City of College Station
CAPITAL IMPROVEMENTS PROGRAM BUDGET
FOR FISCAL YEAR 2012
OCTOBER 1, 2011 to SEPTEMBER 30, 2012
Home of Texas A&M University ®
TABLE OF CONTENTS
Executive Summary ............................................................................................................. 1
General Government Capital Improvement Projects
Street, Traffic, Sidewalk and Trail Projects ............................................................... 11
Street Rehabilitation Projects ................................................................... 17
Street Extension Projects ......................................................................... 24
Street TxDOT Projects ............................................................................. 41
Traffic Projects ......................................................................................... 44
Sidewalk and Trail Projects ...................................................................... 56
CDBG Funded Street Projects ................................................................. 67
Parks and Recreation Projects .................................................................................. 71
CDBG Funded Parks and Recreation Projects .......................................... 92
General Government Facility and Technology Projects ............................................ 95
Public Facility Projects ................................................................................ 98
Technology Projects .................................................................................. 104
Special Revenue Capital Improvement Projects
Drainage Projects .................................................................................................... 111
Park Land Dedication Projects ................................................................................ 121
Enterprise Funds Capital Improvement Projects
Electric Service Projects ......................................................................................... 149
Water Service Projects ............................................................................................ 153
Production Projects ................................................................................ 158
Distribution Projects ............................................................................... 177
Rehabilitation Projects ........................................................................... 190
Wastewater Service Projects ............................................................................. 203
Collection Projects ............................................................................ 208
Rehabilitation Projects ...................................................................... 216
Treatment Projects ........................................................................... 219
TABLE OF CONTENTS
Estimated Operations and Maintenance (O&M) Costs
General Government Capital Improvement Projects O&M Costs. .......................... 245
Special Revenue Capital Improvement Projects O&M Costs .................................. 246
Enterprise Funds Capital Improvement Projects O&M Costs .................................. 247
Index by Project/Work Order Name .................................................................................... 249
Index by Project/Work Order Number ................................................................................. 251
Fiscal Year 2011 – 2012
Capital Improvements Program Budget
Executive Summary
The following is the annual City of College Station Capital Improvements Program (CIP) Budget document. The CIP budget
provides the framework for capital improvement projects to be conducted in the 2012 fiscal year that begins October 1, 2011
and ends on September 30, 2012.
On an annual basis, the City of College Station prepares a five-year Capital Improvements Program (CIP). The CIP is
presented for City Council review as part of the annual budget process. The program consolidates all anticipated capital needs
for which funding authorization exists, while separating the projects into several sections depending on the services provided
and the respective funding source. Once the budget is approved by the City Council, the assigned project managers manage
their respective projects with budgetary oversight from the Office of Budget and Strategic Planning and the Finance
Department.
Summary capital project schedules have been included in the annual College Station Approved Budget; however, this CIP
budget document permits greater communication among City staff, administration, Council and citizens regarding capital
projects. Areas of enhanced information conveyed within this document include individual project detail pages and
corresponding maps, where applicable. The project sheets detail the project number, project manager, funding source(s),
description of purpose and need, funding per year and category, and the estimated impact, if any, on future operating budgets.
The maps provide citizens and officials a greater understanding of the scope and the impact of the specific projects through
the illustration of the planned action.
The projects presented in this document are grouped according to major funding source. For example, projects for which the
major funding source is the Streets Capital Improvement Projects Fund are included in the Streets, Traffic, Sidewalks and
Trails section of the document. A number of projects included in this document have multiple funding sources. The project
sheets for these projects include an expenditure summary for each funding source as well as a combined expenditure
summary that reflects the total projected expenditures for the project. The project sheets for projects with multiple funding
sources are included in the section of the CIP document that reflects the project’s primary funding source.
CAPITAL PROJECTS FUNDING
The City operates under the laws of the State of Texas and the City of College Station's Home Rule Charter. Two categories
of capital expenditures are defined by the City. The first category of capital expenditure is for major capital projects. Major
capital projects are projects that cost more than $50,000 and provide a fixed asset or equipment that has a useful life of three
years or more. The second category of capital expenditure is for minor capital projects. Minor capital projects are projects
that cost more than $5,000 and less than $50,000 and provide a fixed asset or equipment that has a useful life of three years or
more.
The approved Capital Improvements Budget for FY12 totals $37,349,793 for all funds that include capital projects. This
budget amount does not, however, reflect all projected capital expenditures for FY12. In the case of projects for which funds
have already been approved and budgeted, the City may continue to spend money to complete these projects without
including the projected FY12 expense as a new appropriation. The project budgets that have been appropriated carry forward
until the project is complete. Only portions of the project budgets that have not been previously appropriated are included as
new appropriations in the FY12 budget. The total projected to be spent in FY12 on capital projects including both new
appropriations as well as existing appropriations is approximately $56 million.
The City only has legal authority to issue General Obligation (GO) debt after a successful citizen referendum. GO debt is
debt that obligates the City to repay the issue with ad valorem tax revenues. The City uses GO debt for the acquisition and
development of parks and recreation facilities; rights-of-way acquisition; construction and reconstruction of streets; and for
public buildings such as City offices, libraries, swimming pools and other general use facilities.
The most recent General Obligation bond election was held in November of 2008. Voters approved $76,950,000 in General
Obligation Bond (GOB) authorization to be issued over 7 years for streets, traffic, and fire station projects, the Library
expansion project, and parks projects including an addition at the Lincoln Center and the Lick Creek Park Nature Center. In
November 2003, the citizens of College Station approved $38,405,000 in GOB authorization for street, traffic, police and fire
station projects, the City Center project, and parks projects including the second phase of Veterans Park. A small amount of
the 03 GOB debt remains to be issued.
1
In FY11, the City issued $1,960,000 in GOB debt for various General Government capital projects. Of this, $700,000 was
issued for street, traffic and sidewalk projects. This includes $100,000 for sidewalk improvements. It is anticipated that these
funds will be used for the construction of sidewalks along Lincoln Avenue. $400,000 was included for the Barron Road
East/Lakeway project. $50,000 was issued for the Rock Prairie Road West right-of-way project. In addition, $150,000 was
issued for the Lick Creek Hike and Bike Trail project. $1,260,000 was issued for Parks and Recreation projects. This includes
$100,000 for the master planning related to the Lick Creek Nature Center and $380,000 for various neighborhood park
improvements. Also included was $780,000 for the replacement of the concession and restroom complex at Central Park.
The FY12 Approved Budget includes the projected issuance of $8,045,000 in GO’s. Included is $5,330,000 for street,
sidewalk, traffic and transportation projects. This includes $440,000 for street oversize participation projects. These funds
will be used toward building increased capacity into the streets that are being constructed by developers. $500,000 is
projected to be used toward the construction of the Jones Butler extension. This project includes the design and construction
of a major collector from the intersection of Luther Street & Jones-Butler to the intersection of George Bush & Penberthy
Road. An additional $600,000 has been included for new traffic signal projects throughout the City. An estimated $500,000 is
projected to be issued for the design of the Health Science Center Parkway. These funds will come from the authorization
related to the Barron Road Widening Phase II project. The Barron Road Widening Phase II project is under construction and
is anticipated to come in well below the amount authorized through the GOB. The remaining Barron Road Widening Phase II
authorization in the amount of $990,000 has been projected to be issued in FY12 for other street improvement projects.
Included in this is $567,000 for the Rock Prairie Road Bridge Widening project that was added in FY11. $700,000 is
projected for the Barron Road East/Lakeway project which will extend Barron Road from State Highway 6 east at the
existing Barron Road to a future intersection with the extension of Lakeway Drive. An estimated $200,000 is projected to be
issued for sidewalk projects to be constructed in FY12. The specific projects on which these funds will be used are in the
process of being identified. $250,000 is estimated to be issued for the Rock Prairie Road West right-of-way project. This
project is for the purchase of additional right-of-way from State Highway 6 to Normand Drive to provide for the future
widening of that section of Rock Prairie Road. It is estimated that $450,000 will be issued for the design work related to the
Lick Creek Hike and Bike Trail. Finally, $700,000 is projected for the University Drive Pedestrian Improvement Phase II-IV
project. This project consists of implementing the remaining phases (2 through 5) of the pedestrian improvements on
University Drive. The project is to improve pedestrian travel in the Northgate area of College Station, especially to facilitate
pedestrian movement across and along University Drive between Boyett Street and South College Avenue.
GOB debt in the amount of $2,715,000 is projected for Parks and Recreation projects. $220,000 is included for the purchase
of land for neighborhood parks. $100,000 is estimated to be issued for the completion of the Lick Creek Trail. This park
project is for construction of a compacted gravel trail over the existing dirt trail in Lick Creek Park. $1,645,000 has been
projected for the East District Maintenance Shop Replacement. These funds will be used to replace the existing shop. Finally,
$750,000 is included for design and construction work on the Lick Creek Nature Center.
The City has statutory authority, and City Council policy allows for the use of non-voter authorized debt instruments such as
certificates of obligation and contract obligations (generally referred to as CO's). City Council policy allows the City to use
such instruments for capital items such as the following:
The purchase and replacement of major computer systems and other technology-based items that have useful lives
of not more than ten years.
The purchase and replacement of major equipment items such as fire-fighting equipment. The City has, however,
developed policies and procedures to provide almost all of this equipment without issuing debt.
The purchase of land and development of land for economic development uses.
In the last 3 years, at the recommendation of the City’s financial advisors, the City has issued CO’s in lieu of Utility
Revenue Bonds, for the Electric, Water and Wastewater utilities.
In FY11, the City did not issue any CO debt for General Government projects. $7,835,000 in CO debt was issued in FY11 for
Utility projects. Prior to FY08, Utility Revenue Bond debt had been used for the Utility projects. However, based on the
recommendations from the City’s financial advisors, and due to the marketability of the bonds as well as the volatility of the
bond market, CO debt has been issued for utility projects from FY08 forward. $4,735,000 was issued for Electric projects
and $3,100,000 for Wastewater projects. In addition, $100,000 was issued to cover debt issuance costs.
2
The FY12 Approved Budget includes the issuance of $100,000 in CO debt for General Government projects. This amount
will be used for the Fiber Optic Infrastructure project. This project will support the installation of fiber optic cable to continue
expansion of the city's network to new buildings and facilities, and to permit the connection of existing facilities that are not
currently on the network.
It is anticipated that Certificates of Obligation will be issued in FY12 for Utility capital projects. Funds in the amount of
$6,100,000 are estimated for Water capital projects and funds in the amount of $7,580,000 are estimated for Wastewater
capital projects, and funds in the amount of $8,825,000 are estimated for Electric capital projects.
GOVERNMENTAL CAPITAL PROJECTS
Below are descriptions of the governmental capital projects included in the FY12 Approved Budget. The funds expended on
these projects are considered significant and nonroutine.
STREETS, TRAFFIC, SIDEWALKS AND TRAIL CAPITAL PROJECTS
Street Rehabilitation Projects
In FY12, funds in the amount of $145,384 are included for the Tauber and Stasney Rehabilitation project. These streets
are located in the Northgate area. The project includes the rehabilitation of Tauber Street and Stasney Street from University
Drive to Cherry Street as well as the design and construction of new sidewalks on College Main. The project also includes
the water and wastewater line rehabilitation. The majority of the construction on these streets should be complete in FY11,
but the FY12 estimate reflects remaining expenditures. Other rehabilitation projects estimated for FY12 include the Bird
Pond Rehabilitation project. This project is for the rehabilitation of Bird Pond Road from the city limits to Rock Prairie
Road. Funding for this project will come from the authorization related to the Barron Road Widening Phase II project. The
Barron Road Widening Phase II project is under construction and is anticipated to come in well below the amount authorized
through the GOB. An additional rehabilitation project included in the FY12 Approved Budget is the Cooner Street
Rehabilitation project. This project includes the rehabilitation of paving and water and wastewater lines along Cooner
Street. The project may include concrete pavement, curb, gutter, storm drainage and sidewalks. The majority of the funding
for the Streets component of this project will be from Community Development Block Grant (CDBG) funds. $1,075,634 of
the $1,203,000 Streets budget will be funded with CDBG funds. The balance of the budget will come from Barron Road
Widening Phase II authorization.
Street Extension Projects
$5,302,598 is the estimated expenditure included for various street extension and widening projects. Included in this is
$572,611 for Oversize Participation (OP) projects that may arise throughout the fiscal year. These funds are used for
building increased capacity into the streets that are being constructed by developers. Of this amount, $472,611 is from OP
funds authorized as part of the 2003 GOB. An additional $100,000 of OP funds is budgeted and reflects assessments
expected to be received as a result of the Holleman Extension project. It is estimated that $500,000 in assessments will be
received over the next five years as the area adjacent to Holleman Drive develops. As a significant portion of the Holleman
Extension project budget was funded using OP funds, the received assessments will be earmarked for future OP projects.
These funds will not be available for expenditure until they are received.
Other street extension projects include the extension of Victoria Avenue. It is estimated that $316,519 will be spent in FY12
to extend Victoria Avenue from Southern Plantation Drive to connect with William D. Fitch Parkway (SH40), aligning with
the existing Victoria Avenue on the south side of William D. Fitch Parkway (SH40). The roadway will be a major collector
consisting of two travel lanes and a center turn lane with bike lanes, sidewalks, landscaping and storm drainage. Water and
wastewater upgrades will also be made as part of this project. The project is being completed in advance of the new College
Station ISD (CSISD) high school, which is expected to open in August of 2012. An estimated $575,692 is projected for the
extension of Jones-Butler Drive. This project includes the design and construction of a major collector from the intersection
of Luther Street & Jones-Butler to the intersection of George Bush & Penberthy Road. The project will also include
sidewalks, bike lanes and an equestrian crossing. $500,000 is projected in FY12 for the design of the Health Science Center
Parkway. This project is a component of the Bio-Medical Corridor agreement.
The budget also includes an estimated FY12 expenditure of $931,684 for the Rock Prairie Road East Widening project.
These funds will be used for design and right-of-way acquisition costs related to the future widening of Rock Prairie Road.
Construction funds are not included in the project budget. $266,379 is the projected FY12 expenditure for the Rock Prairie
Road West right-of-way project. This project includes the purchase of additional right-of-way from State Highway 6 to
Normand Drive to provide for the future widening of that section of Rock Prairie Road. Funds have also been estimated for
the design of the Rock Prairie Road Bridge Widening project. This project was added in late FY11. The City of College
Station will design the bridge widening and TxDOT will construct the project. The bridge will be widened to six lanes with
3
U-turn lanes constructed at the north and south ends of the existing bridge. The project will also include sidewalks and bike
lanes or a multi-use path. In addition, acceleration/deceleration lanes will be added along the frontage roads. The design will
be paid for by the City of College Station using the remaining unallocated Barron Road Widening Phase II authorization
(2008 GOB). The construction will be paid for by TxDOT using Proposition 12 funds received from the State that must be
used on bridges and overpasses. Design began late FY11 with construction estimated to begin in FY13.
In addition, $1,125,429 is the estimated FY12 expenditure for the phase II of construction to Barron Road from Decatur
Drive to William D. Fitch Parkway (SH40). This project will widen Barron Road from Decatur Drive to Barron Cutoff Road
on the southwest side of William D. Fitch Parkway (SH40). The existing Barron Road is a two lane rural road. Upon
completion of this project, Barron Road will be expanded to a divided four lane minor arterial roadway with medians, bicycle
lanes and sidewalks. In addition, new traffic signals will be installed at the intersection of Barron Road and Victoria Avenue
and at Barron Road and William D. Fitch Parkway (SH40). This project is anticipated to be completed in advance of the
opening of the new CSISD high school in August of 2012. Finally, $710,000 is included for design work on the Barron
Road East/Lakeway extension project. This project will extend Barron Road from State Highway 6 east at the existing
Barron Road to a future intersection with the extension of Lakeway Drive. The Barron Road extension will be combined with
the Lakeway Drive extension.
Street TxDOT Projects
Projected expenditures include $91,562 for the Wellborn Widening Reimbursement project. As part of an AFA with
TxDOT, the City is required to reimburse 10% of the right-of-way costs associated with the Wellborn Widening project. The
majority of the reimbursement was paid in prior years, but it is anticipated that a final payment will need to be made in FY12.
Traffic Projects
The FY12 Approved Budget includes an estimated $842,574 for traffic projects throughout the City. Funds are included for a
new traffic signal at the intersection of Wellborn and F&B and a signal at the intersection of State Highway 30 and
Copperfield. In addition, $65,000 is included for the design of a signal at FM 2818 and FM 60. $23,790 is included for
traffic system safety improvement projects and $32,536 is included for traffic signal communication projects. These
projects support traffic signal connectivity as well as other City data and voice services.
Sidewalk and Trail Projects
The City of College Station has worked over the years to ensure adequate transportation infrastructure is constructed for
pedestrians and bicyclists. The City has an adopted Bicycle, Pedestrian and Greenways Master Plan. In FY12, $200,000 is
included for sidewalk improvement projects throughout the City. The specific projects on which these funds will be used
are in the process of being identified. $224,000 is estimated to be spent on Phase II of the Hike and Bike Trail Completion
project. This project will continue the 10' wide multi-use trail from Welsh Avenue to the Campus Village trail to the west.
The trail will also be extended from the northern connection of the Campus Village Trail through Southwest Park as part of
the Southwest Park development, providing continuity of the hike & bike trail system from Texas Avenue to Southwest
Parkway. In addition, $508,000 is projected to be used toward the design of the Lick Creek Hike and Bike Trail. This
project is for the construction of approximately three miles of hike and bike trails along Lick Creek between Westfield Park
and Lick Creek Park. The trails will connect residential neighborhoods and CSISD property. An estimated $679,500 will be
spent toward the design of Phase II of the University Drive Pedestrian Improvements project. This project consists of
implementing the remaining phases (2 through 5) of the Pedestrian Improvements on University Drive. The project is
designed to improve pedestrian travel in the Northgate area of College Station, especially to facilitate pedestrian movement
across and along University Drive between Boyett Street and South College Avenue. Finally, funds in the amount of
$637,000 are estimated for the construction of the College Main Plaza Improvements. This project is for the construction of
a pedestrian plaza with bike lane from University Drive to Patricia Street. In addition, intersection improvements will be
made along Lodge Street and Patricia Street. Funding for this project will come from several sources. A portion will come
from the balance of the Discovery Drive project, which is complete and came in under budget. The balance of the budget will
come from Certificates of Obligation (CO’s) issued in prior years for the Police Station Improvements project ($208,707) and
the completion of the 2nd floor of the Municipal Court building ($18,376). Use of these funds is limited to certain types of
projects, but they may be used for the College Main Plaza Improvements project.
PARKS AND RECREATION CAPITAL PROJECTS
In FY12, expenditures in the amount of $2,271,230 are estimated for Parks and Recreation capital improvement projects.
Included is $68,384 for field redevelopment projects. A portion of the funds will be used for replacement and repairs to
numerous athletic facilities and parks throughout the City. The funds for these projects are collected from the fees paid by
players and teams from both City leagues and outside user groups. The funds are used to pay for replacement items and
facility upgrades at City athletic facilities.
4
$81,696 is the estimated expenditure for improvements at University Park. This project will consist of the addition of 14
parking spaces to the existing parking lot. Also included in the project is the addition of a landscape island, sidewalks, curb
and gutter, and relocation of the irrigation system, as needed. Funds in the amount of $293,843 are estimated for the purchase
of park land throughout the City as part of the Neighborhood Parks Revolving Fund project. These funds are used for
acquiring properties for neighborhood parks in advance of development. $792,307 is included for improvements at Stephen
C. Beachy Central Park. These include the construction of a new concession complex and restroom building. An estimated
$100,000 is included for the Lick Creek Park Iron Bridge Trail Completion. This project is for the construction of a
compacted gravel trail over the existing dirt trail in Lick Creek Park. $198,000 has been included for the design of the East
District Maintenance Shop Replacement. These funds will be used to replace the existing shop. Finally, funds are included
for the detailed design of the Lick Creek Nature Center. This center, proposed to be built at Lick Creek Park, will serve as a
nature center for visitors who want to learn more about the park.
GENERAL GOVERNMENT AND CAPITAL EQUIPMENT CAPITAL PROJECTS
General government and capital equipment projects are planned assets that have value to more than one specific area of City
operations. The two main divisions within this category are public facilities and technology projects. Estimated expenditures
for public facility projects in FY12 include $6,349,265 for the construction of Fire Station #6. Fire Station #6 will serve the
busy University Drive corridor. Construction is expected to be completed in FY12. In addition, $599,000 is included in the
budget for the purchase and installation of a Fire Emergency Response Alerting System. This system will replace the fire
station alerting system and the PA systems in stations 1, 2 and 4. A portion of the funding for this system will come from the
balance of budget remaining from the Fire Station #3 Relocation project. Certificates of Obligation in the amount of
$239,409 remain and may be used toward this project. The additional needed budget will come from the balance of the Radio
System Replacement project, which is complete and came in under budget. The budget for the Radio System Replacement
project was a combination of CO debt and Equipment Replacement Funds. Finally, $20,000 is included for the purchase of
library books. The funds for the purchase of these books come from donations collected for this purpose.
The FY12 Approved Budget also includes a projected expenditure of $832,000 for technology projects. Included is $300,000
for the replacement of the City’s Mobile Data Terminal system. This project is for the replacement of the electronic
equipment that provides the interface between the radio frequency system (800 MHz radio system) and the Internet Protocol
system (Computer Aided Dispatch). The goal of the project is to provide a public safety radio system that meets current and
anticipated needs. $122,500 is projected for the Fiber Optic Infrastructure project. This project will support the
installation of fiber optic cable to continue expansion of the city's network to new buildings and facilities, and to permit the
connection of existing facilities that are not currently on the network. An estimated $224,500 is included for the E-mail and
File System Migration project. This project will migrate the city E-mail system from GroupWise to another e-mail system.
The project will also implement a new e-mail archive system and will move file and print management. Finally, $185,000 has
been included for a Network and Data Security Upgrade project. This project will examine city wide data security
standards, policies and procedures and will result in establishing guidelines and business practices that will bring the city
more closely in alignment with industry best practices for information security. These latter two projects, as well as $200,000
of the MDT System Replacement budget, will be funded using a portion of the balance of the Radio System Replacement
project, which is complete and came in under budget.
Finally, funds in the amount of $763,286 will be transferred to the Electric Fund. These funds reflect the balance of the Radio
System Replacement project. In addition, as mentioned in the Sidewalks and Trails section of the Streets Capital overview,
$227,083 will be transferred to the Streets Capital Improvement Projects Fund for use on the College Main Plaza
Improvements project.
SPECIAL REVENUE CAPITAL PROJECTS
Below are descriptions of the special revenue capital projects included in the FY12 Approved Budget. The funds expended
on these projects are considered significant and non-routine.
Drainage Capital Improvement Projects
Drainage capital projects are funded by revenue generated through a drainage utility fee that is collected from residential and
commercial utility users. Significant Drainage capital projects include a projected $355,000 for Greenways land acquisition
throughout the City. The City’s Greenways Master Plan calls for future trail development in urban and suburban greenways.
The funds for this project were from prior years’ debt issue. $200,000 is included for Minor Drainage Improvement
projects. These funds are used for minor unscheduled drainage projects that arise throughout the fiscal year. $286,000 is
included for Erosion Control in the Wolf Pen Creek trail area. Bank stabilization measures will be designed and
constructed to protect the trails, irrigation, benches and other improvements in the upper trails area from erosion. An
estimated $50,070 is included for Stormwater Mapping projects. These funds will be used for mapping of the City’s
5
stormwater infrastructure. Finally, $500,000 is included for the completion of a Drainage Master Plan. The results of the
study will be an inventory of existing infrastructure and a twenty (20) year maintenance and infrastructure improvement plan
for those portions of the drainage basins that lie within the city limits. The plan will form the foundation for future
infrastructure projects.
Park Land Dedication Capital Improvement Projects
The Park Land Dedication Funds account for the receipt and expenditure of funds received by the City from residential land
developers who dedicate land, or money in lieu of land, for use in the development of neighborhood parks in residential
areas. The projects in the Park Land Dedication Capital Improvement Projects Funds are funded using the dedicated park
land funds.
Park Land dedication funds must be used for the development of parks within the zone to which the funds are dedicated. In
FY12, expenditures for Park Land Dedication projects are estimated at $1,420,175 for projects that are anticipated to be
completed in the various park zones. Funds in the amount of $4,895 are included for improvements at University Park.
These improvements will include additional parking and a retaining wall at the large dog pond. The Park Land Dedication
funds for this project will be supplemented with Neighborhood Park Improvement bond funds. An estimated $36,000 is
included for improvements at Carter Crossing Park. The park will be constructed in phases as funds become available and
is planned to ultimately include sidewalks, an entry plaza, a tot playground, creek crossings, benches and trees with
irrigation. $208,280 is the FY12 estimated expenditure for improvements at Southwest Park. This phase of the project will be
the construction of a 10 foot wide hike and bike trail through Southwest Park. The trail will connect with the north end of the
Campus Village Trail and will continue to Southwest Parkway. The project will include a bridge crossing, retaining wall,
and box culverts. The project will be designed in-house by Public Works staff. It is estimated that $10,000 will be spent in
FY12 for phase III of John Crompton Park. The total project budget for this phase is $149,000. The FY12 expenditure
reflects the estimate of what is needed to complete this phase of the project. Additional funds are projected in a number of
Park Land zones but these funds have not yet been obligated to specific projects. These funds are available to be used for
projects that arise throughout the year within the applicable zones. Funds not used in the fiscal year will carry over to future
fiscal years.
Wolf Pen Creek TIF Capital Projects
The Wolf Pen Creek (WPC) TIF Fund accounts for ad valorem tax and other revenues that are accrued to the WPC TIF
District. The fund also accounts for expenditures on projects that take place in the district. The TIF expired on December 31,
2009. A balance of approximately $3.2 million remains in the WPC TIF Fund. A determination will be made in FY12 as to
how the remaining balance will be spent.
UTILITY CAPITAL PROJECTS
Below are descriptions of the utility capital projects included in the FY12 Approved Budget. The funds expended on these
projects are considered significant and nonroutine.
Electric Capital Projects
$9,571,100 is the approved budgeted appropriation for electric capital projects in FY12. Funds in the amount of $3,000,000
are budgeted for Production projects in FY12. It is anticipated that these funds will be used for a methane gas production
project at the Brazos Valley Solid Waste Management Agency (BVSWMA) landfill. $650,000 is included for General Plant
projects. These include the replacement of the mapping system, enhancements to the SCADA system and plant upgrades.
Also included is $250,000 for the design of renovations to the Utility Service Center Building. Funds in the amount of
$1,160,000 are estimated for Overhead System Improvement projects. These funds will be used for the construction of
overhead feeder extensions and upgrades of existing overhead electric infrastructure. This includes the annual utility pole
replacement program. Funds in the amount of $1,150,000 are estimated for Underground System Improvement projects.
These funds will be used for the construction of new underground electric projects and for conversion of overhead power
lines to underground. $1,380,000 is included in the approved budget for New Service and System Extension projects.
These funds will be used to provide electrical system services for new customer additions (residential, commercial,
apartments and subdivisions). $95,000 is included in the approved budget for Residential Street Lighting projects. These
funds are used for new residential street lighting projects and improvement to existing residential street lighting. Funds in the
amount of $150,000 are estimated for Thoroughfare Street Lighting projects. These funds will be used are for new
thoroughfare street lighting projects and improvements to existing thoroughfare street lights. $759,000 is included in the
approved budget for Distribution projects and $1,175,000 is included for Transmission projects. These funds will be used
for the construction of electric transmission and distribution projects to provide electric capacity to the City of College
Station. Major substation replacement equipment is included in this funding.
6
The FY12 Approved Budget includes a projected debt issue of $8,825,000 for Electric Utility capital projects.
Water Capital Projects
In FY12, $8,456,117 is the approved new appropriation included for water capital projects. Appropriations from prior years
carry forward on capital projects. In some cases, the total new appropriations exceed the total estimate for capital
expenditures because the new appropriations may cover not only the current fiscal year, but future fiscal years as well. The
new appropriations included for FY12 exceed the FY12 projected expenditures for this reason. Total expenditures in FY12
for Water capital projects are projected to be $8,033,942. Water Production projects include an estimated FY12 expenditure
of $5,728,440. $800,000 is included for the purchase of land for future well sites. As capacity needs grow, the City is
preparing for the construction of new wells. A component of this is the land acquisition for new future wells. An estimated
$418,000 is included for the Sandy Point Chemical System Replacement project. The chemical feed and storage facilities
at Sandy Point Pump Station require upgrading to accommodate current expansion of the water production infrastructure and
to be in compliance with current fire codes. As part of the project, the existing chlorine disinfection system will be replaced
to improve personnel safety, operating reliability and cost efficiency. $3,116,645 is included for high service water pump
improvements. This project will increase the pumping capacity of the Dowling Road Pump Station. This project is in
response to analysis of the water system capacities in relation to Texas Commission on Environmental Quality (TCEQ)
requirements. It is anticipated that these improvements will be completed in FY13. $625,000 is included in the approved
budget for the Cooling Tower Expansion project. This project is for the design and construction of an additional water
cooling tower and all of the associated appurtenances to connect this new equipment into the existing system. The additional
tower is needed to meet the increased production capacity of the water system. $371,295 is included for the completion of the
3 Million Gallon Ground Storage Reservoir (MG GSR) Rehabilitation project. As part of this project, the interior
coating of the reservoir will be replaced and some structural upgrades will be made to ensure that it meets TCEQ guidelines.
In addition, $45,000 is included for the design of the same improvements at the 5 Million Gallon Ground Storage
Reservoir (MG GSR). $37,500 is included for the design of renovations at the Utility Service Center. The cost of the
renovations is being shared by the Electric, Water and Wastewater utilities as all three are housed in this facility. It is
anticipated that the renovations will occur in future fiscal years. $25,000 is projected for the continuation of the Supervisory
Control and Data Acquisition (SCADA) man machine interface project. This project is for the evaluation, procurement
and implementation of software packages available to improve the SCADA man machine interface or graphical software.
New servers are included to increase flexibility and reduce vulnerabilities and down time. An additional $50,000 is included
for Well #7 Fiber. This project is for the installation of fiber from Sandy Point pump station to Water Well #7 to create
wireless access point for Water Wells #5, #6, #8 and future wells. Finally, $240,000 is included for the Water Redundant
Communications project. This project is for data communication improvements. These improvements will allow for built-in
redundancy, wireless communications, mobile work force and unforeseen communication plans not related to construction
projects. The main focus is to construct fiber loops which provide multiple paths to all facilities.
Funds in the amount of $997,500 are projected to be expended on Water Distribution projects in FY12. This includes
$100,000 of general Oversize Participation (OP) funds. These funds are used to help meet future capacity needs by
oversizing water lines above the minimum size required to serve a development. $557,000 is the projected FY12 expenditure
for the Wellborn Widening project. This project was for the relocation of water lines outside of pavement areas in
conjunction with Wellborn Widening. This final phase should be completed in FY12. A portion of the expenditures for this
project will be reimbursed by TxDOT. It is estimated that approximately $1,000,000 will be received in FY13 following the
completion of the project. Approximately $2,400,000 was received in FY10 for a portion of the project that has already been
completed. $108,500 is the estimated FY12 expenditure for the Raymond Stotzer West Water Line project. This project is
for the design and construction of water infrastructure to provide service to an area that was annexed by the City of College
Station in 1995. This area is near the intersection of Raymond Stotzer West and FM 2818. In addition, $137,000 is included
for the City of Bryan Raymond Stotzer Phase I water line. This project will consist of the construction of a 12" waterline
along Health Science Center Parkway from FM 47 to Turkey Creek Road, and for the construction of a 16" waterline along
F&B Road from Turkey Creek Road to FM 2818. This project will be designed and constructed by the City of Bryan, but
will be paid for by the City of College Station. This project is a component of the Bio-Medical Corridor agreement. Finally,
$95,000 is estimated in FY12 for the construction of an 8-inch water distribution line to serve the necessary fire protection
for the approved Carter Creek Wastewater Treatment Plant (CCWWTP) Lab/SCADA building.
Rehabilitation projects included in the FY12 Approved Budget include $634,150 for the South Knoll/The Glade project.
This project is for the replacement of water lines in the area bounded by Haines, Southwest Parkway, Glade and Langford.
These aging lines were identified in a 2003 water study as in need of replacement. In addition, $78,534 has been included for
the completion of the Southwood 5-7 project. Construction on this project began in FY11 and should be completed in FY12.
This project is for the replacement of water lines in an area bounded by Southwest Parkway, Harvey Mitchell Parkway,
Welsh and Shadowood. Other rehabilitation projects include the Cooner Street Rehabilitation project and the Plantation
Oaks Water Line Rehabilitation project. The Cooner Street Rehabilitation project includes the rehabilitation of water and
7
wastewater lines and paving along Cooner Street from Texas Avenue to the street terminus. The water distribution lines are
in need of replacement due to an increase in service disruptions caused by deteriorating lines. The FY12 estimate is for the
design of the project. Funding for the majority of the cost of the project design will come from Community Development
Block Grant funds. Construction of the water portion of the project, which will follow in FY13, will be paid for with water
utility revenue. The Plantation Oaks Water Line Rehabilitation project is for the rehabilitation of a 12-inch water line along
Harvey Rd, between Scarlett O’Hara Drive and Munson Avenue. This segment of the line is being replaced due to continuing
failures that are causing service disruptions to customers in this area.
Contingency in the amount of $150,000 has been included in the FY12 Approved Budget. These funds will be available for
use on unanticipated projects as well as to offset project overruns. Finally, $150,000 has been included for the meter
replacement program that was implemented in FY08. This program is for the replacement of water meters on a routine basis
to ensure efficient water readings.
The FY12 Approved Budget includes an estimated $1,950,000 in current revenues that will be transferred from operations to
fund water capital projects. Additionally, a debt issue of $6,100,000 is projected in FY12 for Water capital projects.
Wastewater Capital Projects
The FY12 Approved Budget includes $4,815,757 in new appropriations for numerous wastewater capital projects.
Appropriations from prior years carry forward on capital projects. Therefore, the projected expenditures exceed the new
appropriations included for FY12. Total expenditures in FY12 for Wastewater capital projects are projected to be $9,144,828.
Wastewater Collection projects include $100,000 for oversize participation and planning. These funds are available to
meet future anticipated capacity in the construction of wastewater lines above the minimum size needed to serve the
development. An estimate of $325,000 is included for the East Side FM 158 Sewer Line project. This project will construct
gravity sewer lines, lift station and forced main to serve properties along FM 158 south of the intersection with FM 30 in
service territory acquired from the City of Bryan and within the City of Bryan's corporate limits. This project is the result of a
service territory swap coordinated as part of the Bio-Medical Corridor agreement. Design of the line is estimated to begin in
FY12 with construction following in FY13 and FY14. $44,965 has been estimated in FY12 for upgrades to the wastewater
infrastructure that are being completed as part of the Victoria Avenue Extension project. In FY12, $934,758 is the
estimated expenditure for the Scott and White Sewer Line/Lift Station project. This project consists of the design,
construction, and land acquisition required for a new lift station facility (on the Scott & White property) and a force main
along State Highway 6 that will connect to the Spring Creek trunk line. Funding for this project will come from the Economic
Development Fund, from Scott and White and from wastewater utility revenue. Funding is also included in the FY12
approved budget for the design of the Bee Creek Parallel Trunkline. The existing Bee Creek Trunkline sub-basin currently
serves areas along FM2818, from areas north of Wellborn Road to the Carters Creek Wastewater Treatment Plant. This
project will install a gravity line to increase the system capacity of the Bee Creek Trunkline sub-basin to accept the ultimate
build-out demand anticipated in this respective area. This project is expected to span several years with construction being
completed in FY14. $225,000 is included in the approved budget for the design of the FM 2154 Sewer Trunkline. This
project is for the design, easement acquisition and construction of a gravity sanitary sewer line along the east side of
FM2154, a lift station in the proximity of the intersection of FM2154/Greens Prairie Trail and a force main along the south
side of Greens Prairie Trail. This project is also expected to span several fiscal years, with completion estimated for FY15.
Rehabilitation projects included in the FY12 Approved Budget include South Knoll/The Glade. This project is for the
replacement of wastewater lines in the area bounded by Haines, Southwest Parkway, Glade and Langford. These aging lines
were identified in a 2003 water study as in need of replacement. In addition, $136,331 has been included for the completion
of the Southwood 5-7 project. Construction on this project began in FY11 and should be completed in FY12. This project is
for the replacement of wastewater lines in an area bounded by Southwest Parkway, Harvey Mitchell Parkway, Welsh and
Shadowood. Also included in the FY12 Approved Budget is the Cooner Street Rehabilitation project. The Cooner Street
Rehabilitation project includes the rehabilitation of water and wastewater lines and paving along Cooner Street. The sanitary
sewer lines are in need of replacement due to an increase in service disruptions caused by deteriorating lines. The FY12
estimate is for the design of the project. Funding for the majority of the cost of the project design will come from Community
Development Block Grant funds. Construction of the wastewater portion of the project, which will follow in FY13, will be
paid for with wastewater utility revenue. Finally, funds in the amount of $309,029 are included in the approved budget for the
Northeast Trunkline Rehabilitation. A study conducted in 2010 identified major defects within the Northeast Trunkline.
The intent of this project is to repair/replace the most critical segments of this interceptor.
Funds in the amount of $3,271,047 have been estimated for Treatment and Disposal projects. $924,509 is included for the
Carter Creek Headworks Improvements project. This project will replace or refurbish components of the existing
headworks that have become unserviceable. $167,000 is the projected expenditure for the construction of catwalks around
the Lick Creek clarifiers. The catwalks will provide safe access for the operators to operate and maintain the clarifiers. An
8
estimated $155,000 is included for centrifuge improvements at the Lick Creek Wastewater Treatment Plant (LCWWTP).
Improvements include installing a larger sludge discharge hopper, a sludge conveyor and a work platform around the
centrifuge. $156,100 is included for completion of the Lick Creek Sludge Holding Tank Improvements. This project will
ultimately expand the size of the waste sludge holding tank at the Lick Creek Wastewater Treatment Plant. An additional
$168,438 is estimated for the completion of the Lick Creek Return Activated Sludge Modifications project. The Return
Activated Sludge Pumps are not consistently pumping return activated sludge at an appropriate rate. This is a critical function
essential to meeting TCEQ mandated treatment requirements. This project will reconfigure the sludge piping so that the
pumps will perform acceptably. $200,000 is included for the Lick Creek Sludge Blower Replacement project. This project
will replace the current blower units which are at the end of their service life. New blowers are needed to maintain quality of
sludge during storage prior to dewatering. $850,000 is included for the Lick Creek Centrifuge Replacement project. This
project will replace the sludge dewatering centrifuge at the LCWWTP. The current centrifuge has exceeded its useful life. An
estimated $650,000 is included for the Carter Creek Digested Sludge Aerator Replacement project. This project will
replace the current aeration diffusers in Digested Sludge Holding Tanks #1 and #2 at the CCWWTP. Continued failures of
the existing diffusers make replacement essential.
Funds in the amount of $34,768 are estimated for the SCADA replacement project. This project will replace the control
equipment that has exceeded its useful life. $592,808 is the projected expenditure for the completion of the Carters Creek
Lab and SCADA Building project. The existing building no longer meets laboratory standards. In addition, $99,006 is
estimated for Process Control Improvements at LCWWTP. This project will be for the purchase and installation of
improved process control instrumentation at the Plant. An additional $117,259 has been included in FY12 for the installation
of SCADA at the new lift stations. This will allow for monitoring and alarming of the new lift stations. $120,000 is included
for the Carter Creek Fiber Ring project. This project will provide for data communication improvements that will allow
for built-in redundancy, wireless communications, mobile work force, and unforeseen communication plans not related to
construction projects. The main focus is to construct fiber loops which provide multiple paths to all facilities. $37,500 is
included for the design of renovations at the Utility Service Center. The cost of the renovations is being shared by the
Electric, Water and Wastewater utilities as all three are housed in the facility. It is anticipated that the renovations will occur
in future fiscal years. Finally, $111,172 is included for the Aggie Acres Fiber Optic Conduit project. This project will
connect the Aggie Acres lift station in the ETJ to the City's sewer system.
Finally, contingency in the amount of $150,000 has been included in the FY12 Approved Budget. These funds will be
available for use on unanticipated projects as well as to offset project overruns.
A total of $1,120,000 in current revenues from operations is estimated to be used to fund Wastewater capital projects.
Additionally, a debt issue of $7,580,000 is projected in FY12 for wastewater capital projects.
Additional O&M Costs
The FY12 Approved Budget includes a number of capital projects that have been recently completed and have added
operations and maintenance (O&M) expense. In particular, the City’s General Fund has been and will continue to be
impacted by capital projects as they come online. In some situations, the O&M cost of a project is minimal and can be
absorbed by the City department that is benefiting the most from the project. In other situations, the O&M cost is more
significant and funding for these additional expenses is addressed through the Service Level Adjustment (SLA) process. In
these situations, SLAs are submitted for the O&M needs of the capital projects and funding is considered as part of the
budget process.
Departments are expected to consider the impact of current and planned capital improvement projects on operations and
maintenance (O&M) budgets. This analysis is a component of the 5-year Strategic Business Plans that are completed by all
City departments. Projections as to the impact of capital projects on O&M budgets that are included in the Strategic Business
Plans are used by the Finance Office in financial forecasting.
Due to the limited availability of funds for FY12, increases in budgets for O&M related to capital projects were minimal.
Instead, departments were asked to evaluate current operations and make adjustments that would allow service levels to be
met without a corresponding increase in budget. It is anticipated that the availability of funding for the O&M costs,
particularly in the General Fund, will be limited in upcoming years. Therefore, departments will continue to evaluate current
operations before increases in budget will be approved. Recommendations may also be made to delay projects for which
O&M funding does not exist.
Governmental Projects O&M
The FY12 Approved Budget includes funds that will be used toward the anticipated O&M costs associated with the opening
of Fire Station #6. A total of $1,853,555 has been included in the FY12 budget for this purpose. This includes the salary and
benefits for the hiring of ambulance crew (nine personnel) and an engine crew (nine personnel). Nine of these positions were
9
approved as part of the FY11 Approved Budget, but the positions were not filled due to the delay in the construction of the
fire station. The remaining nine positions will be added to the FY12 budget as part of the SLA process. Other O&M costs
related to Fire Station #6 that are in the budget include budget for various supplies and maintenance, as well as purchased
services such as utility costs.
The FY12 Approved Budget also includes budget for O&M costs associated with several street projects. Budget for street
sweeping, landscaping and irrigation has been included in the Public Works base budget for the Tauber and Stasney
Rehabilitation project, the Holleman Extension project, the Victoria Avenue Extension project and the Royder Road project.
In addition, budget for the utility costs associated with several new traffic signals, as well as budget for maintenance of
several hike and bike trails, is also included in the Public Works base budget.
Finally, included in the approved Parks and Recreation base budget are funds for the O&M costs associated with the Skate
Park, as well as budget for the maintenance costs associated with the improvements at Emerald Forest Park.
Special Revenue Projects O&M
Funds have been included in the FY12 Approved Parks and Recreation base budget for estimated O&M costs associated with
several Special Revenue capital projects. $15,000 has been included to cover estimated supply and landscaping costs in
Southwest Park. In addition, $150 has been included for electric utility costs related to the Rain Water Harvesting project that
is anticipated will be completed in FY11. Finally, $92,000 has been for estimated O&M costs associated with capital projects
in the WPC TIF area. Estimated costs include funds for temporary/seasonal personnel, supplies, contract labor and utility
costs.
Utility Projects O&M
The City of College Station strives to provide superior electric, water, and wastewater services to its citizens. Part of this
effort includes investment in the capital that makes up the infrastructure. These investments take place in the form of capital
improvement projects. Some of these improvements require additional operating and maintenance (O&M) costs. These costs
are identified and ultimately become part of the cost of providing these utility services. In some situations, the O&M cost of a
project is minimal and can be absorbed by the City department that is benefiting the most from the project. In these
situations, SLAs are submitted for the O&M needs of the capital projects and funding is considered as part of the budget
process (i.e. for additional personnel). In some situations the anticipated O&M cost is added to the base budget (i.e.
additional budget for utility costs).
Several increases were made to the FY12 base budget for additional O&M costs related to new capital projects. Funds in the
amount of $20,000 were included in the Water Production O&M budget for the electric utility costs related to phase I of the
Water Reclamation project. This project should be completed in FY11. Budget was also included in the Water Production
O&M budget for electric utility costs related to Well #8. Finally, budget was included in the Wastewater Treatment O&M
budget for electric utility costs related to the Carters Creek Service Water Improvements project.
More detailed sheets that reflect the estimated O&M costs associated with the capital projects have been included in the final
section of the CIP document.
10
GENERAL GOVERNMENT-
STREETS, TRAFFIC, SIDEWALK AND TRAIL
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH
FISCAL YEAR 2016-2017
11
GENERAL GOVERNMENT
STREETS, TRAFFIC, SIDEWALKS, AND TRAILS CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT REVISED APPROVED
PROJECT BUDGET APPROPRIATIONS FY 10 - 11 FY 11 - 12
NUMBER AMOUNT THROUGH FY10 APPROPRIATIONS APPROPRIATIONS
BEGINNING FUND BALANCE:17,758,173 7,431,751
ADDITIONAL RESOURCES:
GENERAL OBLIGATION BONDS (03 GOB)440,000 440,000
GENERAL OBLIGATION BONDS (08 GOB)2,960,000 4,890,000
CERTIFICATES OF OBLIGATIONS - -
INTERGOVERNMENTAL TRANSFERS - 227,083
INTRAGOVERNMENTAL TRANSFERS - 555,000
INVESTMENT EARNINGS 160,000 25,000
OTHER - -
SUBTOTAL ADDITIONAL RESOURCES 3,560,000$ 6,137,083$
TOTAL RESOURCES AVAILABLE 21,318,173$ 13,568,834$
STREET REHABILITATION PROJECTS
1/2 TAUBER AND STASNEY REHAB/NG SIDEWALKS ST0505 2,760,523 2,760,523 - -
3 BIRD POND ROAD REHABILITATION ST1112 1,800,000 1,800,000 - -
1/3 COONER STREET REHAB ST1201 1,203,000 - - 164,000
CLOSED PROJECTS
SUBTOTAL 4,560,523$ -$ 164,000$
STREET EXTENSION PROJECTS
2 OVERSIZE PARTICIPATION (OP)ST0519 472,611 - 472,611 -
* OP (HOLLEMAN ASSESSMENT)ST1204 500,000 - - 100,000
2 HOLLEMAN EXTENSION ST0913 2,125,000 2,125,000 - -
3 VICTORIA AVENUE EXT ST0903 2,455,000 2,455,000 - -
3 JONES BUTLER (PENBERTHY) EXTENSION ST0905 3,283,500 369,365 2,914,135 -
3 ROYDER ROAD IMPROVEMENTS ST1037 1,000,000 1,000,000 - -
3 HEALTH SCIENCE CENTER PARKWAY ST1205 2,500,000 - - 2,500,000
ROCK PRAIRIE ROAD PROJECTS -
2 ROCK PRAIRIE RD WIDENING - DESIGN & ROW ST0417 2,969,000 2,969,000 - -
3 ROCK PRAIRIE RD WEST ROW ST1025 740,000 115,000 - 250,000
** ROCK PRAIRIE RD BRIDGE WIDENING DESIGN ST1118 567,000 567,000 - -
BARRON ROAD PROJECTS -
3 BARRON ROAD WIDENING PHASE II ST1026 5,363,779 7,801,145 - -
3 BARRON ROAD EAST/LAKEWAY ST1101 15,135,000 190,000 210,000 1,100,000
*** CLOSED PROJECTS - -
SUBTOTAL 17,591,510$ 3,596,746$ 3,950,000$
STREET TXDOT PROJECTS
WELLBORN WIDENING REIMBURSEMENT ST0510 780,633 780,633 - -
NORTHGATE PEDESTRIAN IMPROVEMENTS AFA ST1117 274,570 274,570 - -
CLOSED TXDOT PROJECTS - -
SUBTOTAL 1,055,203$ -$ -$
BUDGET APPROPRIATIONS
12
GENERAL GOVERNMENT
STREETS, TRAFFIC, SIDEWALKS, AND TRAILS CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT
EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED
THROUGH FY09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY 16-17
13,747,959 21,886,547 7,431,751 2,751,417 1,138,832 537,252 286,252 155,512
1,080,000 - 440,000 - - - - -
11,445,000 700,000 4,890,000 14,355,000 15,800,000 600,000 600,000 -
- - - - - - - -
5,500 291,290 227,083 - - - - -
- 55,790 555,000 1,020,634 100,000 100,000 44,210 -
21,033 72,000 25,000 25,000 10,000 5,000 4,000 2,000
6,415 - - - - - - -
12,557,948$ 1,119,081$ 6,137,083$ 15,400,634$ 15,910,000$ 705,000$ 648,210$ 2,000$
26,305,907$ 23,005,628$ 13,568,834$ 18,152,051$ 17,048,832$ 1,242,252$ 934,462$ 157,512$
477,846 146,103 1,991,190 145,384 - - - - -
- - 175,000 1,625,000 - - - - -
- - - 154,000 1,049,000 - - - -
118,209 - - - - - -
477,846$ 264,311$ 2,166,190$ 1,924,384$ 1,049,000$ -$ -$ -$ -$
- - - 472,611 - - - - -
- - - 100,000 100,000 100,000 100,000 100,000
77,364 910,186 1,137,450 - - - - - -
78,105 122,709 1,937,667 316,519 - - - - -
7,769 58,689 214,205 575,692 2,427,145 - - - -
- 44,278 955,722 - - - - - -
- - - 500,000 2,000,000 - - - -
747,026 4,607 354,000 931,684 931,683 - - - -
- 34,721 54,629 266,379 384,271 - - - -
- - 500 226,300 226,800 113,400 - - -
- 104,350 4,134,000 1,125,429 - - - - -
- - 330,000 710,000 4,614,320 9,480,680 - - -
724,975 1,557,749 269,007 77,984 - - - -
1,635,238$ 2,837,289$ 9,387,180$ 5,302,598$ 10,684,219$ 9,694,080$ 100,000$ 100,000$ -$
453,680 - 235,391 91,562 - - - - -
- - 274,570 - - - - - -
978,193 160,858 99,247 3,875
1,431,872$ 160,858$ 609,208$ 95,437$ -$ -$ -$ -$ -$
PROJECTED EXPENDITURES
13
GENERAL GOVERNMENT
STREETS, TRAFFIC, SIDEWALKS, AND TRAILS CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT REVISED APPROVED
PROJECT BUDGET APPROPRIATIONS FY 10 - 11 FY 11 - 12
NUMBER AMOUNT THROUGH FY10 APPROPRIATIONS APPROPRIATIONS
BUDGET APPROPRIATIONS
TRAFFIC PROJECTS
2 TRAFFIC SYSTEM SAFETY IMPR.ST0511 43,203 43,203 - -
2 SIGNAL @ BARRON/SH40 ST1029 75,000 75,000 - -
2/3 SIGNAL @ TEXAS/KRENEK TAP ST1105 200,000 200,000 - -
SIGNAL @ GB DRIVE EAST & DOMINIK ST0205 170,000 170,000 - -
3 NEW TRAFFIC SIGNAL PROJECTS (2008 GOB)ST1027 1,904,198 - 292,698
3 SIGNAL @ WELLBORN/F&B ST1031 250,000 250,000 - -
2/3 SIGNAL @ SH30/COPPERFIELD ST1106 525,000 286,248 238,752 -
2/3 SIGNAL WARRANT STUDY ST1107 42,000 28,450 13,550 -
3 SIGNAL @2818/FM 60 ST1207 380,000 - - -
3 SIGNAL @ UNIVERSITY DR/UNIVERSITY TOWN CTR TBD 100,000 - - -
2 TRAFFIC SIGNAL COMMUNICATIONS ST0411 90,091 90,091 - -
CLOSED PROJECTS
SUBTOTAL 1,142,992$ 545,000$ -$
SIDEWALKS & TRAILS
2005 BIKE LOOP - BIKE LOOP COMPLETION ST0530 327,202 327,202 - -
MISC. BIKE TRAILS - BIKE LOOP COMPLETION ST9803 169,000 169,000 - -
2 HIKE AND BIKE TRAILS - LONGMIRE IMPROVEMENTS ST0521 1,033,624 1,033,624 - -
3 SIDEWALK IMPROVEMENTS (2008 GOB)ST1028 200,000 - - 200,000
2/3 LINCOLN SIDEWALKS ST0910 249,167 249,167 - -
3 HIKE AND BIKE TRAIL COMPLETION ST0904 749,000 749,000 - -
3 HIKE AND BIKE TRAIL COMPLETION PHASE II ST1103 251,000 251,000 - -
3 LICK CREEK HIKE AND BIKE TRAIL ST1104 4,410,000 - 100,000 563,000
3 UNIVERSITY DR PEDESTRIAN IMP Ph II ST1206 7,055,000 - - 829,500
COLLEGE MAIN PLAZA IMPROVEMENTS ST1113 692,000 692,000 - -
CLOSED PROJECTS
SUBTOTAL 3,470,993$ 100,000$ 1,592,500$
CAPITAL PROJECTS SUBTOTAL 27,821,221$ 4,241,746$ 5,706,500$
OTHER 779,228 -
DEBT ISSUANCE COSTS 12,000 35,000
GENERAL & ADMIN. CHARGES 377,517 368,924
TOTAL EXPENDITURES 5,410,491$ 6,110,424$
CAFR Adjustment
ENDING FUND BALANCE:15,907,682$ 7,458,410$
* Estimated $500,000 to be received through future assessments related to Holleman Extension project. Funds will not be available for expenditure until they are received.
**Project added to FY11 Revised Budget. Budget transferred from Barron Rd Widening Phase II.
***FY12 closed Projects includes balance of ST0804 ($73,984) - Discovery Drive Extension.
1 - Funded through CDBG Funds.
2 - Indicates projects funded through 2003 G.O. Bond Authorization
3 - Indicates projects funded through 2008 G.O. Bond Authorization
14
GENERAL GOVERNMENT
STREETS, TRAFFIC, SIDEWALKS, AND TRAILS CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT
EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED
THROUGH FY09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY 16-17
PROJECTED EXPENDITURES
- - 19,413 23,790 - - - - -
138 40,524 34,338 - - - - - -
- - 200,000 - - - - - -
33,373 - 136,627 - - - - - -
- - - 11,248 120,000 600,000 600,000 572,950 -
- - - 250,000 - - - - -
- - 65,000 460,000 - - - - -
- - 42,000 - - - - - -
- - - 65,000 315,000 - - - -
- - - - 100,000 - - - -
27,555 - 30,000 32,536 - - - - -
6,713 304,422 111,832 - - - - -
67,778$ 344,946$ 639,210$ 842,574$ 535,000$ 600,000$ 600,000$ 572,950$ -$
- - 327,202 - - - - - -
59,063 - 109,937 - - - - - -
820,519 39,770 173,335 - - - - - -
- - - 200,000 - - - - -
82 254 248,831 - - - - - -
41,392 126,501 581,107 - - - - - -
- - 27,000 224,000 - - - - -
- - 50,000 508,000 1,151,000 2,701,000 - - -
- - - 679,500 3,194,000 3,181,500 - - -
- - 55,000 637,000 - - - - -
14,112 230,544 34,932 - - - - - -
935,168$ 397,069$ 1,607,344$ 2,248,500$ 4,345,000$ 5,882,500$ -$ -$ -$
4,547,903$ 4,004,473$ 14,409,132$ 10,413,493$ 16,613,219$ 16,176,580$ 700,000$ 672,950$ -$
20,585 779,228 - - - - - -
11,846 8,000 35,000 50,000 60,000 6,000 6,000 -
566,845 377,517 368,924 350,000 275,000 250,000 100,000 100,000
4,603,749$ 15,573,877$ 10,817,417$ 17,013,219$ 16,511,580$ 956,000$ 778,950$ 100,000$
184,389
21,886,547$ 7,431,751$ 2,751,417$ 1,138,832$ 537,252$ 286,252$ 155,512$ 57,512$
15
Home of Texas A&M University ®
16
STREET REHABILITATION PROJECTS
17
PROJECT:Tauber/Stasney Rehab and Northgate Sidewalks
FUND(S):PROJECT NUMBERS & BUDGET:
139 - Streets Capital Fund Streets:ST0505 $2,760,523
238 - Water Capital Fund Water:WF0625888 $296,403
239 - Wastewater Capital Fund Wastewater: WF0625893 $450,626
Total Project Budget:$3,507,552
PROJECT
MANAGER:Edward McDonald
FUNDING
PROJECT SOURCES:Streets - CDBG, GOB's
CLIENT:Public Works W/WW - Long Term Debt/Utility Revenue
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 105,915 399,773 224,457 832 730,978
2010 11 2 631 190 2 631 190
PROJECT SCOPE
Project includes new concrete pavement, storm sewers, water lines, wastewater lines, sidewalks and street trees along Tauber and Stasney
meeting the requirement of the UDO. Construct sidewalks along the west side of College Main from Cherry to Louise meeting the
requirements of the UDO. The project also contains funds budgted from IT & electric for work outside outside the project scope for the
placement of conduit in the area for future fiber and electrical service.
This project is for the rehabilitation of Tauber and Stasney Street from University Drive to Cherry Street. This project will include eight foot
sidewalks to be placed on the east and west sides of Stasney between University Drive and Church Avenue. This project also includes the
rehabilitation of water and wastewater lines in the Northgate area, in the vicinity of Tauber Street and Stasney Street. Several sanitary sewer
lines are in need of replacement due to an increase in service disruptions caused by deteriorating lines, shallow lines, and poor access. The
water distribution lines are in need of replacement due to an increase in service disruptions caused by deteriorating lines and inadequate fire
protection due to the existence of smaller lines within the respective area.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
2010-11 - - 2,631,190 - 2,631,190
2011-12 - - 145,384 - 145,384
2012-13 - - - - -
2013-14 - - - - -
2014-15 - - - - -
2015-16 - - - - -
2016-17 - - - - -
832$ PROJECT TOTAL 3,507,552$ 105,915$ 399,773$ 3,001,031$
18
Streets Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 105,915 292,744 224,457 832 623,949
2010-11 1,991,190 1,991,190
2011-12 145,384 145,384
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Streets Total 105,915$ 292,744$ 2,361,031$ 832$ 2,760,523$
Water Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 21,403 - - 21,403
2010-11 275,000 275,000
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Water Total -$ 21,403$ 275,000$ -$ 296,403$
Wastewater Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 85,626 - - 85,626
2010-11 365,000 365,000
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016 17
PROJECT:
PROJECT CALENDAR OF EXPENDITURES BY FUND
Tauber/Stasney Rehab and Northgate Sidewalks
2016-17 -
Wastewater Total -$ 85,626$ 365,000$ -$ 450,626$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$ 7,500$
-
-
-
-
-
7,500
$105,915
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
$832 $0 $3,507,552PROJECT TOTAL $399,773 $3,001,031
First Fiscal Year Estimated Annual
One Time Costs Recurring Cost
19
PROJECT:Bird Pond Rehabilitation PROJECT #: ST1112
PROJECT
FUND(S): 139- Streets BUDGET:$1,800,000
PROJECT FUNDING
MANAGER: Edward McDonald SOURCES: 2008 GOB
PROJECT
CLIENT: Public Works-Streets
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 - 175,000 - - 175,000
2011-12 - - 1,625,000 - 1,625,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 175,000$ 1,625,000$ -$ 1,800,000$
Personnel (Salaries/Benefits)
Sli
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
Rehabilitation of Bird Pond Road from the city limits to Rock Prairie Road. Proposed Design is for a 2-lane major collector of a rural/estate cross
section as called for within the Comprehensive Plan.
PROJECT SCOPE
Rehabilitation of Bird Pond Road from the city limits to Rock Prairie Road. Proposed Design is for a 2-lane major collector of a rural/estate cross
section as called for within the Comprehensive Plan.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
5,000
-
-
-
5,000
Fm
2154H arvey R dWilliam D. Fitch PkwyR dRock Prairie Rd
Fr
os
t Dr
Bird P o n d R dBradley RdFoxfi r e D rW o o d c r e e k DrHarris DrS H
6
SSebesta RdOlden LnC arter Lake D rHu
n
ti
n
g
t
o
n
D
rFreneau DrFinney
20
Home of Texas A&M University ®
21
PROJECT:Cooner Street Reconstruction
FUND(S):Water Capital Projects PROJECT NUMBERS & BUDGET:
Wastewater Capital Projects Streets:ST1201 $1,203,000
Streets Capital Projects Water:WF1440709 $446,000
Wastewater: WF1440708 $657,000
Total Project Budget:$2,306,000
PROJECT
MANAGER:Jeff Haeber
FUNDING
PROJECT SOURCES:CDBG Funds
CLIENT:Water Services / Public Works Utility Revenue
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 - - - - -
PROJECT SCOPE
Approximately 2,200 LF of 12-inch Water Line, Approximately 100 LF of 8-inch Water Line, Approximately 2,000 LF of 15-inch Sanitary
Sewer Collection Line, Approximately 250 LF of 6-inch Sanitary Sewer Collection Line, and Street Reconstruction utilizing concrete
pavement, curb, gutter, underground storm drain, and sidewalks.
This project includes the rehabilitation of water and wastewater lines and paving along Cooner Street. The sanitary sewer lines are in need
of replacement due to an increase in service disruptions caused by deteriorating lines. The water distribution lines are in need of
replacement due to an increase in service disruptions caused by deteriorating lines. The project may include; concrete pavement, curb,
gutter, storm drainage, and sidewalks.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
2011-12 - 264,000 - 27,000 291,000
2012-13 - 30,000 1,958,000 27,000 2,015,000
2013-14 - - - - -
2014-15 - - - - -
2015-16 - - - - -
2016-17 - - - - -
54,000$ PROJECT TOTAL 2,306,000$ -$ 294,000$ 1,958,000$
LIONS LIONS Nimitz StUniversity Dr ECooner StEi
senhower StJane StAsh StPoplar StTurner StLive Oak StMacarthur StPeyton StPoplar StF
m 2154Harvey RdWilliam D. Fitch Pkwy22
Streets Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 - - - - -
2011-12 - 145,000 - 9,000 154,000
2012-13 - 10,000 1,030,000 9,000 1,049,000
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Streets Total -$ 155,000$ 1,030,000$ 18,000$ 1,203,000$
Water Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 - - - - -
2011-12 - 46,000 - 9,000 55,000
2012-13 - 10,000 372,000 9,000 391,000
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Water Total -$ 56,000$ 372,000$ 18,000$ 446,000$
Wastewater Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 - - - - -
2011-12 - 73,000 - 9,000 82,000
2012-13 - 10,000 556,000 9,000 575,000
2013-14 -
2014-15 -
2015-16 -
PROJECT:
PROJECT CALENDAR OF EXPENDITURES BY FUND
Cooner Street Reconstruction
2016-17 -
Wastewater Total -$ 83,000$ 556,000$ 18,000$ 657,000$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
1,880
-$ 1,880$
-
-
-
One Time Costs Recurring Cost
-
-
$0
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
$54,000 $0 $2,306,000PROJECT TOTAL $294,000 $1,958,000
First Fiscal Year Estimated Annual
23
STREET EXTENSION PROJECTS
24
PROJECT:Oversize Participation PROJECT #: ST0519
FUND(S):139 - Streets CIP Fund PROJECT
BUDGET: $472,611
PROJECT FUNDING
MANAGER:Alan Gibbs SOURCES: 2003 GO Bonds
PROJECT
CLIENT:Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 - - - - -
2011-12 - - 472,611 - 472,611
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 472,611$ -$ 472,611$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Parent Project Funds provided for City-wide oversize participation projects.
Original project budget = $2,700,000.
$516,569 transferred to Corsair/AMS Street Extension (ST0612) in FY06.
$23,431 transferred to Waterwood OP in FY06.
$187,569 transferred back from ST0612 in FY07.
$27,004 transferred to ST0802 - FY08.
$256,046 transferred back from ST0612 in FY09
$740,000 transferred to ST0913 in FY10
$1,364,000 transferred to ST0913 in FY10
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e S
W
ellb
orn R
d
Fm 158
25
PROJECT:Oversize Participation PROJECT #: ST1204
(Holleman Assessment)
FUND(S): 139 - Streets CIP Fund PROJECT
BUDGET: $500,000
PROJECT FUNDING
MANAGER: Alan Gibbs SOURCES: Holleman Assessment
PROJECT
CLIENT:Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 - - - - -
2011-12 - - 100,000 - 100,000
2012-13 - - 100,000 - 100,000
2013-14 - - 100,000 - 100,000
2014-15 - - 100,000 - 100,000
2015-16 - - 100,000 - 100,000
2016-17 -
PROJECT TOTAL -$ -$ 500,000$ -$ 500,000$
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
The specific Oversize Participation projects on which these funds will be used will be determined as the projects are developed.
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
It is estimated that $500,000 in assessments will be received in the next five years as the areas adjacent to Holleman Drive develop. As a
significant portion of the Holleman Extension project was funded using Oversize Participation (OP) funds, the received assessments will be
earmarked for future OP projects. This project will be used to track the assessments received as well as the resultant OP expenditures.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
-
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e S
W
ellb
orn R
d
Fm 158
26
Home of Texas A&M University ®
27
PROJECT: Holleman Extension
FUND(S): PROJECT NUMBERS & BUDGET:
139 - Streets Capital Fund Streets:ST0913 $2,125,000
238 - Water Capital Fund Water: WF1254634 $118,027
Total Project Budget:$2,243,027
PROJECT
MANAGER:Daniel Beamon
FUNDING
PROJECT SOURCES:Streets - GOB
CLIENT:Public Works Water - Long Term Debt/Utility Revenue
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 34,864 1,029,812 352
2010-11 - 44,000 1,133,999 -
2011-12 - - - -
2012-13 - - - -
2013-14 - - - -
2014-15 - - - - -
PROJECT SCOPE
1,177,999
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
This project is for the extension of Holleman Drive so that it connects to Jones Butler which would provide access to FM 2818 at the
signalized intersection with Holleman. As part of this project, a water line will be extended.
-
-
-
1,065,028
2014 15
2015-16 - - - -
2016-17 - - - -
-
-
PROJECT TOTAL 2,243,027$ -$ 78,864$ 2,163,811$ 352$
Fm 2154
Harvey Mitchell Pkwy SWell
b
o
rn
R
dHol
l
eman Dr WJones-butl
er
RdC h ristin e L n
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyTe
x
a
s
Av
e
SW
ell
b
orn R
d
Fm 158
28
Streets Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 34,864 952,334 352 987,550
2010-11 - 44,000 1,093,450 - 1,137,450
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Streets Total -$ 78,864$ 2,045,784$ 352$ 2,125,000$
Water Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - 77,478 - 77,478
2010-11 40,549 40,549
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Water Total -$ -$ 118,027$ -$ 118,027$
-$ 78,864$ 2,163,811$
PROJECT:
PROJECT CALENDAR OF EXPENDITURES BY FUND
Holleman Extension
PROJECT TOTAL
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
352$ 2,243,027$
First Fiscal Year Annual Estimated
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
First Fiscal Year Annual Estimated
One Time Costs Recurring Cost
-$ -$
4,810
29
PROJECT:Victoria Avenue Extension
FUND(S):PROJECT NUMBERS & BUDGET:
139 - Streets Capital Fund Streets:ST0903 $2,455,000
238 - Water Capital Fund Water:WF1158553 $228,375
239 - Wastewater Capital Fund Wastewater: WF1158560 $47,000
Total Project Budget:$2,730,375
PROJECT
MANAGER:Donald Harmon
FUNDING
PROJECT SOURCES:Streets - 08 G.O.B.: $2,455,000
CLIENT:Public Works W/WW - URB
Water Services / Stephen Maldonado, Jr
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 203,439 223 7,587 211,249
PROJECT SCOPE
The roadway will be a major collector consisting of two travel lanes and a center turn lane with bike lanes, sidewalks, landscaping, and storm
drainage. Water and wastewater line upgrades will also be made as part of this project.
This project will extend Victoria Avenue from Southern Plantation Drive to connect with State Highway 40, aligning with the existing Victoria
Avenue on the south side of State Highway 40.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Prior Years 203,439 223 7,587 211,249
2010-11 - 121,656 2,066,694 14,257 2,202,607
2011-12 - 13,296 301,223 2,000 316,519
2012-13 - - - - -
2013-14 - - - - -
2014-15 - - - - -
2015-16 - - - - -
2016-17 - - - - -
23,844$ PROJECT TOTAL 2,730,375$ -$ 338,391$ 2,368,140$
Victoria AvenueSt
a
t
e
Hwy
6
Fm 2154R o c k P ra irie R d
Fm
2
1
5
4Harvey RdWilliam D. Fitch PkwyTexas Ave SW
el
l
b
o
rn
R
d
Fm 158
30
Streets Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 193,227 - 7,587 200,814
2010-11 - 119,656 1,803,754 14,257 1,937,667
2011-12 - 13,296 301,223 2,000 316,519
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Streets Total -$ 326,179$ 2,104,977$ 23,844$ 2,455,000$
Water Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 8,177 223 - 8,400
2010-11 - 2,000 217,975 - 219,975
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Water Total -$ 10,177$ 218,198$ -$ 228,375$
Wastewater Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 2,035 - - 2,035
2010-11 - - 44,965 - 44,965
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
PROJECT:
PROJECT CALENDAR OF EXPENDITURES BY FUND
Victoria Avenue Extension
2015 16
2016-17 -
Wastewater Total -$ 2,035$ 44,965$ -$ 47,000$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$ 4,425$
-
-
-
-
-
4,425
$0
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
$23,844 $0 $2,730,375PROJECT TOTAL $338,391 $2,368,140
First Fiscal Year Estimated Annual
One Time Costs Recurring Cost
31
PROJECT:Jones Butler (Penberthy) Extension PROJECT #: ST0905
FUND(S): 139 - Streets Capital Projects Fund PROJECT
BUDGET: $3,283,500
PROJECT FUNDING
MANAGER: Jeff Haeber SOURCES: 2008 General Obligation Bonds
PROJECT
CLIENT: Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 64,502 - 1,956 66,458
2010-11 203,750 10,455 214,205
2011-12 64,300 500,000 11,392 575,692
2012-13 64,300 2,349,180 13,665 2,427,145
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 396,852$ 2,849,180$ 37,468$ 3,283,500$
Design, bidding, and construction of approximately 2,100 LF of a concrete curb and gutter roadway with necessary storm sewer extensions.
A bridge class culvert will need to be installed for the White's Creek Tributary crossing along with a livestock crossing underneath the
roadway.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
This project makes an important connection between high density student housing and TAMU campus. Penberthy will extend from Luther /
Jones-Butler intersection across TAMU property to the George Bush / Penberthy intersection. The project will require an equestrian
crossing to accommodate university operations. A traffic signal will need to be installed at the George Bush / Penberthy Intersection.
Original budget = $3,275,000; $8,500 transferred from ST0507 - FY09
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
4,233 -$
Recurring Cost
-
-
One Time Costs
4,233
-
- We
ll
b
o
r
n
Rd
Harve y M i t c h e l l Pkwy S
Jones-butler R
dWel
s
h Av
e
Olsen Blvd
Christin e L n
Penberth
y
B
l
v
d Village DrDis
c
o
v
ery D
r
D
etroit StRes
e
arc
h Pkwy
B
arbara Bu s h D r
Arizona StBurt StFm
2
1
5
4Harvey RdW illia m D. Fitch PkwyT
exa
s A
ve S
W
ellb
o
rn R
d
Fm 158
32
PROJECT:Royder Road Improvements PROJECT #: ST1037
FUND(S): 139 - Streets CIP PROJECT
BUDGET: $1,000,000
PROJECT FUNDING
MANAGER: Jeff Haeber SOURCES: 2008 General Obligation Bonds
PROJECT
CLIENT: Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 44,278 - - 44,278
2010-11 - 77,163 $857,562 20,996 955,722
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 121,441$ 857,562$ 20,996$ 1,000,000$
Engineering, bidding, and construction administration of Royder Rd / Greens Prairie Trail Improvements.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual First Fiscal Year
This project will make partial improvements to Royder Road to facilitate the new elementary school at the corner of Royder Road and
Greens Prairie Trail. The improvements to Royder Road include partial drainage improvements, partial curb and gutter roadway, and new
driveways into the school site. The improvements to Greens Prairie Trail include drainage improvements, deceleration lane into the school,
and a left turn lane into the school site. The intersection at Royder and Greens Prairie Trail will be improved with concrete pavement to
better withstand the increased traffic.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
2,886 -$
Recurring Cost
-
-
One Time Costs
2,886
-
- Fm 2154Harvey RdWilli am D. Fitch PkwyArrington RdRoyder RdGr e e n s P ra irie Rd WFm 2154Gus Roy Rd33
PROJECT:Health Science Center Parkway PROJECT #: ST1205
FUND(S): 139 - Streets Capital Projects Fund PROJECT
BUDGET: $2,500,000
PROJECT FUNDING
MANAGER: TBD SOURCES: 2008 General Obligation Bonds
(Barron Rd Ph II authorization)
PROJECT
CLIENT: Public Works
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 500,000 500,000
2012-13 2,000,000 2,000,000
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 500,000$ 2,000,000$ -$ 2,500,000$
Personnel (Salaries/Benefits)
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
This project is a result of an agreement with the City of Bryan for the joint development of The Reseach Valley BioCorridor. The purpose of
the BioCorridor — an economic development endeavor believed to be of monumental proportions — is to attract bio-related industries that
develop life-changing medical technologies.
PROJECT SCOPE
This project is for the extension of the Health Science Center Parkway.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
- F & B RdR a y m o n d S to tz er PkwyTurkey Creek RdS H 47 / R.s . P k w y Re
se
a
r
c
h
Pkwy
College Station S H 6 SF
r
ont
age 6
Rd E
R ock Prairie Rd
Fm
21
54Harvey RdWelsh AveF & B RdTexas AveFm 158
S H 6 S
City of Bryan
City of CS
34
PROJECT:Rock Prairie Road East Widening PROJECT #: ST0417
Design & ROW
FUND(S):139 - Street Capital Projects PROJECT
BUDGET: $2,969,000
PROJECT FUNDING
MANAGER: Jeff Haeber SOURCES: 2003 GOB's
PROJECT
CLIENT: Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 11,526 729,117 - 10,990 751,633
2010-11 320,000 30,000 4,000 354,000
2011-12 925,319 6,365 931,684
2012-13 925,318 6,365 931,683
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 2 182 163$759 117$$27 720$2 969 000$
Acquire the necessary ROW to widen Rock Prairie Road east of SH6 from a rural two-lane roadway to the functional classification shown in
the Thoroughfare Plan-SH 6 to Bird Pond is a 4-lane major arterial; Bird Pond to bradley is a 2-lane major collector; Bradley to William D.
Fitch is a 4-lane minor arterial.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
This project is for design services related to the widening of Rock Prairie East to a minor arterial section as shown on the Thoroughfare
Plan from SH 6 Frontage Road to W.D. Fitch Parkway. This includes design for the minor arterial section, sidewalks, storm drain facilities,
lighting plan, etc. This budget also includes funds for all Right of Way (ROW) acquisition for the full minor arterial section. The project
consists of design and ROW only. No funds are included in this budget for construction. Bleyl & Associates was awarded the engineering
design by the City Council on February 10, 2005 for $795,000. This is a professional services contract for the engineering design for the
proposed widening of Rock Prairie Road to a minor arterial from Highway 6 to W.D. Fitch Parkway. The conceptual design will include
topographic and utility surveys and provide an assessment of the interrelationship between rights-of-way, utilities, existing easements and
drainage. The contract includes development of plans, specifications and final cost estimates. It will also provide survey work and legal
descriptions for purchase of right-of-way.
PROJECT SCOPE
PROJECT TOTAL 2,182,163$ 759,117$ -$ 27,720$ 2,969,000$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
-
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
35
PROJECT:Rock Prairie Road West ROW PROJECT #: ST1025
FUND(S):139 - Streets Capital Projects Fund PROJECT
BUDGET: $740,000
PROJECT FUNDING
MANAGER: Jeff Haeber SOURCES: 2008 General Obligation Bonds
PROJECT
CLIENT:Public Works
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 34,721 - - 34,721
2010-11 46,601 8,028 54,629
2011-12 248,707 9,644 8,028 266,379
2012-13 376,243 8,028 384,271
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 624,950$ 90,966$ -$ 24,085$ 740,000$
Personnel (Salaries/Benefits)
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
This project includes the purchase of additional right-of-way from State Highway 6 to Normand Drive to provide for the future widening of that
section of Rock Prairie Road.
PROJECT SCOPE
Acquire right-of-way along Rock Prairie Road from State Highway 6 to Normand to allow for improvements to Rock Prairie Road in the future
when TxDOT or the City improves the Rock Prairie Road Interchange.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
Fm
2
1
5
4Harvey RdWi llia m D. Fitch PkwyTexas Ave S
W
ellbor
n Rd
Fm 158
R o c k P ra ir ie R d
S H 6 S
Front
a
g
e
6
Rd EPi
er
r
e Pl
To d d T rlNormand
D
r AlleyGail PlA ust in Ave
A r n o ld R d
P in o n D rSandy CirS u s s e x D r
36
PROJECT:Rock Prairie Road Bridge Widening Design PROJECT #: ST1118
FUND(S):139 - Street Capital Projects PROJECT
BUDGET: $567,000
PROJECT FUNDING
MANAGER: Jeff Haeber SOURCES: 2008 GOB
(Barron Rd Widening Ph II
PROJECT authorization)
CLIENT: Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years
2010-11 500 500
2011-12 211,600 14,700 226,300
2012-13 211,600 15,200 226,800
2013-14 105,800 7,600 113,400
2014-15 -
2015-16 -
PROJECT TOTAL -$ 529,000$ -$ 38,000$ 567,000$
Personnel (Salaries/Benefits)
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
This project is for the engineering services of the Rock Prairie Road Bridge Improvements. The bridge will be expanded from its current
condition to increase capacity across the bridge and improve vehicular movements along State Highway 6 at this corridor. An environmental
assessment of the area in question may be required. In addition to the bridge, the design services may also include facilities for pedestrians
and bicyclists to cross the bridge, median improvements, traffic signal improvements, and stand alone U-Turn bridge structures north and
south of the main bridge structure.
PROJECT SCOPE
Expand the Rock Prairie Road Bridge from its existing condition to increase capacity as identified in a Traffic Study by Kimley Horn &
Associates, Inc.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
()
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
F
m
2154Harvey RdW illiam D. Fitch PkwyL
o
n
g
mi
r
e Dr Fr
ont
age 6
Rd ER o ck P rairie R d
Ear
l Rudde
r
Fwy SFr
ont
ag
e
6
R
d
WS H
6
SB irm in g h am R dOnra
mp 6 N
R a m p
37
Barron Road Widening Phase 2
FUND(S): 139 - Streets Capital Projects Fund PROJECT NUMBERS & BUDGET:
238 - Water Capital Fund Streets: ST1026 $5,363,779
Water: WF1332871 $50,000
Total Project Budget: $5,413,779
PROJECT
MANAGER:Daniel Beamon
FUNDING
PROJECT SOURCES:2008 General Obligation Bonds
CLIENT:Public Works W/WW - Long Term Debt/Utility Revenue
Water Services (Ed Savage)
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 38,085 8,911 57,355
2010-11 - 34,000 4,150,000 -
2011-12 - 43,000 1,082,429 -
2012 13
1,125,429
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
PROJECT SCOPE
This project includes the upgrade of Barron Road from a two lane rural highway to a four lane road with sidewalks, raised center median,
landscaping, storm sewers and street lighting. In 2003, voters approved funds for the design of this section of roadway as well as to
purchase necessary right of way. In 2008, voters approved funds to construct Barron from Decatur Drive to William D Fitch Parkway.
The upgrade of Barron Road will include landscaping, street lighting, and raised median center. This project includes the addition of
signals at Barron/Victoria and Barron/SH40. The project will also include some improvements to the water system. Water lines and
meters will be relocated as required. The water portion of the project will be funded by Water Capital Projects Fund.
104,350
4,184,000
2012-13 - - - -
2013-14 - - - -
2014-15 - - - -
2015-16 - - - -
2016-17 - - - -
PROJECT TOTAL 5,413,779$ -$ 115,085$ 5,241,340$ 57,355$
-
-
-
-
- Fm 2154W i l l i a m D F i t c h P wBarron RdDecatur DrVi
ct
or
i
a AvFm
2
1
54Harvey RdWilliam D. Fitch PkwyTexas Ave SWe
ll
b
o
r
n
R
d
Fm 158
38
Streets Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 38,085 8,911 57,355 104,350
2010-11 34,000 4,100,000 4,134,000
2011-12 43,000 1,082,429 1,125,429
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Streets Total -$ 115,085$ 5,191,340$ 57,355$ 5,363,779$
Water Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 50,000 50,000
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Water Total -$ -$ 50,000$ -$ 50,000$
$0
First Fiscal Year Annual Estimated
$115,085
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
$5,241,340 $5,413,779
PROJECT:
PROJECT CALENDAR OF EXPENDITURES BY FUND
PROJECT TOTAL $0
Barron Road Widening Phase 2
$57,355
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
First Fiscal Year Annual Estimated
One Time Costs Recurring Cost
-$ -$
11,000
39
PROJECT:Barron Road East/Lakeway Drive
FUND(S): 139 - Streets Capital Projects Fund PROJECT NUMBER: ST1101
PROJECT BUDGET: $15,135,000
PROJECT
MANAGER: Edward McDonald
FUNDING
PROJECT SOURCES: 2008 General Obligation Bonds
CLIENT:Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 - 320,000 - 10,000 330,000
2011-12 - 685,000 - 25,000 710,000
2012-13 - 105,800 4,483,520 25,000 4,614,320
2013-14 - 100,000 9,330,680 50,000 9,480,680
2014-15 - - - - -
2015-16 - - - - -
2016-17 - - - - -
PROJECT SCOPE
110,000$
This project is the extension of Barron Road from SH 6 east at the existing Barron Road to a future intersection with the extension of
Lakeway. The Barron extension will be combined with the Lakeway extension. The portion of Lakeway included extends from its intersection
with Barron southward to connect to Lakeway that will be built by private development.
PROJECT DESCRIPTION
PROJECT TOTAL 15,135,000$ -$ 1,210,800$ 13,814,200$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
-$ 11,543$
11,543
-
-
One Time Costs Recurring Cost
-
-
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Estimated Annual
Fm
2
1
5
4Harvey RdWi llia m D. Fitch PkwyTexas Ave S
W
ellb
orn R
d
Fm 158
Lakeway Dr.B a rro n R d
S H 6 SF
r
o
nt
age
6
R
d
E
Rock Prairie Rd
Barron RdL
o
n
g
mire Dr
D
ec
atur Dr William D. Fitch PkwySpe
ar
m
an DRitchey RdAgate DrOfframp 6 SNorfolk Ct40
STREET TXDOT PROJECTS
41
PROJECT: Wellborn Rd Widening PROJECT #: ST0510
FUND: 139 - Streets Capital Projects PROJECT
BUDGET: $780,633
PROJECT FUNDING
MANAGER: TBD SOURCES: Streets Capital Projects Fund
Funds for this project are designated to pay the City's portion of right-of-way costs for TxDot's Wellborn
Road Widening project.
FISCAL YEAR LAND ENG. CONSTR. MISC.PROJECT TOTAL
Prior Years - - - 453,680 453,680
2010-11 - - - 235,391 235,391
2011-12 - - - 91,562 91,562
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
TOTAL -$ -$ -$ 780,633$ 780,633$
Total
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
OPERATING COSTS
First Fiscal Year Annually Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0
First Fiscal Year Annually
$0 $0
42
PROJECT:Northgate Pedestrian PROJECT #: ST1117
Improvements AFA
FUND(S):139 - Streets Capital Projects Fund PROJECT
BUDGET: $274,570
PROJECT FUNDING
MANAGER: Troy Rother SOURCES: Transfer from ST0804
PROJECT
CLIENT: Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc OH Project Total
Prior Years - - - - -
2010-11 274,570 274,570
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ -$ 274,570$ -$ 274,570$
PROJECT DESCRIPTION
During the March 24, 2011, City Council Workshop, an item was presented to the City Council describing this project and through the
corporative efforts between the City of College Station, TxDOT, TAMU, and the Northgate Merchants improves pedestrian safety in the
Northgate area. At the City Council Meeting, a Memorandum of Understanding (MOU) between the City and the Northgate Merchant
Association was approved by the City Council.The current construction cost estimated developed by TxDOT for this project is $2,274,570.
The TxDOT budget for the project is $2 Million. Some additional features added to the project by the City of College Station. These additional
features were included in an AFA that was approved by Council on June 23, 2011. This project reflects the expenditure for this AFA.
PROJECT SCOPE
Some additional features added to the project by the City of College Station include retractable bollards (identified early in the project as a
necessity to allow for emergency vehicle access), a traffic barrier along University Drive between College Main and Boyett (an item included
in the MOU), and powder coated signal poles at Boyett and University Drive (City standard).
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
University DrR o s s S tChurch AveFirst St Na
g
l
e
S
t
Boyett StCherry StTaube
r
St
W
ellb
orn R
d N St
asney S
t
B
izz
e
ll StPo lo RdSpence StIreland St
Jone s S tAsbury StSpruce StAgronomy Rd
C o ke St
L a m a r S tR a mp
Bizzell St
La
m
ar S
t
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e S
W
ellb
orn R
d
Fm 158
43
TRAFFIC PROJECTS
44
PROJECT:Traffic System Safety Improvements PROJECT #: ST0511
FUND(S):139 - Streets CIP Fund PROJECT
BUDGET: $43,203
PROJECT FUNDING
MANAGER:Lee Robinson SOURCES: 2003 GOB - $500,000
PROJECT
CLIENT: Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 19,413 19,413
2011-12 23,790 23,790
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 43,203$ -$ 43,203$
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
This project serves to hold funds for traffic system safety improvement projects. Original budget was $500,000. This project serves as a
holding account for new traffic safety improvements projects. These funds are critical to meeting needs that arise throughout the year.
Median improvements have been made to improve safety at high crash locations. Intersection improvements have been made to improve
signal operation and safety. Pedestrian improvements have been made at intersections to facilitate safety near schools. As new projects are
created, funds will be allocated to those projects and this project balance will be reduced.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
Recurring Cost
-
-
One Time Costs
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e S
W
ellb
orn R
d
Fm 158
45
PROJECT: Barron/SH40 Signal PROJECT #: ST1029
FUND: 139 - Streets CIP Fund PROJECT
BUDGET: $75,000
PROJECT
MANAGER:Troy Rother FUNDING
SOURCES: 2008 GO Bonds - ST1027
PROJECT
CLIENT: Public Works
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 4,753 35,909 - 40,662
2010-11 34,338 34,338
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
TOTAL -$ 4,753$ 70,247$ -$ 75,000$
PROJECT DESCRIPTION
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
This project is for the installation of a signal at the intersection of Barron and State Highway 40. An additional $150,000
is budgeted for this signal as part of the Barron Rd Widening Phase II project (ST1026). The funds from ST1030 will be
used for advance equipment purchases.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$ 2,045$
2,045
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Annual Estimated
One Time Costs Recurring Cost
Fm
2
1
5
4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell
b
o
r
n
R
d
Fm 158
Barron RdS H
40 / William D Fitch Pkwy
R
en
ee LnVictoria AveEagle AvePassendale LnDelrey Dr
I
ncour
t
La
neJamey LnS H 40 / William D Fitch Pkw y
46
PROJECT:Krenek Tap/Texas Avenue Signal PROJECT #: ST1105
FUND(S):139 - Streets CIP Fund PROJECT
BUDGET: $200,000
PROJECT FUNDING
MANAGER:Troy Rother SOURCES: 2008 GO Bonds - ST1027
PROJECT
CLIENT:Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 200,000 200,000
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 200,000$ -$ 200,000$
This project will consist of a thorough survey of the intersection, traffic signal design with safety and efficiency in mind. Construction of the
signal and pavement markings and signs included. This project will include installing extending the bike and hike trail from Bee Creek to the
proposed traffic signal.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
This project is for the installation of a signal at the intersection of Krenek Tap and Texas Avenue.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
2,045 -$
g
10
-
540
175
1,320
Fm
2154H arvey Rd
Willia m D. Fitch PkwyBEE CREEK & ARBORETUMBEE CREEK & ARBORETUM
CY MILLER CY MILLER
Texas A
ve S Krenek Tap RdA
n
d
erson St
W illiam King Cole DrO ak Forest M hp47
PROJECT:SIGNAL @ GEORGE BUSH/DOMINIK PROJECT #: ST0205
FUND(S):139 - Streets Capital Projects PROJECT
BUDGET: $170,000
PROJECT FUNDING
MANAGER:LEE ROBINSON SOURCES: 1998 G.O. BONDS
CIP FUNDS
PROJECT
CLIENT:Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 5,309 20,032 8,033 33,373
2010-11 136,627 136,627
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 5,309$ 156,659$ 8,033$ 170,000$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
Since the widening of G Bush East a new traffic warrant study was conducted, at that time the intersection did not meet traffic volumes to
warrant a signal. It was decided to do another warrant study after completion of Texas Avenue Phase II project. Most all materials are in-
stock to build this traffic signal. More than likely if this location meets warrants during the next study it will be built in 2010-2011 fiscal year.
PROJECT SCOPE
Relocate telephone pole, underground transformer and reroute ATM's electrical service. Detail intersection survey, design traffic signal and
construct traffic signal with pedestrian signals, crosswalks and install ADA ramps.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Recurring Cost
10
-
One Time Costs
540
175
1,320
-
2,045
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
Av
e
S
W
ellb
orn R
d
Fm 158
Harvey RdTexas Ave STexas AveFoster A
v
eDom inik DrFrancis DrHolleman Dr E
Un iv e rs ity Oa k s Bl v d
Pur
y
e
ar Dr
M
il
ner Dr
Richards StGilc h r i s t A v e
Red m o n d D rWalton Dr
Kyle Ave48
PROJECT:New Traffic Signal Projects (2008 GOB) PROJECT #: ST1027
FUND(S): 139 - Streets Capital Projects PROJECT
BUDGET: $1,904,198
PROJECT FUNDING
MANAGER: Lee Robinson SOURCES: 2008 GOB
PROJECT
CLIENT: Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 - -
2011-12 11,248 11,248
2012-13 120,000 120,000
2013-14 600,000 600,000
2014-15 600,000 600,000
2015-16 572,950 572,950
2016-17 -
PROJECT TOTAL -$ -$ 1,904,198$ -$ 1,904,198$
Personnel (Salaries/Benefits)
Once traffic warrants are met at the signals are prioritized, designed and constructed to make intersections safer.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
This project serves to hold funds for new traffic signal projects.
Original budget was $3,000,000 ($500,000 per year FY 10 thru 15). As new signal projects are created, funds will be allocated to those
projects and this project balance will be reduced.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
2,045 -$
-
-
-
-
2,045
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e
S
W
ellb
orn R
d
Fm 158
49
PROJECT: Wellborn/F&B Signal PROJECT #: ST1031
FUND: 139 - Streets CIP Fund PROJECT
BUDGET: $250,000
PROJECT
MANAGER:Troy Rother FUNDING
SOURCES: 2008 GO Bonds - ST1027
PROJECT
CLIENT: Public Works
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 - - 250,000 - 250,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
TOTAL -$ -$ 250,000$ -$ 250,000$
PROJECT DESCRIPTION
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
This project is for the installation of a signal at the intersection of Wellborn and F&B. This signal will be installed as part
of an ILA with the City of Bryan. Both cities will participate in the cost of the signal.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
One Time Costs Recurring Cost
-$ 2,045$
2,045
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Annual Estimated
Fm
2
1
5
4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell
b
o
r
n
R
d
Fm 158
Barron RdS
H
40 / William D Fitch P kwy
R
en
ee LnVictoria AveEagle AvePassendale LnDelrey Dr
I
ncour
t
LaneJamey LnS H 40 / William D Fitch Pk w y
50
PROJECT:SH30/Copperfield Signal PROJECT #: ST1106
FUND(S):139 - Streets CIP Fund PROJECT
BUDGET: $525,000
PROJECT FUNDING
MANAGER:Troy Rother SOURCES: 2008 GO Bonds - ST1027
PROJECT
CLIENT:Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 - 65,000 - - 65,000
2011-12 - - 460,000 - 460,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 65,000$ 460,000$ -$ 525,000$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
This project is for the installation of a signal at the intersection of State Highway 30/Copperfield.
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
g
-
-
-
-
2,045
-
2,045
H arvey R dU niv e rs ity D rH arvey RdOld Ti RdVista LnCopp
e
rfield Pkwy
Lori Ln
Ranchero R dLinda Ln
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e
S
W
ellb
o
rn R
d
Fm 158
51
PROJECT:Signal Warrant Study PROJECT #: ST1107
PROJECT
FUND(S): 139 - Streets CIP Fund BUDGET: $40,000
PROJECT FUNDING
MANAGER: Troy Rother SOURCES: 2003 GOB - $28,450
2008 GOB - $13,550
PROJECT
CLIENT: Public Works
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 42,000 42,000
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 42,000$ -$ -$ 42,000$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
Signal warrant study.
PROJECT SCOPE
Conduct signal warrant studies for various high volume intersections in the City, including, FM 2154 at SH 40, FM 2154 at Navarro, and
Longmire at Graham.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s A
v
e S
W
ellborn R
d
Fm 158
52
PROJECT:2818/FM 60 Signal PROJECT #: ST1207
FUND(S):139 - Streets CIP Fund PROJECT
BUDGET: $380,000
PROJECT Troy Rother FUNDING
MANAGER:SOURCES: 2008 GO Bonds - ST1027
PROJECT
CLIENT:Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 - - - - -
2011-12 - 65,000 - - 65,000
2012-13 - - 315,000 - 315,000
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 65,000$ 315,000$ -$ 380,000$
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
This project is for the installation of a signal at the intersection of 2818 and FM60.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
2,045 -$
g
-
-
-
-
2,045 Fm 2154Harvey RdWilliam D. Fitch PkwyRaymond Stotzer PkwyRes
e
a
r
c
h PkwySyste m L o o p
H
a
r
v
e
y
Mit
c
h
e
ll
P
k
wy
S
O
nra
mp R.s.
PkwyOfframp R.s. Pkw y
R
a
m
p
53
PROJECT:University Drive/University Town PROJECT #: TBD
Center Signal
FUND(S): 139 - Streets CIP Fund PROJECT
BUDGET: $100,000
PROJECT FUNDING
MANAGER: Troy Rother SOURCES: 2008 GO Bonds - ST1027
PROJECT
CLIENT: Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 - - - - -
2011-12 - - - - -
2012-13 - - 100,000 - 100,000
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 100,000$ -$ 100,000$
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
This project is for the installation of a signal at the intersection of University Drive and University Town Center.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
2,045 -$
g
-
-
-
-
2,045
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e
S
W
ellb
orn R
d
Fm 158
T
arr
o
w
S
t
U n i v e r s i t y D r E
Lincoln AveS p r i n g L o o p
Munson AveAlleyRose CirChimney H ill DrTarrow St E
Vassar CtApril Bloom
C
h
u
r
chill St
54
PROJECT:Traffic Signal Communications PROJECT #: ST0411
FUND(S):139 - Streets Capital Projects PROJECT
BUDGET: $90,091
PROJECT FUNDING
MANAGER: Lee Robinson SOURCES: 2003 GOB - $250,000
PROJECT
CLIENT:Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - 27,555 - 27,555
2010-11 30,000 30,000
2011-12 32,536 32,536
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 90,091$ -$ 90,091$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
This project is a general holding project for specific traffic signal communication project locations. This project will consist of installing fiber
optics to interconnect traffic signals and, in some cases, will utilize wireless technology. Presently 15 signals are not interconnected.
Communications provides instant upload and download of data, ability to monitor the system and possible make repairs from the signal shop.
Installed wireless radios on Texas, installed conduit for fiber optics at Holleman & G Bush. Upgrades from copper cables to fiber optics will
continue to be made and communications will be made to signals that are currently without.
Original project budget = $250,000; Budget transferred to secondary projects as they've been established.
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e S
W
ellb
orn R
d
Fm 158
55
SIDEWALK AND TRAIL PROJECTS
56
PROJECT: BIKE LOOP - 2005 PROJECT #: ST0530
FUND: 139 - Streets Capital Projects PROJECT
BUDGET: $327,202
PROJECT
MANAGER: Danielle Charbonnet FUNDING
SOURCES: 1989 GOB
PROJECT
CLIENT: Public Works
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 327,202 327,202
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
TOTAL -$ -$ 327,202$ -$ 327,202$
PROJECT DESCRIPTION
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
This project will complete the third and final phase of the College Station Bike Loop Project (ST-9409 and ST0530),
which was implemented to construct a bike loop system connecting the Texas A&M University campus, the City of
College Station parks, and local residential areas. Funds from ST9803 and ST0521 are expected to be spent in
conjunction with this project's funds to complete the bike loop project, 2005 Bike Loop Phase II -- Bike Loop
Completion.
PROJECT SCOPE
This phase of the project will connect the existing bike path that terminates in Bee Creek Park to Texas Avenue and
also provide a connection with the Bee Creek Bridge crossing near Longmire Court.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
One Time Costs Recurring Cost
200
1,250
-$ 1,450$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Annual Estimated
Fm
2
1
5
4Harvey RdWilliam D. Fitch PkwyTexas Ave SWellb
o
r
n
R
d
Fm 158
57
PROJECT: MISC BIKE TRAILS - BIKE LOOP PROJECT #: ST9803
FUND: 139 - Streets CIP Fund PROJECT
BUDGET: $169,000
PROJECT
MANAGER: Danielle Charbonnet FUNDING
SOURCES: 98 GOB
PROJECT
CLIENT: Public Works
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 36,097 22,752 214 59,063
2010-11 94,937 15,000 109,937
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
TOTAL -$ 36,097$ 117,689$ 15,214$ 169,000$
PROJECT DESCRIPTION
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
OPERATIONS AND MAINTENANCE COSTS
Fi t Fi l Y AlEtitd
This project serves to hold funds for bike trail projects. Original budget was $180,000. As new bike trail projects are
created, funds will be allocated to those projects and this project balance will be reduced. Projects on which these
funds have been used include the Anderson Street Sidewalks and remaining funds will be used on the 2005 Bike
Loop project. (See project ST-0530 for additional project information.)
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
One Time Costs Recurring Cost
-$ -$
First Fiscal Year Annual Estimated
Fm
2
1
5
4Harvey RdWilliam D. Fitch PkwyTexas Ave SWellb
o
r
n
R
d
Fm 158
58
PROJECT:PROJECT #: ST0521
FUND: 139 - Streets CIP Fund PROJECT
BUDGET: $1,033,624
PROJECT
MANAGER:FUNDING
SOURCES: 2003 GOB
PROJECT
CLIENT: Public Works - Troy Rother
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 120,201 722,131 17,957 860,289
2010-11 18,000 155,335 173,335
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
TOTAL -$ 138,201$ 877,466$ 17,957$ 1,033,624$
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT SCOPE
Hike & Bike Trails - Longmire Imp
PROJECT DESCRIPTION
Danielle Charbonnet
The majority of these funds were spent on the 2005 Bike Loop Phase I Project-- Longmire Improvements, which
included pedestrian improvements to FM 2818 and Longmire intersection, bike lanes on Longmire, and a bridge over
Bee Creek. The balance of the funds will be used to complete the CS Bike Loop project, which is Phase II to this
project.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
200
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Annual Estimated
One Time Costs Recurring Cost
200$ -$ Fm
2
1
5
4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell
b
o
r
n
R
d
Fm 158
59
PROJECT:Sidewalk Improvements (2008 GOB) PROJECT #: ST1028
FUND(S):139 - Streets CIP Fund PROJECT
BUDGET: $200,000
PROJECT FUNDING
MANAGER:Gary Balmain SOURCES: 2008 GO Bonds
PROJECT
CLIENT:Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 200,000 200,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 200,000$ -$ 200,000$
Project scope will be defined by the Bicycle Pedestrian and Greeways Master Plan.
Potential projects include a Dexter Drive sidewalk and a Guadalupe Drive sidewalk.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Funds provided for sidewalk improvement projects throughout the City. Plan to build sidewalks along thoroughfares and collectors and to
retrofit older neighborhoods. This project serves as a holding account until specific projects are identified. $100,000 per year FY 10 thru 12
Original Budget = $300,000
$100,000 transferred to ST0910 - FY10
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
-
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e
S
W
ellborn R
d
Fm 158
60
PROJECT:Lincoln Sidewalk Improvements PROJECT #: ST0910
FUND(S):139 - Streets Capital Projects Fund PROJECT
BUDGET: $249,167
PROJECT FUNDING
MANAGER: Philip Bargas SOURCES: ST0517 - 03 GOB - $149,167
ST1028 - 08 GOB - $100,000
PROJECT
CLIENT:Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 336 - - 336
2010-11 2,961 30,324 215,546 248,831
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 2,961$ 30,660$ 215,546$ -$ 249,167$
Design, bidding, construction phase services, and construction of approximately 2,380 LF of 6' wide sidewalk.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
This project is for the acquisition of right-of-way and the construction of sidewalks on the north side of Lincoln Avenue extending from
Avenue A to University Drive.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
g
-
-
-
-
- Lincoln AveFrancis DrU niversity Dr E
T
e
x
a
s
A
v
e
Dominik DrM
u
n
s
o
n A
v
e
P
urye
a
r D
r
M
il
ner DrFront StSpr i n g L oop
Cooner StPolo RdCarol StKyle AveAsh StRampChimney Hill DrFore
s
t Dr
Fm
2
1
5
4H arvey R dWi llia m D. Fitch PkwyTexas Ave S
W
ellb
o
r
n Rd
Fm 158
61
PROJECT: Hike and Bike Trail Completion PROJECT #: ST0904
FUND:139 - Streets Capital Projects Fund PROJECT
BUDGET: $749,000
PROJECT
MANAGER: Danielle Charbonnet FUNDING
SOURCES: 2008 General Obligation Bonds
PROJECT
CLIENT:P&DS - Venessa Garza
FISCAL YEAR Land Engineering Construction Misc OH Project Total
Prior Years - 109,389 58,295 209 167,893
2010-11 35,000 526,000 1,000 19,107 581,107
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
TOTAL -$ 144,389$ 584,295$ 1,209$ 19,107$ 749,000$
PROJECT DESCRIPTION
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Fi t Fi l Y AlEtitd
This project is for the construction of a 10' wide multi-use trail along FM 2818 from Welsh Avenue to Longmire Drive. The
trail will be extended to Texas Avenue budget allowing. One million dollars was allocated through the November 2008 Bond
for the implementation of projects identified by the Hike and Bike Task Force and adopted by City Council on November 23,
2004. High priority trail projects identified by the Hike and Bike Task Force in 2004 that have not been completed included a
portion of this multi-use path from Welsh to Bee Creek. The trail will provide connectivity to key destinations along the
corridor, including A&M Consolidated High School, Bee Creek Park, and residential and commercial properties.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
One Time Costs Recurring Cost
First Fiscal Year Annual Estimated
1,000
-$ 1,000$
Fm
2
1
5
4Harvey RdWilliam D. Fitch PkwyTexas Ave SWellb
o
r
n
R
d
Fm 158
Welsh Av
e Texas Ave SGlade StHarve y M i t c h e ll P k w y SHolleman DrD e a c o n D rLongmire Dr
A
nderson St
Alley
La
wye
r St
Dexter Dr S
H a in e s D rLee AveChri s tin e L n
T r e e h o u s e T r lKrenek Tap RdNavarro DrMile DrMorgans LnNevada StT h o m a s S t62
PROJECT:Hike and Bike Trail Completion Phase II PROJECT #: ST1103
FUND(S):139 - Streets Capital Projects Fund PROJECT
BUDGET: $251,000
PROJECT FUNDING
MANAGER: Danielle Charbonnet SOURCES: 2008 General Obligation Bonds
PROJECT P&DS - Venessa Garza
CLIENT:
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 27,000 - 27,000
2011-12 16,000 158,000 50,000 224,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 43,000$ 158,000$ 50,000$ 251,000$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated AnnualFirst Fiscal Year
This project is Phase II of the Hike and Bike trail along FM 2818. One million dollars was allocated through the November 2008 Bond for the
implementation of projects identified by the Hike and Bike Task Force and adopted by City Council on November 23, 2004. The trail will
provide connectivity to key destinations along the corridor, including A&M Consolidated High School, Bee Creek and Southwest Park, and
residential and commercial properties.
PROJECT SCOPE
The trail, which will be designed in-house by Public Works staff, will continue the 10' wide multi-use trail from Welsh Avenue to the Campus
Village trail to the west. The trail will also be extended from the northern connection of the Campus Village Trail through Southwest Park as
part of the Southwest Park development, providing continuity of the hike & bike trail system from Texas Avenue to Southwest Parkway, which
is on the Bikeway Master Plan.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
2,000
-
-
-
2,000
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyTexas Ave SW
el
l
b
orn R
d
Fm 158
Wel
s
h Av
e
T
e
x
a
s
A
v
e
SGl
a
d
e
S
t
Harve y M i t c h e ll P k w y SHolleman DrD e a c o n D rLongmire Dr
Anderson St
Alle
y
La
w
yer St
D
e
xter D
r S
H a in e s D rL
e
e
Av
e
Christin e L n
T r e e h o u s e T r lKrenek Tap RdNav arro DrM ile D rMorgans LnNevada StT h o m a s S t63
PROJECT:Lick Creek Hike and Bike Trail PROJECT #: ST1104
FUND(S): 139 - Streets Capital Projects Fund PROJECT
BUDGET: $4,410,000
PROJECT FUNDING
MANAGER: Danielle Charbonnet SOURCES: 2008 General Obligation Bonds
PROJECT
CLIENT: P&DS - Venessa Garza
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 50,000 50,000
2011-12 70,000 400,000 38,000 508,000
2012-13 105,000 1,000,000 46,000 1,151,000
2013-14 2,663,000 38,000 2,701,000
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 70,000$ 555,000$ 3,663,000$ 122,000$ 4,410,000$
Pl(Sli/Bfit)
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
The Lick Creek Hike and Bike Trail project will construct about 3 miles of Hike and Bike Trails along Lick Creek between Westfield Park and
Lick Creek Park connecting residential neighborhoods and CSISD property. This project is on the City's Bikeway Master Plan and was
ranked as a High priority project by the Bike and Hike Task Force.
PROJECT SCOPE
Engineering, bidding, and construction administration for the Lick Creek Hike and Bike Trail.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
8,000
-
-
-
8,000
S H 6 S
Fr
o
n
t
age
6
Rd E
F
r
onta
g
e 6 R
d WBarron RdFm 2154Rock Prairie Rd
L
ongmir
e
Dr
Graham RdVi
ct
or
i
a Ave
Lakeway Dr
S H 40 / William D F itc h P k w y Olden LnP o n d e ro s a D rSt A
n
dr
e
w
s
D
r
Cas t l e g ate Dr Carll LnRitchey RdAster DrDover DrFm
2
1
5
4Harvey RdWilliam D. Fitch PkwyTexas Ave SW
ellb
orn
R
d
Fm 158
64
PROJECT:University Drive Pedestrian PROJECT #: ST1206
Improvements Phases 2-5
FUND(S):139 - Streets Capital Projects Fund PROJECT
BUDGET: $7,055,000
PROJECT FUNDING
MANAGER: Danielle Charbonnet SOURCES: 2008 General Obligation Bonds
PROJECT
CLIENT: Public Works - Troy Rother
Project Total
FISCAL YEAR Land Engineering Construction Misc OH Project Total
Prior Years - - - - -
2010-11 -
2011-12 150,000 500,000 5,000 24500 679,500
2012-13 150,000 3,000,000 5,000 39000 3,194,000
2013-14 3,142,500 5,000 34000 3,181,500
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 150,000$ 650,000$ 6,142,500$ 15,000$ 97,500$ 7,055,000$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
This project consists of implementing the remaining phases (2 through 5) of the Pedestrian Improvements on University Drive. The project
developed a plan to improve pedestrian travel in the Northgate area of College Station, especially to facilitate pedestrian movement across
and along University Drive between Boyett Street and South College Avenue. This project was ranked as a High priority project by City staff.
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Recurring Cost
-
-
One Time Costs
-
-
-
-
TBD
University DrR o s s S tChurch AveFirst St Na
g
l
e
St
Boyett StCherry StTauber
St
W
ellb
orn R
d N Stasney StB
izz
e
ll StPo lo RdSpence StIreland St
Jone s S tAsbury StSpruce StAgronomy Rd
C o ke St
L a m a r S tR a mp
Bizzell St
La
mar S
t
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e
S
W
ellb
orn R
d
Fm 158
65
PROJECT:College Main Plaza Improvements PROJECT #: ST1113
(College Main Pedestrian Plaza &
Lodge & Patricia Street Improvements)
PROJECT
FUND(S): 139 - Streets Capital Fund BUDGET:$692,000
PROJECT FUNDING
MANAGER: Jeff Haeber SOURCES:Various
PROJECT
CLIENT: Public Works
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 40,000 15,000 55,000
2011-12 7,000 625,000 5,000 637,000
2012-13 .-
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 47,000$ 625,000$ 20,000$ 692,000$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated AnnualFirst Fiscal Year
Construct a pedestrian plaza with bike lane from University Drive to Patricia along with Roadway improvements along Lodge & Patricia
Street.
PROJECT SCOPE
Design, bidding, and construction to convert College Main into a pedestrian plaza by widening existing sidewalks along both sides of the
street by approximately 14 feet and leaving a 10 foot wide area bounded with curb and gutter for a bike lane along with lighting relocations,
bollards at two different locations, and roadway improvements at Lodge & Patricia Street. No ROW acquisitions will be required for this
project.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
-
-
College Station S H 6 SF
r
ont
age 6
Rd E
R ock Prairie RdFm
2
1
5
4Harvey RdWelsh AveF & B RdTexas AveFm 158
S H 6 S Church AveUniversity DrCollege Main Tauber StAsbury StSecond StBoyett St Lodge StStasney StPatricia StN e w S tHo g g StLouise AveHousto
n
S
t N66
COMMUNITY DEVELOPMENT BLOCK
GRANT FUNDED (CDBG) STREET
PROJECTS
67
PROJECT: College Main Rehabilitation PROJECT #: ST1102
FUND: 122 - CDBG Fund PROJECT
BUDGET: $398,000
PROJECT
MANAGER:Philip Bargas FUNDING
SOURCES: CDBG Funds
PROJECT
CLIENT: Public Works
FISCAL YEAR LAND ENG. CONSTR. MISC. OVERHEAD PROJECT TOTAL
Prior Years $0 $0 $0 $0
2010-11 46,000 $46,000
2011-12 11,000 341,000 $352,000
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $57,000 $341,000 $0 $0 $398,000
PROJECT DESCRIPTION
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
This project is for the upgrade a portion of College Main between the City limit and about halfway between Spruce &
Cherry Streets. This section of College Main was not rehabilitated back in the 1990's and the City of Bryan is working
on rehabilitating the portion of College Main in its city limits.
PROJECT SCOPE
This section of roadway proposed to be rehabilitated by the City of College Station is about 230 feet long. The project
scope includes the replacement of all of the existing roadway, sidewalks and drainage infrustructure to a maintenance
overlay and sidewalk extension project.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Estimated Annual
One Time Costs Recurring Cost
-$ - Nagl
e StCollege M
ain
Colleg
e
Main St Cherry StT
a
u
b
e
r StStasney St
Spruce StBoyett St
Aspen St
Cross StFoch St
Cross StNORTHGATE PARKNORTHGATE PARK Nagl
e StTauber StFm 2154Harvey RdW illiam D. Fitch Pkwy68
PROJECT:FM 2154 Sidewalk Improvements - Design PROJECT #: ST1203
(Luther to SW Parkway)
FUND(S):139- Streets CIP Fund PROJECT
BUDGET:$75,000
PROJECT FUNDING
MANAGER: Ed McDonald SOURCES: CDBG
PROJECT
CLIENT: Public Works
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 30,000 30,000 15,000 75,000
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 30,000$ 30,000$ -$ 15,000$ 75,000$
Personnel (Salaries/Benefits)
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
This project is for the design of a sidewalk on one side of FM 2154 from Luther to Southwest Parkway.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
-
W
elsh A
ve
Wel
l
bor
n RdH a rv e y M itchell Pkwy SLuther St W
S outhw est P kw yHollem an DrJ
o
nes-b
utle
r Rd
La
w
yer St
H a in e s D rLuther StChristine LnGlade St
George Bush Dr W
AlleyDexter
D
r SMar
i
on Pugh DrN ueces Dr
L
an
gford StFidelity StNevada StW in d i n g R d
Me
d
i
n
a
D
r
Fm
2
1
5
4Harvey RdWilliam D. Fitch PkwyTexas Ave SWe
l
l
b
o
r
n
R
d
Fm 158
69
PROJECT:University Drive Sidewalk Improvements - Design PROJECT #: ST1202
FUND(S):122 - CDBG Fund PROJECT
BUDGET:$75,000
PROJECT FUNDING
MANAGER:Ed Mc Donald SOURCES: CDBG
PROJECT PRIORITY:
CLIENT:Public Works
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 60,000 15,000 75,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 60,000$ -$ 15,000$ 75,000$
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
This project is for the design of an eight foot sidewalk on the south side of University Drive East (Major Arterial) from Texas Avenue South to
approximately Lions Park. This project was identified in the Eastgate Neighborhood Plan. Construction funds are not currently budgeted.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s A
v
e S
W
ellbor
n
R
d
Fm 158
70
GENERAL GOVERNMENT-
PARKS AND RECREATION
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH
FISCAL YEAR 2016-2017
71
GENERAL GOVERNMENT
PARKS AND RECREATION PROJECTS
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT REVISED APPROVED
PROJECT BUDGET APPROPRIATIONS FY 10 - 11 FY 11 - 12
NUMBER AMOUNT THROUGH FY10 APPROPRIATIONS APPROPRIATIONS
BEGINNING FUND BALANCE:$904,245 $1,448,747
ADDITIONAL RESOURCES:
GENERAL OBLIGATION BONDS (2003 GOB)- -
GENERAL OBLIGATION BONDS (2008 GOB)2,180,000 2,715,000
CERTIFICATES OF OBLIGATIONS - -
INTERGOVERNMENTAL TRANSFERS - -
INTRAGOVERNMENTAL TRANSFERS 235,910
INVESTMENT EARNINGS 7,000 15,000
OTHER 81,600 81,600
SUBTOTAL ADDITIONAL RESOURCES $2,504,510 $2,811,600
TOTAL RESOURCES AVAILABLE $3,408,755 $4,260,347
PARK PROJECTS
FIELD REDEVELOPMENT PK0300 ANNUAL - - 68,384
1 CREEK VIEW NEIGHBORHOOD PARK PK0906 515,000 515,000 - -
1 NEIGHBORHOOD PARK IMP PROJECTS PK0910 10,907 - 10,907 -
1 EMERALD FOREST PARK IMPROVEMENTS PK0713 106,000 106,000 - -
1 UNIVERSITY PARK IMPROVEMENTS PK0410 93,000 - 93,000 -
1 SANDSTONE SHADE COVER PK1108 27,750 3,192 24,558 -
1 THOMAS PARK SHADE COVER PK1112 30,000 16,850 13,150 -
1 WOODCREEK PARK SITE IMPROVEMENTS PK1114 72,850 - 72,850 -
1 SKATE PARK PK0911 924,451 924,451 - -
1 NEIGHBORHOOD PARKS REVOLVING FUND PK0912 1,000,000 1,000,000 -
1 BEACHY CENTRAL PARK IMPROVEMENTS PK1001 930,000 150,000 780,000 -
1 LICK CREEK PK IRON BRIDGE TRAIL COMPL PK1201 100,000 - - 100,000
BUDGET APPROPRIATIONS
,,
1 LINCOLN CENTER ADDITION TBD 4,285,000 - - -
1 EAST DISTRICT MAINTENANCE SHOP REP PK1101 1,645,000 - 1,645,000 -
1 LICK CREEK NATURE CENTER PK1102 2,495,000 - 100,000 2,395,000
CLOSED PROJECTS 5,227 100,403
CAPITAL PROJECTS SUBTOTAL $2,720,720 $2,839,868 $2,563,384
MISCELLANEOUS - -
DEBT ISSUANCE COST 10,000 20,000
GENERAL & ADMIN. CHARGES 52,759 43,029
TOTAL EXPENDITURES $2,902,627 $2,626,413
CAFR Adjustment
ENDING FUND BALANCE:$506,128 $1,633,934
1 - Indicates projects funded through 2008 G.O. Bond Authorization
72
GENERAL GOVERNMENT
PARKS AND RECREATION PROJECTS
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT
EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED
THROUGH FY09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY 16-17
$1,335,947 $1,796,539 $1,448,747 $1,926,088 $401,474 $184,953 $137,245 $123,050
- - - - - - - -
870,000 1,260,000 2,715,000 2,175,000 395,000 3,840,000 -
- - - - - - - -
- - - - - - - -
235,910 - - - - -
3,731 14,000 15,000 15,000 9,000 5,000 2,500 2,500
82,232 80,000 81,600 83,200 84,900 86,600 88,300 90,100
$955,963 $1,589,910 $2,811,600 $2,273,200 $488,900 $3,931,600 $90,800 $92,600
$2,291,910 $3,386,449 $4,260,347 $4,199,288 $890,374 $4,116,553 $228,045 $215,650
344,108 10,315 83,115 68,384 86,772 265,421 64,308 84,995 126,322
3,289 15,669 8,000 - 488,042 - - - -
- - 10,907 - - - - - -
- 4,539 101,461 - - - - - -
- 2,304 9,000 81,696
- - 27,750 - - - - - -
- - 30,000 - - - - - -
- - 72,850 - - - - - -
28,709 112,725 783,017 - - - - - -
417,400 12,534 276,223 293,843 - - - - -
- 70,193 67,500 792,307 - - - - -
- - - 100,000 - - - - -
PROJECTED EXPENDITURES
,
- - - - 50,000 395,000 3,840,000 - -
- - 2,000 198,000 1,445,000 - - - -
- - 100,000 737,000 1,658,000 - - - -
202,241 298,120 - - - - - -
$793,506 $430,520 $1,869,943 $2,271,230 $3,727,814 $660,421 $3,904,308 $84,995 $126,322
- - - - - - - -
787 15,000 20,000 20,000 5,000 35,000 - -
93,578 52,759 43,029 50,000 40,000 40,000 20,000 10,000
$524,885 $1,937,702 $2,334,259 $3,797,814 $705,421 $3,979,308 $104,995 $136,322
29,514
$1,796,539 $1,448,747 $1,926,088 $401,474 $184,953 $137,245 $123,050 $79,328
73
PROJECT: Field Redevelopment Projects PROJECT #: PK0300
FUND: 138 - Parks CIP PROJECT
BUDGET:Annual
PROJECT Peter Lamont/Pete Vanecek FUNDING
MANAGER:SOURCES: Field Redevelopment Fees
PROJECT
CLIENT: Parks and Recreation
FISCAL YEAR Land EngineeringConstruction Misc Project Total
Prior Years 354,423 354,423
2010-11 83,115 83,115
2011-12 68,384 68,384
2012-13 86,772 86,772
2013-14 265,421 265,421
2014-15 64,308 64,308
2015-16 84,995 84,995
2016-17 126,322 126,322
TOTAL -$ -$ -$ 1,133,740$ 1,133,740$
PROJECT DESCRIPTION
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Fi t Fi l Y AlEtitd
This project will include replacement and repairs to numerous athletic facilities throughout the City. These funds
are collected from user groups and PARD programs specifically for these purposes.
PROJECT SCOPE
Items include drinking fountains, shade covers, light and base replacement as well as fence and bleacher
repairs. Additions to turf maintenance are also included for several fields. FY12 allocations are as follows:
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
First Fiscal Year Annual Estimated
One Time Costs Recurring Cost
-$ -$
74
PROJECT:CREEK VIEW NEIGHBORHOOD PARK PROJECT #: PK0906
FUND(S): 138 - Parks CIP Fund PROJECT
BUDGET: $515,000
PROJECT FUNDING
MANAGER: Edward McDonald SOURCES: 2008 General Obligation
Bonds
PROJECT
CLIENT: Parks and Recreation
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 18,311 289 358 18,958
2010-11 8,000 8,000
2011-12 -
2012-13 33,000 455,042 488,042
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 59,311$ 455,331$ 358$ 515,000$
Personnel (Salaries/Benefits)
The project may include a playground, picnic pavilion, lighting, bridges, landscaping, practice ball fields, sidewalks, etc.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
3 000
First Fiscal Year
One Time Costs
PROJECT SCOPE
This neighborhood park project is located adjacent to the recently completed CSISD Elementary School. Current City park property will be
combined with property leased from CSISD to constitute the park. The park will serve the surrounding neighborhood and assist the CSISD
elementary school activities.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
23,140 -$
3,740
3,000
1,650
-
14,750
Proposed Zone
10 Park
75
PROJECT:PROJECT #:
PROJECT
FUND:BUDGET: $10,907
PROJECT
MANAGER: FUNDING
SOURCES:
PROJECT Bonds
CLIENT: Parks and Recreation
Original budget = $900,000
$204,573 - Pebble Creek Bball Pavilion (PK0914) - FY09 $8,579 - Castlegate Park Imp (PK1107) - FY11
$43,577 - Park Shade Covers (PK0913) - FY09 $27,750 - Sandstone Shade Cover (PK1108) - FY11
$30,000 - NH Park Fencing (PK0917) - FY09 $21,808 - Southwood Pk Imp (PK1110) - FY11
$106,000 - Emerald Forest Park Imp (PK0713) - FY10 $30,000 - Thomas Pk Shade Cover (PK1112) - FY11
$229,000 - Brothers Pond Pk Imp (PK1003) - FY10 $72,850 - Woodcreek Park Imp (PK1114) - FY11
$20,132 - Merry Oaks Park Area Lights (PK1105) - FY11 $1,824 - Lemontree Park Swing Set (PK1106) - FY11
$93,000 - University Pk Imp (PK0410) - FY11
FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL
Prior Years - - - - -
2010-11 10,907 10,907
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
NEIGHBORHOOD PARK PK0910
IMPROVEMENTS
138 - Parks CIP Fund
Pete Vanecek
2008 General Obligation
PROJECT DESCRIPTION/STATUS
This project would address Neighborhood Park improvements, bringing older parks up to current standards.
Projects will be identified by the Parks and Recreation Department.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
2015 16
2016-17
TOTAL -$ -$ 10,907$ -$ 10,907$
Total
Personnel -
Supplies -
Service -
Capital -
TOTAL -$
NET INCREASE IN OPERATING COSTS
First Fiscal Year Annually
-$ -$ Fm
2
1
54Harvey RdWilliam D. Fitch PkwyTexas Ave SWell
b
o
r
n
R
d
Fm 158
76
Home of Texas A&M University ®
77
PROJECT:Emerald Forest Park Imp. Combo
FUND(S):PROJECT NUMBERS & BUDGET:
138 - Parks CIP Fund Parks CIP: PK0713 $106,000
178 - Zone 8 Parkland Dedication Fund Parkland Ded: PK0713 $63,000
Total Project Budget:$169,000
PROJECT
MANAGER:Jeff Haeber
FUNDING
PROJECT SOURCES:138 - 2008 General Obligation Bond
CLIENT:Parks and Recreation 178 - Zone 8 Parkland Dedication
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 1,089 3,450 - 4,539
2010-11 - 23,275 131,280 9,906 164,461
2011-12 - - - - -
2012-13 - - - - -
2013 14
PROJECT SCOPE
PROJECT DESCRIPTION
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
This neighborhood park project is for renovations to the playground, drainage, and sidewalks within the Park. The existing sidewalk will be
replaced and built at a higher elevation. The existing playground unit will be replaced and elevated. Drainage issues within the park will be
addressed. The Parks CIP budget for this project was transferred from PK0910 - Neighborhood Park Improvements.
Engineering, bidding, and construction administration of Emerald Forest Park Improvements.
2013-14 - - - - -
2014-15 - - - - -
2015-16 - - - - -
2016-17 - - - - -
169,000$ 24,364$ 134,730$ 9,906$ PROJECT TOTAL -$
78
Parks CIP
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 1,089 3,450 - 4,539
2010-11 $23,275 $68,280 9,906 101,461
2011-12 - -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Parks Total -$ 24,364$ 71,730$ 9,906$ 106,000$
Parkland Dedication Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 63,000 63,000
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Parkland Total -$ -$ 63,000$ -$ 63,000$
Personnel (Salaries/Benefits)
9,906$ 169,000$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
PROJECT:Emerald Forest Park Imp. Combo
PROJECT CALENDAR OF EXPENDITURES BY FUND
PROJECT TOTAL -$ 24,364$ 134,730$
First Fiscal Year Annual Estimated
One Time Costs Recurring Cost
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
225
-
550
-$ 775$
-
-
79
PROJECT:University Park - Phase II
FUND(S):PROJECT NUMBERS & BUDGET:
138 - Parks CIP Fund Parks CIP: PK0410 $93,000
172 - Zone 2 Parkland Dedication Fund Parkland Ded: PK0410 $12,000
Total Project Budget:$105,000
PROJECT
MANAGER:Phlip Bargas
FUNDING
PROJECT SOURCES:138 - 2008 General Obligation Bond
CLIENT:Parks and Recreation 172 - Zone 2 Parkland Dedication
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - 4,089 - 4,089
2010-11 - 9,000 5,320 - 14,320
2011-12 - 5,000 81,591 - 86,591
2012-13 - - - - -
2013-14 -----
PROJECT DESCRIPTION
This project will add parking spaces to the existing park. The Parks CIP budget for this project was transferred from PK0910 - Neighborhood
Park Improvements.
PROJECT SCOPE
City staff will design an addition to the existing parking lot adding 14 parking spaces, 1 being handicap accessible, landscape island,
sidewalks, curb and gutter, and relocation of the irrigation system as needed.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
2013-14 - - - - -
2014-15 - - - - -
2015-16 - - - - -
2016-17 - - - - -
105,000$ PROJECT TOTAL -$ -$ 14,000$ 91,000$
80
Parks CIP
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - 2,304 - 2,304
2010-11 9,000 9,000
2011-12 5,000 76,696 81,696
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Parks Total -$ 14,000$ 79,000$ -$ 93,000$
Parkland Dedication Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - 1,785 - 1,785
2010-11 5,320 5,320
2011-12 4,895 4,895
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Parkland Total -$ -$ 12,000$ -$ 12,000$
Personnel (Salaries/Benefits)
-$ 105,000$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Annual Estimated
One Time Costs Recurring Cost
-
PROJECT:University Park - Phase II
PROJECT CALENDAR OF EXPENDITURES BY FUND
PROJECT TOTAL -$ 14,000$ 91,000$
First Fiscal Year
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
100
-$ 200$
-
-
-
100
-
81
PROJECT:Sandstone Park Shade Cover PROJECT #: PK1108
FUND(S):138 - Parks CIP Fund PROJECT
BUDGET: $27,750
PROJECT FUNDING
MANAGER:Pete Vanecek SOURCES: 2008 GOB - ST0910
PROJECT
CLIENT:CSPARD
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 $2,750 $25,000 27,750
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 2,750$ 25,000$ -$ 27,750$
Personnel (Salaries/Benefits)
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
This park project is for a shade cover over the playground at Sandstone Park.
The budget for this project was transferred from PK0910 - Neighborhood Park Improvements.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
-
Fm
2
1
5
4Harvey RdWilliam D. Fitch PkwyTexas Ave SWellb
o
r
n
R
d
Fm 158
SANDSTONE PARKSANDSTONE PARK
Sebesta RdE m e r a ld P k w y
Bent Tree Dr Sandstone DrAlley
Drift
wood DrCorsair CirO a k w o o d T rlGreenleaf DrTopaz Ct
B r ia r R o s e C t
Jade Ct
82
PROJECT:Thomas Park Shade Cover PROJECT #: PK1112
FUND(S):138 - Parks CIP Fund PROJECT
BUDGET: $30,000
PROJECT FUNDING
MANAGER:Pete Vanecek SOURCES: 2008 GOB - ST0910
PROJECT
CLIENT:CSPARD
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 $30,000 30,000
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 30,000$ -$ 30,000$
Personnel (Salaries/Benefits)
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
This park project is for a shade cover over the playground at Thomas Park.
The budget for this project was transferred from PK0910 - Neighborhood Park Improvements.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
-
Fm
2
1
5
4Harvey RdWilliam D. Fitch PkwyTexas Ave SW
el
l
b
orn
R
d
Fm 158
THOMAS THOMAS
EASTGATE EASTGATE
P
uryear Dr
Francis D rMiln
e
r Dr
W
alto
n Dr
F
o
ster A
ve Kyle AveW
illia
m
s St
Gilchrist AveH
arrington Ave
Brooks AveJames Pk
w
y
Bolton AveJames Pk
w
yBolton Ave83
PROJECT:Wood Creek Park Improvements PROJECT #: PK1114
FUND(S):138 - Parks CIP Fund PROJECT
BUDGET:$72,850
PROJECT FUNDING
MANAGER:Pete Vanecek SOURCES: 2008 GOB - ST0910
PROJECT
CLIENT:CSPARD
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 72,850 72,850
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 72,850$ -$ 72,850$
Personnel (Salaries/Benefits)
The budget for this project was transferred from PK0910 - Neighborhood Park Improvements.
PROJECT SCOPE
New concrete walks,a drinking fountain,curbing and gravel will be installed to address safety concerns.Also the basketball court will be
resurfaced.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
-
Fm
2
1
5
4Harvey RdWilliam D. Fitch PkwyTexas Ave SW
ellb
or
n
R
d
Fm 158
WOODCREEK WOODCREEK AlleyW o o d c r e e k D r Stonebrook DrWaterford Dr
Brookwater CirShadowcrest DrRiverstone CtEs s e x G r e e n
Whitney Ln84
PROJECT:SKATE PARK PROJECT #: PK0911
FUND(S): 138 - Parks CIP Fund PROJECT
BUDGET: $924,451
PROJECT FUNDING
MANAGER: Edward McDonald SOURCES: 2008 General Obligation
Bonds
PROJECT
CLIENT: Parks and Recreation
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 140,248 - 1,186 141,434
2010-11 41,672 741,345 783,017
2011-12 .-
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 181,920$ 741,345$ 1,186$ 924,451$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECTSCOPE
This project is for the design and construction of an in-ground, concrete skate park.
The Skate Park will be located at the Southwood Athletic Complex. The project may include the skate facility, outdoor pavilions, fencing,
landscaping, water fountains, lighting, seating areas, etc.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Recurring Cost
1,200
-
One Time Costs
2,000
-
4,200
-
7,400
Fm 2154Roc k Prairie R d Fr
ont
age 6
Rd ENavarro DrA lleyPi
erre Pl
Eagle AveMortier DrH a rtford D rHaley P lNormand Dr
G ail PlSchaffer RdSophia L n
K ern sto w n L nCarmel PlBr
i
dl
e CtPinon DrFm
2154Harvey RdW illiam D. Fitch PkwyTexas Ave SWe
ll
bor
n RdFm 158
85
PROJECT:NEIGHBORHOOD PARKS REVOLVING PROJECT #: PK0912
FUND
FUND(S):PROJECT
138 - Parks CIP Fund BUDGET: $1,000,000
PROJECT FUNDING
MANAGER:David Schmitz SOURCES:
2008 General Obligation
PROJECT Bonds
CLIENT:Parks and Recreation
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 425,047 4,887 - - $429,934
2010-11 275,000 1,223 $276,223
2011-12 293,843 $293,843
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
PROJECT TOTAL $993,890 $4,887 $0 $1,223 $1,000,000
Personnel (Salaries/Benefits)
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
This fund is for acquiring properties for neighborhood parks in advance of development. As the land develops, the fund will be reimbursed
through park land dedication.
()
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e S
W
ellborn R
d
Fm 158
86
PROJECT:BEACHY CENTRAL PARK PROJECT #: PK1001
IMPROVEMENTS
PROJECT
FUND(S):138 - Parks CIP Fund BUDGET: $930,000
PROJECT FUNDING
MANAGER: Daniel Beamon SOURCES: 2008 General Obligation
Bonds
PROJECT
CLIENT: Parks and Recreation
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 70,136 0 57 70,193
2010-11 $67,000 500 67,500
2011-12 30,000 762,307 792,307
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 167,136$ 762,807$ 57$ 930,000$
Personnel (Salaries/Benefits)
The new building will include restrooms, concession area, storage and a meeting room.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project is for the demolition and construction of a new softball concession complex and restroom building at the softball fields in Stephen
C. Beachy Central Park.
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
87
PROJECT:LICK CREEK PARK IRON BRIDGE PROJECT #: PK1201
TRAIL COMPLETION
FUND(S):PROJECT
138 - Parks CIP Fund BUDGET: $100,000
PROJECT FUNDING
MANAGER: Pete Vanecek SOURCES: 2008 General Obligation
Bonds
PROJECT
CLIENT:Parks and Recreation
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 10,000 85,000 5,000 100,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 10,000$ 85,000$ 5,000$ 100,000$
Personnel (Salaries/Benefits)
PROJECT SCOPE
This park project is for construction of a compacted gravel trail over the existing dirt trail in Lick Creek Park.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
1 250
First Fiscal Year
One Time Costs
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
1,050
1,250
400
-
-
-
2,700
88
PROJECT:LINCOLN CENTER ADDITION PROJECT #: TBD
FUND(S): 138 - Parks CIP Fund PROJECT
BUDGET: $4,285,000
PROJECT Daniel Beamon FUNDING
MANAGER: SOURCES: 2008 General Obligation
Bonds
PROJECT
CLIENT: Parks and Recreation
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 50,000 50,000
2013-14 395,000 395,000
2014-15 3,840,000 3,840,000
2015-16 -
2016-17 -
PROJECT TOTAL -$ 445,000$ 3,840,000$ -$ 4,285,000$
Personnel (Salaries/Benefits)
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
30,000
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project is for the expansion of the Lincoln Center building, to include additional space for programming and storage.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
()
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
12,450
,
-
-
55,600
-
98,050
89
PROJECT:EAST DISTRICT MAINTENANCE SHOP PROJECT #: PK1101
REPLACEMENT
FUND(S):PROJECT
138 - Parks CIP Fund BUDGET: $1,645,000
PROJECT FUNDING
MANAGER:Daniel Beamon SOURCES:
2008 General Obligation
PROJECT Bonds
CLIENT:Parks and Recreation
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 2,000 2,000
2011-12 198,000 198,000
2012-13 1,445,000 1,445,000
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 200,000$ 1,445,000$ -$ 1,645,000$
Personnel (Salaries/Benefits)
PROJECT SCOPE
This project is for the construction of a new East District maintenance shop. The new building will include restrooms, work areas, open bays,
office area, storage, and a meeting room.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
()
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
90
PROJECT:Lick Creek Nature Center PROJECT #: PK1102
FUND(S):138 - Parks CIP Fund PROJECT
BUDGET: $2,495,000
PROJECT FUNDING
MANAGER: Danielle Charbonnet SOURCES: 2008 General Obligation
Bonds
PROJECT
CLIENT: Parks and Recreation
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 100,000 100,000
2011-12 207,000 500,000 30,000 737,000
2012-13 1,591,000 67,000 1,658,000
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 307,000$ 2,091,000$ 97,000$ 2,495,000$
Personnel (Salaries/Benefits)
Supplies
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
26 000
128,750
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project is for the design and construction of a Nature Center in Lick Creek Park.
The first phase of the design will include the development of a Master Plan in order to determine the strategic placement of the facility, major
amenities and features, basic infrastructure needs, construction phasing and develop a planning level construction cost estimate. The
master plan will also provide a basis for the development of the operation and maintenance cost of the facility. Detailed design and
construction will follow in accordance with the plan.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
247,650 -$
26,000
-
-
92,900
91
COMMUNITY DEVELOPMENT BLOCK
GRANT FUNDED (CDBG) PARKS AND
RECREATION PROJECTS
92
PROJECT:Georgie K. Fitch Improvements PROJECT #: PK1104
FUND(S):122 - CDBG Fund PROJECT
BUDGET: $103,500
PROJECT FUNDING
MANAGER:Pete Vanecek SOURCES: CDBG Funds
PROJECT
CLIENT:CSPARD
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 2,500 3,000 3,500 9,000
2011-12 94,500 94,500
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 2,500$ 97,500$ 3,500$ 103,500$
Personnel (Salaries/Benefits)
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project is for a lighted concrete walking/ jogging trail, with trees.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
750 -$
25
-
225
-
500 Fm 2154Harvey RdWillia m D. Fitch PkwyH a rv e y M itc h e ll P w
We
l
s
h
A
v Balcones Dr Ri
o Grande
Bl
Nueces Dr
Navarro DrSan Saba DrA irlin e D rSan Benito DrBlanco DrGEORGIE K FITCH PARKGEORGIE K FITCH PARKWels
h
A
v
e
Pe
dernales Dr
93
Home of Texas A&M University ®
94
GENERAL GOVERNMENT-
FACILITY AND TECHNOLOGY
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH
FISCAL YEAR 2016-2017
95
GENERAL GOVERNMENT
FACILITIES AND TECHNOLOGY CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT REVISED APPROVED
BUDGET APPROPRIATIONS FY10-11 FY11-12
AMOUNT THROUGH FY10 APPROPRIATIONS APPROPRIATIONS
BEGINNING FUND BALANCE:11,507,268$ 9,781,490$
ADDITIONAL RESOURCES:
GENERAL OBLIGATION BONDS (03 GOB)500,000$ -$
GENERAL OBLIGATION BONDS (08 GOB)- -
CERTIFICATES OF OBLIGATIONS 380,000 100,000
INTERGOVERNMENTAL TRANSFERS - -
INTRAGOVERNMENTAL TRANSFERS 231,040 -
INVESTMENT EARNINGS 133,000 25,000
OTHER - -
SUBTOTAL ADDITIONAL RESOURCES 1,244,040$ 125,000$
TOTAL RESOURCES AVAILABLE 12,751,308$ 9,906,490$
PUBLIC FACILITIES
LIBRARY BOOK DONATIONS GG9901 291,348 291,348 - -
NORTHGATE IMPROVEMENTS GG0803 180,495 180,495 - -
2 FIRE STATION #6 GG0903 6,990,000 6,990,000 - -
FIRE EMERGENCY RESPONSE ALERTING GG1201 599,000 - - 599,000
2 LIBRARY EXPANSION GG1010 8,385,000 932,000 - -
* CLOSED PROJECTS - -
FACILITY PROJECTS SUBTOTAL -$ -$ 599,000$
TECHNOLOGY PROJECTS 0
MDT SYSTEM REPLACEMENT CO0701 300,000 300,000 - -
WIRELESS INFRASTRUCTURE CO0704 200,000 200,000 - -
FIBER OPTIC INFRASTRUCTURE CO0902 1,000,000 339,000 25,534 36,390
E-MAIL AND FILE SYSTEM MIGRATION CO1201 224,500 - - 224,500
NETWORK & DATA SECURITY UPGRADE CO1202 185,000 - - 185,000
* CLOSED PROJECTS 431,040
IT PROJECTS SUBTOTAL 839,000$ 456,574$ 445,890$
CAPITAL PROJECTS SUBTOTAL 839,000$ 456,574$ 1,044,890$
DEBT ISSUANCE COSTS 5,000$ 1,000$
TRANSFERS 735,910 990,369
OTHER - -
GENERAL & ADMIN. CHARGES 92,942 89,118
TOTAL EXPENDITURES 1,290,426$ 2,125,377$
CAFR Adjustment
ENDING FUND BALANCE:11,460,882$ 7,781,113$
1 - Indicates projects funded through 2003 G.O. Bond Authorization
2 - Indicates projects funded through 2008 G.O. Bond Authorization
BUDGET APPROPRIATIONS
96
GENERAL GOVERNMENT
FACILITIES AND TECHNOLOGY CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT
EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED
THROUGH FY09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY16-17
9,118,722$ 13,351,649$ 9,781,490$ 594,972$ 571,823$ 592,767$ 344,031$ 209,031$
-$ -$ -$ -$ -$ -$ -$ -$
6,240,000 - - 400,000 4,000,000 3,985,000 - -
1,050,000 - 100,000 100,000 100,000 225,000 - -
- - - - - - - -
7,111 108,500 - - - - - -
14,704 58,000 25,000 5,000 5,000 5,000 2,500 2,500
82,512 - - - - - - -
7,394,327$ 166,500$ 125,000$ 505,000$ 4,105,000$ 4,215,000$ 2,500$ 2,500$
16,513,049$ 13,518,149$ 9,906,490$ 1,099,972$ 4,676,823$ 4,807,767$ 346,531$ 211,531$
178,722 18,766 40,000 20,000 20,000 13,860 - - -
79,497 9,301 91,697 - - - - - -
9,715 226,020 405,000 6,349,265 - - - - -
- - - 599,000 - - - - -
- 6,919 - - 315,149 3,819,696 4,243,236 - -
788,496 567,525 430,766 - - - - -
267,934$ 1,049,502$ 1,104,222$ 7,399,031$ 335,149$ 3,833,556$ 4,243,236$ -$ -$
- - - 300,000 - - - - -
76,114 4,866 99,020 - - - - - -
33,093 58,986 186,345 122,500 113,000 134,500 103,500 135,000 113,076
- - - 224,500 - - - - -
- - - 185,000 - - - - -
1,859,760 917,298 - - - - - -
109,207$ 1,923,612$ 1,202,663$ 832,000$ 113,000$ 134,500$ 103,500$ 135,000$ 113,076$
2,973,114$ 2,306,885$ 8,231,031$ 448,149$ 3,968,056$ 4,346,736$ 135,000$ 113,076$
109,565$ 5,000$ 1,000$ 5,000$ 41,000$ 42,000$ -$ -$
- 1,331,832 990,369 - - - -
2,857 - - - - - - -
113,708 92,942 89,118 75,000 75,000 75,000 2,500 2,500
3,199,244$ 3,736,659$ 9,311,518$ 528,149$ 4,084,056$ 4,463,736$ 137,500$ 115,576$
37,844$
13,351,649$ 9,781,490$ 594,972$ 571,823$ 592,767$ 344,031$ 209,031$ 95,955$
PROJECTED EXPENDITURES
97
PUBLIC FACILITY PROJECTS
98
PROJECT:LIBRARY BOOK DONATIONS PROJECT #: GG9901
FUND(S): General Government CIP PROJECT
BUDGET:$291,348
PROJECT FUNDING
MANAGER: David Gerling SOURCES: Funds raised by donations
for library materials
PROJECT
CLIENT: Parks and Recreation
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - 197,488 197,488
2010-11 40,000 40,000
2011-12 20,000 20,000
2012-13 20,000 20,000
2013-14 13,860 13,860
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ -$ 291,348$ 291,348$
P l (S l i /B fit )
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
This money was raised through donations for adding to the collection of books and other items in the Larry J. Ringer Library. Based on
history we anticipate spending $20,000 per year until the funds are depleted.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
-
Larry J. Ringer Library
99
PROJECT:Northgate Improvements PROJECT #: GG0803
FUND(S):137 - General Government CIP PROJECT
BUDGET: $180,495
PROJECT FUNDING
MANAGER: David Gwin SOURCES: 2005 Certificates
of Obligation
PROJECT
CLIENT: Economic Development
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 972 - 87,826 88,798
2010-11 91,697 91,697
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 972$ -$ 179,523$ 180,495$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
Construction of capital improvements in the Northgate area.
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
g
-
-
-
-
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e S
W
el
l
b
orn R
d
Fm 158
100
PROJECT:Fire Station No. 6 PROJECT #: GG0903
FUND(S):137 - General Government CIP Fund PROJECT
BUDGET: $6,990,000
PROJECT FUNDING
MANAGER: Donald Harmon SOURCES: 2008 General Obligation Bonds
PROJECT
CLIENT: Fire Department
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 235,472 - 263 235,735
2010-11 300,000 100,000 5,000 405,000
2011-12 89,278 6,109,027 150,960 6,349,265
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 624,750$ 6,209,027$ 156,223$ 6,990,000$
P l (S l i /B fit )
PROJECT DESCRIPTION
PROJECT SCOPE
Construct a new fire station on the north end of the city to provide better coverage and improved response time to the entertainment corridor
and the University. Operating costs reflect estimated recurring annual expense following full implementation.
This project is for the construction of a new fire station as identified for the 2008 bond election during a facilities planning session in early
2004. Fire Station No. 6 will be located on the southwest corner of the University Drive and Tarrow Street intersection, and will provide the
department improved coverage and response time to the University Drive corridor.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
1 069 368
First Fiscal Year
One Time Costs
72 390Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL **
*Amount included in the FY12 Approved Budget for Fire Station #6 is total of one-time and recurring costs: $1,853,555.
1,214,485$
5,000
14,400
42,800
120,000
639,070$
57,975
1,069,368 72,390
384,480
11,100
9,000
67,042
-
Fm
2
1
5
4Harvey RdWilliam D. Fitch PkwyTexas Ave SWell
b
o
r
n
R
d
Fm 158
U n iversi t y D r E
Lincoln AveTarrow StNimitz StCooner StW a lton DrTexas
AvePasler StEisenhower StFranc is D rAlleyAsh StAshburn AveChimney Hill DrTar
ro
w St
E
Vassar CtChurchill St101
PROJECT:Fire Emergency Response Alerting System PROJECT #: GG1201
FUND(S):137 - General Government CIP PROJECT
BUDGET:$599,000
PROJECT FUNDING
MANAGER: TBD SOURCES: Transfer from GG0401 ($239,409)
2007 CO's
PROJECT Transfer from CO0601 ($359,591)
CLIENT: Fire Department Equipment Replacement Funds
FISCAL YEAR Hardware Software Consulting/Training Other Project Total
Prior Years - - - - -
2010-11 -
2011-12 599,000 599,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 599,000$ -$ -$ -$ 599,000$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual First Fiscal Year
This project is to replace the fire station alerting system and the PA systems in stations 1, 2 and 4. The recommended system meets the
requirements of NFPA 1221 and is designed around a dual link communications of RF and wired IP on separate links that provide for a true
redundant alerting system. The current Fire Station Tone out system is obsolete and does not work well with the new digital radio system. This
system must be compatible with the CAD system upgrade and will include the system as a whole, including dispatch equipment, transmission
medium (wireless vs wired) and fire station equipment. Compatibility with the City of Bryan fire tone out is needed to facilitate automatic aid
agreement.
PROJECT SCOPE
The costs include the complete alerting package for six fire stations and associated programming required to interface with our Computer
Aided Dispatch. Costs for replacing Public address systems at Station 1, 2, and 4 are also included.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Recurring Cost
-
-
One Time Costs
-
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e
S
W
ellb
o
r
n
R
d
Fm 158
102
PROJECT:PROJECT #:
FUND(S):PROJECT
BUDGET:
PROJECT FUNDING
MANAGER: SOURCES:
PROJECT Bonds
CLIENT: Parks and Recreation
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 6,690 - 229 6,919
2010-11 -
2011-12 -
2012-13 300,000 15,149 315,149
2013-14 300,000 3,500,000 19,696 3,819,696
2014-15 265,000 3,960,268 17,968 4,243,236
2015-16 - -
2016-17 -
PROJECT TOTAL -$ 871,690$ 7,460,268$ 53,042$ 8,385,000$
The expansion & renovation to the Larry J. Ringer Library located at 1818 Harvey Mitchell Parkway shall include an expansion of
approximately 15,000 square feet with 16,000 square feet of additional parking.
PROJECT SCOPE
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
LARRY J. RINGER LIBRARY EXPANSION GG1010
Preliminary, Conceptual, Final Design, and Construction Phase Services for Library Expansion. This shall include all associated mechanical,
electrical, plumbing, structural, civil, and fire protection systems, rest room facilities, and office/storage needs including modifications to the
existing parking lot and driveway.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
2008 General Obligation
$8,385,000137 - General Government CIP
Jeff Haeber
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
-
57,000
g
8,000
121,000
20,000
206,000 -$
Larry J. Ringer Library
103
TECHNOLOGY PROJECTS
104
PROJECT: MDT SYSTEM REPLACEMENT PROJECT #: CO0701
FUND: 137 - GENERAL GOVERNMENT CIP PROJECT
BUDGET: $300,000
PROJECT FUNDING
MANAGER: Ben Roper SOURCES: EQUIPMENT REPLACEMENT
FUND
PROJECT
CLIENT: Fire, PD, Utilities
FISCAL YEAR Hardware Software Cons/Training Other PROJECT TOTAL
Prior Years - - - - -
2010-11 -
2011-12 180,507 22,590 81,403 15,500 300,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
The goal of this project is to provide Public Safety Radio System data that meets the current and anticipated
coverage needs of Fire, PD and Emergency Responders. The current system is obsolete and does not provide
complete coverage in key areas that are experiencing growth.
PROJECT SCOPE
This project replaces the electronic equipment that provides the interface between the radio frequency system
(800 MHz radio system) and the Internet Protocol system (Computer Aided Dispatch). This equipment is located at
the Radio Tower and is anticipated to be upgraded following the Radio System Voice Replacement. The Data
System vendor, Motorola, does not offer a low data rate system to replace or upgrade the current data system. A
new vendor, CalAmp (formerly DataRadio), does provide a similar system.
PROJECT DESCRIPTION
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
2015 16
2016-17 -
TOTAL 180,507$ 22,590$ 81,403$ 15,500$ 300,000$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
11,000
300,000$
207,597
Recurring Cost
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
11,000$
First Fiscal Year
81,403
Annual Estimated
One Time Costs
11,000
105
PROJECT:Wireless Infrastructure PROJECT #: CO0704
FUND(S): 137 - General Government CIP PROJECT $200,000
BUDGET:
PROJECT FUNDING
MANAGER: Ben Roper SOURCES: Certificates of Obligation
PROJECT
CLIENT: Information Technology
Project Total
FISCAL YEAR Hardware Software Consulting/Training Other Project Total
Prior Years 18,896 - 57,176 4,908 80,980
2010-11 70,000 29,020 99,020
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 88,896$ -$ 57,176$ 33,928$ 180,000$
Personnel (Salaries/Benefits)
A revised wireless plan was approved by Council in November 2008. This plan included staff and citizen wireless access inside designated
city facilities, a pilot video surveillance project in Northgate, the creation of hot zones for staff and citizen access in select locations
throughout the city.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project will allow the use of Wireless Fidelity (WiFi), by city employees in selected areas of the city, both internal to buildings and
externally in designated "hot zones". The first two phases of the project, wirless access at designated city facilities and the Northgate Video
Surveillance Pilot Project are complete. The final phase is to provide hotspots at designated locations.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
-$
-
-
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e
S
W
ellb
o
rn
R
d
Fm 158
106
PROJECT:Fiber Optic Infrastructure PROJECT #: CO0902
FUND(S): 137 - General Government CIP PROJECT
BUDGET: $1,000,000
PROJECT FUNDING
MANAGER: Ben Roper SOURCES: Certificates of Obligation
PROJECT
CLIENT: Information Technology
Project Total
FISCAL YEAR Hardware Software Consulting/Training Other Project Total
Prior Years 37,633 - 54,131 315 92,079
2010-11 20,000 165,345 1,000 186,345
2011-12 20,000 100,000 2,500 122,500
2012-13 28,000 80,000 5,000 113,000
2013-14 30,000 100,000 4,500 134,500
2014-15 25,000 75,000 3,500 103,500
2015-16 30,000 100,000 5,000 135,000
2016-17 27,000 74,580 11,496 113,076
PROJECT TOTAL 217,633$ -$ 749,056$ 33,311$ 1,000,000$
Personnel (Salaries/Benefits)
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project will support the installation of fiber optic cable to continue expansion of the city's network to new buildings and facilities, and to
permit the connection of existing facilities that are not currently on the network.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
-$
-
-
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e
S
W
ellb
o
rn
R
d
Fm 158
107
PROJECT: E-mail and File System Migration PROJECT #: CO1201
FUND(S): 137 General Government CIP PROJECT 224,500$
BUDGET:
PROJECT Erin Provazek FUNDING TBD
MANAGER:SOURCES: Certificates of Obligation
PROJECT
CLIENT: All City Departments
FISCAL YEAR Hardware Software Consulting/Training Other Project Total
Prior Years - - - - -
2010-11 -
2011-12 6,000 153,591 20,000 44,909 224,500
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 6,000$ 153,591$ 20,000$ 44,909$ 224,500$
Personnel (Salaries/Benefits)
Supplies
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
The city’s E-mail and file systems are managed by Novell software applications. In November 2010, Novell was purchased by Attachmate
Corp. Attachmate is controlled by a consortium led by Microsoft. This sale leaves considerable doubt regarding the long term viability of all
Novell software, but in particular the GroupWise E-mail application and Novell file management application.
PROJECT SCOPE
This project will migrate the city E-mail system from GroupWise to Microsoft Exchange Outlook, and implement Microsoft Enterprise
licensing. This project will also implement a new E-mail Archive system and move file and print management from Novell to Microsoft.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
55,391
-
-
6,000
61,391
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e
S
W
ellb
o
rn
R
d
Fm 158
108
PROJECT: Network & Data Security Upgrade PROJECT #: CO1202
FUND(S): 137 General Government CIP PROJECT $185,000
BUDGET:
PROJECT Ben Roper FUNDING
MANAGER:SOURCES: Certificates of Obligation
PROJECT IT
CLIENT:
FISCAL YEAR Hardware Software Consulting/Training Other Project Total
Prior Years - - -
2010-11 -
2011-12 180,000 5,000 185,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 180,000$ 5,000$ 185,000$
Personnel (Salaries/Benefits)
Supplies
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
This project will examine city wide data security standards, policies and procedures and will result in establishing guidelines and business
practices that will bring the city more closely in alignment with the ISO 27002 standard for information security
PROJECT SCOPE
Included is a security assessment of the main City Computer operating system. Additionally, this project provides the first Payment Card
Industry (PCI) Readiness Assessment. This assessment is the initial step to achieve compliance with standards set by credit card
companies to ensure that we are taking necessary action to be confident that users personal data is secure and protected.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
10,000
-
-
10,000
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e
S
W
ellb
o
rn
R
d
Fm 158
109
Home of Texas A&M University ®
110
SPECIAL REVENUE
DRAINAGE
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH
FISCAL YEAR 2016-2017
111
DRAINAGE UTILITY
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT REVISED APPROVED
PROJECT BUDGET APPROPRIATIONS FY10-11 FY11-12
NUMBER AMOUNT THROUGH FY10 APPROPRIATIONS APPROPRIATIONS
BEGINNING FUND BALANCE:2,216,320$ 2,244,529$
ADDITIONAL RESOURCES:
UTILITY REVENUES 1,886,800$ 1,976,200$
INTEREST ON INVESTMENTS 29,900 8,100
BOND PROCEEDS - -
INTERGOVERNMENTAL TRANSFERS - -
INTRAGOVERNMENTAL TRANSFERS 14,000 13,473
TRANSFERS OUT - -
OTHER - -
SUBTOTAL ADDITIONAL RESOURCES 1,930,700$ 1,997,773$
TOTAL RESOURCES AVAILABLE 4,147,020$ 4,242,302$
DRAINAGE CAPITAL
GREENWAYS PROJECTS SD9903 3,640,000$ 3,640,000 - -
MINOR DRAINAGE IMPROVEMENTS SD1201 ANNUAL 70,407 123,851 200,000
EMERALD FOREST DRAINAGE IMP SD1006 257,120$ 237,120 20,000 -
W SOUTHWOOD 5-7 SD1103 56,149$ - 56,149 -
WOLF PEN CREEK EROSION CONTROL SD1102 312,000$ - 50,500 261,500
STORMWATER MAPPING SD0523 67,070$ 34,070 16,000 -
MTIGATION FENCING - ARRINGTON/DECATUR SD0901 100,000$ 100,000 - -
DRAINAGE MASTER PLAN SD1202 500,000$ - - 500,000
CLOSED PROJECTS - - -
CAPITAL G&A 212,922 160,510
CAPITAL PROJECTS SUBTOTAL 479,422$ 1,122,010$
BUDGET APPROPRIATIONS
DRAINAGE OPERATIONS
DRAINAGE INSPECTION (PLANNING & DEV SERVICES) ANNUAL - 74,300
DRAINAGE MAINTENANCE OPERATIONS (PUBLIC WORKS)ANNUAL 869,531 941,713
PAY PLAN CONTINGENCY - -
MOSQUITO ABATEMENT 7,200 7,200
BEE CREEK MITIGATION MONITORING/REPORTING (SD0902)28,000 13,000
TRANSFERS OUT 65,000 -
GENERAL & ADMIN. 315,451 330,845
TOTAL EXPENDITURES 1,764,604$ 2,489,068$
Measurement Focus Adjustment
ENDING FUND BALANCE: 2,382,416$ 1,753,234$
W Project funded through combination of sources. Project sheet reflected in Water section of CIP document.
112
DRAINAGE UTILITY
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT
EXPENDITURES ACTUAL ESTIMATED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED
THROUGH FY09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY 16-17
2,932,126$ 2,505,270$ 2,244,529$ 1,323,664$ 1,276,382$ 1,568,615$ 1,883,773$ 2,216,317$
1,895,263$ 1,918,632$ 1,976,200$ 2,035,500$ 2,096,600$ 2,159,500$ 2,224,300$ 2,291,000$
14,915 12,000 8,100 10,000 10,000 10,000 12,000 14,000
- - - - - - - -
- - - - - - - -
- - 13,473 - - - - -
- - - - - - - -
- - - - - - - -
1,910,178$ 1,930,632$ 1,997,773$ 2,045,500$ 2,106,600$ 2,169,500$ 2,236,300$ 2,305,000$
4,842,304$ 4,435,902$ 4,242,302$ 3,369,164$ 3,382,982$ 3,738,115$ 4,120,073$ 4,521,317$
2,356,401 493,106 127,500 355,000 307,993 - - - -
- 194,258 200,000 200,000 200,000 200,000 200,000 200,000
- 41,192 215,928 - - - - - -
- - 56,149 - - - - - -
- - 26,000 286,000 - - - - -
- - - 50,070 17,000 - - - -
2,944 15,764 40,800 - - - - - -
- - - 500,000 - - - - -
409,121 81,877
212,922 160,510 165,325 170,285 175,394 180,655 186,075
959,182$ 955,434$ 1,551,580$ 690,318$ 370,285$ 375,394$ 380,655$ 386,075$
PROJECTED EXPENDITURES
- - 74,300 76,529 78,825 81,190 83,625 86,134
817,631 820,288 941,713 969,964 999,063 1,029,035 1,059,906 1,091,703
- - - - - -
17,760 7,200 7,200 7,200 7,200 7,200 7,200 7,200
- 28,000 13,000 8,000 8,000 - - -
- 65,000 - - - - - -
555,426 315,451 330,845 340,770 350,993 361,523 372,369 383,540
2,349,999$ 2,191,373$ 2,918,638$ 2,092,782$ 1,814,367$ 1,854,342$ 1,903,756$ 1,954,653$
12,965
2,505,270$ 2,244,529$ 1,323,664$ 1,276,382$ 1,568,615$ 1,883,773$ 2,216,317$ 2,566,665$
113
PROJECT:GREENWAYS PROJECTS PROJECT #: SD9903
FUND(S): 912 - DRAINAGE UTILITY FUND PROJECT
BUDGET: $3,640,000
PROJECT FUNDING
MANAGER:Venessa Garza SOURCES: General Obligation Bonds
PROJECT
CLIENT:Planning & Development Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 2,777,811 56,608 - 15,088 2,849,507
2010-11 100,000 25,000 2,500 127,500
2011-12 300,000 50,000 5,000 355,000
2012-13 252,993 50,000 5,000 307,993
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 3,430,804$ 181,608$ -$ 27,588$ 3,640,000$
P l (S l i /B fit )
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
This project serves to hold funds for new greenways projects. Original budget was $3,640,000. $1,194,124 of Greenways funds were spent
on the City Center land purchase.
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e
S
W
ellb
orn R
d
Fm 158
114
PROJECT:MINOR DRAINAGE PROJECT #: SD1201
IMPROVEMENTS
FUND(S):PROJECT
912 - DRAINAGE FUND BUDGET: $200,000
PROJECT FUNDING
MANAGER: Gary Balmain SOURCES: DRAINAGE UTILITY
FUND
PROJECT
CLIENT: Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 194,258 194,258
2011-12 200,000 200,000
2012-13 200,000 200,000
2013-14 200,000 200,000
2014-15 200,000 200,000
2015-16 200,000 200,000
2016-17 200,000 200,000
PROJECT TOTAL -$ -$ 1,394,258$ -$ 1,394,258$
Funds budgeted on an annual basis as available for minor drainage improvements throughout the City. The funds are used to construct
improvements to our storm drainage system and to replace drainage infrastructure that is no longer adequate either due to it wearing out or
due to increased capacity demand. Projects that have been done in the past include the Camelot Subdivision channel improvements, repairs
to a washed out culvert on Rock Prairie West, replacement of aged culvert on Southwest Parkway, installation of concrete valley gutter in the
Raintree subdivision and repairs to erosion on Wolf Pen Creek, the King Cole Culvert Replacement and Emerald Forest Drainage
Improvements. Additional projects may come out of planned neighborhood rehab projects in the eastgate area
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
The project will be used to identify and repair/replace deteriorated corrugated metal culvert pipe.
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s A
v
e S
W
ellb
orn R
d
Fm 158
115
PROJECT:Emerald Forest Drainage Improvements PROJECT #: SD1006
FUND(S):PROJECT
912 - DRAINAGE FUND BUDGET: $257,120
PROJECT FUNDING
MANAGER: Jeff Haeber SOURCES: DRAINAGE UTILITY FUND
PROJECT
CLIENT:Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 41,192 - - 41,192
2010-11 21,908 183,115 10,906 215,928
2011-12 - -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 63,100$ 183,115$ 10,906$ 257,120$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
This project is for the design of drainage improvements in Emerald Forest. Residents concerned about standing water, erosion and the
stability of some of the existing retaining walls contacted the City for help.
PROJECT SCOPE
The area of proposed improvements is situated in the common back lot line of Emerald Forest Phases Three and Four, specifically adjacent
to the common utility easement from Emerald Parkway to Sebesta Road. This project will require authorization from the U.S. Army Corps of
Engineers under Nationwide Permits for impacts to waters of the U.S.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
g
-
-
-
-
-
-
-
Fm
2
1
5
4Harvey RdWi llia m D. Fitch PkwyTexas Ave S
W
ellborn R
d
Fm 158
E m e r a ld Pkwy
Sebesta RdFrontage 6 Rd ESands t one Dr
Fr o s t D r
Fo xfire DrAppomatt
ox Dr
Oakwood TrlBent Oak StAlle
yOnramp 6 NCorsair CirAmber R id g e D r
D
riftw
ood Dr
F
o
xfire Dr
116
PROJECT:Wolf Pen Creek Erosion Control PROJECT #: SD1102
FUND(S):PROJECT
912 - DRAINAGE FUND BUDGET: $312,000
PROJECT FUNDING
MANAGER: Danielle Charbonnet SOURCES: DRAINAGE UTILITY
FUND
PROJECT
CLIENT:Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 22,000 4,000 26,000
2011-12 3,000 257,000 26,000 286,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 25,000$ 257,000$ 30,000$ 312,000$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
This project is for the design of erosion control measures along the upper trails of Wolf Pen Creek. Bank stabilization measures will be
designed to protect the trails, irrigation, benches and other improvements in the upper trails area from erosion.
PROJECT SCOPE
Plans, specifications, and cost estimates for bank stabilization for areas in the Wolf Pen Creek upper trails area that are subject to erosion.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Recurring Cost
-
-
One Time Costs
-
-
-
-
-
Fm
2
1
5
4Harvey RdWilli a m D. Fitch PkwyTexas
A
ve
S
W
ellborn R
d
WOLF PEN CREEK PARKWOLF PEN CREEK PARK
Dar
t
mo
uth
St Colgate DrManuel DrH o l l e m a n D r E
Sterling StCy
p
r
e
s
s
Dr
All
e
yAzalea CtRichards StC a m ell ia CtCr
e
s
t St
Kalanchoe Ct117
PROJECT:Stormwater Mapping PROJECT #: SD0523
FUND(S):912 - Drainage Fund PROJECT
BUDGET: $67,070
PROJECT FUNDING
MANAGER:TBD SOURCES: Drainage Utility Fund
PROJECT
CLIENT:Public Works
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 50,070 50,070
2012-13 17,000 17,000
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 67,070$ -$ -$ 67,070$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated AnnualFirst Fiscal Year
This project provides funds for the mapping of College Station stormwater infrastructure. This project serves as a holding account for specific
projects yet to be identified.
Original Budget $200,000, $50,000 transferred to SD0703 - FY07, $7,000 transferred to SD0805 - FY08, $10,000 transferred to SD0703 -
FY08, $49,930 transferred to SD1005 - FY10, $16,000 transferred to SD0703 - FY10
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s
A
v
e S
W
el
l
b
orn R
d
Fm 158
118
PROJECT: Fence for Mitigation at Arrington/PROJECT #: SD0901
Decatur
FUND: 912 - Drainage Utility Fund PROJECT
BUDGET: $100,000
PROJECT FUNDING
MANAGER: Jeff Haeber SOURCES: Drainage Utility Funds
PROJECT
CLIENT: Public Works
FISCAL YEAR LAND ENG. CONSTR. MISC.PROJECT TOTAL
Prior Years 8,403 10,305 18,708
2010-11 2,800 35,000 3,000 40,800
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
TOTAL -$ 11,203$ 45,305$ 3,000$ 59,508$
PROJECT DESCRIPTION
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
OPERATIONS AND MAINTENANCE COSTS
The goal of this project is to construct a fence around the TxDOT Conservation Easement in order to maintain the
integrity of the easement and protect the endangered Navasota Ladies Tresses plants. Project is anticipated to
come in under budget.
PROJECT SCOPE
The project is for the design, bidding, and construction of approximately 5,200 Linear Feet of barbed wire fence
including access gates.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
One Time Costs Recurring Cost
-$ -$
First Fiscal Year Annual Estimated
119
PROJECT:Drainage Master Plan PROJECT #: SD1202
FUND(S):912 - Drainage Fund PROJECT $500,000
BUDGET:
PROJECT TBD FUNDING
MANAGER:SOURCES: Drainage Utility Fund
PROJECT Department of Public Works
CLIENT:
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 500,000 500,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 500,000$ -$ -$ 500,000$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
Develop an inventory of existing infrastructure and a twenty (20) year maintenance and infrastructure improvement plan for those portions of
the drainage basins that lie within the city limits.
This is a consulting contract and will form the foundation for future infrastructure projects.
PROJECT SCOPE
Develop a twenty (20) year plan for maintenance and infrastructure improvement projects.
Develop a GIS layer of existing infrastructure.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s A
v
e S
W
ellb
orn R
d
Fm 158
120
SPECIAL REVENUE -
PARK LAND DEDICATION
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH
FISCAL YEAR 2016-2017
121
Home of Texas A&M University ®
122
1
2
3
4
5
6
7
8
9
10 11
1213
14
1516
17
18
19 20 21
22
23
24
25
26 27
28
29
Grimes
County
Burleson
County
Legend
Neighborhood Park Zones
TAMU Property
CS City Limits
Parkland Dedication Zones
N
Adopted by City Council Oct.23,2008
123
GENERAL GOVERNMENT
PARK LAND DEDICATION
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT REVISED APPROVED
PROJECT BUDGET APPROPRIATIONS FY 10-11 FY 11-12
NUMBER AMOUNT THROUGH FY10 APPROPRIATIONS APPROPRIATIONS
BEGINNING FUND BALANCE:1,319,067$ 1,587,848$
ADDITIONAL RESOURCES:
CONTRIBUTIONS 300,000$ 300,000$
INVESTMENT EARNINGS 16,000 5,000
INTRAGOVERNMENTAL TRANSFERS - -
OTHER - -
SUBTOTAL ADDITIONAL RESOURCES 316,000$ 305,000$
TOTAL RESOURCES AVAILABLE 1,635,067$ 1,892,848$
PARKLAND DEDICATION FUND
ZONE 1 PARK PK0051 15,000 - 18,000 15,000
ZONE 2 PARK PK0052 20,000 - - 20,000
PK UNIVERSITY PARK PK0410 12,000 - 12,000 -
ZONE 3 PARK PK0053 85,000 - 70,000 85,000
CENTRAL PK RAINWATER HARVESTING PK1013 50,000 50,000 - -
ZONE 4 PARK PK0054 - - 37,000 -
CARTER CROSSING PARK PK1202 36,000 - - 36,000
ZONE 5 PARK PK0055 - - - -
ZONE 6 PARK PK0056 95,000 - 95,000 95,000
SOUTHWEST PARK DEVELOPMENT PK0806 268,000 258,000 10,000 -
ZONE 7 PARK PK0057 10,000 - - 10,000
JOHN CROMPTON PARK PHASE III PK0904 149,000 114,000 35,000 -
ZONE 8 PARK PK0058 - - - -
PK EMERALD FOREST PARK IMP.PK0713 63,000 48,000 15,000 -
ZONE 9 PARK PK0059 20,000 - - 20,000
ZONE 10 PARK PK0060 285,000 170,000 285,000
ZONE 11 PARK PK0061 - - 32,000 -
ZONE 12 PARK PK0824 24,000 - 24,000 24,000
ZONE 13 PARK PK0807 - - - -
ZONE 14 PARK PK0717 77,000 - 77,000 77,000
ZONE 15 PARK PK0808 325,000 - 268,000 325,000
COMMUNITY PARK ZONE B PK1203 155,000 - - 155,000
SOUTHWOOD VALLEY IMP PK1117 60,000 - 60,000 -
COMMUNITY PARK ZONE C PK1204 35,000 - - 35,000
NEIGHBORHOOD PARK ZONE 24 PK1205 15,000 - - 15,000
CLOSED PROJECTS 103,500 -
CAPITAL PROJECTS SUBTOTAL 470,000$ 1,026,500$ 1,197,000$
OTHER - -
GENERAL & ADMIN. CHARGES 19,513 26,373
TOTAL EXPENDITURES 1,046,013$ 1,223,373$
CAFR Adjustment
ENDING FUND BALANCE:589,054$ 669,475$
PK = Project funded through combination of sources. Project sheet reflected in Parks and Recreation section of CIP document.
BUDGET APPROPRIATIONS
124
GENERAL GOVERNMENT
PARK LAND DEDICATION
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT
EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED
THROUGH FY09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY 16-17
1,489,259$ 1,669,186$ 1,587,848$ 453,160$ 431,787$ 416,787$ 401,787$ 386,787$
590,487$ 300,000$ 300,000$ -$ -$ -$ -$
5,879 8,000 5,000 5,000 5,000 5,000 5,000 5,000
- - - - - - -
- - - - - - -
596,366$ 308,000$ 305,000$ 5,000$ 5,000$ 5,000$ 5,000$ 5,000$
2,085,625$ 1,977,186$ 1,892,848$ 458,160$ 436,787$ 421,787$ 406,787$ 391,787$
- - - 15,000 - - - - -
- - - 20,000 - - - - -
1,785 5,320 4,895 - - - - -
- - - 85,000 - - - - -
- - 50,000
- - - - - - - - -
- - - 36,000 - - - - -
- 650 - - - - - - -
- 502 - 95,000 - - - - -
220 - 59,500 208,280 - - - - -
- - - 10,000 - - - - -
54,957 27,956 56,087 10,000 - - - - -
- - - - - - - - -
- - 63,000 - - - - - -
- - - 20,000 - - - - -
- - - 285,000 - - - - -
- - - - - - - - -
- - - 24,000 - - - - -
- - - - - - - - -
- - - 77,000 - - - - -
- 6 - 325,000 - - - - -
- - - 155,000 - - - - -
- - 60,000 - - - - - -
- - - 35,000 - - - - -
- - - 15,000 - - - - -
372,767 82,000
55,177$ 403,666$ 375,907$ 1,420,175$ -$ -$ -$ -$ -$
- - - - - - -
13,431 19,513 26,373 20,000 20,000 20,000 20,000 20,000
417,097$ 389,338$ 1,439,688$ 26,373$ 20,000$ 20,000$ 20,000$ 20,000$
658$
1,669,186$ 1,587,848$ 453,160$ 431,787$ 416,787$ 401,787$ 386,787$ 371,787$
PROJECTED EXPENDITURES
125
PROJECT: ZONE 1 PARK PROJECT #: PK0051
FUND: 171 - Zone 1 Parkland PROJECT
BUDGET: $15,000
PROJECT
MANAGER: TBD FUNDING
SOURCES: Zone 1 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
FISCAL YEAR LAND ENG. CONSTR. MISC.PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 15,000 $15,000
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $15,000 $0 $15,000
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
OPERATING COSTS
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvements
as identified for the Spruce Street property (Northgate Park) in Park Zone 1.
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0
First Fiscal Year Annually
$0 $0
126
PROJECT: ZONE 2 PARK PROJECT #: PK0052
FUND: 172 - Zone 2 Parkland PROJECT
BUDGET: $20,000
PROJECT
MANAGER: TBD FUNDING
SOURCES: Zone 2 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
improvement and renovation projects as identified in Park Zone 2.
FISCAL YEAR LAND ENG. CONSTR. MISC.PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 20,000 $20,000
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $20,000 $0 $20,000
Total
Personnel $0
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
OPERATING COSTS
First Fiscal Year Annually
Supplies $0
Service $0
Capital $0
TOTAL $0$0 $0
127
PROJECT: ZONE 3 PARK PROJECT #: PK0053
FUND: 173 - Zone 3 Parkland PROJECT
BUDGET: $85,000
PROJECT
MANAGER: TBD FUNDING
SOURCES: Zone 3 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
improvement and renovation projects as identified in Park Zone 3.
FISCAL YEAR LAND ENG. CONSTR. MISC.PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 85,000 $85,000
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $85,000 $0 $85,000
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0
OPERATING COSTS
First Fiscal Year Annually
$0 $0
128
PROJECT:Rainwater Harvesting Central Park PROJECT #: PK1013
FUND(S):PROJECT
173 - Zone 3 Parkland BUDGET: $50,000
PROJECT FUNDING
MANAGER: Pete Vanecek SOURCES: Zone 3 Parkland Dedication
Funds
PROJECT
CLIENT: Parks and Recreation
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 2,000 46,500 1,500 50,000
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 2,000$ 46,500$ 1,500$ 50,000$
Personnel (Salaries/Benefits)
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
This park project is for landscape and hardscape enhancements at the office and pavilion and the Rainwater Harvesting System
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
25
-
25
-
100
-
150
129
PROJECT: ZONE 4 PARK PROJECT #: PK0054
FUND: 174 - Zone 4 Parkland PROJECT
BUDGET: $0
PROJECT
MANAGER: TBD FUNDING
SOURCES: Zone 4 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
improvement and renovation projects as identified in Park Zone 4.
FISCAL YEAR LAND ENG. CONSTR. MISC.PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 $0
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $0 $0 $0
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0$0 $0
OPERATING COSTS
First Fiscal Year Annually
130
PROJECT:Carters Crossing Park PROJECT #: PK1202
FUND(S):174 - Zone 4 Park Land PROJECT
BUDGET: $36,000
PROJECT FUNDING
MANAGER: Pete Vanecek SOURCES: Zone 4 Park Land Dedication
Funds
PROJECT
CLIENT: Parks and Recreation
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 3,000 28,500 4,500 36,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 3,000$ 28,500$ 4,500$ 36,000$
This project will be completed in phases as funding permits. The FY12 estimate reflects the funding that is available for the first phase of the
project.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
The project will include some development of the park to include a tot playground, sidewalks, benches, entryway, trash can and creek
crossing (to be determined).
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
-
Fm
2
1
5
4Harvey RdW illiam D. Fitch PkwyT
e
x
a
s A
v
e S
W
ellb
o
r
n
R
d
Fm 158
A
P
P
O
M
A
T
T
O
X D
RIV
E
NORTH FOREST PARKWAYSHADOW OAKSS T T H O M A S R D
S P R IN G C R E E K
WI
LDEWOOD CI
RCARTER'S CROSSING CARTER'S CROSSING
131
PROJECT: ZONE 5 PARK LAND PROJECT #: PK0055
FUND: 175 - Zone 5 Parkland PROJECT
BUDGET: $0
PROJECT
MANAGER: TBD FUNDING
SOURCES: Zone 5 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
FISCAL YEAR LAND ENG. CONSTR. MISC.PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 $0
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $0 $0 $0
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
OPERATING COSTS
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvements
and renovation projects identified in Zone 5.
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0$0 $0
OGCOSS
First Fiscal Year Annually
132
PROJECT: ZONE 6 PARK PROJECT #: PK0056
FUND: 176 - Zone 6 Parkland PROJECT
BUDGET: $95,000
PROJECT
MANAGER: TBD FUNDING
SOURCES: Zone 6 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
improvement and renovation projects as identified in Park Zone 6.
FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 95,000 $95,000
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $95,000 $0 $95,000
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
OPERATING COSTS
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0
OPERATING COSTS
First Fiscal Year Annually
$0 $0
133
PROJECT:Southwest Park Development PROJECT #: PK0806
FUND(S):176 - Zone 6 Parkland PROJECT
BUDGET: $268,000
PROJECT FUNDING
MANAGER: Danielle Charbonnet SOURCES: Zone 6 Parkland Dedication
Funds
PROJECT
CLIENT: Parks and Recreation
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - 220 220
2010-11 1,500 44,000 14,000 59,500
2011-12 11,000 177,000 20,280 208,280
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 1,500$ 55,000$ 177,000$ 34,500$ 268,000$
Personnel (Salaries/Benefits)
The trail will connect with the north end of the Campus Village Trail at Christine Lane and continue to Southwest Parkway. The project
includes a bridge crossing, retaining wall, and box culverts. It will be designed in-house by Public Works staff and constructed with Phase II
of the Hike & Bike Trail Completion Project, ST-1103.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
The first phase will be to construct a 10' wide hike and bike trail through Southwest Park. This connection will provide a continuous trail from
Texas Avenue to Southwest Parkway.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
15,000 -$
2,400
-
-
-
12,600
134
PROJECT: Zone 7 Parkland PROJECT #: PK0057
FUND: 177 - Zone 7 Parkland PROJECT
BUDGET:$10,000
PROJECT
MANAGER: TBD FUNDING
SOURCES: Zone 7 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
FISCAL YEAR LAND ENG. CONSTR. MISC.PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 10,000 $10,000
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $10,000 $0 $10,000
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
OPERATING COSTS
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park improvement
and renovation projects in Park Zone 7.
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0$0
OPERATING COSTS
First Fiscal Year Annually
135
PROJECT:John Crompton Park, Phase III PROJECT #: PK0904
FUND(S):177 - Zone 7 Parkland PROJECT
BUDGET: $149,000
PROJECT Pete Vanecek FUNDING
MANAGER: SOURCES: Zone 7 Parkland Dedication
Funds
PROJECT
CLIENT: Parks and Recreation
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 4,194 78,719 - 82,913
2010-11 4,658 $51,429 56,087
2011-12 $10,000 10,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 10,000$ 8,852$ 130,148$ -$ 149,000$
Personnel (Salaries/Benefits)
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
Phase III development of Crompton Park.
PROJECT SCOPE
Improvements include the addition of concrete sidewalks, area lights, signage, land acquisition and a playground.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
-
136
PROJECT: ZONE 8 PARK PROJECT #: PK0058
FUND: 178 - Zone 8 Parkland PROJECT
BUDGET: $0
PROJECT
MANAGER: TBD FUNDING
SOURCES: Zone 8 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
improvement and renovation projects as identified in Park Zone 8.
FISCAL YEAR LAND ENG. CONSTR. MISC.PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 $0
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $0 $0 $0
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0$0 $0
OPERATING COSTS
First Fiscal Year Annually
137
PROJECT: ZONE 9 PARK PROJECT #: PK0059
FUND: 179 - Zone 9 Parkland PROJECT
BUDGET: $20,000
PROJECT
MANAGER: TBD FUNDING
SOURCES: Zone 9 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
improvement and renovation projects as identified in Park Zone 9.
FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 20,000 $20,000
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $20,000 $0 $20,000
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
OPERATING COSTS
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0
OPERATING COSTS
First Fiscal Year Annually
$0 $0
138
PROJECT:PROJECT #: PK0060
FUND:PROJECT
BUDGET:$285,000
PROJECT
MANAGER: TBD FUNDING
SOURCES: Zone 10 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
FISCAL YEAR LAND ENG. CONSTR. MISC.PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 285,000 $285,000
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $285,000 $0 $285,000
Total
Personnel $0
Supplies $0
Service $0
ZONE 10 PARK
180 - Zone 10 Parkland
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
OPERATING COSTS
First Fiscal Year Annually
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
improvement and renovation projects as identified in Park Zone 10.
Service $0
Capital $0
TOTAL $0$0 $0
139
PROJECT: ZONE 11 PARK PROJECT #: PK0061
FUND:PROJECT
BUDGET: $0
PROJECT
MANAGER: TBD FUNDING
SOURCES: Zone 11 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
improvement and renovation projects as identified in Park Zone 11.
FISCAL YEAR LAND ENG. CONSTR. MISC.PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 $0
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $0 $0 $0
181 - Zone 11 Parkland
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0
OPERATING COSTS
First Fiscal Year Annually
$0 $0
140
PROJECT: ZONE 12 PARK PROJECT #: PK0824
FUND:PROJECT
BUDGET:$24,000
PROJECT
MANAGER: TBD FUNDING
SOURCES: Zone 12 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
improvement and renovation projects as identified in Park Zone 12.
FISCAL YEAR LAND ENG. CONSTR. MISC.PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 24,000 $24,000
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $24,000 $0 $24,000
182 - Zone 12 Parkland
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0
OPERATING COSTS
First Fiscal Year Annually
$0 $0
S
H 6 S
LAKEWAY DRIVE
ARRINGTON ROADGREENS PRAIRIE ROAD WESTW A Y F A R E R L NVICTORIA AVEO
N
R
A
MP
6
N
SH 6 S
11
12
21
20
10
22
13
9
29
26
28
22
24
14
23
5
8
19 21
17 11
4
6
27
25
9
2
18 13
3
20
15
12
10
16
7
1
141
PROJECT: ZONE 13 PARK PROJECT #: PK0807
FUND: PROJECT
BUDGET: $0
PROJECT
MANAGER: TBD FUNDING
SOURCES: Zone 13 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 $0
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $0 $0 $0
OPERATING COSTS
183 - Zone 13 Parkland
improvements and renovation projects as identified in Park Zone 13.
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0
OPERATING COSTS
First Fiscal Year Annually
$0 $0
SH
6
SBARRON ROADVI
CTORI
A AVEGREENS PRAIRIE ROAD WESTFM 2154GRAHAM ROADDECATUR DRI
VEALLEYP1-735ABBATE ROADFM 2154FM 2154VICTORIA AVE13
10
15
19
12
5
20
9
18
26
29
26
28
22
24
14
23
5
8
19 21
17 11
4
6
27
25
9
2
18 13
3
20
15
12
10
16
7
1
142
PROJECT: ZONE 14 PARK PROJECT #: PK0717
FUND: PROJECT
BUDGET: $77,000
PROJECT
MANAGER: PETE VANECEK FUNDING
SOURCES: Zone 14 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 77,000 $77,000
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $77,000 $0 $77,000
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
OPERATING COSTS
184 - Zone 14 Parkland
improvements and renovation projects as identified in Park Zone 14.
PROJECT DESCRIPTION/STATUS
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0
OPERATING COSTS
First Fiscal Year Annually
$0 $0
SH
6
SROCK PRAIRIE ROADOLDEN LANEBRADLEY ROADSH 6 S24
14
28
23
9
11
8
25
10
1213
29
26
28
22
24
14
23
5
8
19 21
17 11
4
6
27
25
9
2
18 13
3
20
15
12
10
16
7
1
143
PROJECT: ZONE 15 PARK PROJECT #: PK0808
FUND: PROJECT
BUDGET: $325,000
PROJECT
MANAGER: TBD FUNDING
SOURCES: Zone 15 Parkland Dedication
PROJECT Funds
CLIENT: Parks and Recreation
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 325,000 $325,000
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $325,000 $0 $325,000
OPERATING COSTS
185 - Zone 15 Parkland
improvements and renovation projects as identified in Park Zone 15.
PROJECT DESCRIPTION/STATUS
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0
OPERATING COSTS
First Fiscal Year Annually
$0 $0
29
26
28
22
24
14
23
5
8
19 21
17 11
4
6
27
25
9
2
18 13
3
20
15
12
10
16
7
1
FM 2154WELSH AVEHOLL
EMAN DRI
VE SOUTHDOWLING ROAD NORTHO N R A M P
MEIR LANEFM 21545
15
18 13
7
10
19
6
29
17
144
PROJECT: Community Park Zone B PROJECT #: PK1203
FUND:PROJECT
BUDGET: $155,000
PROJECT
MANAGER: TBD FUNDING
SOURCES: Community Park Zone B Parkland
PROJECT Dedication Funds
CLIENT: Parks and Recreation
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
FISCAL YEAR LAND ENG. CONSTR. MISC.PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 155,000 $155,000
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $155,000 $0 $155,000
161 -Community Park Zone B
PROJECT DESCRIPTION/STATUS
improvements and renovation projects as identified in Community Park Zone B.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
OPERATING COSTS
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0$0 $0
First Fiscal Year Annually
OPERATING COSTS
B
A
D
C
B
A
D
C
145
PROJECT:Southwood Valley Improvements PROJECT #: PK1117
FUND(S):162 - Community Park Zone B Parkland PROJECT
BUDGET: $60,000
PROJECT Pete Vanecek FUNDING
MANAGER: SOURCES: Community Park Zone B
Park Land Dedication Funds
PROJECT
CLIENT:Parks and Recreation
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 42,000 18,000 60,000
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 42,000$ 18,000$ 60,000$
Personnel (Salaries/Benefits)
This project is for replacement of existing concrete walks and ramps at the Sr.and Little League ballfied complexes.It is also to purchase site
furnishings such as picnic tables,benches,and bbq grills for a shaded picnic area
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
-
Fm 2154Roc k Prairie R d Fr
ont
age 6 Rd ENavarro DrA lleyPi
erre Pl
Eagle AveMortier DrH a rtfo rd D rHaley P lNormand Dr
G ail PlSchaffer RdSophia L n
Ke rn sto w n L nCarmel PlBr
i
dl
e CtPinon DrFm
2154Harvey RdW illiam D. Fitch PkwyTexas Ave
SWellbor
n RdFm 158
146
PROJECT: Community Park Zone C PROJECT #: PK1204
FUND:PROJECT
BUDGET: $35,000
PROJECT
MANAGER: TBD FUNDING
SOURCES: Community Park Zone C Parkland
PROJECT Dedication Funds
CLIENT: Parks and Recreation
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
FISCAL YEAR LAND ENG. CONSTR. MISC.PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 35,000 $35,000
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $35,000 $0 $35,000
162 -Community Park Zone C
PROJECT DESCRIPTION/STATUS
improvements and renovation projects as identified in Community Park Zone C.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
OPERATING COSTS
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0$0 $0
First Fiscal Year Annually
OPERATING COSTS
D
C
B
A
D
C
147
PROJECT: Neighborhood Park Zone 24 PROJECT #: PK1205
FUND: PROJECT
BUDGET: $15,000
PROJECT
MANAGER: TBD FUNDING
SOURCES: Neighborhood Park Zone 24
PROJECT Parkland Dedication Funds
CLIENT: Parks and Recreation
In accordance with the Parkland Dedication Ordinance, these funds have been set aside for park
FISCAL YEAR LAND ENG. CONSTR. MISC. PROJECT TOTAL
Prior Years $0 $0 $0 $0 $0
2010-11 $0
2011-12 15,000 $15,000
2012-13 $0
2013-14 $0
2014-15 $0
2015-16 $0
2016-17 $0
TOTAL $0 $0 $15,000 $0 $15,000
194 - Neighborhood Park Zone 24
PROJECT DESCRIPTION/STATUS
improvements and renovation projects as identified in Neighborhood Park Zone 24.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
OPERATING COSTS
Total
Personnel $0
Supplies $0
Service $0
Capital $0
TOTAL $0
First Fiscal Year Annually
OPERATING COSTS
$0 $0
S
H
6
SHARVEY ROADROCK PRAIRIE ROADFRONTAGE 6 RD WFROST DRIVE24
8 14
25
4
5
3
9
28
6
23
2
11
29
26
28
22
24
14
23
5
8
19 21
17 11
4
6
27
25
9
2
18 13
3
20
15
12
10
16
7
1
148
ELECTRIC
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH
FISCAL YEAR 2015-2016
149
ELECTRIC SERVICE
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2015-2016
FY10-11
FY 09-10 REVISED FY 10-11
ACTUAL BUDGET ESTIMATE
BEGINNING FUND BALANCE:$994,199 $535,220 $831,557
UTILITY REVENUE BONDS/CO's $7,655,377 $5,410,000 $4,735,000
INTEREST ON INVESTMENTS (1,671) 6,000 6,000
OTHER - - -
INTERGOVERNMENTAL TRANSFERS - - 886,953
INTRAGOVERNMENTAL TRANSFERS - - -
SUBTOTAL ADDITIONAL RESOURCES $7,653,706 $5,416,000 $5,627,953
TOTAL RESOURCES AVAILABLE $8,647,905 $5,951,220 $6,459,510
CAPITAL PROJECTS:
PRODUCTION - - -
GENERAL PLANT 168,398 1,050,000 1,050,000
OVERHEAD SYSTEM IMPROV. 1,194,338 1,100,000 1,060,000
UNDERGROUND SYSTEM IMPROV. 910,036 1,200,000 993,000
NEW SERVICES & SYSTEM EXT. 1,038,215 1,294,000 1,056,168
RES. STREET LIGHTING 365,040 85,000 86,000
THOR. STREET LIGHTING 589,541 250,000 247,000 ,,,
DISTRIBUTION 2,460,530 523,000 690,000
TRANSMISSION 2,098,919 373,000 483,068
GENERAL AND ADMINISTRATIVE 26,210 23,215 23,215
DEBT ISSUANCE COST 3,950 25,000 15,000
TOTAL EXPENDITURES 8,855,177$ 5,923,215$ 5,703,451$
MEASUREMENT FOCUS ADJUSTMENT 1,038,829$
ENDING FUND BALANCE:$831,557 $28,005 $756,059
150
ELECTRIC SERVICE
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2015-2016
FY11-12
APPROVED PROJECTED PROJECTED PROJECTED PROJECTED
BUDGET FY12-13 FY13-14 FY14-15 FY15-16
$756,059 $15,959 $9,959 $28,959 $3,959
$8,825,000 $9,115,000 $4,160,000 $4,200,000 $1,900,000
6,000 4,000 4,000 6,000 6,000
- - - - -
- - - - -
- - - - 3,500,000
$8,831,000 $9,119,000 $4,164,000 $4,206,000 $5,406,000
$9,587,059 $9,134,959 $4,173,959 $4,234,959 $5,409,959
3,000,000 - - - -
650,000 1,050,000 50,000 50,000 50,000
1,160,000 1,100,000 950,000 950,000 950,000
1,150,000 1,300,000 1,100,000 1,100,000 1,050,000
1,380,000 1,294,000 1,380,000 1,466,000 1,553,000
95,000 95,000 95,000 95,000 95,000
150,000 150,000 450,000 450,000 570,000 ,,,,,
759,000 1,981,000 75,000 75,000 1,075,000
1,175,000 2,100,000 - - -
22,100 25,000 25,000 25,000 25,000
30,000 30,000 20,000 20,000 10,000
9,571,100$ 9,125,000$ 4,145,000$ 4,231,000$ 5,378,000$
$15,959 $9,959 $28,959 $3,959 $31,959
151
Home of Texas A&M University ®
152
WATER
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH
FISCAL YEAR 2016-2017
153
WATER SERVICE
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
FY12 REVISED APPROVED
PROJECT WORK REQUEST APPROVED APPROPRIATIONS FY10 - 11 FY11 - 12
NUMBER NUMBER BUDGET THROUGH FY10 APPROPRIATIONS APPROPRIATIONS
BEGINNING FUND BALANCE:74,998$ 74,998$
ADDITIONAL RESOURCES:
UTILITY REVENUE BONDS/CERTIFICATES OF OBLIGATION 5,450,000$ 6,100,000$
INTEREST ON INVESTMENTS 7,200 10,000
TRANSFERS FROM OPERATIONS 5,250,000 1,950,000
OTHER 130,000 48,000
SUBTOTAL ADDITIONAL RESOURCES 10,837,200$ 8,108,000$
TOTAL RESOURCES AVAILABLE 10,912,198$ 8,182,998$
PRODUCTION PROJECTS
SOURCE AND SUPPLY PLANT - WSWOC
LAND ACQUISITION - WELLS WT0206 WF0377324 5,862,507 6,667,217 - -
WELL #9 TBD 3,846,000 - - -
WELL #9 COLLECTION LINE WF1249597 1,875,000 25,000 - -
WELL FIELD COLLECTION SYSTEM LOOP TBD 900,000 - - -
WATER PUMPING AND TREATMENT PLANT - WPWOC -
SANDY POINT CHEMICAL SYS REPLACEMENT - WF1440357 1,733,400 - - 1,733,400
HIGH SERVICE WATER PUMP IMPROVEMENTS - WF1223117 3,553,000 500,000 2,000,000 1,053,000
2010 WELL REHABILITATION - WF1241047 238,215 400,000 - -
COOLING TOWER EXPANSION - WF1440344 3,182,000 - - 3,182,000
COOLING TOWER MEDIA REPLACEMENT - WF1343612 300,000 - 300,000 -
WELLS 1,2,3, & 5 CONTROLS UPGRADE WF1337893 80,000 - 80,000 -
3 MG GSR REHAB WF1330166 408,745 - 400,000 8,745
5 MG GSR REHAB WF1440668 560,000 - - 80,000
WATER WELL SOFT STARTERS TBD 272,000 - - -
WATER GENERAL PLANT - WGWOC -
W UTILITY SERVICE CENTER RENOVATIONS - WF1441516 348,000 - 37,500 -
BUDGET APPROPRIATIONS
SCADA MAN MACHINE INTERFACE WF1442533 205,000 - 205,000 -
WELL #7 FIBER WF1440359 50,000 - - 50,000
WATER REDUNDANT COMMUNICATIONS WF1440364 500,000 - - 500,000
CLOSED PROJECTS
SUBTOTAL
DISTRIBUTION PROJECTS
TRANSMISSION AND DISTRIBUTION PLANT - WTWOC
OVERSIZED PARTICIPATION - WF1366201 ANNUAL - 70,270 100,000
CASTLEGATE II, SECTION 200 -WF1366201/001 29,730 - 29,730 -
WATER RECLAMATION PHASE I WT0110 WF0995711 3,362,000 3,606,730 - -
WELLBORN WIDENING -WF0613546 4,540,115 4,250,000 600,194 -
BARRON ROAD WATER SERVICE EXT -WF1325560 1,413,531 1,584,940 - -
RAYMOND STOTZER WEST WATER LINE -WF1111167 890,000 1,000,000 - -
COB RAYMOND STOTZER PH I WATER LINE WF1440674 1,125,200 - - 1,125,200
ST VICTORIA AVENUE EXTENSION -WF1158553 228,375 228,375 - -
ST BARRON ROAD WIDENING PHASE II -WF1332871 50,000 50,000 - -
154
WATER SERVICE
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT
EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED
THROUGH FY09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY 16-17
6,812,804$ 2,658,750$ 74,998$ 29,762$ 20,835$ 40,785$ 24,550$ 34,950$
-$ -$ 6,100,000$ 7,275,000$ 900,000$ 5,750,000$ 3,900,000$ 2,475,000$
12,413 10,000 10,000 10,000 5,000 10,000 10,000 10,000
4,000,000 5,750,000 1,950,000 775,000 1,200,000 1,550,000 1,375,000 1,525,000
(92,484) - 48,000 1,039,369 - - - -
3,919,929$ 5,760,000$ 8,108,000$ 9,099,369$ 2,105,000$ 7,310,000$ 5,285,000$ 4,010,000$
10,732,733$ 8,418,750$ 8,182,998$ 9,129,130$ 2,125,835$ 7,350,785$ 5,309,550$ 4,044,950$
4,835,713 26,794 200,000 800,000 - - - - -
- - - - - - 939,000 2,907,000 -
- 2,612 14,100 - - - 245,688 1,612,600 -
- - - - - - - - 900,000
- - - 418,000 1,315,400 - - - -
- 98,355 290,000 3,116,645 48,000 - - - -
- 100,715 137,500 - - - - - -
- - - 625,000 2,557,000 - - - -
- - 300,000 - - - - - -
- - 80,000 - - - - - -
- - 37,450 371,295 - - - - -
- - - 45,000 515,000 - - - -
- - - - - 272,000 - - -
- - - 37,500 50,000 260,500 - - -
PROJECT EXPENDITURES
- - 150,000 25,000 30,000 - - - -
- - - 50,000 - - - - -
- - - 240,000 260,000 - - - -
966,632 6,546,037 261,304
5,802,345$ 6,774,513$ 1,470,354$ 5,728,440$ 4,775,400$ 532,500$ 1,184,688$ 4,519,600$ 900,000$
- - 70,270 100,000 100,000 100,000 100,000 100,000 100,000
- 29,730 - - - - - -
293,942 232,460 2,835,598 - - - - - -
3,320,194 102,921 560,000 557,000 - - - - -
1,201,863 - 211,668 - - - - - -
9,557 15,348 16,500 108,500 740,095 - - - -
- - - 137,000 988,200 - - - -
6,270 2,130 219,975 - - - - - -
- - 50,000 - - - - - -
155
WATER SERVICE
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
FY12 REVISED APPROVED
PROJECT WORK REQUEST APPROVED APPROPRIATIONS FY10 - 11 FY11 - 12
NUMBER NUMBER BUDGET THROUGH FY10 APPROPRIATIONS APPROPRIATIONS
BUDGET APPROPRIATIONS
SH 40 WATER LINE - GRAHAM TO BARRON -TBD 2,535,000 25,000 - -
SH 40 WATER LINE - Sonoma Subdivision to Victoria -TBD 643,000 - - -
PATRICIA STREET WATER LINE -WF1246445 115,000 150,000 - -
FM2818/JONES BUTLER WATER LINE CONFLICT -WF1272122 225,000 225,000 - -
VILLA MARIA/FM 2818 WATER LINE CONFLUCT -WF1344704 251,429 251,429 - -
AREA 2 WATER LINE EXTENSION TBD 1,112,568 - - -
WW CCWWTP LAB & SCADA BUILDING - WATER LINE WF1352985 127,000 106,923 20,077 -
DONATED WATER NA - -
CLOSED PROJECTS -
SUBTOTAL
REHABILITATION PROJECTS:
ST TAUBER & STASNEY -WF0625888 296,403 415,044 - -
W SOUTH KNOLL/THE GLADE -WF1044480 2,265,192 2,246,738 - 18,454
W SOUTHWOOD 5-7 -WF1105425 1,966,311 2,197,663 - -
W EASTGATE REHAB -TBD 2,642,029 - - -
W COLLEGE HEIGHTS REHAB -TBD 2,423,844 - - -
W McCULLOCH UTILITY REHAB -TBD 2,789,947 - - -
ST COONER UTILITY REHAB -WF1440709 446,000 - - 65,000
PLANTATION OAKS WATER LINE -WF1433732 240,318 - - 240,318
CLOSED PROJECTS
SUBTOTAL
CAPITAL PROJECTS CONTINGENCY -TBD 129,923 150,000
METER REPLACEMENT PROGRAM -WF1128579 150,000 140,000 10,000 150,000
CAPITAL PROJECTS SUBTOTAL 53,781,859 3,882,694$ 8,456,117$
GENERAL AND ADMINISTRATIVE 70,269 69,294
DEBT ISSUANCE COST 15,000 50,000
TOTAL EXPENDITURES 3,967,963$ 8,575,411$
MEASUREMENT FOCUS ADJUSTMENT
ENDING FUND BALANCE:6,944,235$ (392,413)$
ST Project funded through combination of sources. Project sheet reflected in Streets section of CIP document.
W Project funded through combination of sources. Project sheet reflected in Water section of CIP document.
WW Project funded through combination of sources. Project sheet reflected in Wastewater section of CIP document.
156
WATER SERVICE
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT
EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED
THROUGH FY09 FY 09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY 16-17
PROJECT EXPENDITURES
- - - - 148,500 470,700 1,915,800 - -
- - - - 100,000 100,000 443,000 - -
- 43 114,957 - - - - - -
- - 225,000 - - - - - -
- - 251,429 - - - - - -
- - - - - 221,850 890,718 - -
- - 32,000 95,000 - - - - -
- - - - - - - - -
188,310 361,246 40,334
5,020,136$ 714,148$ 4,657,461$ 997,500$ 2,076,795$ 892,550$ 3,349,518$ 100,000$ 100,000$
21,403 - 275,000 - - - - - -
100,525 79,167 21,250 634,150 1,430,100 - - - -
124,088 74,488 1,689,201 78,534 - - - - -
- - - - - 275,000 2,367,029 - -
- - - - - - - 250,000 2,173,844
- - - - - - - - 449,799
- - - 55,000 391,000 - - - -
- - - 240,318 - - - - -
179,047
246,016$ 332,702$ 1,985,451$ 1,008,002$ 1,821,100$ 275,000$ 2,367,029$ 250,000$ 2,623,643$
- - - 150,000 150,000 150,000 150,000 150,000 150,000
- 214,313 150,000 150,000 150,000 150,000 150,000 150,000 150,000
11,068,497$ 8,035,677$ 8,263,266$ 8,033,942$ 8,973,295$ 2,000,050$ 7,201,235$ 5,169,600$ 3,923,643$
83,757 80,487 69,294 75,000 75,000 75,000 75,000 75,000
2,280 - 50,000 60,000 10,000 50,000 30,000 15,000
8,121,714$ 8,343,753$ 8,153,236$ 9,108,295$ 2,085,050$ 7,326,235$ 5,274,600$ 4,013,643$
47,731$
2,658,750$ 74,998$ 29,762$ 20,835$ 40,785$ 24,550$ 34,950$ 31,307$
157
PRODUCTION PROJECTS
158
PROJECT:Land Acquisition - Wells PROJECT #: WF0377324
WT0206
FUND(S):Water Capital Projects PROJECT
BUDGET: $5,862,507
PROJECT FUNDING
MANAGER: Dave Coleman SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 4,835,848 - 26,659 - 4,862,507
2010-11 200,000 200,000
2011-12 800,000 800,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 5,835,848$ -$ 26,659$ -$ 5,862,507$
Personnel (Salaries/Benefits)
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
Land purchased for Well Site #8, #9, and #10. Also, SB332 may require the City to buy water rights.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
159
PROJECT:Well #9 PROJECT #: TBD
WSWOC
FUND(S):Water Capital Projects PROJECT
BUDGET: $3,846,000
PROJECT FUNDING
MANAGER: Brian J. Smith SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Brian J. Smith
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 -
2014-15 427,000 512,000 939,000
2015-16 32,600 2,874,400 2,907,000
2016-17 -
PROJECT TOTAL -$ 459,600$ 3,386,400$ -$ 3,846,000$
Personnel (Salaries/Benefits)
PROJECT SCOPE
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
This project will construct Water Well Simsboro 9 with its associated electrical, SCADA, security, and drainage infrastructure. Land
acquisition costs are included in a separate project.
Design, bidding, and construction of a 2,800 GPM water well located in North Brazos County. This well will have a collection line that
connects to the existing Well 8 line.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Estimated Annual
Recurring Cost
7,000
First Fiscal Year
One Time Costs
Supplies
Maintenance 5,000
Professional Services
Purchased Services
Capital Outlay
TOTAL
500
92,800 -$
300
80,000
160
PROJECT:Well #9 Collection Line PROJECT #: WF1249597
WSWOC
FUND(S):Water Capital Projects PROJECT
BUDGET: $1,875,000
PROJECT FUNDING
MANAGER: Brian J. Smith SOURCES:
Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Brian J. Smith
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 2,612 - - - 2,612
2010-11 14,100 14,100
2011-12 -
2012-13 -
2013-14 -
2014-15 245,688 245,688
2015-16 100,000 1,512,600 1,612,600
2016-17 -
PROJECT TOTAL 16,712$ 345,688$ 1,512,600$ -$ 1,875,000$
Personnel (Salaries/Benefits)
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECT SCOPE
Project provides for land purchase, engineering design, and construction of collection line progressing from Water Well #9 to a connection
point in the existing wellfield collection line. The additional capacity is required to meet TCEQ regulations for pumping capacity to match
projected population.
This project will provide a 30" collection line from Well 9 to a connection point at Well 8. This line will be adequate to convey the flow from
future wells drilled on City property beyond Well 9.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
1,600 -$
-
-
1,600
-
-
161
PROJECT:PROJECT #: TBD
WSWOC
FUND(S): Water Capital Projects PROJECT
BUDGET:$900,000
PROJECT FUNDING
MANAGER: Brian Smith SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 86 900 160 375 652 725 900 000
Well Field Collection System Loop
This project will consist of the design, construction, and easement acquisition of a well field collection line along West OSR. This proposed
line connection will incorporate a redundant well field collection system and will also allow flow to be diverted during maintenance/outages in
the well field. This specfic segement of line will connect the existing Well #6 Collection Line to the existing Well #7 Collection Line via a
proposed 30" DIP line along West OSR.
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Design, bidding, and construction of the Well Field Collection System Loop will include:
Approximately 2,300 LF of 30" Ductile Iron Water Transmission Line
Associated appurtenances
2016-17 86,900 160,375 652,725 900,000
PROJECT TOTAL 86,900$ 160,375$ 652,725$ -$ 900,000$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
170
-
-
-
170
162
PROJECT:Sandy Point Pump Station Chemical PROJECT #: WF1440357
Feed & Storage System WPWOC
PROJECT
FUND(S):Water Capital Projects BUDGET:
$1,733,400
PROJECT FUNDING
MANAGER:Brian J. Smith SOURCES:
Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 318,000 100,000 418,000
2012-13 55,400 1,260,000 1,315,400
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 373,400$ 1,360,000$ -$ 1,733,400$
Scope of the project is to provide engineering and construction to add a chemical scrubber to neutralize chlorine gas leaks, increase the
treatment capacity of the existing chlorination system, and add another chlorine injection point on the new parallel well field collection line.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECT SCOPE
The Chemical Feed and Storage facilities at Sandy Point Pump Station require upgrading to accommodate current expansion of its Water
Production infrastructure and to be in compliance with current fire codes. Engineering investigations supporting the expansion effort have
identified the need to replace the existing Chlorine Disinfection System to improve personnel safety, operating reliability, and cost efficiency.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
35,000
-
6,200
-
41,200
163
PROJECT:High Service Pump Improvements PROJECT #: WF1223117
WPWOC
FUND(S):Water Capital Projects PROJECT
BUDGET: $3,553,000
PROJECT FUNDING
MANAGER: Philip Bargas SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Brian J. Smith
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 98,355 - - 98,355
2010-11 290,000 290,000
2011-12 186,645 2,930,000 3,116,645
2012-13 5,000 43,000 48,000
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 580,000$ 2,973,000$ -$ 3,553,000$
Personnel (Salaries/Benefits)
This project will add two, 6,775 gpm vertical turbine pumps to DRPS with associated discharge piping and appurtenances. This project will
also add the necessary electrical equipment supporting these pumps and a tie in to the City's SCADA system.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
$2,800
First Fiscal Year
One Time Costs
PROJECT SCOPE
HDR Consulting Engineers has performed an analysis of our water system capacities in relation to TCEQ requirements. This analysis
revealed that we need to increase our high service pump capacity at Dowling Road Pump Station (DRPS).
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
$0
$67,000-$
$500
$6,000
$6,000
$51,700
164
PROJECT:2010 Well Rehab PROJECT #: WF1241047
WPWOC
FUND(S):Water Capital Projects PROJECT
BUDGET: $238,215
PROJECT FUNDING
MANAGER: Brian J. Smith SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - 100,715 - 100,715
2010-11 137,500 137,500
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 238,215$ -$ 238,215$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project provides for the removal, inspection, and rehabilitation of the pumps and motors for three Simsboro water wells. The pumps in
these wells have reached their expected service life and need to be inspected and rehabilitated before an emergency maintenance event
occurs. The production rate for the pump in Well #5 is below the permitted level and needs to be upgraded. This project was previously
known as "Wells #1 & #3 Pump/Mtr Rehab".
This scope includes: The removal, inspection, refurbishment, and reinstallation of Well pump assemblies #1, #3, #6. The replacement of
the pump in Well #5. The inspection of each of the four affected Wells for structural integrity and production zone problems. The
replacement of the concrete Well pad at Well #3.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
g
-
-
-
-
-
-
-
165
PROJECT:Cooling Tower Expansion PROJECT #: WF1440344
WPWOC
FUND(S):Water Capital Projects PROJECT
BUDGET: $3,182,000
PROJECT FUNDING
MANAGER: Brian J. Smith SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 525,000 100,000 625,000
2012-13 121,000 2,436,000 2,557,000
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 646,000$ 2,536,000$ -$ 3,182,000$
Personnel (Salaries/Benefits)
Project scope is to provide engineering services to create bid documents and inspection services on construction. Construction services to
provide one additional 12.5 MGD cross-flow cooling tower, the piping and connection to existing infrastructure, installation of new electrical
switch gear, and motor control centers along with SCADA instrumentation for the automatic operation of this equipment.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
3,000
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project provides for the engineering design and construction of an additional water cooling tower and all of the associated
appurtenances to connect this new equipment into the existing system. This additional tower is needed to meet the increased production
capacity of the water system in order to satisfy water supply demands.
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
6,000
3,000
-
55,000
-
67,000
166
PROJECT:Cooling Tower Media Replacement PROJECT #: WF1343612
WPWOC
FUND(S): Water Capital Projects PROJECT
BUDGET: $300,000
PROJECT FUNDING
MANAGER: Brian J. Smith SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services / Stephen Maldonado
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 300,000 300,000
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 300,000$ -$ 300,000$
Personnel (Salaries/Benefits)
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project will replace the media material in the existing drinking water cooling towers. The existing media has reached the end of its
service life and must be replaced. No engineering is required for this replace in-kind project.
Project scope is to install new stainless steel materials supports and replace the film fill media with new media. Replace the protective
screens on the sides of the towers and mechanically connect and align some of the fan motors to the gearboxes.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
-
167
PROJECT:Wells 1, 2, 3, and 5 Motor Control Upgrade PROJECT #: WF1337893
WGWOC
FUND(S): Water Capital Projects PROJECT
BUDGET: $80,000
PROJECT FUNDING
MANAGER: Fred Surovik SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 80,000 80,000
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 80,000$ -$ 80,000$
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
PROJECT SCOPE
The original design of motor controls for these wells included a Motor Operated Valve on the well discharge. These valves were integrated
into the motor controls and no longer have parts available. Additionally, the control schematics are no longer accurate, making diagnosis and
repair very difficult, especially when the well capacity is needed immediately. Staff has obtained pricing for a wholesale change out of the
control section of these Motor Control Centers with current production model controls and appropriate documentation under the General
Services Administration Schedule 70, which is pre competed. Although the existing motor starters will need to be changed out at some point
in the future, this addresses the most pressing of our needs and delays the need for the replacement of the entire Motor Control Center for at
least a decade at a small percentage of the cost.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
-
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
168
PROJECT:3 MG Ground Storage Reservoir Rehabilitation PROJECT #: WF1330166
WSWOC
FUND(S):Water Capital Projects PROJECT
BUDGET: $408,745
PROJECT FUNDING
MANAGER: Brian J. Smith SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 37,450 37,450
2011-12 15,000 356,295 371,295
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 52,450$ 356,295$ -$ 408,745$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated AnnualFirst Fiscal Year
PROJECT SCOPE
This project is needed to replace the coating systems and replace the overflow structure for the three million gallon ground storage
reservoir. We have reports from two separate inspection firms which indicate the interior coatings have started to fail and that the overflow
structure which must be upsized. The project budget includes funding for the engineering and construction costs associated with the
needed rehabilitation.
The engineering scope of work includes: development of the scope of work and technical specifications, assistance with bidding, inspection
services, and the review and approval of pay applications. The construction scope of work includes: replacement of the existing overflow
structure to a new properly sized overflow, sandblast removal of the old interior, and exterior tank coatings, and installation of the new
interior and exterior coatings on the tank.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
-
-
169
PROJECT:5 MG Ground Storage Reservoir Rehabilitation PROJECT #: WF1440668
WSWOC
FUND(S):Water Capital Projects PROJECT
BUDGET: $560,000
PROJECT FUNDING
MANAGER: Brian J. Smith SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 45,000 45,000
2012-13 25,000 490,000 515,000
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 70,000$ 490,000$ -$ 560,000$
The engineering scope of work includes: development of the scope of work and technical specifications, assistance with project bidding,
inspection services, and the review and approval of pay applications. The construction scope of work includes: replacement of the existing
overflow structure, removal and replacement of the interior coatings on the tank.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project is needed to replace the interior coating system and replace the now undersized overflow structure for the five million gallon
ground storage reservoir. The most recent facility inspection report indicates the interior coatings have started to fail and must be
replaced, soon. The project budget includes funding for the engineering and construction costs associated with the needed rehabilitation.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
Recurring Cost
-
-
One Time Costs
-
-
-
170
PROJECT:Water Well Soft Starters PROJECT #: TBD
FUND(S): Water Capital Projects PROJECT
BUDGET:272,000$
PROJECT Michael Kellogg FUNDING
MANAGER: SOURCES: Long Term Debt
PROJECT Water Services
CLIENT:
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 52,000 220,000 272,000
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 52,000$ 220,000$ -$ 272,000$
Personnel (Salaries/Benefits)
This project will replace the exisiting motor starters and motor protection relays on Water Wells 1, 2, 3, and 5. The existing components are
old technology and have exceeded their service life. This is the second phase of upgrades that will extend the service life of this critical
infrastructure at least 10 years at a fraction of the cost of outright replacement.
PROJECT SCOPE
This project will complete the motor control upgrades for Water Wells 1, 2, 3, and 5.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
-$Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
- -$
-$
-
-
-
-
-
-$
-$
-$
-$
171
PROJECT:Utility Service Center Renovations
FUND(S):Water Capital Projects PROJECT NUMBERS & BUDGET:
Wastewater Capital Projects Water:WF1441516 $348,000
Wastewater: WF1441517 $348,000
Total Project Budget:$696,000
PROJECT
MANAGER:TBD
FUNDING
PROJECT SOURCES: Long Term Debt/Utility Revenue
CLIENT:Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
PROJECT DESCRIPTION
This project renovates the Utility Service Center. Improvements include additional office space, HVAC refurbishments, additional Dispatching facilities
made necessary by the Homelands Security Act and E.R.C.O.T. The existing facilities are 20 years old and refurbishment is needed to extend the
service life.
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
2010-11 - - - - -
2011-12 - - 75,000 - 75,000
2012-13 - 100,000 - - 100,000
2013-14 - - 521,000 - 521,000
2014-15 - - - - -
2015-16 - - - - -
2016-17 - - - - -
696,000$ PROJECT TOTAL -$ 100,000$ 596,000$ -$
172
Water Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 37,500 37,500
2012-13 50,000 50,000
2013-14 260,500 260,500
2014-15 -
2015-16 -
2016-17 -
Water Total -$ 50,000$ 298,000$ -$ 348,000$
Wastewater Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 37,500 37,500
2012-13 50,000 50,000
2013-14 260,500 260,500
2014-15 -
2015-16 -
2016-17 -
Wastewater Total -$ 50,000$ 298,000$ -$ 348,000$
Personnel (Salaries/Benefits)
Supplies
Maintenance
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Estimated Annual
One Time Costs Recurring Cost
Utility Service Center RenovationsPROJECT:
PROJECT CALENDAR OF EXPENDITURES BY FUND
100,000$ 596,000$ -$ 696,000$ PROJECT TOTAL -$
-
-
-
Professional Services
Purchased Services
Capital Outlay
TOTAL -$ -$
-
-
-
173
PROJECT:SCADA Man Machine Interface PROJECT #: WF1442533
WGWOC
FUND(S):Water Capital Projects PROJECT
BUDGET: $205,000
PROJECT FUNDING
MANAGER:Michael Kellogg SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 150,000 150,000
2011-12 25,000 25,000
2012-13 30,000 30,000
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 25,000$ 180,000$ -$ 205,000$
PROJECT DESCRIPTION
PROJECT SCOPE
This project will evaluate, procure and implement software packages available to improve the SCADA Man Machine Interface or graphical
software. New servers are included in the project to increase flexibility and reduce vulnerabilities and downtime. The software must be able to
utilize technologies such as Terminal Services, OPC, and be compatible with the existing control hardware. In addition, it will include software
and consulting to implement performance indicators, dashboards, and business data analysis to become best in class. The goal is the
Integrated Architecture system leverages one common multidisciplined control engine, one development environment, one networking
protocol, and one service-oriented architecture (SOA). The architecture provides fully integrated, scalable solutions for the full range of
control and information disciplines.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
-
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
174
PROJECT:Well 7 fiber PROJECT #: WF1440359
WGWOC
FUND(S): Water Capital Projects PROJECT
BUDGET:$50,000
PROJECT FUNDING
MANAGER: Michael Kellogg SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 50,000 50,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 50,000$ -$ 50,000$
Install fiber from Sandy Point pump station to Water Well #7 to create wireless access point for Water Wells #5,#6,#8, and future wells.
Based on projected plans of well sites through Water Well #10.
PROJECT SCOPE
Install fiber in existing conduit and pull boxes. Terminate all fibers at both ends and light to create connectivity.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
-
175
PROJECT:Water Redundant Communications PROJECT #: WF1440364
WGWOC
FUND(S):Water Capital Projects PROJECT
BUDGET: $500,000
PROJECT FUNDING
MANAGER: Michael Kellogg SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 240,000 240,000
2012-13 260,000 260,000
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 500,000$ -$ 500,000$
This project will provide for data communication improvements. This will allow for built-in redundancy, wireless communications, mobile work
force, and any unforeseen communication plan not related to construction projects. The main focus is to construct fiber loops which provide
multiple paths to all facilities.
PROJECT SCOPE
Currently defined areas of data vulnerability are : Single Wireless controller for IP radios that control well field production and security. Single
path or spur of fiber to Dowling Road Pump Station that control Pumps and Chemical feed that provide water to the customers. Single path or
spur of fiber to all Elevated Storage Tanks. Single Spur of Fiber to Sandy Point Pump Station that controls transfer pumps and access point
for wireless communications.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual First Fiscal Year
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
-
-
176
DISTRIBUTION PROJECTS
177
WORK
ORDER #: WF1366201
PROJECT: Oversized Participation Water Lines PROJECT #: WTWOC
FUND: Water Capital Projects PROJECT
BUDGET:Annual
PROJECT
MANAGER: Stephen Maldonado, Jr. FUNDING
SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 70,270 70,270
2011-12 100,000 100,000
2012-13 100,000 100,000
2013-14 100,000 100,000
2014-15 100,000 100,000
2015 16 100 000 100 000
These funds are available for oversize participation with developers in the construction of water lines above the
minimum size needed to serve the development. This allows lines to be built large enough to meet future
development without having to go back and install larger lines. Projects are identified based on development activity.
PROJECT SCOPE
PROJECT DESCRIPTION
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
2015-16 100,000 100,000
2016-17 100,000 100,000
TOTAL -$ -$ 670,270$ -$ 670,270$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Annual Estimated
One Time Costs Recurring Cost
-$ -$
178
PROJECT:Water Reclamation (PH I) PROJECT #: WF0995711
WT0110
FUND(S):Water Capital Projects PROJECT
BUDGET:
$3,362,000
PROJECT FUNDING
MANAGER: Daniel Beamon SOURCES:
Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Jennifer Nations
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 65,227 460,903 272 - 526,402
2010-11 171,238 2,664,360 2,835,598
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 65,227$ 632,141$ 2,664,632$ -$ 3,362,000$
Personnel (Salaries/Benefits)
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project will consist of designing and constructing reclaimed water infrastructure from Carters Creek Wastewater Treatment Plant to
Veterans Park. The overall reclaimed water infrastructure will help to decrease the overall peak water demand on our potable water
distribution system. The land costs are for the acquisition of a public utility easement.
Transfer Pumps will be installed and constructed near the CCWWTP effluent outfall that will treat and pump the reclaimed water through
13,500 lf of pipeline, to a ground storage reservoir at Veteran's Park Booster pumps will be installed to pump water from the ground storage
tank to the existing irrigation system.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
46,000 -$
26,000
20,000
-
-
179
PROJECT:Wellborn Widening PROJECT #: WF0613546
WTWOC
FUND(S):Water Capital Projects PROJECT
BUDGET:
$4,540,115
PROJECT FUNDING
MANAGER: Danielle Charbonnet SOURCES:
Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Fred Surovik
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 97,121 224,093 3,101,901 - 3,423,115
2010-11 105,000 450,000 5,000 560,000
2011-12 7,000 550,000 557,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 97,121$ 336,093$ 4,101,901$ 5,000$ 4,540,115$
PROJECT SCOPE
With the TXDOT widening of Wellborn Road, water lines from FM 2818 to SH 40 must be relocated outside of future pavement areas. It is
expected that partial reimbursement will be forthcoming from TxDOT on this utility project for up to 95.6% of eligible project costs. This line
has been completed from Harvey Mitchell Parkway to N Graham Road. The segment from N Graham to Graham Road was delayed by
lengthy easement negotiations.
The first phase is completed. Phase II of the project will install approximately 2600 linear feet (LF) of 24-inch waterline between North
Graham Road and Graham Road, and approximately 290 LF of 12-inch waterline under Wellborn Road (FM 2154) at Graham Road to
connect to the existing line.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
-
180
PROJECT:Barron Road Water Service Extension PROJECT #: WF0379197 / WF1325560
WTWOC
FUND(S):Water Capital Projects PROJECT
BUDGET: $1,413,531
PROJECT FUNDING
MANAGER: Philip Bargas SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Stephen Maldonado, Jr.
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 3,287 246,290 952,287 - 1,201,863
2010-11 1,300 49,612 160,756 211,668
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 4,587$ 295,902$ 1,113,043$ -$ 1,413,531$
This project includes construction of approximately 2,200 LF of 12" PVC water line and associated appurtenances from Southern Trace
Subdivision to Barron Road.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
RiCt
First Fiscal Year
OTi Ct
PROJECT SCOPE
This project is to install the water distribution lines in the Barron Road and Wellborn Road area. The 18" water line along Barron Road from
Victoria Road to Wellborn Road has been designed and constructed within previous phases of this project. The remaining portion of the
project to be designed and constructed consists of a 12" water line along Wellborn Road up to Southern Trace Subdivision. This project
provides water service to residents within the City of College Station's Water CCN that are currently served by the Wellborn Special Utility
District.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
Recurring Cost
-
-
One Time Costs
-
-
-
181
PROJECT:Raymond Stotzer West Water Line PROJECT #: WF1111167
WTWOC
PROJECT
FUND(S):Water Capital Projects BUDGET: $890,000
PROJECT FUNDING
MANAGER:Danielle Charbonnet SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services / Fred Surovik
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 5,580 19,325 - - 24,905
2010-11 1,000 15,000 500 16,500
2011-12 15,000 90,000 3,500 108,500
2012-13 720,000 20,095 740,095
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL 21,580$ 124,325$ 720,000$ 24,095$ 890,000$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
PROJECT SCOPE
This project will consist of the design and construction of water infrastructure to an area that was annexed by the City of College Station in
1995 that is near the intersection of Raymond Stotzer West and FM 2818. The project will consist of water distribution lines of various
sizes: a 16" water line along Turkey Creek Road from Melrose Pkwy to FM 60, and an 8" line east of Turkey Creek Road to connect with the
8" line in the cemetery. Metes & bounds descriptions for an easement between SH 47 and Turkey Creek Road is included, but the detailed
design and construction of the water line in this segment will be development driven.
This project will install water lines in the portion of College Station included in the Bio Medical Corridor. This estimate was prepared based
on the preliminary master plan and is based on installing approximately 4,500 linear feet of various sized water lines.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
-
182
PROJECT:COB Raymond Stotzer Ph. I Waterline PROJECT #: WF1440674
WTWOC
PROJECT
FUND(S):Water Capital Projects BUDGET: $1,125,200
PROJECT FUNDING
MANAGER:Fred Surovik SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - -
2010-11 -
2011-12 130,000 7,000 137,000
2012-13 965,200 23,000 988,200
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 130,000$ 965,200$ 30,000$ 1,125,200$
PROJECT SCOPE
This project will consist of the design and construction of water infrastructure to an area that was annexed by the City of College Station in
1995 that is near the intersection of Raymond Stotzer West and FM2818. The project will consist of water distribution lines. The project will
be designed and constructed by the City of Bryan with HSC Pkwy, but paid for by COCS Utility Revenue.
This project will construct a 12" waterline along Health Science Center Pkwy from FM 47 to Turkey Creek Road, and a 16" waterline along
F&B from Turkey Creek Road to FM 2818.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Recurring CostOne Time Costs
-
-
-
183
PROJECT:SHWY40 Water Line Extension PROJECT #: TBD
(Barron Rd to Graham Rd)WTWOC
PROJECT
FUND(S):Water Capital Projects BUDGET: $2,535,000
PROJECT FUNDING
MANAGER:Stephen Maldonado, Jr.SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 148,500 148,500
2013-14 470,700 470,700
2014-15 1,915,800 1,915,800
2015-16 -
2016-17 -
PROJECT TOTAL 148,500$ 470,700$ 1,915,800$ -$ 2,535,000$
Personnel (Salaries/Benefits)
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project consists of an extension of a water distribution line that will complete a section of an existing 24" water distribution line. This
connection will assist in proper operation of the distribution system by increasing connectivity between Dowling Road Pump Station and the
Greens Prairie Elevated Storage Tank.
This portion will connect the existing 24" water distribution line at Barron Rd to a future 24" water distribution line near the intersection of
Wellborn Road and Graham Road. Design, bidding, and construction of the SHWY40 Water Line Extension project will include
approximately 3,800 LF of 24-inch water distribution line.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
184
PROJECT:SHWY40 Water Line Extension PROJECT #: TBD
(Sonoma Subdivision to Victoria Avenue)WTWOC
PROJECT
FUND(S):Water Capital Projects BUDGET: $643,000
PROJECT FUNDING
MANAGER: Stephen Maldonado, Jr. SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 100,000 100,000
2013-14 100,000 100,000
2014-15 443,000 443,000
2015-16 -
2016-17 -
PROJECT TOTAL 100,000$ 100,000$ 443,000$ -$ 643,000$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project consists of an extension of water distribution line that will complete part of an existing 24" water distribution line. This connection
will assist in proper operation of the distribution system by increasing connectivity between Dowling Road Pump Station and the Greens
Prairie Elevated Storage Tank.
This portion will connect the existing 24" water distribution line at the Sonoma Subdivision to the 24" water distribution line at Victoria Avenue.
A portion of this line is currently being constructed as part of the Sonoma PH III Waterline Oversized Participation project. Design, bidding,
and construction of the SH40 Water Line Extension project will include approximately 3,100 LF of 24-inch water distribution line.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
g
-
-
-
-
-
-
-
185
PROJECT:Patricia Street Waterline PROJECT #: WF1246445
WTWOC
PROJECT
FUND(S):Water Capital Projects BUDGET: $115,000
PROJECT FUNDING
MANAGER:Danielle Charbonnet SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services / Stephen Maldonado
Project Total
FISCAL YEAR Land Engineering Construction Misc OH Project Total
Prior Years - - 43 - 43
2010-11 106,957 5,000 3,000 114,957
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 107,000$ 5,000$ 3,000$ 115,000$
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual First Fiscal Year
PROJECT SCOPE
This Northgate location is served by an old 2” water line that is not adequate to provide the fire flow required by law for high-occupancy
facilities in this area to operate. On February 11, 2010, Council approved a Joint Project Contract, which will replace a line to enable the
development of the Aquarium Bar. The City will replace the line, and the developer will pay an engineering firm to design the project,
create bid documents, and provide the standard post-award design services. This will compensate the City for the reduced efficiency of
replacing this line ahead of all other rehabilitation work that will need to be done in this area in the future.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
186
PROJECT:FM 2818 / Jones-Butler Waterline Conflict PROJECT #: WF1272122
WSWOC
FUND(S):Water Capital Projects PROJECT
BUDGET: $225,000
PROJECT FUNDING
MANAGER: Daniel Beamon SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Stephen Maldonado, Jr.
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 30,861 194,139 225,000
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 30,861$ 194,139$ -$ 225,000$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECT SCOPE
TXDOT is currently building a grade separation for the intersection of FM 2818 (Harvey Mitchell Pkwy) and FM 2154 (Wellborn Road),
which includes a frontage road and drainage ditch on the south side of FM 2818, west of FM 2154. An existing 30" City of College Station
water transmission line located at the intersection of FM 2818 and Jones-Butler Road, and within state ROW has been uncovered during
the excavation of the aforementioned drainage ditch.
This project is for the design and construction for relocating 550 lf of 30" waterline to eliminate the conflict for the TXDOT construction.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
-
187
PROJECT:PROJECT #: WF1272122
WPWOC
FUND(S):PROJECT
BUDGET: $251,429
PROJECT Philip Bargas FUNDING
MANAGER: SOURCES: Long Term Debt/Utility Revenue
PROJECT Water Services Department
CLIENT:
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 49,186 202,243 251,429
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Villa Maria/FM 2818 Water
Transmission Line Conflict
The existing water transmission line from Sandy Point Pump Station to Dowling Road Pump Station is in conflict with TxDoTs proposed grade
separation of Villa Maria and 2818. Water Services has developed an agreement with TxDoT whereby Water services will cut and cap the
existing line and remove the portion in conflict but not actually under the roadway and TxDoT will have their contractor remove the section
under the roadway and place an encasement pipe in an alternate location during construction of the grade separation. Upon completion of the
grade separation, Water Services will initiate a separate project to restore the 30" pipeline in a location not conflicting with the grade
separation. The parallel transmission line has adequate capacity for the construction period, but we will not have redundant pipelines during
the construction period.
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
This project will remove approximately 1,200 ft of 30" water line, wich will be replaced by another project in an alternate location after
completion of the grade separation.
2016-17 -
PROJECT TOTAL -$ 49,186$ 202,243$ -$ 251,429$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
-
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
188
PROJECT:Area 2 Water Line Extension PROJECT #: TBD
WTWOC
FUND(S): Water Capital Projects PROJECT
BUDGET:
PROJECT FUNDING
MANAGER: Stephen Maldonado, Jr SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 221,850 221,850
2014-15 890,718 890,718
2015-16 -
2016-17 -
PROJECT TOTAL -$221 850$890 718$-$1 112 568$
In 2010, the City of College Station and the Wellborn SUD finalized a water CCN settlement agreement in which the City of College Station
acquired the water CCN area near Arrington Road and Greens Prairie Road. As part of the settlement, the City of College Station agreed to
disconnect the transferred water lines, in the respective water CCN area, from Wellborn SUD’s system and reconnect them onto the City of
College Station’s water distribution system within 5 years of the agreement being executed. Because no water distribution lines exist in this
area, this project consists of designing/constructing water distribution lines along Greens Prairie Road and Arrington Road.
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Design, bidding, and construction of Area 2 Water Line Rehabilitation Project will include:
Approximately 5,200 LF of 12" Water Line
Approximately 2,400 LF of 8" Water Line
Approximately 1,800 LF of 6" Water Line
$1,112,568
PROJECT TOTAL -$ 221,850$ 890,718$ -$ 1,112,568$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
One Time Costs
-
-
-
-
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
189
REHABILITATION PROJECTS
190
Home of Texas A&M University ®
191
PROJECT:South Knoll / The Glade
FUND(S):Water Capital Projects PROJECT NUMBERS & BUDGET:
Wastewater Capital Projects Water:WF1044480 $2,265,192
Wastewater: WF1044485 $3,005,683
Total Project Budget:$5,270,875
PROJECT
MANAGER:Edward McDonald
FUNDING
PROJECT SOURCES: Long Term Debt/Utility Revenue
CLIENT:Water Services / Ed Savage
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 299,482 - - 299,482
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
This project includes the rehabilitation of water and wastewater lines in the Southwood area, in the vicinity of Haines Street, Southwest Parkway,
Glade Street, Langford Street. The sanitary sewer lines are in need of replacement due to an increase in service disruptions caused by deteriorating
lines, shallow lines, and poor access. The water distribution lines are in need of replacement due to an increase in service disruptions caused by
deteriorating lines and inadequate fire protection due to the existence of smaller lines within the respective area. Design, bidding, and construction of
the South Knoll/The Glade Utility Rehabilitation project will include approximately 9,800 LF of water distribution line and approximately 11,300 LF of
sanitary sewer collection line.
PROJECT SCOPE
Design, bidding, and construction of the South Knoll/The Glade Utility Rehabilitation Project will include:
Approximately 9,800 LF of Water Distribution Line
Approximately 11,300 LF of Sanitary Sewer Collection Line
,,
2010-11 - 131,250 - - 131,250
2011-12 - 41,850 1,439,488 - 1,481,338
2012-13 - - 3,358,804 - 3,358,804
2013-14 - - - - -
2014-15 - - - - -
2015-16 - - - - -
2016-17 - - - - -
5,270,874$ PROJECT TOTAL -$ 472,582$ 4,798,292$ -$
192
Water Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 179,692 - - 179,692
2010-11 21,250 21,250
2011-12 21,250 612,900 634,150
2012-13 1,430,100 1,430,100
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Water Total -$ 222,192$ 2,043,000$ -$ 2,265,192$
Wastewater Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 119,791 - - 119,791
2010-11 110,000 110,000
2011-12 20,600 826,588 847,188
2012-13 1,928,704 1,928,704
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Wastewater Total -$ 250,391$ 2,755,292$ -$ 3,005,683$
Personnel (Salaries/Benefits)
Supplies
Maintenance
-
-
-
South Knoll / The GladePROJECT:
PROJECT CALENDAR OF EXPENDITURES BY FUND
472,582$ 4,798,292$ -$ 5,270,874$ PROJECT TOTAL -$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Estimated Annual
One Time Costs Recurring Cost
Professional Services
Purchased Services
Capital Outlay
TOTAL -$ -$
-
-
-
193
PROJECT: Southwood 5 - 7 Rehab
FUND(S): PROJECT NUMBERS & BUDGET:
Water: WF1105425 $1,966,311
Wastewater: WF1105424 $2,983,734
Drainage: SD1103 $56,149
Total Project Budget: $5,006,194
PROJECT
MANAGER: Ed McDonald
FUNDING
PROJECT SOURCES:
CLIENT: Water Services: Ed Savage
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
PROJECT DESCRIPTION
Water Capital Projects
Wastewater Captial Projects
Long Term Debt/Utility Revenue
Design, bidding, and construction of the Southwood 5-7 Utility Rehabilitation project will include approximately 4,000 LF of 4-inch
water distribution line, approximately 2,600 LF of 6-inch water distribution line, approximately 2,000 LF of 8-inch water distribution
line, approximately 6,800 LF of 12-inch water distribution line, approximately 1,200 LF of 8-inch sanitary sewer collection line,
approximately 1,300 LF of 12-inch sanitary sewer collection line, and approximately 3,200 LF of 18-inch sanitary sewer collection
line.
PROJECT SCOPE
This project includes the rehabilitation of water and wastewater lines in the Southwood area, in the vicinity of Southwest Parkway,
FM2818, Glade St., Welsh, and Shadowood. The sanitary sewer lines are in need of replacement due to an increase in service
disruptions caused by deteriorating lines, shallow lines, and poor access. The water distribution lines are in need of replacement due
to an increase in service disruptions caused by deteriorating lines and inadequate fire protection due to the existence of smaller lines
within the respective area.
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 39,708 383,045 66 -
2010-11 - 100,002 4,268,508 -
2011-12 - - 214,865 -
2012-13 - - - -
2013-14 - - - -
2014-15 - - - -
2015-16 - - - -
2016-17 - - - -
-
-
-
4,368,510
214,865
-
PROJECT TOTAL 5,006,194$ 39,708$ 483,047$ 4,483,439$ -$
-
422,819
194
Water Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 347 198,163 66 - 198,576
2010-11 67,132 1,622,069 1,689,201
2011-12 78,534 78,534
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Water Total 347$ 265,295$ 1,700,669$ -$ 1,966,311$
Wastewater Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 39,361 184,882 - - 224,243
2010-11 32,870 2,590,290 2,623,160
2011-12 136,331 136,331
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Wastewater Total 39,361$ 217,752$ 2,726,621$ -$ 2,983,734$
Drainage Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 56,149 56,149
2011-12 -
2012-13 -
Southwood 5 - 7 RehabPROJECT:
PROJECT CALENDAR OF EXPENDITURES BY FUND
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Drainage Total -$ -$ 56,149$ -$ 56,149$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$ -$ -$ -$
483,047$ 4,483,439$ -$ 5,006,194$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Annual Estimated
One Time Costs Recurring Cost
PROJECT TOTAL 39,708$
195
PROJECT:Eastgate Rehab PH IV
FUND(S):Water Capital Projects PROJECT NUMBERS & BUDGET:
Wastewater Capital Projects Water:TBD $2,642,029
Wastewater: TBD $2,805,830
Total Project Budget:$5,447,859
PROJECT
MANAGER:Stephen Maldonado, Jr.
FUNDING
PROJECT SOURCES: Long Term Debt/Utility Revenue
CLIENT:Water Services
Project Total
PROJECT DESCRIPTION
PROJECT SCOPE
This project consists of the replacement of water and sewer lines in the area bounded by Lincoln Avenue to the north, Walton Drive to the east,
Francis Drive to the south, and Texas Avenue to the west. The sewer lines are in need of replacement due to an increase in service disruptions
caused by deteriorating materials, shallow lines, and poor access to mains located near back lot lines(NOTE: This project will move any rear serving
sewer mains to front lot lines). The sewer mains were also identified by Water Services Department personnel during training exercises for smoke
testing that identifies inflow and infiltration. The water distribution lines are in need of replacement due to an increase in service disruptions caused by
deteriorating materials and inadequate fire protection. Within certain areas of Eastgate's respective boundary, the existing water distribution does not
currently meet the Unified Bryan/College Station Design Guidelines for fire protection because of existing smaller line sizes and inefficient fire hydrant
spacing. This project also includes the milling/overlaying of all existing aging streets in the respective project area. The overall Eastgate
Rehabilitation project is separated into Phase IV, Phase V, and Phase VI.
Design, bidding, and construction of Eastgate PHIV Utility Rehabilitation Project will include:
Approximately 2,700 LF of 6‐inch Water Distribution Line
Approximately 3,500 LF of 8‐inch Water Distribution Line
Approximately 3,100 LF of 12‐inch Water Distribution Line
Approximately 8,500 LF of 6‐inch Sanitary Sewer Collection Line
Approximately 2,500 LF of 8‐inch Sanitary Sewer Collection Line
Approximately 75,000 SY of 1.5‐inch Mill/Overlay of the Existing Aging Streets for the Entire Project Area (TO BE FUNDED COMPLETELY BY THE
WATER SERVICES DEPARTMENT)
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
j
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 - - - - -
2011-12 - - - - -
2012-13 - - - - -
2013-14 - 550,000 - - 550,000
2014-15 - 150,000 4,747,859 - 4,897,859
2015-16 - - - - -
2016-17 - - - - -
PROJECT TOTAL -$ 700,000$ 4,747,859$ -$ 5,447,859$
196
Water Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 275,000 275,000
2014-15 75,000 2,292,029 2,367,029
2015-16 -
2016-17 -
Water Total -$ 350,000$ 2,292,029$ -$ 2,642,029$
Wastewater Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 275,000 275,000
2014-15 75,000 2,455,830 2,530,830
2015-16 -
2016-17 -
Wastewater Total -$ 350,000$ 2,455,830$ -$ 2,805,830$
Personnel (Salaries/Benefits)
Eastgate Rehab PH IVPROJECT:
PROJECT CALENDAR OF EXPENDITURES BY FUND
700,000$ 4,747,859$ -$ 5,447,859$ PROJECT TOTAL -$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Estimated Annual
One Time Costs Recurring Cost
- ()
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$ -$
-
-
-
-
-
197
PROJECT:College Heights Utility Rehabilitation
FUND(S):Water Capital Projects PROJECT NUMBERS & BUDGET:
Wastewater Capital Projects Water:TBD $2,423,844
Wastewater: TBD $1,302,844
Total Project Budget:$3,726,688
PROJECT
MANAGER:Stephen Maldonado, Jr.
FUNDING
PROJECT SOURCES: Long Term Debt/Utility Revenue
CLIENT:Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
PROJECT DESCRIPTION
PROJECT SCOPE
This project includes the rehabilitation of water and wastewater lines in the northside area, in the vicinity of Eisenhower Street, University Drive, Jane
Street, and Nimitz Street. The sanitary sewer lines are in need of replacement due to an increase in service disruptions caused by deteriorating lines,
shallow lines, and poor access to mains located near back lot lines(NOTE: This project will move any rear serving sewer mains to front lot lines). The
water distribution lines are in need of replacement due to an increase in service disruptions caused by deteriorating lines and inadequate fire
protection due to the existence of smaller lines within the respective area. Design, bidding, and construction of College Heights Utility Rehabilitation
project will include approximately, approximately 4,000 LF of 8-inch water distribution line, approximately 2,000 LF of 12-inch water distribution line,
approximately 1,000 LF of 6-inch sanitary sewer collection line, and approximately 5,000 LF of 8-inch sanitary sewer collection line. This project also
includes the milling/overlaying of all existing aging streets in the respective project area.
Design, bidding, and construction of College Heights Utility Rehabilitation Project will include:
Approximately 4,000 LF of 8‐inch Water Distribution Line
Approximately 2,000 LF of 12‐inch Water Distribution Line
Approximately 1,000 LF of 6‐inch Sanitary Sewer Collection Line
Approximately 5,000 LF of 8‐inch Sanitary Sewer Collection Line
Approximately 75,000 SY of 1.5‐inch Mill/Overlay of the Existing Aging Streets for the Entire Project Area (TO BE FUNDED COMPLETELY BY THE
WATER SERVICES DEPARTMENT)
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Prior Years - - - - -
2010-11 - - - - -
2011-12 - - - - -
2012-13 - - - - -
2013-14 - - - - -
2014-15 - - - - -
2015-16 - 500,000 - - 500,000
2016-17 - 103,980 3,122,708 - 3,226,688
PROJECT TOTAL -$ 603,980$ 3,122,708$ -$ 3,726,688$
198
Water Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 250,000 250,000
2016-17 51,990 2,121,854 2,173,844
Water Total -$ 301,990$ 2,121,854$ -$ 2,423,844$
Wastewater Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 250,000 250,000
2016-17 51,990 1,000,854 1,052,844
Wastewater Total -$ 301,990$ 1,000,854$ -$ 1,302,844$
Personnel (Salaries/Benefits)
Supplies
College Heights Utility RehabilitationPROJECT:
PROJECT CALENDAR OF EXPENDITURES BY FUND
603,980$ 3,122,708$ -$ 3,726,688$ PROJECT TOTAL -$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Estimated Annual
One Time Costs Recurring Cost
-
-
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$ -$
-
-
-
-
199
PROJECT:McCulloch Utility Rehabilitation
FUND(S):Water Capital Projects PROJECT NUMBERS & BUDGET:
Wastewater Capital Projects Water:TBD $2,789,947
Wastewater: TBD $2,381,515
Total Project Budget:$5,171,462
PROJECT
MANAGER:Stephen Maldonado, Jr.
FUNDING
PROJECT SOURCES: Long Term Debt/Utility Revenue
CLIENT:Water Services
PROJECT DESCRIPTION
PROJECT SCOPE
This project includes the rehabilitation of water and wastewater lines in the Southgate area, in the vicinity of Arizona Street, Phoenix Street, Carolina
Street, and Georgia Street. The sanitary sewer lines are in need of replacement due to an increase in service disruptions caused by deteriorating
lines, shallow lines, and poor access to mains located near back lot lines(NOTE: This project will move any rear serving sewer mains to front lot lines).
The water distribution lines are in need of replacement due to an increase in service disruptions caused by deteriorating lines and inadequate fire
protection due to the existence of smaller lines within the respective area. This project also includes the milling/overlaying of all existing aging streets
in the respective project area.
Design, bidding, and construction of College Heights Utility Rehabilitation Project will include:
Approximately 4,400 LF of 6‐inch Water Distribution Line
Approximately 4,050 LF of 8‐inch Water Distribution Line
Approximately 1,650 LF of 12‐inch Water Distribution Line
Approximately 14,140 LF of 6‐inch Sanitary Sewer Collection Line
Approximately 2,240 LF of 12‐inch Sanitary Sewer Collection Line
Approximately 50,000 SY of 1.5‐inch Mill/Overlay of the Existing Aging Streets for the Entire Project Area (TO BE FUNDED COMPLETELY BY THE
WATER SERVICES DEPARTMENT)
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 - - - - -
2011-12 - - - - -
2012-13 - - - - -
2013-14 - - - - -
2014-15 - - - - -
2015-16 - - - - -
2016-17 - 899,598 - - 899,598
2017-18 - - 4,271,864 - 4,271,864
5,171,462$ PROJECT TOTAL -$ 899,598$ 4,271,864$ -$
OJ C C O U S SC
200
Water Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 449,799 449,799
2017-18 2,340,148 2,340,148
Water Total -$ 449,799$ 2,340,148$ -$ 2,789,947$
Wastewater Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 449,799 449,799
2017-18 1,931,716 1,931,716
Wastewater Total -$ 449,799$ 1,931,716$ -$ 2,381,515$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Estimated Annual
One Time Costs Recurring Cost
McCulloch Utility RehabilitationPROJECT:
PROJECT CALENDAR OF EXPENDITURES BY FUND
899,598$ 4,271,864$ -$ 5,171,462$ PROJECT TOTAL -$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$ -$
-
-
-
O e e Costs ecu g Cost
-
-
-
201
PROJECT:Plantation Oaks Water Line Rehabilitation PROJECT #: WF1433732
WTWOC
FUND(S):Water Capital Projects PROJECT
BUDGET:$240,318
PROJECT Stephen Maldonado FUNDING
MANAGER: SOURCES: Long Term Debt/Utility Revenue
PROJECT Water Services Department
CLIENT:
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 50,718 189,600 240,318
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 50,718$ 189,600$ -$ 240,318$
This project includes the rehabilitation of a 12-inch water line along Harvey Rd, between Scarlett O'Hara Drive and Munson Avenue. This
respective 12-inch segment of water line was identified and recommend for replacement in a 2004 electrolysis evaluation performed by a
private consultant. This line was also included in the future 'Plantation Oaks Utility Rehabilitation Project' that is considered a lower priority
area, however, after recent/continuing failures, staff feels that this segment should be replaced as soon as possible to eliminate recurring
repairs that are causing service disruptions and limited fire protection to existing customers in this area.
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Design, bidding, and construction of Plantation Oaks Water Line Rehabilitation Project will include:
Approximately 1,850 LF of 12" Water Line
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated AnnualFirst Fiscal Year
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
-
-
202
WASTEWATER
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH
FISCAL YEAR 2016-2017
203
WASTEWATER SERVICE
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
FY12 REVISED APPROVED
PROJECT WORK REQUEST APPROVED APPROPRIATIONS FY10-11 FY11-12
NUMBER NUMBER BUDGET THROUGH FY10 APPROPRIATIONS APPROPRIATIONS
BEGINNING FUND BALANCE:512,852$ 512,852$
ADDITIONAL RESOURCES:
UTILITY REVENUE BONDS/CERTIFICATES OF OBLIGATION 6,425,000$ 7,580,000$
INTEREST ON INVESTMENTS 7,900 10,000
TRANSFERS FROM OPERATIONS 825,000 1,120,000
INTERGOVERNMENTAL - -
OTHER 500,000 72,000
SUBTOTAL ADDITIONAL RESOURCES 7,757,900$ 8,782,000$
TOTAL RESOURCES AVAILABLE 8,270,752$ 9,294,852$
COLLECTION PROJECTS
COLLECTION PLANT - SCWOC
OVERSIZE PARTICIPATION - TBD 100,000 - 100,000 100,000
EAST SIDE FM 158 SEWER LINE WF1382208 1,538,000 - - 735,000
NANTUCKET GRAVITY SEWER WF1094676 432,938 516,000 15,000 -
LICK CREEK PARALLEL TRUNK LINE - PHASE I WF0912284 2,825,000 395,496 - -
ST VICTORIA AVENUE EXTENSION -WF1158560 47,000 47,000 - -
SCOTT AND WHITE SEWER LINE/LIFT STATION WF1338390 1,207,758 - 1,500,000 -
BEE CREEK PARALLEL TRUNKLINE WF1369909 14,703,625 - 2,000,000 106,997
FM 2154 SEWER SERVICE WF1369908 3,332,836 - 500,000 -
SUBTOTAL
REHABILITATION PROJECTS
EMERALD PKWY / BENT OAK -WF0626151 297,064 297,064 - -
ST TAUBER & STASNEY REHAB -WF0625893 450,626 594,109 - -
W SOUTH KNOLL / THE GLADE WF1044485 3 005 683 2 052 223 953 460
BUDGET APPROPRIATIONS
W SOUTH KNOLL / THE GLADE -WF1044485 3,005,683 2,052,223 - 953,460
W SOUTHWOOD 5-7 -WF1105424 2,983,734 2,983,734 - -
W EASTGATE REHAB -TBD 2,805,830 - - -
W COLLEGE HEIGHTS REHAB -TBD 1,302,844 - - -
W COONER UTILITY REHAB -WF1440708 657,000 - - 92,000
W McCULLOCH UTILITY REHAB TBD 2,381,515 - - -
NORTHEAST TRUNK LINE REHAB WF1440716 309,029 - - 309,029
CLOSED PROJECTS
SUBTOTAL
204
WASTEWATER SERVICE
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT
EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED
THROUGH FY09 FY09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY 16-17
929,734$ 1,184,795$ 512,852$ 40,730$ 31,311$ 38,332$ 5,869$ 27,122$
300,468$ 3,130,000$ 7,580,000$ 13,175,000$ 3,860,000$ 5,300,000$ 3,145,000$ 5,575,000$
3,342 7,900 10,000 15,000 10,000 10,000 5,000 7,500
2,700,000 2,625,000 1,120,000 775,000 940,000 1,610,000 1,175,000 1,240,000
- - - - - - - -
- 500,000 72,000 250,000 - - - -
3,003,810$ 6,262,900$ 8,782,000$ 14,215,000$ 4,810,000$ 6,920,000$ 4,325,000$ 6,822,500$
3,933,544$ 7,447,695$ 9,294,852$ 14,255,730$ 4,841,311$ 6,958,332$ 4,330,869$ 6,849,622$
- - 100,000 100,000 100,000 100,000 100,000 100,000 100,000
- - - 325,000 831,000 382,000 - - -
33,938 239,825 159,175 - - - - - -
10,422 - - - - - - 1,683,747 1,130,831
2,035 - - 44,965 - - - - -
- - 273,000 934,758 - - - - -
- - 100,000 1,606,997 9,671,149 3,325,479
- - 75,000 225,000 370,000 210,000 2,452,836 - -
46,395$ 239,825$ 707,175$ 3,236,720$ 10,972,149$ 4,017,479$ 2,552,836$ 1,783,747$ 1,230,831$
6,006 39 291,019 - - - - - -
85,626 - 365,000 - - - - - -
66 995 52 796 110 000 847 188 1 928 704
PROJECT EXPENDITURES
66,995 52,796 110,000 847,188 1,928,704 - - - -
110,940 113,303 2,623,160 136,331 - - - - -
- - - - 275,000 2,530,830 - -
- - - - - - - 250,000 1,052,844
- - - 82,000 575,000 - - - -
- - - - - - - - 449,799
- - - 309,029
242,519 907,562 7,423
512,086$ 1,073,700$ 3,396,602$ 1,374,548$ 2,503,704$ 275,000$ 2,530,830$ 250,000$ 1,502,643$
205
WASTEWATER SERVICE
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
FY12 REVISED APPROVED
PROJECT WORK REQUEST APPROVED APPROPRIATIONS FY10-11 FY11-12
NUMBER NUMBER BUDGET THROUGH FY10 APPROPRIATIONS APPROPRIATIONS
BUDGET APPROPRIATIONS
TREATMENT & DISPOSAL PROJECTS
TREATMENT & DISPOSAL/PUMPING PLANT - SPWOC
CARTERS CREEK HEADWORKS IMP WF1223116 1,508,550 500,000 - 1,008,550
LICK CREEK CLARIFIER CATWALKS WF1042497 413,470 387,500 - 25,970
SLUDGE TREATMENT & DISPOSAL/PUMPING PLANT - SSWOC
LICK CREEK CENTRIFUGE IMPROVEMENTS WF1142617 405,571 400,000 85,575 -
LICK CREEK SLUDGE HOLDING TANK IMP WF1142618 452,739 500,000 - -
CARTERS CREEK ATAD IMPROVEMENTS WF1104547 238,593 914,000 - -
LICK CREEK RETURN ACTIVATED SLUDGE MODIFICATIONS WF1142623 433,144 250,000 - 183,144
CC CENTRIFUGE IMPROVEMENTS TBD 2,182,000 - - -
LICK CREEK SLUDGE BLOWER REPLACEMENT WF1440712 200,000 - - 200,000
CC TREATMENT STRUCTURE COATINGS REPLACEMENT TBD 366,000 - - -
LICK CREEK DIGESTION FACILITY TBD 4,097,000 - - -
LICK CREEK CAPACITY EXPANSION TBD 7,127,000 - - -
LICK CREEK CENTRIFUGE REPLACEMENT WF1433858 1,000,000 - 1,000,000 -
CC DIGESTED SLUDGE AERATOR REPLACEMENT WF1441829 650,000 - - 650,000
LIFT STATION FORCE MAIN REHAB TBD 71,797 - - -
CLOSED PROJECTS
SEWER GENERAL PLANT - SGWOC
SCADA REPLACEMENT - WF0742950 545,340 445,340 100,000 -
WW CARTERS CREEK LAB AND SCADA BUILDING WF1129844 1,267,000 838,087 327,000 -
LICK CREEK PROCESS CONTROL IMPROVEMENTS WF1142624 278,435 203,000 - 75,435
SCADA - NEW LIFT STATIONS WF1359125 275,000 80,000 80,000 115,000
REMOTE PLANT SECURITY -WF1219655 300,000 300,000 - -
CC FIBER RING WF1440366 450,000 120,000 - -
CC ELECTRICAL IMPROVEMENTS -TBD 1,323,000 - - -
W UTILITY SERVICE CENTER RENOVATIONS WF1441517 348,000 - 37,500 -
AGGIE ACRES FIBER OPTIC CONDUIT -WF1440367 111,172 --111,172GG C S O C CO U 036 ,,
CLOSED PROJECTS -- -
SUBTOTAL
CAPITAL PROJECTS CONTINGENCY TBD - 33,087 150,000
CAPITAL PROJECTS SUBTOTAL 62,424,293 5,778,162$ 4,815,757$
GENERAL AND ADMINISTRATIVE 70,299 69,294
DEBT ISSUANCE COST 35,000 40,000
TOTAL EXPENDITURES 5,883,461$ 4,925,051$
MEASUREMENT FOCUS ADJUSTMENT
ENDING FUND BALANCE:2,387,291$ 4,369,801$
ST Project funded through combination of sources. Project sheet reflected in Streets section of CIP document.
W Project funded through combination of sources. Project sheet reflected in Water section of CIP document.
WW Project funded through combination of sources. Project sheet reflected in Wastewater section of CIP document.
206
WASTEWATER SERVICE
CAPITAL IMPROVEMENT PROJECTS
FISCAL YEAR 2011-2012 THROUGH FISCAL YEAR 2016-2017
PROJECT
EXPENDITURES ACTUAL ESTIMATE PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED
THROUGH FY09 FY09-10 FY 10-11 FY 11-12 FY 12-13 FY 13-14 FY 14-15 FY 15-16 FY 16-17
PROJECT EXPENDITURES
- 52,402 227,223 924,509 304,416 - - - -
8,374 17,877 220,219 167,000 - - - - -
4,575 50,469 195,527 155,000 - - - - -
4,893 33,776 257,970 156,100 - - - - -
10,641 88,675 139,277 - - - - - -
676 31,080 232,950 168,438 - - - - -
- - - - - - 475,000 1,068,000 639,000
- - - 200,000 - - - - -
- - - - - - 366,000 - -
- - - - - - - - 2,635,000
- - - - - - - - 540,000
- - 150,000 850,000
- - - 650,000
- - - - - - 71,797
77,152 721,248 47,056
149,038 48,626 312,908 34,768 - - - - -
19,087 110,857 544,248 592,808 - - - - -
2,811 24,553 152,065 99,006 - - - - -
- - 63,591 117,259 94,150 - - - -
- 137,693 162,307 - - - - - -
- - - 120,000 - - 330,000 -
- - - - - - 696,000 627,000 -
- - - 37,500 50,000 260,500 - - -
---111,172 -----,
85,957 400,906 45,426
363,204$ 1,718,162$ 2,750,767$ 4,383,560$ 448,566$ 260,500$ 1,608,797$ 2,025,000$ 3,814,000$
- 150,000 150,000 150,000 150,000 150,000 150,000
921,684$ 3,031,688$ 6,854,544$ 9,144,828$ 14,074,419$ 4,702,979$ 6,842,463$ 4,208,747$ 6,697,474$
77,890 70,299 69,294 70,000 70,000 70,000 70,000 70,000
103 10,000 40,000 80,000 30,000 40,000 25,000 40,000
3,109,681$ 6,934,843$ 9,254,122$ 14,224,419$ 4,802,979$ 6,952,463$ 4,303,747$ 6,807,474$
360,931$
1,184,795$ 512,852$ 40,730$ 31,311$ 38,332$ 5,869$ 27,122$ 42,148$
207
COLLECTION PROJECTS
208
WORK
Oversized Participation ORDER #: TBD
PROJECT: Wastewater Lines PROJECT #: SCWOC
FUND: PROJECT
BUDGET:ANNUAL
PROJECT
MANAGER:Stephen Maldonado, Jr.FUNDING
SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 100,000 100,000
2011-12 100,000 100,000
2012-13 100,000 100,000
2013-14 100,000 100,000
2014-15 100,000 100,000
2015-16 100,000 100,000
2016-17 100,000 100,000
Wastewater Capital Projects
PROJECT DESCRIPTION
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
These funds are available for oversize participation with developers in the construction of sewer lines above the
minimum size needed to serve the development. This allows lines to be built large enough to meet future development
without having to go back and install larger lines.
PROJECT SCOPE
Projects are identified based on development activity.
06 00,000 00,000
TOTAL -$ -$ 700,000$ -$ 700,000$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$ -$
OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Annual Estimated
One Time Costs Recurring Cost
209
PROJECT:East Side FM 158 Sewer Service PROJECT #: WF1382208
SCWOC
PROJECT
FUND(S):Wastewater Capital Projects BUDGET: $1,538,000
PROJECT FUNDING
MANAGER: Danielle Charbonnet SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Stephen Maldonado, Jr.
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - -
2010-11 -
2011-12 233,000 80,000 12,000 325,000
2012-13 400,000 10,000 407,000 14,000 831,000
2013-14 375,000 7,000 382,000
2014-15 .-
2015-16 -
2016-17 -
PROJECT TOTAL 633,000$ 90,000$ 782,000$ 33,000$ 1,538,000$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project will provide sewer service to the sewer service area within the City of Bryan Corporate Limits acquired as College Sation Sewer
Service area.
This project will construct gravity sewer, lift station and forced main to serve properties along FM 158 south of the intersection with FM 30 in
service territory acquired from the City of Bryan and within the City of Bryan's corporate limits.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
12,800 -$
$2,400
$2,000
$8,400
-
-
210
WORK
ORDER #: WF1094676
PROJECT: Nantucket Gravity Line PROJECT #: SCWOC
FUND:PROJECT
BUDGET: $432,938
PROJECT
MANAGER: Daniel Beamon FUNDING
SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Stephen Maldonado, Jr.
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 38,577 235,186 - 273,763
2010-11 6,423 152,752 159,175
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016 17
Wastewater Capital Projects
PROJECT DESCRIPTION
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
This work was previously included with the Project titled "Nantucket Lift Station". The work has been separated to clarify
the expenditures. This project originally consisted of the removal of the existing Nantucket Lift Station and force main to
be replaced with gravity sanitary sewer. During design, it was determined that the gravity sewer line would require a
horizontal bore under State Hwy 6 in order to maintain proper gravity sewer grades, therefore, the overall scope and
budget of the project have since been updated.
PROJECT SCOPE
2016-17 -
TOTAL -$ 45,000$ 387,938$ -$ 432,938$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
First Fiscal Year Annual Estimated
One Time Costs Recurring Cost
OPERATIONS AND MAINTENANCE COSTS
-$ -$
-
211
PROJECT:Lick Creek Parallel Trunkline PROJECT #: WF0912284
Phase 1 SCWOC
PROJECT
FUND(S):Wastewater Capital Projects BUDGET: $2,825,000
PROJECT FUNDING
MANAGER: Daniel Beamon SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Stephen Maldonado, Jr.
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 10,422 - - 10,422
2010-11 -
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 200,000 1,483,747 1,683,747
2016-17 100,000 1,030,831 1,130,831
PROJECT TOTAL -$ 310,422$ 2,514,578$ -$ 2,825,000$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project will consist of design and construction of a parallel or replacement trunkline from the southern boundary of Pebble Creek
Subdivision to the Lick Creek Wastewater Treatment Plant.
This project phase may consist of a parallel line to the existing 18" sewer line, with a possible design to install an ultimate 42" line. This
original trunkline serves a large portion of sanitary sewer customers that are south of Barron Road and was originally installed as an 18"
line to serve Pebble Creek. Design, bidding, and construction of the Lick Creek Trunkline PH I project will include approximately 5,400 LF
of wastewater collection system line.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
-
212
PROJECT:PROJECT #: WF1338390
SCWOC
FUND(S): Wastewater Capital Projects PROJECT
BUDGET: 1,207,758
PROJECT Philip Bargas FUNDING
MANAGER: SOURCES: Long Term Debt/Utility Revenue
PROJECT Stephen A. Maldonado, Jr.
CLIENT:
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 55,000 218,000 273,000
2011-12 24,000 910,758 934,758
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Scott & White Lift Station
The proposed Scott & White Hospital, located at the southeast corner of SHWY6 and Rock Prairie Road, will need sewer service by June
2012. A development agreement approved by City Council on November 22, 2010 included a plan for the construction of a new lift station
that will provide sewer service to the proposed Scott & White Hospital. This project consists of the design, construction, and land acquisition
required for a new lift station facility (on the Scott & White property) and a force main along SHWY6 that will connect to the Spring Creek
trunk line.
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Design, bidding, and construction of the Scott & White Lift Station will include:
New Lift Station Facility
Sanitary Sewer Force Main
2016-17 -
PROJECT TOTAL 55,000$ 242,000$ 910,758$ -$ 1,207,758$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
-
-
213
PROJECT:PROJECT #: WF1369909
SCWOC
FUND(S):Wastewater Capital Projects PROJECT
BUDGET:
PROJECT Jeff Haeber FUNDING
MANAGER: SOURCES: Long Term Debt/Utility Revenue
PROJECT Water Services
CLIENT:
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 100,000 100,000
2011-12 250,000 1,356,997 1,606,997
2012-13 200,000 9,471,149 9,671,149
2013-14 200,000 3,125,479 3,325,479
2014-15 -
2015-16 -
Bee Creek Parallel Trunk Line
The existing Bee Creek Trunkline sub-basin currently serves areas along FM2818, from areas north of Wellborn Road, to the Carters Creek
Wastewater Treatment Plant. Much of the existing trunkline was constructed in 1973 and was shown to have several surcharging line
segments in the 2011 HDR Sanitary Sewer Collection System Master Plan Update. This project will install a gravity line to increase the
system capacity of the Bee Creek Trunkline sub-basin to accept the ultimate build-out demand anticipated in this respective area. This
trunkline capacity increase is necessary to proactively prevent surcharge events, possible fines from TCEQ, and customer service
disruptions. The project will also be broken into two(2) contruction phases, with Phase I starting contruction in FY12-13 and spanning from
CCWWTP to Welsh Avenue. Phase II is anticipated to start construcion in FY13-14 and will span from Welsh Avenue to areas north of
Wellborn Road.
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Design, bidding, and construction of the Bee Creek Relief Line will include:
Approximately 28,000LF Of Gravity Sanitary Sewer Main Ranging In Size From 18-inch to 36-inch
$14,703,625
2016-17 -
PROJECT TOTAL 250,000$ 1,856,997$ 12,596,628$ -$ 14,703,625$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
-
-
214
PROJECT: FM 2154 Sewer Trunk Line PROJECT #: WF1369908
SCWOC
PROJECT PROJECT
MANAGER: Philip Bargas BUDGET: $3,332,836
PROJECT FUNDING
CLIENT: Water Services/ Stephen Maldonado, Jr.SOURCES: Long Term Debt/Utility Revenue
Design, bidding, and construction of the FM 2154 Sewer Trunk Line Project will include:
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - -
2010-11 75,000 75,000
2011-12 225,000 225,000
2012-13 290,000 80,000 370,000
2013-14 150,000 60,000 210,000
2014-15 52,250 56,626 2,343,960 2,452,836
2015-16 -
2016-17 -
PROJECT TOTAL 492 250$496 626$2 343 960$$3 332 836$
PROJECT GOALS AND OBJECTIVES
New Lift Station Facility
Approximately 3,800 LF of 8" Sanitary Sewer Force Main
Approximately 9,400 LF of 12" Gravity Sanitary Sewer Main
PROJECT SCOPE
This option includes the design/construction/easement acquisition of installing a gravity sanitary sewer line along the east side of
FM2154, a lift station in the proximity of the intersection of FM2154/Greens Prairie Trail, and a force main along the south side of
Greens Prairie Trail. The location of the proposed lift station and force main is preliminary and was developed from a planning level
stage. Preliminary plan and profile views of the proposed gravity sewer line have also been developed to verify that depths do not
exceed 25‐ft.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT TOTAL 492,250$ 496,626$ 2,343,960$ -$ 3,332,836$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
First Fiscal Year Annual Estimated
One Time Costs Recurring Cost
OPERATIONS AND MAINTENANCE COSTS
-$ 200$
200
215
REHABILITATION PROJECTS
216
WORK
ORDER #: WF0626151
PROJECT: PROJECT #: SCWOC
FUND: PROJECT
BUDGET: $297,064
PROJECT
MANAGER: Ed Savage FUNDING
SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years 1,088 4,958 - - 6,045
2010-11 40 290,979 291,019
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Emerald Parkway / Bent Oak
PROJECT DESCRIPTION
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Wastewater Capital Projects
This project consists of a new alignment of a wastewater collection line that will be installed to provide better flow
hydraulics and will have sealed and bolted manholes. This construction will correct poor flow conveyance through the
particular sewer segment and high levels of infiltration and inflow in the sewer basin upstream of the area. This project is
development driven and Water Services will be working with the land owner to construct per Development Agreement.
PROJECT SCOPE
Phase I of this project will consist of realigning a segment of the respective line with Phase II consisting of removing and
replacing a portion on line in place. Design, bidding, and construction of the Emerald Parkway/Bent Oak Sanitary Sewer
Line project will include approximately 1,000 LF of wastewater collection system line.
TOTAL 1,128$ 4,958$ 290,979$ -$ 297,064$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$ 3,125$
First Fiscal Year Annual Estimated
One Time Costs Recurring Cost
3,125
OPERATIONS AND MAINTENANCE COSTS
217
PROJECT:PROJECT #: WF1440716
SCWOC
FUND(S): Wastewater Capital Projects PROJECT
BUDGET:$309,029
PROJECT FUNDING
MANAGER: Edwin Savage SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 60,953 248,076 309,029
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Northeast Trunkline Rehabilitation
In 2010, Interra Hydro conducted a condition assessment of the Northeast Trunkline and identified major defects within the line, major
defects within manholes/connections, and major embankment degradation areas. The results of this study indicate that there are several line
segments and manholes that have major defects are considered structural/RDII contributory. The intent of this project is to repair/replace the
most critical segments of interceptor.
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Design, bidding, and construction of the Northeast Trunkline Rehabilitation will include:
Isolated segment replacement and pipe bursting with HDPE for identified deficient lines.
2016-17 -
PROJECT TOTAL -$ 60,953$ 248,076$ -$ 309,029$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
-
-
218
TREATMENT PROJECTS
219
PROJECT:Carters Creek Headworks Improvements PROJECT #: WF1223116
SPWOC
FUND(S):Wastewater Capital Projects PROJECT
BUDGET: $1,508,550
PROJECT FUNDING
MANAGER: Philip Bargas SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Doug Wallace
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 52,402 - - 52,402
2010-11 227,223 227,223
2011-12 124,509 800,000 924,509
2012-13 15,000 289,416 304,416
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 419,134$ 1,089,416$ -$ 1,508,550$
Personnel (Salaries/Benefits)
This project will replace or refurbish components of the existing headworks that have become unserviceable.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project has been revised to only restore functionality to the existing headwork equipment rather than the improvements previously
planned. It is fairly certain nutrient removal will be required within the next two discharge permit renewals and it is likely that nutrient
removal will require further modifications of the headworks.
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
220
PROJECT:Lick Creek Clarifier Catwalks PROJECT #: WF1042497
(Lick Creek Misc Improvements)SPWOC
PROJECT
FUND(S): Wastewater Capital Projects BUDGET: $413,470
PROJECT FUNDING
MANAGER: Philip Bargas SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services / Doug Wallace
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 26,251 - - 26,251
2010-11 13,952 206,267 220,219
2011-12 2,000 165,000 167,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 42,203$ 371,267$ -$ 413,470$
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECT SCOPE
Provide funds for constructing catwalks around the Lick Creek Wastewater Treatment Plant Clarifiers. The catwalks will provide safe access
for the operators to operate and maintain the clarifiers. This is an important safety and operational project. This project has been bundled
together with the Return Activated Sludge Modifications, Sludge Holding Tank, Centrifuge, and the Process Control Improvements projects to
provide a more attractive bid package.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Recurring Cost
-
-
One Time Costs
-
-
-
-
-
221
PROJECT:Lick Creek Centrifuge Improvements PROJECT #: WF1142617
(Lick Creek Misc Improvements)SSWOC
PROJECT
FUND(S): Wastewater Capital Projects BUDGET: $405,571
PROJECT FUNDING
MANAGER: Philip Bargas SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services / Doug Wallace
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 55,044 - - 55,044
2010-11 41,201 154,326 195,527
2011-12 5,000 150,000 155,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 101,245$ 304,326$ -$ 405,571$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECT SCOPE
Provide funds for improvements to Lick Creek Wastewater Treatment Plant Centrifuge. These include installing a larger sludge discharge
hopper, a sludge conveyor replacing the current Moyno pump, and a work platform around the centrifuge. This project has been bundled
together with the Sludge Holding Tank Improvements, Return Activated Sludge Modifications, Clarifier Catwalk Improvements, and the
Process Control Improvements to provide a more attractive bid package.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
Recurring Cost
-
-
One Time Costs
-
-
-
222
PROJECT:Lick Creek Sludge Holding Tank PROJECT #: WF1142618
Improvements (Lick Creek Misc Imp)SSWOC
PROJECT
FUND(S):Wastewater Capital Projects BUDGET: $452,739
PROJECT FUNDING
MANAGER: Philip Bargas SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Doug Wallace
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 38,669 - - 38,669
2010-11 28,097 229,873 257,970
2011-12 3,000 153,100 156,100
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 69,766$ 382,973$ -$ 452,739$
PROJECT SCOPE
Provide funds to expand the size of the Waste Sludge Holding Tank at Lick Creek Wastewater Treatment Plant. The construction cost
include up-sizing one positive displacement blower to aerate the increased volume of sludge in the holding tank in case two of the current
blowers cannot provide the correct amount of aeration. This project has been bundled together with the Centrifuge Improvements, Return
Activated Sludge Modifications, Clarifier Catwalk Improvements, and the Process Control Improvements to provide a more attractive bid
package.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
Recurring Cost
-
-
One Time Costs
-
-
-
-
-
223
WORK
CARTERS CREEK ATAD ORDER #: WF1104547
PROJECT: IMPROVEMENTS PROJECT #: SSWOC
(CC MISC IMPROVEMENTS)
FUND: PROJECT
BUDGET: $238,593
PROJECT
MANAGER: Philip Bargas FUNDING
SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Doug Wallace
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 11,338 87,978 - 99,316
2010-11 109 139,168 139,277
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
WASTEWATER CAPITAL PROJECTS
PROJECT DESCRIPTION
PROJECT SCOPE
Provide funds for constructing catwalks around the Carters Creek ATAD reactors, replacing the ATAD motor
operated valves, and rehabilitating the ATAD cooling water system. This project has been bundled with the Clarifier
Improvements, Service Water Improvements, Gravity Thickener Improvements, and the Process Control
Improvements to provide a more attractive bid package.
Improvements include: replacing the motor operated valves (MOVs) with more efficient ones (these MOVs are being
constructed with the CC Miscellaneous Improvements in FY 10; installing catwalks to minimize the need for
operators to walk across the tops of the reactors to perform day-to-day tasks, increasing safety for the operators and
minimizing wear on the insulation and tops of the reactors; and rehabilitating the cooling water system to better cool
Reactor 3 and to transfer heat to Reactors 1 and 2 when needed.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
2015 16
2016-17 -
TOTAL -$ 11,447$ 227,146$ -$ 238,593$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
First Fiscal Year Estimated Annual
One Time Costs Recurring Cost
- -$
224
PROJECT:Lick Creek Return Activated Sludge PROJECT #: WF1142623
Modifications (Lick Creek Misc Imp)SPWOC
PROJECT
FUND(S):Wastewater Capital Projects BUDGET: $433,144
PROJECT FUNDING
MANAGER: Philip Bargas SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Doug Wallace
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 31,756 - - 31,756
2010-11 27,083 205,867 232,950
2011-12 3,000 165,438 168,438
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 61,839$ 371,305$ -$ 433,144$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECT SCOPE
Recent increases in plant loading have made it necessary to run both trains of the Lick Creek Wastewater Treatment Plant. It was found
that the Return Activated Sludge Pumps will not consistently pump Return Activated Sludge at an appropriate rate. This is a critical
function essential to meeting TCEQ mandated treatment requirements. This project will reconfigure the sludge piping so that the pumps
will perform acceptably. This project has been bundled together with the Sludge Holding Tank Improvements, Centrifuge Improvements,
Clarifier Catwalk Improvements, and the Process Control Improvements to provide a more attractive bid package.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
Recurring Cost
-
-
One Time Costs
-
-
-
225
PROJECT:Carters Creek Centrifuge Improvements PROJECT #: TBD
SSWOC
FUND(S):Wastewater Capital Projects PROJECT
BUDGET: $2,182,000
PROJECT FUNDING
MANAGER: Doug Wallace SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 -
2014-15 300,000 175,000 475,000
2015-16 100,000 968,000 1,068,000
2016-17 30,000 609,000 639,000
PROJECT TOTAL -$ 430,000$ 1,752,000$ -$ 2,182,000$
Personnel (Salaries/Benefits)
PROJECT SCOPE
This project is to provide funds for improvements to the existing Carters Creek Wastewater Treatment Plant sludge dewatering system.
These improvements are designed to ensure the critical plant process of dewatering sludge is completed as needed, thereby minimizing
Plant odors.
The scope of this project includes the design, bidding and construction of improvements to the the electrical and instrumentation
components of the existing centrifuge and installation of a second, redundant centrifuge.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
()
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
500
10,000
-
-
-
10,500
226
PROJECT:Lick Creek Sludge Blower Replacement PROJECT #: WF1440712
SSWOC
FUND(S):Wastewater Capital Projects PROJECT
BUDGET: $200,000
PROJECT FUNDING
MANAGER: Brian J. Smith SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 200,000 200,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 200,000$ -$ 200,000$
Personnel (Salaries/Benefits)
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project will replace the current blower units which are at the end of their service life. New blowers are needed to maintain quality of
sludge during storage, before dewatering. The existing sludge blowers are now obsolete, so finding spare parts for these are difficult and
have long delivery times.
Project is to replace the three existing sludge blowers at the Lick Creek wastewater Treatment Plant. No outside Engineering will be used
on this replace in-kind project.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
()
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
227
PROJECT:Carters Creek Treatment Structure PROJECT #: TBD
Coatings Replacement SPWOC
PROJECT
FUND(S):Wastewater Capital Projects BUDGET: $366,000
PROJECT FUNDING
MANAGER: Brian J. Smith SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services / Doug Wallace
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 -
2014-15 66,000 300,000 366,000
2015-16 -
2016-17 -
PROJECT TOTAL -$ 66,000$ 300,000$ -$ 366,000$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
PROJECT SCOPE
Provide funding for engineering and construction services to install new coatings and perform some minor structural repairs to plant
clarifiers. These are issues which were discovered, and quantified, during the Carters Creek Clarifier Improvement Project, but could not
be addressed in that project due to budget constraints. These repairs are necessary to ensure that the full service life of the equipment is
realized and full regulatory compliance is maintained.
Project scope includes engineering and construction to provide new coatings to four (4) clarifiers. These facilities are Clarifiers 2A & 2B
and 3A & 3B.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
Recurring Cost
-
-
One Time Costs
-
-
-
228
PROJECT:Lick Creek Digestion Facility PROJECT #: TBD
SSWOC
FUND(S):Wastewater Capital Projects PROJECT
BUDGET:
$4,097,000
PROJECT FUNDING
MANAGER: Brian J. Smith SOURCES:
Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 435,000 2,200,000 2,635,000
Future Years 262,000 1,200,000 1,462,000
PROJECT TOTAL -$ 697,000$ 3,400,000$ -$ 4,097,000$
P l (S l i /B fi )
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
18 750
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project will provide sludge digestion facilities for the Lick Creek Wastewater Treatment Plant. The digestion facility will be designed
and constructed to produce Class A sludge, per the State Regulatory parameters. Cost numbers are extrapolated out from ATAD system in
1995.
This project will provide a facility to digest the sludge generated at LC WWTP to class A standards for beneficial land application.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
18,750
10,000
-
30,000
2,000
60,750
229
PROJECT:Lick Creek Capacity Expansion PROJECT #: SPWOC
TBD
FUND(S): Wastewater Capital Projects PROJECT
BUDGET:7,127,000$
PROJECT FUNDING
MANAGER: Fred Surovik SOURCES: Long Term Debt
PROJECT
CLIENT: Water Services
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 540,000 540,000
Future Years 752,000 5,825,000 10,000 6,587,000
PROJECT TOTAL -$ 1,292,000$ 5,825,000$ 10,000$ 7,127,000$
This project will increase the Lick Creek Wastewater Treatment Plant capacity from 2 Million Gallons per Day to 4 Million Gallons per Day.
This capacity is needed to serve growth in the LCWWTP service area and maintain compliance with TCEQ regulations.
PROJECT SCOPE
This project will add 2 each 2 MGD trains to the existing plant as designed for the 2001 construction.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
-
230
PROJECT:Lick Creek Centrifuge Replacement PROJECT #: WF1433858
SSWOC
FUND(S): Wastewater Capital Projects PROJECT
BUDGET: $1,000,000
PROJECT FUNDING
MANAGER: Doug Wallace SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 150,000 150,000
2011-12 50,000 800,000 850,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 200,000$ 800,000$ -$ 1,000,000$
Personnel (Salaries/Benefits)
PROJECT SCOPE
This project will replace the sludge dewatering centrifuge at the Lick Creek WWTP. The current centrifuge requires an inordinate amount of
maintenance, at an inordinate cost in down time and money. Funds are included in this project to find and repair the cause of
electrical/electronic problems that currently interfere with the controls of the current centrifuge.
Engineering design, bid and construction for an upgraded replacement centrifuge and associated motor control center for the solids handling
at the Lick Creek Wastewater treatment Plant
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
231
PROJECT:Carters Creek Digested Sludge PROJECT #: WF1441829
Aerator Replacement SSWOC
PROJECT
FUND(S):Wastewater Capital Projects BUDGET: $650,000
PROJECT FUNDING
MANAGER: Doug Wallace SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 80,000 570,000 650,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 80,000$ 570,000$ -$ 650,000$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
RiCt
First Fiscal Year
OTi Ct
PROJECT SCOPE
This project will replace the current aeration diffusers in Digested Sludge Holding Tanks (DSHTs) #1 and #2 at the Carters Creek WWTP.
The diffusers in DSHT #1 experiences failures that require draining that tank and repairing the diffusers approximately every six to nine
months. The manufacturer has tried several fixes, and all have failed. This project would replace those diffusers with a system that can be
cleaned and/or repaired without taking the entire tank out of service. It would also provide similar diffusers in DSHT #2 to minimize the
number of different spare parts to keep on hand.
Provide for the Engineering and Construction of replacement sludge aeration system.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
Recurring Cost
-
-
One Time Costs
-
-
-
232
PROJECT:PROJECT #: TBD
FUND(S):Wastewater Capital Projects PROJECT
BUDGET:$71,797
PROJECT Stephen Maldonado FUNDING
MANAGER: SOURCES: Long Term Debt/Utility Revenue
PROJECT Water Services Department
CLIENT:
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 -
2014-15 14,161 57,636 71,797
2015-16 -
2016-17 -
Lift Station Force Main
Rehabilitation
In 2010, the Lift Station #2(LS#2) discharge forced main failed and caused a significant downstream sanitary sewer spill. This spill violates
our wastewater collection system permit parameters set forth by TCEQ. The subsequent investigation of the failure found that the almost 30-
yr old force main header was not installed to current design/construction cathodic protection standards and our department feels that it
should be rehabilitated to meet current specifications. This project also includes the design/construction of evaluating/rehabilitating a similar
lift station(Lift Station #3) that was installed during the same time period as LS#2.
PROJECT SCOPE
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Design, bidding, and construction of the Lift Station Force Main Rehabilitation will include:
LS#2 Force Main Rehabilitation
LS#3 Force Main Rehabilitation
2016-17 -
PROJECT TOTAL -$ 14,161$ 57,636$ -$ 71,797$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
-
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
233
PROJECT:SCADA Replacement PROJECT #: WF0742950
SGWOC
FUND(S):Wastewater Capital Projects PROJECT
BUDGET:
$545,340
PROJECT FUNDING
MANAGER: Michael Kellogg SOURCES:
Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - 197,664 - 197,664
2010-11 312,908 312,908
2011-12 34,768 34,768
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 545,340$ -$ 545,340$
PROJECT DESCRIPTION
PROJECT SCOPE
This project will facilitate the replacement of control based equipment that has exceeded its useful service life. It will upgrade the control of
the plants into a more integrated architecture that will:
1. Reduce development time and cost by the re-use of engineering practices.
2. Maximize returns from existing assets, through greatly improved control and monitoring.
3. Reduce future installation cost by utilizing standard bus technologies.
4. Provide a means of being proactive in maintaining equipment with available diagnostic tools.
Part of this project included a "radio communications survey" to determine what, if any, additional communications infrastructure would be
needed to communicate with new Lift Stations and potential future annexed property. The radio survey has been completed and the
results indicate that radio towers need to be erected at six lift station sites.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
,,
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
-
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
15,750$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
15,750$
-
-
-
234
Home of Texas A&M University ®
235
PROJECT:CCWWTP Laboratory & SCADA Building
FUND(S): Water Capital Projects PROJECT NUMBERS & BUDGET:
Wastewater Capital Projects Water: WF1352985 $127,000
Wastewater: WF1129844 $1,267,000
Total Project Budget: $1,394,000
PROJECT Philip Bargas
MANAGER:
FUNDING
PROJECT SOURCES:
CLIENT: Water Services / Karl Goldapp
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 129,944 - - 129,944
2010-11 - 118,373 457,875 - 576,248
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
This project is for the replacement of the Lab and SCADA building at the Carters Creek Wastewater Treatment Plant. The existing building was built
in 1982 as a chlorinator building and no longer meets laboratory standards. It is more cost effective to build a new building. The SCADA server room
is housed in a "home made" room within the other 1982 shop building that does not maintain temperature or humidity for the computer equipment.
Each system requires a clean controlled climate, so it is advantageous to construct one building to house both. This project also includes the
design/construction of an 8-inch water distribution line to serve the necessary fire protection for the proposed Lab/SCADA building.
PROJECT SCOPE
This project is for design, bidding, and construction of a 3,000 SF Lab and SCADA building for CCWWTP. In addition to the lab and SCADA areas,
there will be storage, entry vestibule, and four offices. Additionally, there will be an approximately 1,200 LF, 8" offsite water line constructed to
provide required fire flow to the facility.
2011-12 - 9,160 678,648 - 687,808
2012-13 - - - - -
2013-14 - - - - -
2014-15 - - - - -
2015-16 - - - - -
2016-17 - - - - -
1,394,000$ PROJECT TOTAL -$ 257,477$ 1,136,523$ -$
236
Water Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 32,000 32,000
2011-12 95,000 95,000
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Water Total -$ 32,000$ 95,000$ -$ 127,000$
Wastewater Portion
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 129,944 - - 129,944
2010-11 86,373 457,875 544,248
2011-12 9,160 583,648 592,808
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
Wastewater Total -$ 225,477$ 1,041,523$ -$ 1,267,000$
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
-
-
-
One Time Costs Recurring Cost
CCWWTP Laboratory & SCADA BuildingPROJECT:
PROJECT CALENDAR OF EXPENDITURES BY FUND
257,477$ 1,136,523$ -$ 1,394,000$ PROJECT TOTAL -$
First Fiscal Year Estimated Annual
-
Purchased Services
Capital Outlay
TOTAL -$ -$
-
-
237
PROJECT:Lick Creek Process Control PROJECT #: WF1142624
Improvements (Lick Creek Misc Imp)SGWOC
PROJECT
FUND(S): Wastewater Capital Projects BUDGET: $278,435
PROJECT FUNDING
MANAGER: Philip Bargas SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services / Doug Wallace
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - 27,364 - - 27,364
2010-11 22,065 130,000 152,065
2011-12 2,000 97,006 99,006
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ 51,429$ 227,006$ -$ 278,435$
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
PROJECT SCOPE
Provide funds to purchase and install improved process control instrumentation at Lick Creek Wastewater Treatment Plant. This project has
been bundled together with the Sludge Holding Tank Improvements, Centrifuge Improvements, Clarifier Catwalk Improvements, and the
Return Activated Sludge Improvements to provide a more attractive bid package.
Improvements include:
* Flow meters on each plant's influent line, purchase and install positive displacement pumps in each waste sludge line.
* In-line solids meters in the sludge processes.
* In-line solids meters in the aeration basins.
* Dissolved oxygen meters in each aeration basin to replace meters that have reached the end of their service lives, and purchase and install
pH meters in the influent and each aeration basin.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
-
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
-$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
238
PROJECT:SCADA - New Lift Stations PROJECT #: WF1359125
SGWOC
FUND(S): Wastewater Capital Projects PROJECT
BUDGET: $275,000
PROJECT FUNDING
MANAGER: Michael Kellogg SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 63,591 63,591
2011-12 117,259 117,259
2012-13 94,150 94,150
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 275,000$ -$ 275,000$
PROJECT SCOPE
This project is to provide communications and telemetry hardware to enable critical lift station operations to be remotely monitored.
Construction of new lift stations does not include the implementation of monitoring and alarming via the SCADA system. As of 2009, there
are Lift Stations in operation that are not within the SCADA system. Subsequent years allow for SCADA implementation of an additional four
per year.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
First Fiscal Year
One Time Costs
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
-
239
PROJECT:Remote Plant Security PROJECT #: WF1219655
SGWOC
FUND(S): Wastewater Capital Projects PROJECT
BUDGET:
$300,000
PROJECT FUNDING
MANAGER: Michael Kellogg SOURCES:
Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - 137,693 - 137,693
2010-11 162,307 162,307
2011-12 -
2012-13 .-
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 300,000$ -$ 300,000$
Personnel (Salaries/Benefits)
The original security project did not address the security needs of Lick Creek Wastewater Plant and remote package type plants. This project
will address the physical access and monitoring of these plants. It will follow the guidelines, procedures, and standards set in the Wastewater
Security Project. Strategic Business Plan Citywide Safety and Security Strategy 1.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL -$
-
-
-
-
-
-
-
240
PROJECT:Carters Creek Fiber Ring PROJECT #: WF1440366
SGWOC
FUND(S): Wastewater Capital Projects PROJECT
BUDGET: $450,000
PROJECT FUNDING
MANAGER: Michael Kellogg SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT:Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 120,000 120,000
2012-13 -
2013-14 -
2014-15 -
2015-16 330,000 330,000
2016-17 -
PROJECT TOTAL -$ -$ 450,000$ -$ 450,000$
Personnel (Salaries/Benefits)
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project will provide for data communication improvements. This will allow for built-in redundancy, wireless communications, mobile work
force, and any unforeseen communication plan not related to construction projects. The main focus is to construct fiber loops which provide
multiple paths to all facilities.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
-
241
PROJECT:Carters Creek Electrical Improvements PROJECT #: TBD
SGWOC
FUND(S):Wastewater Capital Projects PROJECT
BUDGET:
$1,323,000
PROJECT FUNDING
MANAGER: David Olivarez SOURCES:
Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 -
2012-13 -
2013-14 -
2014-15 96,000 600,000 696,000
2015-16 47,000 580,000 627,000
2016-17 -
PROJECT TOTAL -$ 143,000$ 1,180,000$ -$ 1,323,000$
This project will replace; the motor control centers at two blower installations, install new electrical conduit, pull new electrical conductors,
replace the MS South electrical switchgear.
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
PROJECT SCOPE
The project includes contracting an engineer to design and plan the needed replacements of the Motor Control Centers (MCC's) for Plants
2 and 3, run new conduit and wire from MCC's to clarifiers, including two 2" instrumentation conduits and exterior receptacles. The MS
South Switchgear will also be replaced. This project may need to include providing for a temporary power supply for critical equipment
during construction. Also, the possible installation of a french drain system around Plant 2 Blower Building to eliminate flooding concerns
for this facility during heavy rainfall events.
Personnel (Salaries/Benefits)
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
Estimated Annual
Recurring Cost
-
-
First Fiscal Year
One Time Costs
-
-
-
242
PROJECT:Aggie Acres Fiber Optic Conduit PROJECT #: WF1440367
SCWOC
FUND(S):Wastewater Capital Projects PROJECT
BUDGET: $111,172
PROJECT Michael Kellogg FUNDING
MANAGER: SOURCES: Long Term Debt/Utility Revenue
PROJECT
CLIENT: Water Services
Project Total
FISCAL YEAR Land Engineering Construction Misc Project Total
Prior Years - - - - -
2010-11 -
2011-12 111,172 111,172
2012-13 -
2013-14 -
2014-15 -
2015-16 -
2016-17 -
PROJECT TOTAL -$ -$ 111,172$ -$ 111,172$
Personnel (Salaries/Benefits)
Sli
PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR
PROJECT DESCRIPTION
ESTIMATED OPERATIONS AND MAINTENANCE COSTS
Estimated Annual
Recurring Cost
-
First Fiscal Year
One Time Costs
PROJECT SCOPE
This project is being executed in response to Council's exception to policy to allow connection of this lift station in the ETJ to the City's
sewer system. The fiber optic line will be the most efficient option of meeting TCEQ's requirement that our collection system be "properly
maintained and operated".
Supplies
Maintenance
Professional Services
Purchased Services
Capital Outlay
TOTAL
-
- -$
-
-
-
-
243
Home of Texas A&M University ®
244
Projected Projected Projected Projected Projected Projected
FY12 FY13 FY14 FY15 FY16 FY17 Comments
Street/Traffic Projects
Tauber and Stasney Rehab 8,112 8,355 8,606 8,864 9,130 9,404 Sweeping, landscaping, irrigation
Bird Pond Rehab - 5,000 5,150 5,305 5,464 5,628 Sweeping, landscaping, irrigation
Cooner Street Rehab - - 1,800 1,854 1,910 1,967 Sweeping, landscaping, irrigation
Holleman Extension 4,810 4,954 5,103 5,256 5,414 5,576 Sweeping, landscaping, irrigation
Victoria Avenue Extension 4,425 4,558 4,694 4,835 4,980 5,130 Sweeping, landscaping, irrigation
Jones Butler Extension - - 4,233 4,360 4,491 4,626 Sweeping, landscaping, irrigation
Royder Road 2,886 2,973 3,062 3,154 3,248 3,346 Sweeping, landscaping, irrigation
Health Science Center Parkway - - TBD TBD TBD TBD TBD
Barron Road Widening Phase II - 20,054 20,656 21,275 21,914 22,571 Sweeping, landscaping, irrigation
Barron Road East/Lakeway Drive - - - 11,543 11,889 12,246 Sweeping, landscaping, irrigation
Signal at SH40/Barron 2,045 2,106 2,170 2,235 2,302 2,371 Supply, maintenance and utility costs
Signal at Barron/Victoria 2,045 2,106 2,170 2,235 2,302 2,371 Utility costs
Traffic Signal at George Bush/Dominik 2,045 2,106 2,170 2,235 2,302 2,371 Utility costs
New Traffic Signals (2008 GOB)- 2,045 8,548 14,744 20,937 21,565 Utility costs
Signal at Wellborn/F&B - 2,045 2,106 2,170 2,235 2,302 Utility costs
Signal at Texas/Krenek Tap 2,045 2,106 2,170 2,235 2,302 2,371 Utility costs
Signal at SH30/Copperfield - 2,045 2,106 2,170 2,235 2,302 Utility costs
Signal at 2818/FM 60 - - 2,045 2,106 2,170 2,235 Utility costs
Signal at University Dr/University Town Center - - 2,045 2,106 2,170 2,235 Utility costs
Bike Loop - 2005 1,450 1,494 1,538 1,584 1,632 1,681 Maintenance costs
Hike and Bike Trails - Longmire Improvements 200 206 212 219 225 232 Maintenance costs
Hike and Bike Trail Completion 1,000 1,030 1,061 1,093 1,126 1,159 Trail Maintenance costs
Hike and Bike Trail Completion - Phase 2 2,000 2,060 2,122 2,185 2,251 2,319 Trail Maintenance costs
Lick Creek Hike and Bike Trail - - - 8,000 8,240 8,487 Trail Maintenance costs
University Drive Pedestrian Improvements Ph II - - - - - - TBD - O&M estimated to begin FY15
Street/Traffic Project Totals 33,063$ 65,244$ 83,766$ 111,762$ 120,865$ 124,491$
Parks Projects
Creek View Neighborhood Park - - 23,140 23,834 24,549 25,286 Personnel, supplies, maintenance, landscaping and
utility costs
Emerald Forest Park 775 798 822 847 872 898 Mainteinance costs
University Park - 200 206 212 219 225 Mainteinance costs
Skate Park 7,400 7,622 7,851 8,086 8,329 8,579 Maintenance and utility costs
Lick Creek Park Iron Bridge Trail Completion - 2,700 2,781 2,864 2,950 3,039 Trail Maintenance costs
Lincoln Center Addition - - - - 98,050 100,992 Personnel, supplies, utility costs and facilities
maintenance
Lick Creek Nature Center - - 247,650 255,080 262,732 270,614 Personnel (2 FT + temp/seasonal); supplies; utility
costs; facilities maintenance; and other services
Parks Project Totals 8,175$ 11,320$ 282,450$ 290,923$ 397,701$ 409,632$
Facility and Technology Projects
Fire Station #6 1,853,555 1,348,130 1,382,470 1,417,837 1,454,265 1,491,783
Personnel: ambulance company (9 FTE), engine
company (9 FTE); vehicle maintenance and
replacement; utility and landscaping service costs; and
supplies.
Library Expansion - - - - 206,000 212,180 Personnel (3 positions), supplies, utility costs, book
replacement and facilities maintenance
MDT System Replacement - 11,000 11,330 11,670 12,020 12,381 Maintenance Agreement
E-mail and File System Migration - 61,391 57,233 58,950 60,718 62,540 Licensing Agreement and server cost
Network and Data Security Upgrade - 10,000 10,300 10,609 10,927 11,255 Network and Application Security Testing
Facilities and Technology Project Totals $ 1,853,555 $ 1,430,521 $ 1,461,333 $ 1,499,066 $ 1,743,930 $ 1,790,138
Total Estimated O&M Costs 1,894,793$ 1,507,085$ 1,827,549$ 1,901,751$ 2,262,497$ 2,324,262$
Governmental Funds Capital Improvement Projects
Estimated Operations and Maintenance Costs*
*The Operations and Maintenance costs reflected above are estimates based on anticipated costs associated with each project. In some situations, the O&M cost of a project is minimal and can be
absorbed by the City department that is benefiting the most from the project. In other situations, the O&M cost is more significant and funding for these additional expenses is addressed through the
Service Level Adjustment (SLA) process. As the projects become better defined, the O&M estimates may be revised.
245
Projected Projected Projected Projected Projected Projected
FY12 FY13 FY14 FY15 FY16 FY17 Comments
Parkland Dedication
Southwest Park Development 15,000 15,450 15,914 16,391 16,883 17,389 Supplies and landscaping contract
Rain Water Harvesting 150 155 159 164 169 174 Electric utility costs
Parkland Projects Totals 15,150$ 15,605$ 16,073$ 16,555$ 17,051$ 17,563$
Wolf Pen Creek (WPC) TIF Projects
WPC TIF Capital Projects 92,000 94,760 97,603 100,531 103,547 106,653 Temporary/seasonal personnel, supplies,
chemicals, contract labor and utility costs
WPC Projects Totals 92,000$ 94,760$ 97,603$ 100,531$ 103,547$ 106,653$
Total Estimated O&M Costs 107,150$ 110,365$ 113,675$ 117,086$ 120,598$ 124,216$
Special Revenue Funds Capital Improvement Projects
Estimated Operations and Maintenance Costs*
*The Operations and Maintenance costs reflected above are estimates based on anticipated costs associated with each project. In some situations, the O&M cost of a project is minimal
and can be absorbed by the City department that is benefiting the most from the project. In other situations, the O&M cost is more significant and funding for these additional expenses is
addressed through the Service Level Adjustment (SLA) process. As the projects become better defined, the O&M estimates may be revised.
246
Projected Projected Projected Projected Projected Projected
FY12 FY13 FY14 FY15 FY16 FY17 Comments
Water Projects
Well #9 - - - - - 92,800 Personnel, supplies, maintenance and utility costs
Well #9 Collection Line - - - - - 1,600 Line Maintenance
Wellfield Collection System Loop - - - - - - Maintenance - estimated to begin in FY18
Dowling Road 10 MG Storage Tank - - - - - - TBD - O&M estimated to begin FY17
SPPS Chemical System Replacement - - 41,200 42,436 43,709 45,020 Supplies and maintenance
High Service Water Pump Improvements - - 67,000 69,010 71,080 73,213 Maintenance, utility costs and instrument calibration
Cooling Tower Expansion - - 61,000 62,830 64,715 66,656 Supplies and utility costs
Distribution SCADA - - - 5,000 5,150 5,305 Supply costs
Reclaimed Water - Irrigation Phase I 46,000 47,380 48,801 50,265 51,773 53,327 Supplies, maintenance and utility costs
Water Project Totals 46,000$ 47,380$ 218,001$ 229,541$ 236,428$ 337,921$
Wastewater Projects
East Side FM 158 Sewer Service - - - 12,800 13,184 13,580 Supplies and maintenance costs
FM 2154 Sewer Line - - - - 200 206 Utility costs
Emerald Parkway/Bent Oak 3,125 3,219 3,315 3,415 3,517 3,623 Line Maintenance
Carters Creek Centrifuge Improvements - - - - 10,500 10,815 Supplies and maintenance
Lick Creek Digestion Facility - - - - - 60,750 Personnel, maintenance and utility costs
Wastewater Project Totals 3,125$ 3,219$ 3,315$ 16,215$ 27,401$ 88,973$
Total Estimated O&M Costs 49,125$ 50,599$ 221,317$ 245,756$ 263,829$ 426,894$
*The Operations and Maintenance costs reflected above are estimates based on anticipated costs associated with each project. In some situations, the O&M cost of a project is minimal and
can be absorbed by the City department that is benefiting the most from the project. In other situations, the O&M cost is more significant and funding for these additional expenses is addressed
through the Service Level Adjustment (SLA) process. As the projects become better defined, the O&M estimates may be revised.
Enterprise Funds Capital Improvement Projects
Estimated Operations and Maintenance Costs*
247
Home of Texas A&M University ®
248
Index by Project/Work Order Name
Streets Projects Project # Page Technology Projects Project # Page
BARRON RD EAST/LAKEWAY ST1101 40 E-MAIL AND FILE SYSTEM MIGRATION CO1201 108
BARRON RD WIDENING PHASE II ST1026 38-39 FIBER OPTIC INFRASTRUCTURE CO0902 107
BARRON/SH40 SIGNAL ST1029 46 MDT SYSTEM REPLACEMENT CO0701 105
BIKE LOOP - 2005 ST0530 57 NETWORK & DATA SECURITY UPGRADE CO1202 109
BIRD POND REHAB ST1112 20 WIRELESS INFRASTRUCTURE CO0704 106
COLLEGE MAIN PLAZA IMPROVEMENTS ST1113 66
COLLEGE MAIN REHABILITATION ST1102 68 Drainage Projects Project # Page
COONER STREET RECONSTRUCTION ST1201 22-23 DRAINAGE MASTER PLAN SD1202 120
FM 2154 SIDEWALK IMPROVEMENTS - DESGIN ST1203 69 EMERALD FOREST DRAINAGE IMPROVEMENTS SD1006 116
HEALTH SCIENCE CENTER PARKWAY ST1205 34 FENCE FOR MITIGATION @ ARRINGTON/DECATUR SD0901 119
HIKE AND BIKE TRAIL COMPLETION ST0904 62 GREENWAYS PROJECTS SD9903 114
HIKE AND BIKE TRAIL COMPLETION PHASE II ST1103 63 MINOR DRAINAGE IMPROVEMENTS SD1101 115
HIKE AND BIKE TRAILS - LONGMIRE IMPROVEMENTS ST0521 59 SOUTHWOOD 5-7 DRAINAGE SD1103 194-195
HOLLEMAN EXTENSION ST0913 28-29 STORMWATER MAPPING SD0523 118
JONES BUTLER (PENBERTHY) EXTENSION ST0905 32 WOLF PEN CREEK EROSION CONTROL SD1102 117
KRENEK TAP/TEXAS AVE SIGNAL ST1105 47
LICK CREEK HIKE AND BIKE TRAIL ST1104 64 Parkland Dedication Projects Project # Page
LINCLON SIDEWALK IMPROVEMENTS ST0910 61 CARTERS CROSSING PARK PK1202 131
MISC. BIKE TRAILS - BIKE LOOP ST9803 58 COMMUNITY PARK ZONE B PK1203 145
NEW TRAFFIC SIGNAL PROJECTS (2008 GOB)ST1027 49 COMMUNITY PARK ZONE C PK1204 147
NORTHGATE PEDESTRIAN IMPROVEMENTS AFA ST1117 43 EMERALD FOREST PARK IMPROVEMENTS PK0713 78-79
OVERSIZE PARTICIPATION ST0519 25 NEIGHBORHOOD PARK ZONE 24 PK1205 148
OVERSIZE PARTICIPATION (HOLLEMAN ASSESSMENT) ST1204 26 JOHN CROMPTON PARK PHASE III PK0904 136
ROCK PRAIRIE RD BRIDGE IMPROVEMENTS ST1118 37 RAINWATER HARVESTING CENTRAL PARK PK1013 129
ROCK PRAIRIE RD WEST ROW ST1025 36 SOUTHWEST PARK DEVELOPMENT PK0806 134
ROCK PRAIRIE RD EAST WIDENING - DESIGN AND ROW ST0417 35 SOUTHWOOD VALLEY IMPROVEMENTS PK1117 146
ROYDER ROAD IMPROVEMENTS ST1037 33 UNIVERSITY PARK - PHASE II PK0410 80-81
SH30/COPPERFIELD SIGNAL ST1106 51 ZONE 1 PARK PK0051 126
SIDEWALK IMPROVEMENTS (2008 GOB)ST1028 60 ZONE 2 PARK PK0052 127
SIGNAL @ GB DRIVE EAST & DOMINIK ST0205 48 ZONE 3 PARK PK0053 128
SIGNAL WARRANT STUDY ST1107 52 ZONE 4 PARK PK0054 130
TAUBER AND STASNEY REHAB/NG SIDEWALKS ST0505 18-19 ZONE 5 PARK PK0055 132
TRAFFIC SIGNAL COMMUNICATIONS ST0411 55 ZONE 6 PARK PK0056 133
TRAFFIC SYSTEM SAFETY IMPR.ST0511 45 ZONE 7 PARK PK0057 135
UNIVERSITY DR PEDESTRIAN IMPROVEMENTS PH 2-5 ST1206 65 ZONE 8 PARK PK0058 137
UNIVERSITY DR SIDEWALK IMPROVEMENTS - DESIGN ST1202 70 ZONE 9 PARK PK0059 138
UNIVERSITY DR/UNIVERSITY TOWN CTR SIGNAL TBD 54 ZONE 10 PARK PK0060 139
VICTORIA AVENUE EXTENSION ST0903 30-31 ZONE 11 PARK PK0061 140
WELLBORN/F&B SIGNAL ST1031 50 ZONE 12 PARK PK0824 141
WELLBORN RD WIDENING ST0510 42 ZONE 13 PARK PK0807 142
2818/FM 60 SIGNAL ST1207 53 ZONE 14 PARK PK0717 143
ZONE 15 PARK PK0808 144
Parks Projects Project # Page
BEACHY CENTRAL PARK IMPROVEMENTS PK1001 87 Water Projects Work Order # Page
CREEK VIEW NEIGHBORHOOD PARK PK0906 75 AREA 2 WATER LINE EXTENSION TBD 189
EAST DISTRICT MAINTENANCE SHOP REPLACEMENT PK1101 90 BARRON ROAD WATER SERVICE EXT WF0379197 181
EMERALD FOREST PARK IMPROVEMENTS PK0713 78-79 BARRON ROAD WIDENING PH II WF1332871 38-39
FIELD REDEVELOPMENT PK0300 74 CARTERS CREEK LAB AND SCADA BUILDING WF1352985 236-237
GEORGIE K. FITCH PARK IMPROVEMENTS PK1104 93 COB RAYMOND STOTZER PH I WATER LINE WF1440674 183
LICK CREEK NATURE CENTER PK1102 91 COLLEGE HEIGHTS UTILITY REHAB TBD 198-199
LICK CREEK PARK IRON BRIDGE TRAIL COMPLETION PK1201 88 COOLING TOWER EXPANSION WF1440344 166
LINCOLN CENTER ADDITION TBD 89 COOLING TOWER MEDIA REPLACEMENT WF1343612 167
NEIGHBORHOOD PARK IMPROVEMENTS PK0910 76 COONER STREET RECONSTRUCTION WF1440709 22-23
NEIGHBORHOOD PARKS REVOLVING FUND PK0912 86 EASTGATE REHAB TBD 196-197
SANDSTONE PARK SHADE COVER PK1108 82 FM 2818/JONES-BUTLER WATER LINE CONFLICT WF1272122 187
SKATE PARK PK0911 85 HIGH SERVICE WATER PUMP IMPROVEMENTS WF1223117 164
THOMAS PARK SHADE COVER PK1112 83 HOLLEMAN EXTENSION WF1254634 28-29
UNIVERSITY PARK - PHASE II PK0410 80-81 LAND ACQUISITION - WELLS WF0377324 159
WOOD CREEK PARK IMPROVEMENTS PK1114 84 MCCULLOUGH UTILITY REHAB TBD 200-201
OVERSIZED PARTICIPATION WF1366201 178
Facility Projects Project # Page PATRICIA STREET WATER LINE WF1246445 186
FIRE EMERGENCY RESPONSE ALERTING SYSTEM GG1201 102 PLANTATION OAKS WATER LINE REHAB WF1433732 202
FIRE STATION #6 GG0903 101 RAYMOND STOTZER WEST WATER LINE WF1111167 182
LARRY J. RINGER LIBRARY EXPANSION GG1010 103 SCADA MAN MACHINE INTERFACE WF1442533 174
LIBRARY BOOK DONATIONS GG9901 99 SH 40 WATER LINE- BARRON RD TO GRAHAM RD TBD 184
NORTHGATE IMPROVEMENTS GG0803 100 SH 40 WATER LINE - SONOMA TO VICTORIA TBD 185
SOUTH KNOLL/THE GLADE WF1044480 192-193
SOUTHWOOD 5-7 REHAB WF1105425 194-195
SPPS CHEMICAL SYSTEM REPLACEMENT WF1440357 163
TAUBER AND STASNEY REHAB WF0625888 18-19
249
Index by Project/Work Order Name
Water Projects (con't)Work Order # Page
UTILITY SERVICE CENTER RENOVATIONS WF1441516 172-173
VICTORIA AVENUE EXTENSION WF1158553 30-31
VILLA MARIA/FM 2818 WATER TRANS LINE CONFLICT WF1272122 188
WATER RECLAMATION (PHASE I)WF0995711 179
WATER REDUNDANT COMMUNICATIONS WF1440364 176
WATER WELL SOFT STARTERS TBD 171
WELL FIELD COLLECTION SYSTEM LOOP TBD 162
WELL #7 FIBER WF1440359 175
WELL #9 TBD 160
WELL #9 COLLECTION LINE WF1249597 161
WELLBORN WIDENING WF0613546 180
WELLS 1, 2, 3 AND 5 MOTOR CONTROL UPGRADE WF1337893 168
2010 WELL REHAB WF1241047 165
3 MGSR REHABILITATION WF1330166 169
5 MGSR REHABILITATION WF1440688 170
Wastewater Projects Work Order # Page
AGGIE ACRES FIBER OPTIC CONDUIT WF1440367 243
BEE CREEK PARALLEL TRUNK LINE WF1369909 214
CARTERS CREEK ATAD IMPROVEMENTS WF1104547 224
CARTERS CREEK CENTRIFUGE IMP TBD 226
CARTERS CREEK DIGESTED SLUDGE AERATOR REPL WF1441829 232
CARTERS CREEK ELECTRICAL IMPROVEMENTS TBD 242
CARTERS CREEK FIBER RING WF1440366 241
CARTERS CREEK HEADWORKS IMP WF1223116 220
CARTERS CREEK LAB AND SCADA BUILDING WF1129844 236-237
CC TREATMENT STRUCTURE COATINGS REPLACEMENT TBD 228
COLLEGE HEIGHTS UTILITY REHAB TBD 198-199
COONER STREET RECONSTRUCTION WF1440708 22-23
EASTGATE REHAB TBD 196-197
EAST SIDE FM 158 SEWER SERVICE WF1382208 210
EMERALD PKWY / BENT OAK WF0626151 217
FM 2154 SEWER TRUNK LINE WF1369908 215
LICK CREEK CAPACITY EXPANSION TBD 230
LICK CREEK CENTRIFUGE IMPROVEMENTS WF1142617 222
LICK CREEK CENTRIFUGE REPLACEMENT WF1433858 231
LICK CREEK CLARIFIER CATWALKS WF1042497 221
LICK CREEK DIGESTION FACILITY TBD 229
LICK CREEK PARALLEL TRUNKLINE - PH I WF0912284 212
LICK CREEK PROCESS CONTROL IMPROVEMENTS WF1142624 238
LICK CREEK RETURN ACTIVATED SLUDGE IMP WF1142623 225
LICK CREEK SLUDGE BLOWER REPLACEMENT WF1440712 227
LICK CREEK SLUDGE HOLDING TANK IMPROVEMENTS WF1142618 223
LIFT STATION FORCE MAIN REHABILITATION TBD 233
MCCULLOUGH UTILITY REHAB TBD 200-201
NANTUCKET GRAVITY SEWER LINE WF1094676 211
NORTHEAST TRUNKLINE REHABILITATION WF1440716 218
OVERSIZE PARTICIPATION TBD 209
REMOTE PLANT SECURITY WF1219655 240
SCADA - NEW LIFT STATIONS WF1359125 239
SCADA REPLACEMENT WF0742950 234
SCOTT & WHITE LIFT STATION WF1338390 213
SOUTH KNOLL / THE GLADE WF10444485 192-193
SOUTHWOOD 5-7 WF1105424 194-195
TAUBER & STASNEY REHAB WF0625893 18-19
UTILITY SERVICE CENTER RENOVATIONS WF1441517 172-173
VICTORIA AVENUE EXTENSION WF1158560 30-31
250
Index by Project/Work Order Number
Project # Streets Projects Page Project # Technology Projects Page
ST0205 SIGNAL @ GB DRIVE EAST & DOMINIK 48 CO0701 MDT SYSTEM REPLACEMENT 105
ST0411 TRAFFIC SIGNAL COMMUNICATIONS 55 CO0704 WIRELESS INFRASTRUCTURE 106
ST0417 ROCK PRAIRIE RD EAST WIDENING - DESIGN AND ROW 35 CO0902 FIBER OPTIC INFRASTRUCTURE 107
ST0505 TAUBER AND STASNEY REHAB/NG SIDEWALKS 18-19 CO1201 E-MAIL AND FILE SYSTEM MIGRATION 108
ST0510 WELLBORN RD WIDENING 42 CO1202 NETWORK & DATA SECURITY UPGRADE 109
ST0511 TRAFFIC SYSTEM SAFETY IMPR.45
ST0519 OVERSIZE PARTICIPATION 25 Project # Drainage Projects Page
ST0521 HIKE AND BIKE TRAILS - LONGMIRE IMPROVEMENTS 59 SD0523 STORMWATER MAPPING 118
ST0530 BIKE LOOP - 2005 57 SD0901 FENCE FOR MITIGATION @ ARRINGTON/DECATUR 119
ST0903 VICTORIA AVENUE EXTENSION 30-31 SD1006 EMERALD FOREST DRAINAGE IMPROVEMENTS 116
ST0904 HIKE AND BIKE TRAIL COMPLETION 62 SD1101 MINOR DRAINAGE IMPROVEMENTS 115
ST0905 JONES BUTLER (PENBERTHY) EXTENSION 32 SD1102 WOLF PEN CREEK EROSION CONTROL 117
ST0910 LINCLON SIDEWALK IMPROVEMENTS 61 SD1103 SOUTHWOOD 5-7 DRAINAGE 194-195
ST0913 HOLLEMAN EXTENSION 28-29 SD1202 DRAINAGE MASTER PLAN 120
ST1025 ROCK PRAIRIE RD WEST ROW 36 SD9903 GREENWAYS PROJECTS 114
ST1026 BARRON RD WIDENING PHASE II 38-39
ST1027 NEW TRAFFIC SIGNAL PROJECTS (2008 GOB)49 Project # Parkland Dedication Projects Page
ST1028 SIDEWALK IMPROVEMENTS (2008 GOB)60 PK0051 ZONE 1 PARK 126
ST1029 BARRON/SH40 SIGNAL 46 PK0052 ZONE 2 PARK 127
ST1031 WELLBORN/F&B SIGNAL 50 PK0053 ZONE 3 PARK 128
ST1037 ROYDER ROAD IMPROVEMENTS 33 PK0054 ZONE 4 PARK 130
ST1101 BARRON RD EAST/LAKEWAY 40 PK0055 ZONE 5 PARK 132
ST1102 COLLEGE MAIN REHABILITATION 68 PK0056 ZONE 6 PARK 133
ST1103 HIKE AND BIKE TRAIL COMPLETION PHASE II 63 PK0057 ZONE 7 PARK 135
ST1104 LICK CREEK HIKE AND BIKE TRAIL 64 PK0058 ZONE 8 PARK 137
ST1105 KRENEK TAP/TEXAS AVE SIGNAL 47 PK0059 ZONE 9 PARK 138
ST1106 SH30/COPPERFIELD SIGNAL 51 PK0060 ZONE 10 PARK 139
ST1107 SIGNAL WARRANT STUDY 52 PK0061 ZONE 11 PARK 140
ST1112 BIRD POND REHAB 20 PK0410 UNIVERSITY PARK - PHASE II 80-81
ST1113 COLLEGE MAIN PLAZA IMPROVEMENTS 66 PK0713 EMERALD FOREST PARK IMPROVEMENTS 78-79
ST1117 NORTHGATE PEDESTRIAN IMPROVEMENTS AFA 43 PK0717 ZONE 14 PARK 143
ST1118 ROCK PRAIRIE RD BRIDGE IMPROVEMENTS 37 PK0806 SOUTHWEST PARK DEVELOPMENT 134
ST1201 COONER STREET RECONSTRUCTION 22-23 PK0807 ZONE 13 PARK 142
ST1202 UNIVERSITY DR SIDEWALK IMPROVEMENTS - DESIGN 70 PK0808 ZONE 15 PARK 144
ST1203 FM 2154 SIDEWALK IMPROVEMENTS - DESGIN 69 PK0824 ZONE 12 PARK 141
ST1204 OVERSIZE PARTICIPATION (HOLLEMAN ASSESSMENT) 26 PK0904 JOHN CROMPTON PARK PHASE III 136
ST1205 HEALTH SCIENCE CENTER PARKWAY 34 PK1013 RAINWATER HARVESTING CENTRAL PARK 129
ST1206 UNIVERSITY DR PEDESTRIAN IMPROVEMENTS PH 2-5 65 PK1117 SOUTHWOOD VALLEY IMPROVEMENTS 146
ST1207 2818/FM 60 SIGNAL 53 PK1202 CARTERS CROSSING PARK 131
ST9803 MISC. BIKE TRAILS - BIKE LOOP 58 PK1203 COMMUNITY PARK ZONE B 145
TBD UNIVERSITY DR/UNIVERSITY TOWN CTR SIGNAL 54 PK1204 COMMUNITY PARK ZONE C 147
PK1205 NEIGHBORHOOD PARK ZONE 24 148
Project # Parks Projects Page
PK1001 BEACHY CENTRAL PARK IMPROVEMENTS 87 Work Order # Water Projects Page
PK0906 CREEK VIEW NEIGHBORHOOD PARK 75 WF0377324 LAND ACQUISITION - WELLS 159
PK1101 EAST DISTRICT MAINTENANCE SHOP REPLACEMENT 90 WF0379197 BARRON ROAD WATER SERVICE EXT 181
PK0713 EMERALD FOREST PARK IMPROVEMENTS 78-79 WF0613546 WELLBORN WIDENING 180
PK0300 FIELD REDEVELOPMENT 74 WF0625888 TAUBER AND STASNEY REHAB 18-19
PK1104 GEORGIE K. FITCH PARK IMPROVEMENTS 93 WF0995711 WATER RECLAMATION (PHASE I)179
PK1102 LICK CREEK NATURE CENTER 91 WF1044480 SOUTH KNOLL/THE GLADE 192-193
PK1201 LICK CREEK PARK IRON BRIDGE TRAIL COMPLETION 88 WF1105425 SOUTHWOOD 5-7 REHAB 194-195
TBD LINCOLN CENTER ADDITION 89 WF1111167 RAYMOND STOTZER WEST WATER LINE 182
PK0910 NEIGHBORHOOD PARK IMPROVEMENTS 76 WF1158553 VICTORIA AVENUE EXTENSION 30-31
PK0912 NEIGHBORHOOD PARKS REVOLVING FUND 86 WF1223117 HIGH SERVICE WATER PUMP IMPROVEMENTS 164
PK1108 SANDSTONE PARK SHADE COVER 82 WF1241047 2010 WELL REHAB 165
PK0911 SKATE PARK 85 WF1246445 PATRICIA STREET WATER LINE 186
PK1112 THOMAS PARK SHADE COVER 83 WF1249597 WELL #9 COLLECTION LINE 161
PK0410 UNIVERSITY PARK - PHASE II 80-81 WF1254634 HOLLEMAN EXTENSION 28-29
PK1114 WOOD CREEK PARK IMPROVEMENTS 84 WF1272122 FM 2818/JONES-BUTLER WATER LINE CONFLICT 187
WF1272122 VILLA MARIA/FM 2818 WATER TRANS LINE CONFLICT 188
Project # Facility Projects Page WF1330166 3 MGSR REHABILITATION 169
GG1201 FIRE EMERGENCY RESPONSE ALERTING SYSTEM 102 WF1332871 BARRON ROAD WIDENING PH II 38-39
GG0903 FIRE STATION #6 101 WF1337893 WELLS 1, 2, 3 AND 5 MOTOR CONTROL UPGRADE 168
GG1010 LARRY J. RINGER LIBRARY EXPANSION 103 WF1343612 COOLING TOWER MEDIA REPLACEMENT 167
GG9901 LIBRARY BOOK DONATIONS 99 WF1352985 CARTERS CREEK LAB AND SCADA BUILDING 236-237
GG0803 NORTHGATE IMPROVEMENTS 100 WF1366201 OVERSIZED PARTICIPATION 178
WF1433732 PLANTATION OAKS WATER LINE REHAB 202
WF1440344 COOLING TOWER EXPANSION 166
WF1440357 SPPS CHEMICAL SYSTEM REPLACEMENT 163
WF1440359 WELL #7 FIBER 175
251
Index by Project/Work Order Number
Work Order # Water Projects (con't)Page
WF1440364 WATER REDUNDANT COMMUNICATIONS 176
WF1440674 COB RAYMOND STOTZER PH I WATER LINE 183
WF1440688 5 MGSR REHABILITATION 170
WF1440709 COONER STREET RECONSTRUCTION 22-23
WF1441516 UTILITY SERVICE CENTER RENOVATIONS 172-173
WF1442533 SCADA MAN MACHINE INTERFACE 174
TBD AREA 2 WATER LINE EXTENSION 189
TBD COLLEGE HEIGHTS UTILITY REHAB 198-199
TBD EASTGATE REHAB 196-197
TBD MCCULLOUGH UTILITY REHAB 200-201
TBD SH 40 WATER LINE- BARRON RD TO GRAHAM RD 184
TBD SH 40 WATER LINE - SONOMA TO VICTORIA 185
TBD WATER WELL SOFT STARTERS 171
TBD WELL FIELD COLLECTION SYSTEM LOOP 162
TBD WELL #9 160
Work Order # Wastewater Projects Page
WF0625893 TAUBER & STASNEY REHAB 18-19
WF0626151 EMERALD PKWY / BENT OAK 217
WF0742950 SCADA REPLACEMENT 234
WF0912284 LICK CREEK PARALLEL TRUNKLINE - PH I 212
WF1042497 LICK CREEK CLARIFIER CATWALKS 221
WF10444485 SOUTH KNOLL / THE GLADE 192-193
WF1094676 NANTUCKET GRAVITY SEWER LINE 211
WF1104547 CARTERS CREEK ATAD IMPROVEMENTS 224
WF1105424 SOUTHWOOD 5-7 194-195
WF1129844 CARTERS CREEK LAB AND SCADA BUILDING 236-237
WF1142617 LICK CREEK CENTRIFUGE IMPROVEMENTS 222
WF1142618 LICK CREEK SLUDGE HOLDING TANK IMPROVEMENTS 223
WF1142623 LICK CREEK RETURN ACTIVATED SLUDGE IMP 225
WF1142624 LICK CREEK PROCESS CONTROL IMPROVEMENTS 238
WF1158560 VICTORIA AVENUE EXTENSION 30-31
WF1219655 REMOTE PLANT SECURITY 240
WF1223116 CARTERS CREEK HEADWORKS IMP 220
WF1338390 SCOTT & WHITE LIFT STATION 213
WF1359125 SCADA - NEW LIFT STATIONS 239
WF1369908 FM 2154 SEWER TRUNK LINE 215
WF1369909 BEE CREEK PARALLEL TRUNK LINE 214
WF1382208 EAST SIDE FM 158 SEWER SERVICE 210
WF1433858 LICK CREEK CENTRIFUGE REPLACEMENT 231
WF1440366 CARTERS CREEK FIBER RING 241
WF1440367 AGGIE ACRES FIBER OPTIC CONDUIT 243
WF1440708 COONER STREET RECONSTRUCTION 22-23
WF1440712 LICK CREEK SLUDGE BLOWER REPLACEMENT 227
WF1440716 NORTHEAST TRUNKLINE REHABILITATION 218
WF1441517 UTILITY SERVICE CENTER RENOVATIONS 172-173
WF1441829 CARTERS CREEK DIGESTED SLUDGE AERATOR REPL 232
TBD CARTERS CREEK CENTRIFUGE IMP 226
TBD CARTERS CREEK ELECTRICAL IMPROVEMENTS 242
TBD CC TREATMENT STRUCTURE COATINGS REPLACEMENT 228
TBD COLLEGE HEIGHTS UTILITY REHAB 198-199
TBD EASTGATE REHAB 196-197
TBD LICK CREEK CAPACITY EXPANSION 230
TBD LICK CREEK DIGESTION FACILITY 229
TBD LIFT STATION FORCE MAIN REHABILITATION 233
TBD MCCULLOUGH UTILITY REHAB 200-201
TBD OVERSIZE PARTICIPATION 209
252