HomeMy WebLinkAboutStaff Comments •
CITY OF COLLEGE STATION
DEVELOPMENT SERVICES
1101 Texas Avenue South, PO Box 9960
COLLEGE STATION College Station, Texas 77842
Phone 979.764.3570 / Fax 979.764.3496
MEMORANDUM
February 28, 2003
TO: Mike Tomchesson, Via fax 696.5045
FROM: Bridgette George, Assistant Development Manager
SUBJECT: SOUTHWOOD VALLEY SECT 19, L2R, B14C (FP) - Final Plat
Staff reviewed the above-mentioned final plat as requested. The following page is a list
of staff review comments detailing items that need to be addressed. Please address the
comments and return the following for the plat to be filed at the Brazos County
Courthouse:
One (1) copy of the revised final plat;
One (1) Mylar original of the revised final plat; and
One (1) copy of the digital file of the final plat on diskette or e-mail to
nmanhart@ci.college-station.tx.us
If you have any questions or need additional information, please Carol Cotter or myself
at 764-3570.
Attachments: Staff review comments
cc: Christian A. Galindo Via fax 846-8868
Case file #03-00500048
Home of Texas A8&M University
STAFF REVIEW COMMENTS NO. 1
Project: SOUTHWOOD VALLEY SECT 19, L2R, B14C (FP) - 03-00500048
ENGINEERING
1. Existing 20' PUE along southern boundaries of Lots 1 and 2R of Existing Plat
measure 30' graphically. Please rectify.
Reviewed by: Carol L. Cotter Date: February 28, 2003
ELECTRICAL
1. Developer installs conduit per city specs and design.
2. Developer provides 30' of#4 rigid conduit for riser poles. Developer installs
first 10'. City installs remainder.
3. Developer pours transformer pad(s) per city specs and design.
4. Developer installs pull boxes as per city specs and design.(pull boxes
provided by the city.
5. Developer provides digital AutoCAD 14 version of plat and/or site plan.
email to rbolin(a�ci.college-station.tx.us
6. Developer provides load data for project.
7. Developer provides temporary blanket easement for construction
purposes.
8. Developer provides easements for electric infrastructure as installed for
electric lines.
Reviewed by: Ronnie Bolin Date:2-20-03
NOTE: Any changes made to the plans,that have not been requested by the City of College Station, must be explained in your
next transmittal letter and"bubbled"on your plans.Any additional changes on these plans that have not been pointed out
to the City,will constitute a completely new review.
Page 2 of 2