HomeMy WebLinkAboutCorrespondenceMs. George September 19, 2005 Page 2 9. OK, the oversize participation request will be provided after the approval of the on -site utilities plans. 10. N /A, Public ROW has been removed from the plat. 11. The drainage report will be provided with the site plan or final plat. 12. The utility reports will be provided with the site plan or final plat. 13. ILA correspondence has been previously transmitted. 14. The existing and proposed utilities are shown. 15. N /A; Public ROW has been removed from the plat. 16. N /A; Public ROW has been removed from the plat. 17. The previous plat was performed on an older boundary survey that was performed by others. The attached plat is based on a boundary that we performed that closes within tolerances. ELECTRICAL: 1. OK 2. OK 3. OK 18. OK 19. OK 20. OK 21. OK 22. OK 23. OK 24. OK Very Truly Yours, Steve E. Duncan, P.E. sed @pkengineering.com SED /mon Enclosures cc: David Hillman From: Tony Michalsky To: Alan Gibbs; Trey Fletcher Date: 9/21/2005 3:58:56 PM Subject: Valley Park subdivision, Hwy 60 and 2818 Valley Park subdivision, Hwy 60 and 2818 They submitted a preliminary plat for review. We have a powerline across the property. We have been working with them on the relocation of the powerline. They will be submitting a temporary blanket easement on the property once the close the deal (supposedly in a week or so). We will not need a permanent easement to cover the line. We will be relocating our powerline along the rear of the property an all easement will be dedicated with the plat. If you have any question give me a call, 3438 From: "Steve Duncan" <sed @pkengineering.com> To: "David Hillman" <dhillman @southcorprealty.com> Date: 8/10/2005 4:37:26 PM Subject: FW: FM 2818 & FM 60 8/10/05 <><><> < > < > < > < > < > < > < > < > < > < > < > < > < > < > < >< Steve E. Duncan, P.E., V.P. Pledger Kalkomey, Inc. - Consulting Engineers 7020 Coyote Run, Bryan, Texas 77808 979 - 731 -8000 (voice), 979 - 731 -1500 (fax) sed @pkengineering.com <><><> < > < > < >< > < > < > < > < >< > < > < >< > < > < > < >< - - - -- Original Message---- - From: Jay Page [mailto:JPAGE @dot.state.tx.us] Sent: Wednesday, August 10, 2005 3:56 PM To: Kfogle @cstx.gov Cc: Karl Nelson; sed @pkengineering.com; d.bird @verizon.net Subject: Re: FM 2818 & FM 60 8/10/05 Ken- Attached are the comments for Valley Park Center located @ the NW corner of FM 2818 & FM 60. 1 will send you comments on your other access question @ FM 2154 & SW Parkway later today or in the AM. Jay No virus found in this incoming message. Checked by AVG Anti - Virus. Version: 7.0.338 / Virus Database: 267.10.5/67 - Release Date: 8/9/2005 No virus found in this outgoing message. Checked by AVG Anti - Virus. Version: 7.0.338 / Virus Database: 267.10.5/67 - Release Date: 8/9/2005 CC: "Trey Fletcher" <tletcher @cstx.gov >, "Alan Gibbs" <agibbs @cstx.gov> From: "Steve Duncan" <sed @pkengineering.com> To: "Trey Fletcher" <tletcher @cstx.gov >, "Allan Gibbs" <agibbs @cstx.gov> Date: 7/20/2005 11:21:34 AM Subject: FW: valley park center see if it comes through this time... <><><> < > < > < > < > < > < > < > < > < > < > < > < > <> <> < >< Steve E. Duncan, P.E., V.P. Pledger Kalkomey, Inc. - Consulting Engineers 7020 Coyote Run, Bryan, Texas 77808 979 - 731 -8000 (voice), 979 - 731 -1500 (fax) sed @pkengineering.com <><><> < > < >< > < > < > < >< > < > < > < > < > < >< > < > < >< - - - -- Original Message---- - From: Steve Duncan [mailto:sed @pkengineering.com] Sent: Tuesday, July 19, 2005 3:36 PM To: Jay Page Cc: Allan Gibbs; Trey Fletcher; David Hillman; Kirk Springer; Graham Martin Subject: valley park center jay: enclosed is a 11x17 pdf site plan for the referenced project at fm 2818 and fm 60. please comment on the following: - drive #2 location as it relates to the gore - drive #3 geometry as it relates to the fm 60 frontage road - storm drainage from the detention facility to the storm inlet thanks <><><> < > < > < > < > < > < > < > < > < > < > < > < > < > < > <>< Steve E. Duncan, P.E., V.P. Pledger Kalkomey, Inc. - Consulting Engineers 7020 Coyote Run, Bryan, Texas 77808 979 - 731 -8000 (voice), 979 - 731 -1500 (fax) sed @pkengineering.com <><><> < > < > < > < > < > < > < > < > < > < >< > < > < > < > < >< No virus found in this outgoing message. Checked by AVG Anti - Virus. Version: 7.0.323 / Virus Database: 267.9.1/51 - Release Date: 7/18/2005 No virus found in this outgoing message. Checked by AVG Anti - Virus. Version: 7.0.323 / Virus Database: 267.9.2/52 - Release Date: 7/19/2005 0 -1: S 42° 25'09" E 187.17 1 -2: S 39° 50'26" E 379.05 2 -3: S 35° 42' 32" E 401.44 3 -4: S 28° 21'37" E 552.01 4 -5: S 10° 36' 10" E 251.74 5 -6: N 45 °36'49" W 1154. 6 -7: N 45° 19'08" W 562.E 8 -9: f N 44° 49' 58" E 42 WC Scale: 200 feet per inch. MEMORANDUM To: City of College Station From: Karl Nelson, TxDOT Date: July 22, 2005 Subject: SITE DEVELOPMENT COMMENTS - -- July 18, 2005 NEW DEVELOPMENT IN COLLEGE STATION - WEEK OF 7/18/05 1. Park Place Cross Roads (Site Plan) (BS 6- R) - If no additional Access is required, No Comment. Sidewalk, etc. construction within the Texas Avenue ROW should be deleted due to conflicts with ongoing TxDOT widening project. TxDOT to provide'City approved type sidewalk @ site. Appropriate data will be required for any future work /permits in the ROW @ this site. 2. Valley Park Center (Preliminary Plat) (FM 2818) - Access driveways to FM 2818 must meet TxDOT's current "'Regulations for Access Driveways to State Highways ". Regulations are primarily based on posted speed limits and distances between proposed & adjacent access points. Where posted speed limits are 50 MPH or more the required spacing between access points is 425'. Where driveway spacing is insufficient joint access will be required. Access to Lot 4 may require a decel lane due to possible conflicts with exit ramp traffic Preferable access to Lots 3 & 4 would be from Frontage Road stub -out. Appropriate data will be required for any future permits @ this development site. >>> " Mandi Alford" < Malford(aD_cstx.gov > The following attachment is the list of new development projects submitted to Development Services this week. (7/18/05) Mandi Alford Staff Assistant City of College Station Development Services 1101 Texas Avenue College Station, Tx 77840 (979) 764 -3570 P = Pledger Kalkomey, Inc. K I Consulting Engineers October 10, 2005 Ms. Bridgette George City of College Station P.O. Box 9960 College Station, Texas 77842 Re: Preliminary Plat Valley Park Center PK Job No. 51905 -231 Dear Ms. George, D I . 5 V t , ;J Enclosed please find the following for the referenced project: 1. One (1) Mylar copy of the approved preliminary plat. (P &Z Meeting Oct. 6, 2005) 2. An electronic copy (AutoCAD 2002) of the preliminary plat was emailed to Nanette Manhart this morning. If you have any questions, Thanks. please feel free to contact me. Very Truly Yours, "0, L)4 �X Tim O. Wolf , E.I.T. tow@pkengineering.com Enclosures 7020 Coyote Run Bryan, Texas 77808 979 - 731 -8000, 979 - 731 -1500 (Fax) www.pkengineerin(l.com Brenham - Bryan • Rosenberg S:\2005 \51905 -231 SOUTHCORP -Por Nada\CS- 13- prehtn plat Mylar & CAD submittal.doc P = Pledger Kalkomey, Inc. K Consulting Engineers July 18, 2005 Ms. Bridgette George City of College Station P.O. Box 9960 College Station, Texas 77842 Re: Preliminary Plat Valley Park Center Off -Site Utilities PK Job No. 51905 -231 Dear Mrs. George, 7020 Coyote Run Bryan, Texas 77808 979 - 731 -8000, 979 - 731 -1500 (Fax) www.pkengineering.com Enclosed please find the following for the referenced project: 1. Preliminary Plat Application including all of the Minimum Submittal Requirements. 2. Preliminary Plat and Staff Review Comments Memorandum previously submitted by MDG in 2002 for the same property for your reference. It is noted that a Rezoning Application has been previously submitted requesting that a portion of the site be changed from Cl to C2. Very Truly Yours, Steve E. Duncan, P.E. sed @pkengineering.com SED /mon Enclosures cc: David Hillman Brenham • Bryan • Rosenberg 5:\2005 \51905 -231 SOUTHCORP -Por Nada \CS -04- prelim plat.doc From: Alan Gibbs To: Duncan, Steve; George, Bridgette Date: 8/3/2005 2:36:42 PM Subject: RE: valley view, off -site update See bold responses below. Alan Alan P. Gibbs, P.E. Sr. Asst. City Engineer - Development Public Works Department City of College Station P. O. Box 9960 College Station, Texas 77842 Ph: (979) 764 -3570 Fx: (979) 764 -3496 agibbs @cstx.gov www.cstx.gov >>> "Steve Duncan" <sed @pkengineering.com> 8/1/2005 4:49:06 PM >>> hey guys - forgot to list the TAMU interlocal agreement correspondence also... <><><> < > < > < > < > < > < > <> < > < > < > < > < > < > < > < >< Steve E. Duncan, P.E., V.P. Pledger Kalkomey, Inc. - Consulting Engineers 7020 Coyote Run, Bryan, Texas 77808 979 - 731 -8000 (voice), 979 - 731 -1500 (fax) sedapkengineering.com <><><> < > < > < >< > < > < > < > < > < > < >< > < > < > < > < >< > - - - -- Original Message - - -- • From: Steve Duncan fmailto:sed(-pkengineering.coml • Sent: Sunday, July 31, 2005 9:06 PM • To: Bridgett George • Cc: Trey Fletcher; Allan Gibbs; Spencer Thompson; David Hillman; Tim • Wolff • Subject: valley view, off -site update > bridgett/trey /allan /spencer: • we received bids on the project yesterday and are ready to start • construction on the off -site utilities. please update me on the • following: > EASMENTS: • i dropped of the easment dwg and field notes for the benson tract utitliy • easement dated july 25th with bridgett's name on the cover letter. it is • part of the development permit for the off -site plans that were delivered • on the 18th. i forgot to include the easement dedication sheet and needed • to know how to go about getting it to the right person. is there a person • at legal that i should contact? what is the expected delivery date? • also, i will need to do another very similar easment on the por nada part • of our tract so i want to make sure and get it to the right person as • well. • Bridgette addressed in a separate email. • TXDOT UTILITY PERMIT: • i dropped off the txdot utility permit dated july 22nd with bridgett's • name on the cover letter. status? expected delivery? • The TxDOT permit will be forwarded upon meeting City's comments on the Construction Plans. • OFF -SITE PLANS: • i dropped off the off -site water and sewer plans on the 18th with the • development permit. review status? • Construction Plan comments should go out tommorrow. Additionally, I will Jim Riley with TAMU. • OP REQUEST: • just to repeat from our meeting tuesday, the off -site op request that i • turned in with the development permit on the 18th will be several months • away but will not hold up construction. • Correct. ><><><><><><><><><><><><><><><><><><>< > Steve E. Duncan, P.E., V.P. > Pledger Kalkomey, Inc. - Consulting Engineers > 7020 Coyote Run, Bryan, Texas 77808 > 979 - 731 -8000 (voice), 979 - 731 -1500 (fax) > sed(cDpkenQineering.com ><><><><><><><><><><><><><><><><><><>< • No virus found in this outgoing message. • Checked by AVG Anti - Virus. • Version: 7.0.338 / Virus Database: 267.9.7/60 - Release Date: 7128/2005 No virus found in this outgoing message. Checked by AVG Anti - Virus. Version: 7.0.338 / Virus Database: 267.9.7/60 - Release Date: 7/28/2005 CC: Fletcher, Trey; Hillman, David; Thompson, Spencer; Wolff, Tim From: Bridgette George To: Steve Duncan Date: 8/1/2005 7:32:38 AM Subject: Re: valley view, off -site update Good morning! As far as the easements go, please submit the Easement Dedication Sheet and all necessary attachments to Deborah Grace in our department, she will process it and submit it to our Legal Department as soon as it is reviewed by the Engineer. The process takes approximately 2 -3 weeks depending on a complete submittal and if all the documents you submit are current. Please contact Deborah Grace if you have any further questions. Thanks! Bridgette George '04 Development Coordinator City of College Station P.O. Box 9960 College Station, TX 77842 -9960 979.764.3570 www.cstx.gov >>> "Steve Duncan" <sed @pkengineering.com> 31- Jul -05 9:06 PM >>> bridgett/trey /allan /spencer: we received bids on the project yesterday and are ready to start construction on the off -site utilities. please update me on the following: EASMENTS: i dropped of the easment dwg and field notes for the benson tract utitliy easement dated july 25th with bridgett's name on the cover letter. it is part of the development permit for the off -site plans that were delivered on the 18th. i forgot to include the easement dedication sheet and needed to know how to go about getting it to the right person. is there a person at legal that i should contact? what is the expected delivery date? also, i will need to do another very similar easment on the por nada part of our tract so i want to make sure and get it to the right person as well. TXDOT UTILITY PERMIT: i dropped off the txdot utility permit dated july 22nd with bridgett's name on the cover letter. status? expected delivery? OFF -SITE PLANS: i dropped off the off -site water and sewer plans on the 18th with the development permit. review status? OP REQUEST: just to repeat from our meeting tuesday, the off -site op request that i turned in with the development permit on the 18th will be several months away but will not hold up construction. <><><> < >< > < > < > < > < > < > < > < > < > < >< > < >< > < >< Steve E. Duncan, P.E., V.P. Pledger Kalkomey, Inc. - Consulting Engineers 7020 Coyote Run, Bryan, Texas 77808 979 - 731 -8000 (voice), 979 - 731 -1500 (fax) sed(a)pkengineering.com <><><> < > < > < > < > < >< > < > < > < > < > < > < > < > < >< >< No virus found in this outgoing message. Checked by AVG Anti - Virus. Version: 7.0.338 / Virus Database: 267.9.7/60 - Release Date: 7/28/2005 CC: Alan Gibbs; David Hillman; Deborah Grace; Spencer Thompson; Tim Wolff; Trey Fletcher