HomeMy WebLinkAboutCost Estimate .iiaterwood Townhomes Phase b
Engineer's Estimate
Public Infrastructure Only
General ._._.
1 Mobilization LS 1 $10,000 $10,000
Water
2 6"PVC AWWA C909 CL200 Water Line with Structural Backfill LF 920 $30 $27,600
3 3"PVC ASTM D2241-CL200 LF 39 $15 $585
4 6"x 45 MJ Bend EA 6 $350 $2,100
5 6"x 90 MJ Elbow EA 1 $350 $350
6 6"x 6"MJ Tee EA 7 $600 $4,200
7 6"MJ Gate Valve&Box EA 6 $800 $4,800
8 Connect to Existing System EA 2 $2,000 $4,000
9 Standard Fire Hydrant Assembly EA 2 $3,000 $6,000
10 Trench Safety LF 920 $4 $3,680
Contingency 15% $9,497
General Total $10,000
Water Total $53,315
Grand Total $72,812