October 11, 2005
TO: Veronica Morgan, Mitchell and Morgan, via fax: 979-260-3564
FROM: Lindsay Boyer, Project Manager
SUBJECT: SPRING CREEK COMMONS (FP) - Final Plat
Staff reviewed the above-mentioned final plat as requested. The following page is a list of staff
review comments detailing items that need to be addressed. If all comments have been
addressed and the following information submitted by Monday, October 17th, 10:00 a.m., your
project will be placed on the next available Planning and Zoning Commission meeting
scheduled for, November 3rd, 7:00 p.m. in the City Hall Council Chambers, 1101 Texas
Avenue.
Two (2) 24"x36" copies of the revised final plat;
Twelve (12) 11"x17" copies of the revised final plat;
One (1) Mylar original of the revised final plat; and
One (1) copy of the digital file of the final plat on diskette or e-mail to
nmanhart@cstx.gov
Upon receipt of the required documents for the Planning & Zoning meeting, your project will be
considered formally filed with the City of College Station. Please note that if all comments have
not been addressed your project will not be scheduled for a Planning & Zoning Commission
meeting. Your project may be placed on a future agenda once all the revisions have been made
and the appropriate fees paid. If you have any questions or need additional information, please
call me at 979.764.3570.
Attachments: Staff review comments
cc: Quorum Equities Group, LLC, via U.S. Mail
Case file #05-00500176
Home of Texas A&M University
STAFF REVIEW COMMENTS NO. 1
Project: SPRING CREEK COMMONS (FP) - 05-00500176
ENGINEERING
1. Please provide a point of origin for the plat, preferably from a monument.
2. Include note from preliminary plat in regards to temporary turn around. "Lakeway Drive will
not be required to have a temporary cul-de-sac with each phase of construction as long as
an adjacent site plan, with a driveway located near the end of Lakeway Drive is constructed
concurrently with Lakeway Drive. This site plan, and its associated on site fire lane, must be
adequate to function in lieu of the temporary cul-de-sac."
3. What is the dashed line on the west side of the subject property that continues thru the
property to the northwest?
4. The previously agreed upon conditions associated with Development Permit 04-62 have
been attached. Per the Development Permit, a right turn lane will be required with this site
plan that utilizes the subject driveway in the event that the McDonalds/Exxon driveway
remains open and a joint access is not dedicated. It appears that there is sufficient ROW for
the required right turn lane; however existing utility relocation may be required.
5. The construction documents and reports are still under review and may affect the plat.
Reviewed by: Lindsay Boyer/Josh Norton Date: October 11, 2005
ELECTRICAL
1. Developer installs conduit per city specs and design.
2. Developer provides 30' of rigid conduit for riser poles.
3. Developer pours transformer pad(s) per city specs and design.
4. Developer installs pull boxes as per city specs and design.(pull boxes provided by the
city).
5. Developer provides digital AutoCAD 2000 version of plat and/or site plan email to
tmichals@cstx.gov
6. Developer provides load data for project.
7. Developer provides temporary blanket easement for construction purposes.
8. Developer provides easements for electric infrastructure as installed for electric lines.
9. Developer if responsible for the installation of street light along Lakeway Drive per city
specs and design.
10. If any pole conflicts at intersection of Greens Pr Rd and Lakeway Dr., relocation cost will
be the responsibility of the developer.
11. To discuss any of the above electrical comments, please contact Gilbert Martinez at
979.764.6255. / Sam Weido at 979.764.6314. /Tony Michalsky at 979.764.3438.
Reviewed by: Tony Michalsky or Brent Read Date: October 6, 2005
FIRE
1. No comments
Reviewed by: Steve Smith Date: October 6, 2005
NOTE: Any changes made to the plans,that have not been requested by the City of College Station, must be explained in your
next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not been pointed out
to the City,will constitute a completely new review.
Page 2 of 2