will be available for use on unanticipated projects as well as to offset project overruns. Finally, $360,000 has been included for the meter replacement program that was implemented in FY08. This program is for the replacement of water meters on a routine basis to ensure efficient water readings. The FY10 Approved Budget includes an estimated $7,000,000 in current revenues that will be transferred from operations to fund water capital projects. Additionally, a debt issue of $12,025,000 is projected in FY10 for water capital projects. Wastewater Capital Projects The FY10 Approved Budget includes $4,877,393 in new appropriations for numerous wastewater capital projects. Collection projects include $100,000 for oversize participation and planning. These funds are available to meet future anticipated capacity in the construction of wastewater lines above the minimum size needed to serve the development. $557,000 is the estimated expenditure for land acquisition related to the construction of wastewater lines in annexed areas along Raymond Stotzer West. Due to annexation, development and expected future development, wastewater services are necessary. $300,000 is the projected expenditure for the Koppe Bridge Lift Station project. This project is for the construction of a force main sewer line from the existing Koppe Bridge Lift Station to Creek Meadow Lift Station. This project will allow for the Meadow Creek Package Plant to be taken off line. $307,790 is estimated for the Westminster sewer line construction. This project is being completed in conjunction with TxDOT’s widening of Wellborn Road from FM 2818 to Barron and the line will serve properties along Wellborn Road and Barron Road. An expenditure of $475,000 is estimated for the Nantucket Gravity Sewer project. This project will include the installation of a gravity sewer line. $300,000 is projected for engineering associated with the Lick Creek Parallel Trunk Line – Phase I. This project involves the replacement of a trunk line in Lick Creek Park. This trunk line serves areas south of Barron Road. $23,381 is included for wastewater line improvements along Victoria Avenue. In addition, $100,000 is included for the relocation and improvements to wastewater lines along Barron Road from Decatur Drive to William D. Fitch Parkway. These last two projects will be completed in conjunction with the corresponding street extension projects. An estimated $291,094 is included for the Emerald Parkway/Bent Oak project. This project will provide for new alignment of approximately 1,000 feet of 24 inch wastewater collection line will be installed to provide better flow hydraulics and will have sealed and bolted manholes. $300,000 is projected for the adjustments to wastewater lines that will occur as part of the Bee Creek IV and V drainage project which will provide storm drainage improvements to the flow capacity of Bee Creek Tributary "A." An estimate of $261,820 is included for replacement of wastewater lines along Tauber Street and Stasney Street. This project is being completed in connection with the Streets rehabilitation project. Funds totaling $1,361,513 are projected for the South Knoll/The Glade project. This project is for the replacement of wastewater lines in the area bounded by Haines, Southwest Parkway, Glade and Langford. These aging lines were identified in a 2003 wastewater study as in need of replacement. Finally, $1,537,094 has been included for the Southwood 5-7 project. This project is for the replacement of wastewater lines in an area bounded by Southwest Parkway, Harvey Mitchell Parkway, Welsh and Shadowood. Funds in the amount of $4,041,476 have been projected for Treatment and Disposal projects. $500,000 is included for headworks improvements at the Carters Creek Wastewater Treatment Plant (CCWWTP). These improvements include the replacement of the motorized bar screens, replacement of the grit bridges, overhaul of the shaftless screw conveyor and the installation of mixers in the wells at the end of the grit bridges. In addition, $310,000 is projected for the construction of catwalks around the Lick Creek clarifiers. The catwalks will provide safe access for the operators to operate and maintain the clarifiers. An estimated $363,280 is included for centrifuge improvements at the Lick Creek Wastewater Treatment Plant (LCWWTP). Improvements include installing a larger sludge discharge hopper, a sludge conveyor and a work platform around the centrifuge. $400,000 is included for completion of the Lick Creek Holding Tank Improvements. This project will 7 ultimately expand the size of the waste sludge holding tank at the Lick Creek Wastewater Treatment Plant. An additional $600,000 is estimated for ATAD improvements at the CCWWTP. This includes replacing the ATAD motor operated valves. $200,000 is projected for Lick Creek Return Activated Sludge Improvements. This project is for the hiring of an engineer to modify the existing pumps, flow measurement and sludge waste set up and for the implementation of necessary modifications. Funds in the amount of $155,196 are estimated for the SCADA replacement project. This project will replace the control equipment that has exceeded its useful life. $890,000 is the projected expenditure for the Carters Creek Lab and SCADA Building project. The existing building no longer meets laboratory standards. The funds estimated in FY10 will be for the construction of the new building. In addition, $123,000 is estimated for Process Control Improvements at LCWWTP. This project will be for the purchase and installation of improved process control instrumentation at the Plant. An additional $80,000 has been included in FY10 for the installation of SCADA at the new lift stations. This will allow for monitoring and alarming of the new lift stations. Also included is $300,000 for remote plant security. This project will address the physical access and monitoring of these plants. $120,000 has been included for the Carters Creek Fiber Optic Ring. This project will implement a redundant Fiber Ring to Carters Creek Wastewater Treatment Plant. This will eliminate the spur and provide two paths of data into the Plant and will also eliminate extended outages of data loss from the LCWWTP. Finally, contingency in the amount of $150,000 has been included in the FY10 Approved Budget. These funds will be available for use on unanticipated projects as well as to offset project overruns. A total of $2,700,000 in current revenues from operations is estimated to be used to fund wastewater capital projects. Additionally, a debt issue of $7,600,000 is projected in FY10 for wastewater capital projects. BVSWMA Capital Projects  Appropriations in the amount of $2,495,132 are included in BVSWMA for capital project expenditures. These expenditures are related to construction of the Twin Oaks Landfill. Twin Oaks projects for which appropriations are approved include Construction Project Management, Access Improvements, Design Services, Buildings and Infrastructure construction, and Design Services.   ADDITIONAL O&M COSTS The FY10 Approved Budget includes a number of capital projects that have been recently completed and have added operations and maintenance (O&M) expense. In particular, the City’s general fund has been and will continue to be impacted by capital projects as they come online. In some situations, the O&M cost of a project is minimal and can be absorbed by the City department that is benefiting the most from the project. In other situations, the O&M cost is more significant and funding for these additional expenses is addressed through the Service Level Adjustment (SLA) process. In these situations, SLAs are submitted for the O&M needs of the capital projects and funding is considered as part of the budget process. Departments are expected to consider the impact of current and planned capital improvement projects on operations and maintenance (O&M) budgets. This analysis is a component of the 5-year Strategic Business Plans that are completed by all City departments. Projections as to the impact of capital projects on O&M budgets that are included in the Strategic Business Plans are used by the Finance Office in financial forecasting. Due to the limited availability of funds for FY10, increases in budgets for O&M related to capital projects were limited. Instead, departments were asked to evaluate current operations and make adjustments that would allow service levels to be met without a corresponding increase in budget. It is anticipated that the availability of funding for the O&M costs, particularly in the General Fund, will be limited in upcoming years. Therefore, departments will continue to evaluate current operations before increases in budget will be approved. Recommendations may also be made to delay projects for which O&M funding does not exist. Governmental Projects O&M The FY10 Approved Budget includes setting aside funds that will be used toward the anticipated O&M costs associated with the opening of Fire Station #6. $236,734 was set aside in the FY10 budget for this purpose. Funds will continue to be allocated each year so that the station can be operated once opened. Due to the limited availability of funds for FY10, other increases in budgets for O&M related to governmental capital projects were not included. Special Revenue Projects O&M Due to the limited availability of funds for FY10, increases in budgets for O&M related to special revenue capital projects were not included. 8 Utility Projects O&M The City of College Station strives to provide superior electric, water, and wastewater services to its citizens. Part of this effort includes investment in the capital that makes up the infrastructure. These investments take place in the form of capital improvement projects. Some of these improvements require additional operating and maintenance (O&M) costs. These costs are identified and ultimately become part of the cost of providing these utility services. As part of the budget process, the Water Services Department evaluated current operations to determine if adjustments could be made that would allow service levels to be met without a corresponding increase in budget. Several adjustments were made in the existing budget to accommodate anticipated O&M costs related to recently completed capital projects. Funds in the amount of $12,400 were reallocated within the Water and Wastewater budgets to account for maintenance costs associated with the recently installed physical access security system and video surveillance system. In addition, $14,000 was reallocated within the funds for a service agreement related to the emergency generators that were also recently installed. Finally, funds were reallocated in the Wastewater Fund to accommodate for an increase in the lift station O&M costs. BVSWMA O&M The FY10 Approved Budget includes budget in the amount of $188,800 for the costs associated with the transition of landfill operations from the Rock Prairie Road Landfill to the Twin Oaks Landfill in Grimes County. These costs include seven additional roll-off containers, two storage/work buildings, furniture and equipment, an additional Paradigm scale software license and procurement of general moving and heavy equipment specialty hauling. More detailed sheets that reflect the estimated O&M costs associated with the capital projects have been included in the final section of the CIP document. 9 Home of Texas A&M University ® 10 GGEENNEERRAALL GGOOVVEERRNNMMEENNTT-- SSTTRREEEETTSS,, TTRRAAFFFFIICC,, SSIIDDEEWWAALLKK AANNDD TTRRAAIILL CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000099--22001100 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22001144--22001155 11 GENERAL GOVERNMENT STREETS, TRAFFIC, SIDEWALKS, AND TRAILS CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT REVISED APPROVED PROJECT BUDGET APPROPRIATIONS FY 08-09 FY 09 -10 NUMBER AMOUNT THROUGH FY08 APPROPRIATIONS APPROPRIATIONS BEGINNING FUND BALANCE:24,388,395 10,922,774 ADDITIONAL RESOURCES: GENERAL OBLIGATION BONDS (03 GOB)1,603,000 1,080,000 GENERAL OBLIGATION BONDS (08 GOB)- 8,592,500 CERTIFICATES OF OBLIGATIONS - INTERGOVERNMENTAL TRANSFERS - - INTRAGOVERNMENTAL TRANSFERS 130,671 - INVESTMENT EARNINGS 279,000 77,000 OTHER - SUBTOTAL ADDITIONAL RESOURCES 2,012,671$ 9,749,500$ TOTAL RESOURCES AVAILABLE 26,401,066$ 20,672,274$ STREET REHABILITATION PROJECTS COLLEGE PARK/BREEZY HEIGHTS (SOUTHSIDE) ST0507 2,454,520 2,454,520 - - 2 NORTHGATE STREET REHAB ST0518 417,225 417,225 - - 1/2 TAUBER AND STASNEY REHAB/NG SIDEWALKS ST0505 2,252,110 2,252,110 - - CLOSED PROJECTS SUBTOTAL 5,123,855 -$ -$ STREET EXTENSION PROJECTS 2 OVERSIZE PARTICIPATION ST0519 576,611 256,046 - - 2 MANUEL DRIVE OP ST0802 27,004 27,004 - - 2 HOLLEMAN EXTENSION OP ST0913 2,000,000 700,565 39,435 - DISCOVERY DRIVE EXTENSION ST0804 2,000,000 2,000,000 - - EAGLE AVENUE EXTENSION ST0809 825,000 825,000 - - 3 VICTORIA AVENUE EXT ST0903 2,455,000 - 300,000 2,155,000 3 PENBERTHY EXTENSION ST0905 3,283,500 8,500 - 360,865 ROCK PRAIRIE ROAD PROJECTS - 2 ROCK PRAIRIE RD WIDENING - DESIGN & ROW ST0417 2,969,000 1,921,490 1,047,510 - 3 ROCK PRAIRIE RD WEST ROW ST1025 740,000 - - 115,000 BARRON ROAD PROJECTS - * BARRON ROAD RIGHT OF WAY ST0006 431,000 431,000 - - 2 BARRON ROAD REHABILITATION ST0409 3,000,000 3,000,000 - - 3 BARRON ROAD WIDENING PHASE II ST1026 11,415,000 - - 11,415,000 3 BARRON ROAD EAST/LAKEWAY TBD 15,135,000 - - - WILLIAM D. FITCH PKWY ROAD PROJECTS - 2 WILLIAM D. FITCH PKWY WIDENING PH II ST0520 4,530,000 4,530,000 - - ** CLOSED PROJECTS 125,000 SUBTOTAL 13,699,605 1,386,945$ 14,170,865$ STREET TXDOT PROJECTS TX AVE STREETSCAPE PH II ST9915 975,552 975,552 - - WELLBORN RD WIDENING LANDSCAPING - 2818 to 40 ST0812 96,859 96,859 - - CLOSED TXDOT PROJECTS - - - SUBTOTAL 1,072,411 -$ -$ BUDGET APPROPRIATIONS 12 GENERAL GOVERNMENT STREETS, TRAFFIC, SIDEWALKS, AND TRAILS CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED THROUGH FY07 FY 07-08 FY 08-09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 21,807,526 24,388,395 10,922,774 2,881,868 1,185,866 895,120 625,120 331,120 9,415,000 655,000 1,080,000 440,000 - - - - - 395,000 8,592,500 8,702,500 4,745,000 7,841,000 9,939,000 8,570,000 1,817,160 - - - - - - - - - - - - - - 143,563 130,671 - - - - - - 793,773 400,000 77,000 30,000 20,000 15,000 31,000 16,000 41,392 - - - - - - - 12,210,888$ 1,580,671$ 9,749,500$ 9,172,500$ 4,765,000$ 7,856,000$ 9,970,000$ 8,586,000$ 34,018,414$ 25,969,066$ 20,672,274$ 12,054,368$ 5,950,866$ 8,751,120$ 10,595,120$ 8,917,120$ 199,024 41,241 2,214,255 - - - - - - - - - 417,225 - - - - - 109,161 185,444 273,492 1,684,013 - - 1,207,551 96,023 - - - - - - 308,185$ 1,434,236$ 2,583,770$ 2,101,238$ -$ -$ -$ -$ -$ - - - - 280,000 296,611 - - - - 4,991 22,013 - - - - - - - - 300,000 1,700,000 - - - - - - 46,919 1,146,020 807,061 - - - - - - 3,273 821,727 - - - - - - - - 264,550 1,704,313 486,137 - - - - - - 8,500 360,865 1,417,000 1,497,135 - - - 693,937 47,980 121,610 989,110 1,111,363 5,000 - - - - - - 115,000 118,000 122,000 126,000 129,000 130,000 230,103 48,153 152,744 - - - - - - 384,088 87,145 2,528,767 - - - - - - - - - 5,707,500 5,707,500 - - - - - - - - - 1,685,000 4,280,000 4,495,000 4,675,000 - 306,316 3,340,989 882,695 - - - - - 4,623,807 555,291 527,291 - - - - - 1,308,128$ 5,168,582$ 9,262,211$ 12,793,835$ 9,120,000$ 3,605,746$ 4,406,000$ 4,624,000$ 4,805,000$ 315,926 63,227 - 596,399 - - - - - - 92,984 - - 3,875 - - - - - 484,200 382,054 315,926$ 640,411$ 382,054$ 596,399$ 3,875$ -$ -$ -$ -$ PROJECTED EXPENDITURES 13 GENERAL GOVERNMENT STREETS, TRAFFIC, SIDEWALKS, AND TRAILS CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT REVISED APPROVED PROJECT BUDGET APPROPRIATIONS FY 08-09 FY 09 -10 NUMBER AMOUNT THROUGH FY08 APPROPRIATIONS APPROPRIATIONS BUDGET APPROPRIATIONS TRAFFIC PROJECTS * VIDEO DETECTION - 2009 ST0907 35,116 35,116 - - 2 TRAFFIC SYSTEM SAFETY IMPR. ST0511 41,370 41,370 - - 2 LINCOLN/FOSTER IMPROVEMENTS ST0909 46,220 46,220 - - 2 BIRMINGHAM/LONGMIRE IMP ST0908 120,000 20,000 100,000 - 2 SCHOOL ZONE/PEDESTRIAN FLASHERS ST0916 20,000 20,000 - 2 NEW TRAFFIC SIGNAL PROJECTS (2003 GOB) ST0512 579,807 260,587 71,157 248,063 2 NEW SIGNAL WARRANT STUDY ST0912 39,400 - 39,400 - 2 UNIVERSITY/COPPERFIELD SIGNAL ST0914 200,000 200,000 - - 2 WELLBORN/CAPSTONE SIGNAL STUDY ST0917 1,380 - 1,380 - SIGNAL @ GB DRIVE EAST & DOMINIK ST0205 133,000 133,000 - - 3 NEW TRAFFIC SIGNAL PROJECTS (2008 GOB) ST1027 3,000,000 - - 100,000 2 TRAFFIC SIGNAL COMMUNICATIONS ST0411 82,240 82,240 - - 2 SIGNAL CONTROLLERS FOR FIBER ST0915 23,000 23,000 - - 2 TEXAS AVENUE FIBER ST0906 35,000 35,000 - - CLOSED PROJECTS SUBTOTAL 896,533 211,937$ 348,063$ SIDEWALKS & TRAILS 2005 BIKE LOOP - BIKE LOOP COMPLETION ST0530 327,202 327,202 - - MISC. BIKE TRAILS - BIKE LOOP COMPLETION ST9803 169,000 169,000 - - 2 HIKE AND BIKE TRAILS - LONGMIRE IMPROVEMENTS ST0521 1,033,624 1,033,624 - - COCS BEAUTIFICATION IMPROVEMENTS ST0515 324,000 324,000 - - 2 SIDEWALK IMPROVEMENTS (2003 GOB) ST0517 14,112 14,112 - - 2 LINCOLN SIDEWALKS ST0910 149,167 49,167 100,000 - 3 SIDEWALK IMPROVEMENTS (2008 GOB) ST1028 300,000 - - 100,000 3 HIKE AND BIKE TRAIL COMPLETION ST0904 1,000,000 - 333,000 667,000 3 LICK CREEK HIKE AND BIKE TRAIL TBD 4,410,000 - - - 3 UNIVERSITY DR PEDESTRIAN IMP Ph II TBD 7,055,000 - - - CLOSED PROJECTS SUBTOTAL 1,917,105 433,000$ 767,000$ CAPITAL PROJECTS SUBTOTAL 22,709,509 2,031,882$ 15,285,928$ OTHER 57,000 - LEGISLATIVE CONSULTING - - DEBT ISSUANCE COSTS 11,000 45,000 GENERAL & ADMIN. CHARGES 424,682 415,624 TOTAL EXPENDITURES 2,524,564$ 15,746,552$ ENDING FUND BALANCE:23,876,502$ 4,925,722$ * - Indicates projects funded through November 1998 G.O. Bond Authorization ** - Closed Projects includes balance of ST0211 - Dartmouth Extension. 1 - Funded through CDBG Funds. 2 - Indicates projects funded through 2003 G.O. Bond Authorization 3 - Indicates projects funded through 2008 G.O. Bond Authorization 14 GENERAL GOVERNMENT STREETS, TRAFFIC, SIDEWALKS, AND TRAILS CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED THROUGH FY07 FY 07-08 FY 08-09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 PROJECTED EXPENDITURES - - 35,116 - - - - - - - - 41,370 - - - - - - - - 46,220 - - - - - - - - 120,000 - - - - - - - - 20,000 - - - - - - - - 64,220 515,587 - - - - - - - 39,400 - - - - - - - - 200,000 - - - - - - - - 1,380 - - - - - - 33,373 - - - 99,627 - - - - - - - 100,000 500,000 600,000 600,000 600,000 600,000 22,430 5,125 - 54,685 - - - - - - - 23,000 - - - - - - - - 35,000 - - - - - - 422,303 211,407 - - - - - - 55,803$ 427,428$ 837,113$ 670,272$ 599,627$ 600,000$ 600,000$ 600,000$ 600,000$ 1,236 (1,021) 326,987 - - - - - - - 34,610 - 134,390 - - - - - 6,243 55,783 787,500 184,098 - - - - - - - 74,450 249,550 - - - - - 14,112 - - - - - - - - - - 149,167 - - - - - - - - - 100,000 100,000 100,000 - - - - - 125,000 500,000 375,000 - - - - - - - - 225,000 525,000 2,020,000 1,640,000 - - - - - - - 815,000 3,075,000 3,165,000 783,310 31,358 - - - - - - 21,591$ 872,682$ 1,494,462$ 1,168,038$ 700,000$ 625,000$ 2,835,000$ 4,715,000$ 3,165,000$ 2,009,633$ 8,543,338$ 14,559,610$ 17,329,782$ 10,423,502$ 4,830,746$ 7,841,000$ 9,939,000$ 8,570,000$ 228,381 57,000 - - - - - - 37,045 - - - - - - - 15,588 5,000 45,000 45,000 25,000 35,000 50,000 40,000 805,667 424,682 415,624 400,000 200,000 250,000 275,000 250,000 9,630,019$ 15,046,292$ 17,790,406$ 10,868,502$ 5,055,746$ 8,126,000$ 10,264,000$ 8,860,000$ 24,388,395$ 10,922,774$ 2,881,868$ 1,185,866$ 895,120$ 625,120$ 331,120$ 57,120$ 15 Home of Texas A&M University ® 16 SSTTRREEEETT RREEHHAABBIILLIITTAATTIIOONN PPRROOJJEECCTTSS 17 PROJECT: College Park/Breezy Heights Street Improvements FUND(S): PROJECT NUMBERS & BUDGET: 139 - Streets Capital Fund Streets:ST0507 $2,454,520 238 - Water Capital Fund Water: WF0595915 $1,640,000 239 - Wastewater Capital Fund Wastewater: WF0595926 $1,305,000 912 - Drainage Utility Fund Drainage: SD0601 $443,525 Total Project Budget: $5,843,045 PROJECT MANAGER:Edward McDonald FUNDING PROJECT SOURCES:Streets - CO's CLIENT:Public Works W/WW - Long Term Debt/Utility Revenue Water Services: Ed Savage Drainage - Drainage Utility Streets: Original Budget = $2,500,000; $36,980 transferred to West Park - FY08; $8,500 transferred to ST0905 - FY09 Drainage: Original Budget = $485,000; $41,475 transferred to West Park - FY08 Project Total This project includes street improvements in the area bounded by George Bush Drive, West Dexter Drive, Hereford Street, Holleman Drive, Eleanor Street and Fairview Avenue. As part of this project, the water and wastewater lines will be replaced and drainage improvements will be made. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR PROJECT DESCRIPTION/STATUS Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years -$ 459,719.17$ 1,962.24$ 578.62$ -$ 2008-09 0 29,577 4,864,761 220,000 266,447 2009-10 0 0 0 0 0 2010-11 0 0 0 0 0 2011-12 0 0 0 0 0 2012-13 0 0 0 0 0 2013-14 0 0 0 0 0 2014-15 0 0 0 0 0 $266,447PROJECT TOTAL $5,843,045$0 $489,296 $4,866,723 $220,579 $462,260 $5,380,785 $0 $0 $0 $0 $0 $0 18 Streets Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $239,686 $0 $579 $240,265 2008-09 9,000 2,107,172 60,000 38,083 $2,214,255 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Streets Total $0 $248,686 $2,107,172 $60,579 $38,083 $2,454,520 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $98,863 $1,962 $0 $100,825 2008-09 2,147 1,303,186 110,000 123,842 $1,539,175 2009-10 0$0 2010-11 0$0 2011-12 0$0 2012-13 0$0 2013-14 0$0 2014-15 0$0 Water Total $0 $101,010 $1,305,148 $110,000 $123,842 $1,640,000 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $92,022 $0 $0 $92,022 2008-09 13,978 1,051,404 50,000 97,596 $1,212,978 2009-10 0$0 2010-11 0$0 2011 12 0 $0 PROJECT: PROJECT CALENDAR OF EXPENDITURES BY FUND College Park/Breezy Heights Street Improvements 2011-12 0 $0 2012-13 0$0 2013-14 0$0 2014-15 0$0 Wastewater Total $0 $106,000 $1,051,404 $50,000 $97,596 $1,305,000 Drainage Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $29,148 $0 $0 $29,148 2008-09 4,452 402,999 6,926 $414,377 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Drainage Total $0 $33,600 $402,999 $0 $6,926 $443,525 PROJECT TOTAL $0 $489,296 $4,866,723 $220,579 $266,447 $5,843,045 First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 OPERATING COSTS 19 PROJECT: NORTHGATE STREET REHAB PROJECT #: ST0518 FUND: 139 - STREETS CAPITAL PROJECTS PROJECT BUDGET: $417,225 PROJECT MANAGER: TBD FUNDING SOURCES: 2003 Bond Authorization (GOB's) PROJECT CLIENT: Public Works Rehabilitation of Streets in the Northgate Area of the City to include portions of Church Street, Boyett, Cross, Lodge, Nagle, Patricia, Stasney, Tauber, and Spruce. This project is a funding source for smaller projects that are being completed in the Northgate area. The funds have been used as follows: Original project budget = $4,104,000 $417,225 transferred back from ST0523 - $800,000 transferred to ST0523 (Church Street Rehab) in FY05. balance of project - FY09 $2,000,000 transferred to ST0505 (Tauber and Stasney Rehab) in FY07. $887,063 transferred to ST0523 (Church Street Rehab) in FY07. $416,937 to be transferred to ST0416 (Univ Dr Pedestrian Improvements) in FY08. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 417,225 $417,225 2010-11 $0 2011-12 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $417,225 $0 $417,225 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 20 Home of Texas A&M University ® 21 PROJECT: Tauber/Stasney Rehab and Northgate Sidewalks FUND(S): PROJECT NUMBERS & BUDGET: 139 - Streets Capital Fund Streets:ST0505 $2,252,110 238 - Water Capital Fund Water: WF0625888 $305,660 239 - Wastewater Capital Fund Wastewater: WF0625893 $543,129 Total Project Budget: $3,100,899 PROJECT MANAGER:Edward McDonald FUNDING PROJECT SOURCES:Streets - CDBG, GOB's CLIENT:Public Works (Mark Smith) W/WW - Long Term Debt/Utility Revenue Streets Funding Break Down: $252,110 from CDBG funding &$2,000,000 transferred from ST0518 in FY07. Design for rehabilitation of Tauber and Stasney Street from University Drive to Cherry Street. Design and construction of new sidewalks on College Main. The project also includes the water and wastewater line rehabilitation on Tauber and Stasney streets from University Drive to Cherry Street. The water lines will be replaced with 8" lines and the wastewater lines replaced with 6" lines. PROJECT DESCRIPTION/STATUS Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 73,500 172,602 88,849 545 0 2008-09 40,500 9,000 613,757 40,000 38,625 2009-10 0 7,370 1,912,082 50,000 54,069 2010-11 0 0 0 0 0 2011-12 0 0 0 0 0 2012-13 0 0 0 0 0 2013-14 0 0 0 0 0 2014-15 0 0 0 0 0 $335,496 $741,882 $2,023,521 $0 $0 $92,694PROJECT TOTAL $3,100,899$114,000 $188,972 $2,614,688 $90,545 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR $0 $0 $0 22 Streets Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 73,500$ 131,710$ 88,849$ 545$ $294,605 2008-09 40,500 3,000 216,157 10,000 3,835 $273,492 2009-10 2,370 1,618,282 35,000 28,361 $1,684,013 2010-11 - $0 2011-12 - $0 2012-13 - $0 2013-14 - $0 2014-15 $0 Streets Total $114,000 $137,080 $1,923,288 $45,545 $32,197 $2,252,110 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years -$ 21,403$ -$ -$ $21,403 2008-09 3,000 168,800 20,000 14,770 $206,570 2009-10 2,000 65,000 5,000 5,688 $77,688 2010-11 - $0 2011-12 - $0 2012-13 - $0 2013-14 - $0 2014-15 $0 Water Total $0 $26,403 $233,800 $25,000 $20,458 $305,660 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years -$ 19,489$ -$ -$ $19,489 2008-09 3,000 228,800 10,000 20,020 $261,820 2009-10 3,000 228,800 10,000 20,020 $261,820 2010-11 - $0 PROJECT: PROJECT CALENDAR OF EXPENDITURES BY FUND Tauber/Stasney Rehab and Northgate Sidewalks 2011-12 - $0 2012-13 - $0 2013-14 - $0 2014-15 $0 Wastewater Total $0 $25,489 $457,600 $20,000 $40,040 $543,129 First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 OPERATING COSTS $90,545 $92,694 $3,100,899PROJECT TOTAL $114,000 $188,972 $2,614,688 23 SSTTRREEEETT EEXXTTEENNSSIIOONN PPRROOJJEECCTTSS 24 PROJECT: Oversize Participation PROJECT #: ST0519 FUND: 139 - Streets CIP Fund PROJECT BUDGET: $576,611 PROJECT MANAGER:Alan Gibbs FUNDING SOURCES: 2003 GO Bonds PROJECT CLIENT: Public Works Parent Project Funds provided for City-wide oversize participation projects. Original project budget = $2,700,000. $256,046 transferred back from ST0612 in FY09 $516,569 transferred to Corsair/AMS Street Extension (ST0612) in FY06. $23,431 transferred to Waterwood OP in FY06. $740,000 transferred to ST0913 in FY10 $187,569 transferred back from ST0612 in FY07. $1,260,000 to be transferred to ST0913 in FY10 $27,004 transferred to ST0802 - FY08. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 0 $0 2009-10 0 $0 2010-11 280,000 $280,000 2011-12 296,611 $296,611 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $576,611 $0 $576,611 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 25 PROJECT: Manuel Drive OP PROJECT #: ST0802 FUND: 139 - Streets CIP PROJECT BUDGET: $27,004 PROJECT MANAGER: Alan Gibbs FUNDING SOURCES: 2003 GO Bonds PROJECT transferred from ST0519 CLIENT: Public Works This project will upsize Manuel Drive extension from a local to a minor collector. $27,004 transferred from ST0519 - Oversize Participation - FY08 FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $4,991 $0 $4,991 2008-09 $22,013 $22,013 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $27,004 $0 $27,004 Total PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 First Fiscal Year Annually Harvey RdTe x a s Av e SDart mout h StHolleman D r E Manuel DrColgate DrCor n ell DrFm 2 154Harvey RdWilliam D. Fitch PkwyTexas Ave SWe ll b o r n R d Fm 158 26 PROJECT: Holleman Extension OP PROJECT #: ST0913 FUND: 139 - Streets CIP PROJECT BUDGET: $2,000,000 PROJECT MANAGER: Mark Smith FUNDING SOURCES: 2003 GO Bonds PROJECT transferred from ST0519 CLIENT: Public Works This project is for the extension of Holleman Drive so that it connects to Jones Butler which would provide access to FM 2818 at the signalized intersection with Holleman. The budget for this project will be transferred from ST0519 - Oversize Participation. FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $65,000 $235,000 $300,000 2009-10 $1,700,000 $1,700,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $65,000 $1,935,000 $0 $2,000,000 Total PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 First Fiscal Year Annually $0 $0 Fm 2 154Harvey RdWilliam D. Fitch PkwyTexas Ave SWe ll b o r n R d Fm 158 Fm 2154Harvey Mitchell Pkwy SWe ll b or n RdHol l eman Dr WJones-but l er RdChristine Ln27 PROJECT: Discovery Drive Extension PROJECT #: ST0804 FUND: 139 - Streets CIP PROJECT BUDGET: $2,000,000 PROJECT MANAGER:Jeff Haeber FUNDING SOURCES: Certificates of Obligation PROJECT CLIENT: Public Works This project is being delivered by College Station, and in turn, TXDOT is delivering the University Drive Pedestrian Improvements Phase I Project. This project will extend Discovery Drive north of Raymond Stotzer to a point where it will terminate just past the driveway entrance to the new TIPS building. In addition, pedestrian sidewalks will be added to the north of Raymond Stotzer from Agronomy Road to the new TIPS facility, and a new traffic signal will be added at the Large Animal Hospital driveway at Raymond Stotzer. FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $46,919 $0 $0 $0 $46,919 2008-09 333,950 795,134 16,936 $1,146,020 2009-10 795,134 11,927 $807,061 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $380,869 $1,590,268 $0 $28,863 $2,000,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually Fm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWellb o r n R d Fm 158 Wellb o r n R dUniversity DrGeorge Bush Dr28 Home of Texas A&M University ® 29 PROJECT: Eagle Avenue Extension FUND(S): PROJECT NUMBERS & BUDGET: 139 - Streets Capital Fund Streets:ST0809 $825,000 238 - Water Capital Fund Water: WF1095364 $101,464 Total Project Budget: $926,464 PROJECT MANAGER:Edward McDonald FUNDING PROJECT SOURCES:Streets - CO's CLIENT:Public Works (Mark Smith) Water - Long Term Debt/Utility Revenue The extension of Eagle Avenue from Victoria Avenue to Alexandria Drive. Design has been completed by a private developer who has also dedicated the required Right of Way. Construction of the project is the responsibility of the City of College Station. As part of the project, a water line will be extended along Eagle Avenue. Streets: Original Budget = $800,000; $25,000 transferred from ST0211 - FY08 Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $2,973 $0 $299 $0 2008-09 $0 $0 $880,027 $35,000 $8,164 2009-10 $0 $0 $0 $0 $0 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR PROJECT DESCRIPTION/STATUS $3,273 $923,191 $0$$$$$ 2010-11 $0 $0 $0 $0 $0 2011-12 $0 $0 $0 $0 $0 2012-13 $0 $0 $0 $0 $0 2013-14 $0 $0 $0 $0 $0 2014-15 $0 $0 $0 $0 $0 $0 $0 $8,164PROJECT TOTAL $926,464$0 $2,973 $880,027 $35,299 $0 $ $0 $0 30 Streets Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $2,973 $0 $299 $3,273 2008-09 $786,727 $35,000 $821,727 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Streets Total $0 $2,973 $786,727 $35,299 $825,000 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $93,300 $8,164 $101,464 2009-10 $0 $0 2010-11 $0 $0 2011-12 $0 $0 2012-13 $0 $0 2013-14 $0 $0 2014-15 $0 $0 Water Total $0 $0 $93,300 $0 $8,164 $101,464 First Fiscal Year Annually Total PROJECT TOTAL $0 $2,973 $880,027 OPERATING COSTS $35,299 $8,164 $926,464 PROJECT: PROJECT CALENDAR OF EXPENDITURES BY FUND Eagle Avenue Extension y Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 31 PROJECT: Victoria Avenue Extension FUND(S): PROJECT NUMBERS & BUDGET: 139 - Streets Capital Fund Streets:ST0903 $2,455,000 238 - Water Capital Fund Water: WF1158553 $228,375 239 - Wastewater Capital Fund Wastewater: WF1158560 $25,556 Total Project Budget: $2,708,931 PROJECT MANAGER:Donald Harmon FUNDING PROJECT SOURCES:Streets - 08 G.O.B.: $2,455,000 CLIENT:Public Works W/WW - URB Water Sevices: Stephen Maldonado, Jr Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 0 0 0 0 2008 09 0 212 000 0 60 000 5 600 This project will extend Victoria Avenue from Southern Plantation Drive to connect with State Highway 40, aligning with the existing Victoria Avenue on the south side of State Highway 40. The roadway will be a major collector consisting of two travel lanes and a center turn lane with bike lanes, sidewalks, landscaping, and storm drainage. Water and wastewater line upgrades will also be made as part of this project. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR PROJECT DESCRIPTION/STATUS $0 $277 6002008-09 0 212,000 0 60,000 5,600 2009-10 0 100,000 1,721,500 75,000 48,694 2010-11 0 20,000 400,000 57,776 8,361 2011-12 0 0 0 0 0 2012-13 0 0 0 0 0 2013-14 0 0 0 0 0 2014-15 0 0 0 0 0 $0 $0 $0 $486,137 $0 $277,600 $1,945,194 $62,655PROJECT TOTAL $2,708,931$0 $332,000 $2,121,500 $192,776 Victoria AvenueState Hwy 6Fm 2154R o c k P ra irie R d Fm 21 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 32 Streets Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 $0 2008-09 200,000 0 60,000 4,550 $264,550 2009-10 100,000 1,500,000 75,000 29,313 $1,704,313 2010-11 20,000 400,000 57,776 8,361 $486,137 2011-12 0$0 2012-13 0$0 2013-14 0$0 2014-15 0$0 Streets Total $0 $320,000 $1,900,000 $192,776 $42,224 $2,455,000 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 10,000 875 $10,875 2009-10 200,000 17,500 $217,500 2010-11 0$0 2011-12 0$0 2012-13 0$0 2013-14 0$0 2014-15 0$0 Water Total $0 $10,000 $200,000 $0 18375 $228,375 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 2,000 175 $2,175 2009-10 21,500 1,881 $23,381 2010 11 0 $0 PROJECT: PROJECT CALENDAR OF EXPENDITURES BY FUND Victoria Avenue Extension 2010-11 0$0 2011-12 0$0 2012-13 0$0 2013-14 0$0 2014-15 0$0 Wastewater Total $0 $2,000 $21,500 $0 2056 $25,556 First Fiscal Year Annually Total Personnel $0 Supplies $0 Service 7000 $7,000 Capital $0 TOTAL $0 $7,000 $7,000 PROJECT TOTAL $0 OPERATING COSTS $2,121,500 $192,776 $62,655 $2,708,931$332,000 33 PROJECT: Penberthy Boulevard Extension PROJECT #: ST0905 FUND: 139 - Streets Capital Projects Fund PROJECT BUDGET: $3,283,500 PROJECT FUNDING MANAGER: Jeff Haeber SOURCES: 2008 General Obligation Bonds PROJECT CLIENT: Public Works FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 8,500 0 $8,500 2009-10 355,532 5,333 $360,865 2010-11 1,386,059 10,000 20,941 $1,417,000 2011-12 1,465,010 10,000 22,125 $1,497,135 2012-13 $0 2013 14 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR The project makes an important connection between high density student housing and the A&M campus. Currently the apartment development is connected via Marion Pugh Drive. This connection will be limited by a railroad grade separation proposed by TxDOT. Penberthy Boulevard will be extended from the Luther Street / Jones Butler intersection and across A&M property to the George Bush Drive / Penberthy Boulevard intersection. The project will require an equestrian crossing to accommodate University operations. A traffic signal will need to be installed at the George Bush Drive and Penberthy Boulevard intersection. Original budget = $3,275,000; $8,500 transferred from ST0507 - FY09 2013-14 $0 2014-15 $0 TOTAL $0 $364,032 $2,851,069 $20,000 $48,399 $3,283,500 Total Personnel $0 Supplies $0 Service $5,500 Capital $0 TOTAL $5,500$0 5,500 $5,500 NET INCREASE IN OPERATING COSTS First Fiscal Year Annually We ll b or n Rd Harve y M i t c h e l l Pkwy S Jon es-but le r R dWel sh AveOlsen Blvd Christin e L n P enbert h y Bl v d Village DrDiscovery DrD etr oit StRese a r c h PkwyBarbara Bu s h D r A riz o n a S tBurt StFm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 34 PROJECT: Rock Prairie Road East Widening PROJECT #: ST0417 Design & ROW FUND: 139 - Street Capital Projects PROJECT BUDGET: $2,969,000 PROJECT Jeff Haeber MANAGER: FUNDING SOURCES: 2003 GOB's PROJECT CLIENT: Public Works This project is for design services related to the widening of Rock Prairie East to a minor arterial section as shown on the Thoroughfare Plan from SH 6 Frontage Road to Greens Prairie Road. This includes design for the minor arterial section, sidewalks, storm drain facilities, lighting plan, etc. This budget also includes funds for all Right of Way (ROW) acquisition for the full minor arterial section. The project consists of design and ROW only. No funds are included in this budget for construction. Bleyl & Associates was awarded the engineering design by the City Council on February 10, 2005 for $795,000. This is a professional services contract for the engineering design for the proposed widening of Rock Prairie Road to a minor arterial from Highway 6 to Greens Prairie Road. The conceptual design will include topographic and utility surveys and provide an assessment of the interrelationship between rights-of-way, utilities, existing easements and drainage. The contract includes development of plans, specifications and final cost estimates. It will also provide survey work and legal descriptions for purchase of right-of-way. FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $11,525 $721,203 $0 $9,190 $0 $741,917 2008-09 119,110 2,500 121,610 2009-10 969,110 10,000 10,000 989,110 2010-11 969,110 137,253 5,000 1,111,363 2011-12 . 5,000 5,000 2012-13 0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2012 13 0 2013-14 0 2014-15 0 TOTAL $2,068,855 $858,456 $0 $29,190 $12,500 $2,969,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 35 PROJECT: Rock Prairie Road West ROW PROJECT #: ST1025 FUND: 139 - Streets Capital Projects Fund PROJECT BUDGET: $740,000 PROJECT FUNDING MANAGER: Jeff Haeber SOURCES: 2008 General Obligation Bonds PROJECT CLIENT: Public Works FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 75,000 40,000 $115,000 2010-11 118,000 $118,000 2011-12 122,000 $122,000 2012-13 126,000 $126,000 2013 14 129 000 $129 000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR This project includes the purchase of additional right-of-way from State Highway 6 to Normand Drive to provide for the future widening of that section of Rock Prairie Road. 2013-14 129,000 $129,000 2014-15 130,000 $130,000 TOTAL $700,000 $40,000 $0 $0 $740,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 NET INCREASE IN OPERATING COSTS First Fiscal Year Annually Fm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 R o c k P ra irie R d S H 6 S Fro n t a g e 6 Rd EPi er r e Pl To d d T rlNormand Dr AlleyGail PlA ust in Av eA rn o ld R d P in o n D rSandy Ci r S u s s e x D r 36 PROJECT: BARRON ROAD RIGHT OF WAY PROJECT #: ST0006 FUND: 139 - Street Capital Projects PROJECT BUDGET: $431,000 PROJECT MANAGER: Daniel Beamon FUNDING SOURCES: 1998 General Obligation PROJECT Bond Funds CLIENT: Public Works This project will upgrade Barron Road from a two lane rural highway to a minor arterial road as reflected on the Thoroughfare Plan. This project will establish an alignment and acquire the necessary right-of-way. Original budget = $316,000 2003 budget amendment added $115,000 for land purchase FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $248,689 $29,567 $0 $0 $278,256 2008-09 $152,744 $152,744 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $401,433 $29,567 $0 $0 $431,000 Total PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR PROJECT DESCRIPTION/STATUS OPERATING COSTS First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 First Fiscal Year Annually $0 $0 37 PROJECT: Barron Road Rehabilitation FUND(S): PROJECT NUMBERS & BUDGET: 139 - Streets Capital Fund Streets:ST0409 $3,000,000 238 - Water Capital Fund Water: WF0654325 $100,000 239 - Wastewater Capital Fund Wastewater: WF0654332 $10,850 Total Project Budget: $3,110,850 PROJECT MANAGER:Ed McDonald FUNDING PROJECT SOURCES:Streets - 03 G.O.B.: $3,000,000 CLIENT:Public Works W/WW - Long Term Debt/Utility Revenue Water Services (Ed Savage) PROJECT DESCRIPTION/STATUS This project includes the upgrade of Barron Road from a two lane rural highway to a minor arterial road as reflecting on the Thoroughfare Plan. The Streets portion of the project provides design services for the entire project and for the first phase of construction. The first phase of construction will be from the SH6 frontage road to Decatur Drive. Water lines and meters as well as wastewater lines and manholes will be relocated. The Water portion of this project is expected to come in under budget. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 470,612 0 622 0 2008-09 0 417,700 2,128,696 0 42,046 2009-10 0 0 0 0 0 2010-11 0 0 0 0 0 2011-12 0 0 0 0 0 2012-13 0 0 0 0 0 2013-14 0 0 0 0 0 2014-15 0 0 0 0 0 $471,233 $2,588,442 $0 $0 $0 $0 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR $42,046PROJECT TOTAL $3,059,675$0 $888,312 $2,128,696 $622 $0 $0 Barron RdDecatur Dr E a g le Av Southern Plantation DrFr ont a ge 6 RdTiffany TrCardinal L n S t a r lin g D r Fr ont a ge 6 RdFm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 38 Streets Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $470,612 $0 $622 $0 $471,233 2008-09 377,700 2,113,696 $37,371 $2,528,767 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Streets Total $0 $848,312 $2,113,696 $622 $37,371 $3,000,000 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 30,000 15000 $3,825 $48,825 2009-10 $0 $0 2010-11 $0 $0 2011-12 $0 $0 2012-13 $0 $0 2013-14 $0 $0 2014-15 $0 $0 Water Total $0 $30,000 $15,000 $0 $3,825 $48,825 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 10,000 850 $10,850 2009-10 0$0 2010-11 0 $0 Barron Road RehabilitationPROJECT: PROJECT CALENDAR OF EXPENDITURES BY FUND 2010-11 0 $0 2011-12 0$0 2012-13 0$0 2013-14 0$0 2014-15 0$0 Wastewater Total $0 $10,000 $0 $0 $850 $10,850 First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 $2,128,696 $622PROJECT TOTAL $0 $888,312 OPERATING COSTS $42,046 $3,059,675 39 Barron Road Widening Phase 2 FUND(S): 139 - Streets Capital Projects Fund PROJECT NUMBERS & BUDGET: 238 - Water Capital Fund Streets: ST1026 $11,415,000 239 - Wastewater Capital Fund Water: TBD $150,000 Wastewater: TBD $100,000 Total Project Budget: $11,665,000 PROJECT MANAGER:Daniel Beamon FUNDING PROJECT SOURCES:2008 General Obligation Bonds CLIENT:Public Works W/WW - Long Term Debt/Utility Revenue Water Services (Ed Savage) This project includes the upgrade of Barron Road from a two lane rural highway to a four lane road with sidewalks, raised center median, landscaping, storm sewers and street lighting. In 2003, voters approved funds for the design of this section of roadway as well as to purchase necessary right of way. In 2008, voters approved funds to construct Barron from Decatur Drive to William D Fitch Parkway. The project will also include some improvements to the water and wastewater system to relocate water lines, meters, wastewater lines, and manholes as required to be funded by Water and Wastewater Capital Projects Funds. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR PROJECT DESCRIPTION/STATUS Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 0 0 0 0 2008-09 0 0 0 0 0 2009-10 0 0 5,881,482 0 76,018 2010-11 0 0 5,650,000 0 57,500 2011-12 0 0 0 0 0 2012-13 0 0 0 0 0 2013-14 0 0 0 0 0 2014-15 0 0 0 0 0 $133,518PROJECT TOTAL $11,665,000$0 $0 $11,531,482 $0 $0 $0 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR $0 $0 $5,957,500 $0 $5,707,500 $0 Fm 2154W i l l i a m D F i t c h P wBarron RdDecatur DrVi ct or i a AvFm 215 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 40 Streets Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 $0 2008-09 0$0 2009-10 5,650,000 57,500 $5,707,500 2010-11 5,650,000 57,500 $5,707,500 2011-12 0$0 2012-13 0$0 2013-14 0$0 2014-15 0$0 Streets Total $0 $0 $11,300,000 $0 $115,000 $11,415,000 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 0$0 2009-10 138,889 11,111 $150,000 2010-11 0$0 2011-12 0$0 2012-13 0$0 2013-14 0$0 2014-15 0$0 Water Total $0 $0 $138,889 $0 $11,111 $150,000 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 0$0 2009-10 92,593 7,407 $100,000 2010-11 0 $0 PROJECT: PROJECT CALENDAR OF EXPENDITURES BY FUND Barron Road Widening Phase 2 2010 11 0 $0 2011-12 0$0 2012-13 0$0 2013-14 0$0 2014-15 0$0 Wastewater Total $0 $0 $92,593 $0 $7,407 $100,000 First Fiscal Year Annually Total Personnel $0 Supplies $0 Service 11,000 $11,000 Capital $0 TOTAL $0 $11,000 $11,000 $133,518 OPERATING COSTS $11,531,482 $11,665,000PROJECT TOTAL $0 $0$0 41 PROJECT: Barron Road East/Lakeway Drive PROJECT #: TBD FUND: 139 - Streets Capital Projects Fund PROJECT BUDGET: $15,135,000 PROJECT FUNDING MANAGER: Donald Harmon SOURCES: 2008 General Obligation Bonds PROJECT CLIENT: Public Works FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 600,000 985,000 100,000 $1,685,000 2012-13 450,000 3,630,000 200,000 $4,280,000 2013 14 100 000 4 195 000 200 000 $4 495 000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR The project is the extension of Barron Road from SH 6 east at the existing Barron Road to a future intersection with the extension of Lakeway. The portion of Lakeway included extends from its intersection with Barron southward to connect to Lakeway that will be built by private development. This project is part of a recent thoroughfare plan amendment that was recommended by the East College Station Transportation Study. According to the transportation consultant's study, this new corridor will reduce congestion at the Rock Prairie SH6 intersection. 2013-14 100,000 4,195,000 200,000 $4,495,000 2014-15 50,000 4,500,000 125,000 $4,675,000 TOTAL $600,000 $1,585,000 $12,325,000 $625,000 $15,135,000 Total Personnel $0 Supplies $0 Service $37,000 Capital $0 TOTAL $37,000 NET INCREASE IN OPERATING COSTS First Fiscal Year Annually $0 37,000 $37,000 Fm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 L a k e wa y Dr.Barron RdS H 6 SF r o nt age 6 Rd E Rock Prairie Rd Barron RdLo n g mire DrDeca tur D r William D. Fitch PkwySpearman DRitchey RdAgate DrOffra m p 6 SNorfolk Ct42 Home of Texas A&M University ® 43 PROJECT: W. D. Fitch Parkway Widening Phase II FUND(S): PROJECT NUMBERS & BUDGET: 139 - Streets Capital Fund Streets:ST0520 $4,530,000 238 - Water Capital Fund Water: WF1092576 $35,000 Total Project Budget: $4,565,000 PROJECT MANAGER:Danielle Charbonnet FUNDING PROJECT SOURCES:Streets - 2003 GOB and CO's CLIENT:Public Works: Gary Balmain Water - Long Term Debt/Utility Revenue Water Services: Fred Surovik William D. Fitch Pkwy will be widened to a minor arterial between Pebble Creek Parkway and Rock Prairie Road. The 18" water line that crosses Fitch just west of the intersection will be extended across Rock Prairie Road as a 12" line. The sewer line that is part of the Fitch Area 6 East project (WF0805756) will also be extended across Rock Prairie Road with this project. Substantial completion is January 2010. Project Total PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR PROJECT DESCRIPTION/STATUS j FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $306,316 $0 $0 $0 2008-09 $100,336 $48,470 $3,105,983 $63,000 $58,200 2009-10 $0 $0 $853,665 $10,000 $19,030 2010-11 $0 $0 $0 $0 $0 2011-12 $0 $0 $0 $0 $0 2012-13 $0 $0 $0 $0 $0 2013-14 $0 $0 $0 $0 $0 2014-15 $0 $0 $0 $0 $0 $0 $0 $77,230PROJECT TOTAL $4,565,000$100,336 $354,786 $3,959,648 $73,000 $0 $306,316 $3,375,989 $882,695 $0 $0 WD Fitch  Widening Ph II 44 Streets Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $306,316 $0 $0 $0 $306,316 2008-09 $100,336 $48,470 $3,074,983 $60,000 $57,200 $3,340,989 2009-10 $853,665 $10,000 $19,030 $882,695 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Streets Total $100,336 $354,786 $3,928,648 $70,000 $76,230 $4,530,000 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $31,000 $3,000 $1,000 $35,000 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Water Total $0 $0 $31,000 $3,000 $1,000 $35,000 First Fiscal Year Annually Total PROJECT TOTAL $100,336 $354,786 $3,959,648 OPERATING COSTS $73,000 $77,230 $4,565,000 PROJECT: PROJECT CALENDAR OF EXPENDITURES BY FUND W. D. Fitch Parkway Widening Phase II y Personnel $0 Supplies $0 Service 11,000$ $11,000 Capital $0 TOTAL $0 $11,000 $11,000 45 SSTTRREEEETT TTXXDDOOTT PPRROOJJEECCTTSS 46 PROJECT: TEXAS AVENUE STREETSCAPE PROJECT #: ST9915 PHASE II FUND: 139 - Streets Capital Projects PROJECT BUDGET: $975,552 PROJECT MANAGER: TROY ROTHER FUNDING SOURCES: STREETS CIP PROJECT CLIENT: Public Works This is a part of the Texas Avenue Widening Phase II project. This is for the cost of streetscape improvements such as raised medians and streetscape light poles. Project combined with George Bush Drive Median project in FY06. Budget of $499,552.00 transferred from this project (ST0102). $24,000 transferred to ST0515 - FY09 FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $344 $378,616 $193 $379,153 2008-09 0 2009-10 596,399 596,399 2010-11 0 2011-12 0 2012-13 0 2013-14 0 2014-15 0 TOTAL $0 $344 $975,015 $193 $975,552 Total Personnel $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Personnel $0 Supplies $0 Service $10,000 Capital $0 TOTAL $10,000$0 10,000 $10,000 47 PROJECT: TxDOT Landscaping - Wellborn Rd PROJECT #: ST0812 FM 2818 to SH 40 FUND: 139 - Streets Capital Projects PROJECT BUDGET: $96,859 PROJECT MANAGER: Ross Albrecht FUNDING SOURCES: Street CIP - Fund Balance PROJECT CLIENT: Public Works This project is an Advance Funding Agreement (AFA) with the Texas Department of Transportation (TxDOT) to install, as part of the Wellborn Road Widening project, landscape and hardscape improvements on Wellborn Road from FM 2818 to SH 40. The AFA is for cost participation by the city in the design and construction of the landscape hardscape elements, and also indicates that the city will take over maintenance and responsibilities in the future. The majority of the landscape and hardscape improvements will be located in raised medians. Construction of these improvements is anticipated to be complete in FY11. FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $92,984 $0 $92,984 2008-09 0 2009-10 0 2010-11 3,875 3,875 2011-12 0 2012-13 0 2013-14 0 2014-15 0 TOTAL $0 $0 $96,859 $0 $0 $96,859 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $0 Supplies $0 Service $24,000 Capital $0 TOTAL $24,000$12,000 $12,000 $12,000 $12,000 OPERATING COSTS First Fiscal Year Annually 48 TTRRAAFFFFIICC PPRROOJJEECCTTSS 49 PROJECT:Video Detection - 2009 PROJECT #: ST0907 FUND: 139 - Streets Capital Projects PROJECT BUDGET: $35,116 PROJECT MANAGER: Lee Robinson FUNDING SOURCES: 1998 GOB - ST0011 PROJECT CLIENT: Public Works Vehicle detection is one of the most critical components of a vehicle acutated signal system. Road failures and roadway construction are the main reasons wire wound loops embedded in the roadway fails. The advantage of utilizing cameras are numerous: no long term workzone blocking traffic; the zones can be programmed with a mouse; and, unlike cut loops, the location is permanent. Also, one camera can detect several vehicle movements. The City is gradually replacing failed loops with video cameras. These cameras will be installed in various locations. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 35,116 $35,116 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $35,116 $0 $35,116 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 50 PROJECT: Traffic System Safety Improvements PROJECT #: ST0511 FUND: 139 - Streets CIP Fund PROJECT BUDGET: $41,370 PROJECT Holding Account MANAGER: Lee Robinson FUNDING SOURCES: 2003 GOB - $500,000 PROJECT CLIENT: Public Works This project serves to hold funds for new traffic signal projects. Original budget was $500,000. As new signal projects are created, funds will be allocated to those projects and this project balance will be reduced. Projects on which these funds are currently used include: Original project budget = $500,000 $38 transferred to ST0602 - FY08 $34,290 transferred to ST0525 - FY05 $50,000 transferred to ST0811 - FY08 $27,500 transferred to ST0527 - FY05 $3,516 transferred from ST0527 - FY08 $7,500 transferred to ST0528 - FY05 $31,556 transferred fr ST0811 - balance of proj - FY09 $945 transferred to ST0605 - FY06 $46,220 transferred to ST0909 - FY09 $61,370 transferred to ST0516 - FY06 $120,000 transferred to ST0908 - FY09 $28,000 transferred to ST0602 - FY06 $20,000 transferred to ST0916 - FY09 $100,000 tranferred to ST0602 - FY07 $61,370 transferred from ST0516 - balance of project - FY09 $6,827 transferred to ST0525 - FY07 $52,000 transferred to ST0521 - FY09 $382 transferred to ST0528 - FY07 FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 41,370 $41,370 2009-10 $0 2010-11 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $41,370 $0 $41,370 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 51 PROJECT: Lincoln/Foster Improvements PROJECT #: ST0909 FUND: 139 - Streets CIP Fund PROJECT BUDGET: $46,220 PROJECT MANAGER:Gary Balmain FUNDING SOURCES: 2003 GO Bonds - ST0511 PROJECT CLIENT: Public Works This project is to level the intersection at Lincoln and Foster by widening the valley gutter and concrete apron. FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 46,220 $46,220 2009-10 $0 2010-11 $0 2011-12 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $46,220 $0 $0 $46,220 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually Lincoln AveFrancis DrTexas AveLincoln AveWalt on DrUniversity D r E P ur yea r DrFo ste r AveNi mi t z St Dominik DrM i l ner D r As h bur n Av e Gi lc h r i s t A v eCooner StFront StP olo RdN e w M a in D rAlle y R o s e C irBanks StWellesley CtFm 21 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 52 PROJECT: Birmingham/Longmire Improvements PROJECT #: ST0908 FUND: 139 - Streets CIP Fund PROJECT BUDGET: $120,000 PROJECT MANAGER:Gary Balmain FUNDING SOURCES: 2003 GO Bonds - ST0511 PROJECT CLIENT: Public Works This project was to level the intersection at Longmire and Birmingham by widening the valley gutter and concrete apron. These improvements were completed in FY09. FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 120,000 $120,000 2009-10 $0 2010-11 $0 2011-12 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $120,000 $0 $0 $120,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 Fm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 S H 6 SLongm i r e DrGraham RdF r o n ta g e 6 Rd WF r ont age 6 Rd ER o c k P r a irie R d B irm in g h a m R d B ridle C t Gl enna CtS H 6 S53 PROJECT: School Zone/Pedestrian Flashers PROJECT #: ST0916 FUND: 139 - Streets CIP Fund PROJECT BUDGET: $20,000 PROJECT MANAGER:Lee Robinson FUNDING SOURCES: 2003 GO Bonds - ST0511 PROJECT CLIENT: Public Works The newly opened Creekview Elementary created a need to install (3) school zone flashers. Also installed was a flasher warning of a traffic signal heading northbound Texas Avenue at Deacon Drive. In addition, two pedestrian warning flashers will be installed on University Drive eastbound near Boyett and westbound near Polo Rd. FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 20,000 $20,000 2009-10 $0 2010-11 $0 2011-12 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $20,000 $0 $0 $20,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually Fm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 54 PROJECT: New Traffic Signal Projects (2003 GOB) PROJECT #: ST0512 FUND: 139 - Streets Capital Projects PROJECT BUDGET: $579,807 PROJECT MANAGER: Lee Robinson FUNDING SOURCES: 2003 GOB PROJECT CLIENT: Public Works This project serves to hold funds for new traffic signal projects. Original budget was $2,250,000. As new signal projects are created, funds are allocated to those projects and this project balance is reduced. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 64,220 $64,220 2009-10 515,587 $515,587 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $579 807 $0 $579 807 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $579,807 $0 $579,807 Total Personnel $0 Supplies $0 Service $5,400 Capital $0 TOTAL $5,400 OPERATING COSTS First Fiscal Year Annually $0 5,400 $5,400 55 PROJECT: New Signal Warrant Study PROJECT #: ST0912 FUND: 139 - Streets CIP Fund PROJECT BUDGET: $39,400 PROJECT MANAGER:Troy Rother FUNDING SOURCES: 2003 GO Bonds - ST0512 PROJECT CLIENT: Public Works This project was for the study of 11 intersections to determine whether signals are warranted. The results of the study indicated that signals are warranted at the following intersections (in priority order): SH 40 @ Barron Road SH 40 @ Arrington Road Texas Avenue @ Krenek Tap Road George Bush East @ Dominik SH 30 @ Copperfield FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 39,400 $39,400 2009-10 $0 2010-11 $0 2011-12 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $39,400 $0 $0 $39,400 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually Fm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 56 PROJECT: University/Copperfield Signal PROJECT #: ST0914 FUND: 139 - Streets CIP Fund PROJECT BUDGET: $200,000 PROJECT MANAGER:Troy Rother FUNDING SOURCES: 2003 GO Bonds - ST0512 PROJECT CLIENT: Public Works This project is for the installation of a signal along University Drive at Copperfield. This project is being completed through interlocal agreements with the City of Bryan and TxDOT. The cities will split the cost of this signal construction while TxDOT will pay for the cost to widen the intersection. FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 200,000 $200,000 2009-10 $0 2010-11 $0 2011-12 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $200,000 $0 $0 $200,000 Total Personnel $0 Supplies $0 Service $1,800 Capital $0 TOTAL $1,800 OPERATING COSTS First Fiscal Year Annually $0 1,800 $1,800 University Dr EOld Ti RdCopp erfield PkwyFm 21 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 57 PROJECT: Wellborn/Capstone Signal Study PROJECT #: ST0917 FUND: 139 - Streets CIP Fund PROJECT BUDGET: $1,380 PROJECT MANAGER:Troy Rother FUNDING SOURCES: 2003 GO Bonds - ST0512 PROJECT CLIENT: Public Works This project consists of conducting a signal warrant study at the intersection of Wellborn and Capstone so a determination can be made by Brazos County and TxDOT as to whether or not improvements are needed. FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 1,380 $1,380 2009-10 $0 2010-11 $0 2011-12 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $1,380 $0 $0 $0 $1,380 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually Fm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 Fm 2154Barron RdC a p s t o n e D rAlacia Ct T r e e l i n e D r Bucki ngham Cr Barron Cut-off Rd58 PROJECT: SIGNAL @ GEORGE BUSH/DOMINIK PROJECT #: ST0205 FUND: 139 - Streets Capital Projects PROJECT BUDGET: $133,000 PROJECT FUNDING MANAGER: LEE ROBINSON SOURCES: 1998 G.O. BONDS CIP FUNDS Since the widening of G Bush East a new traffic warrant study was conducted, at that time the intersection did not meet traffic volumes to warrant a signal. It has been decided to do another warrant study after Texas Avenue Phase II project is completed. Most all materials are in-stock to build this traffic signal. More than likely if this location meets warrants during the next study it will be built in 2010-2011 fiscal year. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $5,309 20,032 $8,033 $33,373 2008-09 $0 2009-10 $0 2010-11 99,627 $99,627 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $5,309 $119,659 $8,033 $133,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $0 Supplies $0 Service Utilities $1,800 Capital $0 TOTAL $1,800$0 $1,800 OPERATING COSTS Annually 1,800 First Fiscal Year Fm 2154Harvey RdWilliam D. Fitch PkwyT e x a s Av e SWe ll b o r n R d Fm 158 Harvey RdT e x a s Av e S T e x a s A v eFo st er Ave Dominik DrFrancis DrHolleman Dr EUniversity Oaks BlvdPur y e a r Dr Mil n er Dr Richards StGilc h r i s t A v e Re d m o n d D rWalton D r Kyle Ave59 PROJECT: New Traffic Signal Projects (2008 GOB) PROJECT #: ST1027 FUND: 139 - Streets Capital Projects PROJECT BUDGET: $3,000,000 PROJECT MANAGER: Lee Robinson FUNDING SOURCES: 2008 GOB PROJECT CLIENT: Public Works This project serves to hold funds for new traffic signal projects. Original budget was $3,000,000 ($500,000 per year FY 10 thru 15). As new signal projects are created, funds will be allocated to those projects and this project balance will be reduced. Original project budget = $3,000,000 FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 100,000 $100,000 2010-11 500,000 $500,000 2011-12 600,000 $600,000 2012-13 600,000 $600,000 2013-14 600,000 $600,000 2014-15 600,000 $600,000 TOTAL $0 $0 $3 000 000 $0 $3 000 000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $3,000,000 $0 $3,000,000 Total Personnel $0 Supplies $0 Service $27,000 Capital $0 TOTAL $27,000 OPERATING COSTS First Fiscal Year Annually $0 27,000 $27,000 60 PROJECT: Traffic Signal Communications PROJECT #: ST0411 FUND: 139 - Streets Capital Projects PROJECT BUDGET: $82,240 PROJECT Holding Account MANAGER: Lee Robinson FUNDING SOURCES: 2003 GOB - $250,000 PROJECT CLIENT: Public Works This project will consist of installing fiber optics to interconnect traffic signals and, in some cases, will utilize wireless technology. Presently 15 signals are not interconnected. Communications provides instant upload and download of data, ability to monitor the system and possible make repairs from the signal shop.Installed wireless radios on Texas, installed conduit for fiber optics at Holleman & G Bush. Udgrades from copper cables to fiber optics will continue to be made and communications will be made to signals that are currently without. Original project budget = $250,000 $50,000 transferred to ST0607 in FY06 $240 transferred from ST0703 - FY08 (balance of project) $50,000 transferred to ST0608 in FY06 $35,000 transferred to ST0906 - FY09 $10,000 transferred to ST0703 in FY07 $23,000 transferred to ST0915 - FY09 FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $27,555 $0 $27,555 2008-09 $0 2009-10 54,685 $54,685 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2013-14 $0 2014-15 $0 TOTAL $0 $0 $82,240 $0 $82,240 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS AnnuallyFirst Fiscal Year 61 PROJECT: Signal Controllers for Fiber PROJECT #: ST0915 FUND: 139 - Streets Capital Projects PROJECT BUDGET: $23,000 PROJECT MANAGER: Lee Robinson FUNDING SOURCES: 2003 GOB - ST0411 PROJECT CLIENT: Public Works This project will purchase a group of Nema Type I signal controllers that are fiber optics ready. Fiber was recently installed on Harvey Road and the controllers must upgraded to accommodate the communications. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 23,000 $23,000 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $23,000 $0 $23,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $23,000 $0 $23,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 62 PROJECT: Texas Avenue Fiber PROJECT #: ST0906 FUND: 139 - Streets Capital Projects PROJECT BUDGET: $35,000 PROJECT MANAGER: Lee Robinson FUNDING SOURCES: 2003 GOB - ST0411 PROJECT CLIENT: Public Works This project is needed to restore traffic signal communications that were removed from power poles during the Texas Avenue Phase II widening. Currently communication is occurring through wireless radios. Conduit was installed during the construction and now the fiber optics cable must be installed. This communications media will provide connectivty to the signals and will also provide IT Communications with a additional backup ring for the telephone system. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 35,000 $35,000 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $35,000 $0 $35,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $35,000 $0 $35,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 63 SSIIDDEEWWAALLKKSS AANNDD TTRRAAIILLSS 64 PROJECT: BIKE LOOP - 2005 PROJECT #: ST0530 FUND: 139 - Streets Capital Projects PROJECT BUDGET: $327,202 PROJECT MANAGER: Danielle Charbonnet FUNDING SOURCES: 1989 GOB PROJECT CLIENT: Public Works - Mark Smith This project is Phase III of the ST9409 Bike Loop project. The bike loop will make the connection from the Bee Creek bridge to the existing bike loop. ST9409 included the construction of a bike loop system consisting of signed bike routes, on-street bike lanes, and off-street bike paths to link the Texas A&M University Campus, City of College Station Parks, and local housing areas. Phases I & II are complete. Funds from ST9803 and ST0521 are expected to be spent in conjunction with this project's funds to complete the bike loop project, 2005 Bike Loop Phase II -- Bike Loop Completion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $215 $215 2008-09 326,987 $326,987 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2014-15 $0 TOTAL $0 $0 $326,987 $215 $0 $327,202 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually BEE CREEK PARK & ARBORETUMBEE CREEK PARK & ARBORETUM CY MILLER PARKCY MILLER PARK T e x a s Av e S Krenek Tap RdWilliam King Cole DrAn d e r s on St V a lley V ie w D rFm 2 1 54Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 65 PROJECT: MISC BIKE TRAILS - BIKE LOOP PROJECT #: ST9803 FUND: 139 - Streets CIP Fund PROJECT BUDGET: $169,000 PROJECT MANAGER: Danielle Charbonnet FUNDING SOURCES: 98 GOB PROJECT CLIENT: Public Works - Mark Smith This project serves to hold funds for bike trail projects. Original budget was $180,000. As new bike trail projects are created, funds will be allocated to those projects and this project balance will be reduced. Projects on which these funds have been used include: ST0203 - Anderson Street Sidewalks NOTE : These funds will be spent on the completion of the Bike Loop in conjunction with project ST0530, 2005 Bike Loop Project Ph II -- Bike Loop Completion. FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $34,610 $0 $0 $34,610 2008-09 $0 2009-10 134,390 $134,390 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2014-15 $0 TOTAL $0 $34,610 $134,390 $0 $169,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 Fm 2154Harvey RdWilliam D. Fitch PkwyTexas Ave SWe ll b o r n R d Fm 158 BEE CREEK PARK & ARBORETUMBEE CREEK PARK & ARBORETUM CY MILLER PARKCY MILLER PARK T e x a s Av e SKrenek Tap RdWilliam King Cole DrAnde r s o n St V a lle y V ie w D r66 PROJECT: PROJECT #: ST0521 FUND: 139 - Streets CIP Fund PROJECT BUDGET: $1,033,624 PROJECT MANAGER: FUNDING SOURCES: 2003 GOB PROJECT CLIENT: Public Works - Troy Rother FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $47,106 $6,244 $650 $8,027 $62,026 2008-09 22,500 700,000 28,000 37,000 $787,500 2009-10 124,098 20,000 40,000 $184,098 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Hike & Bike Trails - Longmire Imp These funds will be spent on the 2005 Bike Loop Phase I Project-- Longmire Improvements, which includes intersection improvements for bicyclists and pedestrians at FM 2818 and Longmire, bike lanes, and a bridge over Bee Creek. The remaining funds will be used to complete the CS Bike Loop project, which will be Phase II to this project. NOTE: $75,000 transferred in FY2004-05 to Brison Park Bike & Ped Path ST0524. $2625 was approved for as a match for a grant for a Safe Routes to School course at the 2-24-05 Council meeting. $56,624 transferred from ST0524 in FY07 - project completed under budget. PROJECT DESCRIPTION/STATUS Danielle Charbonnet 2014-15 $0 TOTAL $0 $69,606 $830,342 $48,650 $85,027 $1,033,624 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 Fm 2 1 54Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 BEE CREEK PARK & ARBORETUMBEE CREEK PARK & ARBORETUM CY MILLER PARKCY MILLER PARK T e x a s Av e SKrenek Tap RdWilliam King Cole DrAnder son St V a lle y V ie w D r67 PROJECT:COCS Beautification Improvements FUND(S):139 - Streets CIP Fund PROJECT NUMBERS & BUDGET: Streets ST0515 $324,000 Electric: TBD $50,000 Total Project Budget: $374,000 PROJECT MANAGER:Danielle Charbonnet FUNDING PROJECT SOURCES:Streets - CO's CLIENT:Public Works Electric Fund This project is to design and construct improvements at the University Drive/Highway 6 interchange. The improvements will include hardscape structures, landscaping and utility work to provide irrigation and lighting to the quadrants at this interchange. The first phase of the project, for which this budget has been established, includes site preparation, trees and shrubs, irrigation, and water bores to provide irrigation to each quadrant. Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 $0 $74,450 $0 $0 2009-10 $0 $0 $299,550 $0 $0 2010-11 $0 $0 $0 $0 $0 PROJECT DESCRIPTION/STATUS 299,550 - -$ 74,450 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2011-12 $0 $0 $0 $0 $0 2012-13 $0 $0 $0 $0 $0 2013-14 $0 $0 $0 $0 $0 2014-15 $0 $0 $0 $0 $0 PROJECT TOTAL $374,000$0 $0 $374,000 $0 $0 - - - - Harvey RdTexas AveUniver s ity D r E University DrF r onta g e 6 Rd WMunson AvePu r y ear D rHensel D rAutumn Cir Be r k e l e y S t Walt o n D r N e w M a in D rAlleyFor est Fm 2154Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 68 General Government Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 74,450 $74,450 2009-10 249,550 $249,550 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Streets Total $0 $0 $324,000 $0 $324,000 Electric Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 50,000 $50,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Water Total $0 $0 $50,000 $0 $50,000 PROJECT TOTAL $0 $0 $374,000 $0 $0 $374,000 First Fiscal Year Annually Total PROJECT: COCS Beautification Improvemen PROJECT CALENDAR OF EXPENDITURES BY FUND OPERATING COSTS Personnel $0 Supplies $0 Service 12,500 $12,500 Capital $0 TOTAL $0 $12,500 $12,500 69 PROJECT: Sidewalk Improvements (2003 GOB) PROJECT #: ST0517 FUND: 139 - Streets CIP Fund PROJECT BUDGET: $14,112 PROJECT MANAGER:Charles McLemore FUNDING SOURCES: 2003 GO Bonds - $500,000 PROJECT CLIENT: Public Works Funds provided for sidewalk improvement projects throughout the City. Plan to build sidewalks along thoroughfares and collectors and to retrofit older neighborhoods. Original Budget = $500,000; $4,078 transferred back to ST0517 from ST0609 - $86,400 transferred to ST0529 FY05 balance of proj - FY07 $36,000 transferred to ST0609 FY06 $28,580 transferred to ST0702 - FY08 $50,036 transferred to ST0516 FY06 $75,700 transferred to ST0803 - FY08 $11,349 transferred to WP9905 FY06 $44,623 transferred to ST0805 - FY08 $50,000 transferred to ST0516 in FY07 $73,005 transferred back to ST0517 from ST0803 - FY08 $2,058 transferred to ST0529 - FY07 $35,377 transferred to ST0805 - FY08 $3,700 transferred to ST0529 FY07 & FY09 $30,000 transferred to ST0813 - FY08 $2,720 transferred to ST072 FY07 $42,739 transferred from ST0805 (balance of project) - FY08 $149,167 transferred to ST0910 - FY09 FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $512 $13,600 $0 $14,112 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $512 $13,600 $0 $0 $14,112 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 Fm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 70 PROJECT: Lincoln Sidewalk Improvements PROJECT #: ST0910 FUND: 139 - Streets Capital Projects Fund PROJECT BUDGET: $149,167 PROJECT FUNDING MANAGER: Gary Balmain SOURCES: ST0517 - 03 GOB PROJECT CLIENT: Public Works This project is for the acquisition of right-of-way and the construction of sidewalks on the north side of Lincoln Avenue extending from Avenue A to University Drive. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 149,167 $149,167 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $149,167 $0 $149,167 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually Lincoln AveFrancis DrUniversity Dr E Texas AveDominik DrMunson AveP u ry e a r D rMil n er DrFront StS p r i n g L oop Cooner StPolo RdCarol StKyle AveAsh StRampChimney Hill DrFor est D r Fm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 71 PROJECT: Sidewalk Improvements (2008 GOB) PROJECT #: ST1028 FUND: 139 - Streets CIP Fund PROJECT BUDGET: $300,000 PROJECT MANAGER:Charles McLemore FUNDING SOURCES: 2008 GO Bonds - $300,000 PROJECT CLIENT: Public Works Funds provided for sidewalk improvement projects throughout the City. Plan to build sidewalks along thoroughfares and collectors and to retrofit older neighborhoods. $100,000 per year FY 10 thru 12 Original Budget = $300,000 FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 $0 2009-10 98,000 $2,000 $100,000 2010-11 98,000 $2,000 $100,000 2011-12 98,000 $2,000 $100,000 2012-13 $0 $0 2013-14 $0 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $294,000 $0 $6,000 $300,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 Fm 2 15 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 72 PROJECT: Hike and Bike Trail Completion PROJECT #: ST0904 FUND: 139 - Streets Capital Projects Fund PROJECT BUDGET: $1,000,000 PROJECT MANAGER: Danielle Charbonnet FUNDING SOURCES: 2008 General Obligation Bonds PROJECT CLIENT: P&DS - Venessa Garza FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 $0 2008-09 $100,000 $5,000 $20,000 $125,000 2009-10 $100,000 $50,000 $300,000 $25,000 $25,000 $500,000 2010-11 $319,000 $10,000 $46,000 $375,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR This project provides funds for the implementation of projects identified by the Hike & Bike Task Force and adopted by Council on November 23, 2004. Funds will be used to construct the Bee Creek Trail North West project from Welsh to Texas along the northwest side of FM 2818. This was ranked as the #2 project by the Bike & Hike Task Force (presented at the November 9, 2004 council meeting). 2014-15 $0 TOTAL $100,000 $150,000 $619,000 $40,000 $91,000 $1,000,000 Total Personnel $0 Supplies $0 Service $1,000 Capital $0 TOTAL $1,000 1000 $1,000 NET INCREASE IN OPERATING COSTS First Fiscal Year Annually Fm 2 1 54Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 Welsh Av e Texas Ave SGl ade StHarve y Mi t c h e ll P k w y SHolleman DrD e a c o n D rLongmire D r A nderson St Alley La wye r St Dexter Dr S H a in e s D rLee AveChri s tin e L n T r e e h o u s e T r lKrenek Tap RdNavarro DrMil e DrMorgans LnNevada StT h o m a s S t73 PROJECT: Lick Creek Hike and Bike Trail PROJECT #: TBD FUND: 139 - Streets Capital Projects Fund PROJECT BUDGET: $4,410,000 PROJECT MANAGER: Danielle Charbonnet FUNDING SOURCES: 2008 General Obligation Bonds PROJECT CLIENT: P&DS - Venessa Garza FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 125,000 100,000 $225,000 2011-12 125,000 350,000 20,000 30,000 $525,000 2012-13 1,940,000 40,000 40,000 $2,020,000 2013-14 1,595,000 15,000 30,000 $1,640,000 2014-15 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR The Lick Creek Hike and Bike Trail project will construct about 3 miles of Hike and Bike Trails along Lick Creek between Westfield Park and Lick Creek Park connecting residential neighborhoods and CSISD property. This project is on the City's Bikeway Master Plan and was ranked as a High priority project by the Bike and Hike Task Force. 2014-15 $0 TOTAL $250,000 $450,000 $3,535,000 $75,000 $100,000 $4,410,000 Total Personnel $0 Supplies $0 Service $3,000 Capital $0 TOTAL $3,000 3,000 $3,000 NET INCREASE IN OPERATING COSTS First Fiscal Year Annually S H 6 S Fr o n t age 6 Rd E Fronta ge 6 R d WBarron RdFm 2154Rock Prairie Rd L ongmir e D r Graham RdVictoria AveLakeway Dr S H 40 / Wi l l i a m D F itc h P k w y Olden LnP o n d e ro sa D rS t A n dre w s D r Cas t l e ga t e Dr Carll LnRitchey RdAster DrDover DrFm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 74 PROJECT: University Drive Pedestrian PROJECT #: TBD Improvements Phases 2-5 FUND: 139 - Streets Capital Projects Fund PROJECT BUDGET: $7,055,000 PROJECT MANAGER: Danielle Charbonnet FUNDING SOURCES: 2008 General Obligation Bonds PROJECT CLIENT: Public Works - Troy Rother FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 815,000 $815,000 2013-14 3,075,000 $3,075,000 2014-15 3,165,000 $3,165,000 TOTAL $0 $815,000 $6,240,000 $0 $7,055,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR This project consists of implementing the remaining phases (2 through 5) of the Pedestrian Improvements on University Drive. The project developed a plan to improve pedestrian travel in the Northgate area of College Station, especially to facilitate pedestrian movement across and along University Drive between Boyett Street and South College Avenue. This project was ranked as a High priority project by City staff. NET INCREASE IN OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL TBD First Fiscal Year Annually NET INCREASE IN OPERATING COSTS $0 TBD University DrRoss S tChurch AveFirst St Nagle StBoyett StCherry StTauber StW ellb orn R d N Stasney StBizz ell StP olo RdSpence StIreland St Jone s S tAsbury StSpruce StAgrono m y Rd C o ke St L a m a r S tR a m p Bizzell St La m ar S t Fm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 75 Home of Texas A&M University ® 76 GGEENNEERRAALL GGOOVVEERRNNMMEENNTT-- PPAARRKKSS AANNDD RREECCRREEAATTIIOONN CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000099--22001100 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22001144--22001155 77 1 2 3 4 5 6 7 8 9 10 11 1213 14 1516 17 18 19 20 21 22 23 24 25 26 27 28 29 Grimes County Burleson County T e x a s A v e State H w y 6 U n iversity D rF m 2 1 5 4 W illiam D FitchLegend Neighborhood Park Zones TAMU Property CS City Limits Parkland Dedication Zones N Adopted by City Council Oct. 23, 2008 78 Home of Texas A&M University ® 79 GENERAL GOVERNMENT PARKS AND RECREATION PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT REVISED APPROVED PROJECT BUDGET APPROPRIATIONS FY 08-09 FY 09-10 NUMBER AMOUNT THROUGH FY08 APPROPRIATIONS APPROPRIATIONS BEGINNING FUND BALANCE:$1,815,256 $870,686 ADDITIONAL RESOURCES: GENERAL OBLIGATION BONDS (2003 GOB)- - GENERAL OBLIGATION BONDS (2008 GOB)2,225,000 1,586,000 CERTIFICATES OF OBLIGATIONS - - INTERGOVERNMENTAL TRANSFERS - - INTRAGOVERNMENTAL TRANSFERS 86,896 - INVESTMENT EARNINGS 28,000 5,000 OTHER 86,700 110,800 SUBTOTAL ADDITIONAL RESOURCES $2,426,596 $1,701,800 TOTAL RESOURCES AVAILABLE $4,241,852 $2,572,486 PARKS AND RECREATION PROJECTS FIELD REDEVELOPMENT PK0300 ANNUAL 8,700 26,800 140,840 # VETERANS PARK PHASE II PK0501 6,922,000 6,922,000 - - ADAMSON POOL BATH HOUSE REPLACEMENT PK0701 1,332,830 1,332,830 - - 1 CREEK VIEW NEIGHBORHOOD PARK PK0906 515,000 - 515,000 - 1 NEIGHBORHOOD PARK IMPROVEMENTS PK0910 284,000 - - 270,000 1 PEBBLE CREEK BBALL PAVILION PK0914 246,423 - 246,423 - 1 EMERALD FOREST PARK IMPROVEMENTS PK0713 47,000 - - - 1 NEIGHBORHOOD PK IMP - FENCING PK0917 30,000 - 30,000 - 1 ANDERSON PARK WALKING LOOP PK1002 59,000 - - - 1 BROTHERS POND PARK RUNNING SURFACE PK1003 160,000 - - - 1 MERRY OAKS PARK AREA LIGHTS TBD 15,000 - - - 1 LEMONTREE PARK SWING SET TBD 15,000 - - - 1 SKATE PARK PK0911 920,000 - 920,000 - 1 NEIGHBORHOOD PARKS REVOLVING FUND PK0912 1,000,000 - 500,000 500,000 1 BEACHY CENTRAL PARK IMPROVEMENTS PK1001 930,000 - - 96,000 1 LICK CREEK PK IRON BRIDGE TRAIL COMPL TBD 100,000 - - - 1 LINCOLN CENTER ADDITION TBD 4,285,000 - - - 1 EAST DISTRICT MAINTENANCE SHOP REP TBD 1,645,000 - - - 1 LICK CREEK NATURE CENTER TBD 2,495,000 - - - CLOSED PROJECTS 5,227 198,054 187,177 CAPITAL PROJECTS SUBTOTAL $8,268,757 $2,436,277 $1,194,017 MISCELLANEOUS - - DEBT ISSUANCE COST - 10,000 GENERAL & ADMIN. CHARGES 74,211 65,665 TOTAL EXPENDITURES $2,510,488 $1,269,682 ENDING FUND BALANCE:$1,731,364 $1,302,804 * - FUNDED THROUGH COMMUNITY DEVELOPMENT BLOCK GRANT # - Indicates projects funded through 2003 G.O. Bond Authorization 1 - Indicates projects funded through 2008 G.O. Bond Authorization BUDGET APPROPRIATIONS 80 GENERAL GOVERNMENT PARKS AND RECREATION PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED THROUGH FY07 FY 07-08 FY 08-09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 $2,344,047 1,815,256 870,686 210,981 187,706 167,127 $145,577 $7,037 40,000 - - - - - - - - 1,535,000 1,586,000 1,539,000 3,990,000 383,000 3,757,000 1,440,530 - - - - - - - - - - - - - - - 579,603 96,973 - - - - - - 65,893 31,000 5,000 3,000 4,000 4,000 10,000 10,000 77,415 94,000 110,800 113,000 115,300 117,600 120,000 122,400 $2,203,441 $1,756,973 $1,701,800 $1,655,000 $4,109,300 $504,600 $3,887,000 $132,400 $4,547,488 $3,572,229 $2,572,486 $1,865,981 $4,297,006 $671,727 $4,032,577 $139,437 171,659 77,936 1,300 140,840 99,275 94,879 129,150 233,540 88,258 6,205,333 663,615 53,052 - - - - - - 74,200 9,429 1,249,201 - - - - - - - - 51,000 464,000 - - - - - - - - 4,000 280,000 - - - - - - 246,423 - - - - - - - - - 47,000 - - - - - - - 30,000 - - - - - - - - - 59,000 - - - - - - - - 160,000 - - - - - 15,000 - - - - 15,000 - - 105,000 815,000 - - - - - - - 500,000 500,000 - - - - - - - - 96,000 834,000 - - - - - - - - - 100,000 - - - - - - - 395,000 3,890,000 - - - - - - - - - 152,000 1,493,000 - - - - - - - 231,000 2,264,000 - - 1,952,286 381,356 - - - - - - $6,451,192 $2,703,266 $2,617,332 $2,285,840 $1,638,275 $4,084,879 $512,150 $3,990,540 $88,258 1,700 - - - - - - - 5,846 10,000 10,000 10,000 25,000 4,000 25,000 - 21,420 74,211 65,665 30,000 20,000 10,000 10,000 10,000 $2,732,232 $2,701,543 $2,361,505 $1,678,275 $4,129,879 $526,150 $4,025,540 $98,258 $1,815,256 $870,686 $210,981 $187,706 $167,127 $145,577 $7,037 $41,179 PROJECTED EXPENDITURES 81 PROJECT: Field Redevelopment Projects PROJECT #: PK0300 FUND: 138 - Parks CIP PROJECT BUDGET:Annual PROJECT Peter Lamont/Pete Vanacek FUNDING MANAGER: SOURCES: Field Redevelopment Fees PROJECT CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $249,595 $249,595 2008-09 1,300 $1,300 2009-10 140,840 $140,840 2010-11 99,275 $99,275 2011-12 94,879 $94,879 2012-13 129,150 $129,150 2013-14 253,540 $253,540 2014-15 88,258 $88,258 TOTAL $0 $0 $0 $1,056,837 $1,056,837 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR This project will include replacement and repairs to numerous athletic facilities throughout the City. Items include drinking fountains, shade covers, light and base replacement as well as fence and bleacher repairs. Additions to turf maintenance are also included for several fields. FY10 allocations are as follows: Softball Fields $48,525; Athletic Fields $36,495; Baseball Fields $55,820. These funds are collected from user groups and PARD programs specifically for these purposes. Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 82 PROJECT: PROJECT #:PK0501 PROJECT FUND: 138 - Parks CIP Fund BUDGET: PROJECT MANAGER: Pete Vanecek FUNDING SOURCES: PROJECT CLIENT: Parks and Recreation Original budget = $6,925,000 $3,000 transferred to PK0802 - FY08 FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $554,765 $6,295,304 $18,879 $6,868,948 2008-09 53,052 $53,052 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $554,765 $6,295,304 $71,931 $6,922,000 VETERANS PARK & ATHLETIC COMPLEX, PHASE II PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS $6,922,000 2003 General Obligation Bonds PROJECT DESCRIPTION/STATUS This project was for Phase II of Veterans Park & Athletic Complex. The project included parking, utilities, shop addition, three (3) soccer fields, three (3) softball fields, large group pavilion, and a softball concession stand/restroom building. In addition, Veterans Parkway was extended as part of this project. Project design began in January 2005. Construction began in March 2006 and is now complete. Total Personnel $239,101 Supplies $48,200 Service $288,240 Capital $78,900 TOTAL $654,441 $56,731 21,850 $182,370 OPERATING COSTS First Fiscal Year Annually $274,861 26,350 170,860 $379,580 117,380 78,900 83 PROJECT: PROJECT #: PK0701 PROJECT FUND: BUDGET: $1,332,830 PROJECT FUNDING MANAGER: SOURCES: PROJECT CLIENT: Parks and Recreation Original project budget = $990,000 $52,830 transferred from PK0802 - FY09 $40,000 transferred from PK0521 - FY08 $250,000 transferred from PK0802 - FY08 FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $74,200 $9,366 $63 $83,629 2008-09 1,249,201 $1,249,201 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $74,200 $1,258,567 $63 $1,332,830 ADAMSON POOL BATH HOUSE REPLACEMENT Pete Vanecek Certificates of Obligation 138 - Parks CIP Fund PROJECT DESCRIPTION/STATUS Replacement of the bath house at Adamson Lagoon pool due to its poor condition - leaking/rotten roof and structural problems. The bath house was constructed in 1976. The facility needs to be larger to handle current crowds and meet current Americans With Disabilities Act (ADA) Standards. The replacement structure needs to be approximately 5,000 SF. Asbestos abatement will be required in the existing structure. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 First Fiscal Year Annually OPERATING COSTS $0 $0 84 PROJECT: CREEK VIEW NEIGHBORHOOD PARK PROJECT #: PK0906 FUND: PROJECT BUDGET: $515,000 PROJECT FUNDING MANAGER: SOURCES: Bonds PROJECT CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 51,000 $51,000 2009-10 464,000 $464,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $51,000 $464,000 $0 $515,000 2008 General Obligation 138 - Parks CIP Fund Pete Vanecek PROJECT DESCRIPTION/STATUS CSISD has built an elementary school south of Cypress Grove in Park Zone 10. Discussions with CSISD about developing a needed neighborhood park at the site have been positive. This park will serve the school and a portion of Park Zone 10 that is underserved. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $30,000 Supplies $1,340 Service $9,500 Capital $750 TOTAL $41,590 NET INCREASE IN OPERATING COSTS First Fiscal Year Annually $750 $30,000 $0 $41,590 1,340 9,500 Proposed Zone 10 Park 85 PROJECT: PROJECT #: PROJECT FUND: BUDGET: $284,000 PROJECT MANAGER: FUNDING SOURCES: PROJECT Bonds CLIENT: Parks and Recreation Original budget = $900,000 $15,000 to be transferred to Lemontree $246,423 transferred to PK0914 - FY09 Park Swing Set - FY11 $43,577 transferred to PK0913 - FY09 $160,000 to be transferred to Brothers $30,000 to be transferred to PK0713 - FY09 Park Running Surface - FY10 $47,000 to be transferred to PK0713 - FY10 Balance: TBD $59,000 to be transferred to Anderson Park Walking Loop - FY10 $15,000 to be transferred to Merry Oaks Park Area Lights - FY11 FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 4,000 $4,000 2010-11 280,000 $280,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $284 000 $0 $284 000 PK0910 IMPROVEMENTS NEIGHBORHOOD PARK 2008 General Obligation 138 - Parks CIP Fund TBD This project would address Neighborhood Park improvements, bringing older parks up to current standards. PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $284,000 $0 $284,000 Total Personnel $0 Supplies Service Capital $0 TOTAL NET INCREASE IN OPERATING COSTS $0 $0 AnnuallyFirst Fiscal Year Fm 21 54Harvey RdWilliam D. Fitch PkwyT e x a s Av e SWe ll b o r n R d Fm 158 86 PROJECT: PROJECT #: PROJECT FUND: BUDGET: $246,423 PROJECT MANAGER:FUNDING SOURCES: PROJECT Bonds CLIENT: Parks and Recreation The budget for this project was transferred from PK0910 - Neighborhood Park Improvements. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 25,000 221,423 $246,423 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $25,000 $221,423 $0 $246,423 Pebble Creek Basketball Pavilion PK0914 138 - Parks CIP Fund David Wood 2008 General Obligation PROJECT DESCRIPTION/STATUS This project is for the construction of a new, covered basketball court and pavilion in Pebble Creek Park. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR NET INCREASE IN OPERATING COSTS Total Personnel $1,200 Supplies $0 Service $1,200 Capital $0 TOTAL $2,400 First Fiscal Year Annually NET INCREASE IN OPERATING COSTS $1,200 0 1,200 $0 $2,400 William D. Fitch PkwyFron ta g e 6 R d E Ro y a l A d e la d e D r Agate DrLakeway Dr A u g u s t a C i r St Andrews Dr Q u a lit y CirFm 215 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 87 PROJECT: Emerald Forest Park Imp. Combo FUND(S): PROJECT NUMBERS & BUDGET: 138 - Parks CIP Fund Parks CIP: PK0713 $47,000 178 - Zone 8 Parkland Dedication Fund Parkland Ded: PK0713 $63,000 Total Project Budget: $110,000 PROJECT MANAGER:TBD FUNDING PROJECT SOURCES:138 - 2008 General Obligation Bond CLIENT:Parks and Recreation 178 - Zone 8 Parkland Dedication Parks CIP budget to be transferred from PK0910 - Neighborhood Park Improvements - FY10 Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 2008-09 0 0 0 0 2009-10 0 0 110 000 0 $110 000 $0 $0 PROJECT DESCRIPTION/STATUS Improvements to Emerald Forest Park with the replacement of the old playground and concrete walk at a higher elevation in the floodplain. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2009-10 0 0 110,000 0 2010-11 0 0 0 0 2011-12 0 0 0 0 2012-13 0 0 0 0 2013-14 0 0 0 0 2014-15 0 0 0 0 $110,000PROJECT TOTAL $0 $0 $110,000 $0 $110,000 $0 $0 $0 $0 $0 88 Parks CIP FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 $0 2008-09 $0 2009-10 47,000 $47,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Parks Total $0 $0 $47,000 $0 $47,000 Parkland Dedication Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 63,000 $63,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Parkland Total $0 $0 $63,000 $0 $63,000 First Fiscal Year Annually Total $0 $110,000 OPERATING COSTS PROJECT: Emerald Forest Park Imp. Combo PROJECT CALENDAR OF EXPENDITURES BY FUND PROJECT TOTAL $0 $0 $110,000 First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 89 PROJECT: PROJECT #: PROJECT FUND: BUDGET: $30,000 PROJECT MANAGER:FUNDING SOURCES: PROJECT Bonds CLIENT: Parks and Recreation The budget for this project was transferred from PK0910 - Neighborhood Park Improvements. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 30,000 $30,000 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $30,000 $0 $30,000 Neighborhood Park - Fencing PK0917 138 - Parks CIP Fund Pete Vanecek 2008 General Obligation PROJECT DESCRIPTION/STATUS This project is for the construction of fencing at joint park/school playgrounds that are located at Pebble Creek Elementary and Rock Prairie Elementary. This project will be completed as part of an Interlocal Agreement between the City of College Station and College Station ISD. Each entity will pay 50% of the cost. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR NET INCREASE IN OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 First Fiscal Year Annually NET INCREASE IN OPERATING COSTS 0 0 $0 $0 Fm 2 15 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 Rock Prairie Elementary Pebble Creek Elementary S H 6 SFm 2154Barron R dRock Prairie Rd L ongmir e D r Deac o n D rGraham RdOlden L nTodd T rlAl ex a ndria Ave Eagle AveW o o d c re e k DrCarll Ln90 PROJECT: Anderson Park Walking Loop PROJECT #: PK1002 FUND: PROJECT BUDGET: $59,000 PROJECT FUNDING MANAGER: David Wood SOURCES: PROJECT CSPARD CLIENT: This project is for the installation of a walking/jogging loop around Anderson Park. The budget for this project was transferred from PK0910 - Neighborhood Park Improvements. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 59,000 $59,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $59,000 $0 $59,000 Total Personnel $0 Supplies $0 2008 GOB - ST0910 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually 138 - Parks CIP Fund Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 91 PROJECT: PROJECT # PROJECT FUND: BUDGET: $160,000 PROJECT MANAGER: FUNDING SOURCES: PROJECT CLEINT: CSPARD The budget for this project was transferred from PK0910 - Neighborhood Park Improvements. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 160,000 $160,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $160,000 $0 $160,000 BROTHERS POND PARK, .3 MILE PK1003 MILE RUNNING SURFACE 138 - Parks CIP Fund DAVID WOOD 2008 GOB - ST0910 PROJECT DESCRIPTION/STATUS This would provide a .3-mile running surface on existing concrete walks and some of the gravel trails at Brothers Pond Park. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 92 PROJECT: MERRY OAKS PARK AREA LIGHTS PROJECT #: TBD FUND: PROJECT BUDGET: $15,000 PROJECT FUNDING MANAGER: David Wood SOURCES: PROJECT CSPARD CLIENT: This project is for the installation of additional area lights in Merry Oaks Park. The budget for this project will be transferred from PK0910 - Neighborhood Park Improvements. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 15,000 $15,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $15,000 $0 $15,000 138 - Parks CIP Fund 2008 GOB - ST0910 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $0 Supplies $250 Service $1,500 Capital $0 TOTAL $1,750 OPERATING COSTS 250 First Fiscal Year Annually $0 1,500 $1,750 93 PROJECT: LEMONTREE PARK SWING SET PROJECT #: TBD FUND: PROJECT BUDGET: $15,000 PROJECT FUNDING MANAGER: David Wood SOURCES: PROJECT CSPARD CLIENT: This project is for the installation of a swing set in Lemontree Park. The budget for this project will be transferred from PK0910 - Neighborhood Park Improvements. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 15,000 $15,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $15,000 $0 $15,000 Total Personnel $0 Supplies $0 2008 GOB - ST0910 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually 138 - Parks CIP Fund Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 94 PROJECT: PROJECT #: PROJECT FUND: BUDGET: $920,000 PROJECT MANAGER:FUNDING SOURCES: PROJECT Bonds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 105,000 $105,000 2009-10 815,000 $815,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $105,000 $815,000 $0 $920,000 PROJECT DESCRIPTION/STATUS This project is for the construction of a skate park in College Station. This would include fencing, lights, signage, etc. The Skate Park will be located at the Southwood Athletic Complex. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR PK0911 NET INCREASE IN OPERATING COSTS SKATE PARK 2008 General Obligation 138 - Parks CIP Fund Ed McDonald Total Personnel $16,800 Supplies $1,200 Service $2,400 Capital $2,000 TOTAL $22,400 2,400 1,200 Annually $16,800 First Fiscal Year $2,000 $20,400 2,000 NET INCREASE IN OPERATING COSTS Fm 2154R o c k P ra irie R d Fr ont a g e 6 R d ENavarro DrAlleyPi er r e Pl Eagle AveMortier DrHartford DrHaley P lNor mand D r Gail PlS c h affer R dSophia LnKernstown LnCarmel PlB ridle C t P in o n D rFm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWe ll b o r n R d Fm 158 95 PROJECT: PROJECT #: PROJECT FUND: BUDGET: $1,000,000 PROJECT MANAGER: FUNDING SOURCES: PROJECT Bonds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 500,000 $500,000 2009-10 500,000 $500,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $1,000,000 $0 $0 $0 $1,000,000 Total PK0912 FUND NET INCREASE IN OPERATING COSTS NEIGHBORHOOD PARKS REVOLVING 2008 General Obligation 138 - Parks CIP Fund Pete Vanecek PROJECT DESCRIPTION/STATUS This fund will be used to purchase neighborhood parks in advance of development. As the land develops, the fund will be reimbursed through park land dedication. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR AnnuallyFirst Fiscal Year Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 AnnuallyFirst Fiscal Year Fm 21 54Harvey RdWilliam D. Fitch PkwyT e x a s Av e SWe ll b o r n R d Fm 158 96 PROJECT: PROJECT #: PROJECT FUND: BUDGET: $930,000 PROJECT MANAGER: FUNDING SOURCES: PROJECT Bonds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 96,000 $96,000 2010-11 834,000 $834,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $96,000 $834,000 $0 $930,000 PK1001 IMPROVEMENTS NET INCREASE IN OPERATING COSTS 138 - Parks CIP Fund Capital Project Dept./David Wood 2008 General Obligation BEACHY CENTRAL PARK PROJECT DESCRIPTION/STATUS This project is for the demolition and construction of a new baseball/softball concession complex and restroom building at the softball fields in Stephen C. Beachy Central Park. The new building will include restrooms, concession area, storage and a meeting room. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 NET INCREASE IN OPERATING COSTS $0 $0 AnnuallyFirst Fiscal Year 97 PROJECT: PROJECT #: PROJECT FUND: BUDGET: $100,000 PROJECT MANAGER:FUNDING SOURCES: PROJECT Bonds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 10,000 90,000 $100,000 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $10,000 $90,000 $0 $100,000 TBD TRAIL COMPLETION NET INCREASE IN OPERATING COSTS LICK CREEK PARK IRON BRIDGE 2008 General Obligation 138 - Parks CIP Fund David Wood PROJECT DESCRIPTION/STATUS This project includes the installation of an improved surface along Iron Bridge Trail in Lick Creek Park. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $1,200 Supplies $1,000 Service Capital TOTAL $2,200 NET INCREASE IN OPERATING COSTS $2,200 1,000 Annually $1,200 First Fiscal Year 98 PROJECT: LINCOLN CENTER ADDITION PROJECT #: TBD FUND: PROJECT BUDGET: $4,285,000 PROJECT MANAGER: FUNDING SOURCES: PROJECT Bonds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 395,000 $395,000 2011-12 3,890,000 $3,890,000 2012-13 0 $0 2013-14 $0 2014-15 $0 TOTAL $0 $395,000 $3,890,000 $0 $4,285,000 Ttl 2008 General Obligation 138 - Parks CIP Fund Capital Project Dept./Pete Vanecek Fi t Fi l Y All PROJECT DESCRIPTION/STATUS NET INCREASE IN OPERATING COSTS Completion of the approved W.A. Tarrow Park master plan includes additional parking (200 spaces), an 8,000 to 10,000 square foot addition to Lincoln Center, a small pavilion, and a backstop. Also, the existing buildings that housed the maintenance crew will be converted to other uses. These buildings were originally part of the former Lincoln High School. Also, purchase of one remaining property is required. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $39,000 Supplies $20,000 Service $65,800 Capital $0 TOTAL $124,800$0 20,000 65,800 $124,800 First Fiscal Year Annually 39,000 99 PROJECT: PROJECT #: PROJECT FUND: BUDGET: $1,645,000 PROJECT MANAGER: FUNDING SOURCES: PROJECT Bonds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 152,000 $152,000 2013-14 1,493,000 $1,493,000 2014-15 $0 TOTAL $0 $152,000 $1,493,000 $0 $1,645,000 PROJECT DESCRIPTION/STATUS This project would move the current Stephen C. Beachy Central Park East District Maintenance Shop to an alternate location to improve use of the park. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TBD REPLACEMENT NET INCREASE IN OPERATING COSTS 138 - Parks CIP Fund Capital Project Dept./Pete Vanecek 2008 General Obligation EAST DISTRICT MAINTENANCE SHOP Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 AnnuallyFirst Fiscal Year $0 $0 100 PROJECT: PROJECT #: PROJECT FUND: BUDGET: $2,495,000 PROJECT MANAGER:FUNDING SOURCES: PROJECT Bonds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 231,000 $231,000 2013-14 2,264,000 $2,264,000 2014-15 $0 TOTAL $0 $231,000 $2,264,000 $0 $2,495,000 TBD Lick Creek Nature Center 2008 General Obligation 138 - Parks CIP Fund Capital Project Dept./David Wood PROJECT DESCRIPTION/STATUS The project proposes an Environmental Education Center to be located in Lick Creek Park. The facility would include a building that would include meeting/classroom space, interpretive exhibit space, and office space. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $200,000 Supplies $50,000 Service $50,000 Capital $0 TOTAL 0 $300,000 NET INCREASE IN OPERATING COSTS $0 0 $300,000 50,000 50,000 Annually $200,000 First Fiscal Year Fm 2 1 54Harvey RdWilliam D. Fitch PkwyTexas Ave SWe ll b o r n R d Fm 158 William D. Fitch PkwyS H 4 0 / W i l l i a m D F itc h P k w yFront a g e 6 Rd E Olden L n O a k s D r SBradley RdR o y a l A d e la d e D rA lle yAlley 101 ########## FY09 FY09 FY10 FY10 % Change in FY08 Revised Year-End Approved Approved Budget from Actual Budget Estimate Base Budget Budget FY09 to FY10 BEGINNING BALANCE 1,630,174$ 1,586,438$ 1,586,438$ 2,500,412$ 2,500,412$ REVENUES Ad Valorem Taxes COCS 246,893$ 254,000$ 254,600$ 304,827$ 304,827$ 20.01% Ad Valorem Taxes CSISD 478,707 495,000 494,349 600,997 600,997 21.41% Ad Valorem Taxes Brazos County 226,247 233,000 231,025 276,599 276,599 18.71% Investment Earnings 50,393 10,000 35,000 20,000 20,000 100.00% Total Revenues 1,002,239$ 992,000$ 1,014,974$ 1,202,423$ 1,202,423$ 21.21% TOTAL FUNDS AVAILABLE 2,632,413$ 2,578,438$ 2,601,412$ 3,702,836$ 3,702,836$ 43.61% EXPENDITURES & TRANSFERS Additional Capital Projects WPC Festival Site/Water Feature 3,500 1,196,115 100,000 3,400,000 3,400,000 184.25% Debt Service 1,042,475 - - - - N/A Other - - 1,000 - - N/A Total Expenditures & Transfers 1,045,975$ 1,196,115$ 101,000$ 3,400,000$ 3,400,000$ 184.25% Increase (Decrease) in Fund Balance (43,736)$ (204,115)$ 913,974$ (2,197,577)$ (2,197,577)$ 976.64% ENDING FUND BALANCE 1,586,438$ 1,382,323$ 2,500,412$ 302,836$ 302,836$ City of College Station Wolf Pen Creek TIF Fund Fund Summary Ad Valorem  Taxes CSISD 50% Ad Valorem  Taxes Brazos  County 23% Wolf Pen Creek TIF Fund ‐Sources Wolf Pen Creek TIF Fund ‐Uses The Wolf Pen Creek (WPC) TIF Fund accounts for ad valorem tax and other revenues that are accrued to the WPC TIF District. The fund also accounts for expenditures on projects that take place in the district. The TIF receives ad valorem taxes from the City, School District and County on the incremental increase in assessed valuation (captured value) over the base year (1989). This fund is prepared on the modified accrual basis of accounting. Under this basis, revenues are recognized when they become measurable and available to finance expenditures of the current period. Expenditures are recognized when the related fund liability is incurred with the exception of several items. The full listing of these exceptions can be found in the Financial Policies on page F-1. The ad valorem revenue estimate of $1,182,423 is based on an estimate of the anticipated captured value in the TIF to be generated in FY10. An additional $20,000 in investment earnings is also anticipated. In FY10, expenditures totaling $3,400,000 are projected to be spent on capital improvements in the Wolf Pen Creek area. These improvements include the construction of a festival site and water feature. The FY10 estimated ending fund balance is anticipated to decrease 88% when compared to the FY09 estimated ending fund balance. This is a result of the expenditure of funds on the WPC Festival Site/Water Feature project. The WPC TIF will expire December 31, 2009 and the majority of the remaining TIF funds will be used for this project. Ad Valorem  Taxes COCS 25% Ad Valorem  Taxes CSISD 50% Ad Valorem  Taxes Brazos  County 23% Investment  Earnings 2% Wolf Pen Creek TIF Fund ‐Sources WPC Festival  Site/Water  Feature 100% Wolf Pen Creek TIF Fund ‐Uses 102 PROJECT: PROJECT #: PROJECT FUND: BUDGET: $3,500,000 PROJECT MANAGER: FUNDING SOURCES: PROJECT CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 100,000 $100,000 2009-10 250,000 3,150,000 $3,400,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $350,000 $3,150,000 $0 $3,500,000 Total Personnel $70,000 WOLF PEN CREEK WP0901 FESTIVAL SITE & WATER FEATURE WPC TIF Donald Harmon WPC TIF PROJECT DESCRIPTION/STATUS Development of the Wolf Pen Creek Festival Site &Water Feature that adjoins the amphitheater. The project may include parking, indoor and outdoor pavilions, fencing, plaza, landscaping, etc. This can be done in phases and it will serve as a major attraction for the corridor. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR NET INCREASE IN OPERATING COSTS First Fiscal Year Annually $70,000Personnel $70,000 Supplies $20,000 Service $50,000 Capital $30,000 TOTAL $170,000 $70,000 20,000 50,000 30,000 $0 $170,000 103 Home of Texas A&M University ® 104 GGEENNEERRAALL GGOOVVEERRNNMMEENNTT-- FFAACCIILLIITTYY AANNDD TTEECCHHNNOOLLOOGGYY CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000099--22001100 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22001144--22001155 105 GENERAL GOVERNMENT FACILITIES AND TECHNOLOGY CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT REVISED APPROVED BUDGET APPROPRIATIONS FY08-09 FY09-10 AMOUNT THROUGH FY08 APPROPRIATIONS APPROPRIATIONS BEGINNING FUND BALANCE:12,308,858$ 7,091,268$ ADDITIONAL RESOURCES: GENERAL OBLIGATION BONDS (03 GOB)-$ 250,000$ GENERAL OBLIGATION BONDS (08 GOB)6,990,000 4,932,000 CERTIFICATES OF OBLIGATIONS 3,040,000 425,000 INTERGOVERNMENTAL TRANSFERS - - INTRAGOVERNMENTAL TRANSFERS 662,749 - INVESTMENT EARNINGS 172,000 47,000 OTHER - - SUBTOTAL ADDITIONAL RESOURCES 10,864,749$ 5,654,000$ TOTAL RESOURCES AVAILABLE 23,173,607$ 12,745,268$ PUBLIC FACILITIES LIBRARY BOOK DONATIONS GG9901 291,348 291,348 - - MEMORIAL CEMETERY GG9905 9,930,000 9,930,000 - - 1 CITY HALL IMPROVEMENTS GG0408 4,300,000 645,000 - 203,535 NORTHGATE IMPROVEMENTS GG0803 153,008 153,008 - - FIRST STREET FENCING GG0902 37,153 37,153 - NORTHGATE RESTROOMS GG0522 431,000 431,000 - - MUNICIPAL FACILITY IMPROVEMENTS GG0701 2,000,000 2,000,000 - - 2 FIRE STATION #6 GG0903 6,990,000 - 6,990,000 - 2 LIBRARY EXPANSION GG1010 8,385,000 - - 932,000 * CLOSED PROJECTS - FACILITY PROJECTS SUBTOTAL 13,487,509$ 6,990,000$ 1,135,535$ TECHNOLOGY PROJECTS MDT SYSTEM REPLACEMENT CO0701 100,000 100,000 - - i5 ENHANCEMENT TBD 250,000 - - - UPS REPLACEMENT CO0603 156,833 51,120 22,749 - RADIO SYSTEM REPLACEMENT CO0601 4,885,000 4,885,000 - - WIRELESS INFRASTRUCTURE CO0704 200,000 200,000 - - SERVER CONSOLIDATION CO0901 150,000 - 150,000 - FIBER OPTIC INFRASTRUCTURE CO0902 1,000,000 - 149,737 189,263 CAD HARDWARE OPERATING SYS UPGRADE CO1001 55,000 - - 55,000 ** MISC INFORMATION TECHNOLOGY PROJECTS CO0801 257 257 - - CLOSED PROJECTS 71,300 - IT PROJECTS SUBTOTAL 5,236,377$ 393,786$ 244,263$ CAPITAL PROJECTS SUBTOTAL 18,723,886$ 7,383,786$ 1,379,798$ DEBT ISSUANCE COSTS 30,000$ 27,000$ TRANSFERS - - OTHER 25,000 - GENERAL & ADMIN. CHARGES 96,427 91,147 TOTAL EXPENDITURES 7,535,213$ 1,497,945$ ENDING FUND BALANCE:15,638,394$ 11,247,323$ 1 - Indicates projects funded through 2003 G.O. Bond Authorization 2 - Indicates projects funded through 2008 G.O. Bond Authorization * - Closed projects includes balance of GG0401 - Fire Station #3 Relocation ** - Miscellaneous Information Technology Projects includes balances from closed projects. 106 GENERAL GOVERNMENT FACILITIES AND TECHNOLOGY CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED THROUGH FY07 FY 07-08 FY 08-09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 12,509,488$ 12,308,858$ 7,091,268$ 2,181,455$ 2,778,955$ 965,790$ 926,790$ 922,790$ -$ -$ 250,000$ 3,405,000$ -$ -$ -$ -$ - 750,000 4,932,000 7,540,000 2,153,000 - - - 7,257,310 3,251,000 425,000 470,000 220,000 190,000 - - - 525,000 - - - - - - 91,417 20,825 - 27,380 21,540 36,000 - - 437,755 146,000 47,000 40,000 41,000 22,000 21,000 21,000 2,388 - - - - - - - 7,788,870$ 4,692,825$ 5,654,000$ 11,482,380$ 2,435,540$ 248,000$ 21,000$ 21,000$ 20,298,358$ 17,001,683$ 12,745,268$ 13,663,835$ 5,214,495$ 1,213,790$ 947,790$ 943,790$ 139,898 19,180 20,000 20,000 20,000 20,000 20,000 20,000 12,270 1,939,259 3,505,332 4,485,409 - - - - - - 165,396 23,139 - 660,000 2,080,000 1,371,465 - - - - 8,992 144,016 - - - - - - - - 37,153 - - - - - - - 8,899 422,101 - - - - - - 21,847 52,124 1,926,029 - - - - - - - - 307,800 4,200,000 2,150,000 332,200 - - - - - - 932,000 5,231,500 2,221,500 - - - 3,728,900 1,336,738 197,409 - - - - - 2,266,400$ 7,346,566$ 8,679,246$ 6,009,409$ 9,481,500$ 3,945,165$ 20,000$ 20,000$ 12,270$ - - - - 100,000 - - - - - - - - 250,000 - - - - 25,279 25,986 20,648 - 27,380 21,540 36,000 - - 209 75,173 259,618 3,900,000 650,000 - - - - - - 90,000 110,000 - - - - - - - - 150,000 - - - - - - 118,000 221,000 221,000 220,000 220,000 - - - - 55,000 - - - - - - - 0 257 - - - - 268,185 601,475 - - - - - - 25,488$ 369,344$ 1,089,741$ 4,436,257$ 1,248,380$ 241,540$ 256,000$ -$ -$ 7,715,910$ 9,768,988$ 10,445,666$ 10,729,880$ 4,186,705$ 276,000$ 20,000$ 12,270$ 38,141$ 20,000$ 27,000$ 55,000$ 12,000$ 1,000$ -$ -$ 4,552 - - - - - - - 60,250 25,000 - - - - - - 170,647 96,427 91,147 100,000 50,000 10,000 5,000 2,500 7,989,500$ 9,910,415$ 10,563,813$ 10,884,880$ 4,248,705$ 287,000$ 25,000$ 14,770$ 12,308,858$ 7,091,268$ 2,181,455$ 2,778,955$ 965,790$ 926,790$ 922,790$ 929,020$ 107 PPUUBBLLIICC FFAACCIILLIITTIIEESS 108 PROJECT: LIBRARY BOOK DONATIONS PROJECT #: GG9901 FUND: General Government, CIP PROJECT BUDGET: $291,348 PROJECT MANAGER: David Gerling FUNDING SOURCES: Funds raised by donations PROJECT for library materials CLIENT: Parks and Recreation FISCAL YEAR HARDWARE SOFTWARE CONS/TRAIN OTHER PROJECT TOTAL Prior Years $0 $0 $0 $159,078 $159,078 2008-09 $20,000 $20,000 2009-10 $20,000 $20,000 2010-11 $20,000 $20,000 2011-12 $20,000 $20,000 2012-13 $20,000 $20,000 2013-14 $20,000 $20,000 2014-15 $12,270 $12,270 TOTAL $0 $0 $0 $291 348 $291 348 PROJECT DESCRIPTION/STATUS This money was raised through donations for adding to the collection of books and other items in the Larry J. Ringer Library. Based on history we anticipate spending $20,000 per year until the funds are depleted. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $0 $291,348 $291,348 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 First Fiscal Year Annually OPERATING COSTS $0 $0 Larry J. Ringer Library 109 PROJECT:Memorial Cemetery FUND(S):137 - General Government CIP PROJECT NUMBERS & BUDGET: Gen'l Gov't:GG9905 $9,930,000 Water: WF1048137 $120,000 Total Project Budget: $10,050,000 PROJECT MANAGER:Philip Bargas FUNDING PROJECT SOURCES:Gen'l Gov't - CO's CLIENT:Parks and Recreation W/WW - Long Term Debt/Utility Revenue $275,000 debt issued in 1999 (CO's) $600,000 debt issued in 2005 (CO's) $1,000,000 debt issued in 06 (CO's) $625,000 debt issued in FY07 (CO's) $6,748,000 projected FY08 debt issue (CO's) (includes debt issuance costs) Construction cost includes $200,000 to move overhead electrical lines underground. $640,000 appropriated to budget as part of FY08 budget amendment #3 Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR PROJECT DESCRIPTION/STATUS Development of a new municipal cemetery that will include an area designated for the Aggie Field of Honor. Prior Years $1,489,527 $697,093 $3,351,742 $1,774 $0 2008-09 $0 $200,000 $4,259,865 $50,000 $0 2009-10 $0 $0 $0 $0 $0 2010-11 $0 $0 $0 $0 $0 2011-12 $0 $0 $0 $0 $0 2012-13 $0 $0 $0 $0 $0 2013-14 $0 $0 $0 $0 $0 2014-15 $0 $0 $0 $0 $0 - - - - - $0 - PROJECT TOTAL $10,050,000$1,489,527 $897,093 $7,611,606 $51,774 5,540,135$ 4,509,865 F & B RdR a y mond S totzer PkwyHa r v e y Mit c h ell P k w y STurke y Cr e e k R d Di scovery DrBar bara Bu s h DFm 2 1 54Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 110 General Government Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $1,489,527 $687,802 $3,265,489 $1,774 $5,444,591 2008-09 $200,000 $4,235,409 $50,000 $4,485,409 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Streets Total $1,489,527 $887,802 $7,500,898 $51,774 $9,930,000 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $9,291 $86,253 $0 $95,544 2008-09 $24,456 $24,456 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Water Total $0 $9,291 $110,709 $0 $120,000 PROJECT TOTAL $1,489,527 $897,093 $7,611,606 $51,774 $0 $10,050,000 First Fiscal Year Annually Total OPERATING COSTS PROJECT: Memorial Cemetery PROJECT CALENDAR OF EXPENDITURES BY FUND y Personnel $50,383 $103,300 $153,683 Supplies 5,660 4,660 $10,320 Service 9,947 35,738 $45,685 Capital 85,500 $85,500 TOTAL $151,490 $143,698 $295,188 111 PROJECT: City Hall Improvements PROJECT #: GG0408 FUND: 137 - General Government CIP PROJECT 4,300,000 BUDGET: PROJECT MANAGER: Chuck Gilman FUNDING 2003 General Obligation SOURCES: Bonds PROJECT CLIENT: CMO Phase I of city hall improvements. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $10,737 $114,778 $0 $63,020 $188,535 2008-09 $0 2009-10 600,000 60,000 $660,000 2010-11 2,000,000 80,000 $2,080,000 2011-12 1,300,000 71,465 $1,371,465 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $10,737 $714,778 $3,300,000 $274,485 $4,300,000 Total PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL TBD First Fiscal Year Annually TBD TBD Fm 2 1 54Harvey RdWilliam D. Fitch PkwyTexas Ave SWe l l b o r n R d Fm 158 112 PROJECT: Northgate Improvements PROJECT #: GG0803 FUND: 137 - General Government CIP PROJECT BUDGET: $153,008 PROJECT MANAGER: David Gwin FUNDING SOURCES: 2005 Certificates PROJECT of Obligation CLIENT: Economic Development Construction of improvements in the Northgate area. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $8,992 $8,992 2008-09 $144,016 $144,016 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $0 $153,008 $153,008 Total PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL TBDTBD TBD First Fiscal Year Annually 113 PROJECT: First Street Fencing PROJECT #: GG0905 FUND: 137 - General Government CIP PROJECT BUDGET: $37,153 PROJECT MANAGER: Debbie Eller FUNDING SOURCES: GG0803 - 2005 Certificates PROJECT of Obligation CLIENT: Economic Development This project was for the construction of fencing around the First Street property in Northgate. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $37,153 $37,153 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $0 $37,153 $37,153 Total PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL TBDTBD TBD First Fiscal Year Annually First St Boyett St Church AveW ellborn R d N Louise AveSecond St Patricia StMaple AvePatricia StFm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 114 PROJECT: Northgate Restroom Facilities PROJECT #: GG0522 FUND: 137 - General Government CIP PROJECT BUDGET: $431,000 PROJECT FUNDING MANAGER: Edward McDonald SOURCES: 2005 Certificates of Obligation Project Client: Economic & Community Development (David Gwin) The Northgate restroom project began construction on the spring of 2009 and is now complete. The restrooms are located adjacent to the City's surface parking lot on Church Street. The project involves the construction of a public restroom, expanding the promenade, construction of an improved trash container enclosure, paving over areas once considered for a water feature and completed tree wells on the promenade. Original budget = $300,000 $50,000 transferred from GG0521 - FY08 $81,000 transferred from GG0803 - FY09 FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $8,899 $0 $0 $8,899 2008-09 $14,001 $352,000 $56,100 $422,101 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014 15 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2014-15 $0 TOTAL $0 $22,900 $352,000 $56,100 $431,000 Total Personnel $0 Supplies $0 Service $10,000 Capital $0 TOTAL $10,000$0 $10,000 $10,000 OPERATING COSTS First Fiscal Year Annually University DrW ellb orn R d N Church AveCollege M ain First St Boyett St Tauber StAsbury StStasney StSecond St N e w S tNagl e StSpruce StHo uston S tJ on e s S tPatricia StPatricia StFm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 115 PROJECT: Municipal Facility Improvements PROJECT #: GG0701 FUND: 137 - General Government CIP PROJECT 2,000,000 BUDGET: PROJECT MANAGER: Donald Harmon FUNDING SOURCES: Certificates of Obligation PROJECT CLIENT: Public Works This project is for the completion of the second floor of the Municipal Court building which will be used for City office space The project is being delivered by the alternative method of Construction Manager At Risk (CMAR). Original budget = $1,750,000 $250,000 transferred from GG0801 - FY08 FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $67,856 $250 $5,864 $73,971 2008-09 $195,500 $1,702,066 $28,463 $1,926,029 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $263,356 $1,702,316 $5,864 $28,463 $2,000,000 Total PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Total Personnel $0 Supplies $34,000 Service $30,000 Capital $0 TOTAL $64,000 $15,000 First Fiscal Year Annually $32,000 $17,000 $15,000 $32,000 $17,000 116 PROJECT: Fire Station #6 PROJECT #: GG0903 FUND: 137 - General Government CIP Fund PROJECT BUDGET: $6,990,000 PROJECT MANAGER: Donald Harmon FUNDING SOURCES: 2008 General Obligation Bonds PROJECT CLIENT: Fire Department FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 $207,800 $0 $100,000 $307,800 2009-10 $0 $100,000 $4,000,000 $100,000 $4,200,000 2010-11 $0 $50,000 $2,000,000 $100,000 $2,150,000 2011-12 $0 $20,000 $292,200 $20,000 $332,200 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $377,800 $6,292,200 $320,000 $6,990,000 Total PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR NET INCREASE IN OPERATING COSTS First Fiscal Year Annually This project is for the construction of a new fire station as identified for the 2008 bond election during a facilities planning session in early 2004. The proposed location is currently under review, but the station location will allow the department to provide coverage and improve response time to the University Drive corridor. Operating costs reflect estimated recurring annual cost following full implementation which is projected for FY17. Total Personnel $2,160,000 Supplies $144,000 Service $55,000 Capital $189,606 TOTAL $2,548,606 2,160,000 First Fiscal Year Annually 144,000 55,000 189,606 $2,548,606 Fm 2 1 54Harvey RdWilliam D. Fitch PkwyTexas Ave SWe l l b o r n R d Fm 158 117 PROJECT: PROJECT #: PROJECT FUND: BUDGET: PROJECT MANAGER: FUNDING SOURCES: PROJECT Bonds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $900,000 $32,000 $932,000 2010-11 $151,500 $5,000,000 $80,000 $5,231,500 2011-12 $151,500 $2,000,000 $70,000 $2,221,500 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $1,203,000 $7,000,000 $182,000 $8,385,000 GG1010 NET INCREASE IN OPERATING COSTS 137 - General Government CIP Jeff Haeber 2008 General Obligation LARRY J. RINGER LIBRARY EXPANSION $8,385,000 PROJECT DESCRIPTION/STATUS This project is for the expansion of the Larry J. Ringer College Station Library on Harvey Mitchell Parkway (FM 2818) by 15,256 square feet, with 16,185 square feet of additional parking. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $53,000 Supplies $0 Service $0 Capital $0 TOTAL $0 $138,000 First Fiscal Year NET INCREASE IN OPERATING COSTS $138,000 57,000 28,000 Annually $53,000 Larry J. Ringer Library 118 TTEECCHHNNOOLLOOGGYY PPRROOJJEECCTTSS 119 PROJECT: MDT SYSTEM REPLACEMENT PROJECT #: CO0701 FUND: 137 - GENERAL GOVERNMENT CIP PROJECT BUDGET: $100,000 PROJECT FUNDING MANAGER: Catherine Roberts SOURCES: EQUIPMENT REPLACEMENT FUND PROJECT CLIENT: Fire/PD FISCAL YEAR Hardware Software Cons/Training Other PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 70,000 20,000 5,000 5,000 $100,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $ 0 000 $20 000 $ 000 $ 000 $100 000 upgrade.To a lesser extent, the data system is experiencing the same coverage limitations as the voice system addressed by project CO0601. If the data side requires expansion to a multisite system to support current and projected City growth, costs will likely exceed $100,000. PROJECT DESCRIPTION/STATUS This project replaces the electronic equipment that provides the interface between radio frequency system (800 MHz radio system) and the Internet Protocol system (Computer Aided Dispatch). This equipment is located at the Radio Tower and is anticipated to be upgraded in conjunction with the Radio System Replacement. Current funding is estimated as sufficient to replace existing infrastructure, not enhance or PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $70,000 $20,000 $5,000 $5,000 $100,000 Total Personnel $0 Supplies $0 Service $20,000 Capital $0 TOTAL $20,000 OPERATING COSTS First Fiscal Year Annually $0 $20,000 20,000 120 PROJECT: i5 ENHANCEMENT PROJECT #:TBD FUND: 137 - GENERAL GOVERNMENT CIP PROJECT BUDGET: $250,000 PROJECT MANAGER: ROGER EARWOOD FUNDING PROJECT SOURCES: Future Certificates CLIENT: Information Technology of Obligation ($250,000) The city's midrange computer system consists of two IBM I5e computers and the OS 400 operating system to run several of the City's key operational databases and software applications. Some of these include Utility Customer Service, Finance, Budget, Fleet Management, and Development Services. An upgrade to the hardware is anticipated every three to four years to ensure that the system is performing at the level of efficiency required for its daily use. The project will provide the necessary funding to upgrade the system during the particular year of implementation. The current hardware is now referred to as an IBM i5. The old AS/400 was replaced in January of 2005 with 2 IBM i5s. Additional software was also purchased to enable replication of data from one i5 to the other. This ensures data access on the primary machine 24/7 and provides business continuity and disaster recovery for this system After review, this project was rescheduled for FY 11. FISCAL YEAR HARDWARE SOFTWARE CONS/TRAIN OTHER PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 250,000 $250,000 2011 12 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $250,000 $0 $0 $250,000 Total Personnel $0 Supplies $0 Service $18,000 Capital $0 TOTAL $18,000 *The annual HW maintnance cost is projected to be $18,000 when the next upgrade is implemented in FY11. $0 18,000 $18,000 OPERATING COSTS First Fiscal Year Annually* 121 PROJECT: UPS Replacment PROJECT #: CO0603 FUND: 137 - General Government CIP PROJECT BUDGET: $156,833 PROJECT MANAGER: Catherine Roberts FUNDING PROJECT SOURCES: Equipment Replacement Fund CLIENT: City Wide FISCAL YEAR Hardware Software Cons/Training Other PROJECT TOTAL Prior Years $51,265 $0 $0 $0 $51,265 2008-09 $20,648 $20,648 2009-10 $0 $0 2010-11 $27,380 $27,380 2011-12 $21,540 $21,540 2012-13 $36,000 $36,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Replacement of Uninterruptible Power Supply (UPS) units and associated Battery Cabinets supporting the City's telephone, computer network, and radio systems. Recommended replacement schedule of 9 years for UPS units and every 3 years for associated Battery Cabinets. 2012 13 $36,000 $36,000 2013-14 $0 2014-15 $0 TOTAL $156,833 $0 $0 $0 $156,833 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 122 PROJECT: RADIO SYSTEM REPLACEMENT PROJECT #: CO0601 FUND: 137 - General Government CIP PROJECT BUDGET: $4,885,000 PROJECT MANAGER: Catherine Roberts FUNDING PROJECT SOURCES: Equipment Replacement Fund CLIENT: Information Technology Certificates of Obligation explored the option of participating in a wide area interoperable communications system. The implementation phase of this project cannot begin until the Federally mandated 800 MHz radio rebanding is complete. Original budget = $4,900,000 $15,000 transferred to Area Wide Communications System (CO 0706) - FY 07 FISCAL YEAR HARDWARE SOFTWARE CONS/TRAIN OTHER PROJECT TOTAL Prior Years $69,154 $0 $6,019 $209 $75,382 2008-09 249,618 10,000 $259,618 2009-10 3,000,000 500,000 250,000 150,000 $3,900,000 2010-11 150,000 150,000 250,000 100,000 $650,000 2011-12 $0 2012-13 $0 2013-14 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR The City's 800 MHz radio system was installed in 1996. It was scheduled to begin its replacement in FY07. Project costs are based on replacing the existing radio system with equivalent features. Public Safety Staff have raised the issue of upgrading the current radio system with a more robust, dynamic system which would improve the current, inadequate coverage in south College Station. A RFQ was issued on 9/18/2006 for a consultant to assist in analysis and recommendations for a replacement system. The unilateral replacement of the radio system was deferred while the city 2013-14 $0 2014-15 $0 TOTAL $3,219,154 $650,000 $755,637 $260,209 $4,885,000 Total Personnel $0 Supplies $0 Service $341,352 Capital $0 TOTAL $341,352$130,541 210,811 $210,811 130,541 OPERATING COSTS First Fiscal Year Annually 123 PROJECT: Wireless Infrastructure PROJECT #: CO0704 FUND: 137 - General Government CIP PROJECT $200,000 BUDGET: PROJECT MANAGER: Ben Roper FUNDING Certificates of Obligation SOURCES: PROJECT CLIENT: Information Technology FISCAL YEAR Hardware Software Cons/Training Other PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 50,000 10,000 25,000 5,000 $90,000 2009-10 50,000 5,000 45,000 10,000 $110,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $100,000 $15,000 $70,000 $15,000 $200,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR This project will allow the use of Wireless Fidelity (WiFi), by city employees in selected areas of the city, both internal to buildings and externally in designated "hot zones". A revised wireless plan is was approved by Council in November 2008. This plan included staff and citizen wireless access inside designated city facilities, a pilot video surveillance project in northgate, the creation of hot zones for staff and citizen access in select locations throughout the city. TOTAL $100,000 $15,000 $70,000 $15,000 $200,000 Total Personnel $0 Supplies $5,000 Service $5,000 Capital $10,000 TOTAL $20,000 OPERATING COSTS First Fiscal Year Annually $0 5,000 5,000 10,000 $20,000 124 PROJECT: Server Consolidation PROJECT #: CO0901 FUND: 137 - General Government CIP PROJECT BUDGET: $150,000 PROJECT FUNDING MANAGER: Erik Bodholt SOURCES: Certificates of Obligation FISCAL YEAR Hardware Software Cons/Training Other PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 100,000 30,000 10000 10000 $150,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $100,000 $30,000 $10,000 $10,000 $150,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR This project provides additional hardware to accommodate the increasing demands for additional electronic storage and the software to better manage the data. The hardware upgrades will permit an increase in the current storage allotted each employee. The software will assist in data management by storing only a single copy of each file or document and assist uses to better manage and delete old files. Total Personnel $0 Supplies $0 Service $15,000 Capital $0 TOTAL $15,000$0 0 15,000 0 $15,000 OPERATING COSTS First Fiscal Year Annually 125 PROJECT: Fiber Optic Infrastructure PROJECT #: CO0902 FUND: 137 - General Government CIP PROJECT BUDGET: $1,000,000 PROJECT FUNDING MANAGER: Catherine Roberts SOURCES: Certificates of Obligation FISCAL YEAR Hardware Software Cons/Training Other PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 70,000 45,000 3,000 $118,000 2009-10 131,000 85,000 5,000 $221,000 2010-11 131,000 85,000 5,000 $221,000 2011-12 131,000 85,000 4,000 $220,000 2012-13 131,000 85,000 4,000 $220,000 2013-14 $0 2014-15 $0 TOTAL $594,000 $0 $385,000 $21,000 $1,000,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR This project will support the installation of fiber optic cable to continue expansion of the city's network to new buildings and facilities, and to permit the connection of existing facilities that are not currently on the network. Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 0 0 0 $0 $0 OPERATING COSTS First Fiscal Year Annually 126 PROJECT: CAD HW Oper System Upgrade PROJECT #: CO1001 FUND: 137 - General Government CIP PROJECT $55,000 BUDGET: PROJECT FUNDING MANAGER: Kevin Joyner SOURCES: Certificates of Obligation FISCAL YEAR Hardware Software Cons/Training Other PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 35,000 $8,000 $7,000 $5,000 $55,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $35,000 $8,000 $7,000 $5,000 $55,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR The current CAD operating system was installed in 2003. This project will change the server hardware, and replace the operating system used from AIX (UNIX) to a Windows based system. This change will enable greater support, less expensive hardware, and greater flexibility TOTAL $35,000 $8,000 $7,000 $5,000 $55,000 Total Personnel $0 Supplies $0 Service $15,000 Capital $0 TOTAL $0 * This amount reflects the total annual software maintenance cost paid to Enroute Public Safety. $0 0 15,000* 0 $0 $0 OPERATING COSTS First Fiscal Year Annually 127 PROJECT: Miscellaneous IT Projects PROJECT #: CO0801 FUND: 137 - General Government CIP PROJECT BUDGET: $257 PROJECT FUNDING MANAGER: TBD SOURCES: Certificates of Obligation These funds in this project reflect remaining balances of closed projects for which debt was issued. The balance can be used on other IT projects for which additional funds are needed. $257 transferred from CO0702 - FY09 FISCAL YEAR Hardware Software Cons/Training Other PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 257 $257 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $0 $257 $257 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 0 $0 $0 $0 0 0 OPERATING COSTS First Fiscal Year Annually 128 GGEENNEERRAALL GGOOVVEERRNNMMEENNTT-- DDRRAAIINNAAGGEE CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000099--22001100 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22001144--22001155 129 DRAINAGE UTILITY CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT REVISED APPROVED PROJECT BUDGET APPROPRIATIONS FY08-09 FY09-10 NUMBER AMOUNT THROUGH FY07 APPROPRIATIONS APPROPRIATIONS BEGINNING FUND BALANCE:3,054,197$ 2,155,212$ ADDITIONAL RESOURCES: UTILITY REVENUES 1,758,670$ 1,838,100$ INTEREST ON INVESTMENTS 39,000 14,000 BOND PROCEEDS - - INTERGOVERNMENTAL TRANSFERS - - INTRAGOVERNMENTAL TRANSFERS - - TRANSFERS OUT - - OTHER - - SUBTOTAL ADDITIONAL RESOURCES 1,797,670$ 1,852,100$ TOTAL RESOURCES AVAILABLE 4,851,867$ 4,007,312$ BEE CREEK PH. IV & V. SD0001 1,400,000$ 1,358,000 42,000 - GREENWAYS PROJECTS SD9903 3,640,000$ 3,640,000 - - MINOR DRAINAGE IMPROVEMENTS SD1002 ANNUAL - - 200,000 W. KING COLE CULVERT REPLACEMENT SD0904 265,000$ - 265,000 - COLLEGE PARK/BREEZY HEIGHTS SD0601 443,525$ 443,525 - - STORMWATER MAPPING SD0523 133,000$ 33,000 50,000 17,000 MTIGATION FENCING - ARRINGTON/DECATUR SD0901 100,000$ - 100,000 - CLOSED PROJECTS 7,800 CAPITAL PROJECTS SUBTOTAL 464,800$ 217,000$ OTHER COSTS 7,200 7,200 BEE CREEK MITIGATION MONITORING/REPORTING (SD0902)20,000 36,000 DRAINAGE MAINTENANCE ANNUAL 1,163,069 862,110 DRAINAGE SLA's ANNUAL - - TRANSFERS OUT -- BUDGET APPROPRIATIONS TRANSFERS OUT - - GENERAL & ADMIN. 501,425 542,461 TOTAL EXPENDITURES 2,156,494$ 1,664,771$ ENDING FUND BALANCE: 2,695,373$ 2,342,541$ 130 DRAINAGE UTILITY CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED THROUGH FY07 FY 07-08 FY 08-09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 3,494,526$ 3,054,197$ 2,155,212$ 797,442$ 588,475$ 468,675$ 781,975$ 1,142,275$ 1,254,611$ 1,784,557$ 1,838,100$ 1,893,200$ 1,950,000$ 2,008,500$ 2,068,800$ 2,130,900$ 129,072 39,000 14,000 9,500 10,000 12,000 19,000 19,000 - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - - 7,328 - - - - - - - 1,391,011$ 1,823,557$ 1,852,100$ 1,902,700$ 1,960,000$ 2,020,500$ 2,087,800$ 2,149,900$ 4,885,537$ 4,877,754$ 4,007,312$ 2,700,142$ 2,548,475$ 2,489,175$ 2,869,775$ 3,292,175$ 188,134 8,199 135,000 1,048,200 20,467 - - - - 2,322,851 3,250 50,000 463,899 400,000 400,000 - - - - - - 200,000 200,000 200,000 200,000 200,000 200,000 - - 265,000 - - - - - - 27,798 1,350 414,377 - - - - - - - - 50,000 50,000 33,000 - - - - - - 100,000 - - - - - - - 630,210 93,984 643,009$ 1,108,361$ 1,762,099$ 653,467$ 600,000$ 200,000$ 200,000$ 200,000$ 10,800 7,200 7,200 7,200 7,200 7,200 7,200 7,200 - 20,000 36,000 13,000 8,000 8,000 - - 715,471 1,085,556 862,110 888,000 914,600 942,000 970,300 999,400 - - - - - - - - -------- PROJECTED EXPENDITURES - - - - - - - - 462,060 501,425 542,461 550,000 550,000 550,000 550,000 550,000 1,831,340$ 2,722,542$ 3,209,870$ 2,111,667$ 2,079,800$ 1,707,200$ 1,727,500$ 1,756,600$ 3,054,197$ 2,155,212$ 797,442$ 588,475$ 468,675$ 781,975$ 1,142,275$ 1,535,575$ 131 PROJECT: Bee Creek IV and V FUND(S): PROJECT NUMBERS & BUDGET: 238 - Water Capital Fund Drainage: SD0001 $1,400,000 239 - Wastewater Capital Fund Water: TBD $120,000 912 - Drainage Utility Fund Wastewater: TBD $300,000 Total Project Budget: $1,820,000 PROJECT MANAGER:Danielle Charbonnet FUNDING PROJECT SOURCES:Drainage - Drainage Utility CLIENT:Public Works: Gary Balmain W/WW - Long Term Debt/Utility Revenue Water Services: Ed Savage Credits paid to the Robertson County Mitigation Bank are being proposed in lieu of mitigation on this project. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR PROJECT DESCRIPTION/STATUS Channel improvements to Bee Creek Tributary "A" including bank stabilization and increased flow capacity from Brothers Boulevard past Longmire Drive to Texas Avenue. Water and sewer line relocations are included with this project. Construction Cost Estimate is based on Opinion of Probable Construction Cost developed by the design engineer in 2009. A Letter of Map Revision (LOMR) will be submitted upon construction completion. Miscellaneous expenses in FY11 are for associated submittal fees and public notification. Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 194,651 0 1,683 0 $196,333 2008-09 0 42,000 50,000 5,000 38,000 $135,000 2009-10 0 18,000 1,305,200 70,000 75,000 $1,468,200 2010-11 0 0 0 8,000 12,467 $20,467 2011-12 0 0 0 0 0 $0 2012-13 0 0 0 0 0 $0 2013-14 0 0 0 0 0 $0 2014-15 0 0 0 0 0 $0 $125,467PROJECT TOTAL $0 $254,651 $1,355,200 $84,683 $1,820,000 132 Drainage Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $194,651 $0 $1,683 $196,333 2008-09 42,000 50,000 5,000 38,000 $135,000 2009-10 18,000 930,200 35,000 65,000 $1,048,200 2010-11 8,000 12,467 $20,467 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Drainage Total $0 $254,651 $980,200 $49,683 $115,467 $1,400,000 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 100,000 15,000 5,000 $120,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Water Total $0 $0 $100,000 $15,000 $5,000 $120,000 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 275,000 20,000 5000 $300,000 2010-11 $0 PROJECT: Bee Creek IV and V PROJECT CALENDAR OF EXPENDITURES BY FUND 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Wastewater Total $0 $0 $275,000 $20,000 $5,000 $300,000 First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 $1,355,200 OPERATING COSTS $84,683 $125,467 $1,820,000PROJECT TOTAL $0 $254,651 133 PROJECT: GREENWAYS PROJECTS PROJECT #: SD9903 FUND: 912 - DRAINAGE UTILITY FUND PROJECT BUDGET: $3,640,000 PROJECT FUNDING MANAGER:Venessa Garza SOURCES: General Obligation Bonds PROJECT CLIENT: Planning & Development Services This project serves to hold funds for new greenways projects. Original budget was $3,640,000. $1,194,124 of Greenways funds were spent on the City Center land purchase. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $2,264,907 $55,957 0 $5,237 $2,326,101 2008-09 $50,000 $50,000 2009-10 $463,899 $463,899 2010-11 $400,000 $400,000 2011-12 $400,000 $400,000 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $3,578,806 $55,957 $0 $5,237 $3,640,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $3,578,806 $55,957 $0 $5,237 $3,640,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 134 PROJECT: MINOR DRAINAGE PROJECT #: SD1002 IMPROVEMENTS PROJECT FUND: 912 - DRAINAGE FUND BUDGET:ANNUAL PROJECT FUNDING MANAGER: Gary Balmain SOURCES: DRAINAGE UTILITY FUND PROJECT CLIENT: Public Works Funds budgeted on an annual basis as available for minor drainage improvements throughout the City. FY10 budget = $200,000 FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 200,000 $200,000 2010-11 200,000 $200,000 2011-12 200,000 $200,000 2012-13 200,000 $200,000 2013-14 200,000 $200,000 2014-15 200,000 $200,000 TOTAL $0 $0 $1,200,000 $0 $1,200,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $1,200,000 $0 $1,200,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 135 PROJECT: W. King Cole Culvert Replacement PROJECT #: SD0904 PROJECT FUND: 912 - DRAINAGE FUND BUDGET: $265,000 PROJECT FUNDING MANAGER: Gary Balmain SOURCES: DRAINAGE UTILITY FUND PROJECT CLIENT: Public Works Replace, redesign and resize the collapsed culvert under W. King Cole at the Police Department. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 265,000 $265,000 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $265,000 $0 $265,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 T e x a s Av e SKrenek Tap RdAnder son St Harvey Mitchell P k w y S Morgans LnValley View D rSouthwest Pkwy ES o ut h w o o d Dr William King Cole DrYale CtFm 2 1 5 4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell b o r n R d Fm 158 136 PROJECT: STORMWATER MAPPING PROJECT #: SD0523 FUND: 912 - DRAINAGE FUND PROJECT BUDGET: $133,000 PROJECT FUNDING MANAGER: MARK SMITH SOURCES: DRAINAGE UTILITY FUND PROJECT CLIENT: Public Works Parent Project Mapping of College Station stormwater infrastructure. Original Budget 200,000 $50,000 transferred to SD0703 Bee Creek - LOMR in March 2007 $7,000 transferred to SD0805 - FY08 $10,000 transferred to SD0703 - FY08 FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 50,000 $50,000 2009-10 50,000 $50,000 2010-11 33,000 $33,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $133,000 $0 $0 $133,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $133,000 $0 $0 $133,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 137 PROJECT: Fence for Mitigation at Arrington/ PROJECT #: SD0901 Decatur FUND: 912 - Drainage Utility Fund PROJECT BUDGET: $100,000 PROJECT FUNDING MANAGER: Jeff Haeber SOURCES: Drainage Utility Funds PROJECT CLIENT: Public Works Funds will be used to construct a fence along the Arrington/Decatur Road extension. This fence is required by TxDOT and will protect the Navasota Ladies Tress plants in the area. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 100,000 $100,000 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $100,000 $0 $100,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 138 GGEENNEERRAALL GGOOVVEERRNNMMEENNTT-- CCOONNVVEENNTTIIOONN CCEENNTTEERR CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000099--22001100 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22001144--22001155 139 GENERAL GOVERNMENT CONVENTION CENTER CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT REVISED APPROVED PROJECT BUDGET APPROPRIATIONS FY08-09 FY09-10 NUMBER AMOUNT THROUGH FY08 APPROPRIATIONS APPROPRIATIONS BEGINNING FUND BALANCE:341,251$ 1,204,543$ ADDITIONAL RESOURCES: CERTIFICATES OF OBLIGATION 2,600,000$ -$ INTERGOVERNMENTAL - - INTRAGOVERNMENTAL TRANSFERS 7,141,641 2,700,000 INVESTMENT EARNINGS 8,000 23,600 OTHER - 355,892 SUBTOTAL ADDITIONAL RESOURCES 9,749,641$ 3,079,492$ TOTAL RESOURCES AVAILABLE 10,090,892$ 4,284,036$ PUBLIC FACILITIES CONVENTION CNTR GG0907 TBD -$ 9,600,000$ 376,385$ CLOSED PROJECTS CAPITAL PROJECTS SUBTOTAL 9,600,000$ 376,385$ OTHER 150,000 150,000 TRANSFER OUT 130,671 223,615 DEBT ISSUANCE COSTS - - GENERAL & ADMIN CHARGES - - TOTAL EXPENDITURES 9,880,671$ 750,000$ ENDING FUND BALANCE:210,221$ 3,534,036$ BUDGET APPROPRIATIONS 140 GENERAL GOVERNMENT CONVENTION CENTER CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED THROUGH FY07 FY 07-08 FY 08-09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 328,188$ 341,251$ 1,204,543$ 3,534,036$ 3,363,421$ 3,435,121$ 3,508,321$ 3,582,921$ -$ 3,220,000$ -$ -$ -$ -$ -$ -$ - - - - - - - - - 7,000,000 2,700,000 - - - - - 13,389 (30,000) 23,600 53,000 71,700 73,200 74,600 76,100 - 613,948 355,892 150,000 - - - - 13,389$ 10,803,948$ 3,079,492$ 203,000$ 71,700$ 73,200$ 74,600$ 76,100$ 341,577$ 11,145,199$ 4,284,036$ 3,737,036$ 3,435,121$ 3,508,321$ 3,582,921$ 3,659,021$ 295$ -$ 9,639,985$ 376,385$ 223,615$ -$ -$ -$ -$ 326$ 326$ 9,639,985$ 376,385$ 223,615$ -$ -$ -$ -$ - 150,000 150,000 150,000 - - - - - 130,671 223,615 - - - - - - 20,000 - - - - - - - - - - - - 326$ 9,940,656$ 750,000$ 373,615$ -$ -$ -$ -$ 341,251$ 1,204,543$ 3,534,036$ 3,363,421$ 3,435,121$ 3,508,321$ 3,582,921$ 3,659,021$ PROJECTED EXPENDITURES 141 PROJECT: PROJECT #: GG00907 PROJECT FUND: 128 - Convention Center Fund BUDGET: TBD PROJECT FUNDING MANAGER: SOURCES: Certificates of Obligation PROJECT CLIENT: CMO FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $295 $295 2008-09 9,639,985 $9,639,985 2009-10 376,385 $376,385 2010-11 223,615 $223,615 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $9,639,985 $600,000 $0 $295 $10,240,280 Convention Center Ph III TBD Design and constructuion of Convention Center / Hotel. PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $9,639,985 $600,000 $0 $295 $10,240,280 Total Personnel TBD Supplies TBD Service TBD Capital TBD TOTAL TBDTBD TBD OPERATING COSTS First Fiscal Year Annually 142 SSPPEECCIIAALL RREEVVEENNUUEE -- PPAARRKKLLAANNDD DDEEDDIICCAATTIIOONN CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000099--22001100 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22001144--22001155 143 GENERAL GOVERNMENT   PARKLAND DEDICATION  CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009‐2010 THROUGH FISCAL YEAR 2014‐2015 PROJECT REVISED APPROVED PROJECT BUDGET APPROPRIATIONS FY 08-09 FY 09-10 NUMBER AMOUNT THROUGH FY08 APPROPRIATIONS APPROPRIATIONS BEGINNING FUND BALANCE:1,610,534$ 1,188,689$ ADDITIONAL RESOURCES: CONTRIBUTIONS 290,000$ 300,000$ INVESTMENT EARNINGS 25,000 8,000 INTRAGOVERNMENTAL TRANSFERS - - OTHER - - SUBTOTAL ADDITIONAL RESOURCES 315,000$ 308,000$ TOTAL RESOURCES AVAILABLE 1,925,534$ 1,496,689$ PARKLAND DEDICATION FUND ZONE 1 PARK PK0051 18,000 - 18,000 ZONE 2 PARK PK0052 - - 31,961 - PARKWAY PARK PK0903 12,500 - - 12,500 ZONE 3 PARK PK0053 142,000 - 115,000 142,000 CENTRAL PARK POND SIDEWALK PK0805 61,000 44,390 70,610 - ZONE 4 PARK PK0054 - - - - WINDWOOD PARK IMP PK0916 76,500 - 76,500 - ZONE 5 PARK PK0055 - - - - STEEPLECHASE PARK BENCH TBD 810 - 810 - ZONE 6 PARK PK0056 - - - - SOUTHWEST PARK DEVELOPMENT PK0806 268,000 202,761 57,239 8,000 ZONE 7 PARK PK0057 - - - - JOHN CROMPTON PARK PHASE III PK0904 114,000 - 114,000 - ZONE 8 PARK PK0058 - - - - EMERALD FOREST PARK IMP. PK0713 63,000 41,000 7,000 - ZONE 9 PARK PK0059 33,000 - 3,677 33,000 ZONE 10 PARK PK0060 190,000 - 131,812 190,000 SOUTHERN OAKS TRAIL AND LIGHTS PK0905 130,000 - 130,000 - CASTLEROCK PARK DEVELOPMENT PK0922 76,000 - - 76,000 ZONE 11 PARK PK0061 2,750 - 324 2,750 ZONE 12 PARK PK0824 44,500 - 26,308 44,500 ZONE 13 PARK PK0807 50,000 - 632 50,000 ZONE 14 PARK PK0717 97,000 - 81,871 97,000 ZONE 15 PARK PK0808 173,000 - 107,136 173,000 ZONE 16 PARK TBD - - - - CLOSED PROJECTS 42,422 CAPITAL PROJECTS SUBTOTAL 288,151$ 997,302$ 846,750$ OTHER - - GENERAL & ADMIN. CHARGES 10,120 14,388 TOTAL EXPENDITURES 1,007,422$ 861,138$ ENDING FUND BALANCE:918,112$ 635,551$ BUDGET APPROPRIATIONS 144 GENERAL GOVERNMENT   PARKLAND DEDICATION  CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009‐2010 THROUGH FISCAL YEAR 2014‐2015 PROJECT EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED THROUGH FY07 FY 07-08 FY 08-09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 1,558,514$ 1,610,534$ 1,188,689$ 435,771$ 431,771$ 430,771$ 429,771$ 427,771$ 599,840$ 290,000$ 300,000$ -$ -$ -$ -$ -$ 63,096 20,000 8,000 6,000 9,000 9,000 8,000 8,000 - - - - - - - - - - - - - - - - 662,936$ 310,000$ 308,000$ 6,000$ 9,000$ 9,000$ 8,000$ 8,000$ 2,221,450$ 1,920,534$ 1,496,689$ 441,771$ 440,771$ 439,771$ 437,771$ 435,771$ - - - 18,000 - - - - - - - - - - - - - - - - - 12,500 - - - 142,000 - - - - - - - 61,000 - - - - - - - - - - - - - - - - - 76,500 - - - - - - - - - - - - - - - - - 810 - - - - - - - - - - - - - - - - 220 100,000 167,780 - - - - - - - - - - - - - - - - 61,000 53,000 - - - - - - - - - - - - 63,000 - - - - - - - - 33,000 - - - - - - - - 190,000 - - - - - - - 130,000 - - - - - - - - 76,000 - - - - - - - - - 2,750 - - - - - - - - 44,500 - - - - - - - 50,000 - - - - - - - - 97,000 - - - - - - - - 173,000 - - - - - - - - - - - - - - 588,491 216,416 -$ 588,711$ 721,726$ 1,046,530$ -$ -$ -$ -$ -$ 785 - - - - - - - 21,420 10,120 14,388 10,000 10,000 10,000 10,000 10,000 610,916$ 731,846$ 1,060,918$ 10,000$ 10,000$ 10,000$ 10,000$ 10,000$ 1,610,534$ 1,188,689$ 435,771$ 431,771$ 430,771$ 429,771$ 427,771$ 425,771$ PROJECTED EXPENDITURES 145 1 2 3 4 5 6 7 8 9 10 11 1213 14 1516 17 18 19 20 21 22 23 24 25 26 27 28 29 Grimes County Burleson County T e x a s A v e State H w y 6 U n iversity D rF m 2 1 5 4 W illiam D FitchLegend Neighborhood Park Zones TAMU Property CS City Limits Parkland Dedication Zones N Adopted by City Council Oct. 23, 2008 146 PROJECT: ZONE 1 PARK PROJECT #: PK0051 FUND: 171 - Zone 1 Parkland PROJECT BUDGET: $18,000 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 1 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 18,000 $18,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $18,000 $0 $18,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvements as identified for the Spruce Street property (Northgate Park) in Park Zone 1. Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 SS First Fiscal Year Annually $0 $0 147 PROJECT: ZONE 2 PARK PROJECT #: PK0052 FUND: 172 - Zone 2 Parkland PROJECT BUDGET: $0 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 2 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 2. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $0 $0 $0 Total Personnel $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 148 PROJECT: PARKWAY PARK PROJECT #: PK0903 FUND: 172 - Zone 2 Parkland PROJECT BUDGET: $12,500 PROJECT MANAGER: David Wood FUNDING SOURCES: Zone 2 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation along Woodland Parkway. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 12,500 $12,500 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $12,500 $0 $12,500 Total PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually These funds will be used for improvements in Parkway Park, to include the addition of the park THIS PROJECT IS IN DESIGN BY PARD PLANNING. Total Personnel $1,500 Supplies $500 Service $0 Capital $0 TOTAL $2,000 First Fiscal Year Annually $1,500 $0 $2,000 500 149 PROJECT: ZONE 3 PARK PROJECT #: PK0053 FUND: 173 - Zone 3 Parkland PROJECT BUDGET: $142,000 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 3 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 3. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 142,000 $142,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $142,000 $0 $142,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 150 PROJECT: Stephen C. Beachy Central Park PROJECT #: PK0805 Pond Sidewalk FUND: 173 - Zone 3 Parkland PROJECT BUDGET: $61,000 PROJECT MANAGER: David Wood FUNDING SOURCES: Zone 3 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation These funds will be used for improvements at Stephen C. Beachy Central Park. Improvements will include the addition of a concrete sidewalk around the third pond in the park. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 61,000 $61,000 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $61,000 $0 $61,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 151 PROJECT: ZONE 4 PARK PROJECT #: PK0054 FUND: 174 - Zone 4 Parkland PROJECT BUDGET: $0 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 4 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 4. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $0 $0 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 152 PROJECT: Windwood Park Improvements PROJECT #: PK0916 FUND: 174 - Zone 4 Parkland PROJECT BUDGET: $76,500 PROJECT MANAGER: Pete Vanecek FUNDING SOURCES: Zone 4 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation Improvements at Windwood Park will include a shelter, fencing and a new drinking fountain. In addition, the swingset will be replaced using Parks O&M playground equipment replacement funds. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 76,500 $76,500 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $76,500 $0 $76,500 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $76,500 $0 $76,500 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 153 PROJECT: ZONE 5 PARK LAND PROJECT #: PK0055 FUND: 175 - Zone 5 Parkland PROJECT BUDGET: $0 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 5 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $0 $0 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvements and renovation projects identified in Zone 5. Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 154 PROJECT: Steeplechase Park Bench PROJECT #: TBD FUND: 175 - Zone 5 Parkland PROJECT BUDGET: $810 PROJECT MANAGER: David Wood FUNDING SOURCES: Zone 5 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 810 $810 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $810 $0 $810 PROJECT DESCRIPTION/STATUS This project is for the Installation of a bench with a concrete pad in Steeplechase Park. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 155 PROJECT: ZONE 6 PARK PROJECT #: PK0056 FUND: 176 - Zone 6 Parkland PROJECT BUDGET: $0 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 6 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 6. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $0 $0 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 156 PROJECT: Southwest Park Development PROJECT #: PK0806 FUND: 176 - Zone 6 Parkland PROJECT BUDGET: $268,000 PROJECT MANAGER: David Wood FUNDING SOURCES: Zone 6 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $220 $220 2008-09 100,000 $100,000 2009-10 167,780 $167,780 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $100,000 $167,780 $220 $268,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Southwest Park will be developed as a typical neighborhood park with features that may include items such as a playground, walks, picnic units, basketball court, etc. Total Personnel $12,000 Supplies $4,800 Service $13,200 Capital $2,000 TOTAL $32,000 $12,000 4,800 $2,000 $30,000 13,200 2,000 OPERATING COSTS First Fiscal Year Annually 157 PROJECT: Zone 7 Parkland PROJECT #: PK0057 FUND: 177 - Zone 7 Parkland PROJECT BUDGET: $0 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 7 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $0 $0 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvement and renovation projects in Park Zone 7. Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 OPERATING COSTS First Fiscal Year Annually 158 PROJECT: John Crompton Park, Phase III PROJECT #: PK0904 FUND: 177 - Zone 7 Parkland PROJECT BUDGET: $114,000 PROJECT MANAGER: Pete Vanecek FUNDING SOURCES: Zone 7 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation Phase III development of Crompton Park. Improvements include the addition of concrete sidewalks, area lights, signage, land aqusition, and pond improvements. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 61,000 $61,000 2009-10 53,000 $53,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $114,000 $0 $114,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $4,000 Supplies $4,000 Service $0 Capital $0 TOTAL $8,000$0 $8,000 $4,000 4,000 OPERATING COSTS First Fiscal Year Annually John Crompton Pk Ph III 159 PROJECT: ZONE 8 PARK PROJECT #: PK0058 FUND: 178 - Zone 8 Parkland PROJECT BUDGET: $0 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 8 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 8. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $0 $0 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 160 PROJECT: ZONE 9 PARK PROJECT #: PK0059 FUND: 179 - Zone 9 Parkland PROJECT BUDGET: $33,000 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 9 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 9. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 33,000 $33,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $33,000 $0 $33,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 161 PROJECT: PROJECT #: PK0060 FUND: PROJECT BUDGET:$190,000 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 10 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 190,000 $190,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $190,000 $0 $190,000 Total Personnel $0 Supplies $0 Service $0 ZONE 10 PARK 180 - Zone 10 Parkland PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 10. Service $0 Capital $0 TOTAL $0$0 $0 162 PROJECT: Southern Oaks Trail and Lights PROJECT #: PK0905 PROJECT FUND: BUDGET: $130,000 PROJECT FUNDING MANAGER: David Wood SOURCES: PROJECT CLIENT: Parks and Recreation This project is for the construction of concrete sidewalks, a disc golf course, and the installation of area lights and trees in the southern portion of Southern Oaks Park. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 130,000 $130,000 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $130,000 $0 $130,000 Zone 10 Park Land Dedication Funds Zone 10 Dedication Fund PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $7,280 Supplies $728 Service $0 Capital $0 TOTAL $8,008$0 $8,008 $7,280 728 OPERATING COSTS First Fiscal Year Annually 163 PROJECT: CASTLE ROCK PARK DEVELOPMENT PROJECT #: PK0922 FUND: PROJECT BUDGET: $76,000 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 10 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 76,000 $76,000 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $76,000 $0 $76,000 Total Personnel $0 Supplies $0 180 - Zone 10 Parkland PROJECT DESCRIPTION/STATUS In accordance with the Parkland Dedication Ordinance, these funds have been set aside for development of Castle Rock Park in Park Zone 10. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Supplies $0 Service $7,510 Capital $0 TOTAL $7,510$0 $7,510 7,510 164 PROJECT: ZONE 11 PARK PROJECT #: PK0061 FUND: PROJECT BUDGET: $2,750 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 11 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 11. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 2,750 $2,750 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $2,750 $0 $2,750 OPERATING COSTS 181 - Zone 11 Parkland PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 165 PROJECT: ZONE 12 PARK PROJECT #: PK0824 FUND: PROJECT BUDGET:$44,500 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 12 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 12. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 44,500 $44,500 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $44,500 $0 $44,500 182 - Zone 12 Parkland PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 166 PROJECT: ZONE 13 PARK PROJECT #: PK0807 FUND: PROJECT BUDGET: $50,000 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 13 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 50,000 $50,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $50,000 $0 $50,000 183 - Zone 13 Parkland improvements and renovation projects as identified in Park Zone 13. PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 167 PROJECT: ZONE 14 PARK PROJECT #: PK0717 FUND: PROJECT BUDGET: $97,000 PROJECT MANAGER: PETE VANECEK FUNDING SOURCES: Zone 14 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 97,000 $97,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $97,000 $0 $97,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS 184 - Zone 14 Parkland improvements and renovation projects as identified in Park Zone 14. Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 168 PROJECT: ZONE 15 PARK PROJECT #: PK0808 FUND: PROJECT BUDGET: $173,000 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 15 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 173,000 $173,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $173,000 $0 $173,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS 185 - Zone 15 Parkland improvements and renovation projects as identified in Park Zone 15. Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 169 PROJECT: ZONE 16 PARK PROJECT #: TBD FUND: PROJECT BUDGET: $0 PROJECT MANAGER: TBD FUNDING SOURCES: Zone 16 Parkland Dedication PROJECT Funds CLIENT: Parks and Recreation In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $0 $0 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS 186 - Zone 16 Parkland improvements and renovation projects as identified in Park Zone 16. Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 170 EELLEECCTTRRIICC CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000099--22001100 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22001133--22001144 171 ELECTRIC SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2013-2014 FY 08-09 ACTUAL REVISED ESTIMATE FY07-08 BUDGET FY 08-09 BEGINNING FUND BALANCE:$2,805,968 $872,560 $392,526 SUBTOTAL ADDITIONAL RESOURCES $7,146,016 $9,751,000 $7,136,844 TOTAL RESOURCES AVAILABLE $9,951,984 $10,623,560 $7,529,370 TOTAL EXPENDITURES 9,717,537$ 10,188,378$ 7,089,322$ MEASUREMENT FOCUS ADJUSTMENT 158,079$ ENDING FUND BALANCE:$392,526 $435,182 $440,048 172 ELECTRIC SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2013-2014 FY 09-10 APPROVED PROJECTED PROJECTED PROJECTED PROJECTED BUDGET FY10-11 FY11-12 FY12-13 FY13-14 $440,048 $185,838 $301,838 $77,838 $179,989 $8,678,000 $6,313,000 $8,688,000 $7,599,151 $7,113,000 $9,118,048 $6,498,838 $8,989,838 $7,676,989 $7,292,989 8,932,210$ 6,197,000$ 8,912,000$ 7,497,000$ 7,167,000$ $185,838 $301,838 $77,838 $179,989 $125,989 173 Home of Texas A&M University ® 174 WWAATTEERR CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000099--22001100 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22001144--22001155 175 WATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 11/12/09 4:06 PM FY10 PROJECT APPROVED APPROVED PROJECT WORK REQUEST BUDGET APPROPRIATIONS FY08-09 FY09-10 NUMBER NUMBER AMOUNT THROUGH FY08 APPROPRIATIONS APPROPRIATIONS BEGINNING FUND BALANCE:3,021,021$ 1,453,809$ ADDITIONAL RESOURCES: UTILITY REVENUE BONDS/CERTIFICATES OF OBLIGATION 10,750,000$ 12,025,000$ INTEREST ON INVESTMENTS 12,000 18,000 TRANSFERS FROM OPERATIONS 3,600,000 7,000,000 OTHER 3,525,260 2,344,326 SUBTOTAL ADDITIONAL RESOURCES 17,887,260$ 21,387,326$ TOTAL RESOURCES AVAILABLE 20,908,281$ 22,841,135$ PRODUCTION PROJECTS SOURCE AND SUPPLY PLANT - WSWOC PARALLEL WELLFIELD COLL LINE PH I - WF0352553 5,081,362 2,275,191 1,987,555 818,616 LAND ACQUISITION - WELLS WT0206 WF0377324 6,667,217 3,480,614 3,142,000 44,603 WELL #8 - WF1097966 5,120,000 - 500,000 4,620,000 WELL#8 COLLECTION LINE - WF1097967 3,000,000 - 950,000 2,050,000 WELL #9 TBD 4,727,000 - - - WELL #9 COLLECTION LINE TBD 4,131,831 - - - DOWLING ROAD 10 MG STORAGE TANK WT0117 WF0353631 7,432,856 - - - WATER PUMPING AND TREATMENT PLANT - WPWOC SANDY POINT CHEMICAL SYS REPLACEMENT - TBD 1,698,964 - - - HIGH SERVICE WATER PUMP IMPROVEMENTS WF1223117 2,500,000 - - 500,000 WELLS #1 AND #3 PUMP/MOTOR REHAB TBD 400,000 - - 400,000 COOLING TOWER EXPANSION TBD 3,170,000 - - - EMERGENCY ELECTRIC GENERATOR EXPANSION TBD 700,000 - - - WELL #1 MOTOR CONTROL CENTER REPLACEMENT TBD 580,000 - - - WELL #2 MOTOR CONTROL CENTER REPLACEMENT TBD 580,000 - - - WELL #3 MOTOR CONTROL CENTER REPLACEMENT TBD 580,000 - - - WATER GENERAL PLANT - WGWOC SCADA REPLACEMENT - WF0742940 259,476 351,751 - - WATER PLANT SECURITY - WF0466439 1,489,480 1,567,969 - - UTILITY SERVICE CENTER RENOVATIONS - TBD 348,000 - - - SCADA MAN MACHINE INTERFACE TBD 205,000 - - - COMMUNICATIONS INFRASTRUCTURE IMPROVEMENTS TBD 480,000 - - - DISTRIBUTION SCADA TBD 900,000 - - - CLOSED PROJECTS SUBTOTAL 6,579,555$ 8,433,219$ DISTRIBUTION PROJECTS TRANSMISSION AND DISTRIBUTION PLANT - WTWOC OVERSIZED PARTICIPATION - TBD ANNUAL - 100,000 100,000 WATER RECLAIM / IRRIGATION WT0110 WF0995711 3,606,730 575,730 - 3,031,000 WELLBORN WIDENING - WF0613546 4,250,000 4,250,000 - - BARRON ROAD WATER SERVICE EXT - WF0379197 2,383,253 2,384,475 - - RAYMOND STOTZER WEST - WF1111167 3,440,000 - 1,000,000 - EAGLE AVENUE EXT - WF1095364 101,464 92,000 - - W.D. FITCH WATER LINE EXTENSION - WF1092576 35,000 25,000 10,000 - BARRON ROAD WIDENING PHASE II - TBD 150,000 - - 150,000 VICTORIA AVENUE EXTENSION - WF1158553 228,375 - 15,000 213,375 SH 40 WATER LINE - GRAHAM TO BARRON TBD 2,586,000 - - 25,000 SH 40 WATER LINE - Iron Horse to Victoria TBD 643,000 - - - WATER RECLAMATION PHASE II TBD 1,475,000 - - - FM 60 WIDENING WATER RELOCATION TBD 2,478,000 - - 299,500 176 WATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED THROUGH FY07 FY 07-08 FY 08-09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 11,127,771$ 3,021,021$ 1,453,809$ 848,447$ 805,436$ 250,436$ 282,541$ 600,841$ 6,900,000$ 7,535,000$ 12,025,000$ 6,750,000$ 10,800,000$ 9,000,000$ 7,300,000$ 5,250,000$ 90,141 - 18,000 7,200 9,000 4,000 7,000 7,000 - 600,000 7,000,000 600,000 1,300,000 2,250,000 2,000,000 2,050,000 124,801 7,768 2,344,326 586,082 - 1,888,900 - - 7,114,942$ 8,142,768$ 21,387,326$ 7,943,282$ 12,109,000$ 13,142,900$ 9,307,000$ 7,307,000$ 18,242,713$ 11,163,789$ 22,841,135$ 8,791,729$ 12,914,436$ 13,393,336$ 9,589,541$ 7,907,841$ 44,286 159,544 377,532 4,500,000 - - - - - 204,671 3,361,544 1,201,002 1,000,000 900,000 - - - - - - 245,000 4,875,000 - - - - - - - 1,000,000 2,000,000 - - - - - - - - - - 2,200,000 2,527,000 - - - - - - 25,000 1,975,000 2,131,831 - - 471,856 - - - - - 80,000 3,919,000 2,962,000 - - - - - - 200,000 1,498,964 - - - - - 400,000 2,100,000 - - - - - - - 400,000 - - - - - - - - - - 300,000 2,870,000 - - - - - - - - - 75,000 625,000 - - - - - - - - 580,000 - - - - - - - - 580,000 - - - - - - - - 580,000 109,173 15,303 - 110,000 25,000 - - - - 1,060,780 43,700 385,000 - - - - - - - - - - 348,000 - - - - - - - - 117,000 25,000 63,000 - - - - - - 240,000 240,000 - - - - - - - - 300,000 300,000 300,000 - 9,575,733 2,359,749 1,890,766$ 13,155,823$ 5,568,283$ 13,285,000$ 3,755,000$ 5,240,000$ 9,470,795$ 4,294,000$ 5,327,000$ - - 100,000 100,000 100,000 100,000 100,000 100,000 100,000 41,730 36,487 400,000 2,650,000 478,513 - - - - 3,292,101 17,140 75,000 865,759 - - - - - 1,160,089 18,431 23,334 127,007 1,054,392 - - - - - - 354,000 366,000 950,000 1,770,000 - - - - - 101,464 - - - - - - - - 35,000 - - - - - - - - - 150,000 - - - - - - - 10,875 217,500 - - - - - - - - 25,000 200,000 2,361,000 - - - - - - - 90,000 553,000 - - - - - - 450,000 1,025,000 - - - - 299,500 443,500 1,735,000 - - - 177 WATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 FY10 PROJECT APPROVED APPROVED PROJECT WORK REQUEST BUDGET APPROPRIATIONS FY08-09 FY09-10 NUMBER NUMBER AMOUNT THROUGH FY08 APPROPRIATIONS APPROPRIATIONS 2002 ANNEXATION PROJECTS - ROCK P RD S OF CARTER LAKE (AREA 5) - WF0805789 178,811 434,000 - - WILLIAM D FITCH EAST (AREA 6) - WF0805807 672,000 672,000 - - NANTUCKET EAST OF HARPERS FERRY (AREA 3) TBD 95,000 - - - DONATED WATER NA CLOSED PROJECTS 1,300,000 - SUBTOTAL 2,425,000$ 3,818,875$ REHABILITATION PROJECTS: BARRON ROAD REHAB - WF0654325 100,000$ 100,000 - - BEE CREEK PHASES IV & V TBD 120,000 120,000 - - TAUBER & STASNEY - WF0625888 305,660 120,000 159,347 26,313 COLLEGE PARK/BREEZY HEIGHTS - WF0595915 1,640,000 1,640,000 - - SOUTH KNOLL/THE GLADE - WF1044480 1,725,000 900,000 825,000 - SOUTHWOOD 5-7 - WF1105425 1,492,279 - 1,507,500 - EASTGATE REHAB TBD 2,275,000 - - - MCCOLLOCH REHAB TBD 1,782,500 - - - NORTHGATE REHAB TBD 1,500,000 - - - THE KNOLL REHAB TBD 1,489,200 - - - CLOSED PROJECTS 77,756,758 SUBTOTAL 2,491,847$ 26,313$ CAPITAL PROJECTS CONTINGENCY - WF0608079 150,000$ - 140,000 150,000 METER REPLACEMENT PROGRAM WF1128579 360,000 360,000 CAPITAL PROJECTS SUBTOTAL 162,710,216 11,996,402$ 12,788,407$ (162,710,216) GENERAL AND ADMINISTRATIVE 83,757 80,487 DEBT ISSUANCE COST 106,000 80,000 TOTAL EXPENDITURES 12,186,159$ 12,948,894$ MEASUREMENT FOCUS ADJUSTMENT ENDING FUND BALANCE:8,722,122$ 9,892,241$ 178 WATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED THROUGH FY07 FY 07-08 FY 08-09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 - 19,300 139,644 19,867 - - - - - - 3,942 - 334,000 334,058 - - - - - - - - - - - 95,000 - - 31,454 685,577 38,323 4,517,162$ 928,734$ 1,491,863$ 5,134,824$ 3,316,405$ 6,519,000$ 645,000$ 1,125,000$ 100,000$ - - 48,825 - - - - - - - - - 120,000 - - - - - 21,403 - 206,570 77,688 - - - - - 87,467 13,358 1,539,175 - - - - - - - 134 138,000 1,436,866 150,000 - - - - - - 94,569 1,267,823 129,888 - - - - - - - - - 225,000 2,050,000 - - - - - - - - - 928,100 854,400 - - - - - - 275,000 1,225,000 - - - - - - - - 776,600 712,600 49,316 3,938 108,870$ 62,808$ 2,031,077$ 2,902,377$ 279,888$ 225,000$ 2,325,000$ 2,929,700$ 1,567,000$ - - 140,000 150,000 150,000 150,000 150,000 150,000 150,000 - - 360,000 360,000 360,000 360,000 360,000 360,000 360,000 6,516,799$ 14,147,365$ 9,591,223$ 21,832,201$ 7,861,293$ 12,494,000$ 12,950,795$ 8,858,700$ 7,504,000$ 309,836 83,757 80,487 100,000 100,000 100,000 100,000 100,000 (10,825) 35,000 80,000 25,000 70,000 60,000 30,000 20,000 14,446,376$ 9,709,980$ 21,992,688$ 7,986,293$ 12,664,000$ 13,110,795$ 8,988,700$ 7,624,000$ (775,316)$ 3,021,021$ 1,453,809$ 848,447$ 805,436$ 250,436$ 282,541$ 600,841$ 283,841$ 179 PPRROODDUUCCTTIIOONN PPRROOJJEECCTTSS 180 WORK ORDER #: WF0352553 PROJECT: PARALLEL WELLFIELD COLLECTION PROJECT #: WSWOC LINE PHASE I FUND: WATER CAPITAL PROJECTS PROJECT BUDGET:$5,081,362 PROJECT MANAGER: PHILIP BARGAS FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Stephen Maldonado Construction of a collection line for the water wells parallel to the existing line. The existing line is operating at maximum design capacity with the input of six wells. The construction of Well #7 will require this additional pipeline to deliver water to Sandy Point Pump Station. In addition, will possibly replace the short collection lines (stub outs) for Wells #1 and #2. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 171,585 32,245 0 0 $203,830 2008-09 37,532 340,000 $377,532 2009-10 4,500,000 $4,500,000 2010-11 $0 2011-12 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $209,117 $372,245 $4,500,000 $0 $5,081,362 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 181 WORK ORDER #: WF0377324 PROJECT: LAND ACQUISITION - WELLS PROJECT #: WT0206 FUND: WATER CAPITAL PROJECTS PROJECT BUDGET:$6,667,217 PROJECT MANAGER: DAVE COLEMAN FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services Land to be purchased for future Well Sites #8, #9, and #10. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 3,566,215 0 0 0 $3,566,215 2008-09 1,201,002 $1,201,002 2009-10 1,000,000 $1,000,000 2010-11 900,000 $900,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2014-15 $0 TOTAL $6,667,217 $0 $0 $0 $6,667,217 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 182 WORK ORDER #: WF1097966 PROJECT: WELL #8 PROJECT #: WSWOC FUND: WATER CAPITAL PROJECTS PROJECT BUDGET: $5,120,000 PROJECT FUNDING MANAGER: PHILIP BARGAS SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Brian J. Smith FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 245,000 0 $245,000 2009-10 125,000 4,750,000 $4,875,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 PROJECT DESCRIPTION/STATUS This project will construct Water Well Simsboro 8 with its associated electrical, SCADA, security, and drainage infrastructure. Land acquisition costs are included in a separate project. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2014-15 $0 TOTAL $0 $370,000 $4,750,000 $0 $5,120,000 Total Personnel $7,000 Supplies $500 Service $60,000 Capital $0 TOTAL $67,500 0 $0 $67,500 $7,000 500 60,000 OPERATING COSTS First Fiscal Year Annually 183 WORK ORDER #: WF1097967 PROJECT: WELL #8 COLLECTION LINE PROJECT #: WSWOC FUND: WATER CAPITAL PROJECTS PROJECT BUDGET: $3,000,000 PROJECT FUNDING MANAGER: PHILIP BARGAS SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Brian J. Smith Project provides for engineering design, and construction of collection line progressing from Water Well #8 to a connection point in the existing wellfield collection line. The additional capacity is required to meet TCEQ regulations for pumping capacity to match projected population. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 240,000 760,000 $1,000,000 2009-10 60,000 1,940,000 $2,000,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $300,000 $2,700,000 $0 $3,000,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $4,000 Supplies $0 Service $300 Capital $0 TOTAL $4,300 0 $0 $4,300 300 0 OPERATING COSTS First Fiscal Year Annually $4,000 184 WORK ORDER #: TBD PROJECT: WELL #9 PROJECT #: WSWOC FUND: WATER CAPITAL PROJECTS PROJECT BUDGET: $4,727,000 PROJECT FUNDING MANAGER: BRIAN J. SMITH SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 200,000 2,000,000 $2,200,000 2012-13 100,000 2,427,000 $2,527,000 2013-14 $0 2014-15 $0 TOTAL $0 $300,000 $4,427,000 $0 $4,727,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR This project will construct Water Well Simsboro 9 with its associated electrical, SCADA, security, and drainage infrastructure. Land acquisition costs are included in a separate project. TOTAL $0 $300,000 $4,427,000 $0 $4,727,000 Total Personnel $7,000 Supplies $500 Service $60,000 Capital $0 TOTAL $67,500$0 500 60,000 0 $67,500 $7,000 OPERATING COSTS First Fiscal Year Annually 185 WORK ORDER #: TBD PROJECT: WELL #9 COLLECTION LINE PROJECT #: WSWOC FUND: WATER CAPITAL PROJECTS PROJECT BUDGET: $4,131,831 PROJECT FUNDING MANAGER: BRIAN J. SMITH SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services Project provides for land purchase, engineering design, and construction of collection line progressing from Water Well #9 to a connection point in the existing wellfield collection line. The additional capacity is required to meet TCEQ regulations for pumping capacity to match projected population. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 25,000 $25,000 2011-12 175,000 1,800,000 $1,975,000 2012-13 100,000 2,031,831 $2,131,831 2013-14 $0 2014-15 $0 TOTAL $25,000 $275,000 $3,831,831 $0 $4,131,831 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $4,000 Supplies $0 Service $300 Capital $0 TOTAL $4,300 $4,000 OPERATING COSTS First Fiscal Year Annually $0 0 300 0 $4,300 186 WORK ORDER #: WF0353631 PROJECT: DOWLING ROAD TEN MG TANK PROJECT #: WT0117 FUND: WATER CAPITAL PROJECTS PROJECT BUDGET:$7,432,856 PROJECT MANAGER: FRED SUROVIK FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services Construct new Ground Storage Tank of 10 MG capacity at the Dowling Road Pump Station. The additional capacity will be required to meet TCEQ regulations for storage and pumping capacity to satisfy water service driven by community growth. Engineering investigations supporting the expansion effort have identified the need to modify existing buried water supply and discharge pipes, valves, and appurtences to improve personnel safety, operating reliability, and cost efficiency. Fund expenditures have been moved back to allow time for new City road construction to be completed. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 141,295 330,561 0 0 $471,856 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 80,000 $80,000 2013-14 152 000 3 767 000 $3 919 000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2013-14 152,000 3,767,000 $3,919,000 2014-15 2,962,000 $2,962,000 TOTAL $141,295 $562,561 $6,729,000 $0 $7,432,856 Total Personnel $1,400 Supplies $0 Service $1,300 Capital $0 TOTAL $2,700$200 $0 $1,300 $0 $2,500 $1,200 OPERATING COSTS First Fiscal Year Annually $200 187 WORK ORDER #: TBD PROJECT: SANDY POINT PUMP STATION PROJECT #: WPWOC CHEMICAL FEED & STORAGE SYSTEM FUND: WATER CAPITAL PROJECTS PROJECT BUDGET: $1,698,964 PROJECT MANAGER: BRIAN J. SMITH FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services The Chemical Feed and Storage facilities at Sandy Point Pump Station require upgrading to accommodate current expansion of its Water Production infrastructure and to be in compliance with current fire codes. Engineering investigations supporting the expansion effort have identified the need to replace the existing Chlorine Disinfection System to improve personnel safety and operating reliability and cost efficiency. This project has not yet entered the design phase. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 200,000 $200,000 2012-13 100,000 1,398,964 $1,498,964 2013-14 $0 2014-15 $0 TOTAL $0 $300,000 $1,398,964 $0 $1,698,964 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $1,200 Supplies $30,000 Service $4,000 Capital $0 TOTAL $35,200 30,000 0 $0 $35,200 4,000 1,200 OPERATING COSTS First Fiscal Year Annually 188 WORK ORDER #: WF1223117 PROJECT: HIGH SERVICE WATER PUMP PROJECT #: WPWOC IMPROVEMENTS FUND: WATER CAPITAL PROJECTS PROJECT BUDGET: $2,500,000 PROJECT MANAGER: Philip Bargas FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services: Brian J. Smith FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 400,000 $400,000 2010-11 100,000 2,000,000 $2,100,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 PROJECT DESCRIPTION/STATUS HDR Consulting Engineers has performed an analysis of our water system capacities in relation to TCEQ requirements. This analysis revealed that we need to increase our high service pump capacity. This project will replace the existing HS #3 & #4 pumps with higher capacity fixed speed pumps. This project will also replace the existing electrical equipment supporting these pumps. The budget numbers are based on the costs to upgrade HS #1 & #2 in 2001. An updated construction budget will be developed as part of the engineering services for this project. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2014-15 $0 TOTAL $0 $500,000 $2,000,000 $0 $2,500,000 Total Personnel $1,281 Supplies $192 Service $228,000 Capital $0 TOTAL $229,473$0 $229,473 1,281 192 228,000 OPERATING COSTS First Fiscal Year Annually 189 WORK ORDER #: TBD PROJECT: WELLS #1 & #3 PUMP/MTR REHAB PROJECT #: WPWOC FUND: WATER CAPITAL PROJECTS PROJECT BUDGET: $400,000 PROJECT MANAGER: BRIAN J. SMITH FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 50,000 350,000 $400,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $50,000 $350,000 $0 $400,000 PROJECT DESCRIPTION/STATUS This project provides for the removal, inspection, and rehabilitation of the pumps and motors for two Simsboro water wells. The pumps in these two wells have reached their expected service life and need to be inspected and rehabilitated before an emergency maintenance event occurs. This project should begin, and be completed, during October of 2009 through May 2010. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR $$,$,$$, Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 190 WORK ORDER #: TBD PROJECT: COOLING TOWER EXPANSION PROJECT #: WPWOC FUND: WATER CAPITAL PROJECTS PROJECT BUDGET: $3,170,000 PROJECT MANAGER: Brian J. Smith FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services The engineering design and construction of an additional cooling tower, wet well, and switchgear is needed to satisfy community water production demands. One additional 12.5 MGD Cooling Tower will be initiated in FY 2012 to coincide with the increase in demand beyond firm capacity of 25 MGD. This project has not yet entered design phase. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 300,000 $300,000 2012-13 100,000 2,770,000 $2,870,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2012-13 100,000 2,770,000 $2,870,000 2013-14 $0 2014-15 $0 TOTAL $0 $400,000 $2,770,000 $0 $3,170,000 Total Personnel $7,000 Supplies $7,000 Service $127,000 Capital $0 TOTAL $141,000$80,000 3,000 55,000 0 $61,000 4,000 3,000 72,000 OPERATING COSTS First Fiscal Year Annually 4,000 191 WORK EMERGENCY ELECTRIC ORDER #: TBD PROJECT: PROJECT #: WPWOC FUND: PROJECT BUDGET: $700,000 PROJECT FUNDING MANAGER: DAVID OLIVAREZ SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 75,000 $75,000 2014-15 25,000 600,000 $625,000 TOTAL $0 $100,000 $600,000 $0 $700,000 WATER CAPITAL PROJECTS GENERATOR EXPANSION PROJECT DESCRIPTION/STATUS This project will install an additional emergency electric generator at a wellsite to be determined. An additional generator at a wellsite will increase the availablity of water during a grid outage to approximately 10,000 GPM. This project supports the Council directive of providing essential services during an extended power outage. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $100,000 $600,000 $0 $700,000 Total Personnel $1,000 Supplies $4,000 Service $5,000 Capital $0 TOTAL $10,000$0 4,000 5,000 0 $10,000 $1,000 OPERATING COSTS First Fiscal Year Annually 192 PROJECT: Well 1 Motor Control Center PROJECT #: TBD Replacement FUND: Water Capital Projects PROJECT BUDGET: $580,000 PROJECT FUNDING MANAGER: Fred Surovik SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Production: David Olivarez Well 1 Motor Control Center was installed with the original construction in the early 1980's and has exceeded its service life. Replacement is necessary to ensure an adequate water supply for College Station during peak demand periods. A more detailed cost estmate will be prepared as part of the engineering services. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 100,000 480000 $580,000 TOTAL $0 $100,000 $480,000 $0 $580,000 Total PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 First Fiscal Year Annually 193 PROJECT: Well 2 Motor Control Center PROJECT #: TBD Replacement FUND: Water Capital Projects PROJECT BUDGET: $580,000 PROJECT FUNDING MANAGER: Fred Surovik SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Production: David Olivarez Well 2 Motor Control Center was installed with the original construction in the early 1980's and has exceeded its service life. Replacement is necessary to ensure an adequate water supply for College Station during peak demand periods. A more detailed cost estmate will be prepared as part of the engineering services. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 100,000 480000 $580,000 TOTAL $0 $100,000 $480,000 $0 $580,000 Total PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 First Fiscal Year Annually 194 PROJECT: Well 3 Motor Control Center PROJECT #: TBD Replacement FUND: Water Capital Projects PROJECT BUDGET: $580,000 PROJECT FUNDING MANAGER: Fred Surovik SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Production: David Olivarez Well 3 Motor Control Center was installed with the original construction in the early 1980's and has exceeded its service life. Replacement is necessary to ensure an adequate water supply for College Station during peak demand periods. A more detailed cost estmate will be prepared as part of the engineering services. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 100,000 480000 $580,000 TOTAL $0 $100,000 $480,000 $0 $580,000 Total PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 First Fiscal Year Annually 195 WORK ORDER #: WF0742940 PROJECT: SCADA REPLACEMENT PROJECT #: WGWOC FUND: WATER CAPITAL PROJECTS PROJECT BUDGET:$259,476 PROJECT MANAGER: MIKE KELLOGG FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services This project will facilitate the replacement of control based equipment that has exceeded its useful service life. It will upgrade the control of the plants into a more integrated architecture that will: 1. Reduce development time and cost by the re-use of engineering practices. 2. Maximize returns from existing assets, through greatly improved control and monitoring. 3. Reduce future installation cost by utilizing standard bus technologies. 4. Provide a means of being proactive in maintaining equipment with available diagnostic tools. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 124,476 0 $124,476 2008-09 $0 2009-10 110,000 $110,000 2010-11 25,000 $25,000 2011-12 $0 2012-13 $0 2013-14 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2013-14 $0 2014-15 $0 TOTAL $0 $0 $259,476 $0 $259,476 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 OPERATING COSTS First Fiscal Year Annually $0 0 0 $0 196 WORK ORDER #: WF0466439 PROJECT: WATER PLANT SECURITY PROJECT #: WGWOC FUND: WATER CAPITAL PROJECTS PROJECT BUDGET:$1,489,480 PROJECT MANAGER: MICHAEL KELLOGG FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services Design, construct, and install equipment and systems to strengthen security and minimize risks of potential terrorists activities and other threats to City's Water Production infrastructure including geographically isolated water wells, pumping stations, and storage reservoirs. Vulnerability Assessment consultant Contract 03-66 mandated by the U.S. Department of Homeland Security, the Centers for Disease Control and Prevention (CDC), and Environmental Protection Agency (EPA) approved by City Council 03-13-03. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 176,469 865,059 62,952 $1,104,480 2008-09 385,000 $385,000 2009-10 $0 2010 11 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $176,469 $1,250,059 $62,952 $1,489,480 Total Personnel $0 Supplies $6,200 Service $0 Capital $0 TOTAL $6,200 OPERATING COSTS First Fiscal Year Annually $0 6,200 $6,200 197 PROJECT: USC RENOVATIONS FUND(S): PROJECT NUMBERS & BUDGET: Water: TBD $348,000 Wastewater: TBD $348,000 Total Project Budget: $696,000 PROJECT MANAGER: Jeff Haeber FUNDING PROJECT SOURCES: CLIENT: Water Services / Dave Coleman Long Term Debt/Utility Revenue WATER CAPITAL PROJECTS WASTEWATER CAPITAL PROJECTS PROJECT DESCRIPTION/STATUS This project is for the renovation of the Utility Service Center. Improvements include additional office space, HVAC refurbishment, additional Dispatching facilities made necessary by the Homelands Security Act and E.R.C.O.T. The existing facilities are over 20 years old and refurbishment is needed to extend the service life of the facility. The Water and Wastewater portions of the budget will be used toward the dispatch area renovation. Additional budget for the project will come from the Electric Fund. Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 2008-09 0 0 0 0 2009-10 0 0 0 0 2010-11 0 0 696,000 0 2011-12 0 0 0 0 2012-13 0 0 0 0 2013-14 0 0 0 0 2014-15 0 0 0 0 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR $0 $0 PROJECT TOTAL $0 $0 $696,000 $0 $696,000 $0 $696,000 $0 $0 $0 $0 198 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 348,000 $348,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Water Total $0 $0 $348,000 $0 $348,000 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 348,000 $348,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Wastewater Total $0 $0 $348,000 $0 $348,000 OPERATING COSTS First Fiscal Year Annually Total $696,000 PROJECT: USC RENOVATIONS PROJECT CALENDAR OF EXPENDITURES BY FUND PROJECT TOTAL $0 $696,000 $0 First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 199 WORK ORDER #: TBD PROJECT: SCADA MAN MACHINE INTERFACE PROJECT #: WGWOC FUND: WATER CAPITAL PROJECTS PROJECT BUDGET: $205,000 PROJECT FUNDING MANAGER: MICHAEL KELLOGG SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 117,000 $117,000 2011-12 25,000 $25,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR This project will evaluate, procure, and implement software packages available to improve the SCADA Man Machine Interface or graphical software. The software must be able to utilize technologies such as Terminal Services, OPC, and be compatible with the existing control hardware. In addition, it will include software and consulting to implement performance indicators, dashboards, and business data analysis to become best in class. The goal is the Integrated Architecture system leverages one common multidisciplined control engine, one development environment, one networking protocol, and one service-oriented architecture (SOA). The architecture provides fully integrated, scalable solutions for the full range of control and information disciplines. 2012-13 63,000 $63,000 2013-14 $0 2014-15 $0 TOTAL $0 $25,000 $0 $180,000 $205,000 Total Personnel $0 Supplies $0 Service $7,500 Capital $0 TOTAL $7,500 OPERATING COSTS First Fiscal Year Annually $0 7,500 $7,500 200 WORK COMMUNICATION INFRASTRUCTURE ORDER #: TBD PROJECT: IMPROVEMENTS PROJECT #: WGWOC FUND: WATER CAPITAL PROJECTS PROJECT BUDGET:$480,000 PROJECT MANAGER: MICHAEL KELLOGG FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 240,000 $240,000 2011-12 240,000 $240,000 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $480,000 $0 $480,000 This project will provide for data communication improvements. This will allow for built-in redundancy, wireless communications, mobile work force, and any unforeseen communication plan not related to construction projects. The main focus is to construct fiber loops in provide multiple paths to all facilities. Strategic Business Plan Objective 1.1.2 and 1.3.1. PROJECT DESCRIPTION PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 201 WORK ORDER #: TBD PROJECT: DISTRIBUTION SCADA PROJECT #: WGWOC FUND: WATER CAPITAL PROJECTS PROJECT BUDGET: $900,000 PROJECT MANAGER: MICHAEL KELLOGG FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 40,000 260,000 $300,000 2012-13 40,000 260,000 $300,000 2013-14 40,000 260,000 $300,000 2014-15 $0 PROJECT DESCRIPTION/STATUS This project will implement a monitoring system of the distribution system. It will monitor flows, pressure, and water quality. This will help in leak detection, interface with system modeling, and provide alarming for changes in quality. It will also indicate any biological and chemical changes within the distribution system. The location of the units will be determined by existing piping and easements and the ability to provide electrical services. The ideal implementation would be to add four units per year. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2014 15 $0 TOTAL $0 $120,000 $780,000 $0 $900,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 202 DDIISSTTRRIIBBUUTTIIOONN PPRROOJJEECCTTSS 203 WORK ORDER #: TBD PROJECT: OVERSIZE PARTICIPATION WATER LINES PROJECT #: WTWOC FUND: WATER CAPITAL PROJECTS PROJECT BUDGET:Annual PROJECT MANAGER: STEPHEN MALDONADO, JR. FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services These funds are available for oversize participation with developers in the construction of water lines above the minimum size needed to serve the development. This allows lines to be built large enough to meet future development without having to go back and install larger lines. Projects are identified based on development activity. Projects funded for FY 06-07: Sonoma Phase II - 24" water line 167,050.00 WF0934457 / 001 Projects funded for FY 05-06 - WF0763380: Valley Park 102,050.00 WF0763380 / 001 CANCELLED Projects funded for FY 04-05 - WF0592456: Quality Inn Ponderosa $30,067.00 WF0592456 / 001 Waterwood - Central Park Lane Extension $3,670.00 WF0592456 / 002 Cotton - Dartmouth Dr Extension $6,174.55 WF0592456 / 003 CANCELLED Dove Crossing Subdivision, Phase I $14,336.00 WF0592456 / 004 Castlegate - Section 6 $5,784.00 WF0592456 / 005 Projects funded for FY 03-04 - WF0472461: Shenandoah Phase 9 $16,142.82 WF0472465 Westfield Village Phase 6 $8,324.60 WF0472458 Shenandoah Phase 8A $8,957.20 WF0477949 PROJECT DESCRIPTION/STATUS Shenandoah Phase 8A $8,957.20 WF0477949 Shenandoah Phase 12 & 13 $7,524.25 WF0579115 FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 100,000 $100,000 2009-10 100,000 $100,000 2010-11 100,000 $100,000 2011-12 100,000 $100,000 2012-13 100,000 $100,000 2013-14 100,000 $100,000 2014-15 100,000 $100,000 TOTAL $0 $0 $700,000 $0 $700,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually 204 WORK ORDER #: WF0995711 PROJECT: WATER RECLAIMED - IRRIGATION PROJECT #: WT0110 FUND: WATER CAPITAL PROJECTS PROJECT BUDGET: $3,606,730 PROJECT MANAGER: DONALD HARMON FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Jennifer Nations Design and construction of reclaimed water system to provide reclaimed water from Carters Creek Wastewater Treatment Plant for irrigation at Veterans Park and Athletic Complex. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 78,217 0 0 $78,217 2008-09 75,000 300,000 25,000 $400,000 2009-10 25,000 100,000 2,500,000 25,000 $2,650,000 2010-11 50,000 400,000 28,513 $478,513 2011-12 $0 2012-13 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR $ 2013-14 $0 2014-15 $0 TOTAL $100,000 $528,217 $2,900,000 $78,513 $3,606,730 Total Personnel $20,000 Supplies $26,000 Service $30,000 Capital $0 TOTAL $76,000$0 26,000 30,000 $76,000 20,000 OPERATING COSTS First Fiscal Year Annually 205 WORK ORDER #: WF0613546 PROJECT: WELLBORN WIDENING PROJECT #: WTWOC FUND: WATER CAPITAL PROJECTS PROJECT BUDGET: $4,250,000 PROJECT MANAGER: FRED SUROVIK FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services TXDOT will be widening Wellborn Road. Water lines from FM 2818 to SH 40 must be relocated outside future pavement areas. It is expected that partial reimbursement will be forthcoming from TxDOT on this utility project. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 2,175 221,087 3,085,980 $3,309,241 2008-09 75,000 $75,000 2009-10 57,000 808,759 $865,759 2010-11 $0 2011-12 $0 2012-13 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR This line has been completed from Harvey Mitchell Parkway to N Graham Rd. The segment from N Graham to WD Fitch has been delayed by property ownership / easement acquisition disputes. Additional funds are being requested due to construction cost escalation. The amount requested is based on the actual construction cost for initial segment of this line. 2013-14 $0 2014-15 $0 TOTAL $77,175 $278,087 $3,894,739 $0 $4,250,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 206 WORK ORDER #: WF0379197 PROJECT: BARRON ROAD WATER SERVICE PROJECT #: WTWOC EXTENSION FUND: WATER CAPITAL PROJECTS PROJECT BUDGET: $2,383,253 PROJECT MANAGER: STEPHEN MALDONADO, JR. FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 241,499 937,021 $1,178,520 2008-09 3,181 20,153 $23,334 2009-10 127,007 $127,007 2010-11 1,054,392 $1,054,392 2011-12 $0 2012-13 $0 2013-14 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR This project is to replace the water lines in the Barron Road area. The 18" water line along Barron Road from Victoria Road to Wellborn Road has been designed and constructed within previous phases of this project. The remaining portion of the project to be designed and constructed consists of the 12" water line along Barron Cut-Off and the 12" water line along Wellborn Road up to Southern Trace. 2013-14 $0 2014-15 $0 TOTAL $3,181 $388,659 $1,991,413 $0 $2,383,253 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 207 PROJECT: RAYMOND STOTZER WEST FUND(S): WORK ORDER NUMBERS & BUDGET: Water: WF1111167 $3,440,000 Wastewater: WF1111168 $3,788,000 Total Project Budget: $7,228,000 PROJECT MANAGER: Danielle Charbonnet FUNDING PROJECT SOURCES: CLIENT: Water Services - Fred Surovik Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 0 0 0 0 WATER CAPITAL PROJECTS WASTEWATER CAPITAL PROJECTS Long Term Debt/Utility Revnue PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR $0 This project will provide water and wastewater to areas along Raymond Stotzer West. The majority of this area was annexed in 1995 with the remainder of the area annexed in 2004. Development of Traditions in College Station will necessitate the extension of College Station water and wastewater lines. This project is also designated for a future wastewater lift station and force main near Easterwood Airport. We are currently in negotiations with an engineering company to determine a site for the lift station and a route for the water and wastewater lines. A more accurate cost estimate will be prepared once we obtain the location and route, but this planning level estimate is based on the following assumptions: • Extend the 18” DI water line approximately 9000 l.f. to Jones Road with 1 bore and steel casing • 6” force main approximately 15,000 l.f. with 2 bores and steel casing • 8” collection main approximately 10,000 l.f. with manholes spaced every 500 ft. • Lift station estimate is based on a comparison with the Creek Meadow project service area and the lift station cost Prior Years 0 0 0 0 0 2008-09 0 688,000 0 2,000 23000 2009-10 876,000 0 0 10,000 37000 2010-11 432,000 0 1,350,000 46,000 64000 2011-12 0 0 3,700,000 0 0 2012-13 0 0 0 0 0 2013-14 0 0 0 0 0 2014-15 0 0 0 0 0 PROJECT TOTAL $7,228,000$1,308,000 $688,000 $5,050,000 $58,000 $124,000 $0 $923,000 $1,892,000 $3,700,000 $0 $0 $0 $713,000 208 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 343,000 1,000 10,000 $354,000 2009-10 346,000 5,000 15,000 $366,000 2010-11 146,000 750,000 22,000 32,000 $950,000 2011-12 1,770,000 $1,770,000 2012-13 $0 2013-14 $0 2014-15 $0 Water Total $492,000 $343,000 $2,520,000 $28,000 $57,000 $3,440,000 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 345,000 1,000 13,000 $359,000 2009-10 530,000 5,000 22,000 $557,000 2010-11 286,000 600,000 24,000 32,000 $942,000 2011-12 1,930,000 $1,930,000 2012-13 $0 2013-14 $0 2014-15 $0 Wastewater Total $816,000 $345,000 $2,530,000 $30,000 $67,000 $3,788,000 First Fiscal Year Annually Total $688,000 $5,050,000 PROJECT: PROJECT CALENDAR OF EXPENDITURES BY FUND RAYMOND STOTZER WEST $58,000 $124,000 OPERATING COSTS $7,228,000PROJECT TOTAL $1,308,000 First Fiscal Year Annually Total Personnel 2,000 $2,000 Supplies 2,400 $2,400 Service 8,400 $8,400 Capital $0 TOTAL $0 $12,800 $12,800 209 PROJECT: SH 40 Water Line PROJECT #: TBD Graham Rd to Barron Rd PROJECT FUND: Water Capital Projects BUDGET: $2,586,000 PROJECT FUNDING MANAGER: Fred Surovik SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 25,000 $25,000 2010-11 200,000 $200,000 2011-12 21,000 2,340,000 $2,361,000 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $25,000 $221,000 $2,340,000 $0 $2,586,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS This segment of pipe will complete part of a 24" and larger conduit between Dowling Road Pump Station and Greens Prairie Elevated Storage Tank, which is needed for the proper operation of the distribution system. This portion will connect the 24" water line at Graham Rd to the 24" water line at Barron Rd. This project includes a bore across the Union Pacific Railroad Track / Wellborn Road and a bore across WD Fitch Parkway. Costs were derived from the actual costs for the 24" Welborn Widening line constructed in 2006 plus 10% escalation plus 20% for engineering. Distances were approximated from our mapping system. Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 210 PROJECT: SH 40 Water Line PROJECT #: TBD Iron Horse Way to Victoria Avenue PROJECT FUND: Water Capital Projects BUDGET: $643,000 PROJECT FUNDING MANAGER: Fred Surovik SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 90,000 $90,000 2011-12 20,000 533,000 $553,000 2012-13 $0 2013-14 $0 2014-15 $0 PROJECT DESCRIPTION/STATUS This segment of pipe is part of a 24" and larger conduit between Dowling Road Pump Station and Green Prairie Elevated Storage Tank, which is needed for the proper operation of the distribution system. This portion will connect the 24" water line at Iron Horse Way to the 24" water line at Victoria Avenue. Costs were derived from the actual costs for the 24" Welborn Widening line constructed in 2006 plus 10% escalation plus 20% for engineering. Distances were approximated from our mapping system. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2014-15 $0 TOTAL $0 $110,000 $533,000 $0 $643,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 211 WORK ORDER #: PROJECT: WATER RECLAIMED-IRRIGATION-PHASE II PROJECT #: TBD FUND: WATER CAPITAL PROJECTS PROJECT BUDGET: $1,475,000 PROJECT MANAGER: DONALD HARMON FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Jennifer Nations Design and construction of reclaimed water system to extend reclaimed water from Carters Creek Wastewater Treatment Plant for irrigation at Steve Beachy Park and Athletic Complex. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 40,000 185,000 200,000 25,000 $450,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2012-13 40,000 185,000 200,000 25,000 $450,000 2013-14 1,000,000 25,000 $1,025,000 2014-15 $0 TOTAL $40,000 $185,000 $1,200,000 $50,000 $1,475,000 Total Personnel $8,200 Supplies $11,000 Service $12,300 Capital $0 TOTAL $31,500$0 $31,500 11,000 12,300 OPERATING COSTS First Fiscal Year Annually 8,200 212 Home of Texas A&M University ® 213 PROJECT:FM 60 WIDENING WATER RELOCATION FUND(S): WORK ORDER NUMBERS & BUDGET: Water: TBD $2,478,000 Electric: TBD $1,580,000 Total Project Budget: $4,058,000 PROJECT MANAGER: Danielle Charbonnet FUNDING PROJECT SOURCES: CLIENT: Water Services - Ed Savage CSU - Tony Michalsky WATER CAPITAL PROJECTS ELECTRIC CAPITAL PROJECTS Long Term Debt/Utility Revenue PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Relocation of the water line for TxDOT's widening of University Drive East. Water lines will need to be relocated into an easement outside of the right-of-way. A set of electrical conduits and an overhead power line will also be relocated into the new easement, and new street lighting will be installed. The budget includes new ROW extending from HWY 6 to FM 158. The State should reimburse the City for most of the relocation costs and ROW costs for the portion of our existing easements that will be in the proposed State ROW. Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 0 0 0 0 2008-09 0 0 0 0 0 2009-10 580,000 0 0 7,000 9,000 2010-11 400,000 279,000 0 8,000 14,000 2011-12 0 0 2,672,000 26,000 63,000 2012-13 0 0 0 0 0 2013-14 0 0 0 0 0 2014-15 0 0 0 0 0 $0 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR $0 $0 $0 $596,000 PROJECT TOTAL $4,058,000$980,000 $279,000 $2,672,000 $41,000 $86,000 $701,000 $2,761,000 $0 214 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 290,000 0 5,000 4,500 $299,500 2010-11 200,000 230,000 5,000 8,500 $443,500 2011-12 1,692,000 13,000 30,000 $1,735,000 2012-13 $0 2013-14 $0 2014-15 $0 Water Total $490,000 $230,000 $1,692,000 $23,000 $43,000 $2,478,000 Electric Portion FISCAL YEAR PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 290,000 0 2,000 4,500 $296,500 2010-11 200,000 49,000 3,000 5,500 $257,500 2011-12 980,000 13,000 33,000 $1,026,000 2012-13 $0 2013-14 $0 2014-15 $0 Electric Total $490,000 $49,000 $980,000 $18,000 $43,000 $1,580,000 First Fiscal Year Annually Total PROJECT CALENDAR OF EXPENDITURES BY FUND OPERATING COSTS $279,000 $4,058,000PROJECT TOTAL $980,000 $2,672,000 $41,000 $86,000 PROJECT: FM 60 WIDENING WATER RELOCATION First Fiscal Year Annually Total Personnel 2,000 $2,000 Supplies 2,400 $2,400 Service 8,400 $8,400 Capital $0 TOTAL $0 $12,800 $12,800 215 PROJECT: ROCK PRAIRIE ROAD SOUTH OF CARTER LAKE (AREA 5) FUND(S): PROJECT NUMBERS & BUDGET: Water: WF0805789 $178,811 Wastewater: WF0805744 $221,000 Total Project Budget: $399,811 PROJECT MANAGER: FUNDING PROJECT SOURCES: CLIENT: Water Services (Fred Surovik) Project Total FISCAL YEAR LAND ENG CONSTR MISC OVERHEAD PROJECT TOTAL WATER CAPITAL PROJECTS WASTEWATER CAPITAL PROJECTS Long Term Debt/Utility Revenue Jeff Haeber Installation of waterline, lift station, force main, and gravity line to serve Area 5 (2003). Lift station costs are being shared with Area 6. This project also includes a 4" water line along Rock Prairie Road from W.D. Fitch to Lick Creek Wastewater Treatment Plant to loop the system. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR PROJECT DESCRIPTION/STATUS FISCAL YEAR LAND ENG.CONSTR.MISC.OVERHEAD PROJECT TOTAL Prior Years 0 44,694 136,353 0 0 2008-09 0 9,200 193,359 0 16,205 2009-10 0 0 0 0 0 2010-11 0 0 0 0 0 2011-12 0 0 0 0 0 2012-13 0 0 0 0 0 2013-14 0 0 0 0 0 2014-15 0 0 0 0 0 PROJECT TOTAL $399,811$0 $53,894 $329,712 $0 $0 $181,047 $218,764 $16,205 $0 $0 $0 $0 $0 216 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 22,591 136,353 0 $158,944 2008-09 1,700 16,695 1472 $19,867 2009-10 0$0 2010-11 0$0 2011-12 0$0 2012-13 0$0 2013-14 0$0 2014-15 0$0 Water Total $0 $24,291 $153,048 $0 $1,472 $178,811 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 22,103 0 0 $22,103 2008-09 7,500 176,664 14733 $198,897 2009-10 0$0 2010-11 0$0 2011-12 0$0 2012-13 0$0 2013-14 0$0 2014-15 0$0 Wastewater Total $0 $29,603 $176,664 $0 $14,733 $221,000 First Fiscal Year Annually Total Personnel $0 Supplies $0 $0 $16,205PROJECT TOTAL $0 $53,894 $329,712 OPERATING COSTS ROCK PRAIRIE ROAD SOUTH OF CARTER LAKE (AREA 5)PROJECT: PROJECT CALENDAR OF EXPENDITURES BY FUND $399,811 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 217 PROJECT: WILLIAM D FITCH EAST (AREA 6) FUND(S): PROJECT NUMBERS & BUDGET: Water: WF0805807 $672,000 Wastewater: WF0805756 $638,000 Total Project Budget: $1,310,000 PROJECT MANAGER: FUNDING PROJECT SOURCES: CLIENT: Water Services (Fred Surovik) PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Long Term Debt/Utility Revenue PROJECT DESCRIPTION/STATUS WATER CAPITAL PROJECTS WASTEWATER CAPITAL PROJECTS Jeff Haeber Installation of lift station, gravity line, and force main to serve Annexation Area 6 (2003). Installation of water line to serve Area 6 in City's CCN. In addition, possible 2007 annexation Area 2 to add to facility. This project formerly known as "Greens Prairie Road Corridor East (Area 6). Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 32,321 0 0 2008-09 0 33,000 840,723 0 69,898 2009-10 0 0 309,313 0 24,745 2010-11 0 0 0 0 0 2011-12 0 0 0 0 0 2012-13 0 0 0 0 0 2013-14 0 0 0 0 0 2014-15 0 0 0 0 0 $0 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR $94,643PROJECT TOTAL $1,310,000$0 $65,321 $1,150,036 $0 $0 $0 $0 $32,321 $334,058 $0 $943,621 218 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 3,942 0 0 $3,942 2008-09 8,000 301,259 24,741 $334,000 2009-10 309,313 24,745 $334,058 2010-11 0$0 2011-12 0$0 2012-13 0$0 2013-14 0$0 2014-15 0$0 Water Total $0 $11,942 $610,572 $0 $49,486 $672,000 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 28,379 0 0 $28,379 2008-09 25,000 539,464 45157 $609,621 2009-10 0$0 2010-11 0$0 2011-12 0$0 2012-13 0$0 2013-14 0$0 2014-15 0$0 Wastewater Total $0 $53,379 $539,464 $0 $45,157 $638,000 First Fiscal Year Annually Total PROJECT CALENDAR OF EXPENDITURES BY FUND $94,643 OPERATING COSTS $1,310,000 WILLIAM D FITCH EAST (AREA 6) $0 PROJECT: PROJECT TOTAL $0 $65,321 $1,150,036 First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 219 WORK PROJECT: ORDER #: TBD (AREA 3) PROJECT #: WTWOC FUND: PROJECT BUDGET: $95,000 PROJECT MANAGER: STEPHEN MALDONADO, JR. FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 15,000 80,000 $95,000 2013-14 $0 2014-15 $0 TOTAL $0 $15,000 $80,000 $0 $95,000 NANTUCKET EAST OF HARPERS FERRY WATER CAPITAL PROJECTS PROJECT DESCRIPTION PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR This project is for the installation of an 8" water line along Nantucket Drive East. This proposed project will serve the area annexed in 2002 that is currently a part of the Wellborn / College Station Water CCN dispute. Upon acquisition of this respective area's water CCN, this project can be designed and constructed. Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 220 RREEHHAABBIILLIITTAATTIIOONN PPRROOJJEECCTTSS 221 PROJECT: SOUTH KNOLL / THE GLADE REHAB FUND(S): PROJECT NUMBERS & BUDGET: Water: WF1044480 $1,725,000 Wastewater: WF1044485 $1,701,647 Total Project Budget: $3,426,647 PROJECT MANAGER: Edward McDonald FUNDING PROJECT SOURCES: CLIENT: Water Services: Ed Savage WATER CAPITAL PROJECTS WASTEWATER CAPITAL PROJECTS PROJECT DESCRIPTION/STATUS Long Term Debt/Utility Revenue Replacement of water and wastewater lines in area bounded by Haines, Southwest Parkway, Glade, and Langford. These water lines were identified by the Freese & Nichols Southside Water Study (July 2003). The wastewater lines in the Southside area were identified by the CDM Capacity/Infiltration/Inflow Management Project 2002-2003 Sanitary Sewer Evaluations. Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 268 0 0 2008-09 0 248,000 0 0 2009-10 0 116,000 2,582,279 100,100 2010-11 0 0 300,000 80,000 2011-12 0 0 0 0 2012-13 0 0 0 0 2013-14 0 0 0 0 2014-15 0 0 0 0 $0 PROJECT TOTAL $3,426,647$0 $364,268 $2,882,279 $180,100 $0 $0 $268 $248,000 $380,000 $0 $2,798,379 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 222 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 134 0 0 $134 2008-09 138,000 $138,000 2009-10 78,000 1,298,766 60,100 $1,436,866 2010-11 100,000 50,000 $150,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Water Total $0 $216,134 $1,398,766 $110,100 $1,725,000 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 134 0 0 $134 2008-09 110,000 $110,000 2009-10 38,000 1,283,513 40,000 $1,361,513 2010-11 200,000 30,000 $230,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Wastewater Total $0 $148,134 $1,483,513 $70,000 $1,701,647 First Fiscal Year Annually Total OPERATING COSTS $180,100 $3,426,647PROJECT TOTAL $0 $364,268 $2,882,279 SOUTH KNOLL / THE GLADE REHABPROJECT: PROJECT CALENDAR OF EXPENDITURES BY FUND First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 223 PROJECT: SOUTHWOOD 5 - 7 REHAB FUND(S): PROJECT NUMBERS & BUDGET: Water: WF1105425 $1,492,279 Wastewater: WF1105424 $1,809,221 Total Project Budget: $3,301,500 PROJECT MANAGER: Ed McDonald FUNDING PROJECT SOURCES: CLIENT: Water Services: Ed Savage WATER CAPITAL PROJECTS WASTEWATER CAPITAL PROJECTS Long Term Debt/Utility Revenue Replacement of water and wastewater lines in area bounded by Southwest Parkway, Harvey Mitchell, Welsh, and Shadowood. The water lines were identified by the Freese & Nichols Southside Water Study (July 2003). The wastewater lines were identified by the CDM Capacity/Infiltration/Inflow Management Project 2002-2003 Sanitary Sewer Evaluations. PROJECT DESCRIPTION/STATUS Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 2008-09 0 209,221 0 0 2009-10 0 218,659 2,376,258 210,000 2010-11 0 0 287,362 0 2011-12 0 0 0 0 2012-13 0 0 0 0 2013-14 0 0 0 0 2014-15 0 0 0 0 PROJECT TOTAL $3,301,500$0 $427,880 $2,663,620 $210,000 $0 $0 $209,221 $0 $0 $2,804,917 $287,362 $0 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 224 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 94,569 $94,569 2009-10 98,834 1,074,069 94,920 $1,267,823 2010-11 129,888 $129,888 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Water Total $0 $193,403 $1,203,956 $94,920 $1,492,279 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 114,652 $114,652 2009-10 119,825 1,302,189 115,080 $1,537,094 2010-11 157,474 $157,474 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 Wastewater Total $0 $234,477 $1,459,664 $115,080 $1,809,221 $210,000 $3,301,500PROJECT TOTAL $0 $427,880 $2,663,620 SOUTHWOOD 5 - 7 REHABPROJECT: PROJECT CALENDAR OF EXPENDITURES BY FUND OPERATING COSTS First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 OPERATING COSTS 225 PROJECT: EASTGATE REHAB FUND(S): PROJECT NUMBERS & BUDGET: Water: TBD $2,275,000 Wastewater: TBD $3,275,000 Total Project Budget: $5,550,000 PROJECT MANAGER: ED SAVAGE FUNDING PROJECT SOURCES: Long Term Debt/Utility Revenue CLIENT: Water Services WATER CAPITAL PROJECTS WASTEWATER CAPITAL PROJECTS PROJECT DESCRIPTION/STATUS This project consists of the replacement of water and wastewater lines in the area bounded by Lincoln Avenue to the north, Westover Drive to the east, Dominik Drive to the south, and Texas Avenue to the west. The sanitary sewer lines are in need of replacement due to an increase in service disruptions caused by deteriorating materials, shallow lines, and poor access. The sanitary sewer lines were identified by water services department personnel during training exercises for smoke testing that identifies inflow and infiltration. The water distribution lines are in need of replacement due to an increase in service disruptions caused by deteriorating materials and inadequate fire protection. Within certain areas of Eastgate's respective boundary, the existing water distribution does not currently meet the Unified Bryan/College Station Design Guidelines for fire protection because of existing smaller line sizes and inefficient fire hydrant spacing. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 2008-09 0 0 0 0 2009-10 0 0 0 0 2010-11 0 0 0 0 2011-12 0 450,000 0 0 2012-13 0 100,000 5,000,000 0 2013-14 0 0 0 0 2014-15 0 0 0 0 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR $0 $0 $5,550,000 $0 $0 $450,000 $5,100,000 $0 $0 PROJECT TOTAL $0 $550,000 $5,000,000 $0 226 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 225,000 $225,000 2012-13 50,000 2,000,000 $2,050,000 2013-14 $0 2014-15 $0 Water Total $0 $275,000 $2,000,000 $0 $2,275,000 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 225,000 $225,000 2012-13 50,000 3,000,000 $3,050,000 2013-14 $0 2014-15 $0 Wastewater Total $0 $275,000 $3,000,000 $0 $3,275,000 First Fiscal Year Annually Total Personnel $0 PROJECT: EASTGATE REHAB PROJECT CALENDAR OF EXPENDITURES BY FUND $5,550,000PROJECT TOTAL $0 $550,000 $5,000,000 $0 OPERATING COSTS Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 227 PROJECT: McCULLOCH REHAB FUND(S): PROJECT NUMBERS & BUDGET: Water: TBD $1,782,500 Wastewater: TBD $1,476,500 Total Project Budget: $3,259,000 PROJECT MANAGER: ED SAVAGE FUNDING PROJECT SOURCES: Long Term Debt/Utility Revenue CLIENT: Water Services WATER CAPITAL PROJECTS WASTEWATER CAPITAL PROJECTS Replacement of water and wastewater lines in area bounded by Holleman, Wellborn, Nevada, and Welsh. The water lines were identified by the Freese & Nichols Southside Water Study (July 2003). The wastewater lines were identified by the CDM Capacity/Infiltration/Inflow Management Project 2002-2003 Sanitary Sewer Evaluations. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR PROJECT DESCRIPTION/STATUS Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 2008-09 0 0 0 0 2009-10 0 0 0 0 2010-11 0 0 0 0 2011-12 0 0 0 0 2012-13 0 0 0 0 2013-14 0 184,000 1,513,200 0 2014-15 0 46,000 1,515,800 0 PROJECT TOTAL $3,259,000$0 $230,000 $3,029,000 $0 $0 $0 $0 $1,561,800 $1,697,200 $0 $0 $0 228 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 100,000 828,100 $928,100 2014-15 25,000 829,400 $854,400 Water Total $0 $125,000 $1,657,500 $0 $1,782,500 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 84,000 685,100 $769,100 2014-15 21,000 686,400 $707,400 Wastewater Total $0 $105,000 $1,371,500 $0 $1,476,500 First Fiscal Year Annually Total $0 $3,259,000PROJECT TOTAL $0 $230,000 $3,029,000 McCULLOCH REHABPROJECT: PROJECT CALENDAR OF EXPENDITURES BY FUND OPERATING COSTS y Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 229 PROJECT: NORTHGATE REHAB FUND(S): PROJECT NUMBERS & BUDGET: Water: TBD $1,500,000 Wastewater: TBD $1,750,000 Total Project Budget: $3,250,000 PROJECT MANAGER: ED SAVAGE FUNDING PROJECT SOURCES: CLIENT: Water Services PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR PROJECT DESCRIPTION/STATUS This project consists of the replacement of water and wastewater lines in the Northgate area. A majority of the water distribution lines and sanitary sewer collection lines have been replaced under recent northgate capital improvement projects, however, there are still lines in the area that are in need of rehabilitation. The remaining sanitary sewer lines are in need of replacement due to an increase in service disruptions caused by deteriorating materials, shallow lines, and poor access. The sanitary sewer lines were identified by water services department personnel during routine camera inspections. The remaining water distribution lines are in need of replacement due to an increase in service disruptions caused by deteriorating materials and inadequate fire protection caused by smaller line sizes and inadequate fire hydrant spacing. Long Term Debt/Utility Revenue WATER CAPITAL PROJECTS WASTEWATER CAPITAL PROJECTS Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 2008-09 0 0 0 0 2009-10 0 0 0 0 2010-11 0 0 0 0 2011-12 0 0 0 0 2012-13 0 550,000 0 0 2013-14 0 0 2,700,000 0 2014-15 0 0 0 0 PROJECT TOTAL $0 $550,000 $2,700,000 $0 $0 $3,250,000 $0 $0 $0 $550,000 $2,700,000 $0 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR $0 230 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 275,000 $275,000 2013-14 1,225,000 $1,225,000 2014-15 $0 Water Total $0 $275,000 $1,225,000 $0 $1,500,000 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 275,000 $275,000 2013-14 1,475,000 $1,475,000 2014-15 $0 Wastewater Total $0 $275,000 $1,475,000 $0 $1,750,000 First Fiscal Year Annually Total Personnel $0 $0 $550,000 $2,700,000 $0 OPERATING COSTS $3,250,000PROJECT TOTAL PROJECT: NORTHGATE REHAB PROJECT CALENDAR OF EXPENDITURES BY FUND Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 231 PROJECT: THE KNOLL REHAB FUND(S): PROJECT NUMBERS & BUDGET: Water: TBD $1,489,200 Wastewater: TBD $1,654,600 Total Project Budget: $3,143,800 PROJECT MANAGER: ED SAVAGE FUNDING PROJECT SOURCES: CLIENT: Water Services Water Wastewater PROJECT DESCRIPTION/STATUS Council Award of Construction Contract: Spring 2011 Council Award of Engineering Contract: Fall 2010 Council Award of Construction Contract: Fall 2011 Council Award of Engineering Contract: Fall 2010 Long Term Debt/Utility Revenue WATER CAPITAL PROJECTS WASTEWATER CAPITAL PROJECTS Replacement of water and wastewater lines in area bounded by Haines, Glade, Holleman, and Taurus. The water lines were identified by the Freese & Nichols Southside Water Study (July 2003). The wastewater lines were identified by the CDM Capacity/Infiltration/Inflow Management Project 2002-2003 Sanitary Sewer Evaluations. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Project Total FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 2008-09 0 0 0 0 2009-10 0 0 0 0 2010-11 0 0 0 0 2011-12 0 0 0 0 2012-13 0 0 0 0 2013-14 0 180,000 1,459,900 0 2014-15 0 44,000 1,459,900 0 $1,503,900 PROJECT TOTAL $3,143,800$0 $224,000 $2,919,800 $0 $0 $0 $0 $0 $0 $0 $1,639,900 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 232 Water Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 85,000 691,600 $776,600 2014-15 21,000 691,600 $712,600 Water Total $0 $106,000 $1,383,200 $0 $1,489,200 Wastewater Portion FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 95,000 768,300 $863,300 2014-15 23,000 768,300 $791,300 Wastewater Total $0 $118,000 $1,536,600 $0 $1,654,600 First Fiscal Year Annually Total $224,000 $2,919,800 OPERATING COSTS $0 $3,143,800PROJECT TOTAL $0 THE KNOLL REHABPROJECT: PROJECT CALENDAR OF EXPENDITURES BY FUND First Fiscal Year Annually Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 $0 $0 233 Home of Texas A&M University ® 234 WWAASSTTEEWWAATTEERR CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000099--22001100 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22001144--22001155 235 WASTEWATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 11/12/09 4:07 PM FY10 PROJECT REVISED APPROVED PROJECT WORK REQUEST BUDGET APPROPRIATIONS FY08-09 FY09-10 NUMBER NUMBER AMOUNT THROUGH FY08 APPROPRIATIONS APPROPRIATIONS BEGINNING FUND BALANCE:3,415,150$ 522,649$ ADDITIONAL RESOURCES: UTILITY REVENUE BONDS/CERTIFICATES OF OBLIGATION 3,750,000$ 7,600,000$ INTEREST ON INVESTMENTS 14,000 25,000 TRANSFERS FROM OPERATIONS 3,750,000 2,700,000 INTERGOVERNMENTAL 799,539 - OTHER - - SUBTOTAL ADDITIONAL RESOURCES 8,313,539$ 10,325,000$ TOTAL RESOURCES AVAILABLE 11,728,689$ 10,847,649$ COLLECTION PROJECTS COLLECTION PLANT - SCWOC OVERSIZE PARTICIPATION - TBD 100,000 - 100,000 100,000 RAYMOND STOTZER WEST - WF1111168 3,788,000 1,978,000 - - KOPPE BRIDGE LIFT STATION WF1097963 450,000 100,000 300,000 50,000 WESTMINSTER SEWER LINE - WF0786101 359,314 27,000 - 332,314 NANTUCKET GRAVITY SEWER WF1094676 516,000 25,000 100,000 391,000 LICK CREEK PARALLEL TRUNK LINE - PHASE I WF0912284 2,825,000 25,000 317,500 117,881 VICTORIA AVENUE EXTENSION - WF1158560 25,556 - 5,000 20,556 BARRON ROAD WIDENING PH II - TBD 100,000 - - 100,000 NORTHEAST SEWER TRUNKLINE TBD 2,830,000 - - - LICK CREEK IMPACT FEE LINE TBD 1,144,000 - - - LICK CREEK PARALLEL TRUNKLINE PH II - TBD 3,896,000 - - - ANNEXATION PROJECTS ROCK P RD S OF CARTER LAKE (AREA 5) - WF0805744 221,000 221,000 - - WILLIAM D FITCH EAST (AREA 6) - WF0805756 638,000 638,000 - - CLOSED PROJECTS -- SUBTOTAL 822,500$ 1,111,751$ REHABILITATION PROJECTS: EMERALD PKWY / BENT OAK - WF0626151 297,064 150,006 147,058 - BARRON ROAD REHAB - WF0654332 10,850 100,000 - - BEE CREEK PH IV & V WASTEWATER TBD 300,000 300,000 - - TAUBER & STASNEY REHAB - WF0625893 543,129 120,000 406,671 16,458 COLLEGE PARK/BREEZY HEIGHTS - WF0595926 1,305,000 1,305,000 - - SOUTH KNOLL / THE GLADE - WF1044485 1,701,647 634,200 581,200 486,247 SOUTHWOOD 5-7 - WF1105424 1,809,221 - 1,794,000 15,221 EASTGATE REHAB TBD 3,275,000 - - - MCCULLOCH REHAB TBD 1,476,500 - - - NORTHGATE REHAB TBD 1,750,000 - - - THE KNOLL REHAB TBD 1,654,600 - - - CLOSED PROJECTS SUBTOTAL 2,928,929$ 517,926$ 236 WASTEWATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED THROUGH FY07 FY 07-08 FY 08-09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 3,749,030$ 3,415,150$ 522,649$ 633,591$ 196,017$ 214,098$ 350,398$ 138,798$ 2,200,000$ -$ 7,600,000$ 8,500,000$ 9,250,000$ 5,100,000$ 6,750,000$ 5,500,000$ 52,192 50,000 25,000 7,900 8,700 11,300 10,800 10,800 1,000,000 2,250,000 2,700,000 300,000 1,500,000 1,400,000 1,550,000 1,150,000 734,997 - - - - - - - 880,311 - - - - - - 3,987,189$ 3,180,311$ 10,325,000$ 8,807,900$ 10,758,700$ 6,511,300$ 8,310,800$ 6,660,800$ 7,736,219$ 6,595,460$ 10,847,649$ 9,441,491$ 10,954,717$ 6,725,398$ 8,661,198$ 6,799,598$ - - 100,000 100,000 100,000 100,000 100,000 100,000 100,000 - - 359,000 557,000 942,000 1,930,000 - - - - 150,000 300,000 - - - - - 22,743 1,781 27,000 307,790 - - - - - - 7,062 33,938 475,000 - - - - - - 10,381 - 300,000 2,150,000 364,619 - - - - - 2,175 23,381 - - - - - - - 100,000 - - - - - - - - - - 330,000 2,500,000 - - - - - - - - - 1,144,000 - - - - - 3,896,000 - - - - - 22,103 - 198,897 - - - - - - 28,379 - 609,621 - - - - - - 496,473 85,690 73,225$ 515,697$ 1,566,321$ 2,163,171$ 3,192,000$ 6,290,619$ 430,000$ 2,600,000$ 1,244,000$ 5,970 - - 291,094 - - - - - - - 10,850 - - - - - - - - - 300,000 - - - - - 19,489 - 261,820 261,820 - - - - - 85,797 6,225 1,212,978 - - - - - - - 134 110,000 1,361,513 230,000 - - - - - - 114,652 1,537,094 157,474 - - - - - - - 225,000 3,050,000 - - - - - - - - 769,100 707,400 - - - - 275,000 1,475,000 - - - - - - - 863,300 791,300 - 788,078 180,016 111,256$ 794,436$ 1,890,316$ 3,751,521$ 387,474$ 225,000$ 3,325,000$ 3,107,400$ 1,498,700$ 237 WASTEWATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 11/12/09 4:07 PM FY10 PROJECT REVISED APPROVED PROJECT WORK REQUEST BUDGET APPROPRIATIONS FY08-09 FY09-10 NUMBER NUMBER AMOUNT THROUGH FY08 APPROPRIATIONS APPROPRIATIONS TREATMENT & DISPOSAL PROJECTS TREATMENT & DISPOSAL/PUMPING PLANT - SPWOC CARTERS CREEK CLARIFIER IMPROVEMENTS WF1104545 372,000 205,000 167,000 - CARTERS CREEK HEADWORKS IMP WF1223116 2,500,000 125,000 - 375,000 CARTERS CREEK SERVICE WATER IMP WF0930104 447,000 450,000 - - LICK CREEK CLARIFIER CATWALKS WF1042497 387,500 200,000 50,000 137,500 - SLUDGE TREATMENT & DISPOSAL/PUMPING PLANT - SSWOC - LICK CREEK CENTRIFUGE IMPROVEMENTS WF1142617 400,000 50,000 - 350,000 LICK CREEK SLUDGE HOLDING TANK IMP WF1142618 500,000 97,514 - 402,486 CARTERS CREEK ATAD IMPROVEMENTS WF1104547 914,000 - 900,000 14,000 CARTERS CREEK BAR SCREENS WF1136522 50,000 50,000 - - CC GRAVITY THICKENER - WF1104543 281,000 - 281,000 - LICK CREEK RETURN ACTIVATED SLUDGE MODIFICATIONS WF1142623 250,000 - 60,000 190,000 CC CENTRIFUGE IMPROVEMENTS TBD 2,178,000 - - - CC BLOWER BLDGS IMPROVEMENTS TBD 420,000 - - - COLLEGE STATION SLUDGE FACILITY TBD 5,500,000 - - SEWER GENERAL PLANT - SGWOC SCADA REPLACEMENT - WF0742950 445,340 362,000 - 83,340 CARTERS CREEK FUELING STATION TBD 150,000 - - - CARTERS CREEK LAB AND SCADA BUILDING WF1129844 940,000 - 100,000 840,000 CARTER CREEK PROCESS CONTROL IMPROVEMENTS WF1104553 330,000 35,000 295,000 - LICK CREEK PROCESS CONTROL IMPROVEMENTS WF1142624 203,000 - 105,500 97,500 SCADA - NEW LIFT STATIONS TBD 240,000 - - 80,000 REMOTE PLANT SECURITY - WF1219655 300,000 - - 300,000 LAND ACQUISITION - CCWWTP TBD 2,000,000 - - - LAND ACQUISITION - LCWWTP - TBD 2,000,000 - - - CC FIBER RING TBD 450,000 - - 120,000 LICK CREEK GENERATOR REPLACEMENT TBD 700,000 - - - CC ELECTRICAL IMPROVEMENTS - TBD 1,300,000 - - - CCWWTP MAINTENANCE BLDG TBD 330,000 - - - CC EQUIPMENT SHED TBD 480,000 - - - UTILITY SERVICE CENTER RENOVATIONS TBD 348,000 - - - CLOSED PROJECTS 55,431,721 SUBTOTAL 1,958,500$ 2,989,826$ CAPITAL PROJECTS CONTINGENCY TBD - 150,000 150,000 CAPITAL PROJECTS SUBTOTAL 110,763,442 5,859,929$ 4,769,503$ (46,862,972) GENERAL AND ADMINISTRATIVE 82,227 77,890 DEBT ISSUANCE COST 37,500 30,000 TOTAL EXPENDITURES 5,979,656$ 4,877,393$ MEASUREMENT FOCUS ADJUSTMENT ENDING FUND BALANCE:5,749,033$ 5,970,256$ 238 WASTEWATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 PROJECT EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED THROUGH FY07 FY 07-08 FY 08-09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 - - 372,000 - - - - - - - - - 500,000 2,000,000 - - - - - - 447,000 - - - - - - - 1,806 75,694 310,000 - - - - - - - 36,720 363,280 - - - - - - - 100,000 400,000 - - - - - - - 214,000 600,000 100,000 - - - - - - 50,000 - - - - - - - - 281,000 - - - - - - - - 50,000 200,000 - - - - - - - - - 1,263,000 915,000 - - - - - - - - - 250,000 170,000 - - - - - - 150,000 2,350,000 3,000,000 - - 34,144 81,000 175,000 155,196 - - - - - - - - - 150,000 - - - - - - 50,000 890,000 - - - - - - - 330,000 - - - - - - - 80,000 123,000 - - - - - - - - 80,000 80,000 80,000 - - - - - - 300,000 - - - - - - - - - - 2,000,000 - - - - - - - - - 2,000,000 - - - - - 120,000 - 330,000 - - - - - - - - - - 70,000 630,000 - - - - 750,000 550,000 - - - - - - - 240,000 90,000 - - - - - - - 480,000 - - - - - - - - 348,000 - - - - - 2,278,082 122,533 34,144$ 2,360,888$ 2,383,947$ 4,041,476$ 5,411,000$ 3,965,000$ 2,400,000$ 2,590,000$ 3,630,000$ - - 150,000 150,000 150,000 150,000 150,000 150,000 150,000 218,625$ 3,671,021$ 5,990,584$ 10,106,168$ 9,140,474$ 10,630,619$ 6,305,000$ 8,447,400$ 6,522,700$ 290,418 82,227 77,890 50,000 50,000 50,000 50,000 50,000 (6,583) - 30,000 55,000 60,000 20,000 25,000 20,000 3,954,856$ 6,072,811$ 10,214,058$ 9,245,474$ 10,740,619$ 6,375,000$ 8,522,400$ 6,592,700$ (366,213)$ 3,415,150$ 522,649$ 633,591$ 196,017$ 214,098$ 350,398$ 138,798$ 206,898$ 239 CCOOLLLLEECCTTIIOONN 240 WORK ORDER #: TBD PROJECT: OVERSIZE PARTICIPATION PROJECT #: SCWOC WASTEWATER LINES FUND: PROJECT BUDGET:ANNUAL PROJECT MANAGER:STEPHEN MALDONADO FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services These funds are available for oversize participation with developers in the construction of sewer lines above the minimum size needed to serve the development. This allows lines to be built large enough to meet future development without having to go back and install larger lines. Projects are identified based on development activity. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 100,000 $100,000 2009-10 100,000 $100,000 2010-11 100,000 $100,000 2011-12 100,000 $100,000 2012-13 100,000 $100,000 2013-14 100,000 $100,000 2014-15 100,000 $100,000 TOTAL $0 $0 $700,000 $0 $700,000 WASTEWATER CAPITAL PROJECTS PROJECT DESCRIPTION PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 241 WORK ORDER #: WF1097963 PROJECT: KOPPE BRIDGE LIFT STATION PROJECT #: SCWOC FUND: WASTEWATER CAPITAL PROJECTS PROJECT BUDGET: $450,000 PROJECT MANAGER: DONALD HARMON FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Stephen Maldonado FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 75,000 50,000 25,000 $150,000 2009-10 275,000 25,000 $300,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $75,000 $50,000 $275,000 $50,000 $450,000 PROJECT DESCRIPTION PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS This project provides for the construction of a lift station and force main sewer from the Meadow Creek subdivision to the Castlegate subdivision. This estimate is based on appraised land values and an engineer's estimate of the construction cost with a 20% contingency. Total Personnel $0 Supplies $0 Service $11,000 Capital $0 TOTAL $11,000 OPERATING COSTS First Fiscal Year Annually $11,000$0 11,000 242 WORK ORDER #: WF0786101 PROJECT: Westminster Sewer Line PROJECT #: SCWOC FUND: WASTEWATER CAPITAL PROJECTS PROJECT BUDGET: $359,314 PROJECT MANAGER: Daniel Beamon FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services: Stephen Maldonado, Jr. TxDOT will be widening Wellborn Road from FM 2818 down to near Barron Road. A gravity sewer line will be designed to serve properties along Wellborn Road and Barron Road. The land acquisition portion of the project was transferred from West Park Wastewater Project which came in under budget. Staff considers this proposed sanitary sewer line to be of great priority, because customers along Wellborn Road are served by on-site sewerage systems. These on-site systems present potential conflicts between the proposed water line included in the Capital Improvement Project entitled "Barron Road Water Service Extension". Delays have been encountered acquiring land acquisition. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 2 24,522 0 0 $24,524 2008-09 19,998 7,002 $27,000 2009-10 7,790 300,000 $307,790 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $20 000 $39 314 $300 000 $0 $359 314 PROJECT DESCRIPTION PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $20,000 $39,314 $300,000 $0 $359,314 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 243 WORK ORDER #: WF1094676 PROJECT: NANTUCKET GRAVITY SEWER PROJECT #: SCWOC FUND: WASTEWATER CAPITAL PROJECTS PROJECT BUDGET: $516,000 PROJECT MANAGER: Daniel Beamon FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services: Stephen Maldonado, Jr. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 7,062 0 0 $7,062 2008-09 33,938 $33,938 2009-10 475,000 $475,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 PROJECT DESCRIPTION PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR This work was previously included with the Project titled "Nantucket Lift Station". The work has been seperated to clarifiy the expenditures. This project originally consisted of the removal of the existing Nantucket Lift Station and force main to be replaced with gravity sanitary sewer. During design, it was determined that the gravity sewer line would require a horizontal bore under State Hwy 6 in order to maintain proper gravity sewer grades, therefore, the overall scope and budget of the project have since been updated. This project needs to be completed as promptly as possible as installing the gravity line represents a better value for our ratepayers. 2014-15 $0 TOTAL $0 $41,000 $475,000 $0 $516,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $200$0 200 $200 OPERATING COSTS First Fiscal Year Annually 244 WORK ORDER #: WF0912284 PROJECT: LICK CREEK PARALLEL TRUNKLINE PROJECT #: SCWOC Phase 1 FUND: WASTEWATER CAPITAL PROJECTS PROJECT BUDGET: $2,825,000 PROJECT MANAGER: STEPHEN MALDONADO, JR.FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 10,381 0 0 $10,381 2008-09 $0 2009-10 300,000 $300,000 2010-11 150,000 2,000,000 $2,150,000 2011-12 364,619 $364,619 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $460,381 $2,364,619 $0 $2,825,000 Total PROJECT DESCRIPTION PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually This project is for the installation of a trunkline in Lick Creek Park from Pebble Creek Subdivision to Lick Creek Wastewater Plant. This project phase will parallel an existing 18" sewer line, with possible design to ultimately install a 36"- 42" line. The original trunkline serves all areas south of Barron Road and was installed as an 18" line to serve Pebble Creek. Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 First Fiscal Year Annually 245 WORK ORDER #: TBD PROJECT: NORTHEAST SEWER TRUNKLINE PROJECT #: SCWOC FUND: WASTEWATER CAPITAL PROJECTS PROJECT BUDGET: $2,830,000 PROJECT FUNDING MANAGER: ED SAVAGE SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 $0 $ PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR The Northeast Sewer trunkline currently serves areas West of SH 6 including Northgate, Hensel Park, Chimney Hills, and the Gateway development. This trunkline also serves areas East of SH 6 spanning from FM 60 south to Carters Creek Wastewater Treatment Plant. Much of the existing trunkline was constructed in 1973 and spans along Carters Creek from SH 6 to the Carters Creek Wastewater Treatment Plant. This project will replace the existing line with a larger diameter line to increase capacity while also relocating the proposed line further away from the wandering creek bank. This trunkline replacement and relocation is necessary to proactively prevent surcharge events, emergency failures caused by erosion, and possible fines from TCEQ. 2011-12 $0 2012-13 150,000 180,000 $330,000 2013-14 2500000 $2,500,000 2014-15 $0 TOTAL $150,000 $180,000 $2,500,000 $0 $2,830,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 246 WORK ORDER #: TBD PROJECT: LICK CREEK IMPACT FEE LINE PROJECT #: SCWOC FUND: WASTEWATER CAPITAL PROJECTS PROJECT BUDGET: $1,144,000 PROJECT MANAGER: STEPHEN MALDONADO FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 144,000 1,000,000 $1,144,000 TOTAL $0 $144,000 $1,000,000 $0 $1,144,000 Total Personnel $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Installation of wastewater lines in area bounded by Rock Prairie Road, WD Fitch, and SH 6. Extends Spring Creek Corporate Campus Phase I sewer line to the northern property line of the Business Park. Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 247 WORK ORDER #: TBD PROJECT: LICK CREEK PARALLEL TRUNKLINE PROJECT #: SCWOC Phase 2 FUND: WASTEWATER CAPITAL PROJECTS PROJECT BUDGET: $3,896,000 PROJECT MANAGER: STEPHEN MALDONADO, JR.FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 500,000 3,396,000 $3,896,000 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $500,000 $3,396,000 $0 $3,896,000 Total PROJECT DESCRIPTION PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Installation of a trunkline from north of WD Fitch to the southern boundary of Pebble Creek Subdivision (northern boundary line of Lick Creek Park). This project phase will parallel an existing 18" sewer line, with possible design to install ultimate 42" line. This original trunkline serves everything south of Barron Road and was installed as an 18" line to serve Pebble Creek. Pebble Creek Development has expressed an interest to possibly participate in a development agreement at a future date. Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 First Fiscal Year Annually 248 RREEHHAABBIILLIITTAATTIIOONN PPRROOJJEECCTTSS 249 WORK ORDER #: WF0626151 PROJECT: PROJECT #: SCWOC FUND: PROJECT BUDGET: $297,064 PROJECT MANAGER: ED SAVAGE FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services New alignment of approximately 1,000' of 24" wastewater collection line will be installed to provide better flow hydraulics and will have sealed and bolted manholes. This construction will correct poor flow conveyance through the particular sewer segment and high levels of infiltration and inflow in the sewer basin upstream of the area. This project is development driven and CSU will be working with the land owner to construct. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 1,088 4,883 0 0 $5,970 2008-09 $0 2009-10 291,094 $291,094 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $1,088 $4,883 $291,094 $0 $297,064 WASTEWATER CAPITAL PROJECTS EMERALD PARKWAY / BENT OAK PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel $9,325 Supplies $0 Service $0 Capital $0 TOTAL $9,325$6,200 $3,125 $3,125 OPERATING COSTS First Fiscal Year Annually $6,200 250 TTRREEAATTMMEENNTT 251 WORK ORDER #: WF1104545 PROJECT: PROJECT #: SPWOC (CC MISC IMPROVEMENTS) FUND: PROJECT BUDGET: $372,000 PROJECT MANAGER: PHILIP BARGAS FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Doug Wallace FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 22,000 350,000 $372,000 2009-10 $0 CARTERS CREEK CLARIFIER IMPROVEMENTS Provide funds for improvements to the Carters Creek Wastwater Ttrstment Plant Clarifiers. This project has been bundled with the Service Water Improvements, the ATAD Improvements, Gravity Thickener Improvements, and Process Control Improvements to provide a more attractive bid package. Improvements include: PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR WASTEWATER CAPITAL PROJECTS * Replace clarifier rake drives and walkway surfaces on Clarifiers 2B and 3B * Install safety rails around Clarifiers 2B and 3B. * Engineering to replace clarifier rake drives and walkway surfaces on Clarifiers 2B and 3B * Painting all equipment on clarifiers 2A, 2B, 3A, and 3B * Install an operating platform and replace the walkway surfaces on Clarifiers 2B and 3B $ 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $22,000 $350,000 $0 $372,000 Total Personnel $1,500 Supplies $200 Service $1,000 Capital $0 TOTAL $2,700$0 $200 $1,000 $0 $2,700 $1,500 OPERATING COSTS First Fiscal Year Annually 252 WORK ORDER #: WF1223116 PROJECT: PROJECT #: SPWOC FUND: PROJECT BUDGET: $2,500,000 PROJECT MANAGER:Philip Bargas FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services: Doug Wallace FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 500,000 $500,000 2010-11 2,000,000 $2,000,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $500,000 $2,000,000 $0 $2,500,000 CARTERS CREEK HEADWORKS IMPROVEMENTS Provide funds for engineering and construction to make the following improvements to the Carters Creek Wastewater Treatment Plant Headworks. Replace the motorized bar screens with more efficient step screens. Design, construct, and install more efficient replacements for the current grit bridges. Overhaul the shaftless screw conveyor. Install mixers in the wells at the end of the grit bridges. Project stays mainly the same, except that replacement of the shaftless screw conveyor may be required. PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR WASTEWATER CAPITAL PROJECTS TOTAL $0 $500,000 $2,000,000 $0 $2,500,000 Total Personnel $2,500 Supplies $1,000 Service $80,000 Capital $0 TOTAL $83,500 OPERATING COSTS First Fiscal Year Annually $2,500 $0 $1,000 $80,000 $83,500 253 WORK ORDER #: WF0930104 PROJECT: PROJECT #: SPWOC (CC MISC IMPROVEMENTS) FUND: PROJECT BUDGET: $447,000 PROJECT MANAGER: PHILIP BARGAS FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Doug Wallace FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 CARTERS CREEK SERVICE WATER IMPROVEMENTS PROJECT DESCRIPTION/STATUS Provide funds for improvements to Carters Creek Service Water System. This project has been bundled with the ATAD Improvements, Clarifier Improvements, Gravity Thickener Improvements, and Process Control Improvements to provide a more attractive bid package. Aspects of the project are proposed to include: * Replace the current service water screen with a self-cleaning model * Install complete bleach injection system with a bulk liquid bleach tank * Replace the two service water pumps with more efficient model * An above ground level PVC injection point WASTEWATER CAPITAL PROJECTS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR * An improved bleach pump * A cover for the entire system * A paved drive for the bulk delivery of bleach 2008-09 47,000 400,000 $447,000 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $47,000 $400,000 $0 $447,000 Total Personnel $2,000 Supplies $20,000 Service $6,000 Capital $0 TOTAL $28,000$0 20,000 6,000 $28,000 OPERATING COSTS First Fiscal Year Annually 2,000 254 WORK ORDER #: WF1042497 PROJECT: LICK CREEK CLARIFIER CATWALKS PROJECT #: SPWOC (LICK CREEK MISC IMPROVEMENTS) FUND: PROJECT BUDGET: $387,500 PROJECT MANAGER: PHILIP BARGAS FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Doug Wallace FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 1,806 0 0 $1,806 2008-09 75,694 0 $75,694 2009-10 310,000 $310,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $77,500 $310,000 $0 $387,500 WASTEWATER CAPITAL PROJECTS PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Provide funds for constructing catwalks around the Lick Creek Wastewater Treatment Plant Clarifiers. The catwalks will provide safe access for the operators to operate and maintain the clarifiers. This is an important safety and opertional project. This project has been bundled together with the Sludge Holding Tank Improvements, Return Activated Sludge Modifications, Centrifuge Improvements, and the Process Control Improvements to provide a more attractive bid package. TOTAL $0 $77,500 $310,000 $0 $387,500 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 0 0 $0 $0 OPERATING COSTS First Fiscal Year Annually 255 WORK ORDER #: WF1142617 PROJECT: PROJECT #: SSWOC (LICK CREEK MISC IMPROVEMENTS) FUND: PROJECT BUDGET: $400,000 PROJECT MANAGER: Philip Bargas FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Doug Wallace FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 34,000 2,720 $36,720 2009-10 336,370 26,910 $363,280 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $34,000 $336,370 $0 $29,630 $400,000 LICK CREEK CENTRIFUGE IMPROVEMENTS Provide funds for improvements to Lick Creek WWTP Centrifuge. These include installing a larger sludge discharge hopper, a sludge conveyor replacing the current Moyno pump, and a work platform around the centrifuge. This project has been bundled together with the Sludge Holding Tank Improvements, Return Activated Sludge Modifications, Clarifier Catwalk Improvements, and the Process Control Improvements to provide a more attractive bid package. PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR WASTEWATER CAPITAL PROJECTS TOTAL $0 $34,000 $336,370 $0 $29,630 $400,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 256 WORK ORDER #: WF1142618 PROJECT: PROJECT #: SSWOC (LICK CREEK MISC IMPROVEMENTS) FUND: PROJECT BUDGET: $500,000 PROJECT MANAGER:Philip Bargas FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Doug Wallace FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 100,000 $100,000 2009-10 400,000 $400,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 LICK CREEK SLUDGE HOLDING TANK IMPROVEMENTS Provide funds to expand the size of the Waste Sludge Holding Tank at Lick Creek Wastewater Treatment Plant. The construction cost include up-sizing one positive displacement blower to aerate the increased volume of sludge in the holding tank in case two of the current blowers cannot provide the correct amount of aeration. This project has been bundled together with the Centrifuge Improvements, Return Activated Sludge Modifications, Clarifier Catwalk Improvements, and the Process Control Improvements to provide a more attractive bid package. PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR WASTEWATER CAPITAL PROJECTS $ TOTAL $0 $100,000 $400,000 $0 $500,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 257 WORK CARTERS CREEK ATAD ORDER #: WF1104547 PROJECT: IMPROVEMENTS PROJECT #: SSWOC (CC MISC IMPROVEMENTS) FUND: PROJECT BUDGET: $914,000 PROJECT MANAGER: Philip Bargas FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Doug Wallace FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 14,000 200,000 $214,000 2009-10 600,000 $600,000 2010-11 100,000 $100,000 2011-12 $0 2012-13 $0 Provide funds for constructing catwalks around the Carters Creek ATAD reactors, replacing the ATAD motor operated valves, and rehabilitating the ATAD cooling water system. This project has been bundled with the Clarifier Improvements, Service Water Improvements, Gravity Thickener Improvements, and the Process Control Improvements to provide a more attractive bid package. Improvements include: * Rehabilitate the cooling water system to better cool Reactor 3 and to transfer heat to Reactors 1 and 2 * Install catwalks to minimize the need for operators to walk across the tops of the reactors to perform day-to- day tasks, increasing safety for the operators and minimizing wear on the insulation and tops of the reactors. * Replace the motor operated valves with more efficient ones. PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR WASTEWATER CAPITAL PROJECTS 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $14,000 $900,000 $0 $914,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 258 WORK ORDER #: WF1136522 PROJECT: CARTERS CREEK BAR SCREENS PROJECT #: SPWOC FUND: PROJECT BUDGET: $50,000 PROJECT MANAGER:FRED SUROVIK FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 50,000 $50,000 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $50,000 $0 $50,000 This project is for the rehabilitation of bar screens at the Carters Creek Wastewater Treatment Plant, which are nearing the end of their useful service life. However, staff has elected to perform a major overhaul to extend the service life and defer the implementation of a larger Capital Improvement Project to replace these bar screens and other critical wastewater treatment equipment. This overhaul will be performed in the 2008-09 budget year, and is not expected to exceed the budgeted amount. The contract to perform this work is being negotiated. WASTEWATER CAPITAL PROJECTS PROJECT DESCRIPTION/STATUS OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 First Fiscal Year Annually $0 $0 259 WORK ORDER #: WF1104543 PROJECT:CARTERS CREEK GRAVITY THICKENER PROJECT #: SSWOC (CC MISC IMPROVEMENTS) FUND: PROJECT BUDGET: $281,000 PROJECT MANAGER: PHILIP BARGAS FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Doug Wallace FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 16,000 265,000 $281,000 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $16,000 $265,000 $0 $281,000 WASTEWATER CAPITAL PROJECTS PROJECT DESCRIPTION/STATUS Provide funds for improvements to the Carters Creek Wastwater Ttreatment Plant Gravity Thickener. This project has been bundled with the Service Water Improvements, ATAD Improvements, Clarifier Improvements, and Process Control Improvements to provide a more attractive bid package. Improvements include: * Engineering to replace drive and disconnect switch * Conduct assessment and recommend if basin interior requires recoating * Coordinate outages to maintain proper plant operation * These improvements are additive alternates PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 260 WORK ORDER #: WF1142623 PROJECT: LICK CREEK RETURN ACTIVATED PROJECT #: SPWOC (LICK CREEK MISC IMPROVEMENTS) FUND: PROJECT BUDGET: $250,000 PROJECT MANAGER: Philip Bargas FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Doug Wallace Recent increases in plant loading have made it necessary to run both trains of the Lick Creek Wastewater Treatment Plant. It was found that the Return Activated Sludge Pumps will not consistently pump Return Activated Sludge at an appropriate rate. This is a critical function essential to meeting TCEQ mandated treatment requirements. This project will reconfigure the sludge piping so that the pumps will perform acceptably. This project has been bundled together with the Sludge Holding Tank Improvements, Centrifuge Improvements, Clarifier Catwalk Improvements, and the Process Control Improvements to provide a more attractive bid package. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 50,000 $50,000 2009-10 200,000 $200,000 2010-11 $0 2011-12 $0 2012-13 $0 SLUDGE MODIFICATIONS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR WASTEWATER CAPITAL PROJECTS PROJECT DESCRIPTION/STATUS 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $50,000 $200,000 $0 $250,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 261 WORK ORDER #: TBD PROJECT: PROJECT #: SSWOC FUND: PROJECT BUDGET: $2,178,000 PROJECT MANAGER: DOUG WALLACE FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 263,000 1,000,000 $1,263,000 2011-12 100,000 815,000 $915,000 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $363,000 $1,815,000 $0 $2,178,000 OPERATING COSTS CARTERS CREEK CENTRIFUGE IMPROVEMENTS Provide funds for improvements to the existing Carters Creek Wastewater Treatment Plant sludge dewatering system. The scope of this project includes improvements to the existing centrifuges' operational control and energy efficiency. This project also includes the installation of a second, redundant centrifuge. This additional equipment will ensure the critical plant process of dewatering sludge is completed as needed, and thereby minimizing Plant odors. This project has not yet entered the design phase. PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR WASTEWATER CAPITAL PROJECTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 262 WORK ORDER #: TBD PROJECT: PROJECT #: SSWOC FUND: PROJECT BUDGET: $420,000 PROJECT MANAGER: DOUG WALLACE FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 0 $0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 50,000 200,000 $250,000 2013-14 20,000 150,000 $170,000 2014-15 $0 CARTERS CREEK BLOWER BUILDINGS IMPROVEMENTS PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR WASTEWATER CAPITAL PROJECTS Provide Funds for improvements to Carters Creek Wastewater Treatment Plant Blower Buildings. The scope of this project involves the sound proofing of the plants blower facilities. While we have not received noise complaints from our neighbors yet, recent development has added more residences around the plant. The project has not yet entered the design phase. $ TOTAL $0 $70,000 $350,000 $0 $420,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 263 WORK ORDER #: TBD PROJECT: COLLEGE STATION SLUDGE FACILITY PROJECT #: SSWOC FUND: WASTEWATER CAPITAL PROJECTS PROJECT BUDGET: $5,500,000 PROJECT MANAGER: FRED SUROVIK FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services Future sludge handling facilities for Carters Creek and Lick Creek Plants will be relocated to an area that is unlikely to have residential development immediately adjacent to it. This project will: 1) Establish the criteria for moving and consolidating Carters Creek and Lick Creek sludge processing 2) Develop a plan for timely replacement of existing facilities as they approach their service life. 3) Plan for those facilities to operate economically with a minimum of public impact. 4) Construct facilities that minimize the potential for offending neighboring residents. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011 12 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2011-12 $0 2012-13 150,000 $150,000 2013-14 350,000 2,000,000 $2,350,000 2014-15 3,000,000 $3,000,000 TOTAL $150,000 $350,000 $5,000,000 $0 $5,500,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 264 WORK ORDER #: WF0742950 PROJECT: SCADA REPLACEMENT PROJECT #: SGWOC FUND: PROJECT BUDGET: $445,340 PROJECT MANAGER: MIKE KELLOGG FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services This project will facilitate the replacement of control based equipment that has exceeded its useful service life. It will upgrade the control of the plants into a more integrated architecture that will: 1. Reduce development time and cost by the re-use of engineering practices. 2. Maximize returns from existing assets, through greatly improved control and monitoring. 3. Reduce future installation cost by utilizing standard bus technologies. 4. Provide a means of being proactive in maintaining equipment with available diagnostic tools. Part of this project will include a "radio communications survey". This survey will determine what, if any, additional communications infrastructure may be needed to communicate with new Lift Stations and potential future annexed property. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 115,144 0 $115,144 2008-09 175,000 $175,000 2009-10 155,196 $155,196 2010-11 $0 2011-12 $0 WASTEWATER CAPITAL PROJECTS PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2011 12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $445,340 $0 $445,340 Total Personnel $3,000 Supplies $0 Service $10,000 Capital $0 TOTAL $13,000 $3,000 OPERATING COSTS First Fiscal Year Annually $0 0 10,000 $13,000 265 WORK ORDER #: TBD PROJECT: CARTERS CREEK FUELING STATION PROJECT #: SGWOC FUND: PROJECT BUDGET: $150,000 PROJECT MANAGER: DOUG WALLACE FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $0 2009-10 $0 2010-11 150,000 $150,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $150,000 $0 $150,000 WASTEWATER CAPITAL PROJECTS PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Provide funds for replacing the above ground fuel tanks at Carters Creek Wastewater Treatment Plant. Purchase one 500 gallon unleaded gasoline tank with a spill containment box, one 500 gallon diesel tank with a spill containment box, electrical pumps, hose, nozzles for each, electrical service from Plants 4 and 5 Blower Building, and a weather resistant enclosure for storing the fuel records. OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 266 WORK ORDER#: WF1129844 PROJECT: CCWWTP LABORATORY & SCADA PROJECT #: SGWOC BUILDING FUND: WASTEWATER CAPITAL PROJECTS PROJECT BUDGET: $940,000 PROJECT FUNDING MANAGER:PHILIP BARGAS SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Karl Goldapp FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 50,000 $50,000 2009-10 140,000 750,000 $890,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 Present building was built in 1982 as a chlorinator building and no longer meets laboratory standards. It is more cost effective to build a new building. The SCADA server room is housed in a "home made" room within the other 1982 shop building that does not maintain temperature or humidity for the computer equipment. There is an advantage to construct a building to house both because each require a clean controlled climate. PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR $ 2014-15 $0 TOTAL $0 $190,000 $750,000 $0 $940,000 Total Personnel $0 Supplies $0 Service $900 Capital $0 TOTAL $900$0 900 $900 OPERATING COSTS First Fiscal Year Annually 267 WORK ORDER #: WF1104553 PROJECT:CARTERS CREEK PROCESS PROJECT #: SGWOC CONTROL IMPROVEMENTS (CC MISC IMPROVEMENTS) FUND: PROJECT BUDGET: $330,000 PROJECT MANAGER: PHILIP BARGAS FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Doug Wallace FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 130,000 200,000 $330,000 2009-10 $0 2010 11 $0 * Dissolved oxygen meters in each aeration basin to replace meters that have reached the end of their service lives, and purchase and install pH meters in the influent and each aeration basin. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR WASTEWATER CAPITAL PROJECTS PROJECT DESCRIPTION/STATUS Provide funds to purchase and install improved process control instrumentation at Carters Creek Wastewater Treatment Plant. This project has been bundled with the Clarifier Improvements, Service Water Improvements, Gravity Thickener Improvements, and the ATAD Improvements to provide a more attractive bid package. Improvements include: * Flow meters on each plant's influent line, purchase and install positive displacement pumps in each waste sludge line. * In-line solids meters in the sludge processes. * In-line solids meters in the aeration basins. 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $130,000 $200,000 $0 $330,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 268 WORK ORDER #: WF1142624 PROJECT:LICK CREEK PROCESS CONTROL PROJECT #: SGWOC IMPROVEMENTS (LICK CREEK MISC IMPROVEMENTS) FUND: PROJECT BUDGET: $203,000 PROJECT MANAGER: PHILIP BARGAS FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services / Doug Wallace FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 80,000 0 $80,000 2009-10 123,000 $123,000 Provide funds to purchase and install improved process control instrumentation at Lick Creek Wastewater Treatement Plant. This project has been bundled together with the Sludge Holding Tank Improvements, Centrifuge Improvements, Clarifier Catwalk Improvements, and the Return Activated Sludge Improvements to provide a more attractive bid package. Improvements include: PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR WASTEWATER CAPITAL PROJECTS * Flow meters on each plant's influent line, purchase and install positive displacement pumps in each waste sludge line. * In-line solids meters in the sludge processes. * In-line solids meters in the aeration basins. * Dissolved oxygen meters in each aeration basin to replace meters that have reached the end of their service lives, and purchase and install pH meters in the influent and each aeration basin. 2009-10 123,000 $123,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $80,000 $123,000 $0 $203,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 269 WORK ORDER #: TBD PROJECT: PROJECT #: SGWOC FUND: PROJECT BUDGET: $240,000 PROJECT MANAGER: MICHAEL KELLOGG FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 80,000 $80,000 2010-11 80,000 $80,000 2011-12 80,000 $80,000 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $240 000 $0 $240 000 SCADA - NEW LIFT STATIONS WASTEWATER CAPITAL PROJECTS PROJECT DESCRIPTION/STATUS Constructon of new lift stations does not include the implementation of monitoring and alarming via the SCADA system. As of 2009, there are four (4) Lift Stations in operation that are not within the system. Subsequent years allow for SCADA implementation of an additional four per year. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $240,000 $0 $240,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 270 WORK ORDER #: WF1219655 PROJECT: PROJECT #: SGWOC FUND: PROJECT BUDGET: $300,000 PROJECT MANAGER: MICHAEL KELLOGG FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 300,000 $300,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $300 000 $0 $300 000 REMOTE PLANT SECURITY The original security project did not address the security needs of Lick Creek Wastewater Plant and remote package type plants. This project will address the physical access and monitoring of these plants. It will follow the guidelines, procedures, and standards set in the Wastewater Security Project. Strategic Business Plan Citywide Safety and Security Strategy 1. PROJECT DESCRIPTION/STATUS WASTEWATER CAPITAL PROJECTS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $300,000 $0 $300,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 First Fiscal Year Annually OPERATING COSTS $0 $0 271 WORK ORDER #: TBD PROJECT: LAND ACQUISITION PROJECT #: SGWOC CARTERS CREEK WWTP FUND: WASTEWATER CAPITAL PROJECTS PROJECT BUDGET: $2,000,000 PROJECT MANAGER: DAVE COLEMAN FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 2,000,000 $2,000,000 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $2,000,000 $0 $0 $0 $2,000,000 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Project provides funding for the purchase of land, or a conservation easement, adjacent to Carters Creek Wastewater Treatment Plant. The property, approximately 200 acres bordering the South side of the Plant, is extremely valuable to the operation of the Plant, because we currently use the property to land apply the fully treated and dewatered sludge, and also, we can apply liquid sludge to this property quickly and inexpensively in an operational emergency. In addition to the immediate operational benefits, this purchase would minimize the encroachment of additional development around the Plant. Total Personnel $0 Supplies $0 Service $6,000 Capital $0 TOTAL $6,000 OPERATING COSTS First Fiscal Year Annually 0 $0 $6,000 0 6,000 0 272 WORK ORDER #: TBD PROJECT: LAND ACQUISITION PROJECT #: SGWOC LICK CREEK WWTP FUND: WASTEWATER CAPITAL PROJECTS PROJECT BUDGET: $2,000,000 PROJECT MANAGER: DAVE COLEMAN FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services This project provides funding for the purchase of land, or conservation easements, adjacent to the Lick Creek Wastewater Treatment Plant. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 This land is valuable to the operation of the Plant, because we can minimize the encroachment of development around the Plant. This is especially important for the Lick Creek Plant, because this Plant will be expanded, as required, to accommodate the wastewater treatment needs for the City's future growth. PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2011-12 $0 2012-13 2,000,000 $2,000,000 2013-14 $0 2014-15 $0 TOTAL $2,000,000 $0 $0 $0 $2,000,000 Total Personnel $0 Supplies $0 Service $6,000 Capital $0 TOTAL $6,000 First Fiscal Year Annually OPERATING COSTS 0 $0 $6,000 0 0 6,000 273 WORK ORDER #: TBD PROJECT: PROJECT #: SGWOC FUND: PROJECT BUDGET: $450,000 PROJECT MANAGER: MICHAEL KELLOGG FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 120,000 $120,000 2010-11 $0 2011-12 330,000 $330,000 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $450 000 $0 $450 000 CARTERS CREEK FIBER RING WASTEWATER CAPITAL PROJECTS PROJECT DESCRIPTION/STATUS This project will implement a redundant Fiber Ring to Carters Creek Wastewater Treatment Plant. This will eliminate the spur and provide two paths of data into the Plant. This will also eliminate extended outages of data loss from the Lick Creek Wastewater Treatment Plant. A portion of the fiber path is in conjunction with the Lick Creek Trunkline Project. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $450,000 $0 $450,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 274 WORK ORDER #: TBD PROJECT: PROJECT #: SGWOC FUND: PROJECT BUDGET: $700,000 PROJECT MANAGER: DAVID OLIVAREZ FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 70,000 $70,000 2014-15 70,000 560,000 $630,000 TOTAL $0 $140,000 $560,000 $0 $700,000 LICK CREEK GENERATOR REPLACEMENT PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Provide funds to replace and upgrade the existing Lick Creek Wastewater Treatment Plant emergency power generator, which is nearing the end of its service life. The new generator will provide additional power so that more of the routine Plant processes can be completed while under generator power. The larger generator capacity will also provide operational redundancy and accomodate planned Plant expansion. This project has not yet entered the design phase. This project supports the Council directive of providing essential services during an extended power outage. WASTEWATER CAPITAL PROJECTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 275 WORK ORDER #: TBD PROJECT: PROJECT #: SGWOC FUND: PROJECT BUDGET: $1,300,000 PROJECT MANAGER:DAVID OLIVAREZ FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services Blower Building to Plants 4 and 5 Clarifiers, including two 2" instrumentation conduits. to Plants 2 and 3 Clarifiers, including two 2" instrumentation conduits. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 210,000 540,000 $750,000 2011-12 50,000 500,000 $550,000 2012-13 $0 2013 14 $0 * Replace the motor control centers (MCC) for Plants 2 and 3, run new conduit and wire from those MCCs * Replace the MS South switch gear. * Contract an engineer to design and plan the needed replacements, run new conduit from Plants 4 and 5 CARTERS CREEK ELECTRICAL IMPROVEMENTS PROJECT DESCRIPTION/STATUS WASTEWATER CAPITAL PROJECTS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Provide funds for the engineering and construction of a project to replace parts of the Plant's electrical infrastructure, which is reaching its expected service life. This project has not yet entered the design phase. 2013-14 $0 2014-15 $0 TOTAL $0 $260,000 $1,040,000 $0 $1,300,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS $0 $0 First Fiscal Year Annually 276 WORK ORDER #: TBD PROJECT: CCWWTP MAINTENANCE PROJECT #: SGWOC BUILDING FUND: WASTEWATER CAPITAL PROJECTS PROJECT BUDGET: $330,000 PROJECT MANAGER: FRED SUROVIK FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services The construction of a dedicated maintenance building needed for parts storage, pump, motor, and gearbox repairs. This project has not yet entered the design phase. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 40,000 200,000 $240,000 2011-12 15,000 75,000 $90,000 2012-13 $0 2013-14 $0 2014-15 $0 PROJECT DESCRIPTION PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2014-15 $0 TOTAL $0 $55,000 $275,000 $0 $330,000 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 277 WORK ORDER #: TBD PROJECT: CARTERS CREEK EQUIPMENT SHED PROJECT #: SGWOC FUND: PROJECT BUDGET: $480,000 PROJECT MANAGER: DOUG WALLACE FUNDING SOURCES: Long Term Debt/Utility Revenue PROJECT CLIENT: Water Services FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years 0 0 0 0 $0 2008-09 $0 2009-10 $0 2010-11 80,000 400,000 $480,000 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $80,000 $400,000 $0 $480,000 WASTEWATER CAPITAL PROJECTS PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR This project is to provide funds to construct an equipment protection shed at Carters Creek Wastewater Treatment Plant. This project has not yet entered the design phase. OPERATING COSTS Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually 278 BBRRAAZZOOSS VVAALLLLEEYY SSOOLLIIDD WWAASSTTEE MMAANNAAGGEEMMEENNTT AAGGEENNCCYY ((BBVVSSWWMMAA)) CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000099--22001100 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22001144--22001155 279 CITY OF COLLEGE STATION BRAZOS VALLEY SOLID WASTE MANAGEMENT AGENCY (BVSWMA) PRO - FORMA FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 FY 09 FY 10 APPROPRIATIONS REVISED APPROVED THROUGH FY08 APPROPRIATIONS APPROPRIATIONS REVENUES LANDFILL CHARGES 7,270,000$ 6,598,000$ OTHER SALES - METHANE GAS 180,000 - TRANSFER IN - 6,000,708 INTEREST 447,000 120,000 OTHER - 130,000 TOTAL REVENUES 7,897,000$ 12,848,708$ EXPENDITURES AND TRANSFERS LANDFILL OPERATIONS 2,635,780$ 2,538,411$ ADMINISTRATION 275,872 266,852 EQUIPMENT REPLACEMENT 566,000 1,098,800 APPROVED SLAs 1,116,450 260,800 PAY PLAN CONTINGENCY 23,401 9,509 EXPEND & TRANSFERS SUBTOTAL 4,617,503$ 4,174,372$ Cash for Capital Projects/Fill Sector Projects 550,421$ Debt Funded Capital Projects 1,944,711 Capital Projects Subtotal 11,922,448 2,495,132 NON-DEPARTMENTAL CONTRIBUTIONS -$ -$ OTHER - - TRANSFERS OUT - - DEBT SERVICE TRANSFER - 757,254 GENERAL & ADMIN. TRANSFERS 361,067 260,370 BRYAN COMPOST FACILITY COSTS 80,000 80,000 HOST FEES 166,000 180,000 CONTINGENCY 135,000 147,000 NON-DEPARTMENTAL SUBTOTAL 742,067$ 1,424,624$ TOTAL EXPENDITURES AND TRANSFERS 17,282,018$ 8,094,128$ INCREASE (DECREASE) IN WORKING CAPITAL FROM OPERATIONS, modified accrual budgetary basis (9,385,018)$ 4,754,580$ BEGINNING WORKING CAPITAL, accrual basis of acccounting 11,410,473$ 6,557,513$ Measurement Focus Adjustment RESERVED FOR CLOSURE POST CLOSURE ENDING WORKING CAPITAL, accrual basis of acccounting 2,025,455$ 11,312,093$ 280 CITY OF COLLEGE STATION BRAZOS VALLEY SOLID WASTE MANAGEMENT AGENCY (BVSWMA) PRO - FORMA FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 FY 08 FY 09 FY10 FY 11 FY 12 FY 13 FY 14 FY 15 ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED 111 1 1111 6,719,647$ 6,471,466$ 6,598,000$ 6,792,000$ 6,992,000$ 7,198,000$ 7,410,000$ 7,628,000$ - - - 180,000 180,000 180,000 180,000 180,000 - 4,239,292 6,000,708 - - - - - 498,527 150,000 120,000 104,000 109,000 81,000 76,000 68,000 2,380,502 27,723 130,000 79,000 125,000 426,650 30,500 18,000 9,598,676$ 10,888,481$ 12,848,708$ 7,155,000$ 7,406,000$ 7,885,650$ 7,696,500$ 7,894,000$ 3,961,621$ 4,150,105$ 2,538,411$ 2,620,000$ 2,700,000$ 2,790,000$ 2,880,000$ 2,970,000$ 335,085 286,001 266,852 280,000 290,000 300,000 310,000 320,000 - - 1,098,800 435,300 1,200,000 2,020,800 108,500 80,000 - - 260,800 91,000 253,730 261,342 294,182 303,008 - 9,509 31,200 31,800 32,400 33,000 33,700 4,296,706$ 4,436,106$ 4,174,372$ 3,457,500$ 4,475,530$ 5,404,542$ 3,625,682$ 3,706,708$ 1,795,833$ 4,025,651$ 3,644,838$ 3,922,500$ 2,454,448$ 2,499,425$ 1,285,450$ 4,428,067$ - 4,234,133 6,000,708 - - - - - 1,795,833 8,259,784 9,645,546 3,922,500 2,454,448 2,499,425 1,285,450 4,428,067 50,000$ -$ -$ -$ -$ -$ -$ -$ (765,112) - - - - - - - - - - - - - - - - - 757,254 790,839 798,239 795,189 801,689 807,589 348,505 361,067 260,370 266,000 272,000 278,000 284,000 290,000 - 80,000 80,000 80,000 80,000 80,000 80,000 80,000 104,306 161,330 180,000 190,000 195,000 200,000 205,000 210,000 - - 147,000 147,000 147,000 147,000 147,000 147,000 (262,301)$ 602,397$ 1,424,624$ 1,473,839$ 1,492,239$ 1,500,189$ 1,517,689$ 1,534,589$ 5,830,238$ 13,298,287$ 15,244,542$ 8,853,839$ 8,422,217$ 9,404,156$ 6,428,821$ 9,669,363$ 3,768,439$ (2,409,806)$ (2,395,834)$ (1,698,839)$ (1,016,217)$ (1,518,506)$ 1,267,679$ (1,775,363)$ 11,256,238$ 8,967,319$ 6,557,513$ 4,161,679$ 5,462,840$ 4,446,623$ 2,928,117$ 4,195,797$ (2,153,379)$ 3,903,979 (3,000,000) 8,967,319$ 6,557,513$ 4,161,679$ 5,462,840$ 4,446,623$ 2,928,117$ 4,195,797$ 2,420,433$ 281 CITY OF COLLEGE STATION BRAZOS VALLEY SOLID WASTE MANAGEMENT AGENCY (BVSWMA) PRO - FORMA FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 FY 09 FY 10 APPROPRIATIONS REVISED APPROVED THROUGH FY08 APPROPRIATIONS APPROPRIATIONS BVSWMA CIP FY10 Approved Cash Funded Projects Budget BV0403 - RPR Gas Recovery and final cover 6,229,973 4,045,000 - - Subtotal Rock Prairie Road Cash Funded Capital Projects 4,045,000 - - BV0003 - Twin Oaks land purchase 2,990,063 2,608,500 - - BV0502 - Twin Oaks Permit Application/Legal Fees 2,203,802 1,880,278 - - BV0603 - Twin Oaks Design Services 2,715,120 1,747,000 417,700 550,421 BV0701 - Twin Oaks Cell Construction - Phase I 5,664,812 - 7,390,000 - TBD - Twin Oaks Cell Construction - Phase II A 5,003,873 - - - TBD - Twin Oaks Cell Construction - Phase II B 5,414,540 - - - BV0802 - Twin Oaks Landfill Communications 125,000 40,000 85,000 - TBD - Twin Oaks Compost Facility Design and Construction 2,139,563 - - - TBD - Twin Oaks Petroleum Pipeline Relocation 855,954 - - - Subtotal Twin Oaks Cash Funded Capital Projects 6,275,778 7,892,700 550,421 Debt Funded Projects BV0901 - Twin Oaks Construction Project Management 928,300 0 768,500 159,800 BV0601 - Twin Oaks Access 4,457,118 1,289,330 2,447,503 720,285 BV0602 - Twin Oaks Buildings & Infrastructure 4,855,269 1,251,710 813,745 1,064,626 Subtotal Twin Oaks Debt Funded Capital Projects 2,541,040 4,029,748 1,944,711 Closed Projects - - - Total Capital Projects 12,861,818$ 11,922,448$ 2,495,132$ 282 CITY OF COLLEGE STATION BRAZOS VALLEY SOLID WASTE MANAGEMENT AGENCY (BVSWMA) PRO - FORMA FISCAL YEAR 2009-2010 THROUGH FISCAL YEAR 2014-2015 FY 08 FY 09 FY10 FY 11 FY 12 FY 13 FY 14 FY 15 ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED - - - 3,000,000 - - - - - - - 3,000,000 - - - - 657,228 105,000 - - - - - - 436,976 104,444 383,056 872,500 - - - - 599,211 645,237 638,910 - - - - - - 3,126,940 2,537,872 - - - - - - - - 50,000 2,454,448 2,499,425 - - - - - - - - 100,000 2,618,000 - 40,000 85,000 - - - - - - - - - - - 1,185,450 954,113 - - - - - - - 855,954 1,693,415 4,021,621 3,644,838 922,500 2,454,448 2,499,425 1,285,450 4,428,067 - 385,911 542,389 - - - - - - 1,751,333 2,699,939 - - - - - - 2,096,889 2,758,380 - - - - - - 4,234,133 6,000,708 - - - - - 102,418 4,030 - - - - - - 1,795,833$ 8,259,784$ 9,645,546$ 3,922,500$ 2,454,448$ 2,499,425$ 1,285,450$ 4,428,067$ 283 PROJECT: RPR Gas Recovery and Final Cover PROJECT #: BV0403 FUND: BVSWMA PROJECT BUDGET: $6,229,973 PROJECT FUNDING MANAGER: Samantha Best SOURCES: BVSWMA PROJECT CLIENT: BVSWMA This project is for the construction of approximately 98 acres of Subtitle D Final Cover. An Active Gas Collection and Control System (GCCS) was installed in conjunction with Phase I of the project. The project also includes professional services for project design, bid administration, and quality assurance/quality control during construction, and a global positioning satellite system for compaction and grading work. Phase I construction for 49 acres reached final completion in 2006. Phase II of the project will commence when the remaining landfill footprint reaches design capacity (projected FY 2010-2011). Phase I project has annual operating costs of $7,000.00 It is projected that this project will come in under budget. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $687,595 $2,237,075 $305,303 $3,229,973 2008-09 $0 2009-10 $0 2010-11 500,000 2,500,000 $3,000,000 2011-12 $0 2012-13 $0 2013-14 $0 2014 15 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2014-15 $0 TOTAL $0 $687,595 $2,737,075 $2,805,303 $6,229,973 Total Personnel $0 Supplies $10,000 Service $4,000 Capital $0 TOTAL $14,000 OPERATING COSTS First Fiscal Year Annually $7,000 $7,000 5,000 5,000 2,000 2,000 Twin Oaks Landfill Rock Prairie Landfill College Station Fm 215 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D r284 PROJECT: Twin Oaks Land Purchase PROJECT #: BV0003 PROJECT FUND: BVSWMA BUDGET: $2,990,063 PROJECT FUNDING MANAGER: Pete Caler SOURCES: BVSWMA PROJECT CLIENT: BVSWMA This project is for the purchase of approximately 610 acres in Grimes County for the future SH 30 Landfill site. Approximately 90% of the total acreage has been purchased as of March 2007. The remaining tracts of land were condemned in July 2008. Some outstanding mineral interests and portions of two tracts are pending. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $2,812,691 $315 0 $72,057 $2,885,063 2008-09 75,000 30,000 $105,000 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $2 887 691 $315 $0 $102 057 $2 990 063 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $2,887,691 $315 $0 $102,057 $2,990,063 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually Twin Oaks Landfill Rock Prairie Landfill College Station Fm 215 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D r285 PROJECT: Twin Oaks Permit Application/Legal Fees/PROJECT #: BV0502 Mitigation PROJECT FUND: BVSWMA BUDGET: $2,203,802 PROJECT FUNDING MANAGER: Pete Caler SOURCES: BVSWMA PROJECT CLIENT: BVSWMA This project is for the permitting process for the SH 30 Landfill site in Grimes County, Texas. This project includes engineering fees, mitigation credit purchase (MISC) for section 404 and other miscellaneous permits. This project also includes permit work for a driveway, on-site mitigation plan development, and a landfill permit modification for TMPA property. $603,000 transferred from BV0603 in FY07. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $10,940 $455,173 $377,689 0 $843,802 2008-09 104,444 $104,444 2009-10 130,556 252,500 $383,056 2010-11 872,500 $872,500 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $10 940 $690 173 $377 689 $1 125 000 $2 203 802 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $10,940 $690,173 $377,689 $1,125,000 $2,203,802 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually Twin Oaks Landfill Rock Prairie Landfill College Station Fm 215 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D r286 PROJECT: Twin Oaks Design Services PROJECT #: BV0603 PROJECT FUND: BVSWMA BUDGET: $2,715,120 PROJECT FUNDING MANAGER: Pete Caler SOURCES: BVSWMA PROJECT CLIENT: BVSWMA This project is for design, engineering and architectural services for the SH 30 Landfill Facility. These services will include the design and engineering of disposal cells, access infrastructure, and utilities infrastructure. Architectural services will include the assorted facility buildings and landscaping located at the site. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $1,413,826 $0 $17,148 $1,430,974 2008-09 645,237 $645,237 2009-10 638,910 $638,910 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2014-15 $0 TOTAL $0 $2,697,972 $0 $17,148 $2,715,120 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 Twin Oaks Landfill Rock Prairie Landfill College Station Fm 215 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D r287 PROJECT: Twin Oaks Cell Construction - Phase I PROJECT #: BV0701 PROJECT FUND: BVSWMA BUDGET: $5,664,812 PROJECT FUNDING MANAGER: Pete Caler/Samantha Best SOURCES: BVSWMA PROJECT CLIENT: BVSWMA This project is for Fill Sector 1 at the future Twin Oaks Landfill site in Grimes County. Each fill sector will encompass an area of approximately 20 acres. Construction will include the excavation, recompacted clay liner, HDPE composite liner and related leachate collection structures. Construction is expected to begin in 2008. Also included in this project are water and gas monitoring wells and quality control/quality assurance (MISC) costs. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $2,791,607 335,333 $3,126,940 2009-10 $2,093,705 444,167 $2,537,872 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $4,885,312 $779,500 $5,664,812 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $4,885,312 $779,500 $5,664,812 Total Personnel TBD Supplies TBD Service TBD Capital TBD TOTAL TBD$0 TBD TBD TBD TBD TBD OPERATING COSTS First Fiscal Year Annually Twin Oaks Landfill Rock Prairie Landfill College Station Fm 215 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D r288 PROJECT: Twin Oaks Cell 2A Construction PROJECT #: TBD FUND: BVSWMA PROJECT BUDGET: $5,003,873 PROJECT FUNDING MANAGER: Pete Caler/Samantha Best SOURCES: BVSWMA PROJECT CLIENT: BVSWMA This project is for Fill 2A at the Twin Oaks Landfill site in Grimes County. Each fill sector will encompass an area of approximately 20 acres. Construction will include the excavation, recompacted clay liner, HDPE composite liner and related leachate collection structures. Construction is expected to begin in 2011. Also included in this project are quality control/quality assurance (MISC) costs. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 50,000 $50,000 2011-12 50,000 $2,279,448 125,000 $2,454,448 2012-13 $2,374,425 125,000 $2,499,425 2013-14 $0 2014-15 $0 TOTAL $0 $100,000 $4,653,873 $250,000 $5,003,873 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS Total Personnel TBD Supplies TBD Service TBD Capital TBD TOTAL TBD$0 TBD TBD TBD TBD TBD OPERATING COSTS First Fiscal Year Annually Twin Oaks Landfill Rock Prairie Landfill College Station Fm 215 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D r289 PROJECT: Twin Oaks Cell 2B Construction PROJECT #: TBD FUND: BVSWMA PROJECT BUDGET: $5,414,540 PROJECT FUNDING MANAGER: Samantha Best SOURCES: BVSWMA PROJECT CLIENT: BVSWMA This project is for Fill 2B at the Twin Oaks Landfill site in Grimes County. Each fill sector will encompass an area of approximately 20 acres. Construction will include the excavation, recompacted clay liner, HDPE composite liner and related leachate collection structures. Construction is expected to begin in 2014. Also included in this project are quality control/quality assurance (MISC) costs. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 100,000 $100,000 2014-15 $2,493,000 125,000 $2,618,000 Future Years $2,571,540 125,000 $2,696,540 TOTAL $0 $100,000 $5,064,540 $250,000 $5,414,540 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR Total Personnel TBD Supplies TBD Service TBD Capital TBD TOTAL TBD TBD OPERATING COSTS First Fiscal Year Annually $0 TBD TBD TBD TBD Twin Oaks Landfill Rock Prairie Landfill College Station Fm 215 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D r290 PROJECT: Twin Oaks Landfill Communications PROJECT #: BV0802 FUND: BVSWMA PROJECT BUDGET: $125,000 PROJECT FUNDING MANAGER: Pete Caler/Samantha Best SOURCES: BVSWMA PROJECT CLIENT: BVSWMA This project is for wireless communications at the Twin Oaks landfill site in Grimes County. The project will allow landfill operations to be connected to the City of College Station data network through a wireless connection. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 40,000 $40,000 2009-10 85,000 $85,000 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $40,000 $85,000 $0 $125,000 Total Personnel $0 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR OPERATING COSTS First Fiscal Year Annually Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 Twin Oaks Landfill Rock Prairie Landfill College Station Fm 2 1 5 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D r291 PROJECT: Compost Facility Design and PROJECT #: TBD Construction (Twin Oaks Landfill) PROJECT FUND: BVSWMA BUDGET: $2,139,563 PROJECT FUNDING MANAGER: Pete Caler/Samantha Best SOURCES: BVSWMA PROJECT CLIENT: BVSWMA This project includes the construction of infrastructure for a composting facility at the Twin Oaks Landfill. The estimated start of design and construction is FY2014. The facility will be located on fill sector 1of the landfill footprint. PROJECT DESCRIPTION/STATUS landfill footprint. This project is anticipated to begin in FY14. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008 09 $0 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $84,675 $1,100,775 $1,185,450 2014-15 $954,113 $954,113 TOTAL $0 $84,675 $2,054,888 $0 $2,139,563 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually Harvey RdPwU n iv e rs ity D rTwin Oaks Landfill Rock Prairie Landfill College Station Fm 215 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D rTwin Oaks Landfill Rock Prairie Landfill College Station Fm 215 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D r292 PROJECT: Petroleum Pipeline Relocation PROJECT #: TBD (Twin Oaks Landfill) PROJECT FUND: BVSWMA BUDGET: $855,954 PROJECT FUNDING MANAGER: Pete Caler/Samantha Best SOURCES: BVSWMA PROJECT CLIENT: BVSWMA This project includes the relocation of a petroleum pipeline at the Twin Oaks Landfill. The estimated start of design and construction is FY2015. The pipeline is currently located within the landfill footprint and will be relocated outside the perimeter of the waste fill area. PROJECT DESCRIPTION/STATUS relocated outside the perimeter of the waste fill area. This project is anticipated to begin in FY15. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008 09 $0 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2008-09 $0 2009-10 $0 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 85,595 770,359 $855,954 TOTAL $0 $85,595 $770,359 $0 $855,954 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually Harvey RdPwU n iv e rs ity D rTwin Oaks Landfill Rock Prairie Landfill College Station Fm 2 15 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D rTwin Oaks Landfill Rock Prairie Landfill College Station Fm 2 15 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D r293 PROJECT: Construction Project Management PROJECT #: BV0901 (Twin Oaks Landfill) PROJECT FUND: BVSWMA BUDGET: $928,300 PROJECT FUNDING MANAGER: Pete Caler/Samantha Best SOURCES: BVSWMA PROJECT CLIENT: BVSWMA This project includes Project Management for Phase I construction at the Twin Oaks Landfill. Phase I construction consists of all roads, structures, related infrastructure, and the initial solid waste fill sector at the site in Grimes County. PROJECT DESCRIPTION/STATUS County. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008 09 385 911 $385 911 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR 2008-09 385,911 $385,911 2009-10 542,389 $542,389 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $928,300 $0 $0 $928,300 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0 OPERATING COSTS First Fiscal Year Annually $0 $0 Cll SttiHarvey RdhPwU n iv e rs ity D rTwin Oaks Landfill Rock Prairie Landfill College Station Fm 215 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D rTwin Oaks Landfill Rock Prairie Landfill College Station Fm 215 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D r294 PROJECT: Twin Oaks Access Development PROJECT #: BV0601 PROJECT FUND: BVSWMA BUDGET: $4,457,118 PROJECT FUNDING MANAGER: Pete Caler/Samantha Best SOURCES: BVSWMA PROJECT CLIENT: BVSWMA This project is for access development and fencing for the SH 30 Landfill. This will include a perimeter fence and gates, paved and unpaved roadways, a bridge over Alum Creek parking areas, and State Highway 30 improvements. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $5,202 $644 $5,846 2008-09 1,751,333 $1,751,333 2009-10 2,699,939 $2,699,939 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $4 456 474 $644 $4 457 118 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $4,456,474 $644 $4,457,118 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually Twin Oaks Landfill Rock Prairie Landfill College Station Fm 215 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D r295 PROJECT: Twin Oaks Buildings & Infrastructure PROJECT #: BV0602 PROJECT FUND: BVSWMA BUDGET: $4,855,269 PROJECT FUNDING MANAGER: Pete Caler/Samantha Best SOURCES: BVSWMA PROJECT CLIENT: BVSWMA This project includes the construction of buildings and related infrastructure for the future SH 30 landfill facility in Grimes County. These include a scale house and scales, maintenance facility, waste screening area, service facility for drivers, and a citizens convenience area. Related infrastructure includes landscaping, water and electric supply systems,and a waste-water management system. FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL Prior Years $0 $0 $0 $0 $0 2008-09 $2,096,889 $2,096,889 2009-10 2,758,380 $2,758,380 2010-11 $0 2011-12 $0 2012-13 $0 2013-14 $0 2014-15 $0 TOTAL $0 $0 $4 855 269 $0 $4 855 269 PROJECT DESCRIPTION/STATUS PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR TOTAL $0 $0 $4,855,269 $0 $4,855,269 Total Personnel $0 Supplies $0 Service $0 Capital $0 TOTAL $0$0 $0 OPERATING COSTS First Fiscal Year Annually Twin Oaks Landfill Rock Prairie Landfill College Station Fm 215 4Harvey RdWilliam D Fitch PwWe ll b o r n R d U n iv e rs ity D r296 EESSTTIIMMAATTEEDD OO&&MM CCOOSSTTSS 297 Projected Projected Projected Projected Projected Projected FY10 FY11 FY12 FY13 FY14 FY15 Comments Street/Traffic Projects Victoria Avenue Extension - - 7,000 7,210 7,426 7,649 Street Maintenance Penberthy Extension - - - 5,500 5,665 5,835 Street Maintenance Barron Road Widening Phase II - - 11,000 11,330 11,670 12,020 Street Maintenance Barron Road East/Lakeway Drive - - - - - - TBD - O&M estimated to begin FY16 W.D. Fitch Widening Phase II 11,000 11,330 11,670 12,020 12,381 12,752 Street Maintenance TX Ave Streetscaping Ph II 10,000 10,300 10,609 10,927 11,255 11,593 Landscaping and utility costs TxDOT Landscaping - Wellborn: FM 2818 to SH40 - - 12,000 12,360 12,731 13,113 Landscaping and utility costs New Traffic Signals (2003 GOB) 1,800 3,654 3,764 3,877 3,993 4,113 Utility costs Signal at University/Copperfield 1,800 1,854 1,910 1,967 2,026 2,087 Utility costs Traffic Signal at George Bush/Dominik - - 1,800 1,854 1,910 1,967 Utility costs New Traffic Signals (2008 GOB) - 27,000 31,410 35,952 40,631 45,450 Utility costs COCS Beautification Improvements 12,500 12,875 13,261 13,659 14,069 14,491 Landscaping and utility costs Hike and Bike Trail Completion - - 1,000 1,030 1,061 1,093 Trail Maintenance costs Lick Creek Hike and Bike Trail - - - - - 3,000 Trail Maintenance costs University Drive Pedestrian Improvements Ph II - - - - - - TBD - O&M estimated to begin FY16 Street/Traffic Project Totals 37,100$ 67,013$ 105,423$ 117,686$ 124,817$ 135,161$ Parks Projects Veteran's Park and Athletic Complex, Phase II 390,686 390,491 402,206 414,272 426,700 439,501 Personnel (3 positions plus temp/seasonal funds); supplies; vehicle and machinery maintenance; landscaping service, utility costs; and two vehicles Creek View Neighborhood Park - 41,590 42,838 44,123 45,447 46,810 Personnel, maintenance and utility costs Pebble Creek Basketball Pavillion 2,400 2,472 2,546 2,623 2,701 2,782 Mainteinance costs Merry Oaks Park Area Lights 1,750 1,803 1,857 1,912 1,970 2,029 Maintenance and utility costs Skate Park 2,000 20,400 21,012 21,642 22,292 22,960 Maintenance and utility costs Lick Creek Park Iron Bridge Trail Completion - - - 2,200 2,266 2,334 Trail Maintenance costs Lincoln Center Addition - - - 124,800 128,544 132,400 Personnel (1 position plus temp/seasonal funds); utility costs; and facilities maintenance Lick Creek Nature Center - - - - - 300,000 Personnel (TBD); supplies; utility costs; facilities maintenance; and other services Wolf Pen Creek Festival Site and Water Feature - 170,000 175,100 180,353 185,764 191,336 Personnel, maintenance, supplies and utility costs Parks Project Totals 396,836$ 626,756$ 645,558$ 791,925$ 815,683$ 1,140,153$ Facility and Technology Projects Memorial Cemetery 148,009$ 152,449$ 157,023$ 161,733$ 166,585$ 171,583$ Personnel (3 positions); supplies; vehicle and machinery maintenance; landscaping service and utility costs; vehicles (1 truck, 1 trailer, 1 tractor one mower) City Hall - - - TBD TBD TBD TBD Northgate Improvements TBD TBD TBD TBD TBD TBD TBD Northgate Restroom Facility 10,000 10,300 10,609 10,927 11,255 11,593 Supplies, janitorial contract and utility costs Municipal Facility Improvements 32,000 32,960 33,949 34,967 36,016 37,097 Supplies, janitorial and facility maintenance and utility costs Fire Station #6 236,734 642,750 1,205,750 1,985,956 1,717,106 1,717,106 Personnel: ambulance company (9 FTE), engine company (12 FTE), ladder company (12 FTE); vehicles: ambulance, engine truck, ladder truck and command vehicle; vehicle maintenance and replacement; utility and landscaping service costs; and supplies. Estimated annual on-going cost after full implementation is approximately $2.5 million. Library Expansion - - - 138,000 142,140 146,404 Personnel (2 positions); utility costs; book replacement; and facilities maintenance MDT System Replacement - - 20,000 20,600 21,218 21,855 Maintenance contract i5 Enhancement - - 18,000 18,540 19,096 19,669 Hardware and Software maintenance contract Radio System Replacement Enhancement 69,264 130,541 210,811 219,319 228,226 228,227 Professional Services contract with BVCOG Wireless Infrastructure - 20,000 20,600 21,218 21,855 22,510 Supplies, Purchased Services and Capital Outlay Server Consolidation - 15,000 15,450 15,914 16,391 16,883 Purchased Services - contract CAD Hardware Operating System Upgrade - 15,000 15,450 15,914 16,391 16,883 Maintenance contract Facilities and Technology Project Totals 496,007$ 1,019,000$ 1,707,642$ 2,643,087$ 2,396,279$ 2,409,808$ Convention Center Convention Center - TBD TBD TBD TBD TBD Additional O&M expenses will be incurred as a component of a new convention center. However, estimates will not be available until the project is fully developed. Convention Center Project Totals -$ TBD TBD TBD TBD TBD Total Estimated O&M Costs 929,943$ 1,712,769$ 2,458,623$ 3,552,698$ 3,336,778$ 3,685,122$ Governmental Funds Capital Improvement Projects Estimated Operations and Maintenance Costs* *The Operations and Maintenance costs reflected above are estimates based on anticipated costs associated with each project. In some situations, the O&M cost of a project is minimal and can be absorbed by the City department that is benefiting the most from the project. In other situations, the O&M cost is more significant and funding for these additional expenses is addressed through the Service Level Adjustment (SLA) process. As the projects become better defined, the O&M estimates may be revised. 298 Projected Projected Projected Projected Projected Projected FY10 FY11 FY12 FY13 FY14 FY15 Comments Parkland Dedication Parkway Park - 2,000 2,060 2,122 2,185 2,251 Supplies and additional for landscaping Southwest Park Development 2,000 30,000 30,900 31,827 32,782 33,765 Personnel (1 FTE), supplies and landscaping contract John Crompton Park Ph II - 8,000 8,240 8,487 8,742 9,004 Supplies and additional for landscaping contract Southern Oaks Trail and Lights 8,008 8,248 8,496 8,751 9,013 9,283 Supplies and utilties Castle Rock Park 7,510 7,735 7,967 8,206 8,453 8,706 Additional for landscaping contract Parkland Projects Totals 17,518$ 55,984$ 57,663$ 59,393$ 61,175$ 63,010$ Total Estimated O&M Costs 17,518$ 55,984$ 57,663$ 59,393$ 61,175$ 63,010$ Special Revenue Funds Capital Improvement Projects Estimated Operations and Maintenance Costs* *The Operations and Maintenance costs reflected above are estimates based on anticipated costs associated with each project. In some situations, the O&M cost of a project is minimal and can be absorbed by the City department that is benefiting the most from the project. In other situations, the O&M cost is more significant and funding for these additional expenses is addressed through the Service Level Adjustment (SLA) process. As the projects become better defined, the O&M estimates may be revised. 299 Projected Projected Projected Projected Projected Projected FY10 FY11 FY12 FY13 FY14 FY15 Comments Water Projects Well #8 - 67,500 69,525 71,611 73,759 75,972 Supplies and utility costs Well # 8 Collection Line - 4,300 4,429 4,562 4,699 4,840 Line Maintenance Well #9 - - - - 67,500 69,525 Supplies and utility costs Well #9 Collection Line - - - - 4,300 4,429 Line Maintenance Dowling Road 10 MG Storage Tank - - - - - - TBD - O&M estimated to begin FY16 SPPS Chemical System Replacement - - - - 35,200 36,256 Personnel (1 FTE), supplies and utility costs High Service Water Pump Improvements - - 229,473 236,357 243,448 250,751 Supplies and utility costs Cooling Tower Expansion - - - - 80,000 61,000 Supplies and utility costs Emergency Electric Generator Expansion - - - - - - TBD - O&M estimated to begin FY16 SCADA Man Machine Interface - - - - 7,500 7,725 Software maintenance contract Water Plant Security 6,200 6,386 6,578 6,775 6,978 7,187 Repairs and software consultations Reclaimed Water - Irrigation Phase I - - 76,000 78,280 80,628 83,047 Personnel (1 FTE), supplies, vehicle maintenance, training, utility costs and vehicle (1 pickup truck) Raymond Stotzer - - - 12,800 13,184 13,580 Supplies and utility costs Reclaimed Water - Irrigation Phase II - - - - - 31,500 Supplies and utility costs FM60 Widening Water Line Relocation - - - 12,800 13,184 13,580 Supplies and utility costs Water Project Totals 6,200$ 78,186$ 386,005$ 423,185$ 630,380$ 659,392$ Wastewater Projects Koppe Bridge Lift Station -$ 11,000$ 11,330$ 11,670$ 12,020$ 12,381$ Utility costs Nantucket Gravity Sewer - 200 206 212 219 225 Utility costs Emerald Parkway/Bent Oak - 6,200 3,125 3,219 3,315 3,415 Line Maintenance Carters Creek Clarifier Improvements 2,700 2,781 2,864 2,950 3,039 3,130 Supplies and maintenance Carters Creek Headworks Improvements - - 83,500 86,005 88,585 91,243 Supplies, maintenance contract and utility costs Carters Creek Service Water Improvements 28,000 28,840 29,705 30,596 31,514 32,460 Supplies, maintenance contract and utility costs SCADA Replacement - 13,000 13,390 13,792 14,205 14,632 Maintenance and service contract Carters Creek Lab and SCADA Building - 900 927 955 983 1,013 Janitorial, Maintenance, Utility costs Land Acquisition - CCWWTP - - - 6,000 6,180 6,365 Land maintenance costs Land Acquisition - LCWWTP - - - - 6,000 6,180 Land maintenance costs Wastewater Project Totals 30,700$ 62,921$ 145,048$ 155,399$ 166,061$ 171,043$ BVSWMA Projects RPR Gas Recovery and Final Cover 7,000 7,210 7,426 7,649 7,879 8,115 Maintenance and supplies for flare system Transition Costs for Twin Oaks 188,800 - - - - - 7 roll-off containers, 2 storage/work buildings, furniture and equipment, scale software license and procurement of general moving and heavy equipment specialty hauling Twin Oaks Buildings and Infrastructure - TBD TBD TBD TBD TBD Twin Oaks Cell Construction - TBD TBD TBD TBD TBD Twin Oaks Landfill Communications - TBD TBD TBD TBD TBD Twin Oaks Compost Facility - - - - TBD TBD BVSWMA Project Totals 195,800$ 7,210$ 7,426$ 7,649$ 7,879$ 8,115$ Total Estimated O&M Costs 232,700$ 148,317$ 538,479$ 586,233$ 804,320$ 838,549$ Enterprise Funds Capital Improvement Projects Estimated Operations and Maintenance Costs* *The Operations and Maintenance costs reflected above are estimates based on anticipated costs associated with each project. In some situations, the O&M cost of a project is minimal and can be absorbed by the City department that is benefiting the most from the project. In other situations, the O&M cost is more significant and funding for these additional expenses is addressed through the Service Level Adjustment (SLA) process. As the projects become better defined, the O&M estimates may be revised. The estimated O&M costs of the new landfill are currently under review. It is anticipated that a significant portion of the O&M costs of the new landfill will be offset with the closing of the existing landfill. 300 Index by Project/Work Order Name Streets Projects Project # Page Facility Projects Project # Page BARRON ROAD RIGHT OF WAY ST0006 37 CITY HALL IMPROVEMENTS GG0408 112 BARRON RD EAST/LAKEWAY TBD 42 FIRE STATION #6 GG0903 117 BARRON RD WIDENING PHASE II ST1026 40-41 FIRST STREET FENCING GG0905 114 BARRON ROAD REHABILITATION ST0409 38-39 LARRY J. RINGER LIBRARY EXPANSION GG1010 118 BIKE LOOP - 2005 - BIKE LOOP COMPLETION ST0530 65 LIBRARY BOOK DONATIONS GG9901 109 BIRMINGHAM/LONGMIRE IMPROVEMENTS ST0908 53 MEMORIAL CEMETERY GG9905 110-111 COCS BEAUTIFICATION IMPROVEMENTS ST0515 68-69 MUNICIPAL FACILITY IMPROVEMENTS GG0701 116 COLLEGE PARK/BREEZY HEIGHTS (SOUTHSIDE) ST0507 18-19 NORTHGATE IMPROVEMENTS GG0803 113 DISCOVERY DRIVE EXTENSION ST0804 28 NORTHGATE RESTROOMS GG0522 115 EAGLE AVENUE EXTENSION ST0809 30-31 HIKE AND BIKE TRAIL COMPLETION ST0904 73 Technology Projects Project # Page HIKE AND BIKE TRAILS - LONGMIRE IMPROVEMENTS ST0521 67 CAD HW OPERATING SYSTEM UPGRADE CO1001 127 HOLLEMAN EXTENSION OP ST0913 27 FIBER OPTIC INFRASTRUCTURE CO0902 126 LICK CREEK HIKE AND BIKE TRAIL TBD 74 i5 ENHANCEMENT TBD 121 LINCLON AVENUE SIDEWALK IMPROVEMENTS ST0910 71 MDT SYSTEM REPLACEMENT CO0701 120 LINCOLN/FOSTER IMPROVEMENTS ST0909 52 MISC IT PROJECTS CO0801 128 MANUEL DRIVE OP ST0802 26 RADIO SYSTEM REPLACEMENT CO0601 123 MISC. BIKE TRAILS - BIKE LOOP COMPLETION ST9803 66 SERVER CONSOLIDATION CO0901 125 NEW SIGNAL WARRANT STUDY ST0912 56 UPS REPLACEMENT CO0603 122 NEW TRAFFIC SIGNAL PROJECTS (2003 GOB) ST0512 55 WIRELESS INFRASTRUCTURE CO0704 124 NEW TRAFFIC SIGNAL PROJECTS (2008 GOB) ST1027 60 NORTHGATE STREET REHAB ST0518 20 Drainage Projects Project # Page OVERSIZE PARTICIPATION ST0519 25 BEE CREEK PH. IV & V. SD0001 132-133 PENBERTHY BOULEVARD EXTENSION ST0905 34 COLLEGE PARK/BREEZY HEIGHTS (SOUTHSIDE) SD0601 18-19 ROCK PRAIRIE RD WEST ROW ST1025 36 GREENWAYS PROJECTS SD9903 134 ROCK PRAIRIE RD WIDENING - DESIGN AND ROW ST0417 35 MINOR DRAINAGE IMPROVEMENTS SD1002 135 SCHOOL ZONE/PEDESTRIAN FLASHERS ST0916 54 MITIGATION FENCING @ ARRINGTON/DECATUR SD0901 138 SIDEWALK IMPROVEMENTS ST0517 70 STORMWATER MAPPING SD0523 137 SIDEWALK IMPROVEMENTS (2008 GOB) ST1028 72 W. KING COLE CULVERT REPLACEMENT SD0904 136 SIGNAL CONTROLLERS FOR FIBER ST0915 62 TAUBER AND STASNEY REHAB/NG SIDEWALKS ST0505 22-23 Convention Center Projects Project # Page TEXAS AVENUE FIBER ST0906 63 CONVENTION CENTER GG0907 142 TRAFFIC SIGNAL @ GB DRIVE EAST & DOMINIK ST0205 59 TRAFFIC SIGNAL COMMUNICATIONS ST0411 61 Parkland Dedication Projects Project # Page TRAFFIC SYSTEM SAFETY IMPR. ST0511 51 CASTLE ROCK PARK DEVELOPMENT PK0922 164 TX AVE STREETSCAPE PH II ST9915 47 EMERALD FOREST PARK IMP. PK0713 88-89 UNIVERSITY DR PEDESTRIAN IMPROVEMENTS PH 2-5 TBD 75 JOHN CROMPTON PARK PHASE III PK0904 159 UNIVERSITY/COPPERFIELD SIGNAL ST0914 57 PARKWAY PARK PK0903 149 VICTORIA AVENUE ST0903 32-33 SOUTHERN OAKS TRAIL AND LIGHTS PK0905 163 VIDEO DETECTION - 2009 ST0907 50 SOUTHWEST PARK DEVELOPMENT PK0806 157 WELLBORN RD LANDSCAPING - 2818 to 40 ST0812 48 STEEPLECHASE PARK BENCH TBD 155 WELLBORN/CAPSTONE SIGNAL STUDY ST0917 58 STEPHEN C. BEACHY CENTRAL PK POND SW PK0805 151 WILLIAM D. FITCH PKWY WIDENING PH II ST0520 44-45 WINDWOOD PARK IMPROVEMENTS PK0916 153 ZONE 1 PARK PK0051 147 Parks Projects Project # Page ZONE 2 PARK PK0052 148 ADAMSON POOL BATH HOUSE REPLACEMENT PK0701 84 ZONE 3 PARK PK0053 150 ANDERSON PARK WALKING LOOP PK1002 91 ZONE 4 PARK PK0054 152 BEACHY CENTRAL PARK IMPROVEMENTS PK1001 97 ZONE 5 PARK PK0055 154 BROTHERS POND PARK - RUNNING SURFACE PK1003 92 ZONE 6 PARK PK0056 156 CREEK VIEW NEIGHBORHOOD PARK PK0906 85 ZONE 7 PARK PK0057 158 EAST DISTRICT MAINTENANCE SHOP REPLACEMENT TBD 100 ZONE 8 PARK PK0058 160 EMERALD FOREST IMPROVEMENTS PK0713 88-89 ZONE 9 PARK PK0059 161 FIELD REDEVELOPMENT PK0300 82 ZONE 10 PARK PK0060 162 LEMONTREE PARK SWING SET TBD 94 ZONE 11 PARK PK0061 165 LICK CREEK NATURE CENTER TBD 101 ZONE 12 PARK PK0824 166 LICK CREEK PARK IRON BRIDGE TRAIL COMPLETION TBD 98 ZONE 13 PARK PK0807 167 LINCOLN CENTER ADDITION TBD 99 ZONE 14 PARK PK0717 168 MERRY OAKS PARK AREA LIGHTS TBD 93 ZONE 15 PARK PK0808 169 NEIGHBORHOOD PARK - FENCING PK0917 90 ZONE 16 PARK TBD 170 NEIGHBORHOOD PARK IMPROVEMENTS PK0910 86 NEIGHBORHOOD PARKS REVOLVING FUND PK0912 96 Water Projects Work Order # Page PEBBLE CREEK BASKETBALL PAVILION PK0914 87 BARRON ROAD WATER SERVICE EXT WF0379197 207 SKATE PARK PK0911 95 BARRON ROAD REHAB WF0654325 38-39 VETERANS PARK PHASE II PK0501 83 BARRON ROAD WIDENING PH II TBD 40-41 WOLF PEN CREEK FESTIVAL SITE/WATER FEATURE WP0901 103 BEE CREEK PHASES IV & V TBD 132-133 COLLEGE PARK/BREEZY HEIGHTS WF0595915 18-19 COMMUNICATIONS INFRASTRUCTURE IMP TBD 201 301 Index by Project/Work Order Name Water Projects (con't)Work Order # Page Wastewater Projects (con't)Work Order # Page COOLING TOWER EXPANSION TBD 191 CARTERS CREEK FUELING STATION TBD 266 DISTRIBUTION SCADA TBD 202 CARTERS CREEK GRAVITY THICKENER WF1104543 260 DOWLING ROAD TEN MG TANK WF0353631 187 CARTERS CREEK HEADWORKS IMP WF1223116 253 EAGLE AVENUE EXTENSION WF1095364 30-31 CARTERS CREEK LAB AND SCADA BUILDING WF1129844 267 EASTGATE REHAB TBD 226-227 CARTERS CREEK PROCESS CONTROL IMPROVEMEN WF1104553 268 EMERGENCY ELECTRIC GENERATOR EXP TBD 192 CARTERS CREEK SERVICE WATER IMP WF0930104 254 FM 60 WIDENING WATER RELOCATION TBD 214-215 CCWWTP MAINTENANCE BUILDING TBD 277 HIGH SERVICE WATER PUMP IMPROVEMENTS WF1223117 189 COLLEGE STATION SLUDGE FACILITY TBD 264 LAND ACQUISITION - WELLS WF0377324 182 EASTGATE REHAB TBD 226-227 MCCULLOCH REHAB TBD 228-229 EMERALD PKWY / BENT OAK WF0626151 250 NANTUCKET EAST OF HARPERS FERRY (AREA 3) TBD 220 KOPPE BRIDGE LIFT STATION WF1097963 242 NORTHGATE REHAB TBD 230-231 LAND ACQUISITION - CCWWTP TBD 272 OVERSIZED PARTICIPATION TBD 204 LAND ACQUISITION - LCWWTP TBD 273 PARALLEL WELLFIELD COLL LINE PH I WF0352553 181 LICK CREEK CENTRIFUGE IMPROVEMENTS WF1142617 256 RAYMOND STOTZER WEST WF1111167 208-209 LICK CREEK CLARIFIER CATWALKS WF1042497 255 ROCK P RD S OF CARTER LAKE (AREA 5) WF0805789 216-217 LICK CREEK GENERATOR REPLACEMENT TBD 275 SCADA MAN MACHINE INTERFACE TBD 200 LICK CREEK IMPACT FEE LINE TBD 247 SCADA REPLACEMENT WF0742940 196 LICK CREEK PARALLEL TRUNKLINE - PH I WF0912284 245 SH 40 WATER LINE-GRAHAM RD TO BARRON RD TBD 210 LICK CREEK PARALLEL TRUNKLINE PH II TBD 248 SH 40 WATER LINE-IRON HORSE WAY TO VICTORIA TBD 211 LICK CREEK PROCESS CONTROL IMPROVEMENTS WF1142624 269 SOUTH KNOLL/THE GLADE WF1044480 222-223 LICK CREEK RETURN ACTIVATED SLUDGE IMP WF1142623 261 SOUTHWOOD 5-7 REHAB WF1105425 224-225 LICK CREEK SLUDGE HOLDING TANK IMPROVEMENT WF1142618 257 SPPS CHEMICAL SYSTEM REPLACEMENT TBD 188 MCCULLOCH REHAB TBD 228-229 TAUBER AND STASNEY REHAB WF0625888 22-23 NANTUCKET GRAVITY SEWER WF1094676 244 THE KNOLL REHAB TBD 232-233 NORTHEAST SEWER TRUNKLINE TBD 246 USC RENOVATIONS TBD 198-199 NORTHGATE REHAB TBD 230-231 VICTORIA AVENUE WF1158553 32-33 OVERSIZE PARTICIPATION TBD 241 WATER PLANT SECURITY WF0466439 197 RAYMOND STOTZER WEST TBD 208-209 WATER RECLAIM/IRRIGATION WF0995711 205 REMOTE PLANT SECURITY WF1219655 271 WATER RECLAIM/IRRIGATION PH II TBD 212 ROCK P RD S OF CARTER LAKE (AREA 5) WF0805744 216-217 WD FITCH WATER LINE EXTENSION WF1092576 44-45 SCADA - NEW LIFT STATIONS TBD 270 WELL #1 MOTOR CONTROL CENTER REPLACEMENT TBD 193 SCADA REPLACEMENT WF0742950 265 WELL #2 MOTOR CONTROL CENTER REPLACEMENT TBD 194 SOUTH KNOLL / THE GLADE WF10444485 222-223 WELL #3 MOTOR CONTROL CENTER REPLACEMENT TBD 195 SOUTHWOOD 5-7 WF1105424 224-225 WELL #8 WF1097966 183 TAUBER & STASNEY REHAB WF0625893 22-23 WELL #8 COLLECTION LINE WF1097967 184 THE KNOLL REHAB TBD 232-233 WELL #9 TBD 185 USC RENOVATIONS TBD 198-199 WELL #9 COLLECTION LINE TBD 186 VICTORIA AVENUE WF1158560 32-33 WELLBORN WIDENING WF0613546 206 WESTMINSTER SEWER LINE WF0786101 243 WELLS #1 & #3 PUMP/MOTOR REPLACEMENT TBD 190 WILLIAM D FITCH EAST (AREA 6) WF0805756 218-219 WILLIAM D FITCH EAST (AREA 6) WF0805807 218-219 BVSWMA Projects Project # Page Wastewater Projects Work Order # Page RPR Gas Recovery and Final Cover BV0403 284 COLLEGE PARK/BREEZY HEIGHTS WF0595926 18-19 Twin Oaks Access BV0601 295 BARRON ROAD REHAB WF0654332 38-39 Twin Oaks Buildings & Infrastructure BV0602 296 BARRON ROAD WIDENING PH II TBD 40-41 Twin Oaks Cell Construction Phase 2A TBD 289 BEE CREEK PH IV & V WASTEWATER TBD 132-133 Twin Oaks Cell Construction Phase 2B TBD 290 CARTERS CREEK ATAD IMPROVEMENTS WF1104547 258 Twin Oaks Cell Construction Phase I BV0701 288 CARTERS CREEK BAR SCREENS WF1136522 259 Twin Oaks Compost Facility Design and Construction TBD 292 CARTERS CREEK BLOWER BUILDING IMP TBD 263 Twin Oaks Construction Project Management BV0901 294 CARTERS CREEK CENTRIFUGE IMP TBD 262 Twin Oaks Design Services BV0603 287 CARTERS CREEK CLARIFIER IMPROVEMENTS WF1104545 252 Twin Oaks Land Purchase BV0003 285 CARTERS CREEK ELECTRICAL IMPROVEMENTS TBD 276 Twin Oaks Landfill Communications BV0802 291 CARTERS CREEK EQUIPMENT SHED TBD 278 Twin Oaks Permit Application/Legal Fees BV0502 286 CARTERS CREEK FIBER RING TBD 274 Twin Oaks Petroleum Pipeline Relocation TBD 293 302 Index by Project/Work Order Number Project #Streets Projects Page Project #Facility Projects Page ST0006 BARRON ROAD RIGHT OF WAY 37 GG0408 CITY HALL IMPROVEMENTS 112 ST0205 TRAFFIC SIGNAL @ GB DRIVE EAST & DOMINIK 59 GG0522 NORTHGATE RESTROOMS 115 ST0409 BARRON ROAD REHABILITATION 38-39 GG0701 MUNICIPAL FACILITY IMPROVEMENTS 116 ST0411 TRAFFIC SIGNAL COMMUNICATIONS 61 GG0803 NORTHGATE IMPROVEMENTS 113 ST0417 ROCK PRAIRIE RD WIDENING - DESIGN AND ROW 35 GG0903 FIRE STATION #6 117 ST0505 TAUBER AND STASNEY REHAB/NG SIDEWALKS 22-23 GG0905 FIRST STREET FENCING 114 ST0507 COLLEGE PARK/BREEZY HEIGHTS (SOUTHSIDE) 18-19 GG9901 LIBRARY BOOK DONATIONS 109 ST0511 TRAFFIC SYSTEM SAFETY IMPR. 51 GG9905 MEMORIAL CEMETERY 110-111 ST0512 NEW TRAFFIC SIGNAL PROJECTS (2003 GOB) 55 GG1010 LARRY J. RINGER LIBRARY EXPANSION 118 ST0515 COCS BEAUTIFICATION IMPROVEMENTS 68-69 ST0517 SIDEWALK IMPROVEMENTS 70 Project #Technology Projects Page ST0518 NORTHGATE STREET REHAB 20 CO0601 RADIO SYSTEM REPLACEMENT 123 ST0519 OVERSIZE PARTICIPATION 25 CO0603 UPS REPLACEMENT 122 ST0520 WILLIAM D. FITCH PKWY WIDENING PH II 44-45 CO0701 MDT SYSTEM REPLACEMENT 120 ST0521 HIKE AND BIKE TRAILS - LONGMIRE IMPROVEMENTS 67 CO0704 WIRELESS INFRASTRUCTURE 124 ST0530 BIKE LOOP - 2005 - BIKE LOOP COMPLETION 65 CO0801 MISC IT PROJECTS 128 ST0802 MANUEL DRIVE OP 26 CO0901 SERVER CONSOLIDATION 125 ST0804 DISCOVERY DRIVE EXTENSION 28 CO0902 FIBER OPTIC INFRASTRUCTURE 126 ST0809 EAGLE AVENUE EXTENSION 30-31 CO1001 CAD HW OPERATING SYSTEM UPGRADE 127 ST0812 WELLBORN RD LANDSCAPING - 2818 to 40 48 TBD i5 ENHANCEMENT 121 ST0903 VICTORIA AVENUE 32-33 ST0904 HIKE AND BIKE TRAIL COMPLETION 73 Project #Drainage Projects Page ST0905 PENBERTHY BOULEVARD EXTENSION 34 SD0001 BEE CREEK PH. IV & V. 132-133 ST0906 TEXAS AVENUE FIBER 63 SD0523 STORMWATER MAPPING 137 ST0907 VIDEO DETECTION - 2009 50 SD0601 COLLEGE PARK/BREEZY HEIGHTS (SOUTHSIDE) 18-19 ST0908 BIRMINGHAM/LONGMIRE IMPROVEMENTS 53 SD1002 MINOR DRAINAGE IMPROVEMENTS 135 ST0909 LINCOLN/FOSTER IMPROVEMENTS 52 SD0901 MITIGATION FENCING @ ARRINGTON/DECATUR 138 ST0910 LINCLON AVENUE SIDEWALK IMPROVEMENTS 71 SD0904 W. KING COLE CULVERT REPLACEMENT 136 ST0912 NEW SIGNAL WARRANT STUDY 56 SD9903 GREENWAYS PROJECTS 134 ST0913 HOLLEMAN EXTENSION OP 27 ST0914 UNIVERSITY/COPPERFIELD SIGNAL 57 Project #Convention Center Projects Page ST0915 SIGNAL CONTROLLERS FOR FIBER 62 GG0907 CONVENTION CENTER 142 ST0916 SCHOOL ZONE/PEDESTRIAN FLASHERS 54 ST0917 WELLBORN/CAPSTONE SIGNAL STUDY 58 Project #Parkland Dedication Projects Page ST1025 ROCK PRAIRIE RD WEST ROW 36 PK0051 ZONE 1 PARK 147 ST1026 BARRON RD WIDENING PHASE II 40-41 PK0052 ZONE 2 PARK 148 ST1027 NEW TRAFFIC SIGNAL PROJECTS (2008 GOB) 60 PK0053 ZONE 3 PARK 150 ST1028 SIDEWALK IMPROVEMENTS (2008 GOB) 72 PK0054 ZONE 4 PARK 152 ST9803 MISC. BIKE TRAILS - BIKE LOOP COMPLETION 66 PK0055 ZONE 5 PARK 154 ST9915 TX AVE STREETSCAPE PH II 47 PK0056 ZONE 6 PARK 156 TBD BARRON RD EAST/LAKEWAY 42 PK0057 ZONE 7 PARK 158 TBD LICK CREEK HIKE AND BIKE TRAIL 74 PK0058 ZONE 8 PARK 160 TBD UNIVERSITY DR PEDESTRIAN IMPROVEMENTS PH 2-5 75 PK0059 ZONE 9 PARK 161 PK0060 ZONE 10 PARK 162 Project #Parks Projects Page PK0061 ZONE 11 PARK 165 PK0300 FIELD REDEVELOPMENT 82 PK0713 EMERALD FOREST PARK IMP. 88-89 PK0501 VETERANS PARK PHASE II 83 PK0717 ZONE 14 PARK 168 PK0701 ADAMSON POOL BATH HOUSE REPLACEMENT 84 PK0805 STEPHEN C. BEACHY CENTRAL PK POND SW 151 PK0713 EMERALD FOREST IMPROVEMENTS 88-89 PK0806 SOUTHWEST PARK DEVELOPMENT 157 PK0906 CREEK VIEW NEIGHBORHOOD PARK 85 PK0807 ZONE 13 PARK 167 PK0910 NEIGHBORHOOD PARK IMPROVEMENTS 86 PK0808 ZONE 15 PARK 169 PK0911 SKATE PARK 95 PK0824 ZONE 12 PARK 166 PK0912 NEIGHBORHOOD PARKS REVOLVING FUND 96 PK0903 PARKWAY PARK 149 PK0914 PEBBLE CREEK BASKETBALL PAVILION 87 PK0904 JOHN CROMPTON PARK PHASE III 159 PK0917 NEIGHBORHOOD PARK - FENCING 90 PK0905 SOUTHERN OAKS TRAIL AND LIGHTS 163 PK1001 BEACHY CENTRAL PARK IMPROVEMENTS 97 PK0916 WINDWOOD PARK IMPROVEMENTS 153 PK1002 ANDERSON PARK WALKING LOOP 91 PK0922 CASTLE ROCK PARK DEVELOPMENT 164 PK1003 BROTHERS POND PARK - RUNNING SURFACE 92 TBD STEEPLECHASE PARK BENCH 155 WP0901 WOLF PEN CREEK FESTIVAL SITE/WATER FEATURE 103 TBD ZONE 16 PARK 170 TBD EAST DISTRICT MAINTENANCE SHOP REPLACEMENT 100 TBD LEMONTREE PARK SWING SET 94 Work Order #Water Projects Page TBD LICK CREEK NATURE CENTER 101 WF0352553 PARALLEL WELLFIELD COLL LINE PH I 181 TBD LICK CREEK PARK IRON BRIDGE TRAIL COMPLETION 98 WF0353631 DOWLING ROAD TEN MG TANK 187 TBD LINCOLN CENTER ADDITION 99 WF0377324 LAND ACQUISITION - WELLS 182 TBD MERRY OAKS PARK AREA LIGHTS 93 WF0379197 BARRON ROAD WATER SERVICE EXT 207 WF0466439 WATER PLANT SECURITY 197 WF0595915 COLLEGE PARK/BREEZY HEIGHTS 18-19 303 Index by Project/Work Order Number Work Order #Water Projects (con't)Page Work Order #Wastewater Projects (con't)Page WF0613546 WELLBORN WIDENING 206 WF1094676 NANTUCKET GRAVITY SEWER 244 WF0625888 TAUBER AND STASNEY REHAB 22-23 WF1097963 KOPPE BRIDGE LIFT STATION 242 WF0654325 BARRON ROAD REHAB 38-39 WF1104543 CARTERS CREEK GRAVITY THICKENER 260 WF0742940 SCADA REPLACEMENT 196 WF1104545 CARTERS CREEK CLARIFIER IMPROVEMENTS 252 WF0805789 ROCK P RD S OF CARTER LAKE (AREA 5) 216-217 WF1104547 CARTERS CREEK ATAD IMPROVEMENTS 258 WF0805807 WILLIAM D FITCH EAST (AREA 6) 218-219 WF1104553 CARTERS CREEK PROCESS CONTROL IMPROVEMEN 268 WF0995711 WATER RECLAIM/IRRIGATION 205 WF1105424 SOUTHWOOD 5-7 224-225 WF1044480 SOUTH KNOLL/THE GLADE 222-223 WF1129844 CARTERS CREEK LAB AND SCADA BUILDING 267 WF1092576 WD FITCH WATER LINE EXTENSION 44-45 WF1136522 CARTERS CREEK BAR SCREENS 259 WF1095364 EAGLE AVENUE EXTENSION 30-31 WF1142617 LICK CREEK CENTRIFUGE IMPROVEMENTS 256 WF1097966 WELL #8 183 WF1142618 LICK CREEK SLUDGE HOLDING TANK IMPROVEMENT 257 WF1097967 WELL #8 COLLECTION LINE 184 WF1142623 LICK CREEK RETURN ACTIVATED SLUDGE IMP 261 WF1105425 SOUTHWOOD 5-7 REHAB 224-225 WF1142624 LICK CREEK PROCESS CONTROL IMPROVEMENTS 269 WF1111167 RAYMOND STOTZER WEST 208-209 WF1158560 VICTORIA AVENUE 32-33 WF1158553 VICTORIA AVENUE 32-33 WF1219655 REMOTE PLANT SECURITY 271 WF1223117 HIGH SERVICE WATER PUMP IMPROVEMENTS 189 WF1223116 CARTERS CREEK HEADWORKS IMP 253 TBD BARRON ROAD WIDENING PH II 40-41 TBD BARRON ROAD WIDENING PH II 40-41 TBD BEE CREEK PHASES IV & V 132-133 TBD BEE CREEK PH IV & V WASTEWATER 132-133 TBD COMMUNICATIONS INFRASTRUCTURE IMP 201 TBD CARTERS CREEK BLOWER BUILDING IMP 263 TBD COOLING TOWER EXPANSION 191 TBD CARTERS CREEK CENTRIFUGE IMP 262 TBD DISTRIBUTION SCADA 202 TBD CARTERS CREEK ELECTRICAL IMPROVEMENTS 276 TBD EASTGATE REHAB 226-227 TBD CARTERS CREEK EQUIPMENT SHED 278 TBD EMERGENCY ELECTRIC GENERATOR EXP 192 TBD CARTERS CREEK FIBER RING 274 TBD FM 60 WIDENING WATER RELOCATION 214-215 TBD CARTERS CREEK FUELING STATION 266 TBD MCCULLOCH REHAB 228-229 TBD CCWWTP MAINTENANCE BUILDING 277 TBD NANTUCKET EAST OF HARPERS FERRY (AREA 3) 220 TBD COLLEGE STATION SLUDGE FACILITY 264 TBD NORTHGATE REHAB 230-231 TBD EASTGATE REHAB 226-227 TBD OVERSIZED PARTICIPATION 204 TBD LAND ACQUISITION - CCWWTP 272 TBD SCADA MAN MACHINE INTERFACE 200 TBD LAND ACQUISITION - LCWWTP 273 TBD SPPS CHEMICAL SYSTEM REPLACEMENT 188 TBD LICK CREEK GENERATOR REPLACEMENT 275 TBD SH 40 WATER LINE-GRAHAM RD TO BARRON RD 210 TBD LICK CREEK IMPACT FEE LINE 247 TBD SH 40 WATER LINE-IRON HORSE WAY TO VICTORIA 211 TBD LICK CREEK PARALLEL TRUNKLINE PH II 248 TBD THE KNOLL REHAB 232-233 TBD MCCULLOCH REHAB 228-229 TBD USC RENOVATIONS 198-199 TBD NORTHEAST SEWER TRUNKLINE 246 TBD WATER RECLAIM/IRRIGATION PH II 212 TBD NORTHGATE REHAB 230-231 TBD WELLS #1 & #3 PUMP/MOTOR REPLACEMENT 190 TBD OVERSIZE PARTICIPATION 241 TBD WELL #1 MOTOR CONTROL CENTER REPLACEMENT 193 TBD RAYMOND STOTZER WEST 208-209 TBD WELL #2 MOTOR CONTROL CENTER REPLACEMENT 194 TBD SCADA - NEW LIFT STATIONS 270 TBD WELL #3 MOTOR CONTROL CENTER REPLACEMENT 195 TBD THE KNOLL REHAB 232-233 TBD WELL #9 185 TBD USC RENOVATIONS 198-199 TBD WELL #9 COLLECTION LINE 186 Project #BVSWMA Projects Page Work Order #Wastewater Projects Page BV0003 Twin Oaks Land Purchase 285 WF0595926 COLLEGE PARK/BREEZY HEIGHTS 18-19 BV0403 RPR Gas Recovery and Final Cover 284 WF0625893 TAUBER & STASNEY REHAB 22-23 BV0502 Twin Oaks Permit Application/Legal Fees 286 WF0626151 EMERALD PKWY / BENT OAK 250 BV0601 Twin Oaks Access 295 WF0654332 BARRON ROAD REHAB 38-39 BV0602 Twin Oaks Buildings & Infrastructure 296 WF0742950 SCADA REPLACEMENT 265 BV0603 Twin Oaks Design Services 287 WF0786101 WESTMINSTER SEWER LINE 243 BV0701 Twin Oaks Cell Construction Phase I 288 WF0805744 ROCK P RD S OF CARTER LAKE (AREA 5) 216-217 BV0802 Twin Oaks Landfill Communications 291 WF0805756 WILLIAM D FITCH EAST (AREA 6) 218-219 TBD Twin Oaks Cell Construction Phase 2A 289 WF0912284 LICK CREEK PARALLEL TRUNKLINE - PH I 245 TBD Twin Oaks Cell Construction Phase 2B 290 WF0930104 CARTERS CREEK SERVICE WATER IMP 254 BV0901 Twin Oaks Construction Project Management 294 WF1042497 LICK CREEK CLARIFIER CATWALKS 255 TBD Twin Oaks Compost Facility Design and Construction 292 WF10444485 SOUTH KNOLL / THE GLADE 222-223 TBD Twin Oaks Petroleum Pipeline Relocation 293 304