HomeMy WebLinkAboutFY 2003-2004 Capital Improvements Program BudgetEmbracing the Past, Exploring the Future. 65th Anniversary Edition Northgate 2003 FY2003-2004 Capital improvement project budget City of College Station, Texas Early Northgate TABLE OF CONTENTS EExxeeccuuttiivvee SSuummmmaarryy..................................................................................................1 GGeenneerraall GGoovveerrnnmmeenntt CCaappiittaall IImmpprroovveemmeenntt PPrroojjeeccttss Streets, Traffic, Sidewalks, and Trails.................................................................5 Street Rehabilitation Projects............................................................11 Street Extension Projects..................................................................21 Street TxDOT Projects......................................................................45 Traffic Projects.................................................................................51 Sidewalks and Trails.........................................................................61 Parks Projects..................................................................................................67 Parkland Dedication.........................................................................................85 General Government Facilities and Technology...............................................107 Public Facilities.................................................................................111 Technology Projects ..........................................................................114 Convention Center.........................................................................................125 Business Park.................................................................................................131 Wolf Pen Creek TIF .......................................................................................138 UUttiilliittyy CCaappiittaall IImmpprroovveemmeenntt PPrroojjeeccttss Utilities Capital Projects Budget .....................................................................145 Electric Service ..............................................................................................147 Water Service.................................................................................................151 Rehabilitation Projects....................................................................156 Production Projects ........................................................................161 Distribution ....................................................................................178 Annexation……………………………………………………………………191 Wastewater Service ........................................................................................201 Rehabilitation Projects…………………………………………………… 206 TABLE OF CONTENTS Collection.......................................................................................216 Treatment ......................................................................................227 Annexation.....................................................................................235 Drainage Utility..............................................................................................243 The following is the annual City of College Station Capital Improvement Project (CIP) Budget document. The CIP budget provides the framework for capital improvement projects to be conducted in the 2004 fiscal year that begins October 1, 2003 and ends on September 30, 2004. Summary capital project schedules have been included in the annual College Station Operating Budget, due to the space limitations within the operating budget document. This CIP budget document permits greater communication among City staff, administration, Council, and citizens regarding capital projects. As in the Fiscal Year 2004 Operating Budget, this FY04 CIP Budget document contains the respective capital schedules. Additionally, areas of enhanced information conveyed within this document include individual project detail pages and corresponding maps where applicable. The project sheets detail the project number, manager, funding source(s), description of purpose and need, funding per year and category, and the impact, if any, on future operating budgets. The maps provide citizens and officials a greater understanding of the scope and the impact of the specific projects through the illustration of the planned action. The City of College Station develops and adopts a five-year Capital Improvements Project List. The list is updated annually and presented for City Council review as a part of the annual budget process. The list consolidates all anticipated capital needs for which funding authorization exists, while separating the projects into several sections depending on the services provided and the respective funding source. Once the budget is approved by the City Council, the assigned project managers manage their respective projects with budgetary oversight from the Office of Budget and Strategic Planning and the Finance Department. CCAAPPIITTAALL PPRROOJJEECCTT FFUUNNDDIINNGG The City operates under the laws of the State of Texas and the City of College Station's Home Rule Charter. The City has legal authority to issue general obligation debt only after a positive vote of the citizens. General Obligation (GO) debt is debt that obligates the City to repay the issue with ad valorem tax revenues. The City uses GO debt for the acquisition and development of parks and recreation facilities, rights-of-way and construction of arterial streets, reconstruction of major arterial streets, and for public buildings such as City offices, libraries, swimming pools and other general use facilities. In November 1998, the citizens of College Station approved a $24.24 million general government bond authorization. Information provided to citizens suggested that the City would issue the debt so as to retain the existing debt service tax rate or its effective equivalent. The current plan is to issue the voter approved debt over five years. This will allow the City to construct the projects included in the bond authorization and meet the goal of maintaining the debt service ad valorem tax rate based on the debt requirement and the increase in taxable property values in College Station. Approximately, $855,000 in General Obligation Bonds will be issued in FY 04 for greenway projects. Existing City Council policies allow the City to continue to utilize other types of debt instruments for items such as computers and the College Station Business Park. Alternative debt instruments are planned for authorized uses and the debt service for those issues is included in the analysis of the appropriate debt service funds. A new five-year general obligation bond election is scheduled for November 2003. If successful, this election will provide additional general obligation bond authority for future projects, which is important to the future of College Station. FFIISSCCAALL YYEEAARR 22000033--22000044 CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTT BBUUDDGGEETT EEXXEECCUUTTIIVVEE SSUUMMMMAARRYY 1 The City has authority, and City Council policies allow for the use of non-voter authorized debt issuance such as certificates of obligation, contract obligations and other instruments (generally referred to as CO's). The policy authorized by the City Council allows the City to use such instruments for capital items such as the following: ¾The purchase and replacement of major computer systems and other technology- based items that have useful lives of not more than 10 years. ¾The purchase and replacement of major equipment items such as fire fighting equipment. The City has developed policies and procedures to provide almost all of this equipment without issuing debt. ¾The purchase of land and development of land for economic development uses. The other type of debt that the City will generally use is revenue bonds. Revenue bonds are issued any time there is a need for financing capital construction or acquisition. It is also used when the asset will reside in one or more of the City's enterprise funds. Generally, revenue bonds do not require voter approval. Utility projects are funded through the issuance of revenue bond which are repaid through the rates of the various utilities and/or through the use of operating revenues generated by the utilities. Other resources to fund capital projects include the Wolf Pen Creek Tax Increment Financing District, the Drainage Utility, and Parkland Dedication Funds. Each will provide resources that will be used to complete a number of projects over the next 5 years. Community Development Block Grant funds are also used to fund capital projects. CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS The Approved Capital Improvements Budget for FY 04 total $35,559,321 for all funds which include capital projects. However, this budget amount does not reflect all projected capital expenditures for FY 04. In the case of projects for which funds have already been approved and budgeted, the city may continue to spend money to complete these projects without including the projected FY 04 expense as a new appropriation. The project budgets that have been appropriated carry forward until the project is complete. Only portions of the projects that have not been appropriated previously are included in the FY 04 Budget. GGEENNEERRAALL CCAAPPIITTAALL PPRROOJJEECCTTSS The following is a brief summary of some of the key general government projects scheduled for FY 04. SSTTRREEEETT RREEHHAABBIILLIITTAATTIIOONN PPRROOJJEECCTTSS In FY 04, $1.2 million is approved for rehabilitation to streets in the Southside area. This is a multi-year effort to rehabilitate the infrastructure in older parts of College Station. Also in FY 04, $500,000 will fund various street rehabilitation projects. $200,000 of this amount will be used to overlay newly annexed streets, and $300,000 will be used to rehabilitate thoroughfare streets within the City. SSTTRREEEETT EEXXTTEENNSSIIOONN PPRROOJJEECCTTSS Street extension projects include $632,404 for completing the widening George Bush Dr. from Texas Avenue to Harvey Road. $722,000 is the anticipated project expense for phase II of the Jones Butler Road project. Additionally, the FY 04 Approved Budget projects $2.2 million for the Longmire Drive extension project, $3.7 million toward the widening of Greens Prairie Road, and $3.4 to for the extension of Dartmouth Drive from Krenek Tap Road to FM 2818. These street projects will help to address traffic issues that have been highlighted in the citizen survey and other feedback received from College Station citizens. SSTTRREEEETT TTxxDDOOTT PPRROOJJEECCTTSS Working in conjunction with the Texas Department of Transportation, in FY 04 the City expects to complete the Texas Avenue Streetscape Phase II and George Bush Dr. Medians. It is anticipated that $580,000 will be used for Texas Avenue Widening Phase II 2 streetscaping, and $175,000 for the George Bush Drive medians. TxDOT timing on these projects will determine when these expenditures will be made. The City pays ten percent of right-of-way costs, and also pays for any enhancements, such as the application of any streetscaping desired in the project. TTRRAAFFFFIICC PPRROOJJEECCTTSS In FY 04, there is no approved new budget appropriation for traffic signal enhancements. However, $72,000 is projected to cover the cost of widening Holleman and the intersection of Holleman and Texas Avenue. SSIIDDEEWWAALLKKSS AANNDD TTRRAAIILLSS PPRROOJJEECCTTSS The City of College Station has worked over the years to ensure adequate transportation infrastructure for pedestrians and bicyclists. The City has an adopted sidewalk and bike loop plan. As new development occurs, sidewalks are an important aspect that must be considered. In FY 04, $75,000 for neighborhood capital improvements is approved. The Anderson sidewalk project and the Longmire sidewalk project are expected to be completed in FY 04. PPAARRKKSS CCAAPPIITTAALL PPRROOJJEECCTTSS The most significant parks projects for FY 04 are improvements to the Lincoln Center. The FY 04 budget includes $623,000 to expand the Lincoln Center and $350,000 to add a covered multi-use pavilion to the facilities for basketball and other recreational activities. These projects are part of the implementation of Tarrow Park Master Plan which the City Council approved earlier in 2003. PPAARRKKLLAANNDD DDEEDDIICCAATTIIOONN CCAAPPIITTAALL PPRROOJJEECCTTSS Parkland dedication funds can be used for projects in neighborhood parks within the various park zones. The funds come from a dedication required as new development occurs in College Station. In FY 04, projects anticipated to use parkland dedication funds include $700,000 for Woodway Park development, $175,000 for a park in Zone 5. GGEENNEERRAALL GGOOVVEERRNNMMEENNTT AANNDD CCAAPPIITTAALL EEQQUUIIPPMMEENNTT CCAAPPIITTAALL PPRROOJJEECCTTSS General government and capital equipment projects are planned assets that have value to more than one specific area of City operations. Two main divisions within this category are public facilities and technology projects. In FY 04, significant projects include: $1,255,780 for construction of Fire Station #5; $917,000 to replace the City's phone system, $200,000 to complete the fiber loop, and $100,000 to begin setting aside funds for a topographic/aerial map. Other technology related projects approved for FY 04 include the completion of the replacement of the public safety computer system, as well as the addition of several other public safety technology projects. These include a police booking system, a police field reporting system, and a fire tone out system. CCOONNFFEERREENNCCEE CCEENNTTEERR CCAAPPIITTAALL PPRROOJJEECCTTSS In FY 04, $12,108,750 is the anticipated Conference Center project expense. This project entails the construction of a conference center facility in conjunction with the development of a full service hotel. An additional $1.1 million is projected to cover the cost of associated utility infrastructure.Since this budget was prepared, the proposed conference center was halted and will not be constructed at the proposed site with the proposed partner. The City Council is currently considering options on this matter. BBUUSSIINNEESSSS PPAARRKK PPRROOJJEECCTTSS In FY 04, there are two significant business park related projects. These include $2,320,000 for the construction of the Spring Creek Corporate Campus Phase I and $415,000 for development of a new class B business center. An additional $250,000 is also included in the approved budget for costs associated with the existing business park. These include reimbursement for a fence being built, and funds for minor improvements in the existing business park facility. Additional information will be provided to the City Council as a competitive manner. 3 UUTTIILLIITTYY CCAAPPIITTAALL PPRROOJJEECCTTSS The following is a brief summary of some of the utility capital projects scheduled for FY 04. These capital projects are funded either through existing revenues from these funds, through the issuance of Utility Revenue Bonds, or through drainage utility funds. EELLEECCTTRRIICC CCAAPPIITTAALL PPRROOJJEECCTTSS $5,530,000 is the approved expenditure amount for electric capital projects in FY 04. Additional information will be provided to the City Council as a competitive matter. WWAATTEERR CCAAPPIITTAALL PPRROOJJEECCTTSS In FY 04, $14,769,051 is the projected expenditure for water capital projects. Included in the Approved FY 04 Budget is over $1 million for water line rehabilitation in the Southside area, $3.2 million for the parallel water line transmission project, and $462,900 on projects to provide water to newly annexed portions of the City. Additionally, $4,174,837 is the projected expense for water capital project to provide water service to City residents not currently using College Station water. The Water Capital Projects Fund also includes $305,000 to improve the security of the water supply and $530,000 to provide backup power generation to the water system. The Approved FY 04 Budget also includes $10,400,000 in current revenues from operations, which are approved to fund water capital projects. No debt is projected for issuance in FY 04 for water capital projects. WWAASSTTEEWWAATTEERR CCAAPPIITTAALL PPRROOJJEECCTTSS The FY 04 includes $7,343,720 in projected expenditures for numerous wastewater capital projects. $1.5 million is included for the rehabilitation of wastewater infrastructure in the Southside area. Over $1 million is also included as projected expense for relocating and rehabilitating sewer line beneath Texas Avenue. This project is necessary because of the TxDoT widening of Texas Avenue, and will be done in conjunction with this project. As in the Water Division, the Wastewater Division includes $330,000 to improve security of wastewater facilities and $215,000 for backup power generation to operate the sewer system in the event of a power outage. $535,800 is included to provide sewer services to the newly annexed parts of town. DDRRAAIINNAAGGEE CCAAPPIITTAALL PPRROOJJEECCTTSS The Approved FY 04 drainage capital projects budget includes $ 5,172,056 in improvement to the City's drainage system. The bulk of these expenditures will be for drainage channel improvements in the Bee Creek ($3 million) and Wolf Pen Creek ($1 million) areas of town. 4 GGEENNEERRAALL GGOOVVEERRNNMMEENNTT-- SSTTRREEEETT PPRROOJJEECCTTSS CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000033--22000044 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22000088--22000099 5 GENERAL GOVERNMENT STREETS, TRAFFIC, SIDEWALKS, AND TRAILS CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 PROJECT APPROVED PROJECT BUDGET ACTUAL FY 02-03 BUDGET ESTIMATE NUMBER AMOUNT FY 01-02 APPROPRIATIONS FY 02-03 BEGINNING FUND BALANCE: 12,214,522 21,818,544 21,818,544 ADDITIONAL RESOURCES: GENERAL OBLIGATION BONDS 4,501,000 1,693,000 1,693,000 CERTIFICATES OF OBLIGATIONS 8,977,600 750,000 750,000 INTERGOVERNMENTAL 9,761 768,000 470,000 INTRAGOVERNMENTAL 1,254,447 0 148,000 INVESTMENT EARNINGS 702,874 300,000 600,000 OTHER 329,664 75,000 0 SUBTOTAL ADDITIONAL RESOURCES 15,775,346$ 3,586,000$ 3,661,000$ TOTAL RESOURCES AVAILABLE 27,989,868$ 25,479,544$ 25,479,544$ STREET REHABILITATION PROJECTS GRAHAM RD UPGRADE PH II ST0001 1,718,000 1,221,267 0 235,167 2 TARROW ST. SOUTH ST0002 464,000 6,065 0 417,084 * STREET REHAB. ST0003 2,620,500 4,665 780,000 0 3 FIRST & MAPLE STREET REHAB ST0201 789,250 52,855 0 50,000 DOMINIK ST REHAB ST0216 75,000 24,248 0 780,000 SECOND STREET PLAZA ST0030 675,000 575,947 67,982 WEST PARK (SOUTHSIDE) ST0400 1,200,000 0 0 0 COLLEGE PARK/BREEZY HEIGHTS (SOUTHSIDE) 2,500,000 0 0 0 ANNEXATION OVERLAYS ST0401 200,000 0 0 0 THOROUGHFARE REHABILITATIONS ST0402 300,000 0 0 0 CLOSED PROJECTS 1,154,857 84,965 SUBTOTAL 3,039,905$ 780,000$ 1,635,198$ STREET EXTENSION PROJECTS * JONES-BUTLER RD PH II ST0005 2,036,000 2,111 0 583,000 1 GEORGE BUSH E. WIDENING ST9804 2,312,000 136,736 182,000 673,682 GEORGE BUSH EAST EXT. ST9916 1,735,000 855,340 0 33,000 * ROCK PRAIRIE RD REALIGN ST9923 832,000 639,373 0 9,844 * VICTORIA OP ST9928 626,000 28,526 0 0 * BARRON ROAD ROW ST0006 316,000 2,154 0 217,000 LONGMIRE EXT-BIRMINGHAM-GRAHAM ST0007 455,000 19,905 0 200,308 * LONGMIRE EXT-GRAHAM-CYPRESS MEADO ST0100 2,594,000 183,761 0 431,821 GREENS PRAIRIE RD. WIDENING ST0214 4,369,000 121,593 0 500,000 DARTMOUTH EXTENSION PHASE II ST0211 3,600,000 47,921 0 200,000 UNIVERSITY DR. WIDENING DSN ST0213 250,000 0 0 1,000 BARRON ROAD INTERCHANGE ST0212 675,000 0 0 100,000 GREENS PRAIRIE RD/ARRINGTON ST0304 750,000 0 750,000 750,000 CLOSED PROJECTS 0 0 42 SUBTOTAL 2,037,420$ 932,000$ 3,699,697$ STREET TXDOT PROJECTS TX AVE STREETSCAPE PH II ST9915 500,000 0 0 0 GEORGE BUSH DRIVE MEDIANS ST0102 175,000 0 0 0 SUBTOTAL 0$ 0$ 0$ 1 - George Bush Widening includes $600,000 thoroughfare funds and $890,000 GOB. 2 - Tarrow Street funding includes $272,000 from a grant. 3 - Funded through CDBG Funds. * - Indicates projects funded through November 1998 G.O. Bond Authorization 6 GENERAL GOVERNMENT STREETS, TRAFFIC, SIDEWALKS, AND TRAILS CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 APPROVED FY 03-04 BUDGET PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED APPROPRIATION FY 03-04 FY 04-05 FY 05-06 FY 06-07 FY 07-08 FY 08-09 18,441,308 18,441,308 4,007,044 1,693,044 1,648,044 1,603,044 1,558,044 0 0 0 0 0 0 0 0 0 1,200,000 0 0 0 0 0 0 0 0 0 0 0 1,366,395 1,366,395 1,000,000 0 0 0 0 270,000 270,000 120,000 30,000 30,000 30,000 30,000 0 0 0 0 0 0 0 1,636,395$ 1,636,395$ 2,320,000$ 30,000$ 30,000$ 30,000$ 30,000$ 20,077,703.29 20,077,703$ 6,327,044$ 1,723,044$ 1,678,044$ 1,633,044$ 1,588,044$ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 866,395 0000 0 0 00000 0 0 00000 0 1,200,000 1,200,000 0000 0 0 0 2,500,000 0 0 0 0 200,000 200,000 0000 0 300,000 300,000 0000 0 0 0 0 0 0 0 0 1,700,000$ 2,566,395$ 2,500,000$ 0$ 0$ 0$ 0$ 0 722,000 722,000 0 0 0 0 0 632,404 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 150,000 447,000 0 0 0 0 0 200,000 0 0 0 0 0 0 8,100 0 0 0 0 0 0 2,173,760 0 0 0 0 0 0 3,747,000 0 0 0 0 0 0 3,352,000 0 0 0 0 0 0 246,000 0 0 0 0 0 0 575,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0$ 11,806,264$ 1,169,000$ 0$ 0$ 0$ 0$ 0 580,000 0 0 0 0 0 0 175,000 0 0 0 0 0 0$ 755,000$ 0$ 0$ 0$ 0$ 0$ 7 GENERAL GOVERNMENT STREETS, TRAFFIC, SIDEWALKS, AND TRAILS CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 PROJECT APPROVED PROJECT BUDGET ACTUAL FY 02-03 BUDGET ESTIMATE NUMBER AMOUNT FY 01-02 APPROPRIATIONS FY 02-03 TRAFFIC PROJECTS * TRAFFIC MGMT. IMPROVE. ST0011 728,000 0 0 0 TRAFFIC SIGNAL ENHAN. ST9511 3,463,229 0 538,000 57,711 HOLLEMAN WIDENING ST0106 112,000 39,582 0 72,419 JOE ROUTE @ KIMBROUGH ST0210 10,000 3,118 0 6,882 GB EAST DRIVE@DOMINIK ST0205 100,000 17,267 0 92,733 GB EAST EAST @HOLLEMAN ST0206 110,000 12,842 0 97,158 UNIVERSITY HOME DEPOT ST0207 135,000 12,671 0 122,330 HWY 30/6 SIGNAL UPGRADE ST0219 17,496 17,496 0 0 TEXAS AVENUE@MANUEL DRIVE ST0017 100,000 11,225 0 88,775 FIRE PRE-EMPTION SYSTEM ST9810 175,000 83,651 0 22,833 CLOSED PROJECTS 21,344 0 0 SUBTOTAL 219,196$ 538,000$ 560,841$ SIDEWALKS & TRAILS J&D MILLER PARK SIDEWALK/TRAIL ST0200 29,250 62,230 0 0 NEIGHBORHOOD/STREETSCAPE ST9802 54,800 0 0 0 BIKE LOOP ST9409 1,348,000 941 0 0 MISC. BIKE TRAILS ST9803 180,000 0 0 0 TAMU SIDEWALKS ST9924 400,000 665 400,000 260,000 UNIVERSITY SIDEWALKS CD1275 98,500 0 0 85,500 LONGMIRE SIDEWALKS ST0204 207,000 0 0 75,000 ANDERSON SIDEWALKS ST0203 150,000 779 0 100,000 NEIGHBORHOOD CIP ST0012 ANNUAL 27,066 75,000 75,000 EMERALD FOREST HOA ST0218 7,500 CLOSED PROJECTS 0 0 0 SUBTOTAL 91,681$ 475,000$ 603,000$ TRANSFER OUT 0 0 0 OTHER 25,291 0 0 DEAN INTERNATIONAL 318,675 360,000 270,000 DEBT ISSUANCE COSTS 78,000 19,500 19,500 GENERAL & ADMIN. CHARGES 260,000 250,000 250,000 TOTAL EXPENDITURES 6,070,168$ 3,354,500$ 7,038,236$ GAAP 101,156 ENDING FUND BALANCE:21,818,544$ 22,125,044$ 18,441,308$ Notes: * - Indicates projects funded through November 1998 G.O. Bond Authorization 8 GENERAL GOVERNMENT STREETS, TRAFFIC, SIDEWALKS, AND TRAILS CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 APPROVED FY 03-04 BUDGET PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED APPROPRIATION FY 03-04 FY 04-05 FY 05-06 FY 06-07 FY 07-08 FY 08-09 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 72,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0$ 72,000$ 0$ 0$ 0$ 0$ 0$ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 460,000 0 0 0 0 0 0 180,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 49,000 132,000 0 0 0 0 0 0 50,000 0 0 0 0 0 75,000 75,000 75,000 75,000 75,000 75,000 75,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 124,000$ 257,000$ 715,000$ 75,000$ 75,000$ 75,000$ 75,000$ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 264,000 264,000 0 0 0 0 0 0 0 0 0 0 0 0 350,000 350,000 250,000 0 0 0 0 2,438,000$ 16,070,659$ 4,634,000$ 75,000$ 75,000$ 75,000$ 75,000$ 0 17,639,703$ 4,007,044$ 1,693,044$ 1,648,044$ 1,603,044$ 1,558,044$ 1,513,044$ 9 Embracing the Past Exploring the Future SSTTRREEEETT RREEHHAABBIILLIITTAATTIIOONN PPRROOJJEECCTTSS 11 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:First, Maple & Louise St. Rehab $969 PROJECT #:ST-0201 PROJECT MANAGER:Laura Harris FUNDING SOURCE(S):Community Development Block Grant PROJECT DESCRIPTION/JUSTIFICATION: Rehabilitation of inadequate pavement structure and installation of storm drain facilities. Also includes sidewalks if right-of-way allows. STATUS: Construction Contract Awarded 8/28/2003. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 53 $53 2002-03 27 27 2003-04 20 869 889 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 TOTAL $0 $100 $869 $0 $969 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 PROJECT BUDGET: 12 1111 Nor thg a t e Sub s t a t ionNor thg a t e Sub s t a t ionNo r t h g a t e S ew e r R e h a bNo r t h g a t e S ew e r R e h a b Fi r s t and M ap l e S t r e e t R eh ab i l i t a t ionFi r s t and M ap l e S t r e e t R eh ab i l i t a t ion Thoroughfare RehabThoroughfare RehabChurch Avenue RehabilitationChurch Avenue RehabilitationNo r t h g a t e W a t e r P l a n n i n g and R e l o c a t i onNo r t h g a t e W a t e r P l a n n i n g and R e l o c a t i on Bo y e t t S tBo y e t t S tLouise AvLouise AvPatriciaStPatriciaStWel lbornRdNWel lbornRdN 13 PROJECT NAME:West Park (Southside)$1,200 PROJECT #:ST0400 PROJECT MANAGER:Laura Harris FUNDING SOURCE(S):General Obligation Bonds PROJECT DESCRIPTION/JUSTIFICATION: Rehabilitation of streets and drainage infrastructure in the West Park area of Southside. STATUS: RFQ to be issued 10/2003 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003 -04 110 500 5 615 2004-05 10 575 585 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $0 $120 $1,075 $5 $1,200 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 14 West Park (Southside) West Park (Southside) H i g h l a n d s S t H i g h l a n d s S t Mo n t c l a i r A vMo n t c l a i r A v Ma r y em S tMa r y em S tFidelity StFidelity StLutherStLutherStPark PlacePark Place W.A. TARROW PARK W.A. TARROW PARK LUTHER JONES PARK LUTHER JONES PARK 15 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Annexation Overlays $200 PROJECT #:ST0401 PROJECT MANAGER:Mark Smith FUNDING SOURCE(S):General fund PROJECT DESCRIPTION/JUSTIFICATION: Year one of a 5 year plan for additional funding to overlay recent annexed streets. 22 lane miles of streets were added to the street inventory in the 2002 annexation. This project will be ongoing for a period of 5 years. Each year 4.4 lane miles of street will be overlaid to meet city standards and completed in the 5th year. STATUS: Overlay projects will begin in November, 2003. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003 -04 200 0 200 2004-05 00 0 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $0 $0 $200 $0 $200 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services 200 Capital TOTAL $200 $0 PROJECT BUDGET: 16 5555 2222 4444 6666 3333 Greens Prairie RdGreens Prairie RdGreensPrairieRdGreensPrairieRd17 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Thoroughfare Rehabilitation PROJECT BUDGET: $300 PROJECT #:ST0402 PROJECT MANAGER:Mark Smith FUNDING SOURCE(S):General fund PROJECT DESCRIPTION/JUSTIFICATION: Rehabilitation and resurfacing of existing thoroughfares within the City STATUS: Rehab projects will begin in November 2003 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTRUCTION MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003 -04 50 250 0 300 2004-05 00 0 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $0 $50 $250 $0 $300 OPERATING COSTS CATEGORY 1ST F.Y.ANNUAL Personnel Supplies Services 300 Capital TOTAL $300 $0 18 Sh 21Sh 21 T e x a s A v T e x a s A v Fm158 Fm158 Harvey RdHarvey Rd Fm 2 8 1 8 Fm 2 8 1 8 V illa M a ria R dV illa M a ria R dH arvey M i t c h el l P w SH arvey M i t c h el l P w S T e x a s A v S T e x a s A v S GreensPrairieRdGreensPrairieRd29t hSt29t hStWe l l bor nRdWe l l bor nRdU n iv e rsityDrEU n iv e rsityDrEFm 1 5 8 P w Fm 1 5 8 P w G reensPrairieRdG reensPrairieRd19 Embracing the Past Exploring the Future 20 SSTTRREEEETT EEXXTTEENNSSIIOONN PPRROOJJEECCTTSS 21 PROJECT NAME:Jones-Butler Road Phase II $2,036 PROJECT #:ST0005 PROJECT MANAGER:Bob Mosley FUNDING SOURCE(S):1998 G.O. Bond Authorization PROJECT DESCRIPTION/JUSTIFICATION: Jones-Butler Road would be extended south from Holleman Drive to its intersection with FM 2818. The length of the roadway will be approximately 2,600 feet with a 90 foot wide right-of-way. The project will include drainage facilities, sidewalks, and street lighting. This project is needed to provide a north-south route paralleling Wellborn Road. * The numbers submited by the project managers have been changed to reflect the Approved FY 04 Budget. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 279 7 $286 2002-03 306 306 2003 -04 1288 156 1,444 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $279 $313 $1,288 $156 $2,036 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 22 J o n e s B u t l e r R o a d , P h a s e 2 J o n e s B u t l e r R o a d , P h a s e 2 J o n e s - b u t l e r R d J o n e s - b u t l e r R d G r i d i r o n D r G r i d i r o n D r Legacy LnLegacy LnSiennaDrSiennaDr Southland StSouthland StHolleman Dr WHolleman Dr W Sout h w e st P w W Sout h w e st P w W Marion Pugh DrMarion Pugh Dr Harvey M i t c h e l l P w S Harvey M i t c h e l l P w S Wel lbo rn RdWel lbo rn Rd WOODWAY PARK WOODWAY PARK 23 PROJECT NAME:George Bush Dr. East Widening $2,340 PROJECT #:ST-9804 PROJECT MANAGER:Donald E. Harmon, Jr. FUNDING SOURCE(S):1995 Bond Authorization ($822,000) Thoroughfare Rehab ($600,000) Other Street/Traffic Capital (72,000) General Fund ($68,000) WT0001 ($50,000) PROJECT DESCRIPTION/JUSTIFICATION: George Bush Drive East will be widened from Texas Avenue to Dominik Drive. * The numbers submited by the project managers have been changed to reflect the Approved FY 04 Budget. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 694 125 421 1,240 2002-03 300 200 50 550 2003 -04 500 50 550 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $994 $125 $1,121 $100 $2,340 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 24 Eastgate Ph2 rehabEastgate Ph2 rehabEastgate Utility Rehab Phases 4&5Eastgate Utility Rehab Phases 4&5 T e x a s A v w a t e r / s e w e r r e l o c a t e T e x a s A v w a t e r / s e w e r r e l o c a t eTAMU Side walks TAMU Side walks Thoroughfare RehabThoroughfare RehabAnnual Si d e walk Proje ctAnnualSi d e walk Proje ct G eorgeBushDriveEastW id e n i n g G eorgeBushDriveEastW id e n i n gPuryearDrPuryearDr KyleAvKyleAvJames PwJames PwMil n e r D rMil n e r D r Redmond DrRedmond Dr Milliff Rd Milliff Rd Gilchrist Av Gilchrist Av Moss St Moss StBolton AvBolton Av R o s em a r y L n R o s em a r y L n Brooks AvBrooks AvGilchrist AvGilchrist Av G e o r g e B u s h D r E G e o r g e B u s h D r E Foster A v Foster A v University Oaks BlUniversity Oaks Bl T e x a s A v S T e x a s A v S Harvey RdHarvey Rd THOMAS PARK THOMAS PARK Thomas Park Thomas Park 25 PROJECT NAME:Victoria Oversize Participation $894 PROJECT #:ST9928 PROJECT MANAGER:Laura Harris FUNDING SOURCE(S):1998 G.O. Bond Authorization PROJECT DESCRIPTION/JUSTIFICATION: This project will extend Victoria Street from its current termination at Graham Road south to Barron Road. The street will be a major thoroughfare with a 54 foot width in a 70 foot right-of-way and an approximate length of 4,200 feet. A significant drainage structure will be required. Developer participation is anticipated for right-of-way donation with City oversize participation with street width in excess of 39 feet. The street will provide north-south access to a future CSISD school. * The numbers submited by the project managers have been changed to reflect the Approved FY 04 Budge PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 30 1 $31 2002-03 11 2003 -04 150 1 151 2004-05 710 1 711 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $30 $0 $860 $4 $894 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 26 Thoroughfare RehabThoroughfare RehabBarron Road Right-of- Way Barron Road Right-of- Way Rock Praire/Barron resurfaceRock Praire/Barron resurface Graha m Road Phase I Graha m Road Phase I V i c t o r i a e x t e n s i o n / o v e r s i z e p a r t i c i p a t i o n V i c t o r i a e x t e n s i o n / o v e r s i z e p a r t i c i p a t i o nHartford DrHartford Dr R e n e e L n R e n e e L nAster DrAster DrHasselt StHasselt StWe s t f i e l d D rWe s t f i e l d D r S c h a f f e r R d S c h a f f e r R d Oldenburg Ln Oldenburg LnKarten LnKarten LnBrussels DrBrussels Dr Norton L n Norton L n S p r i n g f i e l d D r S p r i n g f i e l d D rHarvest DrHarvest Dr Orchid St Orchid StChesapeakeLnChesapeakeLnRe g a l R owRe g a l R ow E s s e n L p E s s e n L p W illow PondStW illow PondStCrepeM yrtleStCrepeM yrtleStMullins Ct Mullins CtSunM eadow StSunM eadow StTyler CtTyler CtDanvilleLnDanvilleLnWind m e a d ow sD rWind m e a d ow sD rChesapeakeC tChesapeakeC tDres de n L nDresde n L n CoeburnCtCoeburnCtBarron RdBarron Rd Graha m Rd Graha m Rd V i c t o r i a A v V i c t o r i a A v Fm 2154Fm 2154 N e w p o r t L n N e w p o r t L n EDELWEISS PARK EDELWEISS PARK WESTFIELD PARK WESTFIELD PARK 27 PROJECT NAME:Barron Road Right-Of-Way $316 PROJECT #:ST0006 PROJECT MANAGER:Donald E. Harmon, Jr. FUNDING SOURCE(S):1998 G.O. Bond Authorization PROJECT DESCRIPTION/JUSTIFICATION: Barron Road would be upgraded from a two lane rural roadway to a minor arterial road as reflected on the thoroughfare plan. This project would establish an alignment and acquire the necessary right-of-way. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 86 14 2002-03 100 2 102 2003 -04 198 2 200 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $306 $10 $0 $0 $316 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 28 Thoroughfare RehabThoroughfare RehabBarron Road Right-of- Way Barron Road Right-of- Way Rock Praire/Barron resurfaceRock Praire/Barron resurfaceBarron Cut- Off RdBarron Cut- Off Rd R e n e e L n R e n e e L n Norton L n Norton L n O l d e n b u r g L n O l d e n b u r g L n P i c a d i l l y C r P i c a d i l l y C r Buckingham CrBuckingham CrWim b l e d o n C rWim b l e d o n C rDresde n L nDresde n L n Fm2154Fm2154WESTMINSTERWESTMINSTER BALDPRAIRIEBALDPRAIRIE BALDPRAIRIEBALDPRAIRIE EDELWEISSGARTENSEDELWEISSGARTENS NEEDHAMESTATESNEEDHAMESTATES SIMMONSSIMMONS NEEDHAMESTATESNEEDHAMESTATES CASTLEGATECASTLEGATE WESTFIELDVILLAGEPHASE 1WESTFIELDVILLAGEPHASE1 29 PROJECT NAME:Longmire Birmingham to Graham $237 PROJECT #:ST0007 PROJECT MANAGER:Kimberly Carter FUNDING SOURCE(S):Certificates of Obligation PROJECT DESCRIPTION/JUSTIFICATION: Extension of Longmire Drive from Birmingham road to Graham Road. The extension would provide north/south access from Graham road to rock Prairie Road. The extension is currently included in the Thoroughfare Plan as a major collector roadway. The project is planned as a 48 foot wide road within a 60 foot right-of-way with a length of approximately 800 feet. The street will include sidewalks on both sides. * The numbers submited by the project managers have been changed to reflect the Approved FY 04 Budget. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 45 1 $46 2002-03 177 3 3 183 2003 -04 88 2004-05 0 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $177 $56 $0 $4 $237 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 30 L o n gm i r e E x t e n s i o n L o n gm i r e E x t e n s i o nLongmire SidewalksLongmire SidewalksLongmire Sou th Ex tens ion , Phase I & I ILongmire Sou th Ex tens ion , Phase I & I I F r o n t a g e 6 R d W F r o n t a g e 6 R d WLongmi re D rLongmi re D r Graham RdGraham Rd Birmi n g h a m R d Birmi n g h a m R d 31 PROJECT NAME:Longmire Graham to Cypress $2,813 Meadows PROJECT #:ST0100 PROJECT MANAGER:Kimberly Carter FUNDING SOURCE(S):1998 G.O. Bond Authorization PROJECT DESCRIPTION/JUSTIFICATION: This project will connect Longmire from Graham Road to the existing section of Longmire Road in the Oak Brook subdivision north of Barron Road. The project is planned as a 48 foot wide road within a 60 foot right- of-way with a length of approximately 4,200 feet. The street will include sidewalks on both sides. The Longmire South project is currently included in the Thoroughfare plan as a major collector roadway. The roadway is needed to provide a north-south route paralleling the Hwy 6 frontage road. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 2 182 0.8 $185 2002-03 9 50 127 5 191 2003 -04 700 20 1,200 20 1,940 2004-05 7 470 20 497 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $711 $259 $1,797 $46 $2,813 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 32 Longmire Sou th Ex tens ion , Phase I & I ILongmire Sou th Ex tens ion , Phase I & I I L o n gm i r e E x t e n s i o n L o n gm i r e E x t e n s i o n Fron tage 6 Rd WFron tage 6 Rd WFron tage 6 Rd EFron tage 6 Rd E Bridl e G at e Dr Bridl e G at e DrBr id le T ra i ls C tBr id le T ra i ls C t P urp le Mart in C vPurpleMartinCvLorikeetCtLorikeetCtGraham RdGraham Rd E ag l e A vEagleAvLongmi r e DrLongmi r e Dr L o n gm i r e D r L o n gm i r e D r BRIDLEGATEESTATES PH 1 BRIDLEGATEESTATES PH 1 SPRINGBROOK-CYPRESSMEADOWSPRINGBROOK-CYPRESSMEADOW LICK CREEK PHASE1 LICK CREEK PHASE1 LOBALLMEMORIALLOBALLMEMORIAL BELMONT PLACE BELMONT PLACE SPRINGBROOKSPRINGBROOK 33 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Greens Prairie Widening PROJECT BUDGET:$4,369 PROJECT #:ST0214 PROJECT MANAGER:Donald Harmon FUNDING SOURCE(S):Certificates of Obligation PROJECT DESCRIPTION/JUSTIFICATION: This project will widen Greens Prairie Road from 2 lanes to 4 lanes with a median and turn pockets. The project will be coordinated and designed with the intent to dedicate the roadway to TxDOT. The project also includes various utility relocations and replacements. STATUS: Staff is negotiating a professional services contract. * The numbers submited by the project managers have been changed to reflect the Approved FY 04 Budg PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 429 10 439 2003-04 3900 30 3,930 2004-05 0 2005-06 2006-07 0 2007-08 0 2008-09 TOTAL $0 $429 $3,900 $40 $4,369 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel Supplies Services Cpitl 34 SafetyFenceSafetyFenceGreens Prairie Road widening Greens Prairie Road widening RockPrairieW aterLineRockPrairieW aterLineFire Station 5 Fire Station 5 Business Park Phase IIIBusiness Park Phase III Business Park Balance LandscapingBusiness Park Balance Landscaping Spring Creek Corporate Campus Phase I Spring Creek Corporate Campus Phase I St Andrews DrSt Andrews Dr L a k ew a y D r L a k ew a y D r Greens Prairie Rd W Greens Prairie Rd W P e b ble Creek PwPebbleCreekPw Arrington RdArrington RdVentureD rVentureD rG reensPrairieRdW G reensPrairieRdW 35 PROJECT NAME:Dartmouth Extension Phase II $3,600 PROJECT #:ST0211 PROJECT MANAGER:Donald E. Harmon, Jr. FUNDING SOURCE(S):Certificates of Obligation PROJECT DESCRIPTION/JUSTIFICATION: Dartmouth Drive will be extended from Krenek Tap Road to Harvey Mitchell Parkway. * The numbers submited by the project managers have been changed to reflect the Approved FY 04 Budget. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 80 200 10 290 2002-03 90 200 1500 10 1,800 2003 -04 1500 10 1,510 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $170 $400 $3,000 $30 $3,600 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 36 Da r t mout hDr i v e Ex t e n s i o n Phase2Da r t mout hDr i v e Ex t e n s i o n Phase2D a r tm o u t h D r i v e E x t e n s i o n P h a s e 1 D a r tm o u t h D r i v e E x t e n s i o n P h a s e 1 Willia m King Cole Dr Willia m King Cole DrTeal StTeal StKrenek Tap RdKrenek Tap RdHarvey Mitchell P w SHarvey Mitchell P w S CENTRAL PARK CENTRAL PARK CY MILLER PARK CY MILLER PARK LAKEVIEWACRESLAKEVIEWACRES WILLIAMS-WINDER-KINGWILLIAMS-WINDER-KING DARTMOUTHCROSSINGDARTMOUTHCROSSING E&MJONES FARMPLACE E&MJONES FARMPLACE SOUTHWESTCROSSINGSOUTHWESTCROSSING Public Works Public Works Utility Customer Service Utility Customer Service Municipal Court Municipal Court PolicePolice Central Park PavilionCentral Park Pavilion Parks World Headquarters Parks World Headquarters East District Forestry East District Forestry 37 PROJECT NAME:University Drive Sidewalk $98.5 PROJECT #:CD1275 PROJECT MANAGER:Donald E. Harmon, Jr. FUNDING SOURCE(S):Community Development Block Grant PROJECT DESCRIPTION/JUSTIFICATION: A sidewalk will be constructed along the north side of University Drive between Tarrow and Texas. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 13.0 13.0 2002-03 83.5 2.0 85.5 2003 -04 0.0 2004-05 0.0 2005-06 0.0 2006-07 0.0 2007-08 0.0 2008-09 0.0 TOTAL 0.0 13.0 83.5 2.0 98.5 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 38 Univ er sit y Dri v e wi d e ni n g Univ er sit y Dri v e wi d e ni n g ThoroughfareR e h a b ThoroughfareR e h a b SCOTT & WHITE MEMORIAL HOSP & SCOTT & WHITE MEMORIAL HOSP & BRAZOS VALLEY PHYSICIANS BRAZOS VALLEY PHYSICIANS Frontage 6 R d E Frontage 6 R d E F r o n t a g e 6 R d W F r o n t a g e 6 R d W Old Ti RdOld Ti RdPendletonDrPendletonDrBrighton D r Brighton D r Me a d o w b r o o k D r Me a d o w b r o o k D r Rav e nwo o d D rRav e nwo o d D r S i e r r a D r S i e r r a D r As s o c i a t e s A vAs s o c i a t e s A v P ark Me a d owLnP ark Me a d owLnWoodcrest DrWoodcrestDr Offramp6NOfframp6NE O a k Hill DrEOakHillDr P a r kHurstDrP a r kHurstDrUniversit y Dr Universit y Dr S h a d y D r S h a d y D r ParkLandDrParkLandDr B r o c k h a m p to n D rB r o c k h a m p to n D rCre s to nLnCre s to nLnParkRowP lParkRowP l S u mmergl e n D rS u mmergl e n D rForest DrForest Dr M e r r y O a k s D r M e r r y O a k s D r StoneparcDrStoneparcDrS i e r r a C tSierraCt S e r v a lL n S e r v a lL n Copperfield Dr Copperfield Dr Gl e n h a v e nDrGl e n h a v e nDrAccess RdAccess Rd Univ er sit y Dr E Univ er sit y Dr E Fm 1 5 8 Fm 1 5 8 Harvey RdHarvey Rd U n i v e r s ity D rE U n i v e r s ity D rE VETERANS PARK & ATHLETIC COMPL VETERANS PARK & ATHLETIC COMPL RICHARD CARTER PARK RICHARD CARTER PARK 39 PROJECT NAME:Barron Road Interchange $675 PROJECT #:ST0212 PROJECT MANAGER:Donald E. Harmon, Jr. FUNDING SOURCE(S):Certificates of Obligation PROJECT DESCRIPTION/JUSTIFICATION: Design of a grade separation for the intersection of Barron Road and Highway 6. * The numbers submited by the project managers have been changed to reflect the Approved FY 04 Budget. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 0 2002-03 550 10 560 2003 -04 100 15 115 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $650 $0 $25 $675 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 40 Barron Road interchange design Barron Road interchange design F r o n t a g e 6 R d E F r o n t a g e 6 R d E F r o n t a g e 6 R d W F r o n t a g e 6 R d WBarron RdBarron Rd 41 PROJECT NAME:Greens Prairie/Arrington $1,330 Realignment PROJECT #:ST0304 PROJECT MANAGER:Craig Jordan FUNDING SOURCE(S):Certificates of Obligation $750,000 Brazos $80,000 TxDot $150,000 Developer $350,000 PROJECT DESCRIPTION/JUSTIFICATION: Realignment of Greens Prairie Road 2500 feet west of Highway 6 to connect with future Arrington Road which will connect with future Highway 40. The length of Greens Prairie Road to be constructed is 1844 feet and the length of Arrington Road to be constructed is 605 feet. Existing section of Greens Prairie Road to be removed. STATUS: Epsilon Engineering was awarded a $155,203.00 for design of project on August 11, 2003. Design is 30% done as of September 22, 2003. $750,000 will be appropriated in FY 2003, the remainder will be used in 2005. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2001-02 0 2002-03 11 2003-04 100 9 639 2 750 2004-05 146 422 11 579 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $100 $155 $1,061 $14 $1,330 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET 42 Greens Prairie Road widening Greens Prairie Road widening G r e e n s P r a irie / A rri n g t o n R e alig n me n t G r e e n s P r a irie / A rri n g t o n R e alig n me n t Hwy 4 0 Hwy 4 0 F r o n t a g e 6 R d W F r o n t a g e 6 R d W F r o n t a g e 6 R d E F r o n t a g e 6 R d E Arrington RdArrington Rd South O a k s D r South O a k s D r O nra m p 6 N O nra m p 6 N Wh i t e s C r e e k L nWh i t e s C r e e k L n Off r am p 6 NOff r am p 6 NBarnstableH a r b o r BarnstableH a r b o r R a ven stoneLoR a ven stoneLoCricketPassCricketPassGreens Prairie Rd W Greens Prairie Rd W Arrington RdArrington Rd L a k ew a y D r L a k ew a y D r G reensPrairieRdG reensPrairieRdG reensPrairieRdW G reensPrairieRdW PEBBLE HILLS PARK PEBBLE HILLS PARK 43 Embracing the Past Exploring the Future 44 SSTTRREEEETT TTXXDDOOTT PPRROOJJEECCTTSS 45 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Texas Ave. Streetscape Phase II PROJECT BUDGET: $500 PROJECT #:ST9915 PROJECT MANAGER:TBD FUNDING SOURCE(S):Streets CIP Fund PROJECT DESCRIPTION/JUSTIFICATION: This is part of the Texas Avenue Widening Phase II project. This is for the cost of streetscape improvements such as raised medians and streetscape light poles. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003 -04 580 580 2004-05 0 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $0 $0 $580 $0 $580 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 46 MMAAPP NNOOTT AAVVAAIILLAABBLLEE 47 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:George Bush Drive Medians PROJECT BUDGET: $$175 PROJECT #:ST0102 PROJECT MANAGER:Mark Smith FUNDING SOURCE(S):Streets CIP Fund PROJECT DESCRIPTION/JUSTIFICATION: This project is an advanced funding agreement with the Texas Department of Transportation to construction median along George Bush Dr. STATUS: PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 0 2003-04 175 175 2004-05 0 2005-06 2006-07 0 2007-08 0 2008-09 TOTAL $0 $0 $175 $0 $175 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 48 Holleman DrHolleman DrWe l s h A vWe l s h A v Francis DrFrancis Dr A n d e r s o n S t A n d e r s o n S t Dominik DrDominik DrLincoln AvLincoln Av Park Pl a c e Park Pl a c e F o st e r A v F o st e r A v G l a d e S t G l a d e S t D e xt e r D r D e xt e r D r M u n s o n A v M u n s o n A v W altonDrW altonDrSout h w e st P w Sout h w e st P wFront StFront St L e e A v L e e A v Luther StLuther StMarion Pugh DrMarion Pugh DrHensel DrHensel Dr G e o r g e B u s h D r E G e o r g e B u s h D r E Stall i ngsDrStall i ngsDr T a r r o w S t T a r r o w S t E is e n h o w e r S t E is e n h o w e r S t N a g l e S t N a g l e S t H ollem anDrEH ollem anDrEHenselStHenselStPark PlacePark Place G l a d e St G l a d e St T e x a s A v T e x a s A v We l l bo r n R dWe l l bo r n R d G eorgeBushDrG eorgeBushDrUniversity DrUniversity Dr T e x a s A v S T e x a s A v S C o l l e g e A v C o l l e g e A v George Bush Dr W George Bush Dr W 49 Embracing the Past Exploring the Future 50 TTRRAAFFFFIICC PPRROOJJEECCTTSS 51 PROJECT NAME:Signal-G. Bush East/Dominik $133 PROJECT #:ST0205 PROJECT MANAGER:Lee Robinson FUNDING SOURCE(S):GOB 1998 CIP Funds Holding Account Project ST9511 PROJECT DESCRIPTION/JUSTIFICATION: Installation of a new fully actuated traffic signal, Dominik and G. Bush East is presently a four-way stop. Increased traffic through this intersection especially during peak periods of the day warrants a traffic signal. Due to the widening of G Bush East the construction phase of this signal will be delayed until completion of the widening project. STATUS: Signal Designed is completed and all materials delivered. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 $13 $50 63 2003 -04 $50 50 2004-05 0 2005-06 $20 20 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $13 $50 $70 $133 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services $1500 Utilities Capital TOTAL $0 $1,500 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 52 Thomas Pool Renovation Thomas Pool Renovation George Bush East @ Dominik George Bush East @ Dominik Thomas Park Pool Shade Cover Thomas Park Pool Shade Cover Holleman Widening Design Phase IIHolleman Widening Design Phase II Park Place Elevated Water Storage Park Place Elevated Water Storage R edmon d D r R edmon d D r Kyle AvKyle AvMil n e r D rMil n e r D r P u r y e a r D r P u r y e a r D rJame s P wJame s P w M illiffRdM illiffRdV illa g e D r V illa g e D rArmistead StArmistead St R o s e ma r y LnR o s e ma r y LnMoss St Moss St A u r o r a C t A u r o r a C tGilchrist AvGilchrist Av W o lfR unW o lfR unLenertC rLenertC rPark Pla ce Park Pla ce Dominik DrDominik Dr G e o r g e B u s h D r E G e o r g e B u s h D r E F o s t e r A v F o s t e r A v A n d e r s o n S t A n d e r s o n S t Holle m a n D r Holle m a n D r University Oaks BlUniversity Oaks BlSt al l i ngsDrStal l i ngsDrFrancis DrFrancis Dr T e x a s A v S T e x a s A v S Harvey RdHarvey Rd T e x a s A v T e x a s A v George Bush DrGeorge Bush Dr THOMAS PARK THOMAS PARK OAKS PARKOAKS PARK 53 PROJECT NAME:New Signal-G Bush/Holleman $100 PROJECT #:ST0206 PROJECT MANAGER:Lee Robinson FUNDING SOURCE(S):GOB 1998 CIP Funds Holding Account Project ST9511 PROJECT DESCRIPTION/JUSTIFICATION: The extension of G. Bush East from Harvey Rd to Holleman has created a need to accommodate increased vehicular traffic at this intersection. In order to decrease vehicle delays during peak traffic periods of the day a traffic signal is warranted. STATUS: Traffic Signal construction started the week of September 15th, the contractors TLS had 90 days to project. TLS signal contractor has 90 days to complete the project. Road bores or competed drilling of signal pole shafts are scheduled for the first week of October. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $10 $10 2002-03 $40 40 2003 -04 $40 40 2004-05 0 2005-06 $20 20 2006-07 0 2007-08 2008-09 TOTAL $0 $10 $40 $40 $90 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services $1500 Utilities Capital TOTAL $0 $1,500 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 54 New Signal G Bush/Holleman New Signal G Bush/Holleman Holleman Widening Design Phase II Holleman Widening Design Phase II Richards StRichards StSterling StSterling StHolleman Dr EHolleman Dr E G e o r g e B u s h D r E G e o r g e B u s h D r E Holle m a n D r Holle m a n D r L a s s i e L n L a s s i e L n Manuel Dr Manuel Dr Park Pl a c e Park Pl a c e Harvey RdHarvey Rd T e x a s A v S T e x a s A v S POOHS' PARK POOHS' PARK WOLFPENPLAZAWOLFPENPLAZA CULPEPPERPLAZACULPEPPERPLAZA RICHARDSRICHARDS RICHARDSRICHARDS LACOURPH1LACOURPH1 KFOKFO BOARDWALKBOARDWALK WEST WOLF PEN CREEK WEST WOLF PEN CREEK ANDERSONRIDGEANDERSONRIDGE KAPCHINSKI HILL KAPCHINSKI HILL KAPCHINSKIKAPCHINSKI COURTYARDAPARTMENTSCOURTYARDAPARTMENTS POLAR-BEKPOLAR-BEK KIRKPATRIC KKIRKPATRICK HOLLEMANPLACEHOLLEMANPLACE 55 PROJECT NAME:New Signal-Texas/Manuel $115 PROJECT #:ST0017 PROJECT MANAGER:Lee Robinson FUNDING SOURCE(S):GOB 1998 CIP Funds Holding Account-Project ST9511 PROJECT DESCRIPTION/JUSTIFICATION: This location was studied, surveyed and designed two years earlier. Due to the anticipated start date of Texas Widening Phase II the construction was held off. The Texas project is now set to get started in the summer of 2004. This signal will assist with reducing traffic at the Holleman/Texas signal. STATUS: Traffic Signal construction started the week of September 15th, the contractors TLS had 90 days to project. TLS signal contractor has 90 days to complete the project. Road bores or competed drilling of signal pole shafts are scheduled for the first week of October. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $5,000 $5,000 2002-03 $7,600 $42,000 49,600 2003 -04 $60,000 60,000 2004-05 0 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $0 $12,600 $60,000 $42,000 $114,600 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services $1800 Utilities Capital TOTAL $0 $1,800 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 56 T e x a s A v w a t e r / s e w e r r e l o c a t e T e x a s A v w a t e r / s e w e r r e l o c a t e Anderson Street SidewalkAndersonStreetSidewalk LightsLightsPark Benches Park Benches New Signal G Bush/Holleman New Signal G Bush/Holleman Traffic Signal - Texas & Manuel Traffic Signal - Texas & Manuel Holleman Widening Design Phase II Holleman Widening Design Phase II Sterling StSterling StRichards StRichards St Glade S t Glade S t A n d e r s o n S t A n d e r s o n S t Colg a t e C r Colg a t e C r L a u r a L n L a u r a L n P i n e R i d g e D rPineRidgeDr L em o n T r e e L n L em o n T r e e L n Barthelow Dr Barthelow Dr HolikDrHolikDrCedarRunCedarRunArcticArctic Yale CrYale CrAuburnCtAuburnCtPoto ma cPl Poto ma cPl Am herstCtAm herstCtH a rv a rd C rH a rv a rd C rManuel Dr Manuel DrBrentwood DrBrentwood Dr Anderso n S t Anderso n S t Southwest PwSouthwest PwHolleman Dr EHolleman Dr E Holle m a n D r Holle m a n D r T e x a s A v S T e x a s A v S LEMONTREE PARK LEMONTREE PARK BEE CREEK PARK BEE CREEK PARK ARBORETUM PARKARBORETUM PARK WOLF PEN CREEK PARKWOLF PEN CREEK PARK 57 PROJECT NAME:New Signal-University/Home Depot $156 PROJECT #:ST0207 PROJECT MANAGER:Lee Robinson FUNDING SOURCE(S):GOB 1998 CIP Funds Holding Account-Project# ST9511 PROJECT DESCRIPTION/JUSTIFICATION: Warrant Study, intersection survey, design and construction. Economic Development negotiated with Home Depot for signal at the main driveway for safe traffic movements in and out of the shopping center. STATUS: Traffic Signal construction started the week of September 15th, the contractors TLS had 90 days to project. TLS signal contractor has 90 days to complete the project. Road bores or competed drilling of signal pole shafts are scheduled for the first week of October. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 $16 16 2003 -04 $70 $70 140 2004-05 0 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $0 $16 $70 $70 $156 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services $1800 Utilities Capital TOTAL $0 $1,800 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 58 New Signal/Home Depot New Signal/Home Depot Frontage6RdWFrontage6RdWB e r k e l e y S t B e r k e l e y S tWe s t o v e r S tWe s t o v e r S t Carol StCarol StHolt StHolt StFr ont a g e 6 RdEFront a g e 6 RdE Rose CrRose Cr A s h b u r n A v A s h b u r n A v Autum n C r Autum n C r S h a d y D r S h a d y D r Universit y Dr Universit y Dr April Bl o o mApril Bl o o mN e a l P i c k e t t D r N e a l P i c k e t t D r S u m m ergle n D r S u m m ergle n D r M e r r y O a k s D r M e r r y O a k s D rForestDrForestDrValley Oaks DrValley Oaks DrWo o d h a v e n C rWo o d h a v e n C r Lyceum CtLyceum CtOnramp6S Onramp6SFall CrFall Cr O a k h a v e n C r O a k h a v e n C r GrandO a k sCrGrandO a k sCrSer val LnSer val LnN e a l P i c k e t t D r N e a l P i c k e t t D r M e r r y O a k s D r M e r r y O a k s D rLincoln AvLincoln Av M u n s o n A v M u n s o n A v Francis DrFrancis Dr S p ring LoSpringLo Gl e n h a v e n D rGl e n h a v e n D r Dominik DrDominik Dr Old Oaks Dr Old Oaks DrAccessRdAccessRdSCOTT & WHITE MEMORIAL HOSP &SCOTT & WHITE MEMORIAL HOSP & Unive r s i t y D r E Unive r s i t y D r E UNIVERSITY PARK UNIVERSITY PARK RICHARD CARTER PARKRICHARD CARTER PARK PARKWAY PARK PARKWAY PARK 59 Embracing the Past Exploring the Future 60 SSIIDDEEWWAALLKKSS AANNDD TTRRAAIILLSS 61 PROJECT NAME:Longmire Sidewalks PROJECT #:ST0204 PROJECT MANAGER:Kimberly Carter FUNDING SOURCE(S): 1995 G.O. Bond Authorization (Transferred from ST9510 Miscellaneous Sidewalks) PROJECT DESCRIPTION/JUSTIFICATION: Sidewalk and trail improvements along Longmire in conformance with approved master plans. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 0 2002-03 44 2003 -04 200 3 203 2004-05 0 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $0 $0 $200 $7 $207 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 62 L o ngm i r e S t r e e t L i g h t in g L o ngm i r e S t r e e t L i g h t in gBeeCreekChannelPhasesIV&VBeeCre e k Cha n n e lPhasesIV&VLongmireSidewalks LongmireSidewalks Thor o u g hfare Re ha b Thor o u g hfare Re ha bMis c ella neous SidewalksMis c ella neous Sidewalks Todd TrTodd Tr Aust i n A v Aust i n A v Ce l i n d a C rCe l i n d a C r Hills i d e D r Hills i d e D r NormandDrNormandDrMile Dr Mile Dr Morgans Ln Morgans Ln S a n d y C r S a n d y C r Hawk TreeDr Hawk TreeDr SanFelipeDrSanFelipeDrA i r lin e D rA i r lin e D rAdr i enneDrAdr i enneDrHenryCtHenryCt N o rm a n d C r N o rm a n d C r J e nniferDrJ e nniferDrJ e nn i f e r C r J e nn i f e r C r Pi e r r e P lPi e r r e P l H a l e y P l H a l e y P l Adr i enn e C rAdr i enn e C r B ritt a i n C t B ritt a i n C t Amy C tAmy C tBrothers BlBrothers Bl T e x a s A v S T e x a s A v S 63 PROJECT NAME:Anderson Sidewalks $150 PROJECT #:ST0203 PROJECT MANAGER:Kimberly Carter FUNDING SOURCE(S): 1995 G.O. Bond Authorization (Transferred from ST9510 Miscellaneous Sidewalks) PROJECT DESCRIPTION/JUSTIFICATION: Sidewalk and trail improvements along Anderson Road in conformance with approved master plans. * The numbers submited by the project managers have been changed to reflect the Approved FY 04 Budget. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 44 2003 -04 145 1 146 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $145 $5 $150 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 64 Anderson Street SidewalkAndersonStreetSidewalk Miscellane o u s Sid e w a l k s Miscellane o u s Sid e w a l k s G l a d e S t G l a d e S tPine Ridge Dr Pine Ridge Dr H olik Dr H olik Dr L em o n T r e e L n L em o n T r e e L n Barthelow DrBarthelow Dr L a u r a L n L a u r a L n Cedar RunCedar Run ArcticArctic Haines DrHaines Dr B r i g h t C r B r i g h t C r Clement CtClement CtOakdale CrOakdale CrAlpineCrAlpineCrAnderson S t Anderson S t Brentwood DrBrentwood DrSouthwest PwSouthwest Pw Gla d e S t Gla d e S t LemontreeParkRestroomsLemontreeParkRestrooms 65 PROJECT NAME:Neighborhood CIP ANNUAL PROJECT #:ST0012 PROJECT MANAGER:Mark Smith FUNDING SOURCE(S):General Fund PROJECT DESCRIPTION/JUSTIFICATION: Neighborhood CIP is one means of addressing infrastructure needs identified through small area plans and through the neighborhood traffic calming program. Improvements may include traffic calming measures such as speed cushions and landscaped medians. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 27 $27 2002-03 75 75 2003 -04 75 0 75 2004-05 075 75 2005-06 75 75 2006-07 75 75 2007-08 0 2008-09 0 TOTAL $0 $0 $402 $0 $402 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services 0 Capital 75 75 TOTAL $75 $75 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 66 GGEENNEERRAALL GGOOVVEERRNNMMEENNTT-- PPAARRKKSS PPRROOJJEECCTTSS CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000033--22000044 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22000088--22000099 67 GENERAL GOVERNMENT PARKS PROJECTS CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 PROJECT APPROVED PROJECT BUDGET ACTUAL FY 02-03 BUDGET ESTIMATE NUMBER AMOUNT FY 01-02 APPROPRIATION FY 02-03 BEGINNING FUND BALANCE:4,295,406$ 757,978$ 757,978$ ADDITIONAL RESOURCES: GENERAL OBLIGATION BONDS 0$ 0$ 0$ CERTIFICATES OF OBLIGATIONS 129,000 0 0 INTERGOVERNMENTAL 0 80,000 80,000 INTRAGOVERNEMENTAL 89,000 0 0 INVESTMENT EARNINGS 74,057 10,000 25,000 OTHER 67,525 67,000 67,000 SUBTOTAL ADDITIONAL RESOURCES 359,582$ 172,000$ 172,000$ TOTAL RESOURCES AVAILABLE 4,654,988$ 929,978$ 929,978$ PARK PROJECTS BILLIE MADELEY PARK DEV. PK9706 45,000 29,811 0 0 OAKS PARK IMPR. PK0067 28,000 46,562 0 24,068 RAINTREE PARK IMPR. PK0068 44,000 0 0 0 LICK CREEK DEVELOPMENT PK0069 511,000 35,859 80,000 117,000 VETERANS ATHLETIC PARK DEV PK9941 3,236,000 3,012,561 0 37,000 SOUTHWOOD PARK IMPR. PK0076 156,000 0 119,000 69,000 CENTRAL PARK IMPR. PK0101 17,000 0 0 17,000 THOMAS POOL IMPR. PK0104 19,000 0 0 19,000 BEE CREEK LIGHTS PK0303 118,000 0 0 33,000 COMMUNITY PARK ADD LAND PURCH. 40,000 0 0 0 * LINCOLN CENTER EXP TBD 623,000 0 0 0 * LINC. CTR. COVERED BASKETBALL PAVILLION 350,000 0 0 0 FIELD REDEVELOPMENT PK0300 24,000 0 34,400 24,000 CLOSED PROJECTS 716,316 0 0 DEBT ISSUANCE COST 900 0 0 GENERAL & ADMIN. CHARGES 55,000 20,000 20,000 TOTAL EXPENDITURES 3,897,010$ 253,400$ 360,068$ GAAP 0 ENDING FUND BALANCE:757,978$ 676,578$ 569,910$ * - FUNDED THROUGH COMMUNITY DEVELOPMENT BLOCK GRANT 68 GENERAL GOVERNMENT PARKS PROJECTS CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 APPROVED FY 03-04 PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED APPROPRIATIONS FY 03-04 FY 04-05 FY 05-06 FY 06-07 FY 07-08 FY 08-09 569,910$ 569,910$ 24,910$ 26,210$ 27,210$ 28,210$ 29,210$ 0$ 0$ 0$ 0$ 0$ 0$ 0$ 0 0 0 0 0 0 0 0 0 0 0 0 0 0 1,013,000 1,013,000 0 0 0 0 0 15,000 15,000 1,000 1,000 1,000 1,000 1,000 67,000 67,000 68,300 69,700 71,100 72,500 74,000 1,095,000$ 1,095,000$ 69,300$ 70,700$ 72,100$ 73,500$ 75,000$ 1,664,910$ 1,664,910$ 94,210$ 96,910$ 99,310$ 101,710$ 104,210$ 0 5,000 0 0 0 0 0 00000 0 0 0 16,000 0 0 0 0 0 0 394,000 0 0 0 0 0 0 18,000 0 0 0 0 0 00000 0 0 00000 0 0 00000 0 0 0 85,000 0 0 0 0 0 40,000 40,000 0 0 0 0 0 451,294 623,000 0 0 0 0 0 350,000 350,000 0 0 0 0 0 89,000 89,000 68,000 69,700 71,100 72,500 74,000 00000 0 0 00000 0 0 20,000 20,000 0 0 0 0 0 950,294$ 1,640,000$ 68,000$ 69,700$ 71,100$ 72,500$ 74,000$ 714,616$ 24,910$ 26,210$ 27,210$ 28,210$ 29,210$ 30,210$ 69 Embracing the Past Exploring the Future 70 PPAARRKKSS PPRROOJJEECCTTSS 71 PROJECT NAME:Madeley Park Development $45 Addition PROJECT #:PK9706 PROJECT MANAGER:Peter Vanecek FUNDING SOURCE(S):General Obligation Bonds 99 PROJECT DESCRIPTION/JUSTIFICATION: Funding for minimal development of Billie Madeley Park. Status: Project Complete, except for the plaque dedication PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 30 30 2002-03 55 2003-04 0 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $35 $0 $35 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel 33 Supplies 1 1 Services Capital TOTAL $4 $4 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 72 Cooner Street RehabilitationCooner Street Rehabilitation Madeley Park Development Madeley Park DevelopmentRosemary DrRosemary DrSunny LnSunny Ln L o o p S t L o o p S t Chimney Hill DrChimney Hill Dr L am p w i c k C r L am p w i c k C r Arguello D r Arguello D rRosemary DrRosemary Dr BILLIE MADELY PARK BILLIE MADELY PARK 73 PROJECT NAME:Raintree Park Improvements $44 PROJECT #:PK0068 PROJECT MANAGER:Peter Vanecek FUNDING SOURCE(S):General Obligation Bonds 99 PROJECT DESCRIPTION/JUSTIFICATION: Improvements to include installation of a basketball court and playground replacement. The basketball court will not be built until additional land is available to properly place the court. Status: Playground replacement is complete. The use of remaining funds to be determined. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 14 $14 2002-03 0 2003-04 16 16 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $30 $0 $30 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 74 North Forest Park way North Forest Park wayFron tage 6 Rd EFron tage 6 Rd EFron tage 6 Rd WFron tage 6 Rd W S p r i n g C r e e k S p r i n g C r e e k W ildernessD r N W ildernessD r N Ce n t r alPa r k L n Ce n t r alPa r k L n W ild e rn e s sDrSW ild e rn e s sDrSH orseH a v enLnH orseH a v enLnS h a d o w O a k s S h a d o w O a k sRed Hill DrRed Hill DrSumter DrSumter DrAntietam DrAntietam DrA p p o ma tt o xDr A p p o ma tt o xDr C h ippendale S t C h ippendale S t Mo nitorCtMo nitorCtN o rthrup-grum m anRdN o rthrup-grum m anRdRaintree DrRaintree DrNorth Forest P w North Forest P w A p p omattoxDrA p p omattoxDrKrenek Tap RdKrenek Tap Rd CENTRAL PARK CENTRAL PARK RAINTREE PARK RAINTREE PARK EMERALD FOREST PARK EMERALD FOREST PARK 75 PROJECT NAME:Lick Creek Development $511 PROJECT #:PK0069 & PK9952 PROJECT MANAGER:Ric Ploeger FUNDING SOURCE(S):General Obligation Bonds 99 PROJECT DESCRIPTION/JUSTIFICATION: This amount covers approximately half of the development cost of the approved Master Plan. Improvements include: trails, bridges, signage, roadway, and parking. areas, visitors' center and residences. An $80,000 matching grant was received from TPWD for trails and bridges. STATUS: Expected Completion 9/1/03 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 36 $36 2002-03 117 117 2003-04 394 394 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $547 $0 $547 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel $25 $25 Supplies 10 10 Services 5 5 Capital 10 - TOTAL $50 $40 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 76 11111111 14141414 Thoro u g h f a r e R e h a b Thoro u g h f a r e R e h a b Lick Creek Park Development Lick Creek Park Development Lick Creek Archaelogical Study Lick Creek Archaelogical Study Lick Creek Treatment Plant Expansion Lick Creek Treatment Plant Expansion Rock Prairie Rd Rock Prairie Rd LICK CREEK PARK LICK CREEK PARK 77 PROJECT NAME:Veteran's Park $3,236 PROJECT #:PK9941 PROJECT MANAGER:Ric Ploeger FUNDING SOURCE(S):General Obligation Bonds 99 PROJECT DESCRIPTION/JUSTIFICATION: First phase of the 150 acre Veterans Athletic Park. Infrastructure, six (6) soccer fields, and two (2) soft ball fields included in Phase of this athletic complex. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 139 3,016 32 $3,187 2002-03 37 37 2003-04 18 18 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $139 $3,071 $32 $3,242 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel 80$ 80$ Supplies 50 50 Services 40 40 Capital 50 10 TOTAL 220$ 180$ PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 78 Veterans Park Phase I Veterans Park Phase I Old Ti RdOld Ti Rd Ass o c i a t e s Av Ass o c i a t e s Av C o r o p o r a t e Ce n t e r D r C o r o p o r a t e Ce n t e r D r BRAZOS VALLEY PHYSICIANS BRAZOS VALLEY PHYSICIANS Harvey RdHarvey Rd University Dr E University Dr E VETERANS PARK & ATHLETIC COMPL VETERANS PARK & ATHLETIC COMPL 79 PROJECT NAME:Bee Creek Lights $118 PROJECT #:PK0303 PROJECT MANAGER:Ric Ploeger FUNDING SOURCE(S):General Obligation Bonds 99 PROJECT DESCRIPTION/JUSTIFICATION: Replacement of existing wood poles with concrete poles. Existing light fixtures will be replaced. Status: $50,000 in additional funds added from (PK0076 - Southwood Improvements) Expected completion is set for February of 2004. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 825 33 2003-04 85 85 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $8 $110 $0 $118 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services 2 Capital TOTAL $0 $2 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 80 6666 3333 5555 LightsLightsPark Benches Park Benches Municipal CourtMunicipal Court L a n g f o r d S t L a n g f o r d S t ValleyViewDrValleyViewDrL a u r a L n L a u r a L n A irli n e Dr A irli n e Dr A n d e r s o n S t A n d e r s o n S t A n g e l i n a C r A n g e l i n a C r H i l l s ide DrHillsideDrBee Creek DrBee Creek Dr Willia m King Cole Dr Willia m King Cole Dr Glade S t Glade S tCedarRunCedarRun A s h f o r d D r A s h f o r d D r H i l l t o p D r H i l l t o p D r Barthelo w D r Barthelo w D r LancelotC r LancelotC r AugustineCtAugustineCtRayburn Ct Rayburn Ct L ongmire Ct L ongmire Ct Guadalupe D r Guadalupe D r C o ma l C r C o ma l C r P i ne Rid g eDr P i ne Rid g eDr KingAuthurC rKingAuthurC rYaleCrYaleCrPoto ma cPl Poto ma cPl L a w y e r P l L a w y e r P l S o u t h wo o d D r S o u t h wo o d D r Southwest PwSouthwest Pw L o n g mir e D r L o n g mir e D rBrentwood DrBrentwood DrKrenek Tap RdKrenek Tap RdSouthwest P w ESouthwest P w E Anderson S t Anderson S t D a r tm o u t h S t D a r tm o u t h S t T e x a s A v S T e x a s A v S Harvey Mitchell P w SHarvey Mitchell P w S BEE CREEK PARK BEE CREEK PARK ARBORETUM PARK ARBORETUM PARK LEMONTREE PARK LEMONTREE PARK CY MILLER PARK CY MILLER PARK 81 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Lincoln Center Expansion PROJECT BUDGET: $623 PROJECT #:TBD PROJECT MANAGER:Eric Ploeger FUNDING SOURCE(S):Design and construction FY '02 CD Funds PROJECT DESCRIPTION/JUSTIFICATION: Design funded from the FY02 Community Development budget for an exercise room, dressing rooms, and expansion. Remaining funds will move to construction in FY04. STATUS: PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 623 623 2004 -05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $623 $0 $623 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 82 6666 Lincoln Center Expansion Lincoln Center Expansion E l e a n o r S t E l e a n o r S t Edward StEdward StThompson StThompson StAri z o n a S tAri z o n a S tHolleman DrHolleman Dr W.A. TARROW PARK W.A. TARROW PARK Lincoln Center Lincoln Center Lincoln Center Shop Lincoln Center Shop Lincoln Center Shop Old Office Lincoln Center Shop Old Office 83 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Lincoln Center Expansion PROJECT BUDGET: $350 Covered Basketball Pavillion PROJECT #:TBD PROJECT MANAGER:Eric Ploeger FUNDING SOURCE(S):Community Development Block Grant PROJECT DESCRIPTION/JUSTIFICATION: Design funded from FY02 CD budget for Construction of a Basketball Pavillion STATUS: Design to occur in Fiscal Year 2003. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 350 350 2004 -05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $350 $0 $350 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 84 GGEENNEERRAALL GGOOVVEERRNNMMEENNTT-- PPAARRKKLLAANNDD DDEEDDIICCAATTIIOONN CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000033--22000044 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22000088--22000099 85 GENERAL GOVERNMENT PARKLAND DEDICATION CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 PROJECT APPROVED PROJECT BUDGET ACTUAL FY 02-03 BUDGET ESTIMATE NUMBER AMOUNT FY 01-02 APPROPRIATIONS FY 02-03 BEGINNING FUND BALANCE:1,212,527 1,474,927 1,474,927 ADDITIONAL RESOURCES: CONTRIBUTIONS 209,347$ 50,000$ 50,000$ INVESTMENT EARNINGS 94,750 5,000 5,000 TRANSFERS IN 0 0 0 OTHER 0 0 0 SUBTOTAL ADDITIONAL RESOURCES 304,097$ 55,000$ 55,000$ TOTAL RESOURCES AVAILABLE 1,516,624$ 1,529,927$ 1,529,927$ PARKLAND DEDICATION FUND ZONE 1 PARK PK0051 53,000 0 18,000 22,000 NORTHGATE LINEAR PARK TBD 150,000 0 150,000 0 ZONE 2 PARK PK0052 9,219 0 2,000 0 ZONE 3 (WOLF PEN CREEK)PK0053 5,000 0 0 0 INTRGEN BENCHES PK0212 8,162 8,162 0 0 BENCH REPLCMNT PK0214 9,300 5,570 0 0 ZONE 4 PARK PK0054 5,000 0 20,000 0 ZONE 5 PARK TBD 76,842 0 170,000 0 EDELWEISS PARK PK0216 18,000 0 0 18,000 INTRGEN BENCHES TBD 25,000 0 25,000 25,000 SOUTHWOOD PLAYGROUND CVRS TBD 22,000 0 0 22,000 SOUTHWOOD AP SIDEWALKS 0 0 12,000 ZONE 6 PARK PK0056 51,000 336 88,000 0 SOUTH KNOLL JOGGING TRACK TBD 0 0 8,000 BEE CREEK PARK BENCHES TBD 0 0 12,000 ZONE 7 PARK PK0057 400,202 0 0 0 WOODWAY PARK PK9803 710,000 4,000 700,000 0 ZONE 8 PARK PK0058 612 0 0 0 ZONE 9 PARK PK0059 0 0 0 0 ZONE 10 PARK PK0060 175,000 0 111,000 113,000 SHENANDOAH PARK 0 0 0 0 ZONE 11 PARK PK0061 17,000 27,584 0 0 CLOSED PROJECTS 15,197 0 0 TRANSFER PROJECT 120,000 GENERAL & ADMIN. CHARGES 15,000 5,000 5,000 TOTAL EXPENDITURES 195,849$ 1,289,000$ 237,000$ GAAP (701) ENDING FUND BALANCE:1,320,074$ 240,927$ 1,292,927$ 86 GENERAL GOVERNMENT PARKLAND DEDICATION CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 APPROVED FY03-04 BUDGET PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED APPROPRIATIONS FY 03-04 FY 04-05 FY 05-06 FY 06-07 FY 07-08 FY 08-09 1,292,927 1,292,927 39,927 40,927 41,927 42,927 45,927 50,000$ 50,000$ 0$ 0$ 0$ 0$ 0$ 5,000 5,000 1,000 1,000 1,000 3,000 3,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 55,000$ 55,000$ 1,000$ 1,000$ 1,000$ 3,000$ 3,000$ 1,347,927$ 1,347,927$ 40,927$ 41,927$ 42,927$ 45,927$ 48,927$ 0 0 0 0 0 0 0 0 150,000 0 0 0 0 0 118,000 120,000 0 0 0 0 0 5,000 5,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 20,000 0 0 0 0 0 26,000 26,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 90,000 90,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 700,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 175,000 0 0 0 0 0 14,000 17,000 0 0 0 0 0 0 0 0 0 0 0 5,000 5,000 0 0 0 0 0 258,000$ 1,308,000$ 0$ 0$ 0$ 0$ 0$ 1,089,927$ 39,927$ 40,927$ 41,927$ 42,927$ 45,927$ 48,927$ 87 Embracing the Past Exploring the Future 88 PPAARRKKLLAANNDD DDEEDDIICCAATTIIOONN FFUUNNDD 89 PROJECT NAME:Zone 2 Park $9 PROJECT #:PK0052 PROJECT MANAGER:Ric Ploeger FUNDING SOURCE(S):Fund 172: Park Escrow - Zone 2 PROJECT DESCRIPTION/JUSTIFICATION: In accordance with the Park Zone Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 2. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003 -04 120 120 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $120.00 $0 $120 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 90 2222 P u r y e a r D r P u r y e a r D r N im i t z S t N im i t z S t P a s l e r S t P a s l e r S t M il n e r D r M il n e r D rAsh StAsh St New Mai n Dr New Mai n Dr Gilchrist AvGilchrist Av H a rrin g t o n A v H a rrin g t o n A v J a m e s P w J a m e s P wBanks StBanks St A s h b u r n A v A s h b u r n A v Poplar StPoplar StVassar CtVassar Ct T u r n e r S t T u r n e r S t A v e n u e A A v e n u e A Wal t o n D rWal t o n D rLive Oak StLive Oak StPeyton StPeyton St Wellesley Ct Wellesley CtPreston StPreston StBolton AvBolton Av A v e n u e B A v e n u e B C h u r c h i l l S t C h u r c h i l l S t N unn St N unn StColumbus StColumbus StBrooksAvBrooksAvM a c a rt h u r S t M a c a rt h u r S t James PwJames PwMil n e r D rMil n e r D r Bolton AvBolton AvLincoln AvLincoln Av F o s t e r A v F o s t e r A vFrancis DrFrancis Dr W altonDrW altonDrT a r r o w S t T a r r o w S t T e x a s A v T e x a s A vUniversity Dr EUniversity Dr E THOMAS PARK THOMAS PARK LIONS PARK LIONS PARK EASTGATE PARK EASTGATE PARK 91 PROJECT NAME:Zone 3 $5 PROJECT #:PK0053 PROJECT MANAGER:Ric Ploeger FUNDING SOURCE(S):Fund 173: Park Escrow - Zone 3 PROJECT DESCRIPTION/JUSTIFICATION: In accordance with the Park Zone Dedication Ordinance, these funds have been set aside for park improvement renovation projects as identified in Park Zone 3. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003 -04 55 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $0 $5 $5 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel 55 Supplies Services Capital TOTAL $5 $5 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 92 3333 6666 4444 2222 Sterling StSterling St C y p r e s s D r C y p r e s s D rRichards StRichards StFr ont age6RdWFr ont age6RdWAzalea CtAzalea CtCol gateCrColgateCr C a m elliaCtC a m elliaCtCarnation CtCarnation Ct T e a l S t T e a l S t C r e st S t C r e st S t A s h f o r d D r A s h f o r d D r H i c k o r y D r H i c k o r y D rKalanchoeCtKalanchoeCtC r o s s T i mb e rs D rC r o s s T i mb e rs D rYaleCrYaleCrAuburnCtAuburnCtDartmouth StDartmouth StSouthwest P w ESouthwest P w EHolleman Dr EHolleman Dr EKrenek Tap RdKrenek Tap RdColgate DrColgate Dr Manuel Dr Manuel DrBrentwood DrBrentwood DrCornell D rCornell D r C e n t r a l P a r k L n C e n t r a l P a r k L n E a s tm a r k D r E a s tm a r k D r SouthwestPwSouthwestPwT e x a s A v S T e x a s A v S WOLF PEN CREEK PARK WOLF PEN CREEK PARK CENTRAL PARKCENTRAL PARK 93 PROJECT NAME:Zone 4 Park $5 PROJECT #:PK0054 PROJECT MANAGER:Ric Ploeger FUNDING SOURCE(S):Fund 174: Park Escrow - Zone 4 PROJECT DESCRIPTION/JUSTIFICATION: In accordance with the Park Zone Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 4. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003 -04 20 20 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $20 $0 $20 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 94 4444 2222 Old Ti RdOld Ti RdAs s o c i a t e s A vAs s o c i a t e s A vFrontage6 RdEFr ont age6RdEOn r a mp6 NOn r a mp6 NHarvey RdHarvey Rd VETERANS PARK & ATHLETIC COMPL VETERANS PARK & ATHLETIC COMPL 95 PROJECT NAME:Zone 5 $77 PROJECT #:TBD PROJECT MANAGER:Eric Ploeger FUNDING SOURCE(S):Fund 171: Parks Escrow - Zone 5 PROJECT DESCRIPTION/JUSTIFICATION: In accordance with the Park Zone Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 5. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003 -04 26 26 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $26 $0 $26 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 96 5555 6666 8888 10101010 3333 13131313 15151515 9999 Fm 2 1 5 4 Fm 2 1 5 4We l s h A vWe l s h A v DeaconDrDeaconDrL o n g mi r eDr L o n g mi r eDr Graha m Rd Graha m RdBarron RdBarron RdBrothers BlBrothers Bl R i o G r a n d e B l R i o G r a n d e B l V i c t o r i a A v V i c t o r i a A v R o c k P ra irie R d R o c k P ra irie R dSebesta RdSebesta Rd Sout h w e st P w Sout h w e st P w So u th w ood DrSo u th w ood Dr P o n d e ro saDrP o n d e ro saDrEd e l w eis sAvEd e l w eis sAv F o x f i r e D r F o x f i r e D r E m e r a ld P w E m e r a ld P w N ue c esDr N ue c esDr W ood c r e e k D r W ood c r e e k D r B alconesD r B alconesD r GladeS t GladeS t ArnoldR d ArnoldR d B irm in g h a m R d B irm in g h a m R d E a g le A vE a g le A vBarron RdBarron RdRoc k Pr airi e R d Roc k Pr airi e R d T e x a s A v S T e x a s A v S H a rv e y M itc h ellPw SH a rv e y M itc h ellPw S97 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Zone 6 Park PROJECT BUDGET: $51 PROJECT #:PK0056 PROJECT MANAGER:Ric Ploeger FUNDING SOURCE(S):Fund 176: Park Escrow - Zone 6 PROJECT DESCRIPTION/JUSTIFICATION: In accordance with the Park Zone Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 6. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 0.3 $0 2002-03 0 2003 -04 90 90 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $90 $0 $90 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 98 6666 5555 3333 2222 7777 15151515 1111 4444 We l s h A vWe l s h A v Fm 2 1 5 4 Fm 2 1 5 4Deacon DrDeacon DrHolleman DrHolleman Dr Sout h w e st P w Sout h w e st P w Dominik DrDominik DrA n d e rs o n S t A n d e rs o n S t H o ll e m a n D rEH o ll e m a n D rEBrothers BlBrothers Bl R i o G r a n d e B l R i o G r a n d e B lDartmo uth S tDartmo uth S t LutherStW LutherStW FrancisD rFrancisD rSouthwest P w ESouthwest P w E P ark Pla c eParkPlace F o st e r A v F o st e r A v S o u t h w o odD r S o u t h w o odD r G la d e St G la d e St Krenek Tap RdKrenek Tap Rd V i c t o r i a A v V i c t o r i a A v L o ngmireDr L o ngmireDr De xt e r D r De xt e r D r University Oaks BlUniversity Oaks BlLincoln AvLincoln Av Manuel Dr Manuel DrEde l w eissAvEde l w eissAv F r o n t S t F r o n t S t Hollem anD rW Hollem anD rW L e e A v L e e A v Marion Pugh DrMarion Pugh Dr N u e c esDr N u e c esDrHenselDrHenselDr B alconesD r B alconesD r R o c kP ra irie R d R o c kP ra irie R dNDowlingRdNDowlingRdCorne ll D r C or ne ll D r T e x a s A v S T e x a s A v S We l lbo r n RdWe l lbo r n Rd H a r v ey M i t c h e l l P w SHarveyMitchellPwS Harvey RdHarvey Rd T e x a s A v T e x a s A v University DrUniversity Dr G eorgeBushDrG eorgeBushDrGeorge Bush Dr W George Bush Dr W 99 PROJECT NAME:Woodway Park (Zone 7) $710 PROJECT #:PK9803 PROJECT MANAGER:Ric Ploeger FUNDING SOURCE(S):Fund 177: Park Escrow - Zone 7 PROJECT DESCRIPTION/JUSTIFICATION: Neighborhood Park Development in Zone 7 - Woodway Park. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 44 2002-03 0 2003 -04 710 710 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $714 $0 $714 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel 18 Supplies 2 Services 1 Capital 1 TOTAL $0 $22 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 100 7777 6666 15151515 1111 J o n e s - b u t l e r R d J o n e s - b u t l e r R d WoodsmanDrWoodsmanDrG ri d ir o nDrG ri d ir o nDrSiennaDrSiennaDr Legacy LnLegacy Ln Woodw ayDrWoodwayDr Holleman Dr W Holleman Dr WMarion Pugh DrMarion Pugh DrHollem anDrHollem anDrSout h w e st P w W Sout h w e st P w W Marion Pugh DrMarion Pugh DrS o ut h w estPwW S o ut h w estPwW Wel lbo rn RdWel lbo rn Rd W.A. TARROW PARK W.A. TARROW PARK WOODWAY PARK WOODWAY PARK 101 PROJECT NAME:Zone 10 Park / Shenandoah Park $175 PROJECT #:PK0060 PROJECT MANAGER:Ric Ploeger FUNDING SOURCE(S):Fund 180: Park Escrow - Zone 10 PROJECT DESCRIPTION/JUSTIFICATION: In accordance with the Park Zone Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 10. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 113 113 2003-04 0 2004 -05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $113 $0 $113 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel 9 Supplies 1 Services 1 Capital 1 TOTAL $0 $12 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 102 10101010 13131313 99995555 Hwy 4 0 Hwy 4 0 R e n e e L n R e n e e L n Kernstown LnKernstown LnCard in a lL n Card in a lL n S t a rli n g D rS t a rli n g D rFront Royal DrFront Royal DrWi n d fr e e D rWi n d fr e e D r Skyline CtSkyline CtNorfolk CtNorfolk Ct S t o n y C r e e k L n S t o n y C r e e k L n Roanoke CtRoanoke CtChesapeakeLnChesapeakeLnDo v e T rDo v e T rPurpleMartinCvPurpleMartinCv Remington CtRemington CtPortsmouth CtPortsmouth Ct Mullins Ct Mullins CtBaywood LnBaywood LnTyler CtTyler Ct Mullins Lo S Mullins Lo SDanvilleLnDanvilleLnO ri o le C t O ri o le C t StrasburgCr StrasburgCr M alloryCtM alloryCtW i ndm ea d o w sD rW i ndm ea d o w sD rChesapeakeC tChesapeakeC tCoeburnCtCoeburnCtBarron RdBarron Rd N e w p o r t L n N e w p o r t L n D e c a t u r D r D e c a t u r D r L o n gm i r e D r L o n gm i r e D r E a g leAvE a g leAvH u n t e r C r e e k D r H u n t e r C r e e k D rBarron RdBarron Rd SHENANDOAH PARK SHENANDOAH PARK WESTFIELD PARK WESTFIELD PARK 103 PROJECT NAME:Zone 11 Park $17 PROJECT #:PK0061 PROJECT MANAGER:Ric Ploeger FUNDING SOURCE(S):Fund 181: Park Escrow - Zone 11 PROJECT DESCRIPTION/JUSTIFICATION: In accordance with the Park Zone Dedication Ordinance, these funds have been set aside for park improvement and renovation projects as identified in Park Zone 11. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 27 $27 2002-03 0 2003 -04 17 17 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $44 $0 $44 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 104 11111111 14141414 12121212 5555 Rock Prairie Rd Rock Prairie Rd R o y alA d ela d e D rR o y alA d ela d e D rPebb l e C r e e k PwPebb l e C r e e k PwSt Andrews DrSt Andrews Dr 105 Embracing the Past Exploring the Future 106 GGEENNEERRAALL GGOOVVEERRNNMMEENNTT-- FFAACCIILLIITTIIEESS AANNDD TTEECCHHNNOOLLOOGGYY CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000033--22000044 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22000088--22000099 107 GENERAL GOVERNMENT FACILITIES AND TECHNOLOGY CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 PROJECT TOTAL PROJECT BUDGET ACTUAL FY 02-03 BUDGET ESTIMATE NUMBER AMOUNT FY 01- 02 APPROPRIATIONS FY 02-03 BEGINNING FUND BALANCE:4,466,043$ 6,259,450$ 6,259,450$ ADDITIONAL RESOURCES: GENERAL OBLIGATION BONDS 1,030,000$ 2,097,000$ 2,097,000$ CERTIFICATES OF OBLIGATIONS 2,316,800 57,000 0 INTRAGOVERNMENTAL 12,231 0 113,071 CONTRIBUTIONS 0 0 0 INVESTMENT EARNINGS 218,820 75,000 150,000 OTHER 555 0 13,530 SUBTOTAL ADDITIONAL RESOURCES 3,578,406$ 2,229,000$ 2,373,601$ TOTAL RESOURCES AVAILABLE 8,044,449$ 8,488,450$ 8,633,051$ PUBLIC FACILITIES LIBRARY BOOK DONATIONS GG9901 291,348 0 75,000 75,000 * CEMETERY LAND ACQUISITION GG9905 275,000 0 0 275,000 * FIRE STATION # 5 GG0201 1,567,000 1,220 1,317,000 310,000 * CITY CENTER LAND ACQUISITION GG0002 1,560,000 3,200 0 1,651,000 FIRE STATION #1 REHAB. GG0103 677,000 93,522 0 601,000 1 MUNICIPAL COURT/FIRE ADMIN BUILDING GG0100 3,233,069 820,610 113,069 2,396,153 CLOSED PROJECTS 257,963 0 0 SUBTOTAL 1,176,515$ 1,505,069$ 5,308,153$ TECHNOLOGY PROJECTS HUMAN RESOURCES MODULE CO0021 23,033$ 0$ 0$ 23,030$ PUBLIC SAFETY SYSTEM CO0022 800,000 128,480 0 570,000 AFIX FINGERPRINT SOFTWARE CO0023 25,060 0 0 0 POLICE BOOKING TBD 141,000 0 0 0 POLICE FIELD REPORTING TBD 100,000 0 0 0 FIRE TONE OUT SYSTEM CO0401 50,000 0 0 0 RECORDS STORAGE CO0024 326,000 23,066 57,000 50,000 HAND HELD METER READING REPLACEMENT TBD 50,000 0 0 0 2 AS400 ENHANCEMENT CO0100 175,000 7,654 0 0 PARD AUTOMATION TBD 171,000 0 0 100,000 FIBER OPTIC LOOP ME9701 400,000 179,056 0 150,000 PBX (PHONE SYSTEM) REPLACEMENT TBD 917,000 0 0 0 AUTOMATED CUSTOMER SERVICE CO0102 207,000 93,277 0 35,000 RADIO REPLACEMENT TBD 3,400,000 0 0 0 MOBILE DATA TERMINAL REPLACEMENTS TBD 222,000 0 0 0 ADDITIONAL TECHNOLOGY IMPR. TBD 129,000 0 0 0 WEB SITE REDESIGN TBD 60,000 0 0 60,000 2 ATM NETWORK REPLACEMENT TBD 500,000 0 0 0 TOPOGRAPHIC/AERIAL MAPS TBD 630,000 0 0 0 SUBTOTAL 431,533$ 57,000$ 988,030$ DEBT ISSUANCE COSTS 19,200$ 27,300$ 20,000$ TRANSFERS 89,000 0 0 OTHER 13,749 0 0 GENERAL & ADMIN. CHARGES 55,000 60,000 60,000 TOTAL EXPENDITURES 1,784,997$ 1,649,369$ 6,376,183$ GAAP ADJUSTMENT GAAP 2-$ ENDING FUND BALANCE:6,259,450$ 6,839,081$ 2,256,868$ Notes: * - Funded through November 1998 G.O. Bond Authorization 1 - Total project of $3,120,000 to be funded as follows: $1,800,000 Electric Fund, $700,000 Water Fund, $250,000 W W Fund and $370,000 Sanitation Fund. 2 - Proposed to be funded through the issuance of Certificates of Obligation. 108 GENERAL GOVERNMENT FACILITIES AND TECHNOLOGY CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 APPROVED FY 03-04 BUDGET PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED APPROPRIATIONS FY 03-04 FY 04-05 FY 05-06 FY 06-07 FY 07-08 FY 08-09 2,256,868$ 2,256,868$ 51,368$ 368$ 368$ 3,368$ 6,368$ 0$ 0$ 0$ 0$ 0$ 0$ 0$ 0 0 700,000 0 0 200,000 0 1,017,000 1,017,000 415,000 3,720,000 72,000 0 0 0 0 0 0 0 0 0 90,000 90,000 10,000 20,000 3,000 3,000 3,000 0 0 0 0 0 0 0 1,107,000$ 1,107,000$ 1,125,000$ 3,740,000$ 75,000$ 203,000$ 3,000$ 3,363,868$ 3,363,868$ 1,176,368$ 3,740,368$ 75,368$ 206,368$ 9,368$ 000000 0 000000 0 0 1,255,780 0 0 0 0 0 000000 0 000000 0 000000 0 000000 0 -$ 1,255,780$ -$ -$ -$ -$ -$ 0$ 0$ 0$ 0$ 0$ 0$ 0$ 0 100,000 0 0 0 0 0 000000 0 0 141,000 0 0 0 0 0 0 100,000 0 0 0 0 0 0 50,000 0 0 0 0 0 50,000 50,000 41,000 0 0 0 0 0 0 50,000 0 0 0 0 0 0 200,000 0 0 200,000 0 0 71,000 0 0 0 0 0 100,000 200,000 0 0 0 0 0 917,000 917,000 0 0 0 0 0 0 78,000 0 0 0 0 0 0 0 100,000 3,300,000 0 0 0 0 0 0 155,000 72,000 0 0 0 129,000 0 0 0 0 0 000000 0 0 0 500,000 0 0 0 0 100,000 100,000 265,000 265,000 1,167,000$ 1,936,000$ 1,156,000$ 3,720,000$ 72,000$ 200,000$ 0$ 0$ 0$ 0$ 0$ 0$ 0$ 0$ 000000 0 000000 0 120,720 120,720 20,000 20,000 0 0 0 1,287,720$ 3,312,500$ 1,176,000$ 3,740,000$ 72,000$ 200,000$ 0$ 2,076,148$ 51,368$ 368$ 368$ 3,368$ 6,368$ 9,368$ 109 Embracing the Past Exploring the Future 110 PPUUBBLLIICC FFAACCIILLIITTIIEESS 111 PROJECT NAME:Fire Station #5 $1,567 PROJECT #:GG0201 PROJECT MANAGER:Donald Harmon FUNDING SOURCE(S):1998 G.O. Bond Authorization PROJECT DESCRIPTION/JUSTIFICATION: This new fire station will be located and constructed in the southern portion of the City to provide services to a high growth area of the City. The facility is expected to have two equipment bays of 2300 square feet with the balance of the estimated 6,800 square feet for living quarters, training, kitchen, storage, exercise and decontamination areas. The operating costs include an additional engine company to operate the aerial apparatus on a 24hour 7 day per week schedule. STATUS: A site has been acquired. * The numbers submited by the project managers have been changed to reflect the Approved FY 04 Budget. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 177 133 310 2003-04 1,188 68 1,256 2004-05 0 2005-06 2006-07 0 2007-08 0 2008-09 TOTAL $177 $133 $1,188 $68 $1,566 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel 506 506 Supplies 20 20 Services 40 70 Capital 600 TOTAL $1,166 $596 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 112 Fire Station 5 Fire Station 5 Spring Creek Corporate Campus Phase I Spring Creek Corporate Campus Phase I Spearman Dr Spearman Dr Agate DrAgate DrParkview DrParkview Dr F r o n t a g e 6 Rd E F r o n t a g e 6 Rd E Qu a l i t y C rQu a l i t y C rWingedFootDrWingedFootDrS h o alCreek Dr S h o alCreek Dr Frontage 6 R d WFrontage 6 R d WOnyx DrOnyx Dr Berry C r e e k Berry C r e e k Lake wa y DrLakewa y DrLapis CtLapis CtFirestone DrFirestone DrMuirfieldVillageMuirfieldVillageSapphireD r SapphireD r R o c k y M e a d o w s D r R o c k y M e a d o w s D rW oodl a n d R id g e D rWoodl a n d R id g e D r Putter CtPutter CtDriver CtDriver Ct S l i c e C t S l i c e C t O nra m p 6 S O nra m p 6 S Pl um H o llow D r Pl um H o llow D r B o g e y C t B o g e y C t 12thManCr12thManCrC a d d i e C t C a d d i e C t Camar g o C tCamar g o C tSt Andrews DrSt Andrews Dr L a k ew a y D r L a k ew a y D r Pebble Creek Pw Pebble Creek Pw R o y alAd e l a d e D r R o y alAd e l a d e D r VentureD rVentureD rGreens Prairie RdGreens Prairie Rd PEBBLE CREEK PARK PEBBLE CREEK PARK PEBBLE HILLS PARK PEBBLE HILLS PARK 113 TTEECCHHNNOOLLOOGGYY PPRROOJJEECCTTSS 114 PROJECT NAME:Public Safety System $800 PROJECT #:CO0022 PROJECT MANAGER:Olivia W. Burnside FUNDING SOURCE(S):General Government CIP PROJECT DESCRIPTION/JUSTIFICATION: The Public Safety system includes Computer Aided Dispatch, Police Reporting, EMS Reporting, and Fire Reporting. The current Public Safety software is 10 years old, the original vendor is out of business, the city does not have access to the source code, and the software has not been updated in the last 9 years. Data in the database system is not easily accessible by other database systems (not an open architecture), which makes interfacing to this system difficult in the extreme. Ad hoc reporting is cubersome at best. The replacement system should be much more user friendly, allow broader reporting, make ad hoc reporting available to more end users, be upgraded each year to meet state and federal reporting requirements. This project has evolved as staff endeavored to include various parts in a total solution. After going through the process of evaluating responses to an RFP it was determined that no total solution was available and the project was broken into several components. The amount listed above includes Fire, EMS and Police records management systems as well as a computer aided dispatch (CAD) system. STATUS:Proposals to the RFP were received and evaluated. Benchmarking was done with the top three vendors, with only one passing the benchmark testing. The Fire Dept has implemented a solution. The implementation of an upgrade to the Police and CAD systems is under way. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 130 130 2002-03 570 570 2003 -04 100 100 2004-05 0 2005-06 0 2006-07 0 2007-08 0 TOTAL $0 $0 $0 $800 $800 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services 100 Capital TOTAL $0 $100 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 115 PROJECT NAME:Police Booking $141 PROJECT #:TBD PROJECT MANAGER:Olivia W. Burnside FUNDING SOURCE(S):General Govt. PROJECT DESCRIPTION/JUSTIFICATION: This will automate the booking of detainees in the City's jail facility. It will include live scan of fingerprints thus making it possible to immediately compare detainee fingerprints to those on file. This should speed up the booking process thus allowing officers to return to patrol duty quicker. STATUS: This project has not begun. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 0$0 2002-03 00 2003 -04 141 141 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 TOTAL $0 $0 $0 $141 $141 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services $21 21 Capital TOTAL $21 $21 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 116 PROJECT NAME:Police Field Reporting $100 PROJECT #:TBD PROJECT MANAGER:Olivia W. Burnside FUNDING SOURCE(S):General Govt. PROJECT DESCRIPTION/JUSTIFICATION: This project will allow police officers to fill out report forms electronically as the data is collected. This will mean less time spent in the Police offices filling out reports. STATUS: This project has not begun. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 0$0 2002-03 00 2003 -04 100 100 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $0 $100 $100 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services 15 15 Capital TOTAL $15 $15 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 117 PROJECT NAME:Fire Tone Out System $50 PROJECT #:CO0401 PROJECT MANAGER:Olivia W. Burnside FUNDING SOURCE(S):General Govt. PROJECT DESCRIPTION/JUSTIFICATION: This project will replace the current tone out system which is more than ten years old. The current system does not allow automatic tone out, it requires a person to physically tone out a station on a call. The new system will tone out the Fire Station as soon as a unit is assigned to the call. STATUS: This project has not begun. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 0$0 2002-03 00 2003 -04 50 50 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 TOTAL $0 $0 $0 $50 $50 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services 7.5 7.5 Capital TOTAL $8 $8 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 118 PROJECT NAME:Records Storage $326 PROJECT #:CO0024 PROJECT MANAGER:Olivia W. Burnside FUNDING SOURCE(S):General Government CIP PROJECT DESCRIPTION/JUSTIFICATION: This system provides the city staff a method of centralizing all documents, with proper retention dates, documented security, and a quick method of document retrieval. This reduces the number of copies made because documents can be viewed online. It also reduces the amount of mail sent through the city as well as the amount of storage required. With paper documents no longer retrieved, the citizens should receive responses to requests for city documents much faster, thus providing citizens with quality service. STATUS:The first phase of this project was completed in fiscal year 2000-2001 on time and within budget. Additional in the city, specifically Fiscal Department and Public Utilities Department, implemented imagining in 2003. The project to date is on time and within budget. The amount of the project has been reduced. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 185 $185 2002-03 50 50 2003 -04 50 50 2004-05 41 41 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $0 $326 $326 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel 32 32 Supplies 2.5 2.5 Services 27.6 27.6 Capital TOTAL $62 $62 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 119 PROJECT NAME:PARD Automation $171 PROJECT #:TBD PROJECT MANAGER:Olivia W. Burnside FUNDING SOURCE(S):General Govt PROJECT DESCRIPTION/JUSTIFICATION: This project will provide for the automation of many processes in PARD, such as registration, scheduling of facilities, tracking maintenance. These processes must be automated prior to integrating them with the Automated Customer Service system thought the internet and phone. STATUS: The responses to the RFP are being evaluated at this time. Anticipate system implementation from mid to end of 2003. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 100 100 2003 -04 71 71 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $0 $171 $171 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services 21 21 Capital TOTAL $21 $21 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 120 PROJECT NAME:Fiber Optic Loop $400 PROJECT #:ME9701 PROJECT MANAGER: FUNDING SOURCE(S):$1,100 funded by Electric Utility Revenues $400 funded by General Government PROJECT DESCRIPTION/JUSTIFICATION: Funding is being used to complete a fiber optic infrastructure plan. Previously, the City's data, communication, and traffic systems were fed from a radial fiber optic backbone. A looped, redundant fiber optic backbone is being installed to provide an adequate level of fail safe and appropriate amount of bandwidth. STATUS: The fiber optic loop is complete and the project has moved to connecting outlying facilities and traffic signals. Please transmission over fiber optic has been completed. Fiber optic cable has been in huge demand across the United States. This demand has caused delays in receiving fiber optic cables for up to a year which has caused some delays in the project. The project was reduced by $100,000 in FY 02. $60,000 of the reduction was used to fund the City web site revamp. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 60 1,090 $1,150 2002-03 150 150 2003-04 200 200 2004 -05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 TOTAL $0 $60 $0 $1,440 $1,500 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 121 PROJECT NAME:PBX Phone Replacement $917 PROJECT #:C00400 PROJECT MANAGER:Charlie Shear FUNDING SOURCE(S):Replacement Fund PROJECT DESCRIPTION/JUSTIFICATION: The City's phone system was installed in 1994. It is scheduled for replacement in FY 04. Note: Project costs are based on replacing the phone system with equivalent features. OTIS has been approached by City staff requesting a phone system with additional features. Such an expanded, dynamic system could cost as much as an additional $300,000. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 $50 $867 917 2004 -05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 TOTAL $0 $50 $867 $0 $917 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services $45,000 $45,000 Capital TOTAL $45,000 $45,000 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 122 PROJECT NAME:Automated Customer $207 Service PROJECT #:CO0102 PROJECT MANAGER:Olivia W. Burnside FUNDING SOURCE(S):funded from the Electric Fund PROJECT DESCRIPTION/JUSTIFICATION: This project provides interactive interfaces for citizens to do business with the city through either touch tone phone or internet at any time of the day. STATUS:The first phase of this project was completed in fiscal year 2001-02 when utility bill payment was available by internet and phone. The second phase is to add information and payment of citations to the internet and phone, this should be completed by the end of 2003. The third phase is to integrate requests for building inspections to both internet and phone. This will require participation by the vendor of the building inspection software. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 94 $94 2002-03 35 35 2003 -04 78 78 2004-05 0 2005-06 0 2006-07 0 2007-08 TOTAL $0 $0 $0 $207 $207 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services 38 38 Capital TOTAL $38 $38 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 123 PROJECT NAME:Fiber Optic Loop $400 PROJECT #:ME9701 PROJECT MANAGER: FUNDING SOURCE(S):$1,100 funded by Electric Utility Revenues $400 funded by General Government PROJECT DESCRIPTION/JUSTIFICATION: Funding is being used to complete a fiber optic infrastructure plan. Previously, the City's data, communication, and traffic systems were fed from a radial fiber optic backbone. A looped, redundant fiber optic backbone is being installed to provide an adequate level of fail safe and appropriate amount of bandwidth. STATUS: The fiber optic loop is complete and the project has moved to connecting outlying facilities and traffic signals. Please transmission over fiber optic has been completed. Fiber optic cable has been in huge demand across the United States. This demand has caused delays in receiving fiber optic cables for up to a year which has caused some delays in the project. The project was reduced by $100,000 in FY 02. $60,000 of the reduction was used to fund the City web site revamp. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 60 1,090 $1,150 2002-03 150 150 2003-04 200 200 2004 -05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 TOTAL $0 $60 $0 $1,440 $1,500 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 124 GGEENNEERRAALL GGOOVVEERRNNMMEENNTT-- CCOONNVVEENNTTIIOONN CCEENNTTEERR CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000033--22000044 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22000088--22000099 125 GENERAL GOVERNMENT CONVENTION CENTER CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 PROJECT PROJECT BUDGET ACTUAL FY 02-03 BUDGET ESTIMATE NUMBER AMOUNT FY 01-02 APPROPRIATIONS FY 02-03 BEGINNING FUND BALANCE:9,239,193$ 8,817,029$ 8,817,029$ ADDITIONAL RESOURCES: CERTIFICATES OF OBLIGATION 0$ 11,400,000$ 0$ INTRAGOVERNMENTAL 0 1,100,000 600,000 INVESTMENT EARNINGS 329,134 400,000 300,000 SUBTOTAL ADDITIONAL RESOURCES 329,134$ 12,900,000$ 900,000$ TOTAL RESOURCES AVAILABLE 9,568,327$ 21,717,029$ 9,717,029$ PUBLIC FACILITIES 1 CONFERENCE CNTR HWY 30/60 GG0005 18,000,000 338,434 2,803,038 914,000 2 HWY 30/60 INFRASTRUCTURE GG0105 3,900,000 228,787 0 2,767,000 OTHER 6,549 0 0 DEBT SERVICE 127,529 230,000 230,000 GENERAL & ADMIN CHARGES 50,000 50,000 50,000 TOTAL EXPENDITURES 751,299$ 3,083,038$ 3,961,000$ GAAP 1 ENDING FUND BALANCE:8,817,029$ 18,633,991$ 5,756,029$ 1 - Convention Center funded through $5,500,000 in C.O.s, $500,000 from the Electric Fund, & $600,000 from the Hotel Motel Fund. 2 - Hwy 30/60 Corridor development costs funded through $1,560,000 Electric Fund, $1,690,000 Water Fund, & $400,000 Wastewater Fund. 126 GENERAL GOVERNMENT CONVENTION CENTER CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 APPROVED FY 03-04 BUDGET PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED APPROPRIATIONS FY 03-04 FY 04-05 FY 05-06 FY 06-07 FY 07-08 FY 08-09 5,756,029$ 5,756,029$ 4,893,189$ 300,939$ 306,939$ 312,939$ 318,939$ 11,900,000$ 11,900,000$ 0$ 0$ 0$ 0$ 0$ 250,000 250,000 00000 300,000 300,000 35,000 6,000 6,000 6,000 6,000 12,450,000$ 12,450,000$ 35,000$ 6,000$ 6,000$ 6,000$ 6,000$ 18,206,029$ 18,206,029$ 4,928,189$ 306,939$ 312,939$ 318,939$ 324,939$ 5,805,712 12,108,750 4,627,250 0 0 0 0 0 1,133,000 0 0 0 0 0 0 0 0 0 0 0 0 29,750 29,750 0 0 0 0 0 41,340 41,340 0 0 0 0 0 5,876,802$ 13,312,840$ 4,627,250$ 0$ 0$ 0$ 0$ 12,329,227$ 4,893,189$ 300,939$ 306,939$ 312,939$ 318,939$ 324,939$ 127 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME: 30/60 Corridor Infrastructure PROJECT BUDGET:$3,900 PROJECT #:GG0005 PROJECT MANAGER:Kim Foutz FUNDING SOURCE(S):Electric Fund $1,560,000 Water Fund $1,690,000 Waste Water Fund $400,000 Economic Development Fund $250,000 PROJECT DESCRIPTION/JUSTIFICATION: The project is associated with the development of a hotel and conference center in the Highway 30/60 corridor. The project includes water, waste water, sidewalks, lighting, natural gas, fiber and the extension of Linda Lane to Copperfield Parkway. The utilities will be sized to accommodate development throughout the 30/60 corridor. This project is required as part of the terms of an infrastructure contract entered into among TAC Realty, College Main Ltd., and the City. STATUS: Phase I which includes an 18" water main is complete. Phase IA which includes Copperfield Parkway, water, wastewater, and sidewalks will be awarded by City Council on April 10, 2003. Phase II which includes a cul-de-sac and loop roadways, sidewalks, utilities, and lighting improvements has not yet been bid. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 295 2472 2,767 2003-04 136 997 1,133 2004-05 0 2005-06 2006-07 0 2007-08 0 2008-09 TOTAL $0 $431 $3,469 $0 $3,900 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 128 H w y 3 0/60Infrastructure H w y 3 0/60InfrastructureUniversity Drive widening University Drive widening Veterans Park Phase I Veterans Park Phase I BRAZOS VALLEY PHYSICIANS BRAZOS VALLEY PHYSICIANS Old Ti RdOld Ti RdVista LnVista LnPendletonDrPendletonDrL i n d a L n L i n d a L n Ranchero RdRanchero RdHicks LnHicks LnStoneparcDrStoneparcDrCross Park D r Cross Park D r Fm 1 5 8 Fm 1 5 8 Harvey RdHarvey RdUniversity Dr EUniversity Dr E VETERANS PARK & ATHLETIC COMPL VETERANS PARK & ATHLETIC COMPL 129 GGEENNEERRAALL GGOOVVEERRNNEEMMEENNTT-- BBUUSSIINNEESSSS PPAARRKK CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000033--22000044 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22000088--22000099 130 BBUUSSIINNEESSSS PPAARRKK FFUUNNDD 131 GENERAL GOVERNMENT BUSINESS PARK CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 PROJECT TOTAL PROJECT BUDGET ACTUAL FY 02-03 BUDGET ESTIMATE NUMBER AMOUNT FY 01-02 APPROPRIATIONS FY 02-03 BEGINNING FUND BALANCE:2,435,179$ 2,309,264$ 2,309,264$ ADDITIONAL RESOURCES: CERTIFICATES OF OBLIGATIONS 0$ 3,150,000$ 0$ INTRAGOVERNMENTAL 0 0 0 INVESTMENT EARNINGS 84,138 150,000 70,000 OTHER 74 0 0 SUBTOTAL ADDITIONAL RESOURCES 84,212$ 3,300,000$ 70,000$ TOTAL RESOURCES AVAILABLE 2,519,391$ 5,609,264$ 2,379,264$ BUSINESS PARK FUND BUSINESS PARK PHASE II & III GG9705 2,050,000 56,203 0 0 SPRING CREEK CORPORATE CAMPUS PHASE I DE0001 2,729,000 83,424 225,000 409,000 NEW BUS CENTER B DE0002 2,750,000 0 717,000 0 000 000 000 OTHER 500 0 0 DEBT ISSUANCE COST 15,000 15,000 GENERAL & ADMIN CHARGES 70,000 50,000 50,000 TOTAL EXPENDITURES 210,127$ 1,007,000$ 474,000$ GAAP ENDING FUND BALANCE:2,309,264$ 4,602,264$ 1,905,264$ 132 GENERAL GOVERNMENT BUSINESS PARK CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 APPROVED FY 03-04 BUDGET PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED APPROPRIATIONS FY 03-04 FY 04-05 FY 05-06 FY 06-07 FY 07-08 FY 08-09 2,309,264$ 1,905,264$ 2,165,264$ 360,264$ 390,264$ 420,264$ 450,264$ 3,150,000$ 3,150,000$ 500,000$ 0$ 0$ 0$ 0$ 0 0 0 0 0 0 0 100,000 100,000 30,000 30,000 30,000 30,000 0 0 0 0 0 0 0 0 3,250,000$ 3,250,000$ 530,000$ 30,000$ 30,000$ 30,000$ 0$ 5,559,264$ 5,155,264$ 2,695,264$ 390,264$ 420,264$ 450,264$ 450,264$ 250,000 250,000 0 0 0 0 0 2,320,000 2,320,000 00000 0 415,000 2,335,000 0000 0000000 0000000 0000000 05,00000000 0 00000 00 0 0 0 0 0 2,570,000$ 2,990,000$ 2,335,000$ 0$ 0$ 0$ 0$ 2,989,264$ 2,165,264$ 360,264$ 390,264$ 420,264$ 450,264$ 450,264$ 133 PROJECT NAME:Spring Creek Corp. Campus Ph I $2,729 PROJECT #:DE0001 PROJECT MANAGER:Kim Foutz FUNDING SOURCE(S):Certificates of Obligation of $2.5 million Viatel default payment PROJECT DESCRIPTION/JUSTIFICATION: This project includes acquisition and development of 378 acres (288 useable) for a Class "A" Business Park and associated greenway. Project scope also includes master planning for the site. Construction and engineering costs are for Phase I infrastructure which includes water, wastewater, electric, roadways and other necessary improvements for initial development of the property. STATUS: Acquisition of the 378 acre site is complete. Approximately 110 acres have been transferred to greenways. Master planning is complete. The phase I engineering is scheduled to begin in summer 2003. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 409 409 2003 -04 2320 2,320 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $409 $2,320 $0 $2,729 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 *Initially, annual maintenance will cost approximately $30,000 per year. However, long term, the City will establish a Business Owners Maintenance Organization which will pay fees to maintain the center. CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 134 Spring Creek Corporate Campus PhaseI Spring Creek Corporate Campus PhaseI F r o n t a g e 6 R d E F r o n t a g e 6 R d E Agate DrAgate Dr S pearman Dr S pearman Dr Parkview DrParkview Dr F r o n t a g e 6 R d W F r o n t a g e 6 R d WWingedFootDrWingedFootDrS h o alCreek Dr S h o alCreek DrOldenLnOldenLnO nra m p 6 N O nra m p 6 N OnyxD r OnyxD r Lapis CtLapis Ct Q u a lity CrQualityCr B err y C r e e kB err y C r e e kSapphireDrSapphireDr R o c k y M e a d o w s D r R o c k y M e a d o w s D rWo odl a n d R id g e D rWoodl a n d R id g e D r DriverCtDriverCtS lic e C t S lic e C t 12thManCr12thManCrRock P r a i r i e R d Rock P r a i r i e R d S t Andr ewsDrS t Andr ewsDrL a k ew a y D r L a k ew a y D r Roy a l A d elade D rRoy a l A d elade D rGreens Prairie RdGreens Prairie Rd PEBBLE HILLS PARK PEBBLE HILLS PARK PEBBLE CREEK PARK PEBBLE CREEK PARK 135 PROJECT NAME:New Class "B" Business Cntr. $2,750 PROJECT #:DE0002 PROJECT MANAGER:Kim Foutz FUNDING SOURCE(S):Certificates of Obligation of $2.75 million PROJECT DESCRIPTION/JUSTIFICATION: This project includes engineering and development of an as yet unidentified site for a Class "B" Business Park. Project scope also includes master planning for the site. Construction and engineering costs are for infrastructure which includes water, wastewater, electric, roadways and other necessary improvements for initial development of the property. STATUS: Staff is currently evaluating potential sites. Engineering is scheduled to being in summer 2004. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 415 415 2004-05 $2,335 2,335 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $0 $415 $2,335 $0 $2,750 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 136 MMAAPP NNOOTT AAVVAAIILLAABBLLEE 137 GGEENNEERRAALL GGOOVVEERRNNMMEENNTT-- WWOOLLFF PPEENN CCRREEEEKK TTAAXX IINNCCRREEMMEENNTT FFIINNAANNCCEE DDIISSTTRRIICCTT CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000033--22000044 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22000088--22000099 138 CITY OF COLLEGE STATION WOLF PEN CREEK TIF FUND SUMMARY % CHANGE FY 03 FY 03 FY 04 FY 04 IN BUDGET FY02 REVISED YEAR-END BASE APPROVED FROM FY03 ACTUAL BUDGET ESTIMATE BUDGET BUDGET TO FY 04 BEGINNING BALANCE 1,290,945$ 3,231,563$ 3,231,563$ 2,284,863$ 2,284,863$ REVENUES AD VALOREM TAXES COCS 121,026$ 146,000$ 146,000$ 185,987$ 185,987$ 27.39% AD VALOREM TAXES CSISD 215,216 245,000 245,000 353,000 353,000 44.08% AD VALOREM TAXES BRAZOS CO 93,991 107,000 107,000 154,000 154,000 43.93% INVESTMENT EARNINGS 102,250 60,000 65,000 40,000 40,000 (33.33%) OTHER 0 0 0 0 0 TRANSFERS 120,000 0 0 0 0 PROCEEDS FROM LONG-TERM DEBT 2,316,800 0 0 0 0 N/A TOTAL REVENUES 2,969,283$ 558,000$ 563,000$ 732,987$ 732,987$ 31.36% TOTAL FUNDS AVAILABLE 4,260,228$ 3,789,563$ 3,794,563$ 3,017,850$ 3,017,850$ (20.36%) EXPENDITURES AND TRANSFERS CAPITAL PROJECTS 511,147$ 1,910,000$ 1,016,500$ 1,924,000$ 1,924,000$ 0.73% ENGINEERING (1)0 0 0 150,000 150,000 N/A TRANSFERS (BRIDGE)505,000 0 0 0 0 N/A DEBT SERVICE 0 492,500 492,500 479,103 479,103 OTHER 12,518 700 700 700 700 0.00% TOTAL OPERATING EXPENSES AND TRANSFERS 1,028,665$ 2,403,200$ 1,509,700$ 2,553,803$ 2,553,803$ 6.27% INCREASE (DECREASE) IN FUND BALANCE 1,940,618$ (1,845,200)$ (946,700)$ (1,820,816)$ (1,820,816)$ ENDING FUND BALANCE 3,231,563$ 1,386,363$ 2,284,863$ 464,047$ 464,047$ Notes: 1) Use $150,000 for design of projects during FY 04 and program balance of dollars available for projects in FY 05 WPC PROJECTS TOTAL CURRENT PROJECTS PROJECT LOWER TRAILS PhASE 1 1,430,000$ UPPER TRAILS PHASE 1 1,948,000 PARKING LOT 70,000 TOTAL CURRENT PROJECTS 3,448,000$ WOLF PEN CREEK TIF FUND - SOURCES INVEST. EARNINGS 5%TAXES BRAZOS CO 21% TAXES COCS 26% TAXES CSISD 48% WOLF PEN CREEK TIF FUND - USES DEBT SERVICE 19% ENGINEER. 6% CAPITAL PROJECTS 75% 139 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:WPC Upper Trails PROJECT BUDGET: $1,948 PROJECT #:WP9905 PROJECT MANAGER:Laura Harris FUNDING SOURCE(S):Wolf Pen Creek TIF PROJECT DESCRIPTION/JUSTIFICATION: This project is to design and construct a pedestrian trail system and bridges in the Wolf Pen Creek area to extend from Texas Avenue to Dartmouth. This project may be completed in phases. STATUS: Under Design and in Land Acquistion PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 85 $85 2002-03 550 55 2003 -04 5 55 1000 7 1,067 2004-05 735 6.25 741 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $10 $190 $1,735 $13 $1,948.00 140 W o l f P e n C reek ChannelImprovements W o l f P e n C reek ChannelImprovements G e o r g e B u s h E a s t E x t e n s i o n G e o r g e B u s h E a s t E x t e n s i o n W o lfP e nUpperTrailsW o lfP e nUpperTrailsRichards StRichards StSterling StSterling St C r e s t S t C r e s t S t O l ym p i a W y O l ym p i a W y A t h e n s D r A t h e n s D r Holleman Dr EHolleman Dr E D a r tm o u t h S t D a r tm o u t h S t Manuel Dr Manuel DrStal l ings DrStal l ings DrUniversity Oaks BlUniversity Oaks BlMu n s o n A vMu n s o n A v L a s s i e L n L a s s i e L nHarvey RdHarvey Rd OAKS PARK OAKS PARK WOLF PEN CREEK PARKWOLF PEN CREEK PARK 141 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:WPC Parking Improvements PROJECT BUDGET: $70 PROJECT #:WP9903 PROJECT MANAGER:Laura Harris FUNDING SOURCE(S):Wolf Pen Creek TIF PROJECT DESCRIPTION/JUSTIFICATION: This project is to construct a parking lot at Dartmouth and Holleman to accommodate visitors to the Wolf Pen Creek area. STATUS: In Design PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 10 60 $70 2002-03 0 2003 -04 0 2004-05 0 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $0 $10 $60 $0 $70 142 Wolf Pen Pkg lot Wolf Pen Pkg lot WPC Marquee Sign WPC Marquee Sign Sterling StSterling St C r e s t S t C r e s t S t Richards StRichards StCamellia CtCamellia CtColg a t e C r Colg a t e C r Kalanchoe CtKalanchoe CtCar nat i onCtCarnat i onCt C y p r e s s D r C y p r e s s D r Dartmouth StDartmouth StHolleman Dr EHolleman Dr E Manuel Dr Manuel DrColgate DrColgate Dr WOLF PEN CREEK PARK WOLF PEN CREEK PARK WOODSTOCK#1WOODSTOCK#1 TROYTROY KFOKFO EASTMARKEASTMARK POSTOAKMALLPOSTOAKMALL WOODSTOCK#1WOODSTOCK#1 RICHARDSRICHARDS WOODSTOCK#1WOODSTOCK#1 BRENTWOODBRENTWOOD RICHARDSRICHARDS SOUTHCREEK PH 1SOUTHCREEK PH 1 HOLLEMANPLACEHOLLEMANPLACE WOODBROOKCONDOSWOODBROOKCONDOS Wolf Pen Creek Amp Wolf Pen Creek Amp 143 Embracing the Past Exploring the Future 144 UUTTIILLIITTIIEESS CCAAPPIITTAALL PPRROOJJEECCTTSS BBUUDDGGEETT The City of College Station develops and adopts a five year Capital Improvements Project List. The list is updated annually and is presented for City Council review as a part of the annual budget process. The list consolidates all anticipated capital needs for which funding authorization exists. The list is divided into several sections depending on the services provided and the funding source. Revenue bonds are authorized to be issued any time there is a need for financing capital construction or acquisition and where the asset will reside in one or more of the City's enterprise funds. The City's enterprise funds include Electric, Water, Wastewater, and Solid Waste Collection. Generally, revenue bonds do not require voter approval. These bonds are repaid from the revenues generated by the utilities. No revenue bonds are projected to be issued for any of the water capital improvement projects, however $4,000,000 is projected to be issued for wastewater capital improvement projects in FY 04. Among the decisions and proposals that accompany capital project recommendations is an analysis of potential ongoing costs and any potential impact on utility rates that a project may have. UUTTIILLIITTYY CCAAPPIITTAALL PPRROOJJEECCTTSS EELLEECCTTRRIICC CCAAPPIITTAALL PPRROOJJEECCTTSS $5,530,000 is the approved expenditure amount for electric capital projects in FY 04. Additional information will be provided to the City Council as a competitive matter. WWAATTEERR CCAAPPIITTAALL PPRROOJJEECCTTSS In FY 04, $6,101,737 is the projected new appropriations for water capital projects, and total water capital project expenditures are projected to be $14,769,051. Included in the Approved FY 04 Budget is over $1 million for water line rehabilitation in the Southside area, $3.2 million for the parallel water line transmission project, and $462,900 on projects to provide water to newly annexed portions of the City. Additionally, $4,174,837 is the projected expense for water capital project to provide water service to City residents not currently using College Station water. The Water Capital Projects Fund also includes $305,000 to improve the security of the water supply and $530,000 to provide backup power generation to the water system. The Approved FY 04 Budget also includes $10,400,000 in current revenues from operations are approved to fund water capital projects. No debt is projected for issuance in FY 04 for water capital projects. WWAASSTTEEWWAATTEERR CCAAPPIITTAALL PPRROOJJEECCTTSS In FY 04, $6,159,720 is the projected new appropriations for wastewater capital projects, and total wastewater capital project expenditures are projected to be $7,343,720. $1.5 million is included for the rehabilitation of wastewater infrastructure in the Southside area. Over $1 million is also included as projected expense for relocating and rehabilitating sewer line beneath Texas Avenue. This project is necessary because of the TxDoT widening of Texas Avenue, and will be done in conjunction with this project. As in the Water Division, the Wastewater Division includes $330,000 to improve security of wastewater facilities and $215,000 for backup power generation to operate the sewer system in the event of a power outage. $535,800 is included to provide sewer services to the newly annexed parts of town. DDRRAAIINNAAGGEE CCAAPPIITTAALL PPRROOJJEECCTTSS The Approved FY 04 drainage capital projects budget includes $ 5,172,056 in improvement to the City's drainage system. The bulk of these expenditures will be for drainage channel improvements in the Bee Creek ($3 million) and Wolf Pen Creek ($1 million) areas of town. AADDDDIITTIIOONNAALL OO&&MM CCOOSSTTS The City of College Station strives to provide superior electric, water, and wastewater services to its citizens. Part of this effort includes maintaining a sound infrastructure that is technologically advanced. This requires continuous investment in the capital that makes up the infrastructure. These investments take place in the form of capital improvement projects. These projects may include rehabilitating or replacing old, deteriorating infrastructure; expanding facilities; and adding new facilities and infrastructure. 145 Embracing the Past Exploring the Future 146 EELLEECCTTRRIICC SSEERRVVIICCEE CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000033--22000044 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22000088--22000099 147 ELECTRIC SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 REVISED APPROVED BUDGET ESTIMATE APPROPRIATIONS PROJECTED FY 02-03 FY 02-03 FY 03-04 FY 03-04 SUBTOTAL ADDITIONAL RESOURCES 5,630,000$ 5,730,000$ 5,575,000$ 5,575,000$ TOTAL RESOURCES AVAILABLE 7,282,634$ 7,382,634$ 7,420,634$ 7,420,634$ TOTAL EXPENDITURES 5,537,000$ 5,537,000$ 5,530,000$ 5,530,000$ GAAP ADJUSTMENT ENDING FUND BALANCE:1,745,634$ 1,845,634$ 1,890,634$ 1,890,634$ 148 ELECTRIC SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED FY 04-05 FY 05-06 FY 06-07 FY 07-08 FY08-09. 8,635,000$ 10,140,000$ 7,490,000$ 5,990,000$ 6,075,000$ 10,525,634$ 15,311,634$ 12,795,634$ 9,107,634$ 7,996,634$ 5,354,000$ 10,006,000$ 9,678,000$ 7,186,000$ 7,954,000$ 5,171,634$ 5,305,634$ 3,117,634$ 1,921,634$ 42,634$ 149 Embracing the Past Exploring the Future 150 WWAATTEERR SSEERRVVIICCEE CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000033--22000044 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22000088--22000099 151 WATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 REVISED FY02-03 PROJECT APPROVED TOTAL PROJECT WORK REQUEST BUDGET ACTUAL FY 02-03 BUDGET ESTIMATE NUMBER NUMBER AMOUNT FY 01-02 APPROPRIATIONS FY 02-03 BEGINNING FUND BALANCE:8,618,228$ 8,544,589$ 8,544,589$ ADDITIONAL RESOURCES: UTILITY REVENUE BONDS 7,427,150$ 0$ 0$ INTEREST ON INVESTMENTS 453,166 175,000 370,000 TRANSFERS FROM OPERATIONS 0 1,300,000 1,300,000 OTHER 9,100 0 0 SUBTOTAL ADDITIONAL RESOURCES 7,889,416$ 1,475,000$ 1,670,000$ TOTAL RESOURCES AVAILABLE 16,507,644$ 5,876,403$ 10,214,589$ REHABILITATION PROJECTS: DISTRIBUTION SYSTEM REHAB WT0201 ANNUAL 0 285,000 285,000 FIRST & MAPLE STREETS REHAB WT0212 WF0351786 218,900 12,033 200,000 207,000 GEORGE BUSH E WIDENING TBD WF0390567 88,000 0 50,000 25,000 GREENS PRAIRIE WTR LINE LOWERING - WF0351806 230,000 0 0 230,000 TEXAS AVE. RELOCATION SOUTH WT9804 WF0351282 950,000 0 0 430,000 SOUTHSIDE WATER REHAB A WF0379021 115,000 0 0 115,000 WEST PARK - TBD 1,075,000 0 0 0 COLLEGE PARK/BREEZY HEIGHTS - TBD 1,270,000 0 0 0 SOUTH KNOLL - TBD 1,175,000 0 0 0 SOUTHWOOD 5-7 - TBD 985,000 0 0 0 McCULLOCH - TBD 925,000 0 0 0 THE KNOLL - TBD 900,000 0 0 0 SOUTHSIDE WATER REHAB STUDY WT0105 WF0360070 50,000 170 0 95,000 CLOSED PROJECTS 105,494 SUBTOTAL 117,697$ 535,000$ 1,387,000$ PRODUCTION PROJECTS WELL #6 AND LINE WT0004 WF0352591 2,963,000 299,980$ 0$ 721,000$ WELL #7 WT0106 WF0353607 2,064,000 187,836 0 78,000 WELL #7 COLLECTION LINE WT0203 WF0353621 2,600,000 6,350 494,000 51,000 PARALLEL WELLFIELD COLL LINE PH I WT0205 WF0353553 1,802,000 0 795,000 110,000 COOLING TOWERS EXPANSION TBD TBD 1,829,000 0 0 0 PARALLEL WATER TRANSMISSION WT0005 WF0350259 8,273,000 2,858,658 0 685,000 WATER TRANSMISSION-SH21 - VILLA MARIA WT0116 WF0352317 5,754,000 262,203 440,000 278,000 LAND ACQUISITION - WELLS & PUMP STATION WT0206 TBD 1,250,000 0 300,000 0 DOWLING ROAD 10MG GST WT0117 WF0353631 3,851,000 106,853 84,000 125,000 DOWLING ROAD PUMP STATION PIPING TBD TBD 1,332,000 0 130,000 0 WELLS 4 & 5 PUMP REPLACEMENTS - TBD 150,000 0 0 0 WATER PLANT SECURITY TBD 305,000 0 0 0 EMERGENCY ELECTRIC POWER TBD 780,000 0 0 0 CLOSED PROJECTS 651,000 511,304 0 0 SUBTOTAL 4,233,184$ 2,243,000$ 2,048,000$ 152 WATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 APPROVED FY 04 BUDGET PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED APPROPRIATIONS FY 03-04 FY 04-05 FY 05-06 FY 06-07 FY 07-08 FY 08-09 4,401,403$ 4,401,403$ 207,352$ 234,352$ 75,552$ 112,752$ 130,752$ 0$ 0$ 9,300,000$ 8,400,000$ 7,600,000$ 1,700,000$ 4,100,000$ 175,000 175,000 225,000 125,000 75,000 50,000 50,000 10,400,000 10,400,000 1,000,000 1,000,000 500,000 500,000 500,000 0 0 0 0 0 0 0 10,575,000$ 10,575,000$ 10,525,000$ 9,525,000$ 8,175,000$ 2,250,000$ 4,650,000$ 14,976,403$ 14,976,403$ 10,732,352$ 9,759,352$ 8,250,552$ 2,362,752$ 4,780,752$ 285,000 285,000 285,000 285,000 285,000 285,000 285,000 0000000 38,000 63,000 0 0 0 0 0 0 0 0 0 0 0 0 0 470,000 0 0 0 0 0 0 0 0 0 0 0 0 1,075,000 1,075,000 0 0 0 0 0 0 0 1,270,000 0 0 0 0 0 0 0 1,175,000 0 0 0 0 0 0 0 985,000 0 0 0 0 0 0 0 1,120,000 0 0 0 0 0 0 0 900,000 0 0 0 0 0 0 0 1,398,000$ 1,893,000$ 1,555,000$ 1,460,000$ 1,270,000$ 1,405,000$ 1,185,000$ 0$ 0$ 0$ 0$ 0$ 0$ 0$ 0 106,000 470,000 1,276,000 0 0 0 0 109,000 789,000 1,670,000 0 0 0 0 215,000 1,477,000 0 0 0 0 0 0 0 52,000 1,777,000 0 0 0 3,277,000 1,274,000 0 0 0 0 75,000 75,000 790,000 1,574,000 3,847,000 0 0 0 0 200,000 400,000 371,000 279,000 0 95,000 95,000 1,280,000 2,244,000 0 0 0 80,000 80,000 1,252,000 0 0 0 0 150,000 150,000 0 0 0 0 0 305,000 305,000 0 0 0 0 0 530,000 530,000 240,000 0 0 298,000 0 1,235,000$ 4,942,000$ 7,772,000$ 7,216,000$ 5,995,000$ 577,000$ 0$ 153 WATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 REVISED FY02-03 PROJECT APPROVED TOTAL PROJECT WORK REQUEST BUDGET ACTUAL FY 02-03 BUDGET ESTIMATE NUMBER NUMBER AMOUNT FY 01-02 APPROPRIATIONS FY 02-03 DISTRIBUTION PROJECTS OVERSIZED LINES PARTICIPATION & PLANNING WT0200 ANNUAL 0$ 75,000$ 75,000$ VICTORIA WATER OP TBD TBD 100,000 0 100,000 100,000 BARRON ROAD WATER OP TBD TBD 150,000 0 150,000 35,686 WESTSIDE WATER SERVICES WT9703 WF0353641 3,087,000 48,938 0 80,000 WATER IMPACT FEE WT9905 TBD 359,000 0 0 0 PARK PLACE ELEVATED WATER STORAGE WT0012 WF0353817 3,679,000 2,531,140 0 586,000 WATER RECLAIM / IRRIGATION WT0110 TBD 3,468,000 445 0 0 DARTMOUTH WATER EXTENSION PII TBD WF0350795 220,000 0 220,000 0 JONES-BUTLER WATER EXT PHII TBD TBD 17,000 0 17,000 3,000 ROCK PRAIRIE WATER EXT WELLBORN - WF0352094 2,403,823 168,599 0 481,000 ARRINGTON RD WATER MAIN WELLBORN - WF0379145 612,763 0 0 123,000 BARRON ROAD WELLBORN CUSTOMERS - WF0379197 2,044,845 0 0 409,000 LICK CREEK/ROCK PRAIRIE WELLBORN - WF0379226 157,406 0 0 31,000 CLOSED PROJECTS 0 725,742 SUBTOTAL 3,474,864$ 562,000$ 1,923,686$ ANNEXATION PROJECTS WELLBORN RD N OF GANDY (AREA 1) TBD 448,000 0$ 44,800$ 44,800$ GREENS PR. W. OF ARRINGTON (AREA 2) TBD 347,000 0 34,700 34,700 NANTUCKET E. OF HARPER'S FERRY (AREA 3) TBD 80,000 0 0 0 ROCK P RD S OF CARTER LAKE (AREA 5) TBD 670,000 0 0 0 GREENS PR. RD CORRIDOR EAST (AREA 6) TBD 612,000 0 0 0 0$ 79,500$ 79,500$ GENERAL AND ADMINISTRATIVE 269,883 275,000 275,000 DEBT ISSUANCE COST 125 0 100,000 TOTAL EXPENDITURES 58,554,837$ 8,095,753$ 3,694,500$ 5,813,186$ GAAP ADJUSTMENT 132,698$ ENDING FUND BALANCE:8,544,589$ 2,181,903$ 4,401,403$ 154 WATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 APPROVED FY 04 BUDGET PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED APPROPRIATIONS FY 03-04 FY 04-05 FY 05-06 FY 06-07 FY 07-08 FY 08-09 200,000$ 200,000$ 200,000$ 200,000$ 200,000$ 200,000$ 200,000$ 0 0 0 0 0 0 0 0 114,314 0 0 0 0 0 0 2,598,000 0 0 0 0 0 0 0 212,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 3,468,000 0 220,000 0 0 0 0 0 0 14,000 0 0 0 0 0 403,823 1,922,823 0 0 0 0 0 489,763 489,763 0 0 0 0 0 1,635,845 1,635,845 0 0 0 0 0 126,406 126,406 0 0 0 0 0 2,855,837$ 7,321,151$ 412,000$ 200,000$ 200,000$ 200,000$ 3,668,000$ 22,400$ 22,400$ 380,800$ 0$ 0$ 0$ 0$ 312,300 312,300 0 0 0 0 0 0 0 0 80,000 0 0 0 67,000 67,000 67,000 268,000 268,000 0 0 61,200 61,200 61,200 244,800 244,800 0 0 462,900$ 462,900$ 509,000$ 592,800$ 512,800$ 0$ 0$ 150,000 150,000 150,000 150,000 125,000 50,000 75,000 0 0 100,000 65,000 35,000 0 0 6,101,737$ 14,769,051$ 10,498,000$ 9,683,800$ 8,137,800$ 2,232,000$ 4,928,000$ 8,874,666$ 207,352$ 234,352$ 75,552$ 112,752$ 130,752$ (147,248)$ 155 RREEHHAABBIILLIITTAATTIIOONN PPRROOJJEECCTTSS 156 PROJECT NAME:Distribution System Rehab Annual WORK REQUEST #:WF0410745 FORMER PROJECT #:WT0201 PROJECT MANAGER:Dale Schepers FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: These funds are for general rehabilitation of the water distribution system. Projects are identified on an annual basis. STATUS: Total DSR funding $285,000 for FY03-04 annual amount: Southside Water Rehab Study - WF0360070 - $45,000 University 2" Water Line - WF0351819 - $ 2,500 Northgate Fire Hydrant Coverage Plan - WF0351830 - $750 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 250 $250 2002-03 285 285 2003-04 285 285 2004-05 285 285 2005-06 285 285 2006-07 285 285 2007-08 285 285 2008-09 285 285 TOTAL $0 $0 $1,960 $0 $2,245 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 157 PROJECT NAME:George Bush East Widening $88 WORK REQUEST #:WF0390567 FORMER PROJECT #:ST9804 PROJECT MANAGER:Donald Harmon FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: George Bush Drive East will be widened from Texas Avenue to Dominik Drive. 2" water line will be upgraded to an 8" water line. Coordinated with Streets Project ST9804. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 25 25 2003-04 63 63 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $88 $0 $88 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 158 T e x a s A v w a t e r / s e w e r r e l o c a t T e x a s A v w a t e r / s e w e r r e l o c a tSterling StSterling St Barthelow Dr Barthelow Dr P i n e R i d g e D r P i n e R i d g e D rRichards StRichards StOakdale CrOakdale CrBrentwood DrBrentwood Dr Manuel Dr Manuel Dr Anderson S t Anderson S t Southwest PwSouthwest Pw T e x a s A v S T e x a s A v S 159 PROJECT NAME:Texas Avenue Relocation South $950 WORK REQUEST #:WF0351282 FORMER PROJECT #:WT9804 PROJECT MANAGER:Donald Harmon FUNDING SOURCE(S):Utility Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Texas Avenue will be widened from Dominik to Harvey Mitchell Parkway. Water lines will need to be relocated into an easement outside of the right-of-way. Coordinated with Wastewater Project SS0003. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 50 $50 2002-03 25 400 5 430 2003-04 10 450 10 470 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $85 $850 $15 $950 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: CIP Water Forms, Texas Ave Widen Water 12/3/2003, 4:29 PM 160 Eastgate Ph2 rehabEastgate Ph2 rehabEastgate Utility Rehab Phases 4&5Eastgate Utility Rehab Phases 4&5 T e x a s A v w a t e r / s e w e r r e l o c a t e T e x a s A v w a t e r / s e w e r r e l o c a t eTAMU Side walks TAMU Side walks Thoroughfare RehabThoroughfare RehabAnnual Si d e walk Proje ctAnnualSi d e walk Proje ct G eorgeBushDriveEastW id e n i n g G eorgeBushDriveEastW id e n i n gPuryearDrPuryearDr KyleAvKyleAvJames PwJames PwMil n e r D rMil n e r D r Redmond DrRedmond Dr Milliff Rd Milliff Rd Gilchrist Av Gilchrist Av Moss St Moss StBolton AvBolton Av R o s em a r y L n R o s em a r y L n Brooks AvBrooks AvGilchrist AvGilchrist Av G e o r g e B u s h D r E G e o r g e B u s h D r E Foster A v Foster A v University Oaks BlUniversity Oaks Bl T e x a s A v S T e x a s A v S Harvey RdHarvey Rd THOMAS PARK THOMAS PARK Thomas Park Thomas Park 161 PROJECT NAME:West Park Water Rehab $1,075 WORK REQUEST #:TBD PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Water Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Replacement of water lines in area bounded by George Bush, Luther, Wellborn, and Montclair. Identified by 2003 Southside Water Study. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 98 977 1,075 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $98 $977 $0 $1,075 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 162 Souths ide H is to r ic L igh t ingSouths ide H is to r ic L igh t ing West Park (Southside) West Park (Southside)Thoroughfare RehabThoroughfare RehabTAMU SidewalksTAMU Sidewalks C o lle g e P a r k/ B r e e z y H e i g h t s (Sou t h s i d e ) C o lle g e P a r k/ B r e e z y H e i g h t s (Sou t h s i d e ) F a i r v i e w A v F a i r v i e w A vMo n t c l a i r A vMo n t c l a i r A v H i g h l a n d s S t H i g h l a n d s S t Fidelity StFidelity StKerry StKerry StGrove StGrove StMa r y em S tMa r y em S t W D e x t e r D rW D e x t e r D rA y r s h i r e S t A y r s h i r e S tAngus AvAngus AvRussell StRussell St Guernsey St Guernsey StLuther St W Luther St W Bell StBell StThompson StThompson St L u th erStL u th erStOld Jersey StOld Jersey StWel s h A vWel s h A vLuther StLuther StPark PlacePark PlaceMarion Pugh DrMarion Pugh DrHolleman DrHolleman DrLuther St W Luther St WWel lbo rn RdWel lbo rn Rd W.A. TARROW PARK W.A. TARROW PARK BRISON PARK BRISON PARK LUTHER JONES PARK LUTHER JONES PARK 163 Embracing the Past Exploring the Future 164 PPRROODDUUCCTTIIOONN PPRROOJJEECCTTSS 165 PROJECT NAME:Well #7 $2,128 WORK REQUEST #:WF0353607 FORMER PROJECT #:WT0106 PROJECT MANAGER:TBD FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Purchase land, conduct engineering design, and construction of additional 4 MGD water well. The additional capacity is required to meet TNRCC regulations for pumping capacity to match projected population. STATUS: Consultant's recommendation to start construction FY 2005-06 to meet service demands for FY 2006-07. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 6 192 $198 2002-03 672 78 2003-04 10 96 106 2004-05 33 32 405 470 2005-06 61 1,215 1,276 2006-07 0 2007-08 0 2008-09 0 TOTAL $55 $453 $1,620 $0 $2,128 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel 22 Supplies 11 Services 90 Capital TOTAL $3 $93 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 166 Well #7 Collection Line Well #7 Collection Line Well #7 Well #7Britten RdBritten Rd 167 PROJECT NAME:Well #7 Collection Line $2,625 WORK REQUEST #:WF0353621 FORMER PROJECT #:WT0203 PROJECT MANAGER:TBD FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Project provides for land purchase, engineering design, and construction of collection line progressing from Water Well #7 approximately 10,400 linear feet to a connection point in the existing collection line for Water Well #4. The additional capacity is required to meet TNRCC regulations for pumping capacity to match projected population. Consultant's recommendation to start construction FY 2005-06 to meet service demands for FY 2006-07. STATUS:By action January 7, 2003, Brazos Valley Groundwater Conservation District doubled spacing of new wells completed in the Simsboro formation from one (1) to two (2) feet per one gallon per minute production capacity, thereby, increasing the length of this pipeline to two (2) times the previously estimated length. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 6 $6 2002-03 51 51 2003-04 50 59 109 2004-05 217 40 532 789 2005-06 72 1,598 1,670 2006-07 0 2007-08 0 2008-09 0 TOTAL $273 $222 $2,130 $0 $2,625 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 168 Well #7 Collection Line Well #7 Collection Line Well #7 Well #7Britten RdBritten Rd 169 PROJECT NAME:Parallel Wellfield Collection $1,802 Lines WORK REQUEST #:WF0352553 FORMER PROJECT #:WT0205 PROJECT MANAGER:TBD FUNDING SOURCE(S):Water Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Construction of a collection line for the water wells parallel to the existing line. The existing line is operating at maximum design capacity with the input of six wells. The construction of Well #7 will require this additional pipeline to deliver water to Sandy Point Pump Station. STATUS: FY 2002-2005 phase of the Parallel Collection Line consists of an estimated 7,500 linear foot pipe along Sandy Point Road from the existing Well #4 interconnect to the Sandy Point Pump Station. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 110 110 2003-04 150 65 215 2004-05 77 1,400 1,477 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $150 $252 $1,400 $0 $1,802 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel 0.02 0.02 Supplies 0.01 0.01 Services Capital TOTAL 0.03 0.03 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 170 MMAAPP NNOOTT AAVVAAIILLAABBLLEE 171 PROJECT NAME:Parallel Water Trans. Line $9,115 WORK REQUEST #:WF0350259 FORMER PROJECT #:WT0005 PROJECT MANAGER:Dale Schepers FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: CONSTRUCTION PH: Construct parallel water transmission along FM1687 from the Sandy Point Pump Station to FM2818, then south along FM2818 to SH21; approx 17,314 LF of 48" diameter pipe. CONSTRUCTION PH: Construct parallel water transmission pipeline along FM2818 from Villa Maria Road south to the Dowling Road Pump Station; approx 22,400 LF of 36" diameter pipe. The additional capacity is required to meet TNRCC regulations for pumping capacity to match projected population. This project will be constructed concurrent with the Westside Water Services, Project #WT9703. STATUS: Projects funded from this Parallel Water Trans. Line - FY 02-03: Greens Prairie Water Lowering - WF0351806 - $230,000 Wellborn Customers Transfer - $1,044,000 (Rock Prairie Extension Wellborn - WF0352094 - $481,000) (Arrington Road Water Main Wellborn - WF0379145 - $123,000) (Barron Road Wellborn - WF0379197 - $409,000) (Lick Creek / Rock Prairie Wellborn - WF0379226 - $31,000) PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 290 1,020 2,569 $3,879 2002-03 69 191 425 685 2003-04 266 3,011 3,277 2004-05 156 1,118 1,274 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $359 $1,633 $7,123 $0 $9,115 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel 11 Supplies 0.5 0.5 Services PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 172 MMAAPP NNOOTT AAVVAAIILLAABBLLEE 173 PROJECT NAME:Water Transmission Line $6,826 SH21 - Villa Maria WORK REQUEST #:WF0352317 FORMER PROJECT #:WT0116 PROJECT MANAGER:David Roberts FUNDING SOURCE(S):Water Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Construct parallel water transmission line along FM2818 from Hwy 21 south to Villa Maria Road; approx 21,000 LF of 36" diameter pipe. The additional system capacity required to support Northgate area and provide water service to annexed area west of FM2818 along FM60. Project supports additional water distribution interconnection with TAMU. STATUS: Fund reallocation increasing WT0116 Project Budget by $1,193,000 from WT9703 Westside Water Service. This will cover $800,000 increased land acquisition needs determined by City's Land Agent and construction cost estimate determined by current market values. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 123 139 $262 2002-03 77 201 278 2003-04 75 75 2004-05 750 40 790 2005-06 250 86 1,238 1,574 2006-07 135 3712 3,847 2007-08 0 2008-09 0 TOTAL $1,200 $676 $4,950 $0 $6,826 OPERATING COSTS CATEGORY 1ST Fiscal Year ANNUAL Personnel 11 Supplies 0.5 0.5 Services Capital TOTAL $2 $2 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 174 Wat e r T r a n sm i s s i o n S H 2 1 t o V i l l a M a r i aWat e r T r a n sm i s s i o n S H 2 1 t o V i l l a M a r i a 28th S t 28th S t Beck StBeck StGroesbeck StGroesbeck StFinfeather RdFinfeather Rd Palasota D r Palasota D r S im s A v S im s A v 29th S t 29th S t Leonard RdLeonard RdTurkeyCreekRdTurkeyCreekRdFm 2 8 1 8 Fm 2 8 1 8 Sh 2 1 Sh 2 1 V illa M a r i a R d V illa M a r i a R dRampRampRampRamp 175 Dowling Road Ten Million PROJECT NAME:Gallon Ground $3,851 Storage Tank WORK REQUEST #:WF0353631 FORMER PROJECT #:WT0117 PROJECT MANAGER:TBD FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Construct new Ground Storage Tank of 10 MG capacity at the Dowling Road Pump Station. The additional capacity is required to meet TNRCC regulations for storage and pumping capacity to match projected population. Originally proposed a 5MG capacity at $2,500,000. By doubling the size for increased capacity requirements, the cost savings will be approximately $1,300,000. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 107 $107 2002-03 125 125 2003-04 95 95 2004-05 100 1,180 1,280 2005-06 64 2,180 2,244 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $491 $3,360 $0 $3,851 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel 0.2 0.2 Supplies 00 Services 030 Capital TOTAL $0 $30 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 176 J o n e s B u tle r E x t ensi on,Phase2J o n e s B u tle r E x t ensi on,Phase2Dowling Road 10MG GST/Pump Station Piping Dowling Road 10MG GST/Pump Station Piping Quail Run Quail Run Cain RdCain RdChristine LnChristine LnNorth Do wling RdNorth Do wling RdWoodsmanDrWoodsmanDrJ o n e s - b u tl e r Rd J o n e s - b u tl e r Rd O l d W e l l b o r n R d O l d W e l l b o r n R d B l ueQuai l LnB l ueQuai l LnB luebonne tD r B luebonne tD r B e e l erLn B e e l erLn Qu a il' s Ne s t C r Qu a il' s Ne s t C rSaddleLnSaddleLnLegacyLnLegacyLn Cov e n tr y P l Cov e n tr y P l Fm2 1 5 4Fm2 1 5 4Holleman Dr WHolleman Dr W Sout h w e st P w Sout h w e st P w N Do wling RdN Do wling Rd Sout h w e st P w W Sout h w e st P w W Harvey M i t c h e l l P w S Harvey M i t c h e l l P w SWel l bornRdWel l bornRdWOODWAY PARK WOODWAY PARK SOUTHWEST PARK SOUTHWEST PARK 177 PROJECT NAME:Water Wells #4 & #5 $150 WORK REQUEST #:TBD PROJECT MANAGER:TBD FUNDING SOURCE(S):Water Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Install new replacement pumps in Water Well Numbers 4 and 5 to increase production capacities and meet community's growing demand for drinking water services. STATUS: Existing pump on Water Well Number 4 has been operating in continuous service since the well was drilled in 1989. The pump motor was reconditioned in 1999 concurrent with a project to correct a well subsidence deficiency. Existing pump on Water Well Number 5 has been in service since the well was drilled in 1996. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 150 150 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $150 $0 $150 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 178 WELL 4 WELL 3 WELL 5 R y e S c h o o l R d R y e S c h o o l R dRyeLoopRyeLoop Conquistador CrConquistador Cr 179 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Water Plant Security PROJECT BUDGET: $305 WORK REQUEST #:TDB PROJECT MANAGER:Michael Kellogg FUNDING SOURCE(S):Water Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Design, construct, and install equipment and systems to strengthen security and minimize risks of potential terrorists activities and other threats to City's water production infrastruture including geographically isolated water wells, pumping stations, and storage reservoirs. STATUS: Vulnerability Assessment consultant contract 03-66 mandated by the U.S. Department of Homeland Security, the Centers for Disease Control and Prevention (CDC), and Environmental Protection Agency (EPA) approved by City Council March 13, 2003. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 40 200 65 305 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $40 $200 $65 $305 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel Supplies Services 180 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Emergency Electric Power PROJECT BUDGET: $1,068 WORK REQUEST #:TBD PROJECT MANAGER:TBD FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Provide emergency electric power production equipment to ensure minimum essential water production and distribution services can be maintained in the event of a primary electric service blackout. Emergency electric power production capability will serve the following locations: Dowling Road Pump Station, Sandy Point Pump Station, and two Water Wells. STATUS: City currently unable to satisfy community's water service demand during periods of electric system blackout. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 6 100 424 530 2004-05 2 18 220 240 2005-06 0 2006-07 0 2007-08 8 40 250 298 2008-09 0 TOTAL $0 $16 $158 $894 $1,068 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel 414 Supplies 18 55 Services 39 Capital 727 TOTAL $32 $105 181 DDIISSTTRRIIBBUUTTIIOONN PPRROOJJEECCTTSS 182 Oversize Water Lines PROJECT NAME:Participation & Planning Annual WORK REQUEST #:WF0410857 FORMER PROJECT #:WT0200 PROJECT MANAGER:Dale Schepers FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: These funds are available for oversize participation with developers in the construction of water lines above the minimum size needed to serve the development. This allows lines to be built large enough to meet future development without having to go back and install larger lines. Projects are identified based on development activity. STATUS: **Total OP funding FY02-03 $75,000 for annual amount: Southside Water OP - WF0387838 - $29,600 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 50 150 $200 2002-03 570 75 2003-04 50 150 200 2004-05 50 150 200 2005-06 50 150 200 2006-07 50 150 200 2007-08 50 150 200 2008-09 50 150 200 TOTAL $0 $355 $1,120 $0 $1,475 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 183 Barron Road Water Line PROJECT NAME:Oversized Planning $150 & Participation WORK REQUEST #:TBD PROJECT MANAGER:Kimberly Carter FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Approximately 2,000 linear feet of water line. This is an extension of an existing 18" water line. The project involves maintaining uniformity of the distribution system. STATUS:This water line will be incorporated into the Wellborn Water Capture Project to accommodate the City's obligations for water service to annexed areas. Project funded from Barron Road OP FY 02-03: Alexandria Ph 5 OP - $35,685.75 - WF0356035 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 36 36 2003-04 114 114 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $150 $0 $150 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 184 PROJECT NAME:Westside Water Services $3,087 WORK REQUEST #:WF0353641 FORMER PROJECT #:WT9703 PROJECT MANAGER:Dale Schepers FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Due to annexation, development, and expected future development, water services are needed. They do not currently exist west of 2818. This project will be constructed concurrent with the Parallel Water Transmission Line, Project Project #WT0005. STATUS: Land acquisition is included under WT0005. WT9703 Project amount reduced by $1,193,000 based on current market values. This amount was transferred to WT0116 Water Transmission Line SH21 - Villa Maria for land acquisition. Currently waiting on two property condemnations. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 402 7 $409 2002-03 80 80 2003-04 2,598 2,598 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $482 $2,605 $0 $3,087 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 185 Dartmouth Drive Water PROJECT NAME:Extension - Phase II $220 WORK REQUEST #:WF0350795 PROJECT MANAGER:Donald Harmon FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Dartmouth Drive will be extended from Krenek Tap Road to Harvey Mitchell Parkway (FM 2818). It will be necessary to extend 2,300 linear feet of 12" water line. This project will be coordinated with Streets Project ST0211. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 20 200 220 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $20 $200 $0 $220 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 186 Da r t mout hDr i v e Ex t e n s i o n Phase2Da r t mout hDr i v e Ex t e n s i o n Phase2D a r tm o u t h D r i v e E x t e n s i o n P h a s e 1 D a r tm o u t h D r i v e E x t e n s i o n P h a s e 1 Willia m King Cole Dr Willia m King Cole DrTeal StTeal StKrenek Tap RdKrenek Tap RdHarvey Mitchell P w SHarvey Mitchell P w S CENTRAL PARK CENTRAL PARK CY MILLER PARK CY MILLER PARK LAKEVIEWACRESLAKEVIEWACRES WILLIAMS-WINDER-KINGWILLIAMS-WINDER-KING DARTMOUTHCROSSINGDARTMOUTHCROSSING E&MJONES FARMPLACE E&MJONES FARMPLACE SOUTHWESTCROSSINGSOUTHWESTCROSSING Public Works Public Works Utility Customer Service Utility Customer Service Municipal Court Municipal Court PolicePolice Central Park PavilionCentral Park Pavilion Parks World Headquarters Parks World Headquarters East District Forestry East District Forestry 187 Jones-Butler Road PROJECT NAME:Water Extension - Phase II $17 WORK REQUEST #:TBD PROJECT MANAGER:Craig Jordan FUNDING SOURCE(S):Water Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: This project will extend Jones-Butler Road water line south from Holleman Drive to FM 2818. It will be necessary to extend 16" water line 100 feet across Jones-Butler Road. This project will be coordinated with Streets Project ST0005 which is needed to provide a north-south route paralleling Wellborn Road. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 33 2003-04 14 14 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $3 $14 $0 $17 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 188 1111 1111South s id e H is to r ic L igh t ingSouth s id e H is to r ic L igh t ing J o n e s B u tle r E x t ensi on,Phase2J o n e s B u tle r E x t ensi on,Phase2J o n e s - b u t l e r R d J o n e s - b u t l e r R d WoodsmanDrWoodsmanDrSouthland StSouthland StAr i zon a S tAr i zon a S tOney H e r v ey D rOney H e r v ey D r G r i d i r o n D r G r i d i r o n D rSiennaDrSiennaDr Legacy LnLegacy Ln Wood way DrWoodwayDr Holleman Dr W Holleman Dr W N Do wling RdN Do wling RdLuther St W Luther St W Marion Pugh DrMarion Pugh Dr Sout h w e st P w Sout h w e st P w Sout h w e st P w W Sout h w e st P w W Marion Pugh DrMarion Pugh Dr S o ut h w e stPwW S o ut h w e stPwW Wel lbo rn RdWel lbo rn Rd Harvey M i t c h e l l P w S Harvey M i t c h e l l P w S WOODWAY PARK WOODWAY PARK W.A. TARROW PARK W.A. TARROW PARK 189 PROJECT NAME:Rock Prairie Water $2,571 Extension Wellborn WORK REQUEST #:WF0352094 FORMER PROJECT #:WT0102 PROJECT MANAGER:Kimberly Carter FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Extend 18" water line along Rock Prairie Road from Stonebrook to the Intersection of Rock Prairie Road and Greens Prairie Road, along Greens Prairie until Pebble Creek Development. STATUS: $150,000 of construction funds for FY 2001-02 has been expensed on 18" water line along Rock Prairie Road from South Highway 6 to Stonebrook coordinated with the Rock Prairie Road Realignment Project ST9923. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 9 4 154 $167 2002-03 11 9 461 481 2003-04 1 1,922 1,923 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $20 $14 $2,537 $0 $2,571 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 190 Thoroughfare RehabThoroughfare Rehab Rock P r a i r i e R o a d R e a l i g n m e n t a n d W a t e r L i n e Rock P r a i r i e R o a d R e a l i g n m e n t a n d W a t e r L i n e HWY 6 Water Impact Fee L ineHWY 6 Water Impact Fee L ine Rock Prairie Water Line Rock Prairie Water LineFront age6RdEFront age6RdEO ldR ockP rairieR dO ldR ockP rairieR dOfframp6NOfframp6NAmber woodCtAmberwoodCt Rock P r a i r i e R d Rock P r a i r i e R d 39393939 24052405 21012101 39753975 93149314 93129312 93109310 93099309 93069306 93089308 10081008 93049304 9307930793029302 40134013 13001300 93069306 93109310 191 PROJECT NAME:Arrington Road Water Main $613 Wellborn Customers WORK REQUEST #:TBD PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Fund PROJECT DESCRIPTION/JUSTIFICATION: This project will install a 12" water line along Arrington Road and Hwy 6. This project provides water service to residents of College Station who are currently served by Wellborn Special Utility District. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 64 59 123 2003-04 490 490 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2007-09 TOTAL $0 $64 $549 $0 $613 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 192 PROJECT NAME:Barron Road $2,045 Wellborn Customers WORK REQUEST #:TBD PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: This project will install an 18" water line along Barron Road, a 12" water line along Barron Road Cut Off, and and an 8" water line along Wellborn Road. This project provides water service to residents of College Station who are currently served by Wellborn Special Utility District. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 213 196 409 2003-04 1,636 1,636 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2007-09 0 TOTAL $0 $213 $1,832 $0 $2,045 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 193 PROJECT NAME:Lick Creek/Rock Prairie $157 Wellborn Customers WORK REQUEST #:TBD PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: This project will install an 8" water line from the Lick Creek Wastewater Treatment Plant to Rock Prairie Road. This project provides water service to residents of College Station who are currently served by Wellborn Special Utility District. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 17 14 31 2003-04 126 126 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $17 $140 $0 $157 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 194 AANNNNEEXXAATTIIOONN PPRROOJJEECCTTSS 195 PROJECT NAME:Wellborn Rd N. of Gandy $448 Area#1 WORK REQUEST #:TBD PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Installation of water lines to serve residents annexed in 2002. 12" water line crossings to be installed at Navarro and Gandy. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 45 45 2003-04 22 22 2004-05 381 381 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $22 $45 $381 $0 $448 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 196 1111 1111 Fm 2 1 5 4 Fm 2 1 5 4We l s h A vWe l s h A v D eaconDrD eaconDrSout h w e st P w Sout h w e st P wHollemanDrHollemanDr Luther St W Luther St W RioGr a n d e B lRioGr a n d e B l Brothers BlBrothers Bl S o u t h wo o dDr S o u t h wo o dDr Ede l w eissAvEde l w eissAvMarion Pugh DrMarion Pugh Dr N u e c esDr N u e c esDr B alconesD r B alconesD r NDow lingRdNDow lingRdG eorgeBushDrW G eorgeBushDrW 197 PROJECT NAME:Greens Prairie Rd W. of $347 Arrington (Area 2) WORK REQUEST #:TBD PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Installation of water lines to serve residents annexed in 2002. Installation of 12" water line from Castlegate to White's Creek. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 35 35 2003-04 312 312 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $35 $312 $0 $347 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 198 2222Barron RdBarron Rd Greens Prairie Rd W Greens Prairie Rd W C a stlegateD r C a stlegateD r L a k e wa y D r L a k e wa y D r N e w p o r t L n N e w p o r t L n De ca t u r D rDeca t u r D r V ic t o ri a A v V ic t o ri a A v ArringtonRdArringtonRdA le x a n d ria A v A le x a n d ria A v G reensPrairieRdG reensPrairieRdG reensPrairieR d W G reensPrairieR d W 199 PROJECT NAME:Rock Prairie Rd S. of $670 Carter Lake (Area 5) WORK REQUEST #:TBD PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Installation of water lines to serve residents annexed in 2002. Installation of 12" water line across Greens Prairie and Rock Prairie Roads. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 67 67 2004-05 67 67 2005-06 268 268 2006-07 268 268 2007-08 0 2008-09 0 TOTAL $67 $67 $536 $0 $670 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 200 5555 6666 Thoroughfare Rehab Thoroughfare Rehab G reensPrairieRoadwideningG reensPrairieRoadwideningRoc k P r a i r i e W a t e r L i n e Roc k P r a i r i e W a t e r L i n e Lick Creek Park Development Lick Creek Park Development Lick Creek Archaelogical StudyLick Creek Archaelogical Study Lick Creek Treatment Plant ExpansionLick Creek Treatment Plant Expansion R o ck P r airie Rd R o ck P r airie Rd St AndrewsDrSt AndrewsDrR o y a lA d elad eD rR o y a lA d elad eD rPe bb l e C r e e k PwPe bb l e C r e e k PwGreens Prairie RdGreens Prairie RdGreensPrairieRdGreensPrairieRd201 PROJECT NAME:Greens Prairie Rd Corridor $612 East (Area 6) WORK REQUEST #:TBD PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Utility Revenue Bonds Water Operating Funds PROJECT DESCRIPTION/JUSTIFICATION: Installation of water lines to serve residents annexed in 2002. Installation of 12" water line along Greens Prairie Road. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 61 61 2004-05 61 61 2005-06 245 245 2006-07 245 245 2007-08 0 2008-09 0 TOTAL $61 $61 $490 $0 $612 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 202 5555 6666 4444 Greens Prairie RdGreens Prairie Rd 203 Embracing the Past Exploring the Future 204 WWAASSTTEEWWAATTEERR SSEERRVVIICCEE CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTTSS FFIISSCCAALL YYEEAARR 22000033--22000044 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22000088--22000099 205 WASTEWATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 REVISED FY02-03 PROJECT APPROVED TOTAL PROJECT WORK REQUEST BUDGET ACTUAL FY 02-03 ESTIMATED NUMBER NUMBER AMOUNT FY 01-02 APPROPRIATIONS FY 02-03 BEGINNING FUND BALANCE:9,375,458$ 6,440,563$ 6,440,563$ ADDITIONAL RESOURCES: UTILITY REVENUE BONDS 6,159,100$ 0$ 0$ INTEREST ON INVESTMENTS 375,195 100,000 300,000 TRANSFERS FROM OPERATIONS 00 INTER GOVERNMENTAL 0 270,000 0 OTHER 12,130 0 0 SUBTOTAL ADDITIONAL RESOURCES 6,546,425$ 4,370,000$ 300,000$ TOTAL RESOURCES AVAILABLE 15,921,883$ 7,721,213$ 6,740,563$ REHABILITATION PROJECTS COLLECTION SYSTEM REHAB SS0209 ANNUAL 13,074 285,000$ 205,000$ CARTERS CREEK SCREW LIFT SYSTEM TBD WF0376687 1,292,280 0 286,000 290,400 FIRST & MAPLE STREETS REHAB SS0212 WF0351778 81,300 4,011 75,000 77,000 HENSEL PARK LIFT STATION SS0203 WF0354063 460,000 88,841 77,000 371,000 LIFT STATION #2 FORCEMAIN REALIGNMENT - TBD 300,000 0 0 0 HWY 30 TURNAROUND SS0207 WF0350071 300,000 153,429 0 147,000 TEXAS AVE. RELOCATION SOUTH SS0003 WF0351341 1,600,000 51,999 0 540,000 SOUTHSIDE SEWER UPGRADE A - WF0379101 80,000 0 0 80,000 WEST PARK - TBD 1,500,000 0 0 0 COLLEGE PARK/BREEZY HEIGHTS - TBD 880,000 0 0 0 SOUTH KNOLL - TBD 830,000 0 0 0 SOUTHWOOD 5-7 - TBD 1,175,000 0 0 0 McCULLOCH - TBD 925,000 0 0 0 THE KNOLL TBD 1,000,000 0 0 0 CLOSED PROJECTS 177,165 SUBTOTAL 488,519 723,000$ 1,710,400$ COLLECTION OVERSIZE PARTICIPATION & PLANNING SS0200 ANNUAL 0 250,000 250,000 WESTSIDE SEWER SERVICE SS9702 TBD 2,634,000 624,415 0 0 NORTHEAST TRUNK EXPAN. PHASE I SS9805 WF0351744 530,000 0 0 300,000 DARTMOUTH PHII TBD WF0350773 50,000 0 50,000 0 JONES-BUTLER WASTEWATER EXTENSION TBD TBD 32,500 0 32,500 2,500 GEORGE BUSH DR EAST WIDENING ST9804 WF0390568 12,000 0 0 0 STEEPLECHASE IMPACT FEE - WF0354517 1,000,000 0 0 6,550 LIFT STATION #1 GRAVITY LINE - TBD 120,000 0 0 0 LICK CREEK PARALLEL TRUNK LINE - TBD 3,000,000 0 0 0 MATERIAL STAGING STORAGE AREA - USC - TBD 70,000 0 0 0 CLOSED PROJECTS 1,724 0 SUBTOTAL 626,139$ 332,500$ 559,050$ TREATMENT LICK CREEK TRUNK & PLANT EXPANSION SS9806 WF0355780 10,813,000$ 7,474,645$ 0$ 455,000$ ODOR CONTROL SS9810 WF0354125 1,554,000 187,636 0 62,000 SLUDGE PROCESSING IMPROVEMENTS SS9904 WF0363214 1,823,000 0 0 0 CC PLANT DEMO & MAINT. BLDG SS0204 TBD 250,000 0 150,000 100,000 WASTEWATER PLANT SECURITY - TBD 210,000 0 0 0 CCWWTP PAVEMENT/REPAIRS IMP - TBD 557,000 0 0 0 EMERGENCY ELECTRIC POWER TBD 215,000 0 0 0 CLOSED PROJECTS SS0105 - 651,000 7 400,087 0 0 SUBTOTAL 8,062,368$ 150,000$ 617,000$ 206 WASTEWATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 APPROVED FY 04 BUDGET PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED APPROPRIATIONS FY 03-04 FY 04-05 FY 05-06 FY 06-07 FY 07-08 FY 08-09 3,351,213$ 3,351,213$ 377,493$ 249,233$ 606,033$ 352,233$ 332,233$ 4,000,000$ 4,000,000$ 6,300,000$ 3,100,000$ 3,800,000$ 1,500,000$ 1,500,000$ 100,000 100,000 50,000 25,000 25,000 10,000 10,000 0 0 00000 270,000 270,000 0 0 0 0 0 0000000 4,370,000$ 4,370,000$ 6,350,000$ 3,125,000$ 3,825,000$ 1,510,000$ 1,510,000$ 7,721,213$ 7,721,213$ 6,727,493$ 3,374,233$ 4,431,033$ 1,862,233$ 1,842,233$ 285,000$ 285,000$ 285,000$ 285,000$ 285,000$ 285,000$ 285,000$ 667,920 667,920 333,960 0 0 0 0 00 0 0 0 0 0 0 0 0 0 0 0 0 300,000 300,000 0 0 0 0 0 0 0 0 0 0 0 0 300,000 1,010,000 0 0 0 0 0 0 0 0 0 0 0 0 1,500,000 1,500,000 0 0 0 0 0 0 0 1,305,000 0 0 0 0 0 0 0 830,000 0 0 0 0 0 0 0 1,175,000 0 0 0 0 0 0 0 925,000 0 0 0 0 0 0 0 1,000,000 3,052,920$ 3,762,920$ 1,923,960$ 1,115,000$ 1,460,000$ 1,210,000$ 1,285,000$ 250,000 250,000 250,000 250,000 250,000 250,000 250,000 0 0 1,978,000 0 0 0 0 0 0 0 0 0 0 0 0 50,000 0 0 0 0 0 0 30,000 0 0 0 0 0 0 12,000 0 0 0 0 0 1,000,000 1,000,000 0 0 0 0 0 35,000 35,000 85,000 0 0 0 0 0 0 0 1,250,000 1,750,000 0 0 77,000 77,000 0 0 0 0 0 1,362,000$ 1,454,000$ 2,313,000$ 1,500,000$ 2,000,000$ 250,000$ 250,000$ 0$ 0$ 0$ 0$ 0$ 0$ 0$ 0 0 0 0 0 0 0 234,000 466,000 1,269,000 0 0 0 0 0 150,000 0 0 0 0 0 210,000 210,000 0 0 0 0 0 330,000 330,000 227,000 0 0 0 0 215,000 215,000 0 0 0 0 0 0 0 0 0 0 0 0 989,000$ 1,371,000$ 1,496,000$ -$ -$ -$ -$ 207 WASTEWATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 REVISED FY02-03 PROJECT APPROVED TOTAL PROJECT WORK REQUEST BUDGET ACTUAL FY 02-03 ESTIMATED NUMBER NUMBER AMOUNT FY 01-02 APPROPRIATIONS FY 02-03 ANNEXATION PROJECTS WELLBORN RD N OF GANDY (AREA 1) TBD 618,000 0 61,800 61,800 GREENS PR. W. OF ARRINGTON (AREA 2) TBD 360,000 0 36,000 36,000 NANTUCKET E. OF HARPER'S FERRY (AREA 3) TBD 201,000 0 20,100 20,100 ROCK P RD S OF CARTER LAKE (AREA 5) TBD 207,000 0 0 0 GREENS PR. RD CORRIDOR EAST (AREA 6) TBD 375,000 0 0 0 -$ 117,900$ 117,900$ CLOSED PROJECTS 252,720 0 0 GENERAL AND ADMINISTRATIVE 336,969 200,000 325,000 DEBT ISSUANCE COST 0 20,000 60,000 TOTAL EXPENDITURES 34,413,800$ 9,766,715$ 1,543,400$ 3,389,350$ GAAP ADJUSTMENT 285,395$ ENDING FUND BALANCE:6,440,563$ 6,177,813$ 3,351,213$ 208 WASTEWATER SERVICE CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 APPROVED FY 04 BUDGET PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED PROJECTED APPROPRIATIONS FY 03-04 FY 04-05 FY 05-06 FY 06-07 FY 07-08 FY 08-09 30,900 30,900 525,300 0 0 0 0 324,000 324,000 0 0 0 0 0 180,900 180,900 0 0 0 0 0 0 0 0 20,700 186,300 0 0 0 0 0 37,500 337,500 0 0 535,800$ 535,800$ 525,300$ 58,200$ 523,800$ -$ -$ 0 0 0 0 0 0 0 200,000 200,000 200,000 75,000 75,000 50,000 0 20,000 20,000 20,000 20,000 20,000 20,000 0 6,159,720$ 7,343,720$ 6,478,260$ 2,768,200$ 4,078,800$ 1,530,000$ 1,535,000$ 1,561,493$ 377,493$ 249,233$ 606,033$ 352,233$ 332,233$ 307,233$ 209 RREEHHAABBIILLIITTAATTIIOONN PPRROOJJEECCTTSS 210 PROJECT NAME:Collection System Annual Rehabilitation FORMER PROJECT #:SS0209 PROJECT MANAGER:Dale Schepers FUNDING SOURCE(S):Utility Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: These funds are for general rehabilitation of the wastewater collection system. Projects are identified on an annual basis. STATUS: **Total CRS annual funding $285,000: Projects funded from CSR FY02-03 annual amount: Nantucket - $5,000 - WF0377360 Carters Creek Screwlift Pumps supplemental - $4,000 - WF0376687 PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 25 200 25 $285 2002-03 19 161 25 205 ** 2003-04 25 235 25 285 2004-05 25 235 25 285 2005-06 25 235 25 285 2006-07 25 235 25 285 2007-08 25 235 25 285 2008-09 25 235 25 285 TOTAL $0 $169 $1,536 $175 $2,200 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 211 Carters Creek Screw Lift System PROJECT NAME:Replacements & Modifications $1,292 WORK REQUEST #:TBD PROJECT MANAGER:David Roberts FUNDING SOURCE(S):Utility Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Provide funds for the replacement of Internaliff Screw Lift Pumps which have exceeded their economical life cycle located before the Headworks of Carters Creek Wastewater Treatment Plant. Estimates for FY 2002-03 provide for the replacement of one (1) Screw Lift Pump. Two (2) pumps will be replaced in FY 2003-04 and the final of four (4) will be replaced in FY 2004-05. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 40 250 290 2003-04 60 608 668 2004-05 20 314 334 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $120 $1,172 $0 $1,292 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies -2 -4 Services -3 -6 Capital TOTAL ($5) ($10) CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 212 Odor Control Odor Control Pavement Repairs Pavement Repairs Lift System Replacement Lift System Replacement Carter Creek Administration Facility Carter Creek Administration Facility SpringCre e k SpringCre e k Rolling R o c k P l Rolling R o c k P lWh it e r o s e CtWh it e r o s e Ct Maplewood Ct Maplewood Ct Walnut Grove Ct Walnut Grove CtAppomattoxDrAppomattoxDrNorth Forest P w North Forest P w Carter Creek Carter Creek Carter Creek Carter Creek 213 PROJECT NAME:Lift Station 2 Forcemain $300 Realignment PROJECT #:TBD PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Wastewater Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Installation of force main along SH 6 TxDOT Right of Way to pump Lift Station 2 into Spring Creek Sewer. This will divert to Lick Creek Wastewater Treatment Plant and relieve Carters Creek capacity levels. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 50 250 300 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $50 $250 $0 $300 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 214 MMAAPP NNOOTT AAVVAAIILLAABBLLEE 215 PROJECT NAME:Texas Avenue Relocation $1,600 South Phase II WORK REQUEST #:WF0351341 FORMER PROJECT #:SS0003 PROJECT MANAGER:Donald Harmon FUNDING SOURCE(S):Wastewater Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Texas Avenue will be widened from Dominik to Harvey Mitchell Parkway. Sewer lines will need to be relocated into an easement outside of the right-of-way. Coordinated with Water Project WT9804. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 50 $50 2002-03 35 500 5 540 2003-04 1,000 10 1,010 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $85 $1,500 $15 $1,600 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 216 EastgatePh2rehab EastgatePh2rehab W olfP e n C reekC h a n n e lIm prov e m entsW olfP e n C reekC h a n n e lIm prov e m entsT e x a s A v w a t e r / s e w e r r e l o c a t T e x a s A v w a t e r / s e w e r r e l o c a t Anderson Street Sidewalk Anderson Street SidewalkMis c ella n e o u s S i d e wa lksMis c ella n e o u s S i d e wa lksThoroughfare RehabThoroughfare RehabThoro u g h f a r e Rehab Thoro u g h f a r e Rehab Sterling StSterling St H o l i k D r H o l i k D r Richards StRichards StOrr StOrr St G la d e S t G la d e S t A n d e r s o n S t A n d e r s o n S t R e d mondDr R e d mondDr H a in esDrH a in esDrP in e R i d g e DrPineRidgeDr L e mo n T r e e L n L e mo n T r e e L n M illiffRdM illiffRdL angf or dSt L angf or dSt Barthelow Dr Barthelow Dr Windin g R d Windin g R d L a u r a L n L a u r a L n C r e st S t C r e st S t CedarRunCedarRunB r i g ht C r B r i g ht C r Poto ma cPl Poto ma cPlHolleman DrHolleman Dr Gla d e S t Gla d e S t Manuel Dr Manuel DrHolleman Dr EHolleman Dr EBrentwood DrBrentwood Dr Park Pl a c e Park Pl a c e G e o r g e B u s h D r E G e o r g e B u s h D r E Southwest PwSouthwest Pw L a s s i e L n L a s s i e L n Fo s t e r A v Fo s t e r A v Cornel l DrCornel l DrStal li n g s D rStal li n g s D r T e x a s A v S T e x a s A v SHarvey RdHarvey Rd LEMONTREE PARK LEMONTREE PARK ANDERSON PARK ANDERSON PARK BEE CREEK PARK BEE CREEK PARK OAKS PARK OAKS PARK 217 PROJECT NAME:Westpark Wastewater Rehab $1,500 WORK REQUEST #:TBD PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Wastewater Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Replacement of wastewater lines in area bounded by George Bush, Luther, Wellborn, and Montclair. Identified by RDII Phase II Sewer Study. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 175 1,325 1,500 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $175 $1,325 $0 $1,500 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 218 Souths ide H is to r ic L igh t ingSouths ide H is to r ic L igh t ing West Park (Southside) West Park (Southside)Thoroughfare RehabThoroughfare RehabTAMU SidewalksTAMU Sidewalks C o lle g e P a r k/ B r e e z y H e i g h t s (Sou t h s i d e ) C o lle g e P a r k/ B r e e z y H e i g h t s (Sou t h s i d e ) F a i r v i e w A v F a i r v i e w A vMo n t c l a i r A vMo n t c l a i r A v H i g h l a n d s S t H i g h l a n d s S t Fidelity StFidelity StKerry StKerry StGrove StGrove StMa r y em S tMa r y em S t W D e x t e r D rW D e x t e r D rA y r s h i r e S t A y r s h i r e S tAngus AvAngus AvRussell StRussell St Guernsey St Guernsey StLuther St W Luther St W Bell StBell StThompson StThompson St L u th erStL u th erStOld Jersey StOld Jersey StWel s h A vWel s h A vLuther StLuther StPark PlacePark PlaceMarion Pugh DrMarion Pugh DrHolleman DrHolleman DrLuther St W Luther St WWel lbo rn RdWel lbo rn Rd W.A. TARROW PARK W.A. TARROW PARK BRISON PARK BRISON PARK LUTHER JONES PARK LUTHER JONES PARK 219 CCOOLLLLEECCTTIIOONN 220 Oversize Wastewater Lines PROJECT NAME:Participation & Planning Annual FORMER PROJECT #:SS0200 PROJECT MANAGER:Dale Schepers FUNDING SOURCE(S):Utility Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: These funds are available for oversize participation with developers in the construction of sewer lines above the minimum size needed to serve the development. This allows lines to be built large enough to meet future development without having to go back and install larger lines. Projects are identified based on development activity. STATUS: Total OP annual funding $250,000. Projects funded from OP FY 02-03 annual amount: PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 5 40 5 $50 2002-03 50 195 5 250 2003-04 50 195 5 250 2004-05 50 195 5 250 2005-06 50 195 5 250 2006-07 50 195 5 250 2007-08 50 195 5 250 2008-09 50 195 5 250 TOTAL $0 $355 $1,405 $40 $1,550 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 221 Dartmouth Drive Wastewater PROJECT NAME:Extension - Phase II $50 WORK REQUEST #:WF0350773 PROJECT MANAGER:Donald Harmon FUNDING SOURCE(S):Utility Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Dartmouth Drive will be extended from Krenek Tap Road to Harvey Mitchell Parkway (FM 2818). It will be necessary to replace three 100 linear feet crossings along Dartmouth Drive. (one 15", one 24", and one 30" crossings) This project will be coordinated with Streets Project ST0211. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 545 50 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $5 $45 $0 $50 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 222 T e x a s A v w a t e r / s e w e r r e l o c a t e T e x a s A v w a t e r / s e w e r r e l o c a t e Da rt mo ut hDr i v e Ex t e n s i onPhase2Da rt mo ut hDr i v e Ex t e n s i onPhase2Morgans Ln Morgans LnCent r a l Park L nCent r a l Park L n Willia m King Cole Dr Willia m King Cole DrTealStTealStH i c k o r y D r H i c k o r y D r Cross Ti mbers DrCross Ti mbers Dr V a lle y V ie w DrV a lle y V ie w DrKrenek Tap RdKrenek Tap Rd D a r tm o u t h S t D a r tm o u t h S t T e x a s A v S T e x a s A v S Harvey Mitchell P w SHarvey Mitchell P w S CENTRAL PARK CENTRAL PARK CY MILLER PARK CY MILLER PARK ARBORETUM PARK ARBORETUM PARK LAKEVIEWACRESLAKEVIEWACRES WILLIAMS-WINDER-KINGWILLIAMS-WINDER-KING SOUTHWESTCROSSINGSOUTHWESTCROSSING EASTMARKEASTMARK DARTMOUTHADDITIONDARTMOUTHADDITION SOUTHWOODSOUTHWOOD DARTMOUTHCROSSINGDARTMOUTHCROSSING BRANDYWINEBRANDYWINE E&MJONES FARMPLACE E&MJONES FARMPLACE PHOENIXPH1PHOENIXPH1 WINDSOR POINTE WINDSOR POINTE CRYSTAL PARK PH 1CRYSTAL PARK PH 1 PLEASANTFOREST PH 1PLEASANTFOREST PH 1 BRENTWOODBRENTWOOD 223 Jones-Butler Road PROJECT NAME:Wastewater Extension - Phase II $33 WORK REQUEST #:TBD PROJECT MANAGER:Craig Jordan FUNDING SOURCE(S):Wastewater Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Jones-Butler Road would be extended from Holleman Drive to intersect with FM 2818. It will be necessary to replace three 100 linear feet crossings along Jones-Butler Road. (two 8" crossings and one 15" crossing) This project will be coordinated with Streets Project ST0005 which is needed to provide a north-south route paralleling Wellborn Road. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 33 2003-04 30 30 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $3 $30 $0 $33 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 224 1111 1111South s id e H is to r ic L igh t ingSouth s id e H is to r ic L igh t ing J o n e s B u tle r E x t ensi on,Phase2J o n e s B u tle r E x t ensi on,Phase2J o n e s - b u t l e r R d J o n e s - b u t l e r R d WoodsmanDrWoodsmanDrSouthland StSouthland StAr i zon a S tAr i zon a S tOney H e r v ey D rOney H e r v ey D r G r i d i r o n D r G r i d i r o n D rSiennaDrSiennaDr Legacy LnLegacy Ln Wood way DrWoodwayDr Holleman Dr W Holleman Dr W N Do wling RdN Do wling RdLuther St W Luther St W Marion Pugh DrMarion Pugh Dr Sout h w e st P w Sout h w e st P w Sout h w e st P w W Sout h w e st P w W Marion Pugh DrMarion Pugh Dr S o ut h w e stPwW S o ut h w e stPwW Wel lbo rn RdWel lbo rn Rd Harvey M i t c h e l l P w S Harvey M i t c h e l l P w S WOODWAY PARK WOODWAY PARK W.A. TARROW PARK W.A. TARROW PARK 225 PROJECT NAME:George Bush Drive East $12 Widening - Wastewater WORK REQUEST #WF0390568 ST9804 PROJECT MANAGER:Don Harmon FUNDING SOURCE(S):Utility Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: George Bush Drive East will be widened from Texas Avenue to Dominik Drive. Adjust sewer manholes to grade and new service leads. Coordinated with Streets Project ST9804. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 12 12 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $12 $0 $12 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 226 Eastgate Ph2 rehabEastgate Ph2 rehabEastgate Utility Rehab Phases 4&5Eastgate Utility Rehab Phases 4&5 T e x a s A v w a t e r / s e w e r r e l o c a t e T e x a s A v w a t e r / s e w e r r e l o c a t eTAMU Side walks TAMU Side walks Thoroughfare RehabThoroughfare RehabAnnual Si d e walk Proje ctAnnualSi d e walk Proje ct G eorgeBushDriveEastW id e n i n g G eorgeBushDriveEastW id e n i n gPuryearDrPuryearDr KyleAvKyleAvJames PwJames PwMil n e r D rMil n e r D r Redmond DrRedmond Dr Milliff Rd Milliff Rd Gilchrist Av Gilchrist Av Moss St Moss StBolton AvBolton Av R o s em a r y L n R o s em a r y L n Brooks AvBrooks AvGilchrist AvGilchrist Av G e o r g e B u s h D r E G e o r g e B u s h D r E Foster A v Foster A v University Oaks BlUniversity Oaks Bl T e x a s A v S T e x a s A v S Harvey RdHarvey Rd THOMAS PARK THOMAS PARK Thomas Park Thomas Park 227 PROJECT NAME:Steeplechase Impact Fee $1,007 Wastewater Improvements WORK REQUEST #:WF0354517 PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Wastewater Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Installation of impact fee gravity wastewater line in Harvey Mitchell Parkway/Wellborn Road area. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 77 2003-04 50 200 750 1,000 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $50 $207 $750 $0 $1,007 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 228 MMAAPP NNOOTT AAVVAAIILLAABBLLEE 229 PROJECT NAME:Lift Station #1 Gravity Line $120 Installation PROJECT #:TBD PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Wastewater Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Installation of gravity sewer line from Lift Station #1 to Spring Creek Sewer in order to take Lift Station #1 out of service. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 20 15 35 2004-05 85 85 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $20 $15 $85 $0 $120 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 230 TTRREEAATTMMEENNTT 231 PROJECT NAME:Sludge Processing $1,823 Improvements WORK REQUEST #:WF0363214 FORMER PROJECT #:SS9803 PROJECT MANAGER:David Roberts FUNDING SOURCE(S):Utility Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Project provides for the design and construction of infrastructure required to satisfy increasing demands for wastewater sludge processing services. Digesters and related infrastructure will be designed and constructed to increase the efficiency and cost-effectiveness of sludge handling, processing, conditioning and other functions required to produce an end product meeting Federal, State statutes and rules. This project was previously referred to as "Sludge Handling". PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 84 4 $88 2002-03 0 2003-04 116 350 466 2004-05 39 1,230 1,269 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $239 $1,584 $0 $1,823 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel 14 26 Supplies 19 29 Services 28 44 Capital TOTAL $61 $99 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 232 PROJECT NAME:CCWWTP Maintenance $250 Bldg. & Demo WORK REQUEST #:TBD FORMER PROJECT #:SS0204 PROJECT MANAGER:David Roberts FUNDING SOURCE(S):Utility Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Demolition of abondoned treatment plant. Plant #1 was taken out of service in 1985 and has become an unattractive nuisance, deteriorated beyond repair, and poor land use. The construction of a dedicated maintenance building. A maintenance building is needed for parts storage, pump, motor, and gearbox repairs. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 100 100 2003-04 150 150 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $0 $250 $0 $250 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 233 PROJECT NAME:Wastewater Plant Security $210 WORK REQUEST #:TBD PROJECT MANAGER:Michael Kellogg FUNDING SOURCE(S):Utility Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Design, construct, and install equipment and systems to strengthen security and minimize risks of potential terrorists activities and other threats to City's Wastewater Treatment Plant infrastructures. STATUS: Staff will import concepts developed by Vulnerability Assessment consultant contract 03-66 (approved by City Council 03-13-03, Agenda Item #10.4, to enhance wastewater infrastructure security. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 10 150 50 210 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $10 $150 $50 $210 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 234 Embracing the Past Exploring the Future 235 Carters Creek WWTP PROJECT NAME:Pavement Repairs $557 Improvements WORK ORDER REQUEST#:TBD PROJECT MANAGER:David Roberts FUNDING SOURCE(S):Utility Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Provide funds for design and construction of new and replacement street and parking lot pavements at the Carters Creek Wastewater Treatment Plant. Scope of work involves removal of 7,700 square yards of 37 year old failed asphaltic concrete street pavement and replacement with portland cement concrete pavement designed to carry current traffic loads. Scope also includes addition of 1,400 square yards of new vehicle parking infrastructure. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 47 283 330 2004-05 13 189 25 227 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $60 $472 $25 $557 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services 22 Capital TOTAL $2 $2 PROJECT BUDGET: CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) 236 Odor Control Odor Control Pavement Repairs Pavement Repairs Lift System Replacement Lift System Replacement Carter Creek Administration Facility Carter Creek Administration Facility S p r i n g C r e e k S p r i n g C r e e k S h a d o w O a k s S h a d o w O a k sButl e r R idg e D rButl e r R idg e D rRed Hill DrRed Hill DrSumter DrSumter DrWil d e w o o d C rWil d e w o o d C rNorth Forest P w North Forest P w EMERALD FOREST PARK EMERALD FOREST PARK RAINTREE PARK RAINTREE PARK 237 PROJECT NAME:Emergency Electric Power $215 WORK REQUEST #:TBD PROJECT MANAGER:David Roberts FUNDING SOURCE(S):Utility Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Provide emergency electric power production equipment to ensure minimum essential wastewater collection and treatment services can be maintained in the event of a primary electric service blackout. Emergency electric power production capability will serve: Lift Station #3, four remaining Lift Stations as dictated by service conditions, and Carters Creek Wastewater Treatment Plant (interchangeable with Water Production emergency equipment for Dowling Road and Sandy Point Pump Stations). STATUS: City currently unable to satisfy community's wastewater collection and treatment demand during periods of electric system blackout. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 0 2003-04 5 50 160 215 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $5 $50 $160 $215 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 238 AANNNNEEXXAATTIIOONN PPRROOJJEECCTTSS 239 PROJECT NAME:Wellborn Rd N. of Gandy $618 Area 1 WORK REQUEST #:TBD PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Utility Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Installation of wastewater lines to serve residents annexed in 2002. Installation of 18" wastewater line along North Fork of Bee Creek to Wellborn Road. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 62 62 2003-04 31 31 2004-05 525 525 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $31 $62 $525 $0 $618 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 240 1111 1111 Fm 2 1 5 4 Fm 2 1 5 4We l s h A vWe l s h A v D eaconDrD eaconDrSout h w e st P w Sout h w e st P wHollemanDrHollemanDr Luther St W Luther St W RioGr a n d e B lRioGr a n d e B l Brothers BlBrothers Bl S o u t h wo o dDr S o u t h wo o dDr Ede l w eissAvEde l w eissAvMarion Pugh DrMarion Pugh Dr N u e c esDr N u e c esDr B alconesD r B alconesD r NDow lingRdNDow lingRdG eorgeBushDrW G eorgeBushDrW 241 PROJECT NAME:Greens Prairie Rd W. of $360 Arington (Area 2) WORK REQUEST #:TBD PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Utility Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Installation of wastewater lines to serve residents annexed in 2002. Installation of 12" wastewater line from Arrington Road to Nantuckett Drive along Harpers Ferry. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 36 36 2003-04 324 324 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $36 $324 $0 $360 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 242 2222Barron RdBarron Rd Greens Prairie Rd W Greens Prairie Rd W C a stlegateD r C a stlegateD r L a k e wa y D r L a k e wa y D r N e w p o r t L n N e w p o r t L n De ca t u r D rDeca t u r D r V ic t o ri a A v V ic t o ri a A v ArringtonRdArringtonRdA le x a n d ria A v A le x a n d ria A v G reensPrairieRdG reensPrairieRdG reensPrairieR d W G reensPrairieR d W 243 PROJECT NAME:Nantucket E. of Harpers Ferry $201 (Area 3) WORK REQUEST #:TBD PROJECT MANAGER:Frank Simoneaux FUNDING SOURCE(S):Utility Revenue Bonds PROJECT DESCRIPTION/JUSTIFICATION: Installation of wastewater lines to serve residents annexed in 2002. Installation of 12" wastewater line along Nantucket Drive from SH6 to Harpers Ferry. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 20 20 2003-04 181 181 2004-05 0 2005-06 0 2006-07 0 2007-08 0 2008-09 0 TOTAL $0 $20 $181 $0 $201 OPERATING COSTS CATEGORY 1st Fiscal Year ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT BUDGET: 244 3333 Business Park Balance Landscaping Business Park Balance Landscaping Fr on t ag e 6 Rd WFr on t ag e 6 Rd WFron t a g e 6 Rd EFron t a g e 6 Rd ENantucket DrNantucket Dr Wayfa r e r L n Wayfa r e r L n Midsu m m e r L n Midsu m m e r L n Scrimshaw LnScrimshaw Ln Tucke r N u c k Tucke r N u c k 245 Embracing the Past Exploring the Future 246 DDRRAAIINNAAGGEE UUTTIILLIITTYY CCAAPPIITTAALL IIMMPPRROOVVEEMMEENNTT PPRROOJJEECCTT FFIISSCCAALL YYEEAARR 22000033--22000044 TTHHRROOUUGGHH FFIISSCCAALL YYEEAARR 22000088--22000099 247 DRAINAGE UTILITY CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 PROJECT REVISED PROJECT BUDGET ACTUAL FY 02-03 BUDGET ESTIMATE NUMBER AMOUNT FY 01-02 APPROPRIATIONS FY 02-03 BEGINNING FUND BALANCE:5,764,491$ 6,560,593$ 6,560,593$ ADDITIONAL RESOURCES: UTILITY REVENUES 982,760$ 1,009,500$ 1,021,000$ INTEREST ON INVESTMENTS 232,168 150,000 170,000 BOND PROCEEDS 785,000 1,000,000 1,000,000 INTERGOVERNMENTAL 0 0 0 TRANSFERS IN 0 0 281,839 SUBTOTAL ADDITIONAL RESOURCES 1,999,928$ 2,159,500$ 2,472,839$ TOTAL RESOURCES AVAILABLE 7,764,419$ 8,720,093$ 9,033,432$ BEE CREEK (COMBINED) SD9802 2,500,000$ 12,458$ 500,000$ 500,000$ BEE CREEK PH. IV & V. SD0001 1,400,000 21,394 0 100,000 WPC - TEXAS TO BYPASS SD9901 3,000,000 71,211 0 100,000 GREENWAYS PROJECTS SD9903 3,640,000 109,126 1,000,000 1,480,909 MINOR DRAINAGE IMPROVEMENTS SD0002 ANNUAL 225,108 250,000 0 HALEY TBD 50,000 0 0 50,000 SOUTHSIDE DRAINAGE IMPROVEMENTS 550,000 0 0 260,000 INSBRUCK DETENTION POND ACCESS TBD 200,000 0 0 40,000 VAL VERDE VALLEY GUTTER TBD 200,000 0 0 0 BEE CREEK (LANCELOT TO GUADALUPE) TBD 200,000 0 0 0 WPC (REDMOND TERRACE) TBD 680,000 0 0 0 BEE CREEK (GLADE TO LEMON TREE) TBD 50,000 0 0 0 STORMWATER MAPPING TBD 0 0 0 0 DRAINAGE/STORMWATER MASTERPLAN SD0204 22,000 50,000 50,000 DRAINAGE MAINTENANCE ANNUAL 350,000 410,748 353,727 DRAINAGE MAINTENANCE SLA's ANNUAL 0 0 0 CLOSED PROJECTS 150,820 0 0 OTHER COSTS 8,360 0 GENERAL & ADMIN. 192,146 220,000 220,000 DEBT ISSUANCE COSTS 5,400 10,000 10,000 TOTAL EXPENDITURES 1,168,023$ 2,440,748$ 3,164,636$ GAAP ADJUSTMENT ($35,803) ENDING FUND BALANCE:6,560,593$ 6,279,345$ 5,868,796$ 248 DRAINAGE UTILITY CAPITAL IMPROVEMENT PROJECTS FISCAL YEAR 2003-2004 THROUGH FISCAL YEAR 2008-2009 APPROVED TOTAL FY 03-04 BUDGET PROJECTED PROJECTED PROJECTED PROJECTED PROJECT PROJECT APPROPRIATION FY 03-04 FY 04-05 FY 05-06 FY 06-07 FY 07-08 FY 08-09 5,868,796$ 5,868,796$ 1,459,895$ 5,938$ 31,738$ 22,762-$ 136,838$ 1,041,400$ 1,041,400$ 1,062,200$ 1,094,100$ 1,126,900$ 1,160,700$ 1,195,500$ 160,000 160,000 30,000 10,000 11,000 11,000 12,000 855,000 855,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 2,056,400$ 2,056,400$ 1,092,200$ 1,104,100$ 1,137,900$ 1,171,700$ 1,207,500$ 7,925,196$ 7,925,196$ 2,552,095$ 1,110,038$ 1,169,638$ 1,148,938$ 1,344,338$ 0$ 2,000,000$ 0$ 0$ 0$ 0$ 0$ 0 1,000,000 0 0 0 0 0 0 1,000,000 0 0 0 0 0 0 882,056 882,057 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 290,000 0 0 0 0 0 160,000 160,000 0 0 0 0 0 0 0 0 0 200,000 0 0 200,000 200,000 0 0 0 0 0 0 0 680,000 0 0 0 0 0 0 0 0 0 50,000 0 0 50,000 50,000 50,000 50,000 0 0 0 50,000 0 0 0 0 0 376,639 376,639 387,900 399,500 411,500 423,800 436,500 163,809 163,809 263,200 345,800 247,900 255,300 263,000 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 282,797 282,797 283,000 283,000 283,000 283,000 283,000 10,000 10,000 0 0 0 0 0 1,193,245$ 6,465,301$ 2,546,157$ 1,078,300$ 1,192,400$ 1,012,100$ 982,500$ 6,731,951$ 1,459,895$ 5,938$ 31,738$ (22,762)$ 136,838$ 361,838$ 249 Embracing the Past Exploring the Future 250 DDRRAAIINNAAGGEE CCAAPPIITTAALL PPRROOJJEECCTTSS 251 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Bee Creek Channelization PROJECT BUDGET: $2,500.0 Combined PROJECT #:SD9802 & SD9903 PROJECT MANAGER:Laura Harris FUNDING SOURCE(S):Drainage Utility PROJECT DESCRIPTION/JUSTIFICATION: This project will widen the existing drainage channel of Bee Creek Main Channel from Texas Avenue upstream to Southwest Parkway and Bee Creek Tributary B from its confluence with the Main Channel upstream to Harvey Mitchell Parkway. Has CLOMR from FEMA and Individual 404 Permit from USACE. Need land acquisition and final design plans updated for USACE Individual 404 Permit requirements. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 3 295 298 2002-03 12 7 19 2003 -04 15 62 1095 1,172 2004-05 11 1000 1,011 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $30 $375 $2,095 $0 $2,500 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 252 BeeCreek C om bi ned C h a n n e lIm p ro ve m e n ts BeeCreek C om bi ned C h a n n e lIm p ro ve m e n ts T e x a s A v w a t e r / s e w e r r e l o c a t e T e x a s A v w a t e r / s e w e r r e l o c a t e Anderson Stre et Sid e w al k Anderson Stre et Sid e w al k ValleyViewDrValleyViewDrA n d e r s o n S t A n d e r s o n S t A n g e l i n a C r A n g e l i n a C r Lang f o rd S tLang f o rd S t Bee Creek DrBee Creek Dr L a u r a L n L a u r a L n H i l l t o p D r H i l l t o p D rLancelotCrLancelotCrAugustineCtAugustineCtRayburn Ct Rayburn Ct Longmire Ct Longmire Ct Pot o ma cPl Pot o ma cPl S o uthwood Dr S o uthwood DrSouthwest PwSouthwest Pw L o n g mir e D r L o n g mir e D rKrenek Tap RdKrenek Tap Rd T e x a s A v S T e x a s A v S Harvey Mitchell P w SHarvey Mitchell P w S BEE CREEK PARK BEE CREEK PARK ARBORETUM PARK ARBORETUM PARK LEMONTREE PARK LEMONTREE PARK CY MILLER PARKCY MILLER PARK 253 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Bee Creek Phases IV & V PROJECT BUDGET: $1,400 PROJECT #:SD0001 PROJECT MANAGER:Laura Harris FUNDING SOURCE(S):Drainage Utility PROJECT DESCRIPTION/JUSTIFICATION: Storm drainage improvements to the flow capacity of Bee Creek Tributary "A" including bank stabilization from where Phase I improvements ended at Brothers Boulevard to Longmire Drive and continuing to Texas Avenue. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 147 $147 2002-03 22 2003 -04 50 50 2004-05 21 1180 1,201 2005-06 0 2006-07 0 2007-08 0 2008-09 TOTAL $0 $220 $1,180 $0 $1,400 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 254 Lo n g m i r e S t r e e t L i g h t i n g Lo n g m i r e S t r e e t L i g h t i n g Be e C re e k C h a n n e l P h a s e s I V &V Be e C re e k C h a n n e l P h a s e s I V &V Lo n g m i r e S i d e w a l k s Lo n g m i r e S i d e w a l k s Todd TrTodd Tr N o rm a n d C r N o rm a n d C r Long mire Dr Long mire Dr LONGMIRE PARK LONGMIRE PARK 255 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Wolf Pen Creek Channel PROJECT BUDGET: $3,000.0 Improvements PROJECT #:SD9901 & SD9902 PROJECT MANAGER:Laura Harris FUNDING SOURCE(S):Drainage Utility PROJECT DESCRIPTION/JUSTIFICATION: Channel improvements to Wolf Pen Creek from Texas Avenue to the East Bypass (SD9901 & SD9902). The project will provide point repairs to control erosion and sediment along the deteriorated sections of Wolf Pen Creek. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years 224 24 1 249 2002-03 35 35 2003 -04 50 1000 6 1,056 2004-05 25 630 5 660 2005-06 1000 1,000 2006-07 0 2007-08 2008-09 TOTAL $0 $334 $2,654 $12 $3,000 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 256 Southw estParkw ayUndergroundCo n v e r s io n Southw estParkw ayUndergroundCo n v e r s io n W olfPenCreekChannelIm provem en t s W olfPenCreekChannelIm provem en t s Thoroughfare RehabThoroughfare RehabWPClowertrailsandpedestrianbrid g e s WPClowertrailsandpedestrianbrid g e s Fr ont age6RdWFr ont age6RdWFron tage 6 Rd EFron tage 6 Rd EOnramp 6 SOnramp 6 SOnr amp 6 NOnr amp 6 N H o r s e H a v e n L n H o r s e H a v e n L nSwitch Station RdSwitch Station RdOfframp 6 SOfframp 6 SOfframp6NOfframp6NHolleman Dr EHolleman Dr E C e n t r a l P a r k L n C e n t r a l P a r k L n WOLF PEN CREEK PARK WOLF PEN CREEK PARK EASTMARKEASTMARK POSTOAKMALLPOSTOAKMALL SOUTHCREEK PH 1 SOUTHCREEK PH 1 HORSEHAVENESTATESHORSEHAVENESTATES SUTTONPLACESUTTONPLACE ALLENHONDAALLENHONDA WINDWOODWINDWOOD SOUTHWESTCROSSINGSOUTHWESTCROSSING WINDSOR POINTE WINDSOR POINTE WOODSTOCK#1WOODSTOCK#1 257 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Southside Drainage Improvements PROJECT BUDGET: $550 PROJECT #:SD0300 PROJECT MANAGER:Laura Harris FUNDING SOURCE(S):Drainage Utility PROJECT DESCRIPTION/JUSTIFICATION: First Project: Southside System A Drainage Improvements in the amount of $260,000.00 to be reimbursed by Community Development Funds. Includes improvements in the area of Southside bounded by Welsh Ave., Luther Street, Fairview Ave., and Guernsey Street. Improvments includes drainage flume in alley between Welsh and Fairview, ditch section along Welsh from just south of Guernsey to Park Place, rebuilding the street section of Welsh between Luther and Park Place, installation of storm sewer system along Park Place through Luther Jones Park, and valley gutter across Welsh just north of Guernsey. Additional Southside Drainage Improvements will be incorporated into both the West Park Rehabilitation Project and the Breezy Heights/College Park Rehabilitation Project in the Southside Area in future fiscal years. PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 40 40 2003 -04 5 215 220 2004-05 150 150 2005-06 140 140 2006-07 0 2007-08 0 2008-09 TOTAL $0 $45 $505 $0 $550 OPERATING COSTS CATEGORY 1ST F.Y. ANNUAL Personnel Supplies Services Capital TOTAL $0 $0 258 MMAAPP NNOOTT AAVVAAIILLAABBLLEE 259 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Insbruck Detention Pond Access PROJECT BUDGET: $200 PROJECT #:TBD PROJECT MANAGER:Mark Smith FUNDING SOURCE(S):Drainage Utility Fund PROJECT DESCRIPTION/JUSTIFICATION: Construct concrete valley gutter/access-way to provide access to the detention pond on Insbruck STATUS: PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 40 0 40 2003 -04 160 0 160 2004-05 00 0 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $0 $40 $160 $0 $200 OPERATING COSTS CATEGORY 1ST F.Y.ANNUAL Personnel Supplies Services 0 Capital TOTAL $0 $0 260 Innsbruk Detention Pond AccessInnsbruk Detention Pond AccessThoroughfare RehabThoroughfare RehabSophia LnSophia LnEncinas PlEncinas Pl L i e s l C t L i e s l C t C a t e r i n a L n C a t e r i n a L n B o l e r o S t B o l e r o S t A z t e c S t A z t e c S t G r e t a C t G r e t a C t C o r t e z S t C o r t e z S t I n n s b r u c k C r I n n s b r u c k C r D u r a n g o S t D u r a n g o S t C o c h i s e C t C o c h i s e C t EDELWEISSESTATESEDELWEISSESTATES SOUTHWOODVALLEYSOUTHWOODVALLEY ELMCRESTELMCREST 261 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Bee Creek (lancelot to guadalupe) PROJECT BUDGET: $200 PROJECT #:TBD PROJECT MANAGER:Mark Smith FUNDING SOURCE(S):Drainage Utility Fund PROJECT DESCRIPTION/JUSTIFICATION: Erosion repairs and stream restoration. STATUS: PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 00 0 2003 -04 40 160 0 200 2004-05 00 0 2005-06 0 2006-07 0 2007-08 2008-09 TOTAL $0 $40 $160 $0 $200 OPERATING COSTS CATEGORY 1ST F.Y.ANNUAL Personnel Supplies Services 0 Capital TOTAL $0 $0 262 MMAAPP NNOOTT AAVVAAIILLAABBLLEE 263 CAPITAL IMPROVEMENT PROJECT FORM (x $1,000) PROJECT NAME:Stormwater Mapping PROJECT BUDGET: $200 PROJECT #:TBD PROJECT MANAGER:Mark Smith FUNDING SOURCE(S):Drainage Utility Fund PROJECT DESCRIPTION/JUSTIFICATION: Mapping of College Station stormwater infrastructure. STATUS: PROJECT CALENDAR OF EXPENDITURES BY FISCAL YEAR FY LAND ENG. CONSTR. MISC. PROJ. TOTAL Prior Years $0 2002-03 00 0 2003 -04 50 0 50 2004-05 50 50 2005-06 50 50 2006-07 50 50 2007-08 2008-09 TOTAL $0 $200 $0 $0 $200 OPERATING COSTS CATEGORY 1ST F.Y.ANNUAL Personnel Supplies Services 0 Capital TOTAL $0 $0 264 Embracing the Past Exploring the Future 265