PREAPPLICATION CONFERENCE
The purpose of a preapplication conference is to meet the City staff that will be involved with
your development and identify general issues that need further analysis. Along with the
discussion of these major issues, staff will talk about the development process, distribute
necessary information and discuss what permits will be required for your particular
development. This meeting is in no way a complete review of your project. Staff will perform a
formal thorough review once the minimum requirements are submitted for your particular
development.
Date of Meetin II nn a/'
Meeting:LI •g)W Time:c4.0 Vv Deadline for plans (Monday, to am): g
ig
Applicant: bOth( Vi ( LC)1Number: . 0 -504-1 L
.� � Phone
Property Owner: .t,�J(f l &V cE Phone Number:
Project Locati n egal e cription (including'# of acres):
C.�I)H i
Proposal (type of development — retails, apts, SF, restaurant, etc.):
�I_�T i I' att-Va . G
1 I
V V� --H a • 0/1)11P (1 , il4 ') ( --1-1a.: {dr. .
City Staff Present:
❑ Joey Dunn ❑ Alan Gibbs 0 Steve Smith NAV t SGt,Vc-V
❑ Lance Simms 0 Carol Cotter l Thrry Duffey
'ridgette George Era osh Norton ❑ Eric Dotson
❑ Molly Hitchcock 0 Trey Fletcher ❑ Kristan Clann r
fejennifer Reeves 0 Lindsay Boyer pr. �c.4 e d - c/erir
❑ Jennifer Prochazka Limen Fogle ®' Lr••sS� '
� �r 4
Others in attendance:TO e aJ tv1..1r a i r otvi d VI lIa I O lO tS
Issues to contact applicant back on:
km ; S - CAA-wl CAA-woin ve_, 4 .-rx Dir permi+47
Development Issues: Cte,n/ 0)l.Sh I y, eX IS-h 1,. low Id v
J J
Land Use/Existing Zoning kt f P\
Special zoning district information: 4 A
Subdivision/Platting Issues: Ny1-
T-Fare Plan/Street Issues: N'Pt
Driveway Access: '-',A.. `SUIT - C,t3-h 'T Po T?
Fire Flows:&\ l\ nUet r1,2Ov -
Site Plan Issues:
Non-residential architectural standards: Sl lkpiy'U (SQIO 4- 11cd 1aiS'pr Cli✓1
rn
Parking: e4i no(
m lvl i m�wi st�� `S ;
Lighting: JU
Landscaping:appy1ov?d if site, p1a1
Streetscaping: I C3110U e Ve� 25' 'cidd rI tor)a.j ,W0 pi rP.l�
Po i' � Vlc�
Dumpster: X IAO ' .A 'A A. # t. . r1
G
Electrical: i F Cha.01mtfey JOc . cdroujoyHil Sit(, p4 -fo Svl
� C
Fire Lanes: 't l rG e,/.. A I l ',/11 /. .L' ' A A I I aI41 kv1Gr'
•
Fire Hydrant: I-C -4 r&heS ,30I Pic' -i-hel svou i d be, i f eaU
Signs: pcymi+ted Sepeteaki y t0II1 Ile eC 0,A6.-frier r
Screening/Buffering: 1\ !f\
Easements: MA
Other: n0 S14 iJL r,gored 1 4O thvDoci F
dept-h Qin /if-Oil
'
Parks Board Consideration: k1 Jit
Parkland/Greenways Dedication: J'i)A
Drainage Issues: NSA
Misc.:
Utility Issues: 1\1)1A
Water Availability/Capacity: re 4 d etas rt i e
Sanitary Sewer Availability/Capacity: r4 v'f otd� u +s re vi e'v
Impact Fees: NIS
Miscellaneous: De,W1,D[thpgn - j\epd 0,C1/40S SW/W
Variance Requests: NI A
Permits required for this development:
Building Permit
Development Permit
Conditional Use Permit
TxDOT Utility Permit for work in State ROW
TxDOT Driveway Permit for work in State ROW
Special Review required by:
ZBA Design Review Board
City Council Parks and Recreation Board
Planning and Zoning Commission
Information Provided:
Unified Development Ordinance
Subdivision Regulations
Northgate Design Guidelines
Development Resource Guide
Guide to Building & Development
Drainage Policy & Design Standards
Specifications for Street Construction
Water & Sewer Specifications Manual
Driveway Access Location & Design Policy
CS Business Center Covenants & Restrictions
Fire Department Construction & Development Guide
CS Building Regulations (Local Amendments to the Building Code)
10/3/05 Pac Raising Cane's (Old Wings)
• Platted 1938 and re-platted in 1976 in its current configuration.
• Zoned C-1 General Commercial: Restaurant is a permitted use
• Building setbacks as follows: front-25ft, rear-15ft, side-7.5 ft.
• Building Height Section 7.H. Height - Commercial adjacent to Single
Family has a 1:2 slope Building Setback.
• Buffer: Not required. Section 7.6.B. Applicability2. Exceptions to the
terms of this Section will be made when: The property is zoned NG
and RDD.
• 10-ft parking setback from the ROW when parking is provided in the
front of the building (NRA).
• Parking: Restaurant w/drive thru = 1/100 w/out drive thru 1/65
• Dumpster requires a 12x12 pad and to be screened from all rights of
ways with a screening fence and gates. Opening is required to be a
minimum of 12-ft for sanitation truck access.
• 180-sq.ft end islands are required at the end of every parking row and
a 180 sq. ft. interior island is required for 15 interior parking spaces
provided.
• Landscaping requirements: 30 points for every 1000 sq. ft. of site
area.
• Streetscape requirements: one canopy tree for every 25 linear feet of
frontage planted within the first 50-ft. or two non-canopy trees. An
additional 300 points required for every 50-ft of row frontage and can
be dispersed throughout the site.
• 10:00am submission deadline every Monday morning.
• Site plan is to include everything on the check list (i.e. Site, utilities,
grading, erosion control, landscape and irrigation and NRA must be
submitted prior to building permit)
10/3/05 Pac Raising Cane's (Old Wings)
• Platted 1938 and re-platted in 1976 in its current configuration.
• Zoned C-1 General Commercial: Restaurant is a permitted use
• Building setbacks as follows: front-25ft, rear-15ft, side-7.5 ft.
• Building Height Section 7.H. Height - Commercial adjacent to Single
Family has a 1:2 slope Building Setback.
• Buffer: Not required. Section 7.6.B. Applicability2. Exceptions to the
terms of this Section will be made when: The property is zoned NG
and RDD.
• 10-ft parking setback from the ROW when parking is provided in the
front of the building (NRA).
• Parking: Restaurant w/drive thru = 1/100 w/out drive thru 1/65
• Dumpster requires a 12x12 pad and to be screened from all rights of
ways with a screening fence and gates. Opening is required to be a
minimum of 12-ft for sanitation truck access.
• 180-sq.ft end islands are required at the end of every parking row and
a 180 sq. ft. interior island is required for 15 interior parking spaces
provided.
• Landscaping requirements: 30 points for every 1000 sq. ft. of site
area.
• Streetscape requirements: one canopy tree for every 25 linear feet of
frontage planted within the first 50-ft. or two non-canopy trees. An
additional 300 points required for every 50-ft of row frontage and can
be dispersed throughout the site.
• 10:00am submission deadline every Monday morning.
• Site plan is to include everything on the check list (i.e. Site, utilities,
grading, erosion control, landscape and irrigation and NRA must be
submitted prior to building permit)
Rug 22 05 10: 13a CivilTech Enginering 2813040210 p. 2
GENERAL DEVELOPMENT INFORMATION
CITY OF COLLEGE.STAPutnningekDevetopmaitservTION
1101 Texas Avenue
979.764.3570
Pre-Application Conference (PAC)
Request Form
The purpose of a pre-application conference is to meet the City Staff that will be involved
with your development and identify general issues that need further analysis. Along with
the discussion of these major issues, Staff will talk about the development process,
distribute necessary information and discuss what permits will be required for your
particular development. This meeting is in no way a complete review of your project.
Staff will perform a formal thorough review once the minimum requirements are
submitted for your particular development.
Contact Information: Gr,✓/IilecA el•earn
Name
✓�'� I/, E-Mail Address d'4 h/oto'
Phone Number
Z81-304/- OZoo Fax Number W/- 30`e—02-i°
Development proposal for subject property (type of business, square footage, etc.,):
f 3.00 S� W,f4 Jri°,-t< f / 4.
1;5�' 74969� cis f,��row ,,[ 1 J
ofty.o/ete hew 0-7 a 24
Property Owner:
gd:5'1 Canes JZ�Sfa✓r��l/f, L. t . 6.
/69It J j*f /�•ventie , ( 1/( �1%f=o�, 7X
Address/ Location // / ,y �f_ // / //
Mro(/e4 e Hi IIs Es Az 1-"e5 )Z c/190 i✓�'S/Ion rl of /�
Legal Description J
Minimum Submittal Requirements by the Wednesday before the PAC.
1. Site plan, if applicable (2 copies).
2. Survey of property or key map showing location.
Please fax form to 979.764.3496 or e-mail to bgeoraeOcstx.4ov
Upon receipt you will be contacted to schedule a pre-application conference.
72 City of College Station Guide to Building and Development