HomeMy WebLinkAboutStaff CommentsCITY OF COLLEGE STATION Planning & Development Services 1101 Texas Avenue, P.O. Box 9960 College Station, Texas 77842 Phone 979.764.3570 / Fax 979.764.3496 MEMORANDUM DATE: July 5, 2005 TO: Stephen E. Duncan, P.E., via fax 731 -1500 FROM: Lindsay Boyer, Project Manager SUBJECT: COLLEGE STATION PROF. BLDG TWO (SP) - Site Plan Staff reviewed the above - mentioned site plan as requested. The following page is a list of staff review comments detailing items that need to be addressed. Please address the comments and submit the following information for further staff review: One (1) complete sets of construction documents for the proposed development with the revised site and landscaping plans attached (please submit additional copies to be stamped for your records) One (1) 11 x17 grading and erosion control plan Easement Dedication Sheet and required documents (please allow 4 weeks to process). Please note that the Easement Dedication Sheet and the necessary documents are required prior to the issuance of a building permit. If there are comments that you are not addressing with the revised site plan, please attach a letter explaining the details. If you have any questions or need additional information, please call me at 979.764.3570. Attachments: Staff review comments cc: Walt Schoenvogel, via fax 830 -1363 Case file #05- 00500113 Home of Texas A &M University STAFF REVIEW COMMENTS NO. 1 Project: COLLEGE STATION PROF. BLDG TWO (SP) — 05- 00500113 PLANNING 1. 2. 3. 4. 5. 6. 7. 10 11 12 13 14 15 16 Is North Arrow correct on key map? Provide date of submittal in title block. Month and year is sufficient. The rear building setback should be 15' Please dimension and show bicycle parking facilities in compliance with Section 7.9.F of the UDO. Please provide the dimensions for the driveway throat depth. It appears that it might be a little short of the required 55' Please provide dimensions for opposite right and left driveways. Proposed parking on the Ponderosa #2 tract does not have end islands on the east side of the parking lot. Also, it looks like the curb is inverted, the last space in each row is not usable in that configuration. End islands must be 180 s.f. for the end of each row. It appears that the end islands on the east side of the rear parking rows have islands less than this requirement. Please review the parking requirements for Non - Residential Architectural standards in Section 7.9.H of the LIDO. These requirements are in addition to the requirements for end islands and interior islands. Please make changes to the parking plan in accordance with this section. Currently, the parking lot does not meet the requirements for parking lots over 120 spaces. Please provide the square footage for each use that will be in the building. Parking ratios are different for office (1/250 s.f.) than medical clinics (1/200 s.f.). Also, medical clinics must be less than 20,000 s.f. Otherwise, it will be classified as a hospital. Calculate required parking appropriately. Please provide site plans with number of parking spaces required and provided for the lots that are providing excess parking for this lot, if additional off -site parking will be required upon recalculation of the parking ratios. Please show where the additional parking is located on the other sites. Please be aware that the parking may be no further away than 250 feet from the site. Please clarify all curbing that will be removed between the site and the Remington Lot. Please provide an access easement for the subject property to access the off -site parking on the neighboring lots. This easement is to protect the parking circulation should either of the neighboring properties be sold. Fire lanes should be 26' feet on at least one side of the building for building over 30' feet in height for an aerial apparatus to access the building. Our measurements do not show any fire lane with this width. Please provide screening details for all mechanical equipment. Building elevations and material samples must be reviewed prior to the issuance of a building permit for compliance with the Non - Residential Architectural standards. Reviewed by: Lindsay Boyer Date: June 30, 2005 LAN DSCAPING/STREETSCAPI NG/BUFFER 1. Please extend parking screening into end building. islands around the parking in the front of the NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out to the City, will constitute a completely new review. Page 2 of 3 2. 3 a It is difficult to determine with the legend that is used for the parking screening if the parking will be 100% screened. Please be aware, that at the time of CO, if the parking is not 100% screened, more plantings may be required. All islands must be planted or treated with enhanced paving. Please indicate this on the plan. Irrigation plan must be reviewed and approved prior to Certificate of Occupancy. All plantings must be irrigated. Reviewed by: Lindsay Boyer ENGINEERING Date: June 30, 2005 1. Provide sewer and water demanded 2. Meters must be located within an easeme* 0 Provide fire flow repcO—"* (? Provide drainage repoW"" In regards to the connection to the existing 8in. water main, a tapping sleeve and valvD- may be a better connection in this particular case. TCEQ 290 Appendix I, requires a RPBA for each of the fire and domestic water IinerF going into the building. Verify that fire lane continues around the building with adjacent properties fire lane 8. Upon review of the next submittal the fire department will approve the fire hydrard.-- layout. Reviewed by: Josh Norton Date: July 1, 2005 ELECTRICAL 1. Developer installs conduit per city specs and design. 2. Developer will furnish and install 2 – 4" PVC conduits from existing transformer on adjacent East side property to transformer location at the proposed bldg. From there to the existing pull /junction box located on adjacent West side property. 3. Developer pours transformer pad(s) per city specs and design. 4. Developer provides digital AutoCAD 2000 version of plat and /or site plan email to sweido @cstx.gov. 5. Developer provides load data for project. 6. Developer provides temporary blanket easement for construction purposes. 7. Developer provides easements for electric infrastructure as installed for electric lines 8. To discuss any of the above electrical comments, please contact Sam Weido at 979.764.6314. Reviewed by: Sam Weido MISCELLANEOUS Date: 6 -29 -05 Irrigation system must be protected by either a Pressure Vacuum Breaker, a Reduced Pressure Principle Back Flow Device, or a Double -Check Back Flow Device, and installed as per City Ordinance 2394. 2. All BackFlow devices must be installed and tested upon installation as per City Ordinance 2394. NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out to the City, will constitute a completely new review. Page 3 of 3 s CITY OF COLLEGE STATION Planning & Development Services 1101 Texas Avenue, P.O. Box 9960 College Station, Texas 77842 Phone 979.764.3570 / Fax 979.764.3496 MEMORANDUM July 26, 2005 TO: Steve E. Duncan, PE, via fax 731.1500 FROM: Bridgette George, Development Coordinator SUBJECT: COLLEGE STATION PROF. BLDG TWO (SP) - Site Plan Staff reviewed the above - mentioned site plan as requested. The following page is a list of staff review comments detailing items that need to be addressed. The next submittal will be the third and final review by staff for this round of reviews. If all items have not been addressed on the next submittal, another $200 processing fee will need to be submitted for the subsequent set of three (3) reviews. Please address the comments and submit the following information for further staff review: One (1) complete set of construction documents for the proposed development with the revised site and landscaping plans attached Supporting documents for Blanket Easement If there are comments that you are not addressing with the revised site plan, please attach a letter explaining the details. If you have any questions or need additional information, please call me at 764 -3570. Attachments: Staff review comments cc: Walt Schoenvogel, R &S Leasing, via fax 979.834.1363 Case file #05- 00500113 Home of Texas A &M University w STAFF REVIEW COMMENTS NO. 2 Project: COLLEGE STATION PROF. BLDG TWO (SP) - 05- 00500113 PLANNING 1. Please provide supporting documentation required for processing the easement dedication sheet. These requirements are located at the bottom of the easement dedication sheet. If you have any questions, please contact Deborah Grace in the Planning and Development Services Department for more information 764.3570. 2. Is the curbing to remain on the west side of the parking lot in front of the building? 3. The 26' fire lane should be located between 15 and 30 feet of the building at all times. Please locate this fire lane appropriately. 4. Please provide access agreement. 5. Landscape legend shows 1.5" caliper live oaks, and the points calculation are based upon 2.1" — 3.4" caliper trees. Please correct legend, or correct points calculations. Reviewed by: LINDSAY BOYER Date: July 22, 2005 EN EERING ue to the fact that this development will require 2 hydrants, an additional fire flow test will be required as to demonstrate that the 2 hydrant system creates a flow greater than 2500 gpm. College Station Utilities is working on getting the information to me on the other hydrant so you will not have to get another fire flow test done. Q--The water demand of 75 gpm only requires a 1.5in meter. However this will not officially be ree ewed until building plans are submitted. 3!fhe sanitary sewer service line must be a minimum 1% slope. urther review of the private utilities will be done by the building department upon submittal of the building plans. 1 5. Drainage Report: �`,' Lai Please read your "certification" sheet and update for this project. �(L / Please provide contours and detail of west end of detention system. ., „ �• As slope is labeled on the east end of the detention system, please label slope on both i ides of the west end of the detention system. lease provide grade and detail of all portions of the retaining walls. Please provide detail of output structure from the initial detention basin. Lof! Is the detention system output into public undergrounds storm sewer system? Please explain the down stream system. Is there an agreement for the offsite improvements on the adjacent property to the east. Please provide detail of concrete head wall and output structure. Is there a drainage agreement for these adjoining properties, please spell this agreement out. Please show who is responsible for maintaining this drainage way /detention system. Upon looking at this site, modifications and improvements may need to be done to the existing offsite output structure due to extensive erosion. Reviewed by: Josh Norton Date: July 25, 2005 NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and 'bubbled" on your plans. Any additional changes on these plans that have not been pointed out to the City, will constitute a completely new review. 2 of 2 CITY OF COLLEGE STATION Planning & Development Services 1101 Texas Avenue, P.O. Box 9960 College Station, Texas 77842 Phone 979.764.3570 / Fax 979.764.3496 MEMORANDUM October 28, 2005 TO: Steve Duncan, via fax: 979 - 731- 1500/ FROM: LINDSAY BOYER, Staff Planner SUBJECT: COLLEGE STATION PROF. BLDG TWO (SP) - Site Plan Staff reviewed the above - mentioned site plan as requested. The following page is a list of staff review comments detailing items that need to be addressed. Please address the comments and submit the following information for further staff review: $200 processing fee for the next round of three (3) staff reviews; Six (6) complete sets of construction documents for the proposed development with the revised site and landscaping plans attached; Two (2) revised site plans; One (1) landscaping plan One (1) 11 x1 7 grading and erosion control plan; and Easement Dedication required documents. If there are comments that you are not addressing with the revised site plan, please attach a letter explaining the details. If you have any questions or need additional information, please call me at 764 -3570. Attachments: Staff review comments cc: Walt Schoenvogel, R &S Leasing via fax: 979 - 830 - 13631/ Case file #05- 00500113 Home of Texas A &M University STAFF REVIEW COMMENTS NO. 3 Project: COLLEGE STATION PROF. BLDG TWO (SP) - 05- 00500113 PLANNING /ENGINEERING 1. Additional hydrant will be required due to the FDC location. Please provide plan /profile and an engineers cost estimate for the water main extension and hydrant. Also, a valve will be required after the new hydrant before fire line heads into building. 2. Check alignment of existing hydrant. 3. Please be aware that a Development Permit will not be issued on this property until a blanket easement has been dedicated. None of the supporting documentation has been turned into our offices and this process takes approximately 4 -6 weeks. Please submit all Easement Dedication information to Deborah Grace in the Planning and Development Services office. If you have any questions, please contact here at 764 -3570. 4. Dedicate easement for the 6" fire line for portion of line that is not covered by existing easements up to within 5 -ft of building (This may be done after construction of water line and prior to blanket being released). 5. Label sanitary sewer service line as SDR 26 ASTM D3034. 6. Label flow line elevation of sanitary sewer service as it enters the manhole, as to verify that a drop is not required. 7. Make note that the Irrigation system includes a backflow preventer. Reviewed by: Josh Norton /Lindsay Boyer Date: October 28, 2005 NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out to the City, will constitute a completely new review. 2 of 2