HomeMy WebLinkAbout63 Development Permit 632 DWS Office BuildingABBREVIATED DRAINAGE REPORT
FOR
DWS Office Building
Lot IR, Block "D"
Ashford Square Subdivision
Morgan Rector Survey, A-46
College Station, Brazos County, Texas
25-January 1999
RE.V\EWEO FOR
coMPL\ANCE
FEB 1 91999
COLLt:.\;O:::. ~ 'M. I \ON
ENG\NEER\NG ~
DEVELOPED BY:
Mr. David Scarmardo
D .W .S. Inc .
P .O . Box 4508
Bryan, TX 77805
( 409) 779-7209
PREPARED BY:
Kling Engineering & Surveying
4103 Texas Avenue, Suite 212
Bryan, TX 77802
( 409) 846-6212
,
PURPOSE:
ABBREVIATED DRAINAGE REPORT
for
DWS Office Building
Lot 1 R, Block "D"
Ashford Square Subdivision
Morgan Rector Survey, A-46
College Station, Brazos County, Texas
25-January, 1999
A drainage analysis for Lot IR, Block "D" was previously developed in the drainage report for the
Ashford Square Resubdivision and Dartmouth Addition Subdivision submitted to the City of College
Station dated 26-March, 1998 . The purpose of this report is to verify proposed design conditions are
met by actual planned development and to document private, on-site, storm sewer design .
HYDROLOGIC VERIFICATION:
In the above mentioned drainage report, it was assumed that Lot IR, Block "D" would have a curve
number no greater than 94 (refer to Appendix 8 of the drainage report, page 2.03 of the post-developed
analysis, filename=Last3.ppk). Upon review of the proposed site design, an actual curve number of 94 is
as signe d to the lot (refer to Appendix 1, "Hydrologic Calculations" for graphical representation and
computation). Stormwater from the site will proceed into the adjacent channel and detention facility .
STORM SEWER DESIGN:
The site will be graded to drain to area inlets which will convey storm water runoff via A.D .S .
polyethylene pipe to the adjacent channel and detention facility . Additionally, the area north of the
proposed building adjacent to the Southwest Parkway right-of-way will be graded in a swale to drain to
the creek. The Rational Method with a time of concentration equal to 10 minutes was used to determine
runoff rates for sizing the pipe and area inlets . Flow profiles were calculated within the pipe system by
computer aided use of the standard step method with Manning's friction method . Backwater effects from
the channel flow were considered in pipe sizing . The design storm is the 100 year event with the 25 year
event being analyzed as well .
Runoff from the lot was determined by dividing the lot area into sub-areas based on the proposed
grading plan (refer to Appendix 1, "Hydrologic Calculations" & Appendix 3, "Grading Plan"). The
following tables summarize runoff rate determinations and contributing sub-areas for each area inlet (refer
to Appendix 2, "Hydraulic Calculations" for inlet labeling map).
Sub-areas -Flow rates
Sub-Area Acreage "c" 025 0100
G1 0.003 0.2S 0.01 0.01
G2 0.0037 0.2S 0.01 0.01
G3 0 .0102 0.2S 0.03 0.03
G4 0 .0094 0.2S 0.02 0.03
GS 0.0067 0.2S 0.02 0.02
G6 0.0460 0.2S 0.11 0.13
P1 0.139S 0.9 1.24 1.46
P2 0.10S7 0.9 0.94 1.11
81 0.0379 0.9 0.34 0.40
82 0.0379 0.9 0.34 0.40
Totals 2.93 3.46
Table 1 *i25=9.86 ilOO=fl .64
Inlets -Contributin Flows
Inlet Contributing
Areas
Contributing 025 Contributing 0100
(cfs) (cfs)
1-1 P1, G6 1.36 1 .61
1-2 P2, GS 0.96 1.13
1-3 G1 0 .01 0.01
1-4 G2 0.01 0.01
1-S G3 0.03 0.03
1-6 G4 0.02 0.03
Table 2
Grates sizes were checked with the orifice equation and a ponding depth of 1 ". Minimum required open
area for grates on inlets I-3 through I-6 was determined to be 6 square inches. Grates specified on
grading plan provide 30 square inches . Minimum required open area for grates on inlets I-1 and I-2 was
determined to be 125 square inches . Grates specified on grading plan provide 161 square inches (refer to
Appendix 2 for calculation & Appendix 3 for grading plan).
Material for the storm sewer pipe was chosen to be polyethylene corrugated pipe with smooth interior
wall (Manning's n=l2) as manufactured by Advanced Drainage Systems. The storm sewer modeling
program StormCad, by Haestad Methods, was used to analyze the proposed storm sewer system with
backwater effects from the creek included . Water surface elevations in the detention facility I channel
were based on the following assumptions: (1) Pond is at maximum elevation & peak flow is still entering channel at
developed rates (2) Manning's equation used to determine depth of flow using a channel bottom width at elevation resulting
from peak pond elevation (3) computed depth is added to pond maximum elevation. The following tables summarize
contributing areas I inlets for each pipe and the pipe flow characteristics for the 25 and 100 year events .
1pes -
p· C "b . Fl 1pes -ontn utmg ows
Pipe Contribut ing Contribut ing Contributing 025 Contribut ing Q 100
Inlets Areas (cfs) (cfs)
P-10 1-3 G1 0.01 0 .01
P-9 1-4 G2 0.01 0 .01
P-8 1-S G3, 81 0 .37 0.43
P-7 1-6 G4 , 82 0.36 0.43
P-6 1-1 G6, P1 1.36 1 .61
P-S 1-1, 1-3 G1, G6, P1 1.37 1 .62
P-4 1-1 , 1-2, 1-3 , 1-4 G1 I G2, G6 , P1 1.38 1.63
P-3 1-1 , 1-2, 1-3 , 1-4 G1 , G2 , GS , G6, P1, 2 .34 2.76 P2
P-2 1-1 , 1-2, 1-3 , 1-4, G1 I G2 , G3, GS , G6, 2.71 3.19 1-5 P1,P2,81
P-1 1-1 , 1-2, 1-3 , 1-4, G1 I G2, G3 , G4, GS , 3 .07 3 .62 1-S, 1-6 G6,P1, P2,81 ,82
Table 3
As indicated above, pipes P-7 and P-8 will convey storm water from area inlets and the southeast
half of the building roof, sub-areas B 1 and B2 . Roof gutter downspouts are to tie directly to the
storm sewer system on this side . The northwest side of the roof will drain to the proposed swale .
H d r lY rau JCS -25 year even t
Pipe Upstream Downstream Upstream Downstream Length Section Q2S Average Upstream Downstream
Node Node Invert Invert Size Velocity HGL HGL
Elevation Elevation
(ft) (ft) (ft) (in) (cfs) (ft/s) (ft) (ft)
P-1 J-1 Outlet 272.4S 272.22 2S .04 24 3.07 0 .98 274.60 274.60
P-2 J-2 J-1 272 .92 272 .4S 64 .1S 24 2.71 0 .91 274.62 274 .61
P-3 1-2 J-2 273 .31 272.92 SS.98 24 2.34 0.94 274.63 274 .63
P-4 J-3 1-2 273.7S 273.41 S6 .7S 24 1.38 0 .8S 274.64 274 .64
P-S J-4 J-3 273 .81 273 .7S 9.26 24 1.37 1.0S 274 .6S 274 .6S
P-6 1-1 J-4 273 .84 273.81 3 .99 24 1.36 1.10 274 .66 274.66
P-7 1-6 J-1 27S.OO 272.45 42.2S 8 0.36 1.82 27S .28 274 .61
P-8 1-S J-2 27S.OO 272.92 42 .2S 8 0.36 1.83 27S .28 274 .63
P-9 1-4 J-3 27S .OO 274 .1S 36 .98 8 0.01 o.so 27S .04 274 .6S
P-10 1-3 J-4 27S.OO 274.21 S2.30 8 0 .01 0.47 27S.04 274.66
Table 4
1pes -H d 1' Ly1 rau !CS -100 year event
Pipe Upstream Downstream Upstream Downstream Length Section 025 Average Upstream Downstream
Node Node Invert Invert Size Velocity HGL HGL
Elevation Elevation
(ft) (ft) (ft) (i n) (cfs) (ft/s) (ft) (ft)
P-1 J-1 Outlet 272 .45 272 .22 25.04 24 3.62 1 .15 276.15 276 .14
P-2 J-2 J-1 272.92 272.45 64.15 24 3.19 1.02 276.17 276 .16
P-3 1-2 J-2 273.31 272.92 55 .98 24 2 .76 0 .88 276 .19 276.18
P-4 J -3 1-2 273 .75 273 .41 56 .75 24 1.63 0.52 276.20 276.20
P-5 J-4 J-3 273.81 273.75 9 .26 24 1.62 0 .51 276.20 276 .20
P-6 1-1 J-4 273.84 273.81 3.99 24 1.61 0.51 276.20 276.20
P-7 1-6 J-1 275.00 272.45 42.25 8 0.43 1.23 276 .20 276.16
P-8 1-5 J-2 275.00 272 .92 42 .25 8 0.43 1.23 276.22 276 .18
P-9 1-4 J-3 275.00 274 .15 36 .98 8 0 .01 0.03 276.20 276 .20
P-10 1-3 J-4 275 .00 274.21 52.30 8 0.01 0 .03 276 .20 276.20
Table 5
*Refer to the follo wi ng Appendi x 2 for calculation and graphical representations of pipe labeling described in above tables .
CONCLUSIONS:
As the storm return period increases, backwater effects from the creek channel become more
significant. This analysis assumes that peak elevation in the detention pond I channel coincide with peak
runoff from the office site (worst case scenario). As a result of the backwater effects, pipe diameter had
to be oversized to accommodate stormwater entering the system from the creek. It is shown that at the
time of coincidence, backwater from the creek rises into the system affecting pipe flow velocities . The
site is expected to be well maintained with little chance of significant sedimentation to occur within the
storm sewer from on-site sources . During lesser storm events, such as the 2 year event, backwater from
the creek will be negligible due to maximum water surface elevations in the pond I channel being lower
than the outlet pipe flowline . Analysis of the 2 year event shows velocities in the 24" portion of the storm
sewer system to be 2 .2 ft/s minimum to 3 .89 ft/s maximum (refer to Appendix 2 for calculation). The
storm sewer is expected to be self cleansing due to higher velocities achieved during the more frequent
minor storm events . Upon completion of construction, the system should be thoroughly cleaned of
sediment due to construction to optimize performance . The runoff curve number for this development
matches the design curve number referred to in the original drainage report which documents detention
. c. h . --~II..'''' requirements 1or t e site . --<~ OF "'"'''' -'ll,;·..-'«:;,.' • ,.. .. 4 :• ; .... 7 .. ea« ~ \l l
'/ ''.) ;...-/ I ·~; i'~ ... . ~ .:. .. -.ti;"' ......... . #~ ,,_ f 'f~-:(Y • "" 'I.
; .• -.'> .• I'" -~, \ ic ~ ~ .. ._ .. ~,,..ve"'--e~o ..... f.I "'"" · <'l •...,.-•-1o•J,. ~.! S. J. KLI NG t' ..... , · :_., ...... -~·:··. ·,. •·"~·•••"o ee•J.• ~L -·:.;., 24705 i l'Z j ~~~;-~·,··.:·~ ... ~1.lt/,,,"
l l .... ~. 0 '~ .. P.'I",_~, .... ,. \;\ .. .,..,~ ••~-"al V :l."" .1','.-;,. '* ~ ~·("!'f~c... c " tt.~~·-
\ • ~J ~·----I 21 JI.ht 4 qt
B.J. Kl' g , P .E . 24705
APPENDICES
1)
2)
3)
Hydrologic Calculations
Hydraulic Calculations
Grading Plan -Ashford Square
E:\Projects\Ashford'ap-tract\ddp .wpd
APPENDIX 1
HYDROLOGIC CALCULATIONS
"' c z
" l'T1 z
ro9
~~ • 21 z
~" ~Ro
(/) c
~ z "
~
I
"'Tl
0 :;c
0
0 :;c
< 1'11
DWS Ol'F1CB B1JIU>INO
IDI' 1R, BLOCK "D"
am.VB NUMBBll VAi.UBS
SOUTHWEST PARKWAY
SCALE: 1" =30'
COVER ARCA CN
(acre)
IMPER\!. BLDG . 0 .1517 98
IMPER'J. PVMT . 0 .3114 98
CHANNEL 0 .1033 98
GRASSED 0 .1860 80
TOTAL/AVE . 0.7524 93.5•94
>< r z
" "' (;; z
CD£? ::i:
:<>Z b -<"' )>"' :;o Z:<> . z 0
r1" CJ ;;:::~ :::0
(/)(/) < c ,.,,
"' < ':/ z
"
2002.02 SF
0 .0460 Ac
G6
P2
6075.73 SF
0 .1395 Ac
P1
159.92 SF
0.0037 Ac
4605.84 SF
0.1057 Ac
DWS OFPICB BUJLDJNO
LOr 1R. BLOCX "D"
DRAINACJB SUB -ARBAS
SOUTHWEST PARKWAY
1652.00 SF 1652.19 SF
0.0379 Ac 0.0379 Ac
81 82
445.27 SF G3 407.98 SF
0.0102 Ac 0.0094 Ac
\ \
G4
I
I
I
I
I
SCALE: 1'' =30'
sub-area acreaae "c" i25 i100 025 0100
G1 0 .0030 0.25 9.86 11 .64 0 .01 0.01
G2 0 .0037 0.25 9.86 11.64 0 .01 0 .01
G3 0.0102 0.25 9 .86 11 .64 0.03 0 .03
G4 0.0094 0.25 9.86 11 .64 0.02 0.03
GS 0.0067 0.25 9.86 11.64 0.02 0 .02
G6 0.0460 0 .25 9 .86 11.64 0.11 0 .13
P1 0.1395 0 .9 9 .86 11 .64 1 .24 1.46
P2 0 .1057 0 .9 9.86 11 .64 0.94 1.11
81 0.0379 0.9 9 .86 11 .64 0 .34 0.40
82 0 .0379 0 .9 9.86 11.64 0 .34 0.40
totals: 3.04 3 .59
•acreages, i, & a rounded
APPENDIX2
HYDRAULIC CALCULATIONS
·"7_("' ~ ~ 2 (\'I £ '2 :;:::-
z.~_j L J } 0 I 0 ::'"
[C£6G'O) )7°f'i~ g '0 J / £0 1
(/ = tj
-;1-f-I
7.f'I' <;Z J -=
z_J.j Lf3 I (l =
LS£®'0 > r'f7J 9 -o J /1°.J '/ ~ ti
~c, 71) COi -<r,~ ti ~ :ri~-ios -Z--..I 3 l -_r
L
'1 -\i'wo ::-<!.! ( \ "") , \ = C't:'' 0
-z-.T71-..::c. ll O;I 2 °) £' \ ~ S'Z Q
, 't ~e o · o ~ " 1 __ '--1 I
8·o = PJ ~ ' \;z I ' 'rJ-f r-::; = 0 : ; , oiE " , :i ' JO I
I
I
tsJ /V !£J<; ..J..P~/1// I
I ·,r,g _J.....,/~..::::/O Srl/Q I
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
In ut Data
Mannings Coefficient
Channel Slope
Left Side Slope
Right Side Slope
Bottom Width
Discharge
Results
Depth
Flow Area
Wetted Perimeter
Top Width
Critical Depth
Critical Slope
Velocity
Velocity Head
Specific Energy
Froude Number
Flow is subcritical.
Notes :
WATER DEPTH 25 YR EVENT
Worksheet for Trapezoidal Channel
e :\ha esta d\pi\ashford\ap-tra ct\dra ina ge . f m2
c-c new channel at 25yr pond depth
Trapezoidal Channel
Manning's Formula
Channel Depth
3.000000 H : V
16 .00 ft
754 .91 cfs
4.57 ft
135.81 ft2
44.91 ft
43.42 ft
3.31 ft
0.028318 fUft
5.56 ft/s
0.48 ft
5.05 ft
0.55
25 yr depth assumes : (1) pond is at max elev and peak flow is still entering at developed rates (2) bottom width &
min . elevation used calculated from 25 yr pond depth (3) computed depth is added to pond max elev
01/25/99
10:3 1 :20AM Haestad Methods, Inc . 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5 .12
Page 1 of 1
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
WATER DEPTH 100 YR EVENT
Worksheet for Trapezoidal Channel
e :\haestad\pi\ashford\ap-tract\drainage . fm2
c-c new channel at 1 OOyr pond depth
Trapezoidal Channel
Manning's Formula
Channel Depth
Mannings Coefficient 0.050
Channel Slope / . 08QPD tuft
Left Side Slope ( ~oOOOO H : V
Right Side Slope 3.000000 H : V
Bottom Width 19.40 ft
Discharge 993 .02 cfs
Results
Depth 4.91 ft
Flow Area 167 .75 ft2
Wetted Perimeter 50.48 ft
Top Width 48.88 ft
Critical Depth 3 .58 ft
Critical Slope 0.027369 tuft
Velocity 5.92 tus
Velocity Head 0.54 ft
Specific Energy 5.46 ft
Froude Number 0.56
Flow is subcritical.
Notes:
100 yr depth assumes: (1) pond is at max elev and peak flow is still entering at developed rates (2) bottom width &
min . elevation used calculated from 100 yr pond depth (3) computed depth is added to pond max elev
01/25/99
10:32:30AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5.12
Page 1 of 1
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
Mannings Coefficient
Channel Slope
Left Side Slope
Right Side Slope
Bottom Width
Discharge
Results
Depth
Flow Area
Wetted Perimeter
Top W idth
Critical Depth
Critical Slope
Velocity
Velocity Head
Specific Energy
Froude Number
Flow is subcritical.
Notes:
WATER DEPTH 100 YR EVENT
Worksheet for Trapezoidal Channel
e :\ha es ta d\pi\ashford\ap-tract\draina g e. fm2
start of new channel at 1 OOyr pond depth
Trapezoidal Channel
Manning's Formula
Channel Depth
0.050
0.008000 ft/ft
3.000000 H : V
3 .000000 H : V
15.40 ft
993 .02 cfs
5.29 ft
165.61 ft2
48.88 ft
47.16 ft
3.91 ft
0.027212 ft/ft
6.00 ft/s
0 .56 ft
5.85 ft
0.56
New channel just past SWPKWY culverts -100 yr depth assumes : (1) pond is at max elev and peak flow is still
entering at developed rates (2) bottom width & min . elevation used calculated from 100 yr pond depth (3) computed
depth is added to pond max elev
01/25199
10:34:33AM Haestad Methods , Inc . 37 Brookside Road Water bury, CT 06708 (203) 755-1666
FlowMaster v5.12
Page 1 of 1
"' r z
C) ,..,
z
rn9
;u z -<,..,
)>,..,
Z :JJ ~ . z
.... C) ,.., I ~~ "'Tl
"'"' 0
c ;;a
:JJ 0 G6 < ~ 0
z ;;a
C) < rrl
P1
1-J .-P
,,:
Q
Q
Q q
Q
Q
P-fo
DWS OFFICB Btm.DING
I.Or lR, BLOCK "D"
STORM SBWBR. SCHBMA11C
SOUTH WEST PARKWAY
SCALE: 1" =30'
2 YEAR EVENT -ASSUME FREE OUTFALL, NORMAL DEPTH
------------------Beginning Calculation Cycle -------------------Discharge: D.23 cfs at node 1-6
Discharge: D.87 cfs at node 1-1
Discharge: 0.48e-2 cfs at node 1·3
Discharge: 0.88 cfs at node J-4
Discharge: 0.01 cfs at node 1-4
Discharge: 0.89 cfs at node J-3
Discharge: 1.50 cfs at node 1-2
Discharge: 0.23 cfs at node 1-5
Discharge: 1.74 cfs at node J-2
Discharge: 1.97 cfs at node J-1
Discharge: 1.97 cfs at node Outlet
Beginning iteration 1
Discharge: 0.23 cfs at node 1-6
Discharge: 0.87 cfs at node 1-1
Discharge: 0.48e-2 cfs at node 1-3
Discharge: 0.88 cfs at node J-4
Discharge: 0.01 cfs at node 1-4
Discharge: 0.89 cfs at node J-3
Discharge: 1.50 cfs at node 1-2
Discharge: 0.23 cfs at node 1-5
Discharge: 1.74 cfs at node J-2
Discharge: 1.97 cfs at node J-1
Discharge: 1.97 cfs at node Outlet
Discharge Convergence Achieved in 1 iterations: relative error: 0.0
---------------------Calculations Complete ----------------------
** Analysis Options **
Friction method: Manning's For~la
HGL Convergence Test: 0.001000
Maxinain Network Traversals: 5
Nl..lllber of Flow Profile Steps: 5
Discharge Convergence Test: 0.001000
Maxinain Design Passes: 3
-----------------Network Quick View ------------------------
Discharge I Hydraulic Grade I
Label Length I Size I Upstream I Downstream
P-1 25.04 24 inch 1.97 272.94 272.62
P-3 55.98 24 inch 1.50 273. 73 273.47
P-2 64.15 24 inch 1. 74 273.38 273.04
P-6 3.99 24 inch 0.87 274.17 274.20
P-4 56.75 24 inch 0.89 274.07 273.85
P-5 9.26 24 inch 0.88 274.13 274.14
P-10 52.30 8 inch 0.48e-2 275.03 274.24
P-9 36.98 8 inch 0.01 275.03 274.18
P-8 42.25 8 inch 0.23 275.22 273.47
P-7 42.25 8 inch 0.23 275.22 273.04
Discharge I ------·----~~=~~!!~n~GL i-~~~~~~~~~~-~~~ I Label Ground I
1-1 0.87 277.28 274.25 274.17
1-2 1.50 277.23 273.85 273.73
Outlet 1.97 276.00 272.61 272.61
J-1 1.97 277.00 273.04 272.94
J-2 1.74 277.80 273.47 273.38
J-4 0.88 277.32 274.20 274.13
J-3 0.89 277.45 274.14 274.07
1-3 0.48e-2 277.50 275.04 275.03
1-4 0.01 277.92 275.04 275.03
1-5 0.23 277.60 275.29 275.22
1-6 0.23 277.32 275.29 275.22
Elapsed: 0 minute(s) 1 second(s)
25 YEAR EVENT -ASSUME ~SEL AT OUTLET=274.60
------------------Beginning Calculation Cycle -------------------Discharge: 0.36 cfs at node 1-6
Discharge: 1.36 cfs at node 1-1
Discharge: 0.01 cfs at node 1-3
Discharge: 1.37 cfs at node J-4
Discharge: 0.01 cfs at node 1-4
Discharge: 1.38 cfs at node J-3
Discharge: 2.34 cfs at node 1-2
Discharge: 0.36 cfs at node 1-5
Discharge: 2.71 cfs at node J-2
Discharge: 3.07 cfs at node J-1
Discharge: 3.07 cfs at node Outlet
Begirning iteration 1
Discharge: 0.36 cfs at node 1-6
Discharge: 1.36 cfs at node 1-1
Discharge: 0.01 cfs at node 1-3
Discharge: 1.37 cfs at node J-4
Discharge: 0.01 cfs at node 1-4
Discharge: 1.38 cfs at node J-3
Discharge: 2.34 cfs at node 1-2
Discharge: 0.36 cfs at node 1-5
Discharge: 2.71 cfs at node J-2
Discharge: 3.07 cfs at node J-1
Discharge: 3.07 cfs at node Outlet
Discharge Convergence Achieved in 1 iterations: relative error: 0.0
Information: P-1 Surcharged condition
---------------------Calculations C0111'lete ----------------------
** Analysis Options **
Friction method: Manning's For111.Jla
HGL Convergence Test: 0.001000
Maxinain Network Traversals: 5
Nl.llber of Flow Profile Steps: 5
Discharge Convergence Test: 0.001000
Maxinain Design Passes: 3
-----------------Network Quick View ------------------------
Label
P-1
P-3
P-2
P-6
P-4
P-5
P-10
P-9
P-8
P-7
Label
1-1
1-2
Outlet
J-1
J-2
J-4
J -3
1-3
1-4
1-5
1-6
Elapsed:
Length I
25.04
55.98
64.15
3.99
56.75
9.26
52.30
36.98
42.25
42.25
Discharge I
1.36
2.34
3.07
3.07
2. 71
1.37
1.38
0.01
0.01
0.36
0.36
0 minute(s) 2
Discharge I Hydraulic Grade I
Size I Upstream I Downstream
24 inch 3.07 274.60 274.60
24 inch 2.34 274.63 274.63
24 inch 2. 71 274.62 274.61
24 inch 1.36 274.66 274.66
24 inch 1.38 274.64 274.64
24 inch 1.37 274.65 274.65
8 inch 0.01 275.04 274.66
8 inch 0.01 275.04 274.65
8 inch 0.36 275.28 274.63
8 inch 0.36 275.28 274.61
Ground I
277.28
277.23
276.00
277.00
277.80
277.32
277.45
277.50
277.92
277.60
277 .32
~~:~~;!~n~GL i-~~~~~~~~~~-~~~ I
274.67 274.66
274.64 274.63
274.60 274.60
274.61 274.60
274.63 274.62
274.66 274.65
274.65 274.64
275.05 275.04
275.05 275.04
275.37 275.28
275.36 275.28
second(s)
100 YEAR EVENT -ASSUME WSEL AT OUTLET=276.14
------------------Beginning Calculation Cycle -------------------
Discharge: 0.43 cfs at node 1-6
Discharge: 1.61 cfs at node 1-1
Discharge: 0.01 cfs at node 1-3
Discharge: 1.62 cfs at node J-4
Discharge: 0.01 cfs at node 1-4
Discharge: 1.63 cfs at node J-3
Discharge: 2.76 cfs at node 1-2
Discharge: 0.43 cfs at node 1-5
Discharge: 3 .19 cfs at node J-2
Discharge: 3 .62 cfs at node J-1
Discharge: 3.62 cfs at node Outlet
Beginning iteration 1
Discharge: 0.43 cfs at node 1-6
Discharge: 1.61 cfs at node 1-1
Discharge: 0.01 cfs at node 1-3
Discharge: 1.62 cfs at node J-4
Discharge: 0.01 cfs at node 1-4
Discharge: 1.63 cfs at node J-3
Discharge: 2.76 cfs at node 1-2
Discharge: 0.43 cfs at node 1-5
Discharge: 3.19 cfs at node J-2
Discharge: 3.62 cfs at node J-1
Discharge: 3.62 cfs at node Outlet
Discharge Convergence Achieved in 1 iterations: relative error: 0.0
Information: P-1 Surcharged condition
Information: P-7 Surcharged condition
Information: P-2 Surcharged condition
Information: P-3 Surcharged condition
Information: P-8 Surcharged condition
Information: P-4 Surcharged condition
Information: P-5 Surcharged condition
Information: P-9 Surcharged condition
Information: P-6 Surcharged condition
Information: P-10 Surcharged condition
---------------------Calculations Corrplete ----------------------
** Analysis Options **
Fr i ction method: Mann i ng's Formula
HGL Convergence Test: 0.001000
Maxina.m Network Traversals: 5
Ni.inber of Flow Profile Steps: 5
Discharge Convergence Test: 0.001000
Maxina.m Design Passes: 3
-----------------Network Quick View ------------------------
Discharge I Hydraulic Grade I Label Length I Size I Upstream I Downstream
P-1 25.04 24 inch 3.62 276.15 276.14
P-3 55.98 24 inch 2.76 276. 19 276.18
P-2 64 .15 24 inch 3.19 276. 17 276.16
P-6 3.99 24 inch 1.61 276.20 276.20
P-4 56.75 24 inch 1.63 276.20 276.20
P-5 9.26 24 inch 1.62 276.20 276.20
P-10 52.30 8 inch 0.01 276.20 276.20
P-9 36.98 8 inch 0.01 276.20 276.20
P-8 42.25 8 inch 0.43 276.22 276.18
P-7 42.25 8 i nch 0.43 276.20 276.16
Discharge I
_., _________
~~=~~!!~n~GL i-~~~~~~~~~~-~~~ I Label Ground I
1-1 1.61 277.28 276.21 276.20
1-2 2.76 277.23 276.20 276.19
Outlet 3.62 276.00 276.14 276. 14
J -1 3 .62 277.00 276.16 276.15
J -2 3.19 277.80 276.18 276.17
J-4 1.62 277 .32 276.20 276.20
J-3 1.63 277.45 276.20 276.20
1-3 0.01 277.50 276.20 276.20
1-4 0.01 277.92 276.20 276.20
1-5 0.43 277.60 276.24 276.22
1-6 0.43 277.32 276.22 276.20
Elapsed: 0 minute(s) 2 second(s)
_,
_, ..... .... _, _, ;!:'. N.._N .,_N 10~ _,
Q>o"! ~ ._lf) -,CON
:;:;ON IOv ·r--
:J ·r--c::::N · O~N -:iO N ·r---ON ..
.. N .. c ::::N :.;::; a.. _, 0. gEE :3 EE . QN .. _, 0. =i·-~ gEE -,a::vi :J._ :J
OO:::Vl :J· -:J -,O:::(fl
BYDRAUUC GllADB LINB
25 A 100 YBAR. BVBNTS
_, .... _,
-~ n". NI')
N,..._:r--..
1r--N
-N ..
_, ..... _, n ._lf)
I lf)r'-: -,vn
·r--
c::::N
ON .. 0. -t EE :.;:::; a.. gEE
c:·-:J :J ·-:J _a:::VJ -,Cl::'.(/)
_, ..... _, ..... '<!" ~
IN~ -,nn
·r--
c::::N
.QN .. _, 0. gEE
~--~ -,a::: vi
_, ..... _,
""-v
co~ NI')
~r--:r--
I r--N
-N .. a. -t EE
c:·-:J _0:::(/)
HORIZ. SCALE : 1" =40'
VERT. SCALE: 1" =4'
PROPOSED FIN SHED GRADE ~ L--:::::::100 YR 'Hvo~ li\UUC
278 00
277 .00
276.00
275 .00
./ I GRADE Li'NE
,---.15 YR HYDRAUU1
/ CRADE LINE Elevation ft ,
~~~t!;~~/:::::::ttt~f1::::::~:::=::==~===t:~\~------==~~ I// 11 / ~ 273 .00 Pipe : P-6 I \ Up Invert: 273 .84 ft
I ? \
272 .00 en l~her~ 9~71t81 ft
0+00
Pipe . P-1
Up Invert: 272.45 ft
On Invert: 272 .22 ft
Length : 25 .04 ft
Siz e: 24 i nch
+50 1 +00. 1 +50 2 +00 2 +50 sfzne~ i4 Inch
Station ft
Pipe . P-2 Pipe. P-3 Pipe . P-4 Pipe. P-5
Up Invert : 272.92 ft Up Invert : 273.31 ft Up Invert: 273 .75 ft Up Invert: 273 .8 1 ft
On Invert: 272.45 ft Dn Invert: 272.92 ft On Invert: 273.41 ft On Invert : 273.75 ft
Length : 64.15 ft Length: 55.98 ft Length: 56 .75 ft Length: 9 .26 ft
Size: 24 inch Size: 24 inch Size : 24 inch Size : 24 inch
Table1
2 YR EVEN T
Pipe Upstream Downstream Upstream Downstream Length Section Discharge Average Upstream Downstream Upstream Downstream
Node Node Invert Invert (ft) Size (cfs) Velocity HGL HGL Depth Depth
Elevation Elevation (ft/s) (ft) (ft) (ft) (ft)
(ft) (ft)
P-8 1-5 J-2 275.00 272.92 42.25 8inch 0 .23 1 .52 275.22 273.47 0 .22 0 .55
P-9 1-4 J-3 275.00 274.15 36.98 8inch 0 .01 1.06 275.03 274.18 0 .03 0.03
P-10 1-3 J-4 275.00 274.21 52.30 8inch 0.48e-2 0 .92 275.03 274.24 0 .03 0 .03
P-6 1-1 J-4 273.84 273.81 3 .99 24inch 0 .87 2 .30 274.17 274.20 0 .33 0 .39
P-5 J-4 J-3 273.81 273.75 9 .26 24inch 0 .88 2 .36 274.13 274.14 0.32 0 .39
P-4 J-3 1-2 273.75 273.41 56.75 24inch 0.89 2 .20 274.07 273.85 0 .32 0 .44
P-3 1-2 J-2 273.31 272.92 55.98 24inch 1 .50 2 .61 273.73 273.47 0 .42 0.55
P-2 J-2 J-1 272.92 272.45 64.15 24inch 1 .74 2 .73 273.38 273.04 0 .46 0 .59
P-7 1-6 J-1 275.00 272.45 42.25 8inch 0 .23 1 .50 275.22 273.04 0 .22 0 .59
P-1 J-1 Outlet 272.45 272.22 25.04 24inch 1 .97 3 .89 272.94 272.62 0 .49 0 .40
FREE OUTFALL -ASSUME NORMAL DEPTH @ OUTFALL
Project Title : ASHFORD SQUARE A-P TRACT
e:lhaestadlpilashfordlap-tract\strmswr1 .stm
~ Haestad Methods, Inc .
KLING E NGIN EERING
Project Engineer: KLING ENGINEERING
StormCAD v1 .0
37 Brookside Road Waterbury , CT 06708 USA (203) 755-1666 Page 1 of 1
APPENDIX3
GRADING PLAN -ASHFORD SQUARE
Figure XII
Development Permit
City of College Station, Texas
Site Legal Description: Lot IR, Block D, Ashford Square Subdivision
Site Owner: David Scarmardo
Architect/ R.L. Payne & Associates, Inc./
Kling Engineering & Surveying
Engineer:--------------
Address: P.O. Box 4508, Bryan, TX 77805
Telephone No.: (409)779-7209
Address: 1509 Emerald Pkwy, Suite 104 I
4103 Texas Ave. Ste 212, Bryan
Telephone No. :(409)696-7272 I 846-6212
Contractor: Address: --------------------------~ Telephone No.: _________ _
Date Application Filed: __________ Approved: ___________ _
Application is hereby made for the following development specific waterway alterations:
No waterway alterations -Site Development consisting of grading, building construction, parking
and associated site amenities construction.
~ Application Fee
0 Signed Certifications
0 Drainage and erosion control plan, with supporting Drainage Report two (2) copies each.
0 Site and Construction Plans, with supporting Drainage Report two (2) copies each.
0 Other:
-----------------~
ACKNOWLEDGEMENTS:
I, David Scarmardo , design engineer/owner, hereby acknowledge or affirm that:
The information and conclusions contained in the above plans and supporting documents comply
with the current requirements of the City of College Station, Texas City Code, Chapter 13 and
its associated Drainage Policy and Design Standards.
As a condition of approval of this permit application, I agree to construct the improvements
proposed in this application according to these documents and the requirements of Chapter 13 of
the College Station City Code. ~ 7Rv4J _~ u/) ~flL
Property Owner(s) COfltracto~
Page 1of2
· . . ·~·
12/02/98 15:56 '6'409 764 3496 DEVELOPMENT SVCS !al 006
Fig"re XII Continued
CERTIFICATIONS : (for proposed alterations within designated flood hazard areas.)
A . 1, certify that any nonresidential structure on or proposed
10 be on this site: as part of this application is designated 10 prevent damage to the structure or its
contents as a. result of flooding from the 100 year stonn.
Engineer Date
R . (, --·· .. ___,certify that the finished floor elevation of the lowest
floor, induding any basement, of any residenlial structure, propogcd as part of this application is
at or above the base flood elevation established in the latest Federal Insurance Administration
Flood Hazard Study and maps, as amended .
-~~~~~--~~~~~~~-
Engineer Date
C . I, .. certify that the alterations or development covered by
this permit shall not diminish the flood-carrying ~pacity of the waterway adjoining or crossing
this permitted site and that such alterations or development arc consistent with requirements of
the City of College Station City Code, Chapter 13 conceming encroaclunent:s of.floodways and of
floodway fringes.
Engineer Date
l, , do ccnify that the proposed alterations do not raise the level
of the 100 year flood above elevation established in lhe latest Federal Insurance Administration
Flood Hazard Study.
Engineer Date
CondiLions or comments <ts part of approval : -------------------
In accordance with Chapter l3 of the Code of Ordinances of the City of College Station,
measures shall be taken to insure that debris from construction, erosion, and sedimentation shall
not be deposited in city streets, or existing drainage facilities.
l hereby grant this permit for development. All development shall be in accordance with the plans
and specifications submitted to and approved by the City Engineer for the above named project.
All of the applicable codes and ordinances of the City of College Station shall apply .
44 .......
•
-~ ..... ··
12 /02198 15:56 'Q'409 764 3496 DEVELOPMENT SVCS
Figure XU
Development Pc1-mit
City of College Stl'tion, Texas
Site Legal Description : fo r /fZ I ,3 .. -x.-K f>, ~ Sv"1&2 ~OO!A&<1Y\I
Site Owner : b"""tD .Sc;,A&r'lrirzr.:>o Address:
Telephone:------------
Address: {.qy ,va !_ K_65,,--___ _
Telephone No : ,P4111tl /«65
Addre~s . -------
Telephone No.----------
Date Application Filed: --···-------Approved: _____ ~------
Applica;ion is hereby made for the following development specific waterway alterations :
-Ah Wlfn1J..fy 4wuns!N 'S-._ 7:>,;rzr f/gi/~/?toNr C4Jr=v:sf"?~
cJ.F $RA-OrN4 ,i 8d1u ){Ah ~rzv-.1 , BY.xut< & A ~'4-f2/l? :Sr~
4«Jc3Nt77E :s tctl-s ~o-N
1ZJ: Application Fee ~ / ~
0 Signed Certification!. ;V ///_
. CJ Drainage and erosion control plan, with .supporting Drainage Report two (2) copies each.
Q Site and Construction Plans, with supportir\$ Drainage Rcpon two (2) copies each_
0 Other: -----
ACKNOWLEDGMENTS :
I, b&il I) 5 C<4-h?114i'ZO-D , design engine{r9ereby acknowledge or affirm that:
The information and conclusions contained in the above plans and supporting documents comply
with the current requirements of the City of Coll~ge. Station, Texas City Code, Chapter 13 and its
associated Drainage Policy and Design Standards .
As a condition of approval of this permit application, I agree to construct the improvements
proposed in this application according to these documents and the requirements of Chapter 13 of
t e College . Code. /, ~
Contractor
•
4103 Texas Avenue, Suite 212
Bryan, Texas 77802
TO
ATTENTION
WE TRANSMIT :
D Under Separate Cover
JZf Enclosed
VIA :
DMail
[j'Messenger
D Federal Express
D Express Mail
D Special Courier
D Picked Up By Your Office
NO .
KLING ENGINEERING AND SURVEYING
Consulting Engineers • Land Surveyors
Tel. (409) 846-6212
Fax (409) 846-8252
THE FOLLOWING :
D Prints
D Copies
D Originals
O Plat
D Field Notes
O Plans
t:)f Report
D Estimate
DCut Sheets
DATE
PROJECT N0.
D Computer Printout
O File
D Contract
D
DESCRIPTION
FOR :
P.O. Box 4234
Bryan, Texas 77805
D Your Review & Approval
D Your Review & Comment
D Your Review & Distribution
D Your Rev iew, Revision & Return
D Your Signature & Return
D Your File and /or Use
D As Requested By :
D Please Acknowledge Receipt of
Enclosures
D Please Return Enclosures To Us
D Copies Of This Letter Of Transmittal
Sent To :
:J. \)y-ri.. ; {'\ r'll.. a R ~ J2 nf'lr-t.<\
0 -, If En closures Are Not As Noted ,
e Notify Us At Once. Pleas
Sign ed :
rK Q..,b~'-~
~~
h~ ?C\.; f'J...._
ABBREVIATED DRAINAGE REPORT
FOR
DWS Office Building
Lot lR, Block "D"
Ashford Square Subdivision
Morgan Rector Survey, A-46
College Station, Brazos County, Texas
25-January 1999
_ re ut:;e. Y'e.f'V'-; U-4
~ J?~ j/'(f;'SO /u-J;'o..-,.
~ defM -J/CV\ f ~
~ p ~~A/ C!/v':) OV' ~CA s-----
a e,to tc=s;-11~) ~
(°Joor Ad.~L S70 o~ ~7"~
f~·
_ P:,40 ;h CJ'~ /,.. Gai,...e;t'vo d14..
p~ A-
DEVELOPED BY:
Mr. David Scarmardo
D .W .S. Inc.
P .O . Box 4508
Bryan, TX 77805
( 409) 779-7209
PREPARED BY:
Kling Engineering & Surveying
4103 Texas Avenue, Suite 212
Bryan, TX 77802
(409) 846-6212
DEVELOPMENT PERMIT
PERMIT N0.632-B
DWS Office Building
FOR AREAS OUTSIDE THE SPECIAL FLOOD HAZARD AREA
RE: CHAPTER 13 OF THE COLLEGE STATION CITY CODE
SITE LEGAL DESCRIPTION:
OWNER:
Lot IR Block D, Ashford Square Subdivision
DWS Development Inc.
David Scarmardo
P.O. Box 4508
Bryan, Texas 77805
779-7209
DRAINAGE BASIN: BEE CREEK
SITE ADDRESS:
2501 Ashford Square
TYPE OF DEVELOPMENT:This permit is valid for construction work as per approved site plans.
The Contractor shall take all necessary precautions to prevent silt and debris from leaving the immediate
construction site in accordance with the approved erosion control plan as well as the City of College
Station Drainage Policy and Design Criteria. The Owner and/or Contractor shall assure that all disturbed
areas are sodden and establishment of vegetation occurs prior to removal of any silt fencing or hay bales
used for temporary erosion control. The Owner and/or Contractor shall also insure that any disturbed
vegetation be returned to its original condition. placement and state. The Owner and/or Contractor shall
be responsible for any damage to adjacent properties, city streets or infrastructure due to heavy machinery
and/or equipment as well as erosion. siltation or sedimentation resulting from the permitted work.
Any trees required to be protected by ordinance or as part of the landscape plan must be completely fenced
before any operations of this permit can begin.
This permit, being temporary, is valid only within sixty (60) days of the date shown below, and is not
intended to allow the complete development of the site as proposed. Any work performed after the
expiration of this permit is not covered, and is considered unauthorized .
Jn accordance with Chapter 13 of the Code of Ordinances of the City of College Station , measures shall
be taken to insure that debris from construction, erosion, and sedimentation shall not be deposited in city
streets, or existing drainage facilities.
I hereby grant this permit for development of an area outside the special flood hazard area. All
de ve lopment shall be in accordance with the plans and specifications submitted to and approved by the
City Engineer in t lopment permit application for the above named project and all of the codes
and ordinances e Ci of College Station that apply.
Date
Contractor Date
DEVELOPMENT PERMIT
PERMIT N0.632-A
DWS Office Building
FOR AREAS OUTSIDE THE SPECIAL FLOOD HAZARD AREA
RE: CHAPTER 13 OF THE COLLEGE STATION CITY CODE
SITE LEGAL DESCRIPTION:
OWNER:
Lot lR Block D, Ashford Square Subdivision
DWS Development Inc.
David Scarmardo
P.O. Box 4508
Bryan, Texas 77805
779-7209
DRAINAGE BASIN: BEE CREEK
SITE ADDRESS:
2501 Ashford Square
TYPE OF DEVELOPMENT:This permit is valid for rough cuting and grading only, as shown on
the plans approved by the City of College Station on March 3, 1999.
The Contractor shall take all necessary precautions to prevent silt and debris from leaving the immediate
construction site in accordance with the approved erosion control plan as well as the City of College
Station Drainage Policy and Design Criteria. The Owner and/or Contractor shall assure that all disturbed
areas are sodden and establishment of vegetation occurs prior to removal of any silt fencing or hay bales
used for temporary erosion control. The Owner and/or Contractor shall also insure that any disturbed
vegetation be returned to its original condition, placement and state . The Owner and/or Contractor shall
be responsible for any damage to adjacent properties, city streets or infrastructure due to heavy machinery
and/or equipment as well as erosion, siltation or sedimentation resulting from the permitted work .
Any trees required to be protected by ordinance or as part of the landscape plan must be completely fenced
before any operations of this permit can begin .
This permit, being temporary, is valid only within sixty (60) days of the date shown below, and is not
intended to allow the complete development of the site as proposed. Any work performed after the
expiration of this permit is not covered, and is considered unauthorized.
In accordance with Chapter 13 of the Code of Ordinances of the City of College Station, measures shall
be taken to insure that debris from construction, erosion, and sedimentation shall not be deposited in city
streets, or existing drainage facilities.
I hereby grant this permit for development of an area outside the special flood hazard area. All
development shall be in accordance with the plans and specifications submitted to and approved by the
City Engineer in the development permit application for the above named project and all of the codes
and or inances o the City of College Station that apply.
~ r;
Date
Date
Date