MEMORANDUM
September 16, 2005
TO: Veronica J. B. Morgan, Mitchell & Morgan, LLP, via fax 979.260.3564
FROM: Molly Hitchcock, Staff Planner
SUBJECT: WATERWOOD CONDOS PH 5 (SP) -Site Plan
Staff reviewed the above-mentioned site plan as requested. The following page is a list of staff
review comments detailing items that need to be addressed. The next submittal will be the third
and final review by staff for this round of reviews. If all items have not been addressed on the
next submittal, another $200 processing fee will need to be submitted for the subsequent set of
three (3) reviews. Please address the comments and submit the following information for
further staff review:
Six (6) complete sets of construction documents for the proposed development
with the revised site and landscaping plans attached (please submit additional
copies to be stamped for your records).
Two (2) revised site plans
One (1) landscaping plan
One (1) 11x17 grading and erosion control plan
If there are comments that you are not addressing with the revised site plan, please attach a
letter explaining the details. If you have any questions or need additional information, please
call me at 764-3570.
Attachments: Staff review comments
cc: Jim Stewart, via fax 817.429.8664
Case file #05-00500150
Home of Texas A&M University
STAFF REVIEW COMMENTS NO. 2
Project: WATERWOOD CONDOS PH 5 (SP) - 05-00500150
PLANNING
1. No comment.
Reviewed by: Molly Hitchcock Date: September 16, 2005
ENGINEERING
1. The 3-inch water line requires a 2-inch blowoff, instead of the 1-inch blowoff that is shown.
Reviewed by: Carol Cotter Date: September 13, 2005
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your
next transmittal letter and`bubbled"on your plans.Any additional changes on these plans that have not been pointed out
to the City,will constitute a completely new review. 2 of 2
CITY OF COLLEGE STATION
Planning e'r Development Services
1101 Texas Avenue, P.O. Box 9960
College Station, Texas 77842
Phone 979.764.3570 / Fax 979.764.3496
MEMORANDUM
September 6, 2005
TO: Veronica J. B. Morgan, Mitchell & Morgan, LLP, via fax 979.260.3564
FROM: Molly Hitchcock, Staff Planner
SUBJECT: WATERWOOD CONDOS PH 5 (SP)-Site Plan
Staff reviewed the above-mentioned site plan as requested. The following page is a list of staff
review comments detailing items that need to be addressed. Please address the comments
and submit the following information for further staff review:
One (1) complete set of construction documents for the proposed development
with the revised site and landscaping plans attached
Easement Dedication Sheet and required documents (please allow 4 weeks to
process).
Please note that the Easement Dedication Sheet and the necessary documents are required
prior to the issuance of a building permit. If there are comments that you are not addressing
with the revised site plan, please attach a letter explaining the details. If you have any
questions or need additional information, please call me at 979.764.3570.
Attachments: Staff review comments
cc: Jim Stewart, via fax 817.429.8664
Case file#05-00500150
Home of Texas A&M University
STAFF REVIEW COMMENTS NO. 1
Project: WATERWOOD CONDOS PH 5 (SP) —05-00500150
PLANNING
1. Please provide total site area for Ph. 5 on the site plan.
2. Please identify building setbacks on the site plan.
3. Landscaping will be reviewed when submitted.
Reviewed by: Molly Hitchcock Date: September 2, 2005
ENGINEERING
1. Blow off required at end of 3" water line.
2. Private sewer shall meet plumbing code regarding slope, cleanouts, etc.
3. As discussed with Phase 4, public water main requires a PUE. Please show proposed
PUE or note on plans.
4. On previous phases the water taps were double, but this phase shows a single tap for
each unit. What is the reasoning?
5. FYI: A Development Permit was submitted for Phase 4&5 combined (Rough Grading).
I am assuming a full development permit will follow under the same permit. As
submitted the public infrastructure will only be accepted when both phases are
complete. To have each phase accepted individually will require a separate DP for
Phase 5.
Reviewed by: Carol Cotter Date: September 1, 2005
ELECTRICAL
1. Developer installs conduit per city specs and design.
2. Developer will furnish and install 2-6" pvc conduits along Central Park Lane as shown on
CSU electrical layout.
3. Developer will intercept existing conduit at existing junction box#2747-00 and extend as
shown. If conduit does not exist developer will furnish and install conduit and extend as
shown.
4. Developer pours transformer pad(s) per city specs and design.
5. Developer installs pull boxes as per city specs and design (pull boxes provided by the
city).
6. Developer provides digital AutoCAD 2000 or later version of plat and/or site plan email to
qmartinezcstx.qov.
7. Developer provides easements for electric infrastructure as installed for electric lines.
8. To discuss any of the above electrical comments, please contact Gilbert Martinez at
979.764.6255.
Reviewed by: Gilbert Martinez Date: 09-01-05
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your
next transmittal letter and`bubbled"on your plans.Any additional changes on these plans that have not been pointed out
to the City,will constitute a completely new review.
Page 2 of 3
MISCELLANEOUS
1. Irrigation system must be protected by either a Pressure Vacuum Breaker, a Reduced
Pressure Principle Back Flow Device, or a Double-Check Back Flow Device, and installed
as per City Ordinance 2394.
2. All BackFlow devices must be installed and tested upon installation as per City Ordinance
2394.
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your
next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not been pointed out
to the City,will constitute a completely new review.
Page 3 of 3