Item
Estimated
No. Unit Quantity I Jn' Print Total
Paving Construction
1 Excavation C.Y. 1,157 8.50 9,834.50
2 1.5" HMAC (including prime coat) S.Y. 3,009 8.50 25,576.50
3 6" Lime Stabilized Subgrade (6 %) S.Y. 3,920 4.00 15,680.00
4 6" Crushed Limestone Base S.Y. 4,378 9.00 39,402.00
Paving Subtotal 90,493.00
Drainage Construction
5 18" CMP, (Type 1, 16 gauge, galvanized steel), structural backfill L.F. 48 60.00 2,880.00
6 Rock Rip -Rap Channel Lining (including geotextile fabric) S.Y. 12 70.00 816.90
7 4:1 Sloped Safety End Treatment for 18" CMP EACH 2 1,000.00 2,000.00
Drainage Subtotal 5,696.90
Water Line Construction
8 3" PVC CL 160, ASTM D2241 Water Pipe, non - structural backfill L.F. 897 13.00 11,665.03
9 6 "x3" Reducer EACH 1 175.00 175.00
10 3" x 45 Bend EACH 4 350.00 1,400.00
11 2" Blow OffAssembly EACH 1 7001)0 700.00
12 Connect to Existing Water Line EACH 1 500.00 500.00
13 1.5" Poly (ASTM D3035) Water Services - Long (inludes 3" Casing) EACH 4 1,200.00 4,800.00
Water Line Subtotal 19,240.03
Erosion Control Construction
14 Silt Fence L.F. 1,030 2.50 2,575.00
15 Fibermulch Seeding (all exposed areas) S.Y. 4,500 0.50 2,250.00
16 Construction Exit EACH 1 1,200.00 1,200.00
17 Headwall Protection EACH 1 250.00 250.00
18 Straw Bale Barriers EACH 9 75.00 675.00
1 1 Erosion Control Subtotal' 6,950.00
TOTAL CONSTRUCTION COST $122,379.93
The above construction estimate is based on the engineer's preliminary opinion of probable construction costs. This estimate constitutes
our best judgment at this time. Please note that the engineer does not have any control over contractor or supplier workloads and the
degree to which inflation may affect project costs between now and the bid date. During construction, additional features may become
apparent as the work progresses. which will result in an increase in cost.
t //
Jell P. /ii a _ -P� E OF TF 11
Sco , S I l l
* " * I /
i JEFFERY L. RE RTSON
�.a9.,.•...........94745 OB i Q i
, t l l 0 �.: 4CENSEO �. . ::
0 . 5 -a ,2 (,
g fls/Ug
11EDB McCLURE & BROWNE ENGINEERING /SURVEYING, INC.
- 5 0 _ ,... ci
i3 si3
1008 Woodcreek Drive, Suite 103 • College Station, Texas 77845
a (979) 693 -3838 • Fax: (979) 693 -2554 • Email: McClureBrowne( Verizon.net
Duck Haven Subdivision, Phase IV
Engineer's Opinion of Probable Construction Cost
September 12, 2008
Item Estimated
No. Description Unit Qty Total
Unit Price
Paving Construction
1 Excavation C.Y. 1,157 8.50 9,834.50
2 1.5" HMAC (including prime coat) S.Y. 3,009 8.50 25,576.50
3 6" Lime Stabilized Subgrade (6 %) S.Y. 3,920 4.00 15,680.00
4 6" Crushed Limestone Base S.Y. 4,378 9.00 39,402.00
Paving Subtotal 90,493.00
Drainage Construction
5 18" CMP, (Type I, 16 gauge, galvanized steel), structural backfill L.F. 48 60.00 2,880.00
6 Rock Rip -Rap Channel Lining (including geotextile fabric) S.Y. 12 70.00 816.90
7 4:1 Sloped Safety End Treatment for 18" CMP EACH 2 1,000.00 2,000.00
Drainage Subtotal 5,696.90
Water Line Construction
8 3" PVC CL 160, ASTM D2241 Water Pipe, non - structural backfill L.F. 897 13.00 11,665.03
9 6 "x3" Reducer EACH 1 175.00 175.00
10 3" x 45 Bend EACH 4 350.00 1,400.00
11 2" Blow Off Assembly EACH 1 700.00 700.00
12 Connect to Existing Water Line EACH 1 500.00 500.00
13 1.5" Poly (ASTM D3035) Water Services - Long (inludes 3" Casing) EACH 4 1,200.00 4,800.00
Water Line Subtotal 19,240.03
Erosion Control Construction
14 Silt Fence L.F. 1,030 2.50 2,575.00
15 Fibermulch Seeding (all exposed areas) S.Y. 4,500 0.50 2,250.00
16 Construction Exit EACH 1 1,200.00 1,200.00
17 Headwall Protection EACH 1 250.00 250.00
18 Straw Bale Barriers EACH 9 75.00 675.00
Erosion Control Subtotal' 6,950.00
TOTAL CONSTRUCTION COST $122,379.93
The above construction estimate is based on the engineer's preliminary opinion of probable construction costs. This estimate constitutes
our best judgment at this time. Please note that the engineer does not have any control over contractor or supplier workloads and the
degree to which inflation may affect project costs between now and the bid date. During construction, additional features may become
apparent as the work progresses. which will result in an increase in cost.