HomeMy WebLinkAboutStaff Comments (*ffill111111 CITY OF COLLEGE STATION Planning er' Development Services 1101 Texas Avenue, P.O. Box 9960 College Station, Texas 77842 Phone 979.764.3570 / Fax 979.764.3496 MEMORANDUM March 27, 2006 TO: Todd Carnes, H & C Development, LP FROM: Jennifer Reeves, Project Manager SUBJECT: HERITAGE TOWNHOMES (PDD) - Concept Plan Staff reviewed the above-mentioned concept plan as requested. The following page is a list of staff review comments detailing items that have not been addressed form the first review by Molly Hitchock in November of 2005. The next submittal will be the third and final review by staff for this round of reviews. If all items have not been addressed on the next submittal, another $200 processing fee will need to be submitted for the subsequent set of three (3) reviews. Please address the comments and submit the following information for further staff review: One (1) revised concept plan One (1) revised complete application If there are comments that you are not addressing with the revised concept plan, please attach a letter explaining the details. If you have any questions or need additional information, please call me at 764-3570. Attachments: Staff review comments cc: Case file #05-00500201 Home of Texas A&M University STAFF REVIEW COMMENTS NO. 2 Project: HERITAGE TOWNHOMES (PDD) - 05-00500201 (These are the same comments that have not been addressed since November of 2005). Because substantial information is still needed, the submittal is incomplete. Please see the following comments for guidance in making a complete submittal. PLANNING 1. The application needs to be filled out in its entirety. 2. The other elements of the approved concept plan need to be shown on the new concept plan. As per your submittal, the Design Review Board will only receive a copy of the "Final Plat" showing a pool. The plan should be labeled a "Concept Plan" and should include (graphically or in plan notes) all items that require (or required) modifications from bulk regulations (e.g., setbacks) and all amenities you have provided and are proposing (including landscaping) so that the Board may weigh the pros and cons of the revised request. Reviewed by: Molly Hitchcock Date: November 14, 2005 ENGINEERING 1. As shown, the pool is proposed to be located within a PUE. This will require a PIP application and approval. 2. The pool will also be located within the 100-yr floodplain. All mechanical equipment will have to elevated at least 1 foot above the BFE. 3. Further review is underway to determine the impact/feasibility of the location of the pool in the floodplain. Reviewed by: Carol Cotter Date: November 14, 2005 ELECTRICAL 1. Coordinate electrical changes or needs with College Station Utilities, Electrical Division. 2. To discuss any of the above electrical comments, please contact Gilbert Martinez at 979.764.6255. or email gmartinez@cstx.gov Reviewed by: Gilbert Martinez Date: 11-10-05 NOTE: Any changes made to the plans,that have not been requested by the City of College Station, must be explained in your next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. 2 of 2 CITY OF COLLEGE STATION Planning d Development Services 1101 Texas Avenue,P.O. Box 9960 College Station,Texas 77842 Phone 979.764.3570 / Fax 979.764.3496 MEMORANDUM April 21,2006 TO: Todd Carnes, H & C Development, LP FROM: Jennifer Reeves,Project Manager SUBJECT: HERITAGE TOWNHOMES (PDD) - Concept Plan Staff reviewed the above-mentioned site plan as requested. The following page is a list of staff review comments detailing items that need to be addressed. Please address the comments and submit the following information for further staff review: $200 processing fee for the next round of three (3) staff reviews; One (1) revised concept; One (1) landscaping plan; If there are comments that you are not addressing with the revised site plan,please attach a letter explaining the details. If you have any questions or need additional information,please call me at 979.764.3570. Attachments: Staff review comments Case file#05-00500201 4#1111111111111111 CITY OF COLLEGE STATION Planning 6'Development Services 1101 Texas Avenue, P.O. Box 9960 College Station, Texas 77842 Phone 979.764.3570 / Fax 979.764.3496 MEMORANDUM May 3, 2006 TO: Todd Carnes, H & C Development, LP \'+ r-/W (0613_-139 FROM: Jennifer Reeves, Staff Planner SUBJECT: HERITAGE TOWNHOMES (PDD) Staff reviewed the above-mentioned site plan as requested. The following page is a list of staff review comments detailing items that need to be addressed. Please address the comments and submit the following by 5:00 pm. today. The $200.00 processing fee was due with the last submittal. To continue to move forward with this project please pay this fee with the next submittal. $200 processing fee for the next round of three (3) staff reviews; Ten (10) revised concept plans If there are comments that you are not addressing with the revised site plan, please attach a letter explaining the details. If you have any questions or need additional information, please call me at 979.764.3570. Attachments: Staff review comments cc: Case file # 05-00500201 Home of Texas A&M University STAFF REVIEW COMMENTS No. 4 Project: HERITAGE TOWNHOMES (PDD) - 05-00500201 PLANNING 1. Please list the merritoutiouse modifications for the P.D.D. on the concept plan i.e. setbacks that are being requested and the setbacks that are required for R-3 Townhouse. 2. The original concept plan was approved with a six foot brick wall along the east property line a six foot iron fence along the south property line. 3. (FYI) The original concept plan that was approved was providing a pool, playground, walking path and a gazebo, with the pool being the only amenity being proposed with the revised concept plan staff does not feel like the PDD intent is being met per UDO criteria and will not be supporting this proposal. 4. Please be aware that staff will also be recommending to the Design Review Board that if the concept plan were to be approved that it be approved with a condition that the PUE over the common area be abandoned prior to final staff approval. Reviewed by: Jennifer Reeves Date: May 3, 2006 NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not been pointed out to the City, will constitute a completely new review. 2 of 2 Girl0,544 CITY OF COLLEGE STATION Planning 6-Development Services 1101 Texas Avenue, P.O. Box 9960 College Station, Texas 77842 Phone 979.764.3570 / Fax 979.764.3496 MEMORANDUM August 11, 2006 TO: Todd Carnes, H & C Development, LP, Via Fax 693.7839 & email toddcarnes@tconline.net FROM: Jennifer Reeves, Project Manager SUBJECT: HERITAGE TOWNHOMES (PDD) - Site Plan Staff reviewed the above-mentioned site plan as requested. The following page is a list of staff review comments detailing items that need to be addressed. This item is scheduled to go on the August 25th meeting date for the Design Review Board if the Public utility Abandonment is approved on August 24th by the City Council. Please address the comments and submit the following information by Monday August 14th by 10:00 am to stay on schedule for the August 25th Design Review Board meeting: Eleven (11) revised concept plans One (1)grading plan One (1) development permit If there are comments that you are not addressing with the revised site plan, please attach a letter explaining the details. If you have any questions or need additional information, please call me at 979.764.3570. Attachments: Staff review comments Case file #05-00500201 NOTE: Any changes made to the plans,that have not been requested by the City of College Station,must be explained in your next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. 1 of 2 STAFF REVIEW COMMENTS NO. 5 Project: HERITAGE TOWNHOMES (PDD) - 05-00500201 PLANNING/ENGINEERING 1. Please depict the flood plain on the concept plan. 2. Development permit will be required. 3. Please provide a grading plan. Reviewed by: Jennifer Reeves/Carol Cotter Date: August 9, 2006 NOTE: Any changes made to the plans,that have not been requested by the City of College Station,must be explained in your next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not been pointed out to the City,will constitute a completely new review. 2 of 2 STAFF REVIEW COMMENTS NO.3 Project: HERITAGE TOWNHOMES (PDD) -05-00500201 PLANNING 1. Per Concept Plan checklist please provide the following on the concept plan:: • A key map on the concept plan • Date of the submittal in the title block • 100-year floodplain note,whether it is located on this site or not,referencing FEMA Panel. • Depict all parking areas. • Buildings 2. Per the first two staff review, please provide the landscaping on the concept plan or turn in separate sheet showing the landscaping. 3. Please note all setbacks on the concept plan. 4. Please provide an engineering scale on the concept plan. (1/32 is not an engineering scale) 5. There is a note on the concept plan that refers to sheets LS 2& 3.These sheets have not been submitted to reference. 6. Please list the items/modifications if any(e.g. setbacks,) if they are not being met for R-3. 7. The concept plan does not show a brick wall along the east side property line nor the iron fence to along the south property line. 8. Please show all public utility easements on the concept plan. 9. Please be aware that structures are not permitted in any easements. It appears that the pool is being proposed in a PUE. 10. (FYI) It is staff's opinion that the proposed concept plan is not meeting the PDD intent. Staff strongly recommends that the gazebo and walking path with the pool be relocated to where you are proposing the four lots located at the southeast corner of the property. With the existing detention pond, PUE and common area, it does not make sense to put anything in this area. Staff cannot make a positive recommendation to the Design Review Board of the proposed concept plan. Reviewed by: Jennifer Reeves Date: April 20,2006 HERITAGE TOWN HOMES ACTIVITY REPORT FOR REZONING, PLATTING & CONCEPT PLAN • (1) December 2000 a rezoning for 3500 Harvey Road from A-O Agricultural Open to PDD-H Planned Development District-Housing was approved by the Planning and Zoning Commission.(See Minutes December 7, 2000) MH/TV • (2) January of 2001 a rezoning for 3500 Harvey Road from A-O Agricultural Open to PDD-H Planned Development District-Housing was approved by the City Council with a concept plan. (See Concept Plan and Ord.#2482) MH/TV • (3) March 2001 a Preliminary Plat was approved by the Commission. (See P&Z Minutes March 7, 2001 - Specific Discussions about fencing) TV • (4) May 2001 a Final Plat was approved by the Planning and Zoning Commission. (See P&Z minutes May 3, 2001) TV • (5) May 3, 2005 Molly Hitchcock contacted Todd Carnes about the time line for installing the amenities that were required with the concept plan. (See notes on Molly's calendar) MH • (6)November 7, 2005 Todd Carnes resubmitted a new concept plan and application. • (7)November 14, 2005 Staff Review Comments #1 faxed to Todd ( See Staff Review Comments #1) MH/CC • (8) December 9, 2005 Todd ask Molly' for another copy of Staff review Comments #1. Molly emailed the comments to him the same day. (See email Correspondence) MH • (9) February 17, 2006 An Amending Plat was submitted for Heritage Townhomes by Raybon Metcalf. • (10) February 24, 2006 Staff returned comments to Raybon & Todd. (See Staff review Comments #1) JR/CC • (11) March 14, 2006 (for the March 20th deadline) Todd resubmitted concept plan for review. • (12) March 27, 2006 Staff Review Comments #2 faxed to Todd. (See Staff review Comments#2) JR/CC • (13) April 17, 2006 Todd resubmitted the concept plan. • (14) April 21, 2006 Staff Review Comments #3 faxed to Todd. (See Staff review Comments #3) JR/CC • (15) May 2, 2006 Todd resubmitted the concept plan. • (16) May3, 2006 Staff Review Comments #3 emailed to Todd. (See Staff review Comments #4 and Email correspondence to Todd.) JR/CC • (17) May 5, 2006 Email correspondence between Todd and Jennifer Reeves. • (18) May 9, 2006 Email correspondence between Todd and Jennifer Reeves confirming chain of events to proceed forward. (See email) • (19) May 22, 2006 Raybon Metcalf resubmitted the amending Plat in response to staff review comments. • (20) May 30, 2006 Staff returned Staff Review Comments #2 to Raybon & Todd. (See Staff review Comments #2)JR/CC