HomeMy WebLinkAboutStaff ReportSTAFF REPORT
Item: Consideration of a final plat for Edelweiss Estates Phase 14 (16.634
acres) located west of Phase 15B and northwest of Phase 12. The property is
located adjacent to and immediately east of Welborn Road and south of
Fraternity Row. (00-73)
Applicant: STEVE ARDEN representing Begonia Corporation.
Item Summary: The Phase 14 final plat includes 50 single family (0.28 ac. avg.
lots and is in compliance with the Edelweiss Master Development Plan which
was approved in September 1997.
Budgetary & Financial Summary: N/A
Staff Recommendations: Staff recommends approval of the final plat as
submitted.
Commission Action Options: The Commission has final authority over the final
plat. The options regarding the final plat are approval as submitted, or denial.
Defer action or table only at applicant's request.
Supporting Materials:
1. Location Map
2. Application
3. Infrastructure and Facilities
4. Copy of Final Plat
INFRASTRUCTURE AND FACILITIES
Water: Existing infrastructure is adequate for the proposed use. New infrastructure will be
extended within this subdivision to serve the residential development.
Sewer :Existing infrastructure is adequate for the proposed use .New infrastructure will be
extended within the subdivision to serve the residential development.
Streets : Residential streets to be constructed are as follows :Phase 14-- Sophia Lane will be
extended from Edelweiss Phase IS-B west to near Welborn Road. Streets running south from
Sophia Lane starting from the east are :Salzburg Court ,Von Trapp Lane and Neuburg Court.
Phase 16--Marta Street will run from Edelweiss Avenue west to near Welborn Road. Streets
running north from Marta Street starting from the east are :Von Trapp Lane and Fredrick Court.
Hannover Street will run from Von Trapp Lane west to Wellborn Road. Hannover Street has 60'
R O W and 39' pavement. All other streets have 50' R O W and 28' pavement.
Off-site Easements : N/A
Sidewalks :Sidewalks will be constructed on the south side of Sophie Lane ,the east side of Von
Trapp Lane ,the north side of Marta Street and on both sides of Hannover Street.
Drainage : A detention facility will be constructed in the northwest corner of Phase 14 to serve
both Phase 14 and Phase 16.
Floodplain :There is no floodplain located on these properties.
Oversize Request :None
Parkland Dedication :This dedication was handled in previous phases of Edelweiss Estates.
Impact Fees :None
NOTIFICATION
Advertised Commission Hearing Date(s): 5-04-00