The Traditions Subdivision
Phase 23 - Biomedical Way
Engineer's Preliminary Estimate of Construction
Summary Sheet
'TOTAL CITY OF COLLEGE STATION PUBLIC INFRASTRUCTURE CONSTRUCTION
$
361,968.00
TOTAL SEWER CONSTRUCTION
$
36,925.00
TOTAL CONSTRUCTION
$
398,893.00
Q ........
SCHULTZ
............ 9
2 - If-
F -12327
SCHULTZ ENGINEERING, LLC.
Page 1 of 4
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No. 12327
The Traditions Subdivision
Phase 23 - Biomedical Way
Engineer's Preliminary Estimate of Construction
City of College Station Public Infrastructure Items
Item
Description
p
Unit
Estimated
Q uanti ty
Unit Price
Total
General Items
I
Mobilization, Overhead and Construction Staking
LS
1
$ 8,000.00
$ 8,000.00
2
Traffic Control - complete in place
LS
l
$ 1,000.00
$ 1,000.00
3
Right of Way and Site Preparation
LS
1
$ 5,000.00
$ 5,000.00
4
Topsoil Removal and Replacement, complete in place
LS
l
$ 4,000.00
$ 4,000.00
5
Install 36" Stop Sign, complete in place
EA
1
$ 400.00
$ 400.00
6
Rock RipRap, complete in place
SY
14
$ 20.00
$ 280.00
7
Install End of Street Signs, complete in place
EA
3
$ 250.00
$ 750.00
8
Erosion & Sediment Control - SWPPP Implementation & Maintenance, Silt
Fence, Construction Exit, Rock Filter Dam, etc., complete in place
LS
1
$ 4,000.00
$ 4,000.00
9
Hydroseed and Hydromulch, complete in place
SY
5,000
$ 0.60
$ 3,000.00
General Items Subtotal
$ 26,430.00
Street Construction Items
10
Excavation & Grading, complete in place
LS
1
$ 12,500.00
$ 12,500.00
I I
Remove Concrete Curb & Gutter
LF
90
$ 5.00
$ 450.00
12
Remove Concrete Sidewalk
SF
806
$ 3.00
$ 2,418.00
13
Mixing & incorporation of lime, 8" deep, complete in place
SY
5,500
$ 2.50
$ 13,750.00
14
Hydrated Lime, complete in place (36 Ibs /SY)
Ton
100
$ 170.00
$ 17,000.00
15
Crushed Limestone Base Material - 8" thick, complete in place
SY
3,825
$ I3.50
$ 51,637.50
16
Crushed Limestone Base Material - 6" thick, for temporary turnaround,
complete in place
SY
660
$ 11.50
$ 7,590.00
17
HMAC - Type D Pavement 2" thick - includes prime coat, complete in place
SY
3,825
$ 12.00
$ 45,900.00
18
HMAC - Type D Pavement 1.5" thick - includes prime coat, for temporary
turnaround, complete in place
SY
600
$ 10.50
$ 6,300.00
19
Concrete Curb & Gutter (Standard), complete in place
LF
2,020
$ 11.50
$ 23,230.00
20
Reinforced Concrete Pavement - Aprons - 6" Thick w/ Monolithic Standard
Curb, complete in place
SF
1,385
$ 5.00
$ 6,925.00
21
Concrete Sidewalk - 4" thick, complete in place
SF
12,605
$ 3.80
$ 47,899.00
22
ADA Ramps - Detectable Warning Surfaces, complete in place
EA
2
$ 650.00
$ 1,300.00
Street Construction Items Subtotal
$ 236,899.50
Page 2 of 4
The Traditions Subdivision
Phase 23 - Biomedical Way
Engineer's Preliminary Estimate of Construction
Citv of College Station Public Infrastructure Item.-
Storm Sewer Construction Items
23
24" RCP Pipe, complete in place (Structural)
LF
80
$ 70.00
$ 5,600.00
24
18" RCP Pipe, complete in place (Structural)
LF
42
$ 55.00
$ 2,310.00
25
24" - 4H:1 V Concrete SET, complete in place
EA
1
$ 2,000.00
$ 2,000.00
26
Curb Inlet - 5' wide, complete in place
EA
2
$ 3,000.00
$ 6,000.00
27
Junction Box, complete in place
EA
I
$ 3,000.00
$ 3,000.00
28
Channel Construction - Excavation and Grading, complete in place
LS
1
$ 8,000.00
$ 8,000.00
29
Curlex 11 Blanket Ditch Lining, complete in place
SY
220
$ 3.00
$ 660.00
30
TV Testing and Inspection, complete in place
LF
122
$ 4.25
$ 518.50
Storm Sewer Construction Items
$ 28,088.50
Water Construction Items
31
12" C900 Water Pipe - Structural Backfill, complete in place
LF
1,105
$ 40.00
$ 44,200.00
32
Fire Hydrant Assembly (w /valve, vert. extension), complete in place
EA
2
$ 3,600.00
$ 7,200.00
33
12" M.J. Gate Valve, complete in place
EA
5
$ 2,250.00
$ 11,250.00
34
12" M.J. Tee, complete in place
EA
2
$ 800.00
$ 1,600.00
35
12 "x 6" M.J. Tee, complete in place
EA
1
$ 700.00
$ 700.00
36
4" BlowofFAssembly, complete in place
EA
3
$ 1,200.00
$ 3,600.00
37
Remove 12" Plug and Blocking and Connect to Existing Water Line, complete
in place
EA
1
$ 1,000.00
$ 1,000.00
38
Waterline Testing
LS
1
$ 1,000.00
$ 1,000.00
Water Construction Items Subtotal
$ 70,550.00
General Items Subtotal
$
26,430.00
Street Construction Items Subtotal
$
236,899.50
Storm Sewer Construction Items Subtotal
$
28,088.50
Water Construction Items Subtotal
$
70,550.00
TOTAL CITY OF COLLEGE STATION PUBLIC INFRASTRUCTURE CONSTRUCTION
$
361,968.00
F -12327
Page 3 of 4 SCHULTZ ENGINEERIN% LLC
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No. 12327
The Traditions Subdivision
Phase 23 - Biomedical Way
Engineer's Preliminary Estimate of Construction
City of Bryan Public Sewer Line Construction
Item
Description
Unit
Estimated
Q uanti ty
Unit Price
Total
Sanitary Sewer Construction Items
l
8" PVC Sewer Line - D3034 - Structural Backfill, complete in place
LF
350
$ 32.00
$ 11,200.00
2
12" PVC Sewer Line F D303 - Structural Backfill, complete in place
LF
300
$ 44.00
$ 13,200.00
3
8" PVC Sewer Line ServVe Stubs, complete in place
EA
2
$ 750.00
$ 1,500.00
4
Concrete Manhole - 4' Dia. - complete in place - 10 -12' depth
EA
I
$ 3,250.00
$ 3,250.00
5
Concrete Manhole - 4' Dia. - complete in place - 16 -18' depth
EA
1
$ 4,500.00
$ 4,500.00
6
Connect to Existing 6' Dia. Manhole
EA
1
$ 1,000.00
$ 1,000.00
7
TV Testing and Inspection, complete in place
LF
650
$ 3.50
$ 2,275.00
Sanitary Sewer Construction Items Subtotal
$ 36,925.00
TOTAL SEWER CONSTRUCTION $ 36,925.00
OF T
.NN..N�.
JOSEPH P. SC
V •000....0......
65889
F -12327
SCHULTZ ENGINEERING, LLC.
Page 4 of 4