HomeMy WebLinkAboutStaff Comments STAFF REVIEW COMMENTS NO. 2
Project: A&M UNITED METHODIST FELLOWSHIP HALL
ENGINEERING
1. The sewer connection shown on Sheet C-1 includes a manhole in the middle of
Patricia Street. The preferred connection location is approximately 40-ft northeast
at an existing manhole. Connecting at the existing manhole will require additional
piping on the private side but will preclude the construction of a manhole and be
less of an impact upon public infrastructure.
2. Please provide detail of water line and meter connection at west most building
corner.
3. Please be advised that Public Access Easements are required. Public Utility
Easements may be required, as well.
4. REMOVE NOTE 15 CONCERNING CONTRACTOR TO REMOVE! REPLACE
PARKING METERS. THE CONTERACTOR DOES NOT HAVE THE AUTHORITY
TO REMOVE/ REPLACE PARKING METERS.
5. Crosswalk striping in ROW is to be done by the Public Works Department. You may
show "proposed" striping or removal, however all striping/ removal is to be done by
the City. You may contact Mr. Dale Picha, P.E. for more information.
Reviewed by: Spencer Thompson Date: March 12, 2003
NOTE: Any changes made to the plans,that have not been requested by the City of College Station, must be explained in your
next transmittal letter and"bubbled'on your plans.Any additional changes on these plans that have not been pointed out
to the City,will constitute a completely new review.
2 of 2