HomeMy WebLinkAbout75 Development Permit 538 Ashford Square-·
December 10, 1998
The Ashford Square I Dartmouth Addition Subdivision Drainage Report Dated March 26,
199(~)8, with Addendum dated May 11, 1998, was re-reviewed due to flooding complaints from
the trailer park downstream. Several issues that could effect the flow rate contributing to the pond
were not analyzed. These include detailed analysis of the on-site time-of-concentration, effects of
lost storage in the existing channel, and increased velocities within the channel. A preliminary
model using HEC-1 was developed using the input information provided in the report and showed
that these conditions would not result in a significant impact on the pond. The rating table of the
detention pond was also examined. This revealed that the stage-discharge relationship for the
mortared rock lined trapezoidal channel serving as the outlet used a manning roughness coefficient
of 0.05. Per the DSDP manual and other resources, this type of channel lining would typically
have a coefficient near 0.025. Because this factor results in a direct inverse relationship with the
pond's outflow, the pond discharge is twice the flow rate for a given elevation as reported. This
was also modeled in the HEC-1 model which showed the development with the pond increasing the
100-year storm by approximately 30 cfs or 3 .. 3%
Preliminary calculations were completed to estimate needed modifications to the existing outflow to
:function as was reported. The channel bottom would need to be reduced from 8' bottom to 3' with
on of the side slopes modified from 2: 1 to 1: 1.
Jeff
DESCRIPTION
TRAPEZOIDAL CHANNEL ANALYSIS
RATING CURVE COMPUTATION
December 10, 1998
PROGRAM INPUT DATA
VALUE
Channel Bottom Slope (ft/ft) •....•....••....•.•.......•.....
Manning's Roughness Coefficient In-value) .••................
Channel Left Side Slope (horizontal/vertical) ••.•........•.•
Channel Right Side Slope (horizontal/vertical) ........•.....
0. 008 ---------( o;:0zs~"~ --~
2.0
2.0
8.0 Channel Bottom Width (ft) .....••.•....••...........••....•..
Minimum Flow Depth (ft J •••••••••••••••••••••••••••••••••••••
Maximum Flow Depth (ft) .......•......•............•.•...•...
Incremental Head (ft) ......•.•••••....•.•...•••.•..•........
COMPUTATION RESULTS
Flow Flow Flow Froude Velocity Energy
Depth Rate Velocity Number Head Head
(ft) (cfs) (fps) (ft) (ft)
Flow
Area
(sq ft)
0.5
5.5
0.5
Top
Width
(ft) --------------------------------------------------------------------------------
0.5 13.83 3.07 0.808 0.147 0.647 4.5
1.0 45.88 4.59 0.886 0.327 1.327 10.0
1.5 94.7 5.74 0.932 0.512 2.012 16.5
2.0 160.92 6.7 0.965 0.699 2.699 24.0
2.5 245.57 7.56 0.991 0.887 3.387 32.5
3.0 349.83 8.33 1.013 1. 078 4. 078 42.0
3.5 474.91 9.05 1.032 1.272 4.772 52.5
4.0 622.05 9. 72 1. 049 1.468 5.468 64.0
4.5 792.46 10.36 1.065 1.668 6.168 76.5
5.0 987.33 10.97 1. 079 1. 87 6.87 90.0
5.5 1,207.84 11.56 1.092 2. 076 7. 576 104.5
HYDROCALC Hydraulics for Windows, Version 1.2 Copyright (c) 1996
Dodson & Associates, Inc., 5629 FM 1960 West, Suite 314, Houston, TX 77069
Phone:(281)440-3787, Fax:(281)440-4742, Email:software@dodson-hydro.com
All Rights Reserved.
10.0
12.0
14.0
16.0
18.0
20.0
22.0
24.0
26.0
28.0
30.0
DESCRIPTION
TRAPEZOIDAL CHANNEL ANALYSIS
. RATING CURVE COMPUTATION
December 10, 1998
PROGRAM INPUT DATA
Channel Bottom Slope (ft/ ft) ••..••.•••••......•••••..•......
VALUE
0.008
Manning's Roughness Coefficient (n-value) .................. .
Channel Left Side Slope (horizontal/vertical) ......•........
Channel Right Side Slope (horizontal/vertical) •...•.....•••.
~~
2.0
Channel Bottom Width (ft) ...•.•.....•..•..........••.......•
Minimum Flow Depth (ft) ...•.........•........•........•.....
Maximum Flow Depth (ft) ...•.•......••.•......•.......•......
Incremental Head (ft) ..........•...•.•.•...........•........
Flow
Depth
(ft)
0.5
1.0
1.5
2.0
2.5
3.0
3.5
4.0
4.5
5.0
5.5
Flow
Rate
(cfs)
6.92
22.94
47.35
80. 46
122.78
174.91
237.46
311. 03
396.23
493.67
603.92
COMPUTATION RESULTS
Flow
Velocity
(fps)
1.54
2.29
2.87
3.35
3.78
4.16
4.52
4.86
5.18
5. 49
5.78
Froude
Number
0.404
0.443
0.466
0. 483
0.496
0.507
0.516
0.525
0.532
0.539
0.546
Velocity
Head
(ft)
0.037
0.082
0.128
0.175
0.222
0.27
0.318
0.367
o. 417
0.468
0.519
Energy
Head
(ft)
0.537
1. 082
1.628
2.175
2.722
3.27
3.818
4 .367
4.917
5.468
6.019
Flow
Area
(sq ft)
4.5
10.0
16.5
24.0
32.5
42.0
52.5
64.0
76.5
90.0
104.5
2.0
8.0
0.5
5.5
0.5
Top
Width
(ft)
10.0
12.0
14.0
16.0
18.0
20.0
22.0
24.0
26.0
28.0
30.0
================================================================================
HYDROCALC Hydraulics for Windows, Version 1.2 Copyright (c) 1996
Dodson & Associates, Inc., 5629 FM 1960 West, Suite 314, Houston, TX 77069
Phone: (281)440-3787, Fax: (281)440-4742, Email:software@dodson-hydro.com
All Rights Reserved.
Chapter 3 Basic Data Requirements
Table 3.1 (Continued)
Manning's 'n' Values
Type of Channel and Description Minimum
B. Lined or Built-Up Channels
1. Concrete
a. Trowel finish 0.011
b. Float Finish 0.013
c. Finished, with gravel bottom 0.015
d. Unfinished 0.014
e. Gunite, good section 0.016
f. Gunite, wavy section 0.018
g. On good excavated rock 0.017
h. On irregular excavated rock 0.022
2. Concrete bottom float finished with sides of:
a. -Dressed stone in mortar 0.015
b. Random stone in mortar 0.017
c. Cement rubble masonary, plastered 0.016
d. Cement rubble masonary 0.020
e. Dry rubble on riprap 0.020
3. Gravel bottom with sides of:
a. Formed concrete 0.017
b. Random stone in mortar 0.020
c. Dry rubble or riprap 0.023
'
4. Brick ---
a. Glazed -0.0H
b. In cement mortar 0.012
5. Metal
a. Smooth steel surfaces 0.011
b. Corrugated metal 0.021
6. Asphalt
a. Smooth 0.013
b. Rough _ 0.016
7. Vegetal lining 0.030
3-14
Normal Maximum
0.013 0.015
0.015 0.016
0.017 0.020
0.017 0.020
0.019 0.023
0.022 0.025
0.020
0.027
0.017 0.020
0.020 0.024
0.020 0.024
0.025 0.030
0.030 0.035
0.020 0.025
0.023 0.026
0.033 0.036
0.013 0.015
0.015 0.018
0.012 0.014
0.025 0.030
0.013
0.016 .. -;_;
0.500
..
; ~ ~· . . . \:? ·. >H>· .. ·· ...
CITY OF COLLEGE STATION
REPRINT *** CUSTOMER RECEIPT *** OPER: MRODGERS CT DRAWER: 1
DATE: 3/17/99 00 RECEIPT: 0009703
CUSTOMER LOCATION AMOUNT TP TM
13723 14247 1 $8800.00 •DP CK
D W S DEVELOPMENT INC CK: 3256479
D W S DEVELOPMENT CK ft 3256479
PERFORMANCE GUARANTEE FOR
DETENTION POND
DEBORAH GRACE
TENDER DETAIL
CK 3256479 $8800.00
DATE: 3/17/99 TIME: 16:35:10
TOTAL PERSONAL CHECK $8800.00
AMOUNT TENDERED $8800.00
THANK YOU
.· .. · ..
. . . -:-:.· .. · •, ..
·-... ....,
~ '~(:' .· :-:::::· .
-.
<~~,~r . ~ YJ~ -~ ~
FACSIMILE COVER ~
DATE : ~. \ 1, ..qC{
SHEET
CITY OF COLLEGE STATION
DEVELOPMENT SERVICES
1101 South Texas Avenue, P.O . Bo x 9960
College Station, Texas 77842
Phone (409) 764-3570 Fax (409) 764-3496
#PAGES INCLUDING COVER 1-
If you did not receive a co mplete fax, please call our office imm ediate ly for a n ew transm ittal.
T0 :~~~~~=2~S<PJll_'._J.~~~~~~~~~~~~~~~~
COMPANY:
~~~~~~~~~~~~~~~~~~~~~-
DEPARTMENT:~~~~~~~~--~~-.-----=----~~----
PHONE: FAX: Z4CO 1oRS ---------
REMARKS : D Urgent D For your review D Reply ASAP D Please Comment
~ k>c.J ( ~-\k_ lS 6lt M_~
March l 3. 1999
Rodgers, Miller & E lli son
4444 Ca rt e r C reek Pkwy .
Bryan. Tx . 77802
Attentio n: Chuck E lli so n
Dear C hu c k :
COLLEGE STATION
P. 0. Box 9960 11 01 Texas Av e nue
Tet. 409 764 3500
Co llege Station, TX 77842
Accord in g to our record s , no fi na l in s pectio ns have been called in fo r th e Heritage a t Dartmouth project.
Sincere ly.
Melissa Ro d gers
Senior Sec reta ry
Hom e of Texas A&M University
Wak@orest
June 23 , 1999
Ms. Veronica Morgan
Assistant City Engineer
P.O. Box 9960
MOB I LE HOME PARK
College Station, TX 77842-9960
RE: Detention pond at Ashford Square Development
Dear Veronica,
Allen R. Swoboda
8415 Appomattox Dr.
College Station, TX 77845
We have discussed the problem of getting David Scarmardo to correct the outflow
structure of the detention pond at Ashford Square Development several times. Stewart
Kling has admitted they made a mistake in sizing the outflow structure and has
resubmitted a corrected plan, which has been supposedly approved by the City. This was
several months ago and no work has been done to correct the problem. We have been
working with Mr. Scarmardo since October of 1998. We allowed him to lower the
drainage channel in the creek crossing our property to alleviate the problem of them
constructing the detention pond to deep, with the agreement that he install a concrete
pilot channel and correct the outflow structure. You assured us that the City had a
construction bond to insure that the detention pond was built correctly, and you indicated
that the bond would not be released until all work was completed. Apparently, the bond
has been released and Mr. Scarmardo has no incentive to correct the detention pond.
I am suggesting that the City not issue a Certificate of Occupancy on the office building
which David Scarmardo is building in Ashford Square Development and also the
apartments Emanuel Glockzin is building until the detention pond is satisfactory
completed. The drainage requirements for both of these projects require the detention
pond in question to be operating properly.
30 1 KRENEK TAP ROAD • COLLEGE STATION, TEXAS 77840 • (409) 693-5206 •FAX (409) 696 -2046
Wak~rest
MOBILE HOME PARK
In addition, part of the drainage from the Ashford Square four-plexes is being diverted
around the back of some of the buildings and does not go into the detention pond . This
water is being dumped onto Oak Forest property, which is causing erosion, and water
from their sprinkler system is keeping a part of our property continuously wet so that we
cannot mow the grass. This drainage section is also not draining properly which is
causing a backup of water on the adjacent property which is causing stagnate water to
pond 4 to 5 inches deep which is becoming a breeding ground for mesquites.
I would appreciate whatever you can do to expedite the completion of the
detention pond and the drainage problem at Ashford Square.
Sincerely,
c?~
Allen R. Swoboda
Owner/Oak Forest Mobile Home Park
Cc : Mr. "Skip" Noe
City Manager
P.O. Box 9960
College Station, TX 77842
301 KRENEK TAP R OAD • COLLEGE STATION , TEXAS 77840 • (409) 693 -5206 •FAX (409 ) 696-2046
COLLEGE STATION
P. 0. Box 9960 110 1 Texas Avenu e
Tet 409 7 64 3 500
Col~ge SlaUon , TX 77B42 ~
~~~ 12-Mar-99
Mr. Emanuel H. Glockzin, Jr.
4500 Carter Creek Parkway, Ste. 101
Bcyan. Texas 77802
RE : HERITAGEATDARTMOUTIIPROJECf
Dear Emanuel :
As requested, the City hereby confirms that there is capacity for the post-development runoff from the
Heritage at Dartmouth Project within the Ashford Square detention pond. Your Project, as defin ed in the
Ashford Square report, is Lot Two (2) and Three (3), Bl ock One (l) of the DARTMOUTII ADD ITTO N
SUBDIVISON. You are now authorized to util ize the As hford Square detention pond and no permits,
approvals o r certificates of occupancy from the City will be withheld for your Project on the bas is of
insufficient detention pond cap acity for your Project Further requirements rel ated to the detention po nd
or downstream drainage improvemen ts (Swoboda P roperty) are the responsib il ity of the developer of the
Ashford Square Project The City will not request paym ent or performance fro m you . The C ity has
accepted the d etention po •:d and drainage imp roveme nts as a public dedicati o n and will maintain th e
same at no cost to you.
Very truly yours,
CITY OF COLLEGE ST A TION
by :--'>J--'-----~
Name: ROBERT MOSEL , P.E.
Title: City Engineer
by: ~'fJ~ /~Nam~ NICA J.B . MORGAN, P .E .
~ Title: Asst City Engineer
cc: David Scarmardo, Ashford Square
Natalie Ruiz, Development Coordinator
file
Home of Texas A&M Un iversity
02 /19 /99 14 : 17 '8'409 764 3496 DEVELOPMENT SVC S
TRANSMISSION OK
TX/RX NO .
CO ECTION TEL
CONNECTION ID
START TIME
USAGE TIME
PAGES
RESULT
*************************** *** ACTIVITY REPORT ***
***************************
6555
9p7643489
02 /19 14:16
01 '10
4
OK
~001
DATE:
FACSIMILE ·coVER
SHEET
CITY OF COLLEGE STATION
DEVELOPMENT SERVICES
1101 South Texas Avenue, P.O. Box 9960
College Station, Texas 77842
Phone (409) 764-3570 Fax (409) 764-3496
#PAGES INCLUDING COVER --+---
If you did not receive a complete fax, please call our office immediately for a new transmittal.
TO: ~'S:> -~~--'--_:.____;::=-::_+-------------------
CO MP ANY : ______________________ ~
DEPARTMENT: ----------------------
PHO NE: ----------
FROM: \f ~CA
PHONE: FAX : --------------------
REMARKS : D Urgent D For your review D Reply ASAP D Please Comment
02 /18 /99 12 :4 5
DATE:
'6'409 268 3037 Y-C-B & S
YOUNGKIN, CATLIN, BRYAN, STACY & DILLARD
February 18, 1999
1716 Briarcrest Drive, Suite 206
Bryan, Texas 77802
409/260-7030
Fax No. 409/268 -3037
TO: Veronica J.B. Morgan, P.E.
COMP ANY: City of College Station
Asst. City Engineer
.FAX NUMBER:(409) 764-3496
FROM: Lynette in Pat Stacy's office
RE: HERITAGE AT DARTMOUTH PROJECT.
OUR FILE AND/OR CASE NUMBER: 9387-18
NUMBER OF PAGES: 3 (Including this Page)
Please call immediately if you do not receive the total number of pages.
MESSAGE AND/OR COMMENTS:
OUR LETTER OF 2-18-99 WITH ENCLOSURE: PROPOSED COPY OF CITY'S LETfER TO MR.
GLOCKZIN.
NOTICE
TIIlS FACSThfiLE MESSAGE IS A PRIVILEGED AND CONFIDENTIAL ATTORNEY-CLIENT
COMMUNICATION AND IS TRANSMl'ITED FOR Tl:IF: EXCLUSIVE INFORMATION AND USE OF THE
ADDRESSEE. PERSONS RESPONSIBLE FOR DEUVERlNG TfilS COMMUNICATION TO TIIE
INTENDED RECIPIENT ARE ADMONISHED THAT nus COMMUNICATION MAY BE NO'l' BE
COPIED OR DISSEMINATED EXCEPT AS DIRECTED BY THE ADDRESSEE .
IF YOU RECEIVE THIS COMMUNICATION IN ERROR, PJ .. E~SE NOTIFY US IMMEDIATELY BY
TELEPHONE AND MAIL THE COMMUNICATION TO US AT OUR LETTERHEAD ADDRESS.
@001
02 /18 /99 12 :4 5
Bili Youngkin
Larry A. Catlin ·
'6'409 268 3037 Y-C-B & S
Yo~ Catlin, Bryan, Stacy & Dillard
Anorneys at Law ·
Post Office Box 4629
: Bryan, Texas 77805
Galleria Village .
1716 Briarcrest Drive
Suite 206
@002
Board Ct<t~i/l cd l':<111ily LlW
·r.x.1> l:ln•rcl Leg•I Spccl•liz:itio1i
Travis . .8. B1yan , IJI
Boar<i Certifi ed Crimi.i•l 1'.w
Ti:x.:i s Bt.:r.trd Lc:~ttl Spc d:Jli u til1J1
Pierce P. Stacy, III ·
February 18, 1999 Bryan, Texas77802
Telephone ; (409) 260-7 030
· Fax: C 409}.268-3037
Roard C.:ert1ficd C:nmun::t'1..-:i:.1 l nt~J t-:totalc L;;atv
Tex.'~ "Bu,lrd l.ci;:.I ~ped~liz~rton
jack W. Dillard•
'.•l•o M.,111Y.r of Ml~i.,ipp l nar
Michele P. Esparza
liOl&rtl .ccrtifi c<I (.;r lm1nal L;>w
Tt<.>.ll < r1nard LCl!"Jl Specl•li:t>tiC>I\
SENT BY FAX TRANS1\1ISSION
(409) 764-3496
Veronica J .B. Morgan, P.E ..
Asst . City Engineer
City of College Station
· 2613 Te~as Avenue S .
· College Station, Texas 77840
RE: HERITAGE AT DARTMOUTH PROJECT.
Dear V cronica;
"I am attaching hereto a draft of the lener which Emanuel Glockzin '~ould lfre fo~· the Cicy to e;ic.ccute . in
connection with our detention pond mancr for the. Ashford ·square and .Heritage at Dartmouth Projects.
If you .and Mr. Mos.ely can see fit co execuring ·this letter that will satisfy .us that Glockzin will nor have
to put· additional detention pond improvements or other drainage improvements ·on his Property to gee his Project
· finally approved . If you are not able to sign this lea:er, then please give me a call and let's see what we can do wirh
regard to changes. ·
We sincerely appreciate your help and assistance in this maner as we.II as Mr. Mosely's. You cleared up
a Jot of questions which Emanuel had as _well · as myself. .
Thanking you, I am ·
PPS:lf
GF#9387-18
·Enclosure
. very truly yours,
[2;:f2:nI§:J~fa·rn.~&:~·:B§:_·.~·~x~-~-·:2rt.~.~-·::.·::·.·_·_· .. ·.·.·.:·:.:.·.·_··_·_:_·_· __ ·_·_·_·_·_·_·_::···:· __ ·_:· .. -.-.-.-.::·.·.·:.·.·.· .. :·.·.:· .. ·.·_·_·:.::. ·.:.::: :::·:·.:·.·:·.::·.:·· .. ::.::: ::·::::: .. ·.:·:.·.·:.:: ... ·.·.: .. ·.·.·.·.:·.:.:.· ... ·.·.· ... ·.:: .. · .. ::·: ::r>.~s~·.J;
From:
To:
Date:
Subject:
Bob Mosley
VMORGAN@CITY OF COLLEGE STATION .CITY HALL
3/3/99 1 :1 SPM
Re : status of fax
I have reviewed the letter and would suggest several revisions to the wording:
1) revise "insufficient detention pond or drainage improvements for your Project" to "insufficient
detention pond capacity for your Project".
2) revise "Further requirements for drainage improvements on the Property or adjoining properties
(Swoboda Property) will be performed and paid for by the owners of the Ashford Square Project backed
by Letter of Credit." to "Further requirements related to the detention pond or downstream drainage
improvements (Swoboda Property) are the responsibility of the developer of the Ashford Square project."
I believe that the above wording should be restricted to the detention pond and downstream issues and
items related to payment and a letter of credit is of no consequence to this developer.
With the revisions listed and if you will confirm that the calculated detention conforms to the particular
lots listed, I will be happy to sign. Spelling of the name needs to be corrected.
>>> Veronica Morgan 03/03/99 10:03AM >>>
bob,
i faxed you a copy of a fax and letter sent to me by pat stacy regarding the ashford square detention
pond . have you looked at that? are you willing to sign that letter as written? let me know ... i need to close
my file on this and the attorney's are calling. thanks
v
02 /18 /99 12 :46 '5'409 268 3037 Y-C -B & S
' ; ... "
(PLEASE PUT ON THE CITY'S LETTERHEAD)
Mr. Emanuel H. Glockzin, Jr.
4500 Carter Creek Park-way, Ste . 101
Bryan, Texas 77802
(DATE)
RE: HERITAGE AT DARTMOUTH PROJECT.
Dear Emanuel :
As requested. the City hereby confirms that there is capacity for the post-development runoff from the
Heritage ar Dartmouth Project within the Ashford Square detention pond. Your Project, as defined in the Ashford
Square report , is Lot Two (2) and Three (3), Block One (1) of the DARTMOUTH ADDITION SUBDIVISION.
You are now au t horized to utilize the Ashford Square detention pond and no permits or approvals from the City will
be withheld for your Project on the basis of insufficient detention pond or drainage improvements for your Project.
Further requirements for drainage improvements on the Property or adjoining properties (Swoboda Property) will
be performed and paid for by the owners of the Ashford Square Project backed by a Lener of Credit. The City will
not request payment or performance from you. The City has accepted the detention pond and drainage
improvements as a public dedication and will maintain the same at no cost to you .
Very truly yours ,
CITY OF COLLEGE STATION
by :
~~~~~-~~~~~~~~~~~
Name : ROBERT MOSELY
Title : CiLy Engineer
by :
~~~~~~~~~~~~~~~~
Name : VERONICA J. B. MORGAN, P.E.
Title: Assistant City Engineer
~003
53<6
COLLEGE STATION
P. 0 . Box 9 96 0
September 25, 1998
Fred Paine
Kling Engineering
4103 Texas Avenue, Suite 212
Bryan, Texas 77802
110 1 Te xas Ave n ue
Tel : 409 764 35 00
RE: Ashford Square Detention Pond Acceptance
Dear Fred,
Co ll eg e Station , TX 77 84 2
The City of College Station will accept the detention pond improvements on the Ashford
Square property once :
a) the drainage improvements are completed downstream on the Swoboda
property
and
b) the improvements downstream are sufficient to allow the pond to drain dry.
If you have any further questions, please call.
cc: file
Shirley Volk, Development Coordinator
Bob Mosley, City Engineer
Home of Texas A&M University
September 23 , 1998
Allen Swoboda
8415 Appomattox
College Station, TX 77845
Ms . Veronica Morgan
Assistant Engineer
City of College Station
P .O . Bo .10230
College Station, TX 77842
Dear Veronica,
I have been working with David Scarmardo to alleviate the drainage problem
encountered with the detention pond , which is in his Ashford Square project off
Southwest Parkway.
We have agreed that he will lower the channel depth of the creek, which drains
the said detention pond through Oak Forest Mobile Home Park. The channelization must
have a continuous grade of 0 .50% from the outlet of the pond to the Culvert Bridge at
Oak Forest Street. In order to achieve proper drainage they will need to chip off
approximately 8" of protective concrete over a sewer line, which crosses the creek. The
channel shall have a 6-foot bottom with side slopes of 5 : 1 or less . All dirt removed will
be replaced along the banks of the creek. The banks of the creek will be block sodded for
the first 150 feet from the outflow of the detention pond . The remainder of the creek
banks will be hydro muclh seeded.
The channelization and sodding and seeding will need to be completed by
November 15 , 1998 .
Sincerely,
a~
Allen Swoboda, Owner
Oak Forest Mobile Home Park
10 /16 /98 15:40 '5'409 846 8252 KLI NG ENGR ~~~ COCS VOLK /MORG AN
KLING ENGINEERING & SURVEYING
TELECOPIER COVER SHEET
DATE !u/!(p/!8
t
4EF:fuoover)
Please deliver the following pages to:
Name: ~;12 L~ ;£"--/idf2ot)ILA ~4N
Firm: et'r-/ d (l, S' t£~rl~ ~ s
I
From: Gt?D &N,!;
Kling Engineering & Surveying
4103 South Texas Ave .• Suite 212
Bryan, Texas 77802
Phone: (409)846-6212
Fax: (409)846-8252
We are transmitting _....;;;3"-___ page(s), including this cover letter from our
fax number listed above. If any pages are missing or incomplete, please
contact sender.
141001
10 /16 /98 15 :41 '5'409 846 8252 KLI NG EN GR ............ COCS VOLK /MORG AN
KLING ENGINEERING & SURVEYING
Consulting Engineers • Land Surveyors
4103 Texas Avenue, Suite 212
Bryan,Texas77802
Post OfTice Box 4234
Bryan, Texas 77805
B.J. Kling, P.E., R.P.L.S.
S.M. Kling, R.P.L.S.
Telephone 409/846-6212
Fax 409/846-8252
October 1 6, 1998
MEMO
TO: Gary Arnold
Texcon
General Contractor
Bob Mosley David Scarmardo
City of College Station Developer
City Engineer
FROM: Fred Paine
RE: Ashford Square I Dartmouth Addition Subdivisions
Site Meeting of October 1 6, 1998
Detention Pond Final Acceptance Issues
The following is a summary of my understanding of the discussions that
occurred during the above referenced site meeting:
For final acceptance of the drainage improvements for the Ashford Square
subdivision lots 2-7, block "C", and lots 1-6, block "D" and the Dartmouth Addition
subdivision lots 2-3, block 1, the following issues will be resolved by the contractor.
1) The parking area that is utilized as a drainage way does not convey runoff
to the detention pond as intended, resulting in accumulation of sediment
and a thin layer of irrigation water in the end parking spaces. A grass
berm has been built up which further precludes water from entering the
detention pond under sheet flow conditions causing a channelization of
the water with subsequent erosion. The contractor agreed to place
additional rip-rap on a constant grade from the concrete edge to the
existing pond insuring positive drainage from the parking area/drainage
way and to correct the erosion.
2) Erosion has occurred along the sides of the concrete pilot channels
entering the pond area. This is to be corrected by filling the void spaces
in the rip-rap with smaller rip-rap and concrete grout.
14100 2
10 /16 /98 15:41 '5'409 846 8252
Ashford Square I Dartmouth Addition
Memo -Continued
October 1 6, 1998
KLI NG EN GR ~~~ COCS VOLK /MORG A
3) Excessive sedimentation has occurred within the pond area. While some
sediment is attributed to erosion from items 1 and 2, above, the bulk of
the sediment is coming from the Dartmouth Addition lots 2 and 3
construction where improperly installed and maintained silt fencing is
observed. The Contractor agrees to clean the amount of sediment
existing in the detention pond to date at a future time during the warranty
period. This will be done when the pond has had time to sufficiently
"dry-out" and equipment can be brought in without damaging existing
grading. The City Inspector is aware of the improperly maintained silt
fence and will be in contact with the contractor for the Dartmouth
Addition site to rectify the situation.
4) Positive drainage through the pond and outlet works will need to be
assured. Current downstream channel cleaning allowed for positive
drainage at the project outfall. Any additional downstream channel
improvements are considered "private" in nature and left up to the Owner
of the downstream channel and the Developer to negotiate. Pending
improvements include a low flow concrete flume and re-establishment of
vegetation via sod and hydromulch .
Upon completion of items 1 and 2, above, and visual confirmation of positive drainage
through the outlet works, the Contractor will contact the City Inspector for final
approval and with final approval, an acceptance letter issued by the City of College
Station. It is understood that item 3, above, will be completed during the warranty
period by the Contractor when weather permits sufficient drying of the pond .
Please call should there be any additions, corrections, or comments pertaining to the
site meeting discussions .
cc : Shirley Volk I Veronica Morgan
City of College Station-Development Services
141003
D~ 'SoB
COLLEGE STATION
September 8, 1998
Emmanuel Glockzin
4500 Carter Creek Parkway
Bryan, Texas 77802
Dear Mr. Glockzin,
P. 0 . Box 9960 1101 Texas Avenue
Tel: 409 764 3500
College Station , TX 77842
Per our phone conversation Friday, September 4, 1998, the City of College Station has issued a
development permit for the Heritage @ Dartmouth project. There is one exception noted on the
plans which does not allow the construction of the drive aisle at the far west side of the project
along the creek. This is not being permitted for construction at this time pending the resolution to
the Ashford Square detention pond acceptance . This area will be permitted once:
1. The downstream channel improvements are accomplished to allow the Ashford Square
detention pond to completely drain.
or
2 . The grades on the rear driveway are revis ed and the detention pond design/drawings
located on your site are approved for construction .
The latter of the options would allow your site to stand alone independent of the Ashford Square
detention pond . As your construction progresses remember that this rear drive is essential to allow
your contractor to bring combustibles on site for many of the rear buildings. Please let me know if
you have any questions or concerns .
cc: Site Plan File ./
Development Permit File V
Jon Mies , Fire Marshal
Shirley Volk, Development Coordinator
Home of Texas A&M University
I
I I
I
DEVELOPMENT PERMIT
PERMIT NO . 538
ASHFORD SQUARE FINAL PLAT AREA
FOR AREAS OUTSIDE THE SPECIAL FLOOD HAZARD AREA
RE : CHAPTER 13 OF THE COLLEGE STATION CITY CODE
SITE LEGAL DESCRIPTION:
Ashford Square Lots 2,3,4,5,6,7 Block C
and Lots 1,2,3,4,5,6, of Block D
OWNER:
DWS,Inc.
David Scamardo
P .O . Box 4508
Bryan, Texas 77805
( 409) 779-7209
DRAINAGE BASIN:
Bee Creek
TYPE OF DEVELOPMENT:
SITE ADDRESS:
Southwest Parkway
This permit is valid for demolition ONLY as per the construction plans!
The Contractor shall take all necessary precautions to prevent silt and debris from leaving the immediate
construction site in accordance with the approved erosion control plan as well as the City of College
Station Drainage Policy and Design Criteria. The Owner and/or Contractor shall assure that all disturbed
areas are sodden and establishment of vegetation occurs prior to removal of any silt fencing or hay bales
used for temporary erosion control. The Owner and/or Contractor shall also insure that any disturbed
vegetation be returned to its original condition, placement and state. The Owner and/or Contractor shall
be responsible for any damage to adjacent properties , city streets or infrastructure due to heavy machinery
and/or equipment as well as erosion, siltation or sedimentation resulting from the permitted work.
Any trees required to be protected by ordinance or as part of the landscape plan must be completely fenced
before any operations of this permit can begin .
This permit, being temporary, is valid only within sixty (60) days of the date shown below, and is not
intended to allow the complete development of the site as proposed . Any work performed after the
expiration of this permit is not covered, and is considered unauthorized .
In accordance with Chapter 13 of the Code of Ordinances of the City of College Station, measures shall be
taken to insure that debris from construction , erosion, and sedimentation shall not be deposited in city
streets , or existing drainage facilities.
I hereby grant this permit for development of an area outside the special flood hazard area. All
:velopment shall be in accordance with the plans and specifications submitted to and reviewed for
o pliance by the City of College Station in the development permit application for the above named
~ect and codes and ordinances of the City of College Station that apply .
~f l~tl~
Date
o "3 /r z_ !YB
Date / •
Contractor
., ......
,. ' ..
I
I
"',\_..,
DEVELOPMENT PERMIT
PERMIT NO . 538-A
ASHFORD SQUARE FINAL PLAT AREA
FOR AREAS OUTSIDE THE SPECIAL FLOOD HAZARD AREA
RE : CHAPTER 13 OF THE COLLEGE STATION CITY CODE
SITE LEGAL DESCRIPTION:
Ashford Square Lots 2,3,4 ,5,6,7 Block C
and Lots 1,2 ,3,4,5 ,6, of Block D
OWNER:
DWS, Inc.
David Scamardo
P .O . Box 4508
Bryan, Texas 77805
( 409) 779-7209
DRAINAGE BASIN:
Bee Creek
TYPE OF DEVELOPMENT:
SITE ADDRESS:
Southwest Parkway
This permit is valid for the const111ction of all infrastructure as shown on the approved plans.
The Contractor shall take all necessary precautions to prevent silt and debris from leaving the immediate
construction site in accordance with the approved erosion control plan as well as the City of College
Station Drainage Policy and Design Criteria. The Owner and/or Contractor shall assure that all disturbed
areas are sodden and establishment of vegetation occurs prior to removal of any silt fencing or hay bales
used for temporary erosion control. The Owner and/or Contractor shall also insure that any disturbed
vegetation be returned to its original condition, placement and state. The Owner and/or Contractor shall
be responsible for any damage to adjacent properties , city streets or infrastructure due to heavy machinery
and/or equipment as well as erosion , siltation or sedimentation resulting from the permitted work.
Any trees required to be protected by ordinance or as part of the landscape plan must be completely fenced
before any operations of this permit can begin .
In accordance with Chapter 13 of the Code of Ordinances of the City of College Station, measures shall be
taken to insure that debris from construction, erosion, and sedimentation shall not be deposited in city
streets, or existing drainage facilities.
I hereby grant this permit for development of an area outside the special flood hazard area . All
development shall be in accordance with the plans and specifications submitted to and reviewed for
compliance by the City of Co lege Station in the development permit application for the above named
Dall
project and de d ordinances of the City of College Station that aJ?ply.
BJ/dd'
.s--1 Cf -lg
Date
Contractor Date
CITY OF COLLEGE STATION *** CUSTOKER RECEIPT *** OPER: KRODGERS CT DRAWER: 1 DATE: 5/14/98 00 RECEIPT: 0013612
DESCRIPTION QTY AKOUHT TP TK
KISC EHGR CHARGE $300.00 3D CK
TIKE: 11 :09:23 TOTAL PERSONAL CHECK _ AKOUHT TENDERED
THANK YOU
$300.00
$300.00
..
"
~~~ COCS VOLK /MORG AN
04 /14 /98 09 : 33 '5'409 846 8252 KL IN G EN GR
......----"
TELECOPIER COVER SHEET
IEF :fexcov11r)
Please deliver the following pages to:
Name: //e:tZQIV&4 J//~ni /::.~rztey 'T~ I I
Firm: C!r ,fy cf e ~r
Fax Number: ________________________ _
From: F/2ef-D !KM!
Kling Engineering & SufV&Ying
4103 South Texas Ave., Suite 212
Bryan , Texas 77802
Phone: (409)846-6212
Fax: 1409)846-8252
We are transmitting 2 page(s), including this cover letter from our
fax number listed above. If any pages are missing or incomplete, please
contact sender;/}
Regarding: ~ {;hvrr /j}t:E;r
Cui-SJ~
~00 1
04 /14 /9 8 09 :3 3 '5'4 09 8 4 6 8 25 2 KLI G E NGR ->->-> CO CS VOLK /MORG AN 14100 2
PROJECT: ASHFORD SQUARE SUBDIVSION 13-APRIL-98
ASHFORD WEST DRIVE STA 0+00 TO STA 3+65
BENCHMARK: TOP OF FIRE HYDRANT TO BE RELOCATED
ELEVATION: 275.69
O/S STATION R/L HUB ELEV. TOP OF CURB ELEV. CUT/FILL
KLING ENGINEERING & SUR \!EYING
05 /12 1 98 16 :15 '5'409 8 4 6 8252 KLIN G EN GR _,_,_, COCS VOLK /MORG AN
KLING ENGINEERING & SURVEYING
TELECOPIER COVER SHEET
DATE oe, /1z /?£
Please deliver the following pages to:
Fax Number=-------------------------
From:_h __ £?o~._f ........ ~ ....... rA.J ...... ~ _____________ _
Kling Engineering & Surveying
4103 South Texas Ave., Suite 212
Bryan, Texas 77802
Phone: (409)846-6212
Fax: 1409)846-8252
We are transmitting Z page(s}, including this cover letter from our
fax number listed above. If any pages are missi or incomplete, please
contact sender. r /'l ,,-;--Regarding:,~~~~~~~~~~~~~~~~~~--~~~~·~·~~~~~~~
J(l'{Z1: VA VI 1::>
I
141001
05 /12 /98 16 :1 6 'a4 0 9 846 8252 KLI NG ENGR ->->-> COCS VOLK /MORG A 14100 2
..
41230 Federal Register / Vol. 57, No . 175 / Wednesday. September 9, 1992 / Not ices
Appendix C -NOi Farm Instructions
S.. Reverse tor Instruction• Fctm~. C..W..IDIO-OOM ..__ ......... , ... ,. EPA --·----N'OEll W-.ti~. OC 20"60
FORM ,., Notice of I ntent (NOi) for Storm Water Dlschargu Associated wtth l nduatrlal
Activity Under the NP DES General Permit
SubmlMiCfl ,,, ... ,...,.. o l lntlnr "°"'~ "'*9 .,.. .. ~ ld9nff\lld In Seaiotl I of M '°"" ~ '> De ad'l:lrii9d ~ a NPOES ~ Ul;eO fOI' l lOtn'I
-d~ M&Oda..:I wllh lndua.W d\112( In t'4 s-ldenlllWd In &ec:ocirt 11 al 1l'lla torm . &.aom~a~ otll~ IMMil dlldlarQ91' I) CIQmply _.,
fie..,_ sad ml'lditlesw al .... Plf"'lt, MJ.. N CESSAAV INFOAMATION MUST BE PAOVI OEO ON I FORM.
I. Faouty ()plraa ln farmallcn
Nana: 1UkC:tJ,/l.. I ~ ~S..~/1f:.~. J C:tJtv.~craRS, I J Ptaw: I 4.cq if 7. 7. Ji 'J.., 5;' $i
J.~n .z T:Afio.t ,@ t Sllftmaf ~r AOdr.-: I I I I I I I I I I I I I I I I I I O-..()p«acw:
City : ~,~.,.£~~ ~r.tlE.t..e.& ""'; A.R~.4&] Sia :~ l l PCade : 17.Z.~tJ1l.1 . I I I I I
II . Facillty/Sllll Ux:a•on lnfomlaDon
!/l.(.h{ ffe,& .a 1S.4',A.,< e; I
,, .... Fdcy (Jxalad al ~ Na'l19 : I I I I I I I t I I I I I I I Indian L..andm7 (Y er N)
Adc!IWll : 1A,S:..,/l,et> .£,tJ. .~g,,~~ I I I I I I I I I I I I I I I I I I I
Cltf: k:'.'.'1o 1 L,l, '[&! E. I ,.t;z A, 4/ f?tV. I I I I I I I Slllll : ~ ZIP Cade: I z 7.3.4 , s . I I I I I
~: l31~l1~IJ1~I l.OIQitala :I 0 1~1 ,ll1~1 l 1 Zleuar.: ~ Seaon: L..J Town.nip : I I I I I Range : LI I I I
111. Site ktMrf intormauan
MM ep.air NM19: 1 C1,Z:X I ,12J:;-I L,d,? 4€76/3, £r.!l7/tW , I I I I I I
~WOMBady: 1.B.f\e:: I .~.t2. a-~~ I I I I I I I I I I I I I I
II Veu ... Filing U I Co-f*mit!M, I I ~~~ (YotN) INI Is 1W F~l i~ ~iract t:a Su bm it [I] Enw Swm w .. r a.n.tw Permit NIMT!bar : I I I I I I I I Mcntaring ••? (TI 2. ot 3)
SICar~
Pnnaty: I ,c,o, 2nd : I I I I I I N:IMrr Ccldlt: I I I I 3rd: I I I 4ltl : I I I
H This F~ Mam*-ot 1 Gr~
Aj:lplcaMn. Group~ ber: I I I I I
H Veu ~ 00. EKinno NPOES L, I I I I I Peimi•. en. Pwrmif Numtlrel'I : I I I I I I I I I I I I I I I I I I I I I I I
IV . Adclllanll lnlannatic:in AeQund tar CGnll\leion ~ Orft
Plojecl Compl!llO'I
Start 0.: 0..: II rw Storm Wmr Pa&alar\ ,.....,!Ian PIM
k2..S:l l~ 2a l l'21al ~1 l l ~1.&1 Ea.,_.~.,tm I 1 l12I In Compllnm ..... s-nllOI' Ulcal ~ DilMtlreel (In Alnll: I I I ~and Ermion P!lr.7 (Y OI NI
V. C:.1' San: I ~ W.-~of lilw lhal 11'111 dCll:l,m9r1C nl II •DrdWMllla Ml'8 snipmr9d und« my~ or ~in~~ I
~ dlllQNrd D ._.. l\lt ~ pnlZlnll ~ gdwt nt .,._ .. ~ IUtln'lmd. Ba.a Cl'I my~ CIC t. f*ICl"I s PlflGM-..V ·
,.,. b~tlm , OI ._. prlllOl"a dw.cay ~tar~ fie tfth'M~ll ... lrlarmmion SllblNlllld It, ID .. bemt mr-=:r. and t.W, ftl9.
aacu.11. cmt1ple•. I .,. .._ 1\111 ._. .. llQll!bnt ~ tar llltlmftllng taaa irlarma'°'1. lrdlding 11e ~ ol llnl i11pilolwne1111w
~vtolenl.
PllntfWM: 0..:
l~~~I .H,1 &4f~I( I I I I I I I I I I I I I I I I I I 10, ~£ .dl21il
SIQnaue : ~ -Lt.. ~
EPA F-J51CHI (1-IZ)
KLING ENGINEERING AND SURVEYING
Consulting Engineers • Land Surveyors
4103 T exas Avenue , Suite 2 12
Bryan, Texas 77802
TO
Tei. (409) 846-6212
Fax (409) 846-8252
PROJECT N O .
PRO JECT N AME
ATTENTION REFERE NCE
WE TRANSMIT :
D Under Separate Cover
)q_Enclosed
VIA :
DMail
~Messenger
IO Federal Express
D Express Mail
D Special Courier
D Picked Up By Your Office
NO. z A DtxrA J f).J ......
( ~I A J,:1".
n::>
THE FOLLOWING :
D Prints
D Copies
D Originals
D Plat
D Field Notes
~lans
~Report
D Estimate
D Cut Sheets
D Computer Printout
D File
D Contract
~f(. §.,v.
DESCRIPTION
012.4 ,Al.a...·~ D_ -~-
(., ( l I
s (j) .s-1/1 "~ ~ 1..A •l ... 1 __ ,R J -.JT7 ...... \
(I,... \~7"7' ,,_;n • .,_ \ Q_.....J~
-;-.,7)q,,yJ ./)
{ ;s:, .,. ,_ --,
) (\ -n_-nPf,AJi7X"J -
D.-A I f'I
LJ ,-,.A,LJ-.
If
Al
FOR :
P.O . Box 4234
Bryan , Texas 77805
D Your Rev iew & Approval
D Your Review & Comment
D Your Review & D istribution
D Your Review, Revision & Return
D Your Signature & Return
D Your File and/or Use
D As Requested By :
D Please Acknowledge Receipt of
Enclosures
D Please Return Enclosures To Us
D Copies Of This Letter Of Transmittal
Sent To :
If Enclosures Are Not As Noted ,
Please Notify Us At Once .
Si gned~\)---._::;:::,.
r --
KLING ENG R _,_,... COCS VQLK /MORG AN .--~-· O_O_l_
04 /27 /98 17:54 'a409 846 8252
-· KLING ENGINEERING & SURVEYING
TELECOPIER COVER SHEET
IEF:faxcovar)
DATE e1j-z7 /JJ?3
Please deliver the following pages to:
Name: ~'~ M~A# IJ:~ 3NB3
Firm: c,'Y °" CS.. //)ev. /5¢-s
l
From: [i2..a::r;::> j:;t_/,J6°
Kling Engineering & Surveying
4103 South Texas Ave .. Suite 212
Bryan. Texas 77802
Phone: (409)846-6212
Fax: (409)846-8252
2-We are transmitting _____ page(s), including this cover letter from our
fax number listed above. If any pages are missing or incomplete, please
contact send? . /1
Regarding: ti_SIF?:K:D ~JM6 Fe.-!> <._,;;,,,.J.a
--------------
04 /27 /98 17:54 'B409 846 8252 KLING ENGR
FIELD CHANGE
PROJECT: Streets, Drainage, & Utilities Improvements
FOR: Ashford Square Subdivision
College Station, Texas
TO : Texcon
Bryan, Texas
FAX (409) 778-3331
-+->-> COC S VO LK /M OR~G A=N'----~!41~0_0_2 __
FIELD CHANGE No._1 _
Date: April 27, 1998
This field change covers the modification to plans hereunder described :
Changes made to Street plans as follows:
Joint spacing applicable to Curb & Gutter and Concrete pavement
Contraction joints: Provide grooved contraction joint 2" deep at 15' increments. Tool edges with 1/8"
radius and seal joint with "Sealtight-#164, HI-SPEC or SOF-SEAL" hot applied
sealant· both as mfd. by W .R. Meadows , Inc. Construction joints can be
substituted at specified contraction joint spacing .
Construction joints : Must be substituted at specified contraction joint location only. Provide W'x18"
dowels @ 18" O .C. across construction joint and seal joint with "Sealtight-#164, HI·
SPEC or SOF·SEAL" hot applied sealant -both as mfd . by W .R. Meadows, Inc.
Expansion joints: Provide 3/4" expansion joint as shown on sheet DT-1 of plans every 60' in place of
contraction joint.
The work covered by this field change shall be performed under the same terms and conditions as
set forth and included in the original construction contract.
02 /02 /98 16 :15 '5'409 846 8252 KLING E GR ~~~ COCS VOLK /MO RG A
KLING ENGINEERING & SURVEYING
TELECOPIER COVER SHEET
IEF:fa;u:ovarl
DATE C2&(D-Z... f'J7
Please deliver the following pages to:
Name: __ ~-'-__..__-~_c.A--__ ~ __ 1'1:_4 ________ _
Firm:_C_.A.r..._'t1r--c-r......;..___~ ____ ~_S __ ~_· _77_~---------
Fax Number: ________________________ _
From:_-&_·-~~-+-Q_,_~-----------
Kling Engineering & Surveying
4103 South Texas Ave., Suite 212
Bryan. Texas 77802
Phone: (409)846-6212
Fax: (409)846-8252
3 We are transmitting paga(s), including this cover letter from our
fax number listed above. If any pages are missing or incomplete, please
contactsende~r. _s,r.., ....... -~ / ~y x-,_A-~ Regarding: \..I-' rJr-tr£-O ~ • c:;;.$71r>?rrl~
~001
02 1 02 1 98 16:16
CONTINUED
18 1 LS
19 4 EA
20 4 EA
21 1 EA
22 1 EA
23 1 LS
24 1 LS
25 3 EA
'5'409 846 8252 KLING ENG R +->-> COCS VOLK /MO RG A
Engineer's Estimate
Ashford Square ~ Resubdivision
Infrastructure Improvements
REVISED 23-JANUARY, 1998
Demolish and remove 6.S'xS.5' concrete
inlet box complete per lump sum
Adjust manhole lids flush to finished elev.
provide watertight protection complete and in plac
per each
Adjust waterline valve boxes to finished elevations
complete and in place per each
Demolish & repour concrete parking lot outlet
complete and in place per each
Relocate existing fire hydrant complete and in place
per each
-470 LF Silt Fencing per detail complete and in place
per lineal foot
20% Electrical Cost for Underground service
Street lights
$925.00
$250.00
$175.00
$200.00
$2,000.00
$2,000.00
$7,000.00
$500.00
TOTAL:
*10% Contingency:
GRAND TOTAL:
!41003
$925.00
$1,000.00
$700.00
$200.00
$2,000.00
$2,000.00
$7,000.00
$1,500.00
$190,400.80
$19,040.08
$209,440.88
--__________ ____..
02 1 02 1 98 16:15 '8'4 09 846 8252 KL IN G EN GR ~~~ COCS VOLK /MORG AN ~002
Engineer's Estimate
Ashford Square -Resubdivision
Infrastructure Improvements
REVISED 23-JANUARY, 1998
11EM QlY. UNIT 11 t:.M II UNIT PRICE TOTALAMOUN
NO.
1 2470 SY Demolish & remove existing 6" reinforced
concrete pavement complete per square yard $5.82 $14,375.40
2 81 TON Type A (Slurry) Lime for 6" depth subgrade
treatment -assumed dry unit weight of subgrade
= 120 pcf, 7% lime/unit '-1\1 of subgrade supplied
per ton $90.00 $7,290.00
3 4424 SY LimeTreatment -Lime Treated Sub-grade
(density control) for a depth of 6"
complete and in place per square yard $1.85 $8, 184.40
4 3889 SY 6" thick Reinforced Concrete Pavement
complete and in place per square yard $22.50 $87,502.50
5 2404 LF Monolithic Reinforced Concrete Curbing complete
and in place per lineal foot $8.00 $19,232.00
6 3635 SF 4" thick Reinforced Concrete Sidewalk complete
and in place per square foot $2.90 $10,541.50
7 4 EA 4" thick A. D.A. Reinforced Concrete 'Single'
Ambulatory Ramp complete and in place per each $800.00 $3,200.00
8 4 EA 4" thick AD.A. Reinforced Concrete 'Double'
Ambulatory Ramp complete and in place per each $1,200.00 $4,800.00
9 1 LS Water service line installations (1 1/2" x 1 ")
complete and in place per lump sum $4,800.00 $4,800.00
10 1 EA Water service line installation (1 1/2" x 1 ")
saw-cut and repair existing concrete drive to tie
complete and in place per each $500.00 $500.00
11 1 LS Sanitary Sewer service line installations (4")
complete and in place per lump sum $2,000.00 $2,000.00
12 1 EA Sanitary Sewer service line installations (4")
saw-cut and repair existing concrete drive to tie
complete and in place per each $600.00 $600.00
13 1 LS Grade -140 LF drainage channel , provide sod/
& rock rubble complete and in place per lump sum $5,000.00 $5,000.00
14 140 LF 4" thick, re inf. Concrete pilot channel
complete and in place per lineal foot $3 .50 $490 .00
15 1 LS Relocate existing light pole complete and in $2,000 .00 $2,000.00
pr ace per 1ump ::>u111
.. 16 J> 203 LF Remove and dispose of 2-36" R.C .P. storm $20.00 $4,060.00
sewer pipe complete per lineal foot
17 1 LS Demolish and remove concrete headwall
complete for lump sum $500.00 $500.00
CONTINUED
02 /11 /98 15 : 21 '5'409 846 8252 KLING E GR ~~~ COCS VOLK /IORGAN
KLING ENGINEERING & SURVEYING
TELECOPIER COVER SHEET
(EF:fexcover)
DATE OZ-/11 /f<a
Please deliver the following pages to:
Name:V~ M~~
Firm: Q. "1+ oE C-S.
From:___.._6_........-:_126[> __ ~~--'---r,d_~ ______________ _
Kling Engineering & Surveying
4103 South Texas Ave ., Suite 212
Bryan, Texas 77802
Phone: (409)846-6212
Fax: (409)846-8252
We are transmitting 3 page(s), including this cover letter from our
?"
fax number listed above. If any pages are missing or incomplete, please
contact sender. ~ ~ /
Regarding: 11-srlfJ!eO -~ ~~ Ce>>r
~(7J?f~
~001
-------------
02 /11 /98 15 :21 '5'409 846 8252 KLI NG E GR ~~~ COCS VOLK /IORG AN l4J 002
"" ..... -Engineer's Estimate
Ashford Square -Resubdivision
Infrastructure Improvements
REVISED 11-FEBRUARY, 1998
ITEM QTY. UNIT ITEM ~ UNll PRICE TOTAL AMOUNT
NO .
1 2470 SY Demolish & remove existing 6" reinforced
concrete pavement complete per square yard $5.82 $14,375.40
2 81 TON Type A (Slurry) Lime for 6" depth subgrade
treatment -assumed dry unit weight of subgrade
= 120 pcf, 7% lime/unit wt of subg,rade supplied
per ton $90.00 $7,290.00
3 4424 SY LimeTreatment-Lime Treated Sub-grade
(density control) for a depth of 6"
complete and in place per square yard $1.85 $8,184.40
4 3889 SY 6 11 thick Reinforced Concrete Pavement
complete and in place per square yard $22.50 $87,502.50
5 2404 LF Monolithic Reinforced Concrete Curbing complete
and in place per lineal foot $8.00 $19,232.00
6 3635 SF 4" thick Reinforced Concrete Sidewalk complete
and in place per square foot $2.90 $10,541.50
7 4 EA 4" thick A. D.A. Reinforced Concrete 'Single'
Ambulatory Ramp complete and in place per each $800.00 $3,200.00
8 4 EA 4" thick A.D.A. Reinforced Concrete 'Double'
Ambulatory Ramp complete and in place per each $1.200.00 $4,800.00
9 1 LS Water service line installations (1 1/2" x 1")
complete and in place per lump sum $4,800.00 $4,800.00
10 1 EA Water service line installation (1 1/2" x 1")
saw-cut and repair existing concrete drive to tie
complete and in place per each $500.00 $500.00
11 1 LS Sanitary Sewer service line installations (4")
complete and in place per lump sum $2,000.00 $2,000.00
12 1 EA Sanitary Sewer service line installations (4")
saw-cut and repair existing concrete drive to tie
complete and in place per each $600.00 $600.00
13 1 LS Grade -140 LF drainage channel, provide sod/
& rock rubble complete and in place per lump sum $5,000.00 $5,000.00
14 140 LF 4" thick, reinf. Concrete pilot channel
complete and in place per lineal foot $3.50 $490.00
l :::> 1 u:s l"(e1oca1e ex1s11ng 11gm po1e comp1e1e ana m ~.2,000.00 $2,000.00
place per lump sum
·16 203 LF Remove and dispose of 2-36" R.C.P . storm $20.00 $4,060.00
sewer pipe complete per lineal foot
17 1 LS Demolish and remove concrete headwall
complete per lump sum $500.00 $500.00
CONTINUED
02 /11 /98 15 :22 'B409 846 8252 KLI NG EN GR ->->-> COCS VOLK /MORG AN ~0 _03 __
..
CONTINUED
ITEM ~ QTY. UNIT ITEM UNIT PRICE TOTAL AMOUNT
NO.
18 1 LS Demolish and remove 6 .5'x5.5' concrete $925.00 $925.00
inlet box complete per lump sum
19 4 EA Adjust manhole lids flush to finished elev.
provide watertight protection complete and in place
per each $250.00 $1,000.00
20 4 EA Adjust waterline valve boxes to finished elevations
complete and in place per each $175.00 $700.00
21 1 EA Demolish & repour concrete parking lot outlet
complete and in place per each $200.00 $200.00
22 1 EA Relocate existing fire hydrant complete and in
place per each $2,000.00 $2,000.00
23 1 LS -470 LF Silt Fencing per detail complete and in place
per lineal foot $2,000.00 $2,000.00
24 1 LS 20% Electrical Cost for Underground service $7,000,00 $7,000.00
25 3 EA Street lights $500.00 $1,500.00
26 1 LS Channel Improvements along North property line
complete and in place per lump sum $36,500.00 $36,500.00
27 1 LS Construct -100'x140' stilling basin complete and
in place per lump sum $30,000.00 $30,000.00
28 1 LS Demolish -460 sf existing concrete parking &
relocate perimeter curb complete and in place
per lump sum $2,000.00 $2,000.00
TOTAL: $258,900.80
*10% Contingency: $25,890.08
GRAND TOTAL: $284,790.88
~,,,,,,
;~OFJ"~~ ;.,~ * .... 1 ·L ·· ~~2 t~· -·"--1('°-G" •j B. J. LIN l"_\ . .,._ ............ J. 1
~ \ 24705 ~ f4 •• •
COLLEGE STATION
P. 0 . Box 9960
January 26, 1999
Mr. B.J. Kling ., P.E.
Kling Engineering and Surveying
4103 Texas Avenue, Suite 212
Bryan, Texas 77802
RE: Revised Drainage Report
Ashford Square
Dear Mr. Kling,
11 01 Tex as Avenue
Tel: 409 764 3500
College Station , T X 77 8L2
This is in response to the revised drainage report for the Ashford Square detention pond received
on January 21, 1999. Based upon the model contained in the report, there is an increase of 15 cfs
over existing conditions being discharged from the detention pond after development of the Ashford
Square and Heritage at Dartmouth sites . The report shows that this will result in slight increases
to the depth and width of the flood plain through the Oak Forest mobile home park
The City of College Station Drainage Policy and Design Standards allows for increases in post
development peak runoff flow rates, if there are adequate easements or rights-of-way to contain the
100-year peak flow rate. Currently the channel through the Oak Forest mobile home park does not
meet this requirement. For this reason, the pond as built does not meet city drainage requirements.
Options available to you to correct this situation at this point are:
• redesign the .outlet to detain to predeveloped runoff flow rates and velocities (under this
scenario, the city of College Station drainage standards does not require downstream
easements), or
• acquire the necessary easements downstream to contain the pathway for this 100-year
discharge from the pond, or
• concurrence from the affected downstream property owner that they understand the impact to
their property and will allow the increase in depth and width given the proposed channel
improvements.
If you have any questions, please contact me at 764-3570.
xc : Jim Callaway, Director, Development Services
Bob Mosley, P .E ., City Engineer
vfile
Home of Texas A&M University
0 2 1 03 1 98 08 :15 'B409 8 4 6 8252 KL I NG E NGR ->->-> COCS VOLK /MORG AN
KLING ENGINEERING & SURVEYING
TELECOPIER COVER SHEET
IEF :fll.llcover)
DATE. _____ a_·z.__/o_.3_/9 ___ B ____ _
Please deliver the following pages to:
Name:_~_ru;N __ ct4_...;_jl/,,_<J££t_f.l._~ ___________ _
Firm:.--'"O,,,P.~+-'1'--0f"-'---C_S_, ____________ _
Fax Number:.~------------------------
From: r!Ze>r-:> RAP
Kling Engineering & Surveying
4103 South Texas Ave ., Suite 212
Bryan , Texas 77802
Phone: (409)846 -6212
Fax: (409)846-8252
We are transmitting 4 page(s), including this cover letter from our
fax number listed above. If any pages are missing or incomplete, please
contact sender .
Regarding: ~l/Yc%ZD ~~ -Crtf.W/\}(5t.-f,.n.t~?'S •
14100 1
4103 Texas Avenue, Suite 212
Bryan, Texas 77802
TO
ATIENTION
WE TRANSMIT :
0 Under Separate Cover
~Enclosed
VIA:
OMail
IMMessenger
0 Federal Express
0 Express Mail
0 Special Courier
0 Picked Up By Your Office
NO .
KLING ENGINEERING AND SURVEYING
Consulting Engineers • Land Surveyors
Tel. (409) 846-6212
Fax (409) 846-8252
P.O. Box 4234
Bryan, Texas 77805
DATE 0~/27 ~
t):X-l<.__
THE FOLLOWING :
0 Prints
OCopies
OOriginals
DPlat
0 Field Notes
OPlans
~Report
0 Estimate
OCut Sheets
PROJECT NO.
REFERENC E
0 Computer Printout
OFile
OContract
0
DESCRIPTION
FOR :
0 Your Review & Approval
0 Your Review & Comment
0 Your Review & Distribution
0 Your Review, Revision & Return
0 Your Signature & Return
OYour File and/or Use
0 As Requested By :
0 Please Acknowledge Receipt of
Enclosures
0 Please Return Enclosures To Us
0 Copies Of This Letter Of Transmittal
Sent To :
If Enclosures Are Not As Noted ,
Please Notify Us At Once .
al~!Dk
~~~~~~7~
~~
q, -;)6J
l
~ , c,'.vy-VP)\~
v1(l{lh ~ ;.,.J"-Ac-\---n '.(Yl y ~-r~~~~lc-l0,J)1_~00
~ Sv1'>216 J'?'t ~'";;.} ar t ~en~~ ~J?tM 5
I ~
4103 Texas Avenue, Suite 212
Bryan, Texas 77802
TO
ATTENTION
WE TRANSMIT :
D Under Separate Cover
~nclosed
VIA :
DMail
~essenger
D Federal Express
D Express Mail
D Special Courier
D Picked Up By Your Office
NO.
KLING ENGINEERING AND SURVEYING
Consulting Engineers• Land Surveyors
Tel. (409) 846-6212
Fax (409) 846-8252
D Prints
DCopies
D Originals
D Plat
D Field Notes
~I ans
D Report
D Estimate
D Cut Sheets
DATE
PROJECT NO .
PRO J ECT NAM
REFERE NCE
D Computer Printou t
D File
D Contract
D
DESCRIPTION
FOR:
P.O. Box 4234
Bryan, Texas 77805
D Your Review & Approval
D Your Review & Comment
D Your Review & Distribution
D Your Review, Revision & Return
D -Your Signature & Return
D Your File and /or Use
D As Requested By :
D Please Acknowledge Receipt of
Enclosures
D Please Return Enclosures To Us
D Copies Of This Letter Of Transmittal
Sent To :
If Enclosures Are Not As Noted ,
Please Notify Us At Once.
03 /06 /98 13 :09 'B409 846 8252 KLING E GR ->-->-> COCS VOLK /MORG AN
Figure XII
Application Form
Development Permit
lnsid~E.4Jtablished Flood Hazard Areas '--erfYor College Station, Texas
(re: Ordinance No. 1728)
SitelegalDescription: Ashford Square Lots 2 -7. Block C and Lots 1 -6, Block D
Site Address:
141002
--------------------------------------
Owner: DWS, Inc.
P.O. Box 4508
Address: Bryan, TX 77805
Telephone No.: ( 409) 779-7209
4103 Texas Ave. Suite 212
Architect/ Address: Bryan, TX 77802
Engineer: Kling Engineering & Surveying Telephone No.: {409)846-6212
3407 Tabor Road
Contractor: __ T_ex_c_o_n ________________ Address: Bryan, TX 77808
Telephone No.: (409)778-1355
Date Application Filed: _______________ Approved:-----------
Applicatio!l is ~ereby made for. th~ following s~cific waterway alteratipJlSt" No waterway a 1tera ti ans
--~pp t 1cat10n for demol1t1on · of existing concrete and ut1l1y services.
Attached as part of this application:
O Application Fee
~ Signed Certificate
O Site and Construction Plans, with supporting documentation: two (2) copies of each
Cl Other:------------------
ACKNOWLEDGEMENTS:
1-. I, ?D/frlff} U/c'1t-(4-000 as owner, hereby acknowledge or affirm that:
The above Drainage Plan and supporting documents complies wiht the requirements of Ordinance No. 1728,
and ~rll0~
Owner Date
, VIV 5 f)pw.frJ
Developer Date
, ~<CUJ
Contractor Date
Page 1of2
0 3 /06 /9.8 13: 26 '5'4 09 846 82 5 2 KLIN G ENGR ->->-> COCS VOLK / IO RG AN . . l4J 00 2
Figure XII Continued
CERTIFICATIONS:
A. I, certify that any nonresidential structure on or
proposed to be on this site as part of this application meets flood-proofing requirements as
set out in Section of Ordinance No . 1728
Architect/Engineer Date ..
B. I, certify that the finished floor level of the lowest
floor, including any basement, of any re8idential structure as part of this application is or
proposed to be at or above the base flood elevation as established in the latest Federal
Insurance Administration flood haz.ard study and maps, as amended.
Architect/Engineer Date
Date
D. I, do certify that any alterations, addressed in
Certification 11 D 11 do not raise the level of 100-year flood as referred to Certification 11 B 11 •
Date
REVIEWED FOR APPROVAL:----=---.,...--....-,..._,....---=-------
Floodplain Administrator Date
APPROVAL: Special conditions or comments as part of approval: ----------
Page 2of2
'-.l~--~-~
·~
..
. . .
. '
· ...... ,. · .
. . ·.
\
. · .
. ,, .
• ,. !" ••
~~ __ @~ f ~~ s~~# ~~ CITY OF COLLEGE STATION *** CUSTO"ER RECEIPT *** OPER: "RODGERS CT DRAWER: 1 DATE: 3/04/98 80 RECEIPT: 0009007 DESCRIPTION QTY AtlOUNT TP T" FILING FEE/DS/BI $100.00 B7 CK DWS DEVELOP"ENT-CK2187 DEVELOP"EHT PER"IT ASHFORD SQUARE "R TI"E: 9:47:81 TOTAL PERSONAL CHECK A"OUNT TENDERED THANK YOU $188.80 $108.88
06 /08 /98 15:55 '6'409 846 8252 KLING ENGR -+-+-+ COCS VOLK /MORGAN 141001
Q5h{tyd ~~ ua_r-e_ l)?
?)~1'
KLING ENGINEERING & SURVEYING
DATE o~/os/.PB
'
Please deliver the following pages to:
Name:
Firm:
Fax Number:
From:&~
Kling Engineering & Surveying
4103 South Texas Ave., Suite 212
Bryan, Texas 77802
Phone: (409)846-6212
Fax: (4091846-8252
We are transmitting 2 page(s), including this cover letter from our
fax number listed above. If any pages are missing or incomplete, please
contact sender. n
Regarding: 4/ZO ~ ~ Qo
06 /08/98 1 5:55 ~409 846 8252 KLI NG ENG R ~~~ COCS YOLK /MORGAN
KLING ENGINEERING & SURVEYING
Consulting Engineers • Land Surveyors
4103 Texas Avenue, Suite 212
Rryan,Texas77802
B.J. Kling, P.E ., R.P.L.S .
S.M. Kling, R,P.L.S.
Telephone 409/846-6211.
Fax 409/846-8252
FIELD CHANGE
Post Office Box 4234
Bryan, Texas 77805
PROJECT: Streets, Drainage, & Utilities Improvements FIELD CHANGE No ._2_
• v
FOR : Ashford Square Subdivision
College Station, Texas
Date : June 8 , 1998
TO : Texcon
Bryan, Texas
FAX (409) 778 -3331
This f ield change covers ttw modification to plans hereunder described :
Clarification for detention pond fac ility as follows :
Lone St ar Gas l i ne within slope of pond :
Lone Star Gas Co. has been contacted to give an estimate for deepening the existing lin e . It w ill be our
recommendation to the Owner to have this done . No modification to plan grades is to occu r.
Slew area reclamation:
All organic, unstable and otherwise objectionable material of the slew area within th e limits of pond is to
be excavated and disposed of. Fill the excavated pit with rock or concrete rubble grouted i n place . In
the vicinity of this area, berm of pond may be built up of grouted concrete or rock rubble . Gro ut to be
applied throughout berm, filling all voids as layers are completed.
PER P LAN
PER P LAN
ROCK BER M EXCAVATED &
REPLACED MAT'L
N.T.S.
The work covered by this field change shall be performed under the same terms and conditions as
set forth and included in the original construction contract.
14] 00 2
ADDENDUM TO THE DRAINAGE REPORT
FOR
Lots 2,3,4,5,6, 7, Block "C"
Lots 1,2,3,4,5,6, Block "D"
Ashford Square Subdivision
&
Lots 2 and 3, Block "1"
Dartmouth Addition Subdivision
Morgan Rector Survey, A-46
College Station, Brazos County, Texas
11-May, 1998
DEVELOPED BY:
Mr. David Scarmardo
D .W .S. Inc .
P .O . Box 4508
Bryan, TX 77805
( 409) 779-7209
PREPARED BY:
Kling Engineering & Surveying
4103 Texas Avenue , Suite 212
Bryan, TX 77802
(409) 846-6212
PURPOSE:
ADDENDUM TO THE DRAINAGE REPORT
for
Lots 2,3,4,5,6,7, Block "C"
Lots 1,2,3,4,5,6, Block "D"
Ashford Square Subdivision
&
Lots 2 and 3, Block "1"
Dartmouth Addition Subdivision
Morgan Rector Survey, A-46
College Station, Brazos County, Texas
11-May, 1998
The purpose for this addendum is to further clari fy the original report . The
follo wi ng items will be considered :
1. Table 2 -Pre-developed channel characteristics : emphasis is directed to the fact
that this table represents pre-developed conditions .
2 . Table 4 -Finished floor elevations were set for some lots within the
subdivision . These elevations are recorded on the final Rep lat of the
subdivision .
3 . Specifications for concrete rubble used as rip-rap were included on the plan
sheet to insure no protruding rebar be allowed .
4 . Appendix 3b -Drainage Areas -Post Developed Conditions: With respect to
curve numbers, the 79 .8 acre developed area of SB-II was assumed to be fully
developed with duplex dwellings . The 17 .8 acre grassed area of SB-II was
shown and assumed to be in its pre-developed state. This assumption proves
valid as all development (Jefferson Ridge Apartments) that has occurred has
done so in accordance with City detention requirements .
5. For comparison of pre and post developed conditions at the cross section
nearest the detention pond outlet, the post developed , routed flow leaving the
detention pond was run through cross section F-F . The following table has
been added .
Channel Characteristics
Section F-F Pond Outlet
Pre Post
Q s,io.is.ioo 469 .5 I 603 .8 I 735 .4 I 971.0 469 .0 I 603 .3 I 734 .9 I 970 .5 469 .0 I 603 .3 I 734 .9 I 970 .5
(cfs)
WSEL 268 .8 I 269 .1I269.4 /269 .8 268 .8 I 269 .1I269.4 I 269 .8 268 .9 I 269 .5 I 270 .0 I 270 .8
DEPTH 4 .8 I 5.1 I 5.4 I 5.8 4.8 I 5.1 I 5.4 I 5.8 4 .9 I 5.5 I 6.0 I 6 .8
(ft)
Velocity 7.3 I 8.1I8.7 I 9.7 7 .3 I 8.1I8.7 I 9.7 5.4 I 5.8 I 6 .1I6.5
(ft/s)
APPENDIX 1
REVISED CHANNEL & DETENTION POND PLAN
SEDIMENT / EROSION CONTROL TO BE
REMOVED AT COMPLETION OF PROJECT
FLOW 24"
min .
24"
min .
SEDIMENT CONTROL
N.T.S.
T-POST DRIVEN 24•
FLOW
SEDIMENT CONTROL FABRIC
EROSION CONTROL FENCING
N.T .S.
APPENDIX2
SANITARY SEWER PROFILE IN VICINITY
OF
CHANNEL & DETENTION POND FACILITY
APPENDIX3
HYDRAULIC CALCULATIONS
1********************************************
* HEC-2 YATER SURFACE PROFILES *
•*
* Vers i on 4.6 .2; May 1991
*
*
*
* * RUN DATE 11MAY98 TIME 16:37:50 *
********************************************
11MAY98 16:37:50
*************************************
HEC-2 YATER SURFACE PROFILES
Version 4.6.2; May 1991
*************************************
T1 ASHFORD SQUARE SUBDIVISION
x x xxxxxxx xxxxx x x x x x x x x x xxxxxxx xx xx x x x x x x x x x x x x xxxxxxx xxxxx
T2 PRE DEVELOPED/EXISTING CONDITIONS ·FIRST PROFILE - 5 YR EVENT
T3 DITCH SECTION ON NE. PROPERTY LINE FILE:PSTEXCON.DAT
T4 POST DEVELOPED -ROUTED Q FROM POND
J1 !CHECK INQ NINV !DIR STRT METRIC HVINS
2
J3 VARIABLE CODES FOR SUMMARY PRINTOUT
110
NC .06 .06 .OS • 1 .3
STARTING STATION G·G/STA 0+00 SECTION IN MOBILE HOME PARK
PROFILE J1 = 5 YEAR EVENT;
QT 4 469 603.3
X1 0 8 119 . 24
GR 268 0 266
GR 266 153.29 268
STATION F·F/STA 2+80
X1 280 19 130.6
GR 272 0 270
GR 266 131.5 265
GR 264 139.9 265
GR 269 162 .6 270
*************************************
HEC -2 YATER SURFACE PROFILES
Version 4.6.2; May 1991
*************************************
734.9
153 .29
119 .24
301.81
143.6
100
132.1
141.1
172.4
970.5
264
269.2
235
269
264
266
271
127.92
522.68
300
112.8
132.8
142.4
193.4
xxxxx
Q
263.05
280
268
264
267
272
xxxxx
x x x xxxxx x x
***************************************
* U.S. ARMY CORPS OF ENGINEERS
* HYDROLOGIC ENGINEERING CENTER
* 609 SECOND STREET , SUITED
* DAVIS, CALIFORNIA 95616-4687
* (916) 756-1104
*
*
*
*
* ***************************************
xxxxxxx
THIS RUN EXECUTED 11MAY98
YSEL
267 .15
135. 71
121.8
133.5
143.6
243.4
FQ
264
267
264
268
THIS RUN EXECUTED 11MAY98
PAGE
16:37:50
141
130.6
134.2
152.8
16:37:50
NOTE · AS TERISK (*) AT LEFT OF CROSS-SECTION NUMBER INDICATES MESSAGE IN SUMMARY OF ERRORS LIST
CH SECTION ON NE. PROPER
SUMMARY PRINTOUT TABLE 110
SECNO CIJSEL DIFKIJS EG TOPIJID QLOB QCH QROB
.000 267.15 .00 267.34 188.01 46.47 364.65 57.88
.000 267.35 .00 267.57 214.79 75.36 434.08 93.87
.000 267.51 .00 267.76 236.21 106.26 496.29 132.35
.000 267.76 .oo 268.04 269.68 167.86 593.55 209.09
* 280.000 268.77 .00 269.48 45.58 39.33 388.36 41.30
* 280.000 269.12 .00 269.95 52.50 66.82 466. 11 70.38
* 280.000 269.41 .00 270.32 59.07 98.37 532.97 103.55
* 280.000 269.82 .00 270.89 68.10 159.09 645.12 166.29
11MAY98 16:37:50
SUMMARY OF ERRORS AND SPECIAL NOTES
IJARNING SECNO=
IJARNING SECNO=
IJARNING SECNO=
IJARNING SECNO=
280.000 PROFILE= 1 CONVEYANCE CHANGE OUTSIDE ACCEPTABLE RANGE
280.000 PROFILE= 2 CONVEYANCE CHANGE OUTSIDE ACCEPTABLE RANGE
280.000 PROFILE= 3 CONVEYANCE CHANGE OUTSIDE ACCEPTABLE RANGE
280.000 PROFILE= 4 CONVEYANCE CHANGE OUTSIDE ACCEPTABLE RANGE
PERENC STEN CL STCHL STCHR STEN CR
.00 .oo 119.24 153.29 .00
.00 .00 119.24 153.29 .00
.00 .oo 119.24 153.29 .oo
.00 .00 119.24 153.29 .00
.00 .00 130.60 143.60 .00
.00 .00 130.60 143.60 .00
.00 .00 130.60 143.60 .00
.00 .00 130.60 143.60 .00
PAGE 10
l S U M P 0 l
Interactive Summary Printout
for MS/PC-DOS micro c~ters
May 1991
-----------------------------------
NOTE -Asterisk(*) at left of profile nl.lllber
indicates message in summary of errors
list
CH SECTION ON NE. PROPER
Summary Pr intout
SEC NO Q CIJSEL DEPTH
.00 469.00 267 .15 4.10
.00 603 .30 267.35 4.30
.00 734 .90 267.51 4.46
.00 970.50 267.76 4.71
* 280.00 469.00 268.77 4.77
* 280 .00 603.30 269.12 5 .12
* 280.00 734.90 269.41 5.41
* 280.00 970 .50 269.82 5.82
Summary of Errors and Special Notes
VLOB VCH VROB
1.18 3 .94 1.18
1.39 4 .37 1.39
1.56 4.74 1.56
1.82 5.24 1.82
2.82 7.32 2.81
3.35 8.11 3.34
3.77 8.70 3.79
4.38 9.70 4.46
IJARNING SECNO=
IJARNING SECNO=
IJARNING SECNO =
IJARNING SECNO =
280 .000 PROFILE = 1 KRATIO outside acceptable range
280.000 PROFILE= 2 KRATIO outside acceptable range
280.000 PROFILE = 3 KRATIO outside acceptable range
280.000 PROFI LE= 4 KRATIO outside acceptable range
SHEAR
.80
.96
1. 11
1.33
3.02
3.60
4.06
4.92
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Constant Data
Table
Rating Table for Trapezoidal Channel
e:\haestad\pi\ashford\ashford.fm2
POND OUTLET 2
Trapezoidal Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
0.050
0.008000 ftlft
2.000000 H : V
2.000000 H : V
Left Side Slope
Right Side Slope
Bottom Width 8.00 ft
Input Data
Minimum Maximum
DeEth 4.50 6.80
Rating Table
Depth Discharge Velocity
(ft) (cfs) (ftls)
4 .50 396 .23 5.18
4 .60 414.72 5.24
4 .70 433 .70 5.30
4.80 453.19 5.36
4.90 473.17 5.43
5.00 493 .67 5.49
5.10 514 .67 5.54
5.20 536 .20 5.60
5.30 558 .24 5.66
5.40 580 .82 5.72
5.50 603.92 5.78
5.60 627 .56 5.84
5.70 651.74 5.89
5.80 676.47 5.95
5.90 701 .75 6.01
6.00 727 .58 6.06
6.10 753.97 6.12
6.20 780 .92 6.17
6 .30 808 .44 6 .23
6 .40 836 .53 6 .28
6 .50 865 .20 6 .34
6 .60 894 .45 6.39
Increment
0.10 ft
05/11198
04:49:54 PM Haestad Methods, Inc. -37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5 .12
Page 1 of 2
•
Rating Table
05/11/98
04:49:54 PM
Depth
(ft)
6.70
6.80
Table
Rating Table for Trapezoidal Channel
Discharge Velocity
(cfs) (tus)
924.29 6.45
954 .72 6 .50
Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5.12
Page 2of 2
{j j'6
COLLEGE STATION
P. 0 . Box 9960
September 25, 1998
Fred Paine
Kling Engineering
4103 Texas A venue, Suite 212
Bryan, Texas 77802
1101 Texas Avenue
Tel : 409 764 3500
RE: Ashford Square Detention Pond Acceptance
Dear Fred,
College Station , TX 77842
The City of College Station will accept the detention pond improvements on the Ashford
Square property once:
a) the drainage improvements are completed downstream on the Swoboda
property
and
b) the improvements downstream are sufficient to allow the pond to drain dry.
If you have any further questions, please call.
cc: file
Shirley Volk, Development Coordinator
Bob Mosley, City Engineer
Home of Texas A&M University
September 23 , 1998
Allen Swoboda
8415 Appomattox
College Station, TX 77845
Ms . Veronica Morgan
Assistant Engineer
City of College Station
P .O . Bo:¥. J.0230
College Station, TX 77842
Dear Veronica,
I have been working with David Scarmardo to alleviate the drainage problem
encountered with the detention pond , which is in his Ashford Square project off
Southwest Parkway.
We have agreed that he will lower the channel depth of the creek, which drains
the said detention pond through Oak Forest Mobile Home Park. The channelization must
have a continuous grade of 0 .50% from the outlet of the pond to the Culvert Bridge at
Oak Forest Street . In order to achieve proper drainage they will need to chip off
approximately 8" of protective concrete over a sewer line, which crosses the creek. The
channel shall have a 6-foot bottom with side slopes of 5 : 1 or less . All dirt removed will
be replaced along the banks of the creek. The banks of the creek will be block sodded for
the first 150 feet from the outflow of the detention pond . The remainder of the creek
banks will be hydro muclh seeded .
The channelization and sodding and seeding will need to be completed by
November 15 , 1998 .
Sincerely,
a~
Allen Swoboda, Owner
Oak Forest Mobile Home Park
/. /.) ooa '0 f --------~7J_;-:::'/ll~-----------<4--:-----
-J.M ti r( \-:1,,
KLlNG ENGINEERING & SURVEYING
Consulting Engineers • Land Surveyors
4103 Texas Avenue, Suite 212
Bryan,Texas77802
B.J. Kling, P.E., R.P.L.S .
S.M. Kling, R.P.L.S.
February 25, 1999
Memo:
To: Jeff Tondre
Telephone 409/846-6212
Fax 409/846-8252
City of College Station, Development Services , Engineering
From : Fred Paine ~
re : Ashford Square I Dartmouth Addition Subdivisions Detention Pond
Post Office Box 4234
Bryan, Texas 77805
Accompanying this memo are the final calculations for the above referenced detention
pond. The outlet was modeled with the following modifications:
1. As-built elevation of concrete pilot channel -263.0 (design was 263 .8)
2 . Channel modifications including additional rock rubble placed to achieve a
3' bottom width centered on the concrete pilot channel and extending
vertical for a height of 1 '; then continuing up at 1.25h: 1 v side slopes to
maximum elevation of -271 (existing top of berm).
The accompanying calculations can be compared to the original drainage report's
documentation of existing flowrates . The network summaries in section 1 of the
Haestad-Pond Pack summary output can be used in this comparison. Also, an
elevation-volume-discharge relationship for the revised pond outlet and design pond is
located in section 5 of the output. We are currently developing a plan for the outlet
modifications and downstream erosion control/velocity mitigation as indicated in the
February 5, 1999 letter agreement from Mr. Swoboda . This plan is near completion and
we will submit it to you for review as soon as it is finished .
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Section Data
Cross Section -Revised Pond Outlet Channel
Cross Section for Irregular Channel
e:\haestad\pi\ashford\ashoutlt.fm2
outlet2 revised widened at top as-built
Irregular Channel
Manning's Formula
Discharge
Wtd. Mannings Coefficient
Channel Slope
0.023
0.008000 Wft
Water Surface Elevation
Discharge
271 .0 --
268.00 ft
314.45 cfs
\ J
\ 7 270.0
269.0
268.0
c
0 267.0 :;::;
I'll > Q)
iii
02124199
01 :38:03 PM
266.0
265.0
264.0
263.0
-20.0
\ ... '7 I
\ H 7
I
\ J
\ I
\ I
-15.0 -10 .0 -5.0 0 .0 5 .0 10.0
Station (ft)
Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
15.0
-~
20.0
FlowMaster v5.12
Page 1 of 1
Worksheet
Worksheet for Irregular Channel
Project Description
h:\fred\ashoutlt.fm2 Project File
Worksheet
Flow Element
Method
outlet2 revised widened at top/as-built
Irregular Channel
Manning's Formula
Solve For Discharge
Input Data
Channel Slope 0.008000 ft/ft
Water Surface Elevation 268 .00 ft
Elevation range: 263.00 ft to 271.00 ft.
Station (ft) Elevation (ft)
-18 .50 271.00
-18.00 271.00
-10 .25 271 .00
-1.50 264 .00
-1.50 263 .00
0.00 263.00
1.50 263.00
1.50 264 .00
10.25 271 .00
18.00 271.00
18.50 271 .00
Results
Wtd. Mannings Coefficient 0.023
Discharge . 314.45 cfs
Flow Area 35 .00 ft2
Wetted Perimeter 17.81 ft
Top Width 13.00 ft
Height 5.00 ft
Critical Depth 267 .92 ft
Critical Slope 0.008617 ft/ft
Velocity 8.98 ft/s
Velocity Head 1.25 ft
Specific Energy 269.25 ft
Froude Number 0.97
Flow is subcritical.
Start Station
-1 ~.50
-1.50
1.50
End Station
-1.50
1.50
18 .50
02/1 6199
04:44:48 PM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
Roughness
0.025
0.013
0.025
FlowMaster v5 .12
Page 1 of 1
Table
Rating Table for Irregular Channel
02/16199
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Constant Data
Channel Slope
Input Data
h:\fred\ashoutlt.fm2
outlet2 revised widened at top/as-built
Irregular Channel
Manning's Formula
Discharge
0 .008000 ft/ft
Minimum Maximum
Water Surface Elevation 263.00 271.00
Ratin!1 Table
Water Surface
Elevation Wtd . Mannings Discharge
(ft) Coefficient (cfs)
263.00 0.023 0 .00
263 .20 0.015 1 .71
263.40 0.016 4 .66
263.60 0.017 8 .07
263.80 0 .018 11.72
264.00 0.018 15 .52
264.20 0.019 19.01
264.40 0.020 23.37
264.60 0.020 28 .66
264 .80 0.021 34.92
265 .00 0.021 42.21
265.20 0.021 50 .59
265.40 0.022 60.12
265 .60 0.022 70 .86
265.80 0.022 82 .86
266.00 0.022 96 .19
266.20 0.022 110 .91
266 .40 0.022 127.06
266 .60 0.023 144 .70
266 .80 0 .023 163 .89
267.00 0 .023 184.68
267.20 0.023 207.13
267.40 0.023 231.27
267 .60 0.023 257 .18
267.80 0.023 284 .89
268.00 0.023 314.45
04:41 :39 PM Haestad Methods, Inc. 37 Brookside Road
Increment
0 .20 ft
Velocity
(ft/s)
0 .00
2 .85
3 .88
4.48
4 .88
5 .17
5.21
5.31
5 .46
5.63
5 .82
6 .02
6 .23
6.44
6.66
6 .87
7 .09
7 .30
7.52
7 .73
7.94
8 .15
8.36
8 .57
8.78
8.98
Waterbury, CT 06708
FlowMaster v5.12
(203) 755-1666 Page 1of2
Rating Table
02/16199
04:41 :39 PM
Water Surface
Elevation
(ft)
268 .20
268.40
268.60
268.80
269 .00
269.20
269.40
269.60
269 .80
270.00
270 .20
270 .40
270 .60
270.80
271 .00
Table
Rating Table for Irregular Channel
Wtd. Mannings Discharge Velocity
Coefficient (cfs) (ft/s)
0.023 345.91 9 .19
0 .023 379 .33 9 .39
0.023 414.75 9 .59
0.023 452 .21 9 .79
0.023 491 .77 9 .99
0.024 533.46 10.18
0 .024 577 .34 10.37
0.024 623.45 10.57
0.024 671.83 10.76
0.024 722.53 10 .95
0.024 775 .60 11.14
0.024 831.07 11 .32
0.024 888.98 11.51
0.024 949 .39 11.69
0.024 1,012.33 11.87
Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5 .12
Page 2 of 2
Job File: H:\FRED\LAST3REv.ppk
Rain Dir: J:\HAESTAD\PPK6\UTIL\
==========================
JOB TITLE
==========================
ASHFORD SQUARE RESUBDIVISION PROJECT
MORGAN RECTOR SURVEY, A-46
COLLEGE STATION, BRAZOS COUNTY, TEXAS
DRAINAGE & DETENTION
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50 Date: 02-17-1999
Table of Contents
Table of Contents
******************** NETWORK SUMMARIES *********************
CARRABBA POST 2 A •••• 2
Executive S\.mllary (Nodes) .......... 1.01
CARRABBA POST 2 A •••• 5
Executive S\.mllary (Nodes) ·········· 1.02
CARRABBA POST 2 A ••• 10
Executive S\.mllary (Nodes) ·········· 1.03
CARRABBA POST 2 A ••• 25
Executive S\.mllary (Nodes) .......... 1.04
CARRABBA POST 2 A ••• SO
Executive S\.mllary (Nodes) .......... 1.05
CARRABBA POST 2 A .• 100
Executive S\.mllary (Nodes) .......... 1.06
Network Cales Sequence .••••••...••• 1.07
********************** CN CALCULATIONS *********************
CARRABBA-TR-PST Runoff CN-Area .••••.••••••••••••••. 2.01
SB-2-EX-CON ••••• Runoff CN-Area · •••••••••.••••••••••• 2.02
SB-I POST ••••••• Runoff CN-Area •••••••••••••••.••••. 2.03
*********************** POND VOLUMES ***********************
LASTREV ••••••••• Vol: Planimeter .••••••••••••.•••••• 3.01
******************** OUTLET STRUCTURES *********************
REVISED CHANNEL2 outlet Input Data •••.•••••.••••..•• 4.01
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50 Date: 02·17-1999
Table of Contents ii
Table of Contents (continued)
C~site Rating Curve ••••••••••••• 4.04
*********************** POND RCXJTING ***********************
P COMB •••••••••• Pond E-V-Q Table 5.01
P COMB
P COMB
P COMB
P COMB
P COMB
P COMB
CXJT A •••• 2
Pond Routing Sl.llll\ary ••••••••••••••• 5.04
Detention Time 5.05
CXJT A •••• 5
Pond Routing Sl.llll\ary ••••••••••••••• 5.06
Detention Time
CXJT A ••• 10
Pond Routing Sl.llll\ary
Detention Time
CXJT A ••• 25
5.07
5.08
5.09
Pond Routing SLnmary ••••••••••••••• 5.10
Detention Time
CXJT A ••• 50
Pond Routing Sl.llll\ary
Detention Time
CXJT A •• 100
5.11
5.12
5.13
Pond Routing Sl.llll\ary ••••••••••••••• 5.14
Detention Time ••••••••••••••••••••• 5.15
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50 Date: 02-17-1999
Type •••• Executive SlAllll8ry (Nodes)
Name •••. CARRABBA POST 2
File •••• H:\FRED\LAST3REv.ppk
Storm ••• TypeII 24hr Tag: A •••• 2
NETWORK SUMMARY --NODES
Page 1.01
Event: 2 yr
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID = BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = A .••. 2
Description: 2 YR -24 HR STORM
Data Type, File, ID =Synthetic Storm SCSTYPES.RNF TypeII 24hr
Storm Frequency = 2 yr
Total Rainfall Depth= 4.4210 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max WSEL
Node ID Type ac-ft Trun. hrs cfs ft
-----------------------------------------------------
CARRABBA POST AREA 3.695 11.9750 58.91
P COMB IN POND 37.083 12.0750 332.17
P COMB OUT POND 37.083 12.1500 316.56 268.01
Outfall POINT OF EVAL. JCT 44.015 12.1500 316.56
SB-1 POST AREA 5.010 11. 9750 n.94
SUB-2 EX-CON AREA 28.3n 12.1750 268.64
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C0111JUte Time: 12:06:50 Date: 02-17-1999
Type .••• Executive siirmary (Nodes)
Name •••• CARRABBA POST 2
File •••• H:\FRED\LAST3REv.ppk
Storm ••• TypeII 24hr Tag: A •••• 5
NETWORK SUMMARY --NODES
Page 1.02
Event: 5 yr
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID = BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = A •••• 5
Description: 5 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF TypeII 24hr
Storm Frequency = 5 yr
Total Rainfall Depth= 6.0210 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max IJSEL
Node ID Type ac-ft Trun. hrs cfs ft
-----------------------------------------------------
CARRABBA POST AREA 5.457 11.9750 85.33
P COMB IN POND 54.922 12.0750 486.03
P COMB OUT POND 54.922 12.1500 468. 11 268.88
Outfall POINT OF EVAL. JCT 61.356 12.1500 468.11
SB-1 POST AREA 7.234 11.9750 110.21
SUB-2 EX-CON AREA 42.230 12.1750 395.25
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50 Date: 02-17-1999
Type •••• Executive S~ry (Nodes)
Name •••• CARRABBA POST 2
File •••• H:\FRED\LAST3REv.ppk
Storm ••• TypeII 24hr Tag: A •.• 1D
NETWORK SUMMARY --NODES
Page 1.03
Event: 10 yr
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID = BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = A ••. 10
Description: 10 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 10 yr
Total Rainfall Depth= 7.4390 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max WSEL
Node ID Type ac-ft Trun. hrs cfs ft
-------------------------------------------------·---
CARRABBA POST AREA 7.042 11.9750 108.55
P COMB IN POND 70.988 12.0750 621.84
P COMB OUT POND 70.988 12.1250 602.43 26.9.51
Outfall POINT OF EVAL. JCT 76.548 12.1250 602.43
SB-1 POST AREA 9.222 11. 9750 138.55
SUB-2 EX-CON AREA 54.n4 12. 1750 506.98
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Coq:iute Time: 12:06:50 Date: 02·17-1999
Type .••• Executive Sumiary (Nodes)
Name •••• CARRABBA POST 2
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Typell 24hr Tag: A •.• 25
NETWORK SUMMARY --NODES
Page 1.04
Event: 25 yr
CTrun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID = BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = A .•• 25
Description: 25 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Typell 24hr
Storm Frequency = 25 yr
Total Rainfall Depth= 8.8360 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max IJSEL
Node ID Type ac-ft Trun. hrs cfs ft
-----------------------------------------------------
CARRABBA POST AREA 8.616 11.9750 131.27
P COMB IN POND 86.947 12.0750 754.91
P COMB OOT POND 86.947 12. 1250 734.40 270.04
Outfall POINT OF EVAL. JCT 91.503 12.1250 734.40
SB -1 POST AREA 11. 188 11.9750 166.28
SUB-2 EX-CON AREA 67.143 12.1750 616.42
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24 -97 :053 C~te Time: 12:06:50 Date: 02-17-1999
Type •.•• Executive Surmary (Nodes)
Name •••• CARRABBA POST 2
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Type!! 24hr Tag: A ••• SO
NETIJORK SUMMARY --NODES
Page 1.0S
Event: SO yr
(Trun.= HYG Trl.Wlcation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File,ID = BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name =A •.• SO
Description: SO YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = SO yr
Total Rainfall Depth= 10.3880 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max WSEL
Node ID Type ac-ft Trun. hrs cf s ft
-------------------------------------------------·---
CARRABBA POST AREA 10.373 11. 9750 1S6.36
P COMB IN POND 104.nO 12.0750 901.96
P COMB OUT POND 104.nO 12.12SO 880.2S 270.S7
Outfall POINT OF EVAL. JCT 108.323 12.12SO 880.2S
SB-1 POST AREA 13.378 11.9750 196.9S
SUB-2 EX-CON AREA 81.019 12.1750 737.29
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :OS3 COIJllllte Time: 12:06:SO Date: 02-17-1999
Type •••• Executive Slillll8ry (Nodes)
Name •••• CARRABBA POST 2
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Type!! 24hr Tag: A •• 100
NETWORK SUMMARY ·-NODES
Page 1.06
Event: 100 yr
CTrun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File,ID = BRAZOS.RNQ SCS·24HR ALL
Storm Tag Name = A •• 100
Description: 100 YR -24 HR STORM
Data Type, File, ID =Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 100 yr
Total Rainfall Depth= 11.3530 in
Duration Multipl i er= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max IJSEL
Node ID Type ac-ft Trun. hrs cfs ft
------------------·-----------------------··--·-------
CARRABBA POST AREA 11.468 11. 9750 171.90
P COMB IN POND 115.886 12.0750 993.02
P COMB OUT POND 115.886 12.1250 970.47 270.87
Outfall POINT OF EVAL. JCT 118.863 12.1250 970.47
SB-1 POST AREA 14 .742 11. 9750 215.96
SUB -2 EX -CON AREA 89.676 12. 1750 812.12
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24 -97 :053 Coq:iute Time: 12:06:50 Date: 02 -17 -1999
Type •••• Network Cales Sequence
Name •••• CARRABBA POST 2
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Type!! 24hr Tag: A •• 100
NETWORK RUNOFF NOOE SEQUENCE
Page 1.07
Event: 100 yr
===========================================================================
Runoff Data Apply to Node Receiving Unk
===========================================================================
SCS UH SB·! POST
SCS UH SB-2 EX-CON
SCS UH CARRABBA -PST
Subarea SB-1 POST
Subarea SUB-2 EX-CON
Subarea CARRABBA POST
S/N: HOMOL0863131 KLING ENGINEERING
Add Hyd SB-1 POST
Add Hyd SUB-2 EX-CON
Add Hyd CARRABBA POST
Pond Pack Ver: 6-24 -97 :053 C~te Time: 12:06:50 Date: 02-17-1999
Type •••• Network Cales Sequence
Name •••• CARRABBA POST 2
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Type!! 24hr Tag: A •• 100
Page 1.08
Event: 100 yr
NET~ORK ROUTING SEQUENCE
===========================================================================
Link Operation UPstream Node DNstream Node
===========================================================================
Add Hyd CARRABBA POST
Add Hyd SB-2 EX CON PST
Add Hyd SB-1 POST
Subarea CARRABBA POST
Subarea SUB-2 EX-CON
Subarea SB-1 POST
POND ROUTE TOTAL OUTFL~ •••
Total Pond Outflow Pond P COMB
SET POND ROUTING LINK TO TOTAL POND OUTFL~ •••
Outlet DET POND Outflow P COMB
S/N: HOMOL0863131 KLING ENGINEERING
Pond
Pond
Pond
P COMB
P COMB
P COMB
IN
IN
IN
IN Outflow P COMB
OUT Jct POINT OF EVAL.
Pond Pack Ver: 6-24-97 :053 COfll>Ute Time: 12:06:50 Date: 02-17-1999
Type •••• Runoff CN·Area
Name •••• CARRABBA·TR·PST
File •••• H:\FRED\LAST3REv.ppk
Title ••• CARRABBA-GLOCKSEEN TRACT POST DEVELOPED CONDITIONS
RUNOFF CURVE NUMBER DATA
Page 2.01
.......................................................................... ..........................................................................
CARRABBA·GLOCKSEEN TRACT POST DEVEL OP ED CONDITIONS
lrrpervious
Area Adjustme nt Adjusted
Soil/Surface Description CN acres xc XI.JC CN
---------------------------------------------------
APARTMENT DEVELOPMENT 92 10. 180 92.00
RESERVE TRACT UNDEVELOPED 80 3.010 80.00
NATURAL CONDITIONS 80 .580 80.00
COMPOSITE AREA & WEIGHTED CN ---> 13.770 88.87 (89) ........................................................................... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50 Date: 02-17-1999
Type •••• Runoff CN·Area
Name •••• SB·2·EX·CON
File •••• H:\FRED\LAST3REv.ppk
Title ••• TOTAL SUB-BASIN 2 DRAINAGE AREA. EXISTING CONDITIONS
RUNOFF CURVE NUMBER DATA
Page 2.02
.......................................................................... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
TOTAL SUB-BASIN 2 DRAINAGE AREA. EXISTING CONDITIONS
Soil/Surface Description
HSG·D,FIELD GRASSES,BRUSH
HSG·D,DEVELOPED AREAS
HSG·D,DEVELOPED AREAS
COMPOSITE AREA & ~EIGHTED CN ···>
CN
80
89
89
Area
acres
---------
17.878
n.068
19.110
109.056
lq>ervious
Adjustment
xc xuc
----------
Adjusted
CN
80.00
89.00
89.00
87.52 (88) ........................................................................... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50 Date: 02 -17-1999
Type •••• Runoff CN-Area
Name •••• SB-I POST
File •••• H:\FRED\LAST3REv.ppk
Title ••• SB-I POST-DEVELOPED
RUNOFF CURVE NUMBER DATA
Page 2.03
.......................................................................... ··········································································
SB-I POST-DEVELOPED
l~rvious
Area Adjustment Adjusted
Soil/Surface Description CN acres xc xuc CN
--------------------------------------------.. ------
IMPERVIOUS 98 10.818 98.00
GRASSED 80 5.485 80.00
LOT 1R BLOCK D A-P TRACT 94 .752 94.00
COMPOSITE AREA & ~EIGHTED CN ---> 17.055 92.03 (92) ........................................................................... ···········································································
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C01f4XJte Time: 12:06:50 Date: 02-17-1999
Type •••• Vol: Plan i meter
Name •••• LASTREV
File •••• H:\FRED\LAST3REv.ppk
Title ••• 264
POND VOLUME CALCULATIONS
Planimeter scale: 1.00 ft/in
Elevation
(ft)
Planimeter
(sq. in)
Area
(acres)
A1+A2+sqrCA1*A2) Volune
(acres) (ac-ft)
263.00 .000 .0000 .0000 .000
264.00 91 .400 .0021 .0021 .001
264.50 11573.740 .2657 .2914 .049
265.00 19651.920 .4511 1.0631 .1n
266.00 26179.480 .6010 1.5729 .524
267.00 30727.240 .7054 1.9575 .653
268.00 35761.090 .8210 2.2874 .762
269.00 41750.781 .9585 2.6665 .889
270 .00 47649.031 1.0939 3.0763 1.025
270.80 52255.020 1.1996 3.4390 .917
271.00 54894.520 1.2602 3.6893 .246
272 .00 60530.949 1.3896 3.9731 1.324
POND VOLUME EQUATIONS
Page 3.01
Volune Sl.Jll
(ac -ft)
.000
.001
.049
.226
.751
1.403
2.166
3.055
4.080
4.997
5.243
6.567
* Incremental volune con.,uted by the Conic Method for Reservoir Volunes.
Volune = C1/3) * CEL2-EL1) * CArea1 + Area2 + sq.rt.(Area1*Area2))
where: EL1, EL2 = Lower and upper elevations of the i ncrement
Area1,Area2 =Areas con.,uted for EL1, EL2, respectively
Volune = Incremental ·volune between EL1 and EL2
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24 -97 :053 Con.,ute Time: 12:06:50 Date: 02 -17-1999
Type •••• Outlet Input Data
Name •••• REVISED CHANNEL2
File •••• H:\FRED\LAST3REv.ppk
REQUESTED POND WS ELEVATIONS:
Hin. Elev.=
Increment =
Max. Elev.=
263.00 ft
.20 ft
2n.oo ft
**********************************************
OUTLET CONNECTIVITY
**********************************************
---> Forward Flow Only (Upstream to DnStream)
<---Reverse Flow Only CDnStream to Upstream)
<---> Forward and Reverse Both Allowed
Structure
User Defined Table
TW SETUP, OS Chal'Vlel
No.
--->
Outfall E1 I ft
TW .000
S/N: HOHOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C01TpUte Time: 12:06:50
Page 4.01
E2, ft
272.000
Date: 02-17-1999
Type •••• Outlet Input Data Name •••• REVISED CHANNEL2 File •••• H:\FRED\LAST3REv.ppk OUTLET STRUCTURE INPUT DATA Structure ID Structure Type = 1 = User Defined Table ELEV·FLOW RATING TABLE Elev, ft Flow, cfs ------------------263.DO .00 263.20 1. 71 263.40 4.66 263.60 8.07 263.80 1i.n 264.00 15.52 264.20 19.01 264.40 23.37 264.60 28.66 264.80 34.92 265.00 42.21 265.20 50.59 265.40 60.12 265.60 70.86 265.80 82.86 266.00 96.19 266.20 110.91 266.40 127.06 266.60 144.70 266.80 163.89 267.00 184.68 267.20 207.13 267.40 231.27 267.60 257.18 267.80 284.89 268.00 314.45 268.20 345.91 268.40 379.33 268.60 414.75 268.80 452.21 269.00 491. 77 269.20 533.46 269.40 577.34 269.60 623.45 269.80 671.83 270.00 n2.53 270.20 775.60 270.40 831.07 270.60 888.98 S/N: HOMOL0863131 KLING ENGINEERING Pond Pack Ver: 6-24-97 :053 COll1'lJte Time: 12:06:50 Page 4.02 Date: 02-17-1999
Type •••• Outlet Input Data
Name •••• REVISED CHANNEL2
File •••• H:\FRED\LAST3REv.ppk
Elev, ft Flow, cfs
------------------
270.80 949.39
271.00 1012.33
271.20 1271.91
271.40 1271. 91
2n.oo 1271.91
= Tl.I Structure ID
Structure Type = Tl.I SETUP, OS Channel
FREE OUTFALL CONDITIONS SPECIFIED
CONVERGENCE TOLERANCES •••
Maxilll.lll Iterations= 30
Min. Tl.I tolerance = .01 ft
Max. Tl.I tolerance = .01 ft
Min. HI.I tolerance = .01 ft
Max. HI.I tolerance = .01 ft
Min. Q tolerance = .10 cfs
Max. Q tolerance = .10 cfs
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50
Page 4.03
Date: 02-17-1999
Type •••• C~site Rating Curve
Name •••• REVISED CHANNEL2
File •••• H:\FRED\LAST3REv.ppk
***** COMPOSITE OUTFLOW SUMMARY ****
llS Elev, Total Q Notes
------------------------Converge -------------------------
Elev. Q Tll Elev Error
ft cf s ft +/-ft Contributing Structures
------------------------------------------
263.00 .oo Free Outfall
263.20 1. 71 Free Outfall
263.40 4.66 Free Outfall
263.60 8.07 Free Outfall
263.80 1i.n Free Outfall
264.00 15.52 Free Outfall
264.20 19.01 Free Outfall
264.40 23.37 Free Outfall
264.60 28.66 Free Outfall
264.80 34.92 Free Outfall
265.00 42.21 Free Outfall
265.20 50.59 Free Outfall
265.40 60.12 Free Outfall
265.60 70.86 Free Outfa l l
265.80 82.86 Free Outfall
266.00 96.19 Free Outfall
266.20 110.91 Free Outfall
266.40 127.06 Free Outfall
266.60 144.70 Free Outfall
266.80 163.89 Free Outfall
267.00 184.68 Free Outfall
267.20 207.13 Free Outfall
267.40 231.27 Free Outfall
267.60 257 .18 Free Outfall
267.80 284.89 Free Outfall
268.00 314.45 Free Outfall
268.20 345.91 Free Outfall
268.40 379.33 Free Outfall
268.60 414.75 Free Outfall
268.80 452.21 Free Outfall
269.00 491.n Free outfall
269.20 533.46 Free Outfall
269.40 5n.34 Free outfall
269.60 623.45 Free Outfall
269.80 671.83 Free Outfall
270.00 n2.53 Free Outfall
270.20 m.60 Free Outfall
270.40 831.07 Free Outfall
270.60 888.98 Free Outfall
270.80 949.39 Free Outfal l
S/N: HOMOL0863131 KLING ENGINEERING
Page 4.04
Pond Pack Ver: 6-24-97 :053 C0111XJte Time: 12:06:50 Date: 02-17-1999
Type •••• C~site Rating Curve
Name •.•• REVISED CHANNEL2
File •••• H:\FRED\LAST3REv.ppk
***** COMPOSITE OUTFLOW SUMMARY ****
WS Elev, Total Q
----------------
Elev. Q
ft cf s
--------
271.00 1012.33
271.20 1271.91
271.40 1271.91
271.60 1271.91
271.80 1271.91
2n.oo 1271.91
Notes
--------Converge -------------------------
TW Elev Error
ft +/-ft Contributing Structures
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
S/N: HOMOL0863131 KLING ENGINEERING
Page 4.05
Pond Pack Ver: 6-24 -97 :053 Con.,ute Time: 12:06:50 Date: 02-17 -1999
Type .••• Pond E-V-Q Table
Name •••• P COMB
File •••• H:\FRED\LAST3REv.ppk
LEVEL PCXlL ROUTING DATA
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV.HYG -P COMB
Outflow HYG file= LASTREV.HYG -P COMB
Pond Node Data = P COMB
Pond Volume Data = lastrev
Pond Outlet Data = REVISED CHANNEL2
No Infiltration
INITIAL CONDITIONS
Start i ng WS Elev = 263.00 ft
Start i ng Volume = .000 ac-ft
Start i ng Outflow = .00 cfs
Starting lnfiltr. = .00 cfs
Starting Total Qout= .00 cfs
Time Increment = .0250 hrs
Elevation Outflow Storage Area
ft cfs ac-ft acres
Page 5.01
IN A •.•• 2
OUT A •••• 2
lnfil t.
cfs
Q Total
cfs
2S/t + 0
cf s
------------------------------------------------------------------------------
263.00 .00 .000 .0000 .00 .00 .OD
263.20 1.71 .000 .0001 .DO 1. 71 1.72
263.40 4.66 .000 .0003 .OD 4.66 4.70
263.60 8 .07 .ODO .0008 .DO 8.07 8.22
263.80 11.72 .ODO .0013 .00 11.72 12.07
264.00 15.52 .001 .0021 .OD 15.52 16.20
264.20 19.01 .005 .0546 .DO 19.01 24.04
264.40 23.37 .027 .1m .00 23.37 49.74
264.60 28.66 .077 .2989 .00 28.66 103.66
264.80 34.92 .144 .3711 .00 34.92 174.65
265.00 42.21 .226 .4511 .DO 42.21 261.41
265.20 50.59 .319 .4794 .OD 50.59 359.86
265.40 60.12 .418 .5085 .OD 60.12 464.99
265.60 70.86 .523 .5385 .DO 70.86 577.08
265.80 82.86 .634 .5693 .OD 82.86 696.29
266.00 96.19 .751 .6010 .00 96.19 822.90
266.20 110.91 .873 .6212 .DO 110.91 955.93
266.40 127.06 .999 .6418 .DO 127.06 1094.32
266.60 144.70 1.130 .6626 .OD 144.70 1238.22
266.80 163.89 1.264 .6839 .OD 163.89 1387 .74
267.00 184.68 1.403 .7054 .OD 184.68 1543 .01
267.20 207.13 1.547 .7278 .00 207.13 1704.20
267.40 231.27 1.694 .7506 .OD 231.27 1871.42
S/N: HOMOL086313 1 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50 Date: 02 -17-1999
Type •••• Pond E-V -Q Table
Name •••• P COMB
File •••• H:\FRED\LAST3REv.ppk
LEVEL POOL ROUTING DATA
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV.HYG - P COMB
Outflow HYG file= LASTREV.HYG - P COMB
Pond Node Data = P COMB
Pond VollJlle Data = lastrev
Pond outlet Data = REVISED CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting WS Elev = 263.00 ft
Starting VollJlle =
Starting Outflow =
Starting lnfiltr. =
Starting Total Qout=
Time Increment =
Elevation
ft
outflow
cfs
.000 ac-ft
.00 cfs
.00 cfs
.00 cfs
.0250 hrs
Storage
ac-ft
Area
acres
Page 5.02
IN A •••. 2
OUT A •... 2
lnfil t.
cfs
Q Total
cfs
2S/t. + 0
cfs
------------------------------------------------------------------------------
267.60 257.18 1.847 .m7 .00 257 .18 2044.89
267.80 284.89 2.004 .7971 .00 284.89 2224.63
268.00 314.45 2.166 .8210 .00 314.45 2410.83
268.20 345.91 2.333 .8476 .00 345.91 2603.81
268.40 379.33 2.505 .8747 .00 379.33 2803.93
268.60 414.75 2.682 .9022 .00 414.75 3011.35
268.80 452.21 2.866 .9301 .00 452.21 3226.16
269.00 491.77 3.055 .9585 .00 491.77 3448.54
269.20 533.46 3.249 .9848 .00 533.46 3678.34
269.40 577.34 3.448 1.0116 .00 577.34 3915.45
269.60 623.45 3.653 1.0386 .00 623.45 4160.02
269.80 671.83 3.864 1.0661 .00 671.83 4412.12
270.00 722.53 4.080 1.0939 .00 n2.53 4671.91
270.20 775.60 4.301 1.1199 .00 775.60 4939.27
270.40 831.07 4.528 1.1461 .00 831.07 5214.06
270.60 888.98 4.760 1.1n7 .00 888.98 5496.45
270.80 949.39 4.997 1.1996 .00 949.39 5786.47
271.00 1012.33 5.243 1.2602 .00 1012.33 6087.51
271.20 1271.91 5.498 1.2856 .00 1271.91 6593.54
271.40 1271.91 5.757 1.3112 .00 1271.91 6844.88
271.60 1271.91 6.022 1.3371 .00 1271.91 7101.24
271.80 1271.91 6.292 1.3632 .00 1271.91 7362.60
2n.oo 1271.91 6.567 1.3896 .00 1271.91 7629.09
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 COll'pJte Time: 12:06:50 Date: 02-17-1999
Type •••• Pond E·V·Q Table
Name •••• P COMB
File •••• H:\FRED\LAST3REv.ppk
LEVEL P<XlL ROUTING DATA
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV.HYG · P COMB
Outflow HYG file= LASTREV.HYG · P COMB
Pond Node Data = P COMB
Pond Volume Data = lastrev
Pond Outlet Data = REVISED CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting WS Elev = 263.00 ft
Starting Volume = .000 ac·ft
Starting Outflow = .00 cfs
Starting Infiltr. = .00 cfs
Starting Total Qout= .00 cfs
Time Increment = .0250 hrs
Elevation Outflow Storage Area
ft cfs ac·ft acres
S/N: HOMOL0863131 KLING ENGINEERING
Page 5.03
IN A •••• 2
OUT A ••.. 2
Infil t.
cf s
Q Total
cf s
2S/t + 0
cfs
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50 Date: 02-17-1999
Type •••• Pond Routing Sunnary ·
Name •••• P COMB OUT Tag: A •••• 2
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Typell 24hr Tag: A •••• 2
LEVEL POOL ROUTING SUMMARY
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV.HYG - P COMB
Outflow HYG file= LASTREV.HYG - P COMB
Pond Node Data = P COMB
Pond Volume Data = lastrev
Pond outlet Data = REVISED CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting \IS Elev = 263.00 ft
Starting Volume = .000 ac-ft
Starting Outflow = .00 cfs
Starting lnfiltr. = .00 cfs
Starting Total Qout= .00 cfs
Time Increment = .0250 hrs
INFLOW/OUTFLOW HYDROGRAPH SUMMARY
IN A ••.• 2
OUT A •••• 2
=====================================================
Peak Inflow
Peak Outflow
Peak Elevation
Peak Storage =
= 332.17 cfs
= 316.56 cfs
= 268.01 ft
2.177 ac-ft
at 12.0750 hrs
at 12. 1500 hrs
=====================================================
MASS BALANCE (ac-ft)
+ Initial Vol =
+ HYG Vol IN =
-Infiltration=
-HYG Vol OUT =
-Retained Vol =
.000
37.083
.000
37.083
.000
Page 5.04
Event: 2 yr
Unrouted Vol = .000 ac-ft (.OOOX of Outflow Volume)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50 Date: 02-17-1999
Type •••• Detention Time
Name .••• P COMB ClJT Tag: A •••• 2
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Type!! 24hr Tag: A •••• 2
DETENTION TIMES SUMMARY
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV.HYG -P COMB
Outflow HYG file= LASTREV.HYG - P COMB
Pond Node Data = P COMB
Pond Voliine Data = lastrev
Pond Outlet Data = REVISED CHANNEL2
No Infiltration
APPROXIMATE DETENTION TIME
Tp, Outflow+ lnfilt. = 12.1500 hrs
Tp, Total Inf low = 12.0750 hrs
Peak to Peak = .0750 hrs
Qout+lnfilt. Centroid = 13.6112 hrs
Inf low Centroid = 13.5525 hrs
Centroid to Centroid .0587 hrs
.0589 hrs
.0821 hrs
IN A ••.• 2
ClJT A •••• 2
Page 5.05
Event: 2 yr
Weighted Avg. Plug Time =
Max.Plug Vol. Plug Time=
Max.Inflow Plug Voliine = .685 ac-ft (From 12.0750 to 12.1000 hrs)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50 Date: 02-17-1999
Type •••• Pond Routing Sl.lllll8ry
Name •••• p COMB OUT Tag: A •••• 5
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Typell 24hr Tag: A •••• 5
LEVEL POOL ROUTING SUMMARY
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV.HYG - P COMB
OUtflow HYG file= LASTREV.HYG - P COMB
Pond Node Data = P COMB
Pond Volune Data = lastrev
Pond Outlet Data = REVISED CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting WS Elev = 263.00 ft
Starting Volune = .000 ac-ft
Starting Outflow = .00 cfs
Starting Infiltr. = .00 cfs
Starting Total Qout= .00 cfs
Time Increment .0250 hrs
INFLO\l/OUTFLOlol HYDROGRAPH SUMMARY
IN A •••. 5
OUT A ..•. 5
=====================================================
Peak Inflow
Peak outflow
Peak Elevation
Peak Storage =
= 486.03 cfs
= 468.11 cfs
= 268.88 ft
2.941 ac-ft
at 12.0750 hrs
at 12.1500 hrs
=====================================================
MASS BALANCE (ac-ft)
+ Initial Vol =
+ HYG Vol IN =
-Infiltration=
-HYG Vol OUT =
-Retained Vol =
.000
54.922
.000
54.922
.000
Page 5.06
Event: 5 yr
Unrouted Vol = .000 ac-ft C.OOOX of Outflow Volune)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50 Date: 02-17-1999
Type •••• Detention Time
Name •••• P COMB OUT Tag: A ..•• 5
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Typell 24hr Tag: A ••.• 5
DETENTION TIMES SUMMARY
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV.HYG - P COMB
Outflow HYG file= LASTREV.HYG - P COMB
Pond Node Data = P COMB
Pond Voll.Ille Data = lastrev
Pond Outlet Data = REVISED CHANNEL2
No Infiltration
APPROXIMATE DETENTION TIME
Tp, outflow+ Infilt.
Tp, Total Inf low
Peak to Peak
= 12.1500 hrs
12.0750 hrs
= .0750 hrs
Qout+Infilt. Centroid 13.4326 hrs
Inflow Centroid = 13.3723 hrs
Centroid to Centroid = .0603 hrs
.0605 hrs
.0755 hrs
IN A •••• 5
OUT A •••• 5
Page 5.07
Event: 5 yr
Weighted Avg. Plug Time =
Max.Plug Vol. Plug Time=
Max.Inflow Plug Vol1.111e = 1.003 ac-ft (From 12.0750 to 12.1000 hrs)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50 Date: 02-17-1999
Type •••• Pond Routing Sl.lllll8ry
Name •••• p COMB OUT Tag: A ••• 10
File •••• H:\FREO\LAST3REv.ppk
Storm ••• Typell 24hr Tag: A ••• 10
LEVEL POOL ROUTING SUMMARY
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV.HYG - P COMB
Outflow HYG file= LASTREV.HYG - P COMB
Pond Node Data = P COMB
Pond Volune Data = lastrev
Pond Outlet Data = REVISED CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting WS Elev = 263.00 ft
Starting Volune = .000 ac-ft
Starting Outflow = .00 cfs
Starting Infiltr . = .00 cfs
Starting Total Qout= .00 cfs
Time Increment = .0250 hrs
INFLOW/OUTFLOW HYDROGRAPH SUMMARY
IN A ••• 10
OUT A .•• 10
=====================================================
Peak Inflow
Peak outflow
Peak Elevation
Peak Storage =
= 621.84 cfs
602.43 cfs
= 269.51 ft
3.559 ac-ft
at 12.0750 hrs
at 12.1250 hrs
=====================================================
MASS BALANCE (ac-ft)
+ Initial Vol =
+ HYG Vol IN =
-Infiltration=
-HYG Vol OUT =
-Retained Vol =
.000
70.988
.000
70.988
.000
Page 5.08
Event: 10 yr
Unrouted Vol = .000 ac-ft (.OOOX of Outflow Volune)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50 Date: 02 -17 -1999
Type •••• Detention Time
Name •••• P COMB OUT Tag: A ••• 10
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Type!! 24hr Tag: A ••• 10
DETENTION TIMES SUMMARY
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV.HYG -p COMB
Outflow HYG file= LASTREV.HYG -P COMB
Pond Node Data = p COMB
Pond Volune Data = lastrev
Pond OUtlet Data = REVISED CHANNEL2
No Infiltration
APPROXIMATE DETENTION TIME
Tp, outflow+ lnfilt. = 12.1250 hrs
Tp, Total Inflow = 12.0750 hrs
Peak to Peak = .0500 hrs
Qout+lnfilt. Centroid = 13.3192 hrs
Inf low Centroid = 13.2576 hrs
Centroid to Centroid .0616 hrs
.0617 hrs
.0712 hrs
IN A ••• 10
OUT A ••• 10
Page 5.09
Event: 10 yr
Meighted Avg. Plug Time =
Max.Plug Vol. Plug Time=
Max.Inflow Plug Volune = 1.283 ac-ft (From 12.0750 to 12.1000 hrs)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 COfll>Ute Time: 12:06:50 Date: 02-17-1999
Type •••• Pond Routing S1.1111111ry
Name •••• P COMB OUT Tag: A ••• 25
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Typell 24hr Tag: A ••• 25
LEVEL POOL ROUTING SUMMARY
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV .HYG - P COMB
Outflow HYG file= LASTREV.HYG -P COMB
Pond Node Data = P COMB
Pond Volune Data = lastrev
Pond Outlet Data = REVISED CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting \IS Elev = 263.00 ft
Starting Volune = .000 ac-ft
Starting Outflow = .00 cfs
Starting lnfiltr. = .00 cfs
Starting Total Qout= .00 cfs
Time Increment = .0250 hrs
INFLOW/OUTFLOW HYDROGRAPH SUMMARY
IN A ••• 25
OUT A ••• 25
=====================================================
Peak Inflow
Peak Outf low
Peak Elevation
Peak Storage =
= 754.91 cfs
= 734.40 cfs
= 270.04 ft
4.129 ac-ft
at 12.0750 hrs
at 12. 1250 hrs
=====================================================
MASS BALANCE (ac-ft)
+ Initial Vol =
+ HYG Vol IN =
-Infiltration =
-HYG Vol OUT =
-Retained Vol =
.000
86.947
.000
86.947
.000
Page 5.10
Event: 25 yr
Unrouted Vol = .000 ac-ft (.OOOX of Outflow Volune)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 CC11J'4X.1te Time: 12:06:50 Date: 02-17-1999
Type •••• Detention Time
Name •••• P COMB OUT Tag: A ••• 25
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Type!! 24hr Tag: A ••• 25
DETENTION TIMES SUMMARY
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV.HYG -P COMB
OUtflow HYG file= LASTREV.HYG -P COMB
Pond Node Data = p COMB
Pond Volune Data = lastrev
Pond outlet Data = REVISED CHANNEL2
No Infiltration
APPROXIMATE DETENTION TIME
Tp, Outflow+ Infilt. = 12.1250 hrs
Tp, Total Inf low = 12.0750 hrs
Peak to Peak = .0500 hrs
Qout+Infilt. Centroid = 13.2325 hrs
Inflow Centroid = 13.1695 hrs
Centroid to Centroid .0629 hrs
.0630 hrs
.0679 hrs
IN A ••. 25
OUT A •.• 25
Page 5.11
Event: 25 yr
Weighted Avg. Plug Time =
Max.Plug Vol. Plug Time=
Max.Inflow Plug Volune = 1.558 ac-ft (From 12.0750 to 12.1000 hrs)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C011'4JUte Time: 12:06:50 Date: 02-17-1999
Type •••• Pond Routing S~ry
Name .••• p COMB OUT Tag: A ••• so
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Typell 24hr Tag: A ••• SO
LEVEL POOL ROUTING SUMMARY
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV.HYG · P COMB
OUtflow HYG file= LASTREV.HYG · P COMB
Pond Node Data = P COMB
Pond Volune Data = lastrev
Pond OUtlet Data = REVISED CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting WS Elev = 263.00 ft
Starting Volune = .000 ac·ft
Starting Outflow = .00 cfs
Starting Infiltr. = .00 cfs
Starting Total Qout= .00 cfs
Ti me Increment = .02SO hrs
INFLOW/OUTFLOW HYDROGRAPH SUMMARY
IN A ••• SO
OUT A ••• SO
=====================================================
Peak Inf low
Peak outflow
Peak Elevation
Peak Storage =
= 901.96 cfs
= 880.2S cfs
270.S7 ft
4.n4 ac-ft
at 12.0750 hrs
at 12.12SO hrs
=====================================================
MASS BALANCE (ac-ft)
+ Initial Vol =
+ HYG Vol IN =
-Infiltration=
-HYG Vol OUT =
· Retained Vol =
.000
104.770
.000
104.770
.000
Page S.12
Event: SO yr
Unrouted Vol = .000 ac -ft (.OOOX of Outflow Volume)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :OS3 C~te Time: 12:06:SO Date: 02 -17-1999
Type •••• Detention Time
Name •••• P COMB OUT Tag: A ••• SO
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Typell 24hr Tag: A ••• SO
DETENTION TIMES SUMMARY
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV.HYG - P COMB
Outflow HYG file= LASTREV.HYG - P COMB
Pond Node Data = P COMB
Pond Volume Data = lastrev
Pond Outlet Data = REVISED CHANNEL2
No Infiltration
APPROXIMATE DETENTION TIME
---------------------------------------
Tp, outflow+ lnf i lt.
Tp, Total Inf low
Peak to Peak
Qout+Infilt. Centroid
Inflow Centroid
Centroid to Centroid
=
=
=
=
=
=
12.12SO hrs
12.0750 hrs
.OSOO hrs
13.1SSS hrs
13.0912 hrs
.0643 hrs
.0644 hrs
.0649 hrs
IN A ••• SO
OUT A •.. SO
Page S.13
Event: SO yr
Weighted Avg. Plug Time =
Max.Plug Vol. Plug Time =
Max.Inflow Plug Volume = 1.861 ac-ft (From 12.0750 to 12 .1000 hrs)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24 -97 :OS3 CO!ll>Ute Time: 12:06:SO Date : 02-17-1999
Type •••• Pond Routing S~ry
Name •.•• p COMB OUT Tag: A •• 100
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Typell 24hr Tag: A •• 100
LEVEL POOL ROUTING SUMMARY
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV.HYG - P COMB
Outflow HYG file= LASTREV.HYG - p COMB
Pond Node Data = P COMB
Pond Voll.Ille Data = lastrev
Pond Outlet Data = REVISED CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting ~s Elev = 263.00 ft
Starting Voll.Ille = .000 ac-ft
Starting Outflow = .00 cfs
Starting lnfiltr. = .00 cfs
Starting Total Qout= .00 cfs
Time Increment = .0250 hrs
INFLOW/OUTFLOW HYDROGRAPH SUMMARY
IN A •• 100
OUT A •• 100
=====================================================
Peak Inflow
Peak Outflow
Peak Elevation
Peak Storage =
= 993.02 cfs
= 970.47 cfs
= 270.87 ft
5.078 ac-ft
at 12.0750 hrs
at 12.1250 hrs
=====================================================
MASS BALANCE (ac-ft)
+ Initial Vol =
+ HYG Vol IN =
-Infiltration =
-HYG Vol OUT =
-Retained Vol
.000
115.886
.000
115.886
.000
Page 5.14
Event: 100 yr
Unrouted Vol = -.000 ac-ft (.OOOX of Inflow Voll.Ille)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 COf11XJte Time: 12:06:50 Date: 02-17-1999
Type •••• Detention Time
Name •••• P COMB OUT Tag: A •• 100
File •••• H:\FRED\LAST3REv.ppk
Storm ••• Type!! 24hr Tag: A •• 100
DETENTION TIMES SUMMARY
HYG Dir = H:\FRED\
Inflow HYG file= LASTREV.HYG - p COMB
Outflow HYG file= LASTREV.HYG - P COMB
Pond Node Data = P COMB
Pond Volume Date = lestrev
Pond OUtlet Date = REVISED CHANNEL2
No Infiltration
APPROXIMATE DETENTION TIME
---------------------------------------
Tp, Outflow+ lnfilt.
Tp, Total Inf low
Peek to Peek
Qout+lnfilt. Centroid
Inflow Centroid
Centroid to Centroid
=
=
=
=
=
=
12.1250 hrs
12.0750 hrs
.0500 hrs
13.1151 hrs
13.0501 hrs
.0650 hrs
.0651 hrs
.0633 hrs
IN A •• 100
OUT A •• 100
Page 5.15
Event: 100 yr
Weighted Avg. Plug Time =
Mex.Plug Vol. Plug Time=
Mex.Inflow Plug Volume = 2.049 ec-ft (From 12.0750 to 12.1000 hrs)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Peck Ver: 6-24-97 :053 COflllUte Time: 12:06:50 Date: 02-17-1999
Appendix A
Index of Starting Page Nl.llbers for ID Names
-----c
CARRABBA POST 2 A •••. 2 ••• 1.01,
1.02, 1.03, 1.04, 1.05, 1.06,
1.07
CARRABBA-TR-PST ••• 2.01
-----L -----
LASTREV ••• 3.01
-----p -----
p COMB ••• 5.01, 5.04, 5.05, 5.06,
5.07, 5.08, 5.09, 5.10, 5.11,
5.12, 5.13, 5.14, 5.15
-----R -----
REVISED CHANNEL2 ••• 4.01, 4.04
-----s -----
SB-2-EX-CON ••• 2.02
SB-I POST ••• 2.03
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 12:06:50
A-1
Date: 02-17-1999
4103 Texas Avenue, Suite 212
Bryan , Texas 77802
TO
ATIENTION
WE TRANSMIT:
0 Under Separate Cover
)(.lEnclosed
VIA:
DMail
EI.Messenger
0 Federal Express
0 Express Mai°I
0 Special Courier
0 Picked Up By Your Office
NO.
KLING ENGINEERING AND SURVEYING
Consulting Engineers • Land Surveyors
Tel. (409) 846-6212
·Fax (409) 846-8252
DATE 0/
PROJECT NO.
THE FOLLOWING :
0 Prints
OCopies
DOriginals
OPlat
0 Field Notes
OPlans
~eport
)ld.:Estimate
OCut Sheets
PROJECT NAME
REFERENCE
0 Computer Printout
OFile
OContract
0
DESCRIPTION
FOR:
P.O. Box 4234
Bryan, Texas 77805
OYour Review & Approval
0 Your Review & Comment
0 Your Review & Distribution
0 Your Review, Revision & Return
0 Your Signature & Return
OYour File and/or Use
DAs Requested By :
0 Please Acknowledge Receipt of
Enclosures
0 Please Return Enclosures To Us
0 Copies Of This Letter Of Transmittal
Sent To :
If Enclosures Are Not As Noted ,
Please Notify Us At Once.
Sign~.-J 9 .._,__
ADDENDUM #2 TO THE DRAINAGE REPORT
FOR
Lots 2,3,4,5,6,7, Block "C"
Lots 1,2,3,4,5,6, Block "D"
Ashford Square Subdivision
&
Lots 2 and 3, Block "1"
Dartmouth Addition Subdivision
Morgan Rector Survey, A-46
College Station, Brazos County, Texas
20-January 1999
DEVELOPED BY:
Mr. David Scarrnardo
D .W .S . Inc .
P .O . Box 4508
Bryan, TX 77805
( 409) 779-7209
PREPARED BY:
Kling Engineering & Surveying
4103 Texas Avenue , Suite 212
Bryan, TX 77802
(409) 846-6212
4103 Texas Avenue, Suite 212
Bryan, Texas 77802
KLING ENGINEERING & SURVEYING
Consulting Engineers • Land Surveyors
Telephone 409/846-6212
Fax 409/846-8252
B.J . Kling , P.E., R.P.L.S.
S.M. Kling, R.P.L.S.
Post Office Box 4234
Bryan, Texas 77805
Memo: January 20, 1999
To : Veronica Morgan, P.E.
Assistant City Engineer,
City of College Station
From : Fred Paine
Re : Ashford Square I Dartmouth Addition -Addendum #2 to the Drainage Report
Mr. Bill Kling, P.E. and I have re-evaluated the outlet channel section for the
detention pond and will use this memo as Addendum #2 to the drainage report to
summarize our methodology and proposed modifications . For reference, the original
pond outlet channel used a Manning's n=0 .05 as set forth in the existing drainage report .
The revised outlet channel uses a Manning's n=0 .025. The following is summary of the
logical progress ion used in our evaluation :
1. Upon the rejection of our former solution (baffles), we recalculated the
outfall channel flowrate based on Manning's equation for: (a) the design
section of 8' bottom width and 2:1 side slopes (b) Manning 's n=0 .025 for
cemented rubble masonry . The resulting depth-discharge relationship was
input into our pond model.
2. The pond model was then re-run with the revised outlet channel
characterist ics in place and results were compared to pre-developed
conditions and the "n=0.05" model, both as documented in the existing
dra inage report.
3. Water surface profiles were developed for the downstream channel section
running through the Oak Forest Mobile Home Park to compare pre-
developed and post-developed hydraulic conditions.
The following Table 1 compares the "n=0 .05 " outlet channel characterist ics to the
"n=O 025" outlet channel ~ Pond a WSEL Depth Velocity Peak Storage
Outlet 2,5 , 10,25, 100 2,5 , 10,25, 100 2 ,5, 10,25, 100 2 ,5 , 10,25 , 100 2,5 , 10,25 , 100
Cales . (cfs) (ft) (f/s) (ac-ft)
I n=0.05 318.1 , 469 .0 , 603 .3 , 734.9 , 970 .5 268.0 , 268 .9 , 269.5 , 270 .0, 270 .8 4 .0 , 4 .9, 5.5, 6 .0 , 6 .8 4 .9 , 5.4, 5.8 , 6.1, 6 .5 2.2 , 2.9, 3 .5 , 4 .1, 5.1
[l n=0.025 326 .7, 480.0 , 615.7, 748 .6, 986 .3 266 .9 , 267 .5 , 268 .0, 268 .4 , 269 .0 2 .9 , 3.5 , 4 .0, 4 .4 , 5 .0 8 .2 , 9 .0, 9 .7 , 10.2, 11.0 1 .3 , 1.8 , 2 .1, 2.5, 3.1
Table 1
efer to Appendix 8 of the drainage report "Hydrologic Calculations" for documentation of "n=0 .05 " data .
efer to Appendix 1 of this addendum, "Hydrologic and Routing Calculations" for documentation of "n=0 .025" data.
The following Table 2 compares flow characteristics at the cross section nearest
the detention pond outlet. Routed flowrates leaving the pond are compared to pre-
development flowrates. Note that this cross section , section F-F, was origina ll y
compared to the "n=0.05" pond outflow in the May 11 , 1998 drainage report addendum
and is derived from City contours.
Section F-F
-Pre ***Post:("n=0.05" flows) -Post:("n=0 .025" flows)
0 2,5,10 ,25,100 317.5, 469 .5 , 603.8, 735.4, 971 .0 318 .1 , 469 .0, 603.3, 734.9, 970.5 326.7, 480 .0 , 615.7, 748 .6, 986.3 (cfs)
WSEL 268 .2 ,268.8, 269 .1, 269 .4, 269.8 268 .3,268 .8, 269 .1, 269.4 , 269 .8 268 .3 , 268 .8, 269 .2, 269.4 , 269 .8
Depth 4.2 , 4.8 , 5 .1, 5.4 , 5.8 4 .3 , 4.8, 5.1 , 5.4 , 5.8 4 .3, 4 .8 , 5 .2 , 5.4 , 5.8 (ft)
Velocity 6 .2 , 7 .3 , 8.1, 8.7, 9 .7 6.2, 7.3, 8.1 , 8.7, 9.7 6 .3, 7 .4, 8.1, 8.8, 9 .7 (ft/s)
Hydrograph
App rox . Vol. 35.4, 52 .8, 68 .6, 84 .3, 112.8 37.1 , 54.9, 71 .0, 86 .9, 115.9 37 .1, 54 .9, 71 .0, 86 .9, 115.9
(ac-ft)
Table 2
Table is partial reproduction of table presented in "Addendum to the Dra inage Report", 11-May, 1998 . Additional inf ormation
includes flow characteristics for section F-F based on items 1 & 2 above.
-Refer to drainage report , Appendix 9 , "Hydraulic Calculations" for HEC-2 documentation.
Refer to addendum to drainage report , Appendix 3, "Hydraul ic Calculations" for HEC-2 documentation .
Refer to Append ix 2, of this addendum , "Hydraulic Calculations" for HEC-2 documentation.
Items of interest:
(a) Current pond outlet release rate -vs-Pre-developed runoff rates :
We find that for the storm events summarized above, pond release rates are only
s lightly higher than pre-developed runoff rates . This amount varies from 9 cfs at
the 2 year event to 15 cfs at the 100 year event. In relation to pre-developed
rates, release rates from the pond are an average of only 2% higher.
(b) Pond outlet velocity "n=0 .05" -vs-"n=0.025": Due to the decrease in Manning 's
n , we see an increase in velocities through the outlet channel. It i s shown
however, that the increase in Q does not affect flow characteristics at section F-F
by more than a few hundredths for each calculated parameter (Rounding for
tabulation was to nearest tenth).
(c) Pond water surface elevations "n=0.05" -vs-"n=0.025": As a result of the
decrease in Manning's n, increased velocities through the channel resu lted in an
average decrease of 1.5' in the peak water surface elevations obtained in the
pond .
( d) Storage achieved in pond : One method to estimate storage volume required
for detent ion pond sizing is to overlay the post developed hydrograph with the
pre-developed hydrograph and determine the difference in volume. After routing
computations , the pond under current conditions provides peak storage volumes
ranging from 78% of this estimate at the 2 year event to 100% at the 100 year
event.
Pre-D
Evaluation & Discussion :
(a)The total contributing drainage area for this project consists of approximately
140 acres. Due to various calculation parameters which are subjective in nature :
time of concentration, curve number, drainage area delineation, unintentional
storage of runoff due to interception and surface depression storage, ect., in
addition to the use of a large scale statistical storm distribution assumption (SCS
Type II, 24 hr duration), we believe that it is highly improbable to be able to
estimate runoff quantities within 15 cfs . We consider achieving 98% peak
discharge attenuation acceptable for this project ( 15 cfs out of 971 at the 100 year
event).
The downstream channel section through the Oak Forest mobile home park
currently floods during minor storm events . Prior to commencement of proposed
channel improvements through the mobile home park, on the ground,
topographical information was obtained to develop existing channel cross
sections . Conditions of the existing channel indicated sedimentation and erosion .
Standing water was observed throughout the channel. The area available for the
existing channel section is not adequate to convey stormwater flows without the
banks being overtopped. Additionally, the channel is obstructed by an interior
private road with 4-30" R.C.P . culverts. This road acts as a weir when overtopped
by stormwater. To obtain an estimate of the water surface elevation at the road, a
rating table of discharge -vs-elevation was compiled for various design storm
events (refer to Appendix 2, of this addendum "Hydraulic Calculations" for
computation). An investigation using the HEC-2 to determine water surface
elevations for the channel was conducted to determine the impact of post
development flowrates and channel improvements . Four water surface profiles
were run to model : 1) Pre-development flowrates and existing channel conditions ,
2) Post-development flowrates as discharged from the "n=0.05" pond outfall and
existing channel conditions , 3) Post-development flowrates as discharged from
the "n=0.025" pond outfall and existing channel conditions , 4) Post-development
flowrates as discharged from the "n=0.025" pond outfall and improved channel
conditions . The following tables summarize the results of each run. Refer to
Appendix 2 of this addendum for cross section representation & location .
eve ope d QI E . r Ch XIS mg anne IC dT on 11ons
Storm Qpre WSEL Topwidth
Return (cfs) -450' fl PL -250' flPL -100' fl PL -450' fl PL -250' fl PL -100' fl PL
2 318 266.85 266.88 267.47 251 .65 114.44 70 .01
5 470 267.15 267 .19 267 .89 270.63 153.18 92.87
10 604 267.35 267 .41 268 .17 304.70 182.69 106 .46
25 735 267 .51 267.60 268 .39 309 .50 206.20 116 .86
50 881 267.67 267 .79 268 .61 325.28 277.51 132.39
100 971 267.76 267.90 268.73 326.92 296 .92 138 .22
Table 3
*Starting water surface elevations were obtained by using the flowrates in conjunction with a open channe l
flow analysis of cross section G-G. This section was the starting cross section for HEC-2 runs for the
original report and addendum number 1. The elevations obtained using Manning 's equation were greater
than those calculated at the roadway crossing and therefore are believed to be conservative .
It should be noted that the water surface elevation increases only -1' from the 2
year event to the 100 year event at all sections. The water spread is expected to
encroach into areas occupied by the mobile home units. This demonstrates the
depth of stormwater flow is not significantly affected by the flowrate. The narrow
geometry of the channel and relatively flat overbank section is such that water is
allowed to spread without building up greater depths .
Post-D eve ope d a " o 05" / E · r Ch n= . XIS lnQ anne IC dT d. t I on 1 1ons+se 1men c eane d t 100' fl PL a -
Storm Qpost WSEL Topwidth
Return (cfs) -450' fl PL -250' flPL -100' fl PL -450' fl PL -250' flPL -100' fl PL
2 318 266.85 266.88 267.28 251 .65 114.47 54.18
5 469 267.15 267.19 267.70 270.63 153 .16 83.64
10 603 267 .35 267.41 267 .99 304 .70 182 .67 97.37
25 735 267.51 267.60 268.22 309.50 206 .17 108 .42
50 880 267 .67 267 .79 268.44 325.28 277.43 123.82
100 970 267.76 267.90 268.56 326.92 296.91 129.91
Table 4
*Starting water surface elevations were obtained by using the flowrates in conjunction with a open channel
flow analysis of cross section G-G. This section was the starting cross section for HEC-2 runs for the
original report and addendum number 1. The elevations obtained using Manning's equation were greater
than those calculated at the roadway crossing and therefore a.re believed to be conservative .
Post-D eve ope d a " o 025" / Ex. · ch n= . 1st mg anne IC dT on 1 1ons+se 1ment c eane d t 100' fl PL a -
Storm Qpost WSEL Topwidth
Return (cfs) -450' fl PL -250' flPL -100' fl PL -450' fl PL -250' flPL -100' fl PL
2 327 266.87 266.90 267.31 252.92 117.82 54.87
5 480 267.16 267.21 267.72 271.27 154.76 84.75
10 616 267.36 267.43 268.01 305.00 183 .95 98.43
25 749 267.53 267 .62 268.24 310 .10 210 .30 109 .53
50 896 267.68 267.80 268.46 325.46 283 .74 124.86
100 986 267.77 267 .91 268 .58 327 .11 298.70 130 .91
Table 5
*Starting water surface elevations were obtained by using the flowrates in conjunction with a open channel
flow analysis of cross section G-G. This section was the starting cross section for HEC-2 runs for the
original report and addendum number 1 . The elevations obtained using Manning's equation were greater
than those calculated at the roadway crossing and therefore are believed to be conservative.
As seen in the comparison between Tables 3 and 5 , the water surface elevations did not
noticeably increase (0.02' maximum) as a result of a slightly greater than pre-developed
conditions flowrate. Where sediment was cleaned from the existing channel , a very
slight decrease in elevation was calculated (-0 .15' average). Topwidth did slightly
increase for sections -450' and -250' from the property line but not dramatically (6'
maximum). Again , where sediment was cleaned, a slight decrease in topwidth was
calculated (-10' average). This shows that without any channel improvements, the
correctly calculated discharge from the detention pond does not adversely effect the
downstream flooding situation.
Pos D t-
Channel improvements through this section of the mobile home park have begun
but not been completed . The design section includes a 4' concrete pilot channel
with 4: 1 grassed side slopes . Estimated Longitudinal slope is to be -0.5%.
Although more cross sectional area will be available with the new channel, it will
not significantly alter the total channel volume (refer to Appendix 2, of this
addendum, "Hydraulic Calculations" for verification). The main significance will
be in the channel's flow characteristics. A final HEC-2 run was compiled to model
the current discharge from the detention pond coupled with the proposed channel
improvements. A table summary of results follows.
eve ope d Q" 0 025" /I n= . mprove d Ch anne IC dT on 11ons
Storm Q WSEL Topwidth
Return "n=0.02
5" -450' fl PL -250' flPL -100' fl PL -450' fl PL -250' flPL -100' fl PL
(cfs)
2 327 266.8 266.79 266.88 248.48 97 .86 42.28
5 480 267.15 267.13 267.23 270.63 143 .01 50.30
10 616 267 .39 267.35 267.47 305.90 173.25 68.45
25 749 267 .57 267.52 267.63 311 .30 194 .04 80.15
50 895 267.68 267.62 267 .73 325.46 208 .31 85 .21
100 986 267 .77 267 .70 267 .80 327 .11 234 .65 88.57
Table 6
*Starting water surface elevations were obtained by using the flowrates in conjunction with a open channel
flow analysis of cross section G-G as modified by channel improvements. This section was the starting
cross section for HEC-2 runs for the original report and addendum number 1. The elevations obtained
using Manning's equation were greater than those calculated at the roadway crossing and therefore are
believed to be conservative.
Resulting changes in velocity through this section was a slight increase with
maximum 25 year ·event velocities not exceeding 6 .6 f/s. Water surface
elevations were less than or equal to the pre-developed condition. Topwidth was
decreased from pre-developed conditions at the sections -250' and -100' from
the property line while remaining relatively unchanged (-3.17 <x<+1.8) at the
section-450' from the property line.
(b) Due to the lower roughness coefficient used for the pond outlet channel, an
increase in estimated outflow velocities would result. To minimize the erosive
effect of higher velocities, energy dissipaters will be provided at the end of the
outlet channel. The dissipaters will be 12" diameter concrete cylinders, 2' high
with one #4 bar in each quadrant for reinforcement. Three rows of four cylinders
will be placed 2' apart (center to center) at 1' offsets from each other. An
additional area of concrete rip-rap will be placed on the mobile home park side of
the property line for a distance of 15' for added erosion protection . Refer to
Appendix 3 of this addendum for drawing.
(c) The resulting lower water surface elevation within the detention pond is seen
as a beneficial aspect as it provides more freeboard for each storm event.
( d) We size a detention pond based on an estimate of storage required by
attenuation of post-developed runoff to pre-developed rates . This estimate can
be obtained in several ways. One such way is to overlay pre and post developed
hydrographs and calculate the difference in volume. We find that in the case of
the 2 year event, the pond had a peak storage of -78% of the calculated
difference. As the return period increased, the peak storage achieved in the pond
more closely matched the storage estimate (to 100% at the 100 year event).
The question of where the additional volume would end up leads back to the
hydraulic analysis of the drainage channel through the mobile home park. The
channel improvements will not be significant enough to offset the displaced
volume of water. However, due to increased flow characteristics resulting from
the channel improvements, this volume will pass through the downstream section
with no adverse effects of the existing flooding problem. It should be noted that
the interior road and culverts have a calculated flow rate of 840 cfs at elevation
266.25 and 1199 cfs when this depth is increased by 3" (elev. 266.5). The
flowrate of 1199 cfs is greater than the 100 year event flow rate (986 cfs) and
therefore , no increase in water surface elevation is expected over the roadway .
It is certain that there are many subjective factors which play a major role in the
estimation of storm water runoff rates, each calling for the use of sound engineering
judgment and experience. It is also understood that at this time, accurate hydrologic
design information for rainfall events in this area are non-existent. As a result, we use
hydrologic design practices currently accepted within the field of civil engineering that do
not represent "real world" conditions. Several design storm events are modeled in an
effort to "catch" an actual event that may occur. We base our work on obtaining a
conservative outcome, and do the necessary background and field work to assure a
conservative design. Although mathematically justified, the possibility of a drainage
structure not operating at a desired level under an actual storm event remains with all
hydrologic & hydraulic design. In the case of the flooding in Oak Forest mobile home
park, upstream development has altered the flow of storm water across the tract several
times. Much of the prior development was completed before issues of stormwater
management were of great concern . The hydraulic aspects of the Ashford Square
duplex project and Dartmouth Addition apartment project were designed on the basis
that these developments will not aggravate the existing flooding situation . This facility is
to assure that flooding downstream is not aggravated by this development and to comply
with current City drainage policy.
APPENDIX 1
HYDROLOGIC & ROUTING
CALCULATIONS
Job File: E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Rain Dir: J:\HAESTAD\PPK6\UTIL\
==========================
JOB TITLE
==========================
ASHFORD SQUARE RESUBDIVISION PROJECT
MORGAN RECTOR SURVEY, A-46
COLLEGE STATION, BRAZOS COUNTY, TEXAS
DRAINAGE & DETENTION
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24 -97 :053 C~te Time: 13:36:35 Date: 01-13 -1999
Table of Contents
Table of Contents
******************** NET~ORK SUMMARIES *********************
CARRABBA POST 2 A •••• 2
Executive Sl.1111l8ry (Nodes) .......... 1.01
CARRABBA POST 2 A •••• 5
Executive Sl.1111l8ry (Nodes) .......... 1.02
CARRABBA POST 2 A ••• 10
Executive Sl.1111l8ry (Nodes) .......... 1.03
CARRABBA POST 2 A ••• 25
Executive Sl.1111l8ry (Nodes) .......... 1.04
CARRABBA POST 2 A ••• SO
Executive Sl.1111l8ry (Nodes) .......... 1.05
CARRABBA POST 2 A •• 100
Executive Sl.1111l8ry (Nodes) .......... 1.06
Network Cales Sequence ............. 1.07
********************** CN CALCULATIONS *********************
CARRABBA-TR-PST Runoff CN-Area 2.01
SB-2-EX-CON ••••• Runoff CN·Area 2.02
SB-I POST ••••••• Runoff CN-Area ••••••••••••••••••••• 2.03
*********************** POND VOLUMES ***********************
LAST •••••••••••• Vol: Planimeter •••••••••••••••••••• 3.01
******************** OUTLET STRUCTURES *********************
TRAP CHANNEL2 ••• Outlet Input Data •••••••••••••••••• 4.01
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Co~te Time: 13:36:35 Date: 01-13·1999
Table of Contents ii
Table of Contents (continued)
C<>nlX>site Rating Curve ••••••••••••• 4.04
*********************** POND ROUTING ***********************
p COMB •••••••••• Pond E-V-Q Table ................... 5.01
p COMB OUT A •••• 2
Pond Routing Sll!'fllary ............... 5.03
p COMB OUT A •••• 5
Pond Routing Sll!'fllary ............... 5.04
p COMB OUT A ••• 10
Pond Routing Sll!'fllary ............... 5.05
p COMB OUT A ••• 25
Pond Routing Sll!'fllary ............... 5.06
p COMB OUT A ••• 50
Pond Routing Sll!'fllary ............... 5.07
p COMB OUT A •• 100
Pond Routing Sll!'fllary ............... 5.08
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C0111'Ute Time: 13:36:35 Date: 01-13-1999
Type •••• Executive Sllllll8ry (Nodes)
Name •••• CARRABBA POST 2
File .••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Storm ••• Typell 24hr Tag: A •••• 2
NETllORK SUMMARY --NODES
Page 1.D1
Event: 2 yr
(Trun.= HYG Truncation : Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID = BRAZOS.RNQ SCS-24HR All
Storm Tag Name = A •••• 2
Description: 2 YR -24 HR STORM
Data Type, File, ID =Synthetic Storm SCSTYPES.RNF Typell 24hr
Storm Frequency = 2 yr
Total Rainfall Depth= 4.4210 in
Duration Multiplier = 1
Resulting Durat i on = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max llSEL
Node ID Type ac-ft Trun. hrs cf s ft
------------------------------------................ ...................
CARRABBA POST AREA 3.695 11. 9750 58.91
P COMB IN POND 37.083 12.0750 332 .1 7
P COMB OUT POND 37.083 12.1250 326. 71 266.90
Outfall POINT OF EVAL. JCT 37.083 12.1250 326.72
SB-1 POST AREA 5.010 11. 9750 77.94
SUB -2 EX-CON AREA 28.377 12 .1750 268.64
S/N: HOMOL086313 1 KLING ENGINEERING
Pond Pack Ver: 6 -24 -97 :053 COfl1'Ute Time: 13:36:35 Date : 01 -13-1999
Type •••. Executive SU1111ary (Nodes)
Name .••• CARRABBA POST 2
File .••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Storm ••• Type!! 24hr Tag: A •••• 5
NETWORK SUMMARY --NODES
Page 1.02
Event: 5 yr
CTrun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = A •••• 5
Description: 5 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 5 yr
Total Rainfall Depth= 6.0210 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max WSEL
Node ID Type ac-ft Trun. hrs cfs ft
------------------------------------·--··---...................
CARRABBA POST AREA 5.457 11.9750 85.33
P COMB IN POND 54.922 12.0750 486.03
P COMB OUT POND 54.922 12.1000 480.01 267.52
Outfall POINT OF EVAL. JCT 54.922 12.1000 480.01
SB-1 POST AREA 7.234 11. 9750 110.21
SUB-2 EX-CON AREA 42.230 12.1750 395.25
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35 Date: 01-13-1999
Type •••• Executive SlJTlllary (Nodes)
Name •..• CARRABBA POST 2
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Storm ••• Type!! 24hr Tag: A ••• 10
NETWORK SUMMARY --NODES
Page 1.03
Event: 10 yr
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = A ••• 1D
Description: 10 YR -24 HR STORM
Data Type, File, ID =Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 10 yr
Total Rainfall Depth= 7.4390 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max WSEL
Node ID Type ac-ft Trun. hrs cfs ft
--------------------·----------·---------------------
CARRABBA POST AREA 7.042 11. 9750 108.55
P COMB IN POND 70.988 12.0750 621.84
P COMB OUT POND 70.988 12.1000 615.69 267 .98
Outfall POINT OF EVAL. JCT 70.988 12.1000 615.69
SB-1 POST AREA 9.222 11. 9750 138.55
SUB -2 EX-CON AREA 54.724 12.1750 506.98
S/N: HOMOL086313 1 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~ute Time: 13:36:35 Date: 01-13 -1999
Type •••• Executive Sl.lllllary (Nodes)
Name •••. CARRABBA POST 2
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Storm ••• TypeII 24hr Tag: A ••• 25
NETWORK SUMMARY --NODES
Page 1.04
Event: 25 yr
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = A ••• 25
Description: 25 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF TypeII 24hr
Storm Frequency = 25 yr
Total Rainfall Depth= 8.8360 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max WSEL
Node ID Type ac-ft Trun. hrs cfs ft
---------------------------....................... -----------------
CARRABBA POST AREA 8.616 11. 9750 131.27
P COMB IN POND 86.947 12.0750 754.91
P COMB OUT POND 86.947 12.1000 748.63 268.38
utfal l POINT OF EVAL. JCT 86.947 12.1000 748.63
SB-1 POST AREA 11.188 11.9750 166.28
SUB-2 EX-CON AREA 67.143 12.1750 616.42
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35 Date: 01-13-1999
Type ..•• Executive Sllllllary (Nodes)
Name •••• CARRABBA POST 2
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Storm ••• Typell 24hr Tag: A ••• 50
NETWORK SUMMARY --NODES
Page 1.05
Event: 50 yr
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File,ID = BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = A ••• 50
Description: 50 YR -24 HR STORM
Data Type, File, ID =Synthetic Storm SCSTYPES.RNF Typell 24hr
Storm Frequency = 50 yr
Total Rainfall Depth= 10.3880 in
Duration Multiplier = 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max IJSEL
Node ID Type ac-ft Trun. hrs cfs ft
-----------------------------·------·----·--.........................
CARRABBA POST AREA 10.373 11. 9750 156.36
P COMB IN POND 104.no 12.0750 901.96
P COMB OUT POND 104.no 12.1000 895.47 268.n
tfal l POINT OF EVAL. JCT 104.no 12.1000 895.48
SB-1 POST AREA 13.378 11.9750 196.95
SUB-2 EX-CON AREA 81.019 12.1750 737.29
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35 Date: 01-13-1999
Type •••• Executive Sllllllary (Nodes)
Name .••• CARRABBA POST 2
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Storm ••• Type!! 24hr Tag: A •• 100
NETWORK SUMMARY --NOOES
Page 1.06
Event: 100 yr
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Oesgin Storm File, ID = BRAZOS.RNQ SCS·24HR ALL
Storm Tag Name = A •• 100
Description: 100 YR -24 HR STORM
Data Type, File, ID =Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 100 yr
Total Rainfall Depth= 11.3530 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max IJSEL
Node ID Type ac-ft Trun. hrs cfs ft
-----------------------------------------------------
CARRABBA POST AREA 11.468 11. 9750 171.90
P COMB IN POND 115.886 12.0750 993.02
P COMB OUT PONO 115.886 12.1000 986.35 269.00
Outfall POINT OF EVAL. JCT 115.886 12.1000 986.35
SB-1 POST AREA 14.742 11. 9750 215 .96
SUB-2 EX-CON AREA 89.676 12.1750 812.12
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35 Date: 01-13-1999
Type •••• Network Cales Sequence
Name •••• CARRABBA POST 2
Page 1.07
Event: 100 yr
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Storm ••• Type!! 24hr Tag: A .• 100
NETYORK RUNOFF NODE SEQUENCE
===========================================================================
Runoff Data Apply to Node Receiving Link
===========================================================================
SCS UH SB-I POST
SCS UH SB-2 EX-CON
SCS UH CARRABBA-PST
Subarea SB-1 POST
Subarea SUB-2 EX-CON
Subarea CARRABBA POST
S/N: HOMOL0863131 KLING ENGINEERING
Add Hyd SB-1 POST
Add Hyd SUB-2 EX-CON
Add Hyd CARRABBA POST
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35 Date: 01-13-1999
Type •••• Network Cales Sequence
Name •••• CARRABBA POST 2
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Storm ••• Type!! 24hr Tag: A •• 100
NETYORK ROUTING SEQUENCE
Page 1.08
Event: 100 yr
===========================================================================
Link Operation UPstream Node DNstream Node
===========================================================================
Add Hyd CARRABBA POST
Add Hyd SB-2 EX CON PST
Add Hyd SB-1 POST
Subarea CARRABBA POST
Subarea SUB-2 EX-CON
Subarea SB-1 POST
POND ROUTE TOTAL OUTFLOY •••
Total Pond Outflow Pond P COMB
SET POND ROUTING LINK TO TOTAL POND OUTFLOY •••
Outlet DET POND Outflow P COMB
S/N: HOMOL0863131 KLING ENGINEERING
Pond
Pond
Pond
P COMB
P COMB
P COMB
IN Outflow P COMB
IN
IN
IN
OUT
OUT Jct POINT OF EVAL.
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35 Date: 01-13-1999
Type .••• Runoff CN -Area
Name .••• CARRABBA-TR-PST
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Title ••• CARRABBA-GLOCKSEEN TRACT POST DEVELOPED CONDITIONS
RUNOFF CURVE NUMBER DATA
Page 2.01
.......................................................................... ..........................................................................
CARRABBA-GLOCKSEEN TRACT POST DEVELOPED CONDITIONS
Impervious
Area Adjustment Adjusted
Soil/Surface Description CN acres r.c %UC CN
--------------------------------------------.... -.. ---
APARTMENT DEVELOPMENT 92 10. 180 92.00
RESERVE TRACT UNDEVELOPED 80 3.010 80.00
NATURAL CONDITIONS 80 .580 80.00
COMPOSITE AREA & ~EIGHTED CN ---> 13. 770 88.87 (89) ........................................................................... ...........................................................................
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35 Date: 01-13-1999
Type .••• Runoff CN-Area
Name •••• SB-2-EX-CON
File •.•• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Title .•• TOTAL SUB-BASIN 2 DRAINAGE AREA. EXISTING CONDITIONS
RUNOFF CURVE NUMBER DATA
Page 2.02
.......................................................................... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
TOTAL SUB-BASIN 2 DRAINAGE AREA. EXISTING CONDITIONS
Soil/Surface Description
HSG-D,FIELD GRASSES,BRUSH
HSG-D,DEVELOPED AREAS
HSG-D,DEVELOPED AREAS
COMPOSITE AREA & WEIGHTED CN --->
CN
80
89
89
Area
acres
---·-----
17.878
72.068
19.110
109.056
Impervious
Adjustment
%C XlJC
-... --... --... -...
Adjusted
CN
80.00
89.00
89.00
87.52 (88) ........................................................................... ...........................................................................
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35 Date: 01-13-1999
Type .••• Runoff CN-Area
Name •..• SB-I POST
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Title ••• SB-I POST-DEVELOPED
RUNOFF CURVE NUMBER DATA
Page 2.03
·········································································· ..........................................................................
SB-I POST-DEVELOPED
Soil/Surface Description
IMPERVIOUS
GRASSED
LOT 1R BLOCK D A-P TRACT
COMPOSITE AREA & WEIGHTED CN --->
CN
98
80
94
Area
acres
---------
10.818
5.485
.752
17.055
Impervious
Adjustment Adjusted
%C xuc CN
----------
98.00
80.00
94.00
92.03 (92) ........................................................................... ···········································································
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24 -97 :053 Compute Time: 13:36:35 Date: 01-13-1999
Type •.•• Vol: Planimeter
Name ..•• LAST
File •.•• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Title .•• 264
Elevation
(ft)
264.00
264.50
265.00
266.00
267.00
268.00
269.00
270.00
270.80
271.00
272.00
POND VOLUME CALCULATIONS
Planimeter scale: 1.00 ft/in
Planimeter
(sq. in)
91.400
11573.740
19651.920
26179.480
30727.240
35761.090
41750.781
47649.031
52255.020
54894.520
60530.949
Area
(acres)
.0021
.2657
.4511
.6010
.7054
.8210
.9585
1.0939
1.1996
1.2602
1.3896
A1+A2+sqr(A1*A2) Volune
(acres) (ac·ft)
.0000 .000
.2914 .049
1.0631 .1n
1.5729 .524
1. 9575 .653
2.2874 .762
2.6665 .889
3.0763 1.025
3.4390 .917
3.6893 .246
3.9731 1.324
POND VOLUME EQUATIONS
Page 3.01
Volune Sllll
(ac·ft)
.000
.049
.226
.750
1.403
2.165
3.054
4.079
4.996
5.242
6.567
* Incremental volune computed by the Conic Method for Reservoir Volumes.
Volume= (1/3) * (EL2·EL1) * (Area1 + Area2 + sq.rt.(Area1*Area2))
where: EL 1, EL2
Area1,Area2
Volume
= Lower and upper elevations of the increment
=Areas computed for EL1, EL2, respectively
= Incremental volume between EL1 and EL2
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35 Date: 01-13-1999
Type .••• Outlet Input Data
Name .••• TRAP CHANNEL2
File .••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Title ••• 8 1 BOTTOM WIDTH W/ 2'H : 1'V SIDE SLOPES n=0.025
REQUESTED POND WS ELEVATIONS:
Min. Elev.= 264.00 ft
Increment = .20 ft
Max. Elev.= 272.00 ft
**********************************************
OUTLET CONNECTIVITY
**********************************************
---> Forward Flow Only (Upstream to DnStream)
<---Reverse Flow Only CDnStream to Upstream)
<---> Forward and Reverse Both Allowed
Structure
User Defined Table
TW SETUP, OS Channel
No.
--->
Outfall E1, ft
TW .000
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35
Page 4.01
E2, ft
272.000
Date: 01-13-1999
Type •••• Outlet Input Data
Name •••• TRAP CHANNEL2
File ..•• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Title ••• 8' BOTTOM WIDTH W/ 2'H : 1'V SIDE SLOPES n=0.025
OUTLET STRUCTURE INPUT DATA
Structure ID
Structure Type
= 1
= User Defined Table
ELEV-FLOW RATING TABLE
Elev, ft Flow, cfs
--·---------------
264.00 .00
264.20 2.94
264.40 9.46
264.60 18.90
264.80 31.05
265.00 45.88
265.20 63.38
265.40 83.58
265.60 106.52
265.80 132.28
266.00 160.92
266.20 192.50
266.40 227.11
266.60 264.81
266.80 305.69
267.00 349.83
267.20 397.29
267.40 448.17
267.60 502.54
267.80 560.47
268.00 622.05
268.20 687.36
268.40 756.46
268.60 829.44
268.80 906.37
269.00 987.33
269.20 1072.39
269.40 1161.63
269.60 1255. 13
269.80 1352.94
27D.OO 1455. 16
270.20 1561.84
270.40 1673.07
270.60 1788.91
270.80 1909.43
271.00 2034. 71
271.20 2164.82
271.40 2299.82
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~ute Time: 13:36:35
Page 4.02
Date: 01-13-1999
Type •••• Outlet Input Data
Name .••• TRAP CHANNEL2
File .••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Title ••• 8 1 BOTTOM UIDTH U/ 2 1 H : 1'V SIDE SLOPES n=0.025
Elev, ft Flow, cf s
------------------
271.60 2439.78
271.80 2584 .78
272.00 2734.88
= TU Structure ID
Structure Type = TU SETUP, OS Channel
FREE OUTFALL CONDITIONS SPECIFIED
CONVERGENCE TOLERANCES •••
Maxin.m Iterations= 30
Min. TU tolerance = .01 ft
Max. TU tolerance = .01 ft
Min. HU tolerance = .01 ft
Max. HU tolerance = .01 ft
Min. Q tolerance = • 10 cfs
Max . Q tolerance = • 10 cfs
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35
Page 4.03
Date: 01-13-1999
Type •••• COf11:>osite Rating Curve
Name .••• TRAP CHANNEL2
File •••. E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Title ••• 8 1 BOTTOM WIDTH W/ 2'H : 1'V SIDE SLOPES n=0.025
***** COMPOSITE OUTFLOW SUMMARY ****
WS Elev, Total Q Notes
------------------------Converge -------------------------
Elev. Q TW Elev Error
ft cfs ft +/-ft Contributing Structures
------------------------------------------
264.00 .00 Free Outfall
264.20 2.94 Free Outfa l l
264.40 9.46 Free Outfall
264.60 18.90 Free Outfall
264.80 31.05 Free Outfall
265.00 45.88 Free Outfall
265.20 63.38 Free Outfall
265.40 83.58 Free Outfall
265.60 106.52 Free Outfall
265.80 132.28 Free Outfall
266.00 160.92 Free Outfall
266.20 192.50 Free Outfall
266.40 227.11 Free Outfall
266.60 264.81 Free Outfall
266.80 305.69 Free Outfa l l
267.00 349.83 Free Outfall
267.20 397.29 Free Outfall
267.40 448.17 Free Outfall
267.60 502.54 Free Outfall
267.80 560.47 Free Outfall
268.00 622.05 Free Outfall
268.20 687.36 Free Outfall
268.40 756.46 Free Outfall
268.60 829.44 Free Outfall
268.80 906.37 Free Outfa l l
269.00 987.33 Free Outfa l l
269.20 1072.39 Free Outfall
269.40 1161.63 Free Outfall
269.60 1255.13 Free Outfall
269.80 1352.94 Free Outfall
270 .00 1455. 16 Free Outfall
27D.20 1561.84 Free Outfall
270.40 1673.07 Free Outfall
270.60 1788.91 Free Outfall
270.80 1909.43 Free Outfa l l
271.00 2034 .71 Free Outfall
271.20 2164.82 Free Outfall
271.40 2299.82 Free Outfa l l
271.60 2439.78 Free Outfall
S/N: HOMOL0863131 KLING ENGINEERING
Page 4.04
Pond Pack Ver: 6-24 -97 :053 COf11:>Ute Time: 13:36:35 Date: 01-13-1999
Type •••• C~osite Rating Curve
Name •••• TRAP CHANNEL2
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Title .•. 8 1 BOTTOM WIDTH W/ 2'H : 1'V SIDE SLOPES n=0.025
***** COMPOSITE OUTFLOW SUMMARY ****
WS Elev, Total Q Notes
Elev. Q
--------Converge
TW Elev Error
Page 4.05
ft cfs ft +/-ft Contributing Structures
271.80 2584.78 Free Outfall
272.00 2734.88 Free Outfall
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 COfTllUte Time: 13:36:35 Date: 01-13 -1999
Type •.•• Pond E·V·Q Table
Name •••• P COMB
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
LEVEL POOL ROUTING DATA
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
Inflow HYG file= LASTREV.HYG · P COMB IN A •••• 2
Outflow HYG file= LASTREV.HYG · P COMB
Pond Node Data = P COMB
Pond Volume Data = last
Pond Outlet Data = TRAP CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting YS Elev = 264.00 ft
Starting Volume = .000 ac-ft
Starting Outflow .00 cfs
Starting lnfiltr. = .00 cfs
Starting Total Qout= .00 cfs
Time Increment = .0250 hrs
evation Outflow Storage Area
ft cf s ac-ft acres
OUT A •••. 2
lnfilt.
cfs
Q Total
cfs
Page 5.01
2S/t + 0
cfs
------------------------------------------------------------------------------
264.00 .00 .000 .0021 .00 .00 .oo
264.20 2.94 .004 .0546 .00 2.94 7.29
264.40 9.46 .027 .1m .00 9.46 35.16
264.60 18.90 .077 .2989 .00 18.90 93.23
264.80 31.05 .144 .3711 .00 31.05 170.10
265.00 45.88 .226 .4511 .00 45.88 264.40
265.20 63.38 .319 .4794 .00 63.38 371.97
265.40 83.58 .418 .5085 .00 83.58 487.78
265.60 106.52 .522 .5385 .00 106.52 612.06
265.80 132.28 .633 .5693 .00 132.28 745.03
266.00 160.92 .750 .6010 .00 160.92 886.95
266.20 192.50 .872 .6212 .00 192.50 1036.84
266.40 227.11 .999 .6418 .00 227. 11 1193.69
266.60 264.81 1.129 .6626 .00 264.81 1357.66
266.80 305.69 1.264 .6839 .00 305.69 1528.86
267.00 349.83 1.403 .7054 .00 349.83 1707.48
267.20 397.29 1.546 .7278 .00 397.29 1893.68
267.40 448.17 1.694 .7506 .00 448.17 2087.65
267.60 502.54 1.846 .m7 .00 502.54 2289.57
267.80 560.47 2.003 .7971 .00 560.47 2499.54
268.00 622.05 2.165 .8210 .00 622.05 2717.75
268.20 687.36 2.332 .8476 .00 687.36 2944.58
268.40 756.46 2.504 .8747 .00 756.46 3180.38
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35 Date: 01-13-1999
Type ••.• Pond E-V-Q Table
Name •••• P COMB
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
LEVEL POO L ROUTING DATA
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
Page 5.D2
Inflow HYG file= LASTREV.HYG - P COMB IN A .••• 2
Outflow HYG file = LASTREV.HYG - P COMB
Pond Node Data = P COMB
Pond Voll.Ille Data = last
Pond Outlet Data = TRAP CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting WS Elev = 264.00 ft
Starting Voll.Ille = .000 ac-ft
Starting Outflow = .00 cfs
Starting Infiltr. = .00 cfs
Starting Total Qout= .00 cfs
Time Increment = .0250 hrs
evation Outflow Storage Area
ft cfs ac-ft acres
OUT A •••• 2
lnfilt.
cfs
Q Total
cfs
2S/t + 0
cfs
------------------------------------------------------------------------------
268 .60 829.44 2.682 .9022 .00 829.44 3425 .37
268.80 906.37 2.865 .9301 .00 906.37 3679.64
269.00 987.33 3.054 .9585 .00 987.33 3943.42
269.20 1072.39 3.248 .9848 .00 1072.39 4216.60
269.40 1161.63 3.448 1.0116 .00 1161.63 4499.06
269.60 1255.13 3.653 1.0386 .00 1255. 13 4791.03
269.80 1352.94 3.863 1.0661 .00 1352.94 5092.55
270 .00 1455.16 4.079 1.0939 .00 1455.16 5403.86
270.20 1561.84 4.301 1. 1199 .00 1561.84 5724.83
270.40 1673.07 4.527 1.1461 .00 1673.07 6055 .39
270.60 1788.91 4.759 1.1727 .00 1788.91 6395. 70
270.80 1909.43 4.996 1. 1996 .00 1909.43 6745.84
271.00 2034.71 5.242 1.2602 .00 2034.71 7109.22
271.20 2164.82 5.497 1.2856 .00 2164.82 7485.n
271.40 2299.82 5.756 1.3112 .00 2299.82 7872.1 1
271.60 2439.78 6.021 1.3371 .00 2439.78 8268.44
271.80 2584.78 6.291 1.3632 .00 2584.78 8674 .80
272.00 2734.88 6.567 1.3896 .00 2734.88 9091 .38
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24 -97 :053 COl!l>Ute Time: 13:36:35 Date: 01-13 -1999
Type •••. Pond Rout i ng Sl.lllll8ry
Name •••• P COMB OUT Tag: A •••• 2
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Storm ••• Type!! 24hr Tag: A •.•• 2
LEVEL POOL ROUTING SUMMARY
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
Inflow HYG file= LASTREV.HYG -P COMB
Outflow HYG file= LASTREV.HYG -P COMB
IN A •••• 2
OUT A •••• 2
Pond Node Data = P COMB
Pond Volune Data = last
Pond Outlet Data = TRAP CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting YS Elev 264.00 ft
Starting Volune = .000 ac-ft
Starting Outflow = .00 cfs
Starting Infiltr. = .00 cfs
Starting Total Qout= .00 cfs
Time Increment = .0250 hrs
INFLOl.l/OUTFLO\.I HYDROGRAPH SUMMARY
=====================================================
Peak Inflow
Peak Outflow
Peak Elevation
Peak Storage =
= 332.17 cfs
= 326.71 cfs
= 266.90 ft
1.329 ac-ft
at 12.0750 hrs
at 12.1250 hrs
=====================================================
MASS BALANCE Cac -ft)
+ Initial Vol =
+ HYG Vol IN =
-Infiltration=
-HYG Vol OUT =
-Retained Vol
.000
37.083
.000
37.083
.000
Page 5.03
Event: 2 yr
Unrouted Vol = .000 ac-ft C.000% of Outflow Volume)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35 Date: 01-13-1999
Type ..•• Pond Routing Sl.lllllary
Name •••• p COMB OUT Tag: A •••• 5
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Storm ••• Typell 24hr Tag: A •••• 5
LEVEL POOL ROUTING SUMMARY
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
Inflow HYG file= LASTREV.HYG -P COMB
Outflow HYG file= LASTREV.HYG -P COMB
IN A •••• 5
OUT A .••• 5
Pond Node Data = P COMB
Pond Volune Data = last
Pond Outlet Data = TRAP CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting WS Elev = 264.00 ft
Starting Volune = .000 ac-ft
Starting Outflow = .00 cfs
Starting lnfiltr. = .00 cfs
Starting Total Qout= .00 cfs
Time Increment = .0250 hrs
INFLOW/OUTFLOW HYDROGRAPH SUMMARY
=====================================================
Peak Inf low
Peak Outflow
Peak Elevation
Peak Storage =
= 486.03 cfs
480.01 cfs
= 267.52 ft
1.782 ac-ft
at 12.0750 hrs
at 12.1000 hrs
=====================================================
HASS BALANCE (ac-ft)
+ Initial Vol = .000
+ HYG Vol IN =
-Infiltration =
-HYG Vol OUT =
-Retained Vol =
54.922
.000
54.922
.000
Page 5.04
Event: 5 yr
Unrouted Vol .000 ac-ft (.000% of Outflow Volune)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 13:36:35 Date: 01-13-1999
Type •••• Pond Routing Surmary
Name •••• P COMB OUT Tag: A ••• 10
File •.•• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Storm ..• Typell 24hr Tag: A ••• 10
LEVEL POOL ROUTING SUMMARY
HYG Dir E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
Inflow HYG file= LASTREV.HYG · P COMB IN A ••• 10
Outflow HYG file= LASTREV.HYG - P COMB OUT A ••• 10
Pond Node Data = P COMB
Pond Volume Data = last
Pond Outlet Data = TRAP CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting WS Elev = 264.00 ft
Starting Volume = .000 ac-ft
Starting Outflow .00 cfs
Starting Infiltr. = .00 cfs
Starting Total Qout= .00 cfs
Time Increment = .0250 hrs
INFLOW/OUTFLOW HYDROGRAPH SUMMARY
=====================================================
Peak Inflow
Peak Outflow
Peak Elevation
Peak Storage =
= 621.84 cfs
= 615.69 cfs
= 267.98 ft
2.148 ac·ft
at 12.0750 hrs
at 12.1000 hrs
=====================================================
MASS BALANCE (ac·ft)
Initial Vol =
HYG Vol IN
-Infiltration=
• HYG Vol OUT =
-Retained Vol =
.000
70.988
.000
70.988
.000
Page 5.05
Event: 10 yr
Unrouted Vol = .000 ac·ft (.000% of Outflow Voll.Ille)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 COfT1)Ute Time: 13:36:35 Date: 01-13-1999
Type •••• Pond Routing Sl.Jllllary
Name •••• P COMB OUT Tag: A •.• 25
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Storm ••• Type!! 24hr Tag: A ••• 25
LEVEL POOL ROUTING SUMMARY
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
Inflow HYG file= LASTREV.HYG - P COMB IN A •.• 25
Outflow HYG file= LASTREV.HYG - P COMB OUT A ••• 25
Pond Node Data = P COMB
Pond Volune Data = last
Pond Outlet Data = TRAP CHANNEL2
No Infiltration
INlflAL CONDITIONS
Starting WS Elev = 264.00 ft
Starting Volune = .000 ac-ft
Starting Outflow = .00 cfs
Starting lnfiltr. = .00 cfs
Starting Total Qout= .00 cfs
Time Increment = .0250 hrs
INFLOW/OUTFLOW HYDROGRAPH SUMMARY
=====================================================
Peak Inf low
Peak Outflow
Peak Elevation
Peak Storage =
= 754.91 cfs
= 748.63 cfs
= 268.38 ft
2.484 ac-ft
at 12.0750 hrs
at 12.1000 hrs
=====================================================
MASS BALANCE (ac-ft)
+ Initial Vol =
+ HYG Vol IN =
-Infiltration=
-HYG Vol OUT =
-Retained Vol =
.000
86.947
.000
86.947
.000
Page 5.06
Event: 25 yr
Unrouted Vol = .000 ac -ft (.OOOX of Outflow VollJTle)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35 Date: 01-13 -1999
Type .••• Pond Routing Sllllllary
Name ••.• P COMB OUT Tag: A ••• 50
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Storm ••• Typell 24hr Tag: A •.• 50
LEVEL POOL ROUTING SUMMARY
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
Inflow HYG file= LASTREV.HYG - P COMB IN A ••• 50
Outflow HYG file= LASTREV.HYG - P COMB OUT A ••• 50
Pond Node Data = P COMB
Pond Volume Data = last
Pond Outlet Data = TRAP CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting WS Elev
Starting Volume
Starting Outflow =
Starting Infiltr. =
Starting Total Qout=
Time Increment =
264.00 ft
.000 ac-ft
.00 cfs
.00 cfs
.00 cfs
.0250 hrs
INFLOW/OUTFLOW HYDROGRAPH SUMMARY
=====================================================
Peak Inf low
Peak Outflow
Peak Elevation
Peak Storage =
= 901.96 cfs
= 895.47 cfs
= 268.77 ft
2.839 ac-ft
at 12.0750 hrs
at 12.1000 hrs
=====================================================
MASS BALANCE (ac -ft)
+ Initial Vol =
+ HYG Vol IN =
-Infiltration=
-HYG Vol OUT =
• Reta i ned Vol
.000
104.770
.000
104.770
.000
Page 5.07
Event: 50 yr
Unrouted Vol = -.000 ac -ft (.000% of Inflow Volume)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24 -97 :053 Compute Time: 13:36:35 Date: 01-13-1999
Type •••• Pond Routing SUllll8ry
Name ••.• P COMB OUT Tag: A •• 100
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\LAST3REV.PPK
Storm ••• Typell 24hr Tag: A •• 100
LEVEL POOL ROUTING SUMMARY
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
Inflow HYG file= LASTREV.HYG - P COMB IN A •• 100
Outflow HYG file= LASTREV.HYG -P COMB OUT A •• 100
Pond Node Data = p COMB
Pond Voll.Jlle Data = last
Pond Outlet Data = TRAP CHANNEL2
No Infiltration
INITIAL CONDITIONS
Starting WS Elev = 264.00 ft
Starting Voll.Jlle = .000 ac-ft
Starting Outflow = .00 cfs
Starting lnfiltr. = .00 cfs
Starting Total Qout= .00 cfs
Time Increment = .0250 hrs
INFLOW/OUTFLOW HYDROGRAPH SUMMARY
=====================================================
Peak Inflow
Peak Outflow
Peak Elevation
Peale Storage =
= 993.02 cfs
= 986.35 cfs
= 269.00 ft
3.051 ac-ft
at 12.0750 hrs
at 12.1000 hrs
=====================================================
MASS BALANCE (ac-ft)
+ Initial Vol =
+ HYG Vol IN =
-Infiltration=
-HYG Vol OUT =
-Retained Vol =
.000
115.886
.000
115.886
.000
Page 5.08
Event: 100 yr
Unrouted Vol -.000 ac-ft (.000% of Inflow Volume)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35 Date: 01-13-1999
Appendix A
Index of Starting Page NUTi:iers for ID Names
-----c
CARRABBA POST 2 A •••• 2 ••• 1.D1,
1.02, 1.03, 1.04, 1.05, 1.06,
1.07
CARRABBA-TR-PST ••• 2.01
-----L -----
LAST ••• 3.01
-----p -----
p COMB .•• 5.01, 5.03, 5.04, 5.05,
5.06, 5.07, 5.08
·----s -----
SB-2-EX-CON ••• 2.02
SB-I POST ••• 2.03
-----T -----
TRAP CHANNEL2 ••• 4.01, 4.04
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 13:36:35
A-1
Date: 01·13-1999
APPENDIX2
HYDRAULIC
CALCULATIONS
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Constant Data
RATING TABLE
Rating Table for Trapezoidal Channel
e:\haestad\pi\ashford\ashford .fm2
POND OUTLET 2 rev
Trapezoidal Channel
Manning's Formula
Discharge
Mannings Coefficient
Channel Slope
0.025
0.008000 ft/ft
2.000000 H : V
2.000000 H : V
Left Side Slope
Right Side Slope
Bottom Width 8.00 ft
Input Data
Minimum Maximum
De~th 0.00 8.00
Rating Table
Depth Discharge Velocity
(ft) (cfs) (ft/s)
0.00 0.00 0.00
0.20 2.94 1.75
0.40 9.46 2.69
0.60 18 .90 3.42
0.80 31 .05 4.04
1.00 45 .88 4 .59
1.20 63.38 5.08
1.40 83 .58 5.53
1.60 106.52 5.94
1.80 132.28 6.34
2.00 160.92 6 .70
2.20 192.50 7.06
2.40 227.11 7.39
2 .60 264.81 7.72
2.80 305.69 8.03
3.00 349.83 8.33
3.20 397.29 8.62
3.40 448.17 8.91
3.60 502.54 9.18
3.80 560.47 9.45
4 .00 622.05 9.72
4 .20 687.36 9.98
Increment
0.20 ft
01/20/99
10:27:46AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5.12
Page 1 of 2
Rating Table
01/20199
10:27:46AM
Depth
{ft}
4 .40
4.60
4 .80
5 .00
5.20
5.40
5 .60
5 .80
6 .00
6 .20
6 .40
6.60
6.80
7.00
7.20
7 .40
7 .60
7 .80
8.00
RATING TABLE
Rating Table for Trapezoidal Channel
Discharge Velocity
{cfs} (ft/s}
756.46 10 .23
829.44 10.48
906 .37 10.73
987 .33 10.97
1,072 .39 11.21
1,161 .63 11.44
1 ,255.13 11.67
1 ,352.94 11.90
1 ,455 .16 12.13
1 ,561.84 12.35
1 ,673 .07 12.57
1 ,788 .91 12 .79
1 ,909 .43 13.00
2 ,034 .71 13 .21
2 ,164 .82 13.42
2 ,299.82 13 .63
2 ,439 .78 13 .84
2 ,584.78 14.04
2 ,734.88 14 .24
Haestad Met hods, Inc. 37 Brookside Road Waterbury, CT 067 08 (203) 755-1 666
FlowMaster v5. 12
Page 2 of 2
25 YR -WSEL ESTIMATE SECTION G-G -POST
Worksheet for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e:\haestad\pi\ashford\ashford.fm2
CHANNEL SECTION G-G (SCS)
Irregular Channel
Manning's Formula
Solve For Water Elevation
Input Data
Channel Slope 0.008500 V : H
Elevation range: 263.05 ft to 269.20 ft.
Station (ft) Elevation (ft)
0.00 269.20
220.87 268.00
369 .39 266 .00
381 .30 264 .00
386 .97 263.05
392.76 264.00
403.44 266.00
522 .68 268 .00
Discharge 748 .60 ffl/s
Results
Wtd. Mannings Coefficient 0.050
Water Surface Elevation 267.53 ft
Flow Area 258 .97 ft2
Wetted Perimeter 238 .98 ft
Top Width 238.45 ft
Depth 4.48 ft
Critical Water Elev. 266.93 ft
Critical Slope 0.038100V:H
Velocity 2.89 ft/s
Velocity Head 0.13 ft
Specific Energy 267.66 ft
Froude Number 0.49
Flow is subcritical.
Notes:
Start Station
0.00
End Station
522 .68
Roughness
0.050
SECTION G-G FROM CITY CONTOURS DEVELOPED TO DETERMINE STARTING WATER SURFACE
ELEVATIONS FOR HEC-2 RUNS , OAK FOREST MOBILE HOME PARK -EXISTING CHANNEL CONDITIONS.
01120/99
10:24:01 AM Haestad Methods, Inc . 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5 .12
Page 1 of 1
25 YR -WSEL ESTIMATE SECTION G-G -POST
Worksheet for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
Channel Slope
e:\haestad\pi\ashford\ashford.fm2
CHANNEL SECTION G-G (SCS) chimp
Irregular Channel
Manning's Formula
Water Elevation
0.008500 V : H
Elevation range: 263.05 ft to 269.20 ft.
Station (ft) Elevation (ft)
0 .00 269.20
220.87 268.00
369 .39 266.00
381 .30 264.00
384.97 263.05
386.97 263 .05
388.97 263.05
392.76 264.00
403.44 266.00
522.68 268.00
Discharge 748 .60 ft3/s
Results
Wtd. Mannings Coefficient 0.053
Water Surface Elevation 267 .57 ft
Flow Area 270.11 ft2
Wetted Perimeter '244.20 ft
Top Width 243 .58 ft
Depth 4.52 ft
Critical Water Elev. 266.91 ft
Critical Slope 0.034716 V: H
Velocity 2.77 ft/s
Velocity Head 0.12 ft
Specific Energy 267.68 ft
Froude Number 0.46
Flow is subcritical.
Notes:
Start Station
0.00
369.39
403.44
End Station
369 .39
403.44
522.68
Roughness
0.060
0.028
0.060
SECTION G-G WITH APPLIED CHANNEL IMPROVEMENTS (4:1 SS, 4' CONC. PILOT) DEVELOPED TO
DETERMINE STARTING WATER SURFACE ELEVATIONS FOR CURCHIMP .DAT
01/20/99
10:20:53AM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v5.12
Page 1 of 1
Job File: E:\HAESTAD\PONDPACK\PPK6\ASHFORD\SWOBOOA.PPK
Rain Dir: J:\HAESTAD\PPK6\UTIL\
==========================
JOB TITLE
==========================
To determine flow over 1st road downstream of Ashford Square on
Swoboda tract -2nd road and dbl culverts backwater effects are
neglected.
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 17:10:31 Date: 01-19 -1999
Table of Contents
Table of Contents
******************** OUTLET STRUCTURES *********************
ROADWAY1 •••••... Outlet Input Data .••..•••••••••.••• 1.01
Individual Outlet Curves ••....•••.. 1.04
C~osite Rating Curve ••••...•••.•. 1.08
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~ute Time: 17:10:31 Date: 01-19-1999
Type .••• Outlet Input Data
Name ••.. ROADWAY1
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\SWOBODA.PPK
Title .•• roadway1
REQUESTED POND WS ELEVATIONS:
Min. Elev.= 261.00 ft
Increment = .25 ft
Max. Elev.= 266.50 ft
**********************************************
OUTLET CONNECTIVITY
**********************************************
---> Forward Flow Only (Upstream to DnStream)
<---Reverse Flow Only (DnStream to Upstream)
<---> Forward and Reverse Both Allowed
Structure No. Outfall E1, ft
Page 1.01
E2, ft
--------------------------·--------
Weir-XY Points 2 ---> TW 265.250 266.500
Culvert-Circular ---> TW 261.000 266.500
TW SETUP, OS Channel
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 17:10:31 Date: 01-19-1999
Type •.•. Outlet Input Data
Name .•.. ROADWAY1
File ••.. E:\HAESTAD\PONDPACK\PPK6\ASHFORD\SWOBOOA.PPK
Title ••. roadway1
OUTLET STRUCTURE INPUT DATA
Structure ID
Structure Type
# of Openings
= 2
= Weir·XY Points
WEIR X·Y GROUND POINTS
X, ft Elev, ft
.. --------...........................
.00 266.50
60.00 266.00
140.00 265.30
235.10 265.20
271.20 265.30
304.30 265.50
353.30 265.90
406.80 266.50
Lowest Elev. = 265.20 ft
Weir Coeff. 3.000000
Page 1.02
Weir TW effects (Use adjustment equation)
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6·24·97 :053 C~ute Time: 17:10:31 Date: 01-19-1999
Type •••• Outlet Input Data
Name •••• ROADWAY1
File •••. E:\HAESTAD\PONDPACK\PPK6\ASHFORD\SWOBOOA.PPK
Title ••. roadway1
OUTLET STRUCTURE INPUT DATA
Structure ID
Structure Type
No. Barrels
Barrel Diameter
Upstream Invert
Dnstream Invert
Horiz. Length
Barrel Length
Barrel Slope
Culvert-Circular
= 4
= 2.5000 ft
= 261.00 ft
260.80 ft
= 36.50 ft
= 36.50 ft
= .00548 ft/ft
OUTLET CONTROL DATA .••
Mannings n = .0130
Page 1.03
Ke .5000 (forward entrance loss)
Kb = .009217 (per ft of full flow)
Kr =
HW Convergence =
INLET CONTROL DATA .••
Equation form
Inlet Control K =
Inlet Control M =
Inlet Control c
Inlet Control Y
T1 ratio CHW/D) =
T2 ratio (HW/D) =
Slope Factor =
1.0000
.001
.0098
2.0000
.03980
.6700
1.157
1.304
-.500
(reverse entrance loss)
+/-ft
Use unsubmerged inlet control Form equ. below T1 elev.
Use submerged inlet control Form equ. above T2 elev.
In transition zone between unsubmerged and submerged inlet control,
interpolate between flows at T1 & T2 •••
At T1 Elev= 263.89 ft ---> Flow= 27.16 cfs
At T2 Elev= 264.26 ft ---> Flow= 31.05 cfs
TW Structure ID
Structure Type = TW SETUP, OS Channel
FREE OUTFALL CONDITIONS SPECIFIED
CONVERGENCE TOLERANCES •••
Maxilll.lll Iterations= 30
Min. TW tolerance = .01 ft
Max. TW tolerance = .01 ft
Min. HW tolerance = .01 ft
Max. HW tolerance = .01 ft
Min. Q tolerance =
Max. Q tolerance =
S/N: HOMOL0863131 KLING ENGINEERING
.10 cfs
.10 cfs
Pond Pack Ver: 6-24-97 :053 COl1l>lJte Time: 17:10:31 Date: 01-19-1999
Type •••• Individual Outlet Curves
Name •••. ROADWAY1
File •••. E:\HAESTAD\PONDPACK\PPK6\ASHFORD\SWOBODA.PPK
Title ••. roadway1
RATING TABLE FOR ONE OUTLET TYPE
Structure ID = 2 (Weir-XY Points)
Upstream ID (Pond Water Surf ace)
DNstream ID = TW (Pond Outfall)
WS Elev,Device Q Tail Water Notes
Page 1.04
---------------------------------------------------------
WS Elev. Q TW Elev Converge
ft cfs ft +/·ft Computation Messages
261.00 .00 Free Outfall
E < E1= 265.250
261.25 .00 Free Outfall
E < E1= 265.250
261.50 .00 Free Outfall
E < E1= 265.250
261.75 .00 Free Outfall
E < E1= 265.250
262.00 .00 Free Outfall
E < E1= 265.250
262.25 .00 Free Outfall
E < E1= 265.250
262.50 .00 Free Outfall
E < E1= 265.250
262.75 .00 Free Outfall
E < E1= 265.250
263.00 .00 Free Outfall
E < E1= 265.250
263.25 .00 Free Outfall
E < E1= 265.250
263.50 .00 Free Outfall
E < E1= 265.250
263.75 .00 Free Outfall
E < E1= 265.250
264.00 .00 Free Outfall
E < E1= 265.250
264.25 .00 Free Outfall
E < E1= 265.250
264.50 .00 Free Outfall
E < E1= 265.250
264.75 .00 Free Outfall
E < E1= 265.250
265.00 .00 Free Outfall
E < E1= 265.250
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 COfl1'Ute Time: 17:10:31 Date: 01-19-1999
Type .•.. Individual Outlet Curves
Name .••• ROADWAY1
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\SWOBOOA.PPK
Title ••• roadway1
RATING TABLE FOR ONE OUTLET TYPE
Structure ID = 2 CWeir-XY Points)
Upstream ID = (Pond Water Surface)
DNstream ID = TW (Pond Outfall)
WS Elev,Device Q Tail Water Notes
WS Elev. Q TW Elev Converge
ft cf s ft +/-ft Computation Messages
265.20 .00 Free Outfall
E < E1= 265.250
265.25 .78 Free Outfall
Max.H=.05; Max.Htw=free out;; WCft)=65.6D
265.50 54.51 Free Outfall
Max.H=.30; Max.Htw=free out;; WCft)=187.16
265.75 180.25 Free Outfall
Max.H=.55; Max.Htw=free out;; WCft)=246.35
266.00 375.95 Free Outfall
Max.H=.80; Max.Htw=free out;; WCft)=302.22
266.25 653.75 Free Outfall
Max.H=1.05; Max.Htw=free out;; W(ft)=354.51
266.50 1006.77 Free Outfall
Max.H=1.30; Max.Htw=free out;; WCft)=406.80
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 Compute Time: 17:10:31
Page 1.05
Date: 01 -19-1999
Type •.•• Individual Outlet Curves
Name .••• ROADWAY1
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\SWOBODA.PPK
Title ••. roadway1
RATING TABLE FOR ONE OUTLET TYPE
Structure ID = 1 (Culvert-Circular)
Page 1.06
Mannings open channel maxilll.lll capacity: 32.66 cfs
Upstream ID = (Pond Water Surface)
DNstream ID = TW (Pond Outfall)
NUMBER OF BARRELS = 4
EACH FLOW = SUM OF BARRELS x FLOW FOR ONE BARREL
ws Elev,Device Q Tail water Notes
WS Elev. Q TW Elev Converge
ft cfs ft +/-ft C~utation Messages
------------------------------------------
261.00 .00 Free Outfall
Upstream HW & DNstream TW < Inv.El
261.25 1.06 Free Outfall
CRIT.DEPTH CONTROL Vh= .056ft Der= • 166ft CRIT .DEPTH
261.50 4.13 Free Outfall
CRIT.DEPTH CONTROL Vh= • 113ft Der= .329ft CRIT .DEPTH
261.75 9.10 Free Outfall
CRIT.DEPTH CONTROL Vh= . 172ft Der= .492ft CRIT .DEPTH
262.00 15.73 Free Outfall
CRIT.DEPTH CONTROL Vh= .232ft Der= .652ft CRIT .DEPTH
262.25 23.91 Free Outfall
CRIT.DEPTH CONTROL Vh= .294ft Der= .809ft CRIT .DEPTH
262.50 33.49 Free Outfall
CRIT.DEPTH CONTROL Vh= .358ft Der= .963ft CRIT .DEPTH
262.75 44.16 Free Outfall
CRIT.DEPTH CONTROL Vh= .425ft Der= 1.112ft CRIT .DEPTH
263.00 55.84 Free Outfall
CRIT.DEPTH CONTROL Vh= .495ft Der= 1.258ft CRIT .DEPTH
263.25 68.31 Free Outfall
CRIT.DEPTH CONTROL Vh= .569ft Der= 1.398ft CRIT .DEPTH
263.50 81.24 Free Outfall
CRIT.DEPTH CONTROL Vh= .646ft Der= 1.530ft CRIT .DEPTH
263.75 94.51 Free Outfall
BACKWATER CONTROL •• Vh= .729ft hwDi= 1.656ft Lbw= 36.5ft
264.00 109.51 Free Outfall
BACKWATER CONTROL •• Vh= .764ft hwDi= 1.854ft Lbw= 36.5ft
264.25 123.51 Free Outfall
BACKWATER CONTROL •• Vh= .812ft hwDi= 2.031ft Lbw= 36.5ft
264.50 133.23 Free Outfall
INLET CONTROL ••. Subnerged: HW =3.50
S/N: HOHOL0863131 KLING ENGINEERING
Pond Pack Ver: 6-24-97 :053 C~te Time: 17:10:31 Date: 01-19-1999
Type •••• Individual Outlet Curves
Name •••. ROADWAY1
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\S~BODA.PPK
Title ••• roadway1
RATING TABLE FOR ONE OUTLET TYPE
Structure ID = 1 CCulvert·Circular)
Page 1.07
Mannings open channel maxin.in capacity: 32.66 cfs
Upstream ID = (Pond Water Surface)
DNstream ID = TW (Pond Outfall)
NUMBER OF BARRELS = 4
EACH FL~ = SUM OF BARRELS x FL~ FOR ONE BARREL
WS Elev,Device Q Tail Water Notes
I.IS Elev. Q Tl.I Elev Converge
ft cf s ft +/·ft COfl1)utation Messages
--------........................ --------------------------
264. 75 142.00 Free Outfall
INLET CONTROL ••. Submerged: HW =3.75
265.00 150.30 Free Outfall
INLET CONTROL ••• Submerged: HI.I =4.00
265.20 156.59 Free Outfall
INLET CONTROL ••• Submerged: HW =4.20
265.25 158. 12 Free Outfall
INLET CONTROL .•• Submerged: HW =4.25
265.50 165 .61 Free Outfall
INLET CONTROL ••• Submerged: HW =4.50
265.75 172.81 Free Outfall
INLET CONTROL ••• Submerged: HW =4. 75
266.00 179.67 Free Outfall
INLET CONTROL .•• Submerged: HW =5.00
266.25 186.25 Free Outfall
INLET CONTROL ••• Submerged: HW =5.25
266.50 192.64 Free Outfall
INLET CONTROL ••. Submerged: HW =5.50
S/N: HOMOL0863131 KLING ENGINEERING
Pond Pack Ver: 6·24·97 :053 Compute Time: 17:10:31 Date: 01·19·1999
Type •••• Corrposite Rating Curve
Name •••• ROADWAY1
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\SWOBOOA.PPK
Title ••• roadway1
***** COMPOSITE OUTFLOW SUMMARY ****
WS Elev, Total Q Notes
--------Converge -------------------------
Elev. Q TW Elev Error
ft cfs ft +/-ft Contributing Structures
261.00
261.25
261.50
261.75
262.00
262.25
262.50
262.75
263.00
263.25
263.50
263.75
264.00
264.25
264.50
264.75
265.00
265.20
265.25
265.50
265.75
266.00
266.25
266.50
.00 Free Outfall
1.06 Free Outfall
None contributing
1
4.13
9.10
15.73
23.91
33.49
44.16
55.84
68.31
81.24
94.51
109.51
123.51
133.23
142.00
150.30
156.59
158.90
220.11
353.05
555.62
840.00
1199.41
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
Free Outfall
2 +1
2 +1
2 +1
2 +1
2 +1
2 +1
S/N: HOMOL0863131 KLING ENGINEERING
Page 1.08
Pond Pack Ver: 6-24-97 :053 Corrpute Time: 17:10:31 Date: 01-19-1999
T1 ASHFORD SQUARE SUBDIVISION
T2 DEVELOPED CONDITIONS -FIRST PROFILE -5 YR EVENT
T3 DITCH SECTION -EXISTING COND. FILE:CUREXCON.DAT
T4 POST DEVELOPED -ROUTED "CORRECTED" Q FROM POND
J1 2 267.16
J3 110
NC .06 .06 .05 . 1 .3
* * STARTING STATION G-G/STA 0+00 = SECTION IN MOBILE HOME PARK
* PROFILE J1 = 5 YEAR EVENT;
* QT 4 480 615.7 748.6 986.4 326.7
X1 0 8 119 .24 153.29
GR 268 0 266 119 .24 264 127.92 263.05 135.71 264 141
GR 266 153.29 268 301.81 269.2 522.68
*
* STATION F-F/STA 2+80
* X1 280 19 130.6 143.6 235 300 280
GR 272 0 270 100 269 112.8 268 121.8 267 130.6
GR 266 131.5 265 132.1 264 132.8 264 133.5 264 134.2
GR 264 139.9 265 141.1 266 142.4 267 143.6 268 152.8
GR 269 162.6 270 172.4 271 193.4 272 243.4
*
* EJ
T1 SECOND PROFILE -10 YR EVENT
T2
T3
J1 3 267.36
J2 2
* T1 THIRD PROFILE -25 YR EVENT
T2
T3
J1 4 267.53
J2 3
* T1 FOURTH PROFILE -100 YR EVENT
T2
T3
J1 5 267.77
J2 4
* T1 FIFTH PROFILE - 2 YR EVENT
T2
T3
J1 6 266.87
J2 5
ER
CUREXCON.DAT
EXISTING CHANNEL -DEVELOPED FLOIJS -CORRECTED Q F/ POND
PROFILE 1=5YR EVENT; PROFILE 2=10YR EVENT; PROFILE 3=25YR EVENT; PROFILE 4=100YR EVENT; PROFILE 5=2YR EVENT
*-----------------------------------•
j SUMPO j
Interactive SllTITIBry Printout
for MS/PC-DOS micro corrputers
May 1991
-----------------------------------
NOTE -Asterisk(*) at left of profile nllllber
indicates message in SllTITIBry of errors
list
CH SECTION -EXISTING CON
SllTITIBry Printout
SECNO Q CIJSEL VLOB
.00 480.00 267.16 1.20
{si-~ .00 615.70 267.36 1.41
.00 748.60 267.53 1.58
.00 986.40 261.n 1.84
.00 326.70 266.87 .90
* 280.00 480.00 268.81 2.86
p-,(: 280.00 615.70 269.16 3.39
280.00 748.60 269.43 3.82
* 280.00 986.40 269.85 4.40
* 280.00 326.70 268.29 2.08
SllTITIBry of Errors and Special Notes
VCH VROB TOPIJID
4.00 1.20 189.35
4.43 1.41 216.12
4.76 1.58 238.89
5.29 1.84 271.02
3.39 .90 150.52
7.36 2.85 46.34
8.13 3.39 . 53.35
8.78 3.84 59.54
9.73 4.48 68.88
6.30 2.08 36.61
IJARNING SECNO=
IJARNING SECNO=
IJARNING SECNO=
IJARNING SECNO=
IJARNING SECNO=
280.000 PROFILE= 1 KRATIO outside acceptable range
280.000 PROFILE= 2 KRATIO outside acceptable range
280.000 PROFILE= 3 KRATIO outside acceptable range
280.000 PROFILE= 4 KRATIO outside acceptable range
280.000 PROFILE= 5 KRATIO outside acceptable range
K*CHSL
.00
.00
.00
.00
.00
3.39
3.39
3.39
3.39
3.39
CHANNEL AREAS
EXISTING CONDITIONS IMPROVED CONDITIONS
STA 1 +46 ON PROFILE ,...., 100' F j PROPERTY LINE
5703.39 SF 5799.54 SF
AVE=516 SF AVE=525SF
L= 150' I VOL= 77 400 CF L= 150'. VOL= 78750 CF
STA 2 +98 ON PROFILE ,...., 250' F j PROPERTY LINE
4614 .2 1 SF
AVE=419 SF
L=200', VOL=83800 CF
~-
4703 .2 9 SF ---
AVE=445 SF
L=200', VOL=88920 CF
STA 5+06 ON PROF ILE ,...., 450' F j PROPERTY LINE
3768 .06 SF 4189.80 SF
~r~ v-
TOTAL VOLUME,...161200 CF= 3.701 AC-FT TOTAL VOLUME,.., 167750 CF = 3.851 AC-FT
TOTAL INCREASE IN VOLUME
DUE TO CHANNEL IMPROVEMENTS
,.., 6470 CF ,.., 0.15 AC-FT
KUNG ENGINEERING & SURVEYING
BRYAN . TEXAS
T1
T2
T3
T4
J1
J3
NC
ASHFORD SQUARE I DARTMOUTH ADDITION DRAINAGE
PRE DEVELOPED/EXISTING CONDITIONS Q -FIRST PROFILE-2 YR EVENT
EXISTING DITCH SECTION FILE:FIELDATA\EXCONQ1.DAT
CHANNEL THROUGH OAK FOREST MOBILE HOME PARK -EXISTING CONDITIONS
110
.06
2 U6.~
.06 .OS .1 .3
*
*
*
*
STARTING STATION-STA 0+00 = SECTION IN MOBILE HOME PARK 4S0 1 F/PROP.LINE
PROFILE J1 = 2 YEAR EVENT;
QT 6 317.S 469.S 603.8 73S.4 880.9 970.9
X1 0 30 19S.8 229.7
GR 268.7 0 0267.6 20.1 267.6 21 267.6 31.9
GR 267.3 44.8 267.2 70.3 266 .S 114.6 26S.7 1S1
GR 264.7 200.S 262.S 211.4 2S8.9 212.3 260.1 224.1
GR 262.6 234.1 261.6 238 26S.6 238.3 26S.6 238.9
GR 26S.3 242.8 26S.1 244 26S.S 2S8.1 26S.S 2S8.6
GR 26S.4 273.8 26S.6 29S.1 266 29S.6 26S.8 316.7
* * STATION 2+08 = SECTION IN MOBILE HOME PARK 2S0 1 F/PROP.LINE
* X1 208 23 129.4 162 208 170 208
GR 269.6 0 267.8 23.4 267.7 24.3 267.7 34.6
GR 267.4 47.4 266.9 81.7 266.7 113.3 266.3 129.4
GR 263.6 14S.S 263.S 1S0.4 262.4 1S1.4 262.3 1S6.6
GR 267 201.2 267.8 2S2.1 267.7 281.4 267.S 282.4
GR 267.6 309.1 267.7 309.9 268.4 347.9
*
267.2
264.9
262.6
264.7
26S.2
266.6
267.4
264.8
26S.1
267.9
* STATION 3+60 = SECTION IN MOBILE HOME PARK APPROX. 100' FROM PROP.LINE
X1 360 24 1S2.4 193.0 130 160 152
GR 270.4 0 269.S 3S.8 269.3 37 269.3 49 .4 268 .9
GR 269.1 83.S 268.4 106.1 268.4 110. 7 267.S 137.3 267.4
GR 264.3 169.6 26S.3 171.9 26S.4 178.0 264.4 181.4 266.S
GR 269.1 240.7 270.6 294.0 271.3 321.0 271.0 321.S 271.0
GR 271.2 3S4.0 271.1 367.1 272.0 400.9 272.0 4S3.0
*
* EJ
T1 SECOND PROFILE -S YR EVENT
T2
T3
J1 3 267.1S
J2 2
* T1 THIRD PROFILE -10 YR EVENT
T2
T3
J1 4 267.3S
J2 3
* T1 FOURTH PROFILE -25 YR EVENT
T2
T3
J1 s 267.S1
J2 4
* T1 FIFTH PROFILE -SO YR EVENT
T2
T3
J1 6 267.67
J2 5
* T1 SIXTH PROFILE -100 YR EVENT
T2
T3
J1 7 267.76
J2 6
ER
43.9
19S.8
229.7
239.1
272.8
344.1
46.3
140.6
162
29S.7
63.2
1S2.4
193.0
340.4
BASED ON PRE-DEVELOPMENT FLOWRATES
BASED ON FIELD OBTAINED CROSS SECTIONS THROUGH MOBILE HOME PARK
ORIGINALLY RUN 09/22/98
*-----------------------------------* j s u • p 0 j
Interactive SU1111ary Printout
for MS/PC-DOS micro COf11)Uters
May 1991
-----------------------------------
NOTE -Asterisk C*) at left of profile nunber
indicates message in sU1111ary of errors
list
STING DITCH SECTION
SU1111ary Printout
SECNO Q CWSEL VLOB VCH VROB TOPWID
.00 317.50 266.85 .41 1.16 .50 251.65
.00 469.50 267.15 .56 1.49 .66 270.63
.00 603.80 267.35 .66 1. 74 .80 304.70
.00 735.40 267.51 .76 1.96 .93 309.50
.00 880.90 267.67 .86 2.19 1.05 325.28
.00 970.90 267.76 .92 2.31 1.13 326.92
* 208.00 317.50 266.88 .58 3.05 1.24 114.44 * 208.00 469.50 267.19 .93 3.71 1.62 153. 18
* 208.00 603.80 267.41 1.19 4.14 1.85 182.69
* 208.00 735.40 267.60 1.42 4.47 2.00 206 .20
* 208.00 880.90 267.79 1.62 4.n 2.07 2n.51 * 208.00 970.90 267.90 1.73 4.90 2.06 296.92
* 360.00 317.50 267.47 .24 3.86 1.29 70.01
360.00 469.50 267.89 1.10 4.47 1.66 92.87
360.00 603.80 268.17 1.48 4.90 1.92 106.46
360.00 735.40 268.39 1.76 5.31 2.14 116.86
360.00 880.90 268.61 2.04 5.67 2.34 132.39
360.00 970.90 268.73 2.19 5.88 2.45 138.22
SU1111ary of Errors and Special Notes
\/ARNING SECNO=
\/ARNING SECNO=
\/ARNING SECNO=
\/ARNING SECNO=
\/ARNING SECNO=
\/ARNING SECNO=
\/ARNING SECNO=
208.000 PROFILE= 1 KRATIO outside acceptable range
208.000 PROFILE= 2 KRATIO outside acceptable range
208.000 PROFILE= 3 KRATIO outside acceptable range
208.000 PROFILE= 4 KRATIO outside acceptable range
208.000 PROFILE= 5 KRATIO outside acceptable range
208.000 PROFILE= 6 KRATIO outside acceptable range
360.000 PROFILE= 1 KRATIO outside acceptable range
K*CHSL
.00
.00
.00
.00
.00
.00
16.35
16.35
16.35
16.35
16.35
16.35
13.16
13.16
13.16
13.16
13.16
13.16
T1 ASHFORD SQUARE I DARTMOUTH ADDITION DRAINAGE
T2 DEVELOPED CONDITIONS "DESIGN" Q FROM POND -FIRST PROFILE - 2 YR EVENT
T3 EXISTING DITCH SECT-SEDIMENT CLEANED @ SECT 360 FILE:FIELD\EXCON2Q2.DAT
T4 POST DEVELOPED -ROUTED Q FROM POND
J1 2 266.85
J3 110
NC .06 .06 .05 • 1 .3
*
* STARTING STATION-STA 0+00 = SECTION IN MOBILE HOME PARK 450 1 F /PROP. LI NE
* PROFILE J1 = 100 YEAR EVENT;
* QT 6 318 .1 469 603.3 734.9 880.4 970.5
* X1 0 30 195.8 229.7
GR 268.7 0 0267.6 20.1 267.6 21 267.6 31.9 267.2 43.9
GR 267.3 44.8 267.2 70.3 266.5 114.6 265.7 151 264.9 195.8
GR 264. 7 200.5 262.5 211.4 258.9 212.3 260.1 224.1 262.6 229.7
GR 262.6 234. 1 261.6 238 265.6 238.3 265.6 238.9 264.7 239.1
GR 265.3 242.8 265.1 244 265.5 258.1 265.5 258.6 265.2 272.8
GR 265.4 273.8 265.6 295.1 266 295.6 265.8 316.7 266.6 344.1
*
* STATION 2+08 = SECTION IN MOBILE HOME PARK 250' F/PROP.LINE
* X1 208 23 129.4 162 208 170 208
GR 269.6 0 267.8 23.4 267.7 24.3 267.7 34.6 267.4 46.3
GR 267.4 47.4 266.9 81.7 266.7 113.3 266.3 129.4 264.8 140.6
GR 263.6 145.5 263.5 150.4 262.4 151.4 262.3 156.6 265.1 162
GR 267 201.2 267.8 252.1 267.7 281.4 267 .5 282.4 267.9 295.7
GR 267.6 309.1 267.7 309.9 268.4 347.9
*
* STATION 3+60 = SECTION IN MOBILE HOME PARK APPROX. 100' FROM PROP.LINE
X1 360 24 152.4 193.0 130 160 152
GR 270.4 0 269.5 35.8 269.3 37 269.3 49.4 268.9 63.2
GR 269.1 83.5 268.4 106.1 268.4 110. 7 267.5 137.3 267.4 152.4
GR 264.3 169.6 262.4 171.9 262.4 178.0 262.4 181.4 266.5 193.0
GR 269. 1 240.7 270.6 294.0 271.3 321.0 271.0 321.5 271.0 340.4
GR 271.2 354.0 271.1 367. 1 272.0 400.9 272.0 453.0
*
*
* EJ
T1 SECOND PROFILE - 5 YR EVENT
T2
T3
J1 3 267.15
J2 2
* T1 THIRD PROFILE -10 YR EVENT
T2
T3
J1 4 267.35
J2 3
*
T1 FOURTH PROFILE -25 YR EVENT
T2
T3
J1 5 267.51
J2 4
*
T1 FIFTH PROF! LE -50 YR EVENT
T2
T3
J1 6 267.67
J2 5
* T1 SIXTH PROFILE -100 YR EVENT
T2
T3
J1 7 267.76
J2 6
ER
BASED ON DEVELOPED FLOWRATES -OUTFLOW F/ "DESIGN" POND
BASED ON FIELD OBTAINED CROSS SECTIONS THROUGH MOBILE HOME PARK W/ SEDIMENT CLEANING @ SECT 360 C-100 F/ PL)
ORIGINALLY RUN 09/22/98
*-----------------------------------* j s u • p 0 j
Interactive Sllllll8ry Printout
for MS/PC-DOS micro computers
May 1991
-----------------------------------
NOTE -Asterisk(*) at left of profile nLmber
indicates message in Sllllll8ry of errors
list
STING DITCH SECT-SEDIMEN
Summary Printout
SECNO Q CWSEL VLOB VCH VROB TOPWID
.00 318.10 266.85 .42 1.17 .so 251.65
.00 469.00 267.15 .56 1.49 .66 270.63
.00 603.30 267.35 .66 1.74 .80 304.70
.00 734.90 267.51 .76 1.96 .92 309.50
.00 880.40 267.67 .86 2.18 1.05 325.28 .oo 970.50 267.76 .92 2.31 1.13 326.92
* 208.00 318.10 266.88 .58 3.06 1.24 114.47
* 208.00 469.00 267. 19 .93 3.70 1.62 153. 16
* 208.00 603.30 267.41 1.18 4.14 1.85 182.67
* 208.00 734.90 267.60 1.42 4.47 2.00 206.17
* 208.00 880.40 267.79 1.62 4.77 2.07 277.43
* 208.00 970.50 267.90 1.73 4.90 2.06 296.91
360.00 318.10 267.28 .oo 2.79 .64 54.18
360.00 469.00 267.70 .51 3.49 .98 83.64
360.00 603.30 267.99 .87 4.02 1.23 97.37
360.00 734.90 268.22 1.13 4.47 1.44 108.42
360.00 880.40 268.44 1.37 4.91 1.65 123.82
360.00 970.50 268.56 1.52 5.15 1.77 129.91
Summary of Errors and Special Notes
WARNING SECNO=
WARNING SECNO=
WARNING SECNO=
WARNING SECNO=
WARNING SECNO=
WARNING SECNO=
208.000 PROFILE= 1 KRATIO outside acceptable range
208.000 PROFILE= 2 KRATIO outside acceptable range
208.000 PROFILE= 3 KRATIO outside acceptable range
208.000 PROFILE= 4 KRATIO outside acceptable range
208.000 PROFILE= 5 KRATIO outside acceptable range
208.000 PROFILE= 6 KRATIO outside acceptable range
K*CHSL
.00
.00
.00
.00
.00
.00
16.35
16.35
16.35
16.35
16.35
16.35
.66
.66
.66
.66
.66
.66
T1 ASHFORD SQUARE I DARTMOUTH ADDITION DRAINAGE
T2 DEVELOPED CONDITIONS CORRECTED Q FROM POND -FIRST PROFILE - 2 YR EVENT
T3 EXISTING DITCH SECT-SEDIMENT CLEANED @ SECT 360 FILE:FIELD\EXCON2Q3.DAT
T4 POST DEVELOPED -ROUTED Q FROM POND
J1 2 266.87
J3 110
NC .06 .06 .05 • 1 .3
* * STARTING STATION-STA 0+00 = SECTION IN MOBILE HOME PARK 450 1 F /PROP. LI NE
* PROFILE J1 = 100 YEAR EVENT;
* QT 6 326.7 480 615.7 748.6 895.5 986.4
* X1 0 30 195.8 229 .7
GR 268.7 0 0267.6 20.1 267.6 21 267.6 31.9 267.2 43.9
GR 267.3 44.8 267.2 70.3 266.5 114.6 265.7 151 264.9 195.8
GR 264.7 200.S 262.S 211.4 258.9 212.3 260., 224.1 262.6 229.7
GR 262.6 234.1 261.6 238 265.6 238.3 265.6 238.9 264.7 239.1
GR 265.3 242.8 265.1 244 265.5 258.1 265.5 258.6 265.2 272.8
GR 265.4 273.8 265.6 295.1 266 295.6 265.8 316.7 266.6 344.1
*
* STATION 2+08 = SECTION IN MOBILE HOME PARK 250' F/PROP.LINE
* X1 208 23 129.4 162 208 170 208
GR 269.6 0 267.8 23.4 267.7 24.3 267.7 34.6 267.4 46.3
GR 267.4 47.4 266.9 81.7 266.7 113.3 266.3 129.4 264.8 140.6
I GR 263.6 145.5 263.5 150.4 262.4 151.4 262.3 156.6 265.1 162
GR 267 201.2 267.8 252.1 267.7 281.4 267.5 282.4 267.9 295.7
GR 267.6 309.1 267.7 309.9 268.4 347.9
*
* STATION 3+60 = SECTION IN MOBILE HOME PARK APPROX. 100 1 FROM PROP.LINE
X1 360 24 152.4 193 .0 130 160 152
GR 270.4 0 269.5 35.8 269.3 37 269.3 49.4 268.9 63.2
GR 269.1 83.5 268.4 106.1 268.4 110.7 267.5 137.3 267.4 152.4
GR 264.3 169.6 262.4 171.9 262.4 178.0 ·262.4 181.4 266.5 193.0
GR 269.1 240.7 270.6 294.0 271.3 321.0 271.0 321.5 271 .0 340.4
GR 271.2 354.0 271.1 367.1 272.0 400.9 272.0 453.0
*
*
* EJ
T1 SECOND PROFILE -5 YR EVENT
T2
T3
J1 3 267.16
J2 2
* T1 THIRD PROF I LE -10 YR EVENT
T2
T3
J1 4 267.36
J2 3
* T1 FOURTH PROFILE -25 YR EVENT
T2
T3
J1 5 267 .53
J2 4
* T1 FIFTH PROFILE -50 YR EVENT
T2
T3
J1 6 267 .68
J2 5
* T1 SIXTH PROFILE -100 YR EVENT
T2
T3
J1 7 267.77
J2 6
ER
BASED ON DEVELOPED FLOWRATES -OUTFLOW F/ CORRECTED POND
BASED ON FIELD OBTAINED CROSS SECTIONS THROUGH MOBILE HOME PARK W/ SEDIMENT CLEANING @ SECT 360 c-100 1 F/ PL)
*-----------------------------------* j s u ' ' 0 j Interactive Sl.fllllary Printout
for MS/PC-DOS micro c~uters
May 1991
-----------------------------------
NOTE -Asterisk(*) at left of profile nl.lllber
indicates message in Sl.fllllary of errors
list
STING DITCH SECT-SEDIMEN
Sl.fllllary Printout
SECNO Q CWSEL VLOB VCH VROB TOPWID
.00 326.70 266.87 .42 1.19 .51 252.92
.00 480.00 267.16 .57 1.51 .68 271.27
.00 615.70 267.36 .67 1.76 .81 305.00
.00 748.60 267.53 .77 1.98 .94 310.10 .oo 89S.50 267.68 .87 2.21 1.07 32S .46
.00 986.40 267.77 .93 2.34 1.14 327.11
* 208.00 326.70 266.90 .59 3.10 . 1.26 117 .82
* 208.00 480.00 267.2 1 .95 3.76 1.65 154.76
* 208.00 61S. 70 267.43 1. 21 4.19 1.87 183.9S
* 208.00 748.60 267.62 1.44 4.49 . 2 .01 210.30
* 208.00 895.50 267.80 1.64 4.81 2.08 283.74
* 208 .00 986.40 267 .91 1.75 4 .94 2.07 298.70
360.00 326.70 267.31 .00 2.83 .66 S4.87
360.00 480.00 267.72 .SS 3.54 1.00 84.75
360.00 61S.70 268.01 .89 4.06 1.2S 98.43
360.00 748.60 268.24 1.1S 4 .S1 1.46 109 .S3
360.00 89S.50 268.46 1.40 4.95 1.67 124.86
360.00 986.40 268.S8 1.S5 5.20 1.79 130.91
Sl.fllllary of Errors and Special Notes
WARNING SECNO=
WARNING SECNO=
WARNING SECNO=
WARNING SECNO=
WARNING SECNO=
WARNING SECNO=
208.000 PROFILE= 1 KRATIO outside acceptable range
208.000 PROFILE= 2 KRATIO outside acceptable range
208.000 PROFILE= 3 KRATIO outside acceptable range
208.000 PROFILE= 4 KRATIO outside acceptable range
208.000 PROFILE= 5 KRATIO outside acceptable range
208.000 PROFILE= 6 KRATIO outside acceptable range
K*CHSL
.00
.00
.00
.00
.00
.00
16.3S
16.35
16.35
16.35
16.3S
16.3S
.66
.66
.66
.66
.66
.66
T1 ASHFORD SQUARE I DARTMOUTH ADDITION DRAINAGE
T2 DEVELOPED CONDITIONS CORRECTED Q FROM POND -FIRST PROFILE - 2 YR EVENT
T3 CHANNEL IMPRVMNTS TO DITCH SECTION FILE:FIELD\CURCHMP.DAT
T4 POST DEVELOPED -ROUTED Q FROM POND THROUGH DESIGN CHANNEL SECTION
J1 2 266.8
J3 110
NC .06 .06 .05 • 1 .3
*
* STARTING STATION-STA 0+00 = SECTION IN MOBILE HOME PARK 450° F /PROP. LI NE
* PROFILE J1 = 100 YEAR EVENT;
* QT 6 326.7 480 615.7 748.6 895.5 986.4
* I X1 0 30 195.8 229.7
CI 215 261 .028 4 4 -4
GR 268.7 0 0267.6 20.1 267.6 21 267.6 31.9 267.2 43.9
GR 267.3 44.8 267.2 70.3 266.5 114.6 265.7 151 264.9 195.8
GR 264.7 200.5 262.5 211.4 258.9 212.3 260.1 224.1 262.6 229.7
GR 262.6 234 .1 261.6 238 265.6 238.3 265.6 238.9 264.7 239.1
GR 265.3 242.8 265.1 244 265.5 258.1 265.5 258.6 265.2 272.8
GR 265.4 273.8 265.6 295.1 266 295.6 265.8 316.7 266.6 344.1
*
* STATION 2+08 = SECTION IN MOBILE HOME PARK 250° F/PROP.LINE
* X1 208 23 129.4 162 208 170 208
CI 154 262.04 .028 4 4 -4
GR 269.6 0 267.8 23.4 267.7 24.3 267.7 34.6 267.4 46.3
GR 267.4 47.4 266.9 81.7 266.7 113.3 266.3 129.4 264.8 140.6
GR 263.6 145.5 263.5 150.4 262.4 151.4 262.3 156.6 265.1 162
GR 267 201.2 267.8 252.1 267.7 281.4 267.5 282.4 267.9 295.7
GR 267 .6 309.1 267.7 309.9 268.4 347.9
*
* STATION 3+60 = SECTION IN MOBILE HOME PARK APPROX. 100' FROM PROP.LINE
X1 360 24 152.4 193.0 130 160 152
CI 176 262.8 .028 4 4 -4
GR 270.4 0 269.5 35.8 269.3 37 269.3 49.4 268.9 63.2
GR 269 .1 83.5 268.4 106.1 268.4 110.7 267.5 137.3 267.4 152.4
GR 264.3 169.6 262 171.9 262 178.0 262 181.4 266.5 193.0
GR 269.1 240.7 270.6 294.0 271.3 321.0 271.0 321.5 271.0 340.4
GR 271.2 354 .0 271.1 367.1 272.0 400 .9 272.0 453.0
*
*
* EJ
T1 SECOND PROFILE -5 YR EVENT
T2
T3
J1 3 267. 15
J2 2
* T1 THIRD PROFILE -10 YR EVENT
T2
T3
J1 4 267.39
J2 3
* T1 FOURTH PROFILE -25 YR EVENT
T2
T3
J1 5 267.57
J2 4
* T1 FIFTH PROFILE -50 YR EVENT
T2
T3
J1 6 267.68
J2 5
* T1 SIXTH PROFILE -100 YR EVENT
T2
T3
J1 7 267.77
J2 6
ER
BASED ON DEVELOPED FLO\JRATES · OUTFLOW F/ CORRECTED POND
BASED ON FIELD OBTAINED CROSS SECTIONS THROUGH MOBILE HOME PARK AS MODIFIED BY CHANNEL IMPROVEMEN
*-----------------------------------*
j s u • p 0 j
Interactive Sllllllary Printout
for MS/PC -DOS micro COf1l'.>Uters
May 1991
-----------------------------------
NOTE -Asterisk (*) at left of profile nl.lllber
indicates message in sllllllary of errors
list
NNEL IMPRVMNTS TO DITCH
S1.111118ry Printout
SECNO Q CWSEL VLOB VCH VROB TOPWID K*CHSL
.00 326.70 266 .80 .33 1.61 .40 248.48 .00
.00 480.00 267.15 .44 2.03 .53 270.63 .00
.00 615.70 267.39 .52 2.36 .63 305.90 .00
.00 748.60 267.57 .60 2.66 .73 311.30 .00
.00 895.50 267.68 .69 3 .04 .84 325.46 .00
.00 986.40 267.77 .74 3 .24 .90 327 .11 .00
* 208.00 326.70 266.79 .28 2.85 .52 97 .86 5.00
* 208.00 480.00 267.13 .46 3.61 .73 143.01 5.00
* 208.00 615.70 267.35 .62 4.17 .89 173.25 5.00
* 208.00 748.60 267.52 .77 4.(i8 1.01 194.04 5.00
* 208.00 895.50 267.62 .92 5.36 1.15 208.31 5.00
* 208.00 986.40 267.70 1.02 5.69 1.22 234.65 5.00
* 360.00 326.70 266.88 .00 3.95 .35 42.28 5.00
* 360.00 480.00 267.23 .00 5.03 .64 50.30 5.00
* 360.00 615.70 267.47 .15 5.81 .90 68 .45 5.00
* 360.00 748.60 267.63 .48 -6.61-" 1.09 80.15 5.00
* 360.00 895.50 267. 73 .72 7.57 1.29 85 .21 5 .00
* 360.00 986.40 267.80 .86 8.10 1.41 88.57 5.00
S1.111118ry of Errors and Special Notes
WARNING SECNO= 208.000 PROFILE = 1 KRATIO outside acceptable range
WARNING SEC NO= 208.000 PROFILE= 2 KRATIO outside acceptable range
WARNING SECNO= 208.000 PROFILE= 3 KRATIO outside acceptable range
WARNING SECNO= 208.000 PROFILE= 4 KRATIO outside acceptable range
IJARNING SECNO= 208.000 PROFILE= 5 KRATIO outside acceptable range
IJARNING SECNO= 208 .000 PROFILE= 6 KRATIO outside acceptable range
IJARNING SECNO= 360.000 PROFILE= 1 KRATIO outside acceptable range
IJARNING SECNO= 360.000 PROFILE= 2 KRATIO outside acceptable range
IJARNING SECNO= 360.000 PROFILE= 3 KRATIO outside acceptable range
IJARNING SECNO= 360.000 PROFILE= 4 KRATIO outside acceptable range
IJARNING SECNO= 360.000 PROFILE= 5 KRATIO outside acceptable range
IJARNING SECNO= 360.000 PROFILE= 6 KRATIO outside acceptable range
APPENDIX3
DETENTION POND
OUTFALL CHANNEL MODIFICATIONS
lPROPOSlED lRlEVIBXON
TO
DETJENTION POND OU1FALJL SCALE: 1":z10'
ADD ITIONAL RIP-RAP
MIN 50# PIECES PLACED
PER OWNER'S REQUIREMEN TS
20-JANUAJRY, 1999
/ I ~
15'
MIN .
>
' EXISTING GROUTED
CONC . RIP-RAP
ENERGY DISSIPATOR
6 " D~~#4 BAR
1 EA . QUAD
/
.. \)\!>-')..
#4 BARS
3" CL 1
......, 2 '
"' 1 8"
PRELIMINARY DRAINAGE REPORT
FOR
Lots 2,3,4,5,6,7, Block "C" & Lots 1,2,3,4,5,6, Block "D"
Ashford Square Re-Subdivision
Morgan Rector Survey, A-46
College Station, Brazos County, Texas
06-January, 1998
PREPARED BY:
Kling Engineering & Surveying
4103 Texas Avenue, Suite 212
Bryan , TX 77802
(409)846-6212
PRELIMINARY DRAINAGE REPORT
for
Lots 2,3,4,5,6,7, Block "C"
&
Lots 1,2,3,4,5,6, Block "D"
Ashford Square Re-Subdivision
Morgan Rector Survey, A-46
College Station, Brazos County, Texas
06-January, 1998
GENERAL LOCATION & DESCRIPTION:
The proposed area to be developed is within the Ashford Square Subdivision
located adjacent to the southeast side of Southwest Parkway approximately 135 feet east
of the Texas Avenue (SH 6-Business) and Southwest Parkway intersection (see Appendix
1: "General Location Map"). Private, center drain, concrete alleys comprise the existing
means of vehicle circulation as well as stormwater conveyance throughout the subdivision.
A grate inlet collects water from the alleys and releases to an existing channel via 2-36"
concrete pipes. Currently, the lots are vacant. Existing ground cover consists of grasses
and a few trees . This site is not within the 100 year floodplain according to the Flood
Insurance Rate Map for Brazos County, Texas and Incorporated Areas, Community No.
480083, Panel No. 0144C, effective date: July 2, 1992 (see Appendix 2: "Flood
Insurance Rate Map"). Surrounding developments include a mobile home park to the
south and a commercial shopping center to the east. Proposed improvements include the
re-subdivision of the lots into 19 lots zoned for duplex dwellings . The center drain alley
section will be removed and replaced with a standard crown, 28 foot back to back curb
and gutter street section . The grate inlet and associated pipes will be removep and
replaced with a grassed swale to convey stormwater to the channel.
DRAINAGE BASIN & SUB-BASINS:
The primary drainage basin for this area is the Bee Creek drainage basin . The site
drains southeast to an existing open ditch section witch ultimately discharges into the Bee
Creek main channel. The site area to be studied is included in 17.055 acres comprising the
majority of the Ashford Square Subdivision (see Appendix 3: "Drainage Areas" SB-I).
The existing ditch has an upstream contributing drainage area of approximately 121.256
acres which include -91.178 acres of developed area and -30.078 acres of undeveloped
grassy areas (see Appendix 3 : "Drainage Areas" SB-II). Sub-basins were delineated
using the recent City of College Station topographic maps .
DRAINAGE DESIGN CRITERIA:
An analysis of existing conditions was made to determine design constraints. The
flow to the existing drainage channel from SB-II was determined using the SCS Unit
Hydrograph Method. Water surface elevations were computed using Manning's Equation .
The SCS Unit Hydrograph Method was also used to determine pre and post -developed
runoff from the site area SB-1. The hydrographs for SB-II and SB-I were combined at a
common point in the channel yielding a total pre and post developed hydrograph. Street
flow within the subdivision was determined using the Rational Method . Depth of flow
was determined using Manning's Equation. The 2 -100 year events will be analyzed . Due
to existing conditions of the channel flow, detention will not be provided . A discussion of
existing and post-developed conditions follows .
DRAINAGE ANALYSIS AND DESIGN:
EXISTING CONDITIONS :
The existing channel adjacent to the development has a significant upstream
drainage area. A point of evaluation along the channel immediately downstream of the
development was chosen to enable the combination of the development's hydrograph to
the sub-basin for the channel hydrograph . Existing conditions for the channel and sub-
basins, SB-I and SB-II, were obtained from the City of College Station topographic and
aerial photo maps . The following table summarizes the sub-basin characteristics (see
Appendix 4 "Hydrologic Calculations" for computation).
Table 1
Sub-Basin Total Area (acre) Avg. CN Tc (Min)
SB-1 pre 17.055 89 10
SB-1 post 17 .055 91 10
SB-2 121,256 87 33
Cross sections along the channel were taken adjacent to the site and water surface
elevations were determined (see Appendix 3 "Drainage Areas" for cross section location).
The following table summarizes the results for the 100 year event (see Appendix 4 and 5
for hydrologic and hydraulic computation).
Table 2
Cross WSEL (ft) Top Width Depth (ft) Q100 (cfs) Velocity
Section (ft) (ft/s)
D-D 274 106 .2 4 .8 890 5.4
d'-d' 273 .7 167 .7 4 .5 890 3.2
E-E 272.2 228 .6 6.2 959 .3 2 .9
F...,F .. -. 270 .8 132 .7 7 .8 959.3 3.9
G-G 267 .8 268 4 .7 959 .3 3 .05
The water surface elevations for pre-developed conditions were used to delineate a 100
year area of flooding and is depicted on the drainage exhibit in Appendix 3 . Flooding
occurs on the immediate site area as well as down stream in the mobile home park. Due
the cross sectional geometry, at section E-E the water surface elevation did not drastically
decrease. The 5 through 25 year water surface elevations are 271.5, 271.7, and 271.9
respectively with the 100 year water surface elevation being 272.2. This factor limits the
flow line at which drainage infrastructure can be placed and still be functional.
Additionally, the southmost new street to be constructed has to tie in elevation to existing
pavement within the subdivision limiting the slope and carrying capacity of the road
section. Although no vehicular traffic will use this intersection, current runoff drains
down this street and to the existing channel via existing concrete pipes.
PROPOSED CONDITIONS :
DRAINAGE
Under proposed conditions the curve number for the subdivision increases from 89
to 91 as referenced in table 1 above . The resulting increase in peak stormwater runoff for
each storm event is summarized below for both individual sub-basin and combined sub-
basin hydrographs .
Table 3
Storm Return SB-1 SB-1 Combined Combined
Qprc (cfs) Qpost (cfs) Qpre (cfs) Qpost (cfs)
2 72 .26 75.53 311.84 312.96
5 104 .29 107 .33 462 .32 463 .33
10 132.44 135 .25 595.42 596.34
25 159.98 162 .57 725 .88 726 .73
50 190.39 192 .77 870 .03 870 .80
100 209.22 211.48 959.28 960 .00
The following two graphs depict the hydrograph addition for pre and post developed
conditions at the 100 year event.
RUNOFFHYDROGRAPHS
SCS UNIT HYDROGRAPH METHOD
1100 -.---~~~~~~~~~~~~~~~~~~~--,
1000 ································································································································································································································································
900 ··················································································· ...................... ···············································································································································
ADDEDHYDROGRAPHPEAK
800 ··· SB-2 PEAK ··········· ··························· Q=959 .3cfs@ 12.15 hrs ··············································
_ 700 ... Q=890 cfs @ 12.2 hrs ................................................................................................................................................................................... . J!!
(.) .._. 600 ·················································································· ........................................... .
3: 500 0
ASHFORD SQUARE
................................................................................. ..... ........................................ PRE -DEVELOPED CONDITIONS
..J
LL 400 ························································································· ··································································································································································
SB-1 PEAK 300 ·· Q=209cfs @ 12 .0 hrs ·············· ········· ································································································································································
200
100
0 ---6 7.75 9.5 11.25 13 14.75 16.5 18 .25 20 21.75 23 .5
TIME (hrs)
J-SB-2 ---SB-1 PRE -.k-ADDED HYDR0.1
..-..
J!?
CJ .._..
3:
0
..J
LL
1100
1000
900
800
700
600
500
400
RUNOFFHYDROGRAPHS
SCS UNIT HYDROGRAPH METHOD
................................................................................................................... ADDED HYDROGRAPH PEAK ........................................ .
SB-2 PEAK
Q=890cfs@ 12 .2 hrs
Q=960 .0cfs@ 12 .15 hrs
·················································································· ···· ········································ ASHFORD SQUARE
................................................................................. ..... ........................................ POST DEVELOPED CONDITIONS
SB-1 PEAK 300 ·· Q=21 lcfs@ 12 .0 hrs ·············· ········· ································································································································································
200
100
0 --6 7.75 9.5 11.25 13 14.75 16.5 18.25 20 21.75 23.5 .
TIME (hrs)
1--SB-2 ---SB-1 POST _.._ ADDED HYDRO. ,
In order to utilize the total site area for development, fill will need to be placed on the lots
that presently get inundated . Fill heights were determined based on pre developed water
surface elevations . Fill elevations for the re-subdivided lots are as follows :
Lot 3RBlkD
Lot 4R "
Lot SR "
Lot 6R "
Lot 7R "
Lot 8R "
Lot 9R "
Lot lOR "
elev. = 275.5
elev. = 275.0
elev. = 274 .25
elev.= 273 .5
elev.= 273.5
elev.= 273.0
elev.= 273 .0
elev.= 273 .0
The proposed fill will alter the channel cross section . The new "fill" sections were
modeled using the 100 year post developed flow rates and resulting channel characteristics
tabulated as shown below .
Table 4
Cross WSEL Top Width Depth QlOO Velocity
Section
D-D (filled) 275.0 69.48 5.0 890 6.43
d'-d' (filled) 273 .8 101.1 4 .6 890 3.9
E-E (filled) 272 .6 95 .5 6.6 960 4 .1
F-F (post) 270 .8 132 .8 7.8 960 3.9
G-G (post) 267 .8 268 .1 4.7 960 3.1
The maximum increase in water surface elevation of 0.48 feet occurs at section E-E.
Maximum increase in velocity of 1.19 f7s occurs at this same section. The section just off-
site, section F-F, returns to original pre-developed flow conditions. Section G-G inside of
the mobile home park experiences no change in flow characteristics from the post
developed conditions .
STREETS:
As shown in Appendix 3, the 100 year water surface elevation of the channel
causes water to back up into the existing alley section. Due to the constraint of matching
existing pavement with the new street section, this condition is not be able to be alleviated.
The sbuth:.most street is the most critical with respect to slope and carrying capacity.
Currently the alley section has a slope of 0 .6%. The new street will have approximately
the same slope. The right of way from the back of curb is to be graded on a 5 : 1 up hill
slope to prevent stormwater from the subdivision from exceeding the right of way width
during the 100 year event. This will provide approximately l' of freeboard for the 100
year event. Flow rates for street runoff were determined using the Rational Method. The
following table summarizes street flows and conditions for the southmost street (see
Appendix 4 & 5 for hydrologic and hydraulic computation).
Table 5
Storm Return Q (cfs) Depth@ curb (ft) Top Width
10 81.6 0.78 30 .78
25 93 .2 0.82 31.21
100 110.0 0 .88 31.79
The water surface for the 10 year event exceeds the top of curb for this southmost street
by 0 .28 feet, therefore a variance request will be submitted. The 100 year flow is
contained within the proposed 40' right of way with a depth at the centerline of the road
being 0.38 feet and depth at the curb flowline being 0 .88 feet. These depths are valid until
back water from the channel are encountered the lowest comer of the street. At this
point, water depths in the street will rise to -2.1 feet corresponding to a creek channel
water surface elevation of272.64. A grassed swale will be provided to guide flow from
the subdivision to the ditch channel section. This swale will be in the existing drainage
easement and be at a 1.3% slope. The section will have an 8' flat bottom with 3: 1 side
slopes. Carrying capacity of this channel would be 111 cfs, however, due to the creek
backwater this capacity will be limited .
CONCLUSIONS:
The drainage situation surrounding this development is marginal. Flooding occurs
on site and immediately downstream within the mobile home park. The development of
the site area was analyzed using SCS methods in conjunction with Manning's Equation to
determine water surface elevations and impact. Addition of the sub-basin hydrographs
show that there is a minimal increase, +O. 7 cfs, in pre and post developed peak discharge
through the channel. This supports releasing stormwater runoff from the site undetained
thereby not aggravating peak flow flooding conditions. Although these results appear to
be conducive to developing without major modification to the drainage channel, channel
and slope realignment should be considered to bring the channel into a more uniform
section that might be able to handle the existing flow at lower water surface elevations . ..... _,,,,
-~~OF ~~'''' -~'I"'~~ ~ ;'It'}..,, . ... !t. . t .. j_ \.~ t' a -'-.l!.~WOS r-\-. ..J ~··· ~1! ,,~~At'i.~--..:' ,,~
APPENDICES
1) General Location Map
2) Flood Insurance Rate Map -FEMA
3) Drainage Areas
4) Hydrologic Calculations
5) Hydraulic Calculations
6) Rep lat
APPENDIX 1
GENERAL LOCATION MAP
N.T.S.
KUNG ENGINEERING &: SURVEY ING
BRYAN , TEXAS
.. ··
·. < ...
·. /
·· ...
.......
..... ..·
SUBJECT
TRACT
r:.... . .... .... ·· ... ·· ·· ....
·· ...
::<
..• ·•·
APPENDIX2
FLOOD INSURANCE RATE MAP-FEMA
APPENDIX3
DRAINAGE AREAS
APPENDIX4
HYDROLOGIC CALCULATIONS
Job File: E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Rain Dir : J:\HAESTAD\PPK6\UTIL\
==========================
JOB TITLE
==========================
ASHFORD SQUARE RESUBDIVISION PROJECT
MORGAN RECTOR SURVEY, A·46
COLLEGE STATION, BRAZOS COUNTY, TEXAS
DRAINAGE & DETENTION
S/N: HOMOL0120356 KLING ENG I NEERING & SURVEYING
Pond Pack Ver: 5·05 -97 :050 Compute Time: 09:52:51 Date: 01 -08-1998
Table of Contents
Table of Contents
******************** NETYORK SUMMARIES *********************
PRE ••••••••••••• Pre •• 2
Executive Sl.mllary (Nodes) .......... 1.01
Executive Sl.mllary (Links) .......... 1.02
PRE ••••••••••••• Pre •• 5
Executive Sl.mllary (Nodes) .......... 1.03
Executive Sl.mllary (Links) .......... 1.04
PRE ••••••••••••• Pre.10
Executive Sl.mllary (Nodes) .......... 1.05
Executive Sl.mllary (Links) .......... 1.06
PRE ••••••••••••• Pre.25
Executive Sl.mllary (Nodes) .......... 1.07
Executive Sl.mllary (Links) .......... 1.08
PRE ••••••••••••• Pre.SO
Executive Sl.mllary (Nodes) .......... 1.09
Executive Sl.mllary (Links) .......... 1.10
PRE ••••••••••••• Pre100
Executive Sl.mllary (Nodes) .......... 1.11
Executive Sl.mllary (Links) .......... 1.12
********************** CN CALCULATIONS *********************
SB-2-EX-CON ••••• Runoff CN-Area ..................... 2.01
SB-I PRE •••••••• Runoff CN-Area ..................... 2.02
******************** RUNOFF HYDROGRAPHS ********************
SB-2 EX-CON ••••• Pre •• 2
SCS Unit Hyd. Sl.mllary •••••••••••••• 3.01
SB-2 EX-CON ••••• Pre •• 5
scs Unit Hyd. Sl.llJTlary •••••••••••••• 3.02
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date: 01-08-1998
Table of Contents ii
Table of Contents (continued)
SB-2 EX-CON ••••• Pre.10
SCS Unit Hyd. SlJTlllary •••••••••••••• 3.03
SB-2 EX-CON ••••• Pre.2S
SCS Unit Hyd. SlJTlllary •••••••••••••• 3.04
SB-2 EX-CON ••••• Pre.SO
SCS Unit Hyd. SlJTlllary •••••••••••••• 3.0S
SB-2 EX-CON ••••• Pre100
SCS Unit Hyd. SlJTlllary •••••••••••••• 3.06
SB-I PRE •••••••• Pre •• 2
SCS Unit Hyd. SlJTlllary •••••••••••••• 3.07
SB-I PRE •••••••• Pre •• S
SCS Unit Hyd. SlJTlllary •••••••••••••• 3.08
SB-I PRE •••••••• Pre.10
SCS Unit Hyd. SlJTlllary •••••••••••••• 3.09
SB-I PRE •••••••• Pre.2S
SCS Unit Hyd. SlJTlllary •••••••••••••• 3.10
SB-I PRE •••••••• Pre.SO
SCS Unit Hyd. SlJTlllary •••••••••••••• 3.11
SB-I PRE •••••••• Pre100
SCS Unit Hyd. SlJTlllary •••••••••••••• 3.12
Type •••• Executive S1..1m1ary (Nodes)
Name •••• PRE
File •..• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Pre •• 2
NETWORK SUMMARY ·· NODES
Page 1.01
Event: 2 yr
CTrun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Pre •. 2
Description: 2 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 2 yr
Total Rainfall Depth= 4.4210 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max WSEL
Node ID Type ac-ft Trun. hrs cfs ft
-----------------------------------------------------
POINT OF EVAL. JCT 35. 152 12. 1500 311.84
SB-1 PRE AREA 4.577 12.0000 72.26
SUB-2 .EX·CON AREA 30.575 12.2000 289.36
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date: 01-08-1998
Type .••• Executive Sl.lllll8ry Clinks)
Name ••.• PRE
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm .•• Type!! 24hr Tag: Pre •• 2
NETWORK SUMMARY ·· LINKS
Page 1.02
Event: 2 yr
CUN=Upstream Node; DL=DNstream End of Link; DN=DNstream Node)
CTrun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Pre •• 2
Description: 2 YR · 24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 2 yr
Total Rainfall Depth= 4.4210 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Peak Time Peak Q
Link ID Type ac ·ft Trun. hrs cfs End Points
...................................... .. ..................... ---......... --------------------
oB· 1 PRE ADD UN 4.577 12.0000 72.26 SB·1 PRE
DL 4.577 12.0000 72.26
DN 35.152 12.1500 311.84 POINT OF EVAL.
IB-2 EX·COND ADD UN 30.575 12.2000 289.36 SUB-2 EX -CON
DL 30.575 12.2000 289.36
DN 35. 152 12.1500 311.84 POINT OF EVAL.
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5·05-97 :050 Compute Time: 09:52:51 Date: 01-08-1998
Type ••.• Executive SlJTfllary (Nodes)
Name •••• PRE
File •.•• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• TypeII 24hr Tag: Pre .• 5
NETWORK SUMMARY --NOOES
Page 1.03
Event: 5 yr
CTrun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Pre •• 5
Description: 5 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF TypeII 24hr
Storm Frequency = 5 yr
Total Rainfall Depth= 6.0210 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max WSEL
Node ID Type ac-ft Trun. hrs cf s ft
-------------------------------·---------------------
POINT OF EVAL. JCT 52.613 12.1500 462.32
SB-1 PRE AREA 6.759 12.0000 104.29
SUB-2 EX-CON AREA 45.854 12.2000 428.99
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 COfll>Ute Time: 09:52:51 Date: 01 -08-1998
Type •••• Executive SlllJllary (Links)
Name •••• PRE
File .••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Pre •• 5
NETWORK SUMMARY ·• LINKS
Page 1.04
Event: 5 yr
(UN=Upstream Node; DL=DNstream End of Link; DN=DNstream Node)
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File,10 = BRAZOS.RNQ SCS·24HR ALL
Storm Tag Name = Pre •• 5
Description: 5 YR · 24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 5 yr
Total Rainfall Depth= 6.0210 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Peak Time Peak Q
Link ID Type ac·ft Trun. hrs cfs End Points
---·------------............................... ------------------------
B-1 PRE ADD UN 6.759 12.0000 104.29 SB-1 PRE
DL 6.759 12.0000 104.29
ON 52.613 12.1500 462.32 POINT OF EVAL.
SB-2 EX·COND ADD UN 45.854 12.2000 428.99 SUB-2 EX-CON
DL 45.854 12.2000 428.99
ON 52.613 12.1500 462.32 POINT OF EVAL.
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date: 01-08-1998
Type ..•• Executive Slll'ITl8ry (Nodes)
Name •••• PRE
File ..•• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Pre.10
NETWORK SUMMARY ·· NODES
Page 1.05
Event: 10 yr
CTrun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS·24HR ALL
Storm Tag Name = Pre.10
Description: 10 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 1D yr
Total Rainfall Depth= 7.4390 in
Duration Multiplier = 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max WSEL
Node ID Type ac-ft Trun. hrs cfs ft
---------------------------.......................... --------... -.................
tfall POINT OF EVAL. JCT 68.393 12.1500 595.42
SB-1 PRE AREA 8.722 12.0000 132.44
SUB-2 EX-CON AREA 59.671 12.2000 552.43
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date: 01·08-1998
Type .••• Executive Sllllll8ry Clinks>
Name •••• PRE
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Pre.10
NETYORK SUMMARY ·· LINKS
Page 1.06
Event: 10 yr
CUN=Upstream Node; DL=DNstream End of Link; DN=DNstream Node)
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS·24HR ALL
Storm Tag Name = Pre.10
Description: 10 YR · 24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 10 yr
Total Rainfall Depth= 7.4390 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs
HYG Vol
Link ID Type ac·ft
--·---------------·--------
SB-1 PRE ADD UN 8.722
DL 8.722
ON 68.393
SB-2 EX·COND ADD UN 59.671
DL 59.671
ON 68.393
Step= .1000 hrs End= 24.0000 hrs
Peak Time Peak Q
Trun. hrs cfs End Points
--------..................................
12.0000 132.44 SB-1 PRE
12.0000 132.44
12.1500 595.42 POINT OF EVAL.
12.2000 552.43 SUB-2 EX·CON
12.2000 552.43
12.1500 595.42 POINT OF EVAL.
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5·05-97 :050 CO!f4)Ute Time: 09:52:51 Date: 01·08·1998
Type .••• Executive SU1111ary (Nodes)
Name •••• PRE
File •.•• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Typell 24hr Tag: Pre.25
NETWORK SUMMARY --NODES
Page 1.07
Event: 25 yr
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Pre.25
Description: 25 YR -24 HR STORM
Data Type, File, ID = Synthetic Storm SCSTYPES.RNF Typell 24hr
Storm Frequency = 25 yr
Total Rainfall Depth= 8.8360 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max WSEL
Node ID Type ac-ft Trun. hrs cfs ft
-----------------........................... ---------................. ---------
tfal l POINT OF EVAL. JCT 84.096 12.1500 725.88
SB-1 PRE AREA 10.671 12.0000 159.98
SUB-2 EX-CON AREA 73.425 12.2000 673.42
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05 -97 :050 Co~te Time: 09:52:51 Date: 01-08-1998
Type ••.• Executive Sl.fTlllary Clinks)
Name ..•• PRE
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Pre.25
NETYORK SUMMARY --LINKS
Page 1.08
Event: 25 yr
(UN=Upstream Node; DL=DNstream End of Link; DN=DNstream Node)
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File,ID = BRAZOS.RNQ SCS-24HR All
Storm Tag Name = Pre.25
Description: 25 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 25 yr
Total Rainfall Depth= 8.8360 in
Duration Multiplier = 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step=
HYG Vol
Link ID Type ac -ft Trun .
.......................................... -----------
SB-1 PRE ADD UN 10.671
Dl 10.671
ON 84.096
SB-2 EX-COND ADD UN 73.425
Dl 73.425
ON 84.096
.1000 hrs End= 24.0000 hrs
Peak Time Peak Q
hrs cfs End Points --... -......... .. .........................................
12.0000 159.98 SB -1 PRE
12.0000 159.98
12.1500 725.88 POINT OF EVAL.
12.2000 673.42 SUB -2 EX-CON
12.2000 673.42
12 .1500 725.88 POINT OF EVAL.
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date : 01 -08-1998
Type •••• Executive Sllllll8ry (Nodes)
Name •••• PRE
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Pre.SO
NETIJORK SUMMARY --NODES
Page 1.09
Event: 50 yr
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID = BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Pre.SO
Description: 50 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 50 yr
Total Rainfall Depth= 10.3880 in
Duration Multiplier= 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max \ISEL
Node ID Type ac-ft Trun. hrs cfs ft
------------------·-----------------.................... ---------
Outfall POINT OF EVAL. JCT 101.655 12.1500 870.03
SB-1 PRE AREA 12.847 12.0000 190.39
SUB-2 EX-CON AREA 88.808 12.2000 807.07
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Coll1>Ute Time: 09:52:51 Date: 01-08-1998
Type .••• Executive Sllllll8ry (Links)
Name •••• PRE
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Pre.SO
NETYORK SUMMARY --LINKS
Page 1.10
Event: SO yr
(UN=Upstream Node; DL=DNstream End of Link; DN=DNstream Node)
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Pre.SO
Description: SO YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency 50 yr
Total Rainfall Depth= 10.3880 in
Duration Multiplier = 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step=
HYG Vol
Link ID Type ac-ft Trun.
---------·-----------------
'B-1 PRE ADD UN 12.847
DL 12.847
ON 101.6S5
oB-2 EX-COND ADD UN 88.808
DL 88.808
ON 101.6SS
.1000hrs End= 24.0000 hrs
Peak Time Peak Q
hrs cf s End Points
.................. ----------------
12.0000 190.39 SB-1 PRE
12.0000 190.39
12.1500 870.03 POINT OF EVAL.
12.2000 807.07 SUB-2 EX-CON
12.2000 807.07
12.1500 870.03 POINT OF EVAL.
S/N: HOMOL01203S6 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-0S-97 :050 Compute Time: 09:S2:S1 Date: 01-08-1998
Type •••• Executive Sllllllary (Nodes)
Name •••• PRE
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ..• Type!! 24hr Tag: Pre100
NETWORK SUMMARY ·· NODES
Page 1.1 1
Event: 100 yr
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Pre100
Description: 100 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 100 yr
Total Rainfall Depth= 11.3530 in
Duration Multiplier= 1
Resulting Durat i on = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= 24.0000 hrs
HYG Vol Qpeak Qpeak Max WSEL
Node ID Type ac-ft Trun. hrs cfs ft
--------------------------------------------·--------
POINT OF EVAL. JCT 112.614 12.1500 959 .28
SB-1 PRE AREA 14.203 12 .0000 209.22
SUB-2 EX -CON AREA 98.411 12.2000 889.81
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Corrpute Time: 09:52:51 Date: 01-08 -1998
Type •••• Executive Slll'fl\8ry Clinks)
Name •••• PRE
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm .•• Type!! 24hr Tag: Pre100
NET~ORK SUMMARY --LINKS
Page 1.12
Event: 100 yr
CUN=Upstream Node; DL=DNstream End of Link; DN=DNstream Node)
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Pre100
Description: 100 YR -24 HR STORM
Data Type, File, ID = Synthetic Storm SCSTYPES.RNF Type I I 24hr
Storm Frequency 100 yr
Total Rainfall Depth= 11.3530 in
Duration Multiplier = 1
Resulting Duration = 24.0000 hrs
Resulting Start Time= .0000 hrs Step= • 1000 hrs End= 24.0000 hrs
HYG Vol Peak Time Peak Q
Link ID Type ac-ft Trun. hrs cf s End Points
---------------------------------------------------
SB-1 PRE ADD UN 14 .203 12.0000 209.22 SB-1 PRE
DL 14.203 12.0000 209.22
ON 112.614 12.1500 959.28 POINT OF EVAL.
SB-2 EX -COND ADD UN 98.411 12.2000 889 .81 SUB-2 EX-CON
DL 98.411 12.2000 889.81
ON 112.614 12.1500 959.28 POINT OF EVAL.
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date: 01-08-1998
Type •••• Runoff CN-Area
Name •••• SB-2-EX·CON
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Title .•• TOTAL SUB-BASIN 2 DRAINAGE AREA. EXISTING CONDITIONS
RUNOFF CURVE NUMBER DATA
Page 2.01
.......................................................................... ..........................................................................
TOTAL SUB-BASIN 2 DRAINAGE AREA. EXISTING CONDITIONS
Soil/Surface Description
HSG-D,FIELD GRASSES,BRUSH
HSG-D,DEVELOPED AREAS
HSG-D,DEVELOPED AREAS
COMPOSITE AREA & WEIGHTED CN --->
CN
80
89
89
Area
acres
---------
30.078
72.068
19.110
121.256
I~ervious
Adjustment
%C %UC
---.. -.. ----
Adjusted
CN
80.00
89.00
89.00
86. 77 (87)
··········································································· ...........................................................................
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date: 01-08-1998
Type •••• Runoff CN-Area
Name •.•• SB-I PRE
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Title ••• SB-I PRE-DEVELOPED
RUNOFF CURVE NUMBER DATA
Page 2.02
·········································································· ..........................................................................
SB-I PRE-DEVELOPED
Soil/Surface Description
IMPERVIOUS
GRASSED
COMPOSITE AREA & ~EIGHTED CN --->
CN
98
80
Area
acres --....................
8.507
8.548
17 .055
Impervious
Adjustment Adjusted
xc XlJC CN
-----..............
98.00
80.00
88.98 (89) ........................................................................... ···········································································
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date: 01-08-1998
Type .••. SCS Unit Hyd. Surrnary
Name •••• SB-2 EX-CON Tag: Pre •• 2
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Title ••• SUB-BASIN 2 EXISTING CONDITIONS
Storm ••• Type!! 24hr Tag: Pre .. 2
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 2 year storm
Page 3.01
Event: 2 yr
Duration = 24.0000 hrs Rain Depth = 4.4210 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-2 EX-CON Pre .. 2
Tc = .5500 hrs
Drainage Area= 121.256 acres Runoff CN= 87
============================================
Computational Time Increment .07333 hrs
Computed Peak Time 12.1733 hrs
Computed Peak Flow = 290.14 cfs
Time Increment for HYG File =
Peak Time, Interpolated Output
Peak Flow, Interpolated Output
.0500 hrs
12.2000 hrs
289.36 cfs
============================================
DRAINAGE AREA
ID:SB-2-EX-CON
CN = 87
Area= 121.256 acres
s = 1.4943 in
0 .2S = .2989 in
Cunulative Runoff
3.0254 in
30.571 ac-ft
HYG VollJTle .•• 30 .575 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc = .55000 hrs CID: None Selected)
Computational Iner, Tm= .07333 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising lirri:>)
K = 483.43/645.333, K = .7491 (also, K = 2/(1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak,
Unit peak time
qp = 249.80 cfs
Tp = .36667 hrs
Unit receding lirri:>, Tr= 1.46667 hrs
Tota l unit time, Tb= 1.83333 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date: 01 -08-1998
Type •••• scs Unit Hyd. Sllllllary
Name ..•• SB·2 EX·CON Tag: Pre .• 5
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Pre •• 5
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 5 year storm
Page 3.02
Event: 5 yr
Duration = 24.0000 hrs Rain Depth = 6.0210 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File ·ID= SCSTYPES.RNF · Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File . ID = ASHFORD.HYG . SB·2 EX-CON Pre •• 5
Tc = .5500 hrs
Drainage Area = 121.256 acres Runoff CN= 87
============================================
Computational Time Increment = .07333 hrs
Computed Peak Time = 12.1733 hrs
Computed Peak Flow 430.97 cfs
Time Increment for HYG File =
Peak Time, Interpolated Output
Peak Flow, Interpolated Output =
.0500 hrs
12.2000 hrs
428.99 cfs
============================================
DRAINAGE AREA
ID:SB·2·EX·CON
CN = 87
Area =
s
0.2S
121.256 acres
1.4943 in
.2989 in
Cumulative Runoff
4.5373 in
45.848 ac·ft
HYG Volume ..• 45.854 ac·ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc =
Computational Iner, Tm =
.55000 hrs CID: None Selected)
.07333 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37 .46% under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/(1+CTr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 249.80 cfs
Unj _t peak .time Tp = .36667 hrs
Unit receding limb, Tr = 1.46667 hrs
Total unit time, Tb = 1.83333 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5·05·97 :050 Compute Time: 09:52:51 Date: 01·08·1998
Type ..•• SCS Unit Hyd. Sl.lllllary
Name •••• SB-2 EX-CON Tag: Pre.10
File •.•• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Pre.10
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 10 year storm
Page 3.03
Event: 10 yr
Duration = 24.0000 hrs Rain Depth = 7.4390 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-2 EX-CON Pre.10
Tc = .5500 hrs
Drainage Area= 121.256 acres Runoff CN= 87
============================================
Computational Time Increment .07333 hrs
Computed Peak Time = 12.1733 hrs
Computed Peak Flow = 555.55 cfs
Time Increment for HYG File = .0500 hrs
Peak Time, Interpolated Output = 12.2000 hrs
Peak Flow, Interpolated Output 552.43 cfs
============================================
DRAINAGE AREA
ID:SB-2-EX-CON
CN = 87
Area= 121.256 acres
S = 1.4943 in
0.2S = .2989 in
Cumulative Runoff
5.9045 in
59.663 ac-ft
HYG Volume ••• 59.671 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc = .55000 hrs CID: None Selected)
Computational Iner, Tm= .07333 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising Limb)
K = 483.43/645.333, K = .7491 (also, K = 2/C1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak,
Unit peak .time
qp = 249.80 cfs
Tp = .36667 hrs
Unit receding Limb, Tr= 1.46667 hrs
Total unit time, Tb= 1.83333 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date: 01-08-1998
Type •••• SCS Unit Hyd . SlJTJllary
Name •••• SB-2 EX-CON Tag: Pre.25
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm .•• Type!! 24hr Tag: Pre.25
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 25 year storm
Page 3.04
Event: 25 yr
Duration = 24.0000 hrs Rain Depth = 8.8360 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-2 EX-CON Pre.25
Tc = .5500 hrs
Drainage Area= 121.256 acres Runoff CN= 87
============================================
Computational Time Increment = .07333 hrs
Computed Peak Time = 12.1733 hrs
Computed Peak Flow = 677.66 cfs
Time Increment for HYG File = .0500 hrs
Peak Time, Interpolated Output = 12.2000 hrs
Peak Flow, Interpolated Output 673.42 cfs
============================================
DRAINAGE AREA
ID:SB-2-EX-CON
CN = 87
Area= 121.256 acres
s = 1.4943 in
0.2S = .2989 in
Cumulative Runoff
7.2655 in
73.415 ac-ft
HYG Voll.Ille •.• 73.425 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentrat i on , Tc = .55000 hrs CID: None Selected)
Computational I ner, Tm= .07333 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/(1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 249.80 cfs
Unit peak time Tp = .36667 hrs
Unit receding limb, Tr = 1.46667 hrs
Total unit time, Tb = 1.83333 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date: 01-08-1998
Type •••• SCS Unit Hyd. S1.1m1ary
Name .••. SB-2 EX-CON Tag: Pre.SO
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Typell 24hr Tag: Pre.SO
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: so year storm
Page 3.0S
Event: SO yr
Duration = 24.0000 hrs Rain Depth = 10.3880 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Typell 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-2 EX-CON Pre.SO
Tc = .SSOO hrs
Drainage Area= 121.2S6 acres Runoff CN= 87
============================================
C~tational Time Increment = .07333 hrs
C~ted Peak Time = 12.1733 hrs
C~ted Peak Flow = 812.S7 cfs
Time Increment for HYG File = .OSOO hrs
Peak Time, Interpolated Output = 12.2000 hrs
Peak Flow, Interpolated Output = 807.07 cfs
============================================
DRAINAGE AREA
ID:SB-2-EX-CON
CN = 87
Area= 121.2S6 acres
s = 1.4943 in
0.2S = .2989 in
CllllUlative Runoff
8.7877 in
88.796 ac-ft
HYG Volume .•• 88.808 ac-ft (ar ea under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc = .SSOOO hrs CID: None Selected)
Computational Iner, Tm= .07333 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising lirrb)
K = 483.43/64S .333, K = .7491 (also, K = 2/(1+(Tr/Tp))
Receding/Ris i ng, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 249 .80 cfs
Unit peak _time Tp = .36667 hrs
Unit receding lirrb, Tr = 1.46667 hrs
Total unit time, Tb = 1.83333 hrs
S/N: HOMOL01203S6 KLING ENGINEERING & SURVEYING
Pond Pack Ver: S-OS-97 :OSO Compute Time: 09:S2:S1 Date: 01 -08-1998
Type •••• SCS Unit Hyd. SU111T1ary
Name •••• SB-2 EX-CON Tag: Pre100
File •.•• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• TypeII 24hr Tag: Pre100
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 100 year storm
Page 3.06
Event: 100 yr
Duration = 24.0000 hrs Rain Depth= 11.3530 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -TypeII 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-2 EX-CON Pre100
Tc = .5500 hrs
Drainage Area= 121.256 acres Runoff CN= 87
============================================
Computational Time Increment
Computed Peak Time
Computed Peak Flow
.07333 hrs
12.1733 hrs
896.08 cfs
Time Increment for HYG File = .0500 hrs
Peak Time, Interpolated Output = 12.2000 hrs
Peak Flow, Interpolated Output = 889.81 cfs
============================================
DRAINAGE AREA
ID:SB-2·EX-CON
CN = 87
Area= 121.256 acres
s = 1.4943 in
0.2S = .2989 in
CllllUlative Runoff
9.7378 in
98.398 ac-ft
HYG Volune ••• 98.411 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc = .55000 hrs CID: None Selected)
Computational Iner, Tm= .07333 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising lirrb)
K = 483.43/645.333, K = .7491 (also, K = 2/C1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak,
Unit peak _time
qp = 249.80 cfs
Tp = .36667 hrs
Unit receding lirrb, Tr= 1.46667 hrs
Total unit time, Tb= 1.83333 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date: 01-08-1999
Type .••• scs Unit Hyd. Sunmary
Name .••• SB-I PRE Tag: Pre •• 2
File .••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Pre •• 2
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 2 year storm
Page 3.07
Event: 2 yr
Duration = 24.0000 hrs Rain Depth = 4.4210 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Defau l t Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-I PRE Pre .. 2
Tc = .1667 hrs
Drainage Area = 17.055 acres Runoff CN= 89
============================================
Computational Time Increment .02223 hrs
C~ted Peak Time = 11.9802 hrs
C~ted Peak Flow 73.03 cfs
Time Increment for HYG File = .0500 hrs
Peak Time, Interpolated Output = 12.0000 hrs
Peak Flow, Interpolated Output = 72.26 cfs
============================================
DRAINAGE AREA
ID:SB-1 PRE
CN = 89
Area = 17.055 acres
S = 1.2360 in
0.2S = .2472 in
Cl.lllUlative Runoff
3.2202 in
4.577 ac-ft
HYG Volume .•. 4.577 ac -ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc= .16670 hrs CID: None Selected)
Computational Iner, Tm= .02223 hrs= 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/(1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 115.92 cfs
Uni .t p~ak time Tp = .11113 hrs
Unit receding limb, Tr = .44453 hrs
Total unit time, Tb = .55567 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date: 01-08-1998
Type •••• SCS Unit Hyd. Surrnary
Name •••. SB-I PRE Tag: Pre •• 5
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ..• Type!! 24hr Tag: Pre .• 5
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 5 year storm
Page 3.08
Event: 5 yr
Duration = 24.0000 hrs Rain Depth = 6.0210 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File ·ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-I PRE Pre •• 5
Tc = .1667 hrs
Drainage Area = 17.055 acres Runoff CN= 89
============================================
Computational Time Increment = .02223 hrs
CO!l'pUted Peak Time = 11.9802 hrs
CO!l'pUted Peak Flow = 105.69 cfs
Time Increment for HYG File = .0500 hrs
Peak Time, Interpolated Output = 12.0000 hrs
Peak Flow, Interpolated Output = 104.29 cfs
============================================
DRAINAGE AREA
ID:SB-1 PRE
CN = 89
Area = 17.055 acres
S = 1.2360 in
0.2S = .2472 in
Cumulative Runoff
4.7558 in
6.759 ac-ft
HYG Volume ••• 6.759 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc= .16670 hrs CID: None Selected)
Computational Iner, Tm= .02223 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/C1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 115.92 cfs
Uni _t peak time Tp = .11113 hrs
Unit receding limb, Tr = .44453 hrs
Total unit time, Tb= .55567 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date: 01 -08-1998
Type .••• SCS Unit Hyd. Sl.1111l8ry
Name •••• SB-I PRE Tag: Pre.10
File •••• E:\HAESTAO\PONOPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm .•• Type!! 24hr Tag: Pre.10
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 10 year storm
Page 3.09
Event: 10 yr
Duration = 24.0000 hrs Rain Depth = 7.4390 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-I PRE Pre.10
Tc = .1667 hrs
Drainage Area = 17.055 acres Runoff CN= 89
============================================
Computational Time Increment .02223 hrs
Computed Peak Time = 11.9802 hrs
Computed Peak Flow = 134.41 cfs
Time Increment for HYG File .0500 hrs
Peak Time, Interpolated Output = 12.0000 hrs
Peak Flow, Interpolated Output = 132.44 cfs
============================================
DRAINAGE AREA
ID:SB-1 PRE
CN = 89
Area = 17.055 acres
s = 1.2360 in
0.2S .2472 in
Cumulative Runoff
6.1371 in
8.722 ac-ft
HYG Volume •.• 8.722 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentr a t i on, Tc = .16670 hrs CID: None Selected)
Computational I ner, Tm = .02223 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 C37.46X under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/C1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 115.92 cfs
Un i_t peak .time Tp = • 11113 hrs
Unit receding limb, Tr = .44453 hrs
Total unit time, Tb = .55567 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 09:52:51 Date: 01 -08-1998
Type ••.• SCS Unit Hyd. Sunmary
Name •••• SB-I PRE Tag: Pre.25
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Pre.25
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 25 year storm
Page 3.10
Event: 25 yr
Duration = 24.0000 hrs Rain Depth = 8.8360 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File ·ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-I PRE Pre.25
Tc = • 1667 hrs
Drainage Area = 17.055 acres Runoff CN= 89
============================================
Computational Time Increment
Computed Peak Time
= .02223 hrs
= 11. 9802 hrs
= 162.50 cfs Computed Peak Flow
Time Increment for HYG File = .0500 hrs
Peak Time, Interpolated Output = 12.0000 hrs
Peak Flow, Interpolated Output = 159.98 cfs
WARNING: The difference between calculated peak flow
and interpolated peak flow is greater than 1.50X
============================================
DRAINAGE AREA
ID:SB·I PRE
CN = 89
Area = 17.055 acres
s = 1.2360 in
0.2S = .2472 in
Cumulative Runoff
7.5083 in
10.671 ac-ft
HYG Volume ••• 10.671 ac ·ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc= .16670 hrs (ID: None Selected)
Computational Iner, Tm= .02223 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46X under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/(1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 115.92 cfs
Unit peak time Tp = .11113 hrs
Unit receding limb, Tr = .44453 hrs
Total unit time, Tb = .55567 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Type .... SCS Unit Hyd. Sl.lmlary
Name •..• SB-I PRE Tag: Pre.SO
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm .•• Type!! 24hr Tag: Pre.SO
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: SO year storm
Page3.11
Event: SO yr
Duration 24.0000 hrs Rain Depth = 10.3880 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Typell 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-I PRE Pre.SO
Tc • 1667 hrs
Drainage Area = 17.0SS acres Runoff CN= 89
============================================
Computational Time Increment = .02223 hrs
Computed Peak Time = 11.9802 hrs
Computed Peak Flow = 193.S2 cfs
Time Increment for HYG File = .OSOO hrs
Peak Time, Interpolated Output 12.0000 hrs
Peak Flow, Interpolated Output 190.39 cfs
WARNING: The difference between calculated peak flow
and interpolated peak flow is greater than 1.SO%
============================================
DRAINAGE AREA
ID:SB-1 PRE
CN 89
Area = 17.0SS acres
s 1.2360 in
0.2S = .2472 in
Curulative Runoff
9.0391 in
12.847 ac-ft
HYG Vollllle •.• 12.847 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc= .16670 hrs CID: None Selected)
Computational Iner, Tm = .02223 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/64S.333, K = .7491 (also, K = 2/(1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 11S.92 cfs
Unit peak time Tp = .11113 hrs
Unit receding limb, Tr = .444S3 hrs
Total unit time, Tb = .SSS67 hrs
S/N: HOMOL01203S6 KLING ENGINEERING & SURVEYING
Type •••• SCS Unit Hyd. Sunmary
Name ..•• SB-I PRE Tag: Pre100
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Pre100
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 100 year storm
Page 3.12
Event: 100 yr
Duration = 24.0000 hrs Rain Depth= 11.3530 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-I PRE Pre100
Tc = • 1667 hrs
Drainage Area = 17.055 acres Runoff CN= 89
============================================
Computational Time Increment
Corrputed Peak Time
= .02223 hrs
11.9802 hrs
= 212.72 cfs Coirputed Peak Flow
Time Increment for HYG File = .0500 hrs
Peak Time, Interpolated Output = 12.0000 hrs
Peak Flow, Interpolated Output = 209.22 cfs
~ARNING: The difference between calculated peak flow
and interpolated peak flow is greater than 1.50%
============================================
HYG Voll.Jlle ••.
DRAINAGE AREA
ID:SB-1 PRE
CN = 89
Area = 17.055 acres
S = 1.2360 in
0.2S = .2472 in
Cumulative Runoff
9.9936 in
14.203 ac-ft
14.203 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc= .16670 hrs CID: None Selected)
Computational Iner, Tm= .02223 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/(1+CTr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 115.92 cfs
Unit peak time Tp = .11113 hrs
Unit receding limb, Tr = .44453 hrs
Total unit time, Tb = .55567 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Job File: E:\HAESTAO\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Rain Dir: J:\HAESTAD\PPK6\UTIL\
==========================
JOB TITLE
==========================
ASHFORD SQUARE RESUBDIVISION PROJECT
MORGAN RECTOR SURVEY, A-46
COLLEGE STATION, BRAZOS COUNTY, TEXAS
DRAINAGE & DETENTION
S/N: HOHOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5·05-97 :050 C~ute Time: 10:00:50 Date: 01-08-1998
Table of Contents
Table of Contents
******************** NETWORK SUMMARIES *********************
POST •••••••••••• Dev •• 2
Executive SlmllBry (Nodes) .......... 1.01
Executive SlmllBry Clinks) .......... 1.02
POST •••••••••••• Dev •• 5
Executive SlmllBry (Nodes) .......... 1.03
Executive Sunmary Clinks) .......... 1.04
POST ••••.•••.••. Dev.10
Executive SlmllBry (Nodes) .......... 1.05
Executive SlmllBry Clinks) .......... 1.06
POST •••••••••••• Dev.25
Executive Surrmary (Nodes) .......... 1.07
Executive SlmllBry Clinks) .......... 1.08
POST •••.••••.••• Dev.SO
Executive Sl.lllllary (Nodes) .......... 1.09
Executive Surrmary Clinks) .......... 1.10
POST •••••••••.•• Dev100
Executive SlmllBry (Nodes) .......... 1.11
Executive SlmllBry Clinks) .......... 1.12
********************** CN CALCULATIONS *********************
SB-2-EX -CON .•••• Runoff CN-Area 2.01
SB-I POST .•••••• Runoff CN-Area 2.02
******************** RUNOFF HYDROGRAPHS ********************
SB-2 EX-CON ••••• Dev •• 2
SCS Unit Hyd. SlmllBry ..••••••....•• 3.01
SB-2 EX-CON ••••• Dev .• 5
SCS Unit Hyd. SlmllBry ••••••••••.••• 3.02
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Table of Contents ii
Table of Contents (continued)
SB-2 EX-CON .•••• Dev.10
SCS Unit Hyd. Surmary ••••••.••..•.• 3.03
SB-2 EX-CON .•••• Dev.2S
SCS Unit Hyd. Surmary ••••••••..•••• 3.04
SB-2 EX-CON •.••. Dev.SO
SCS Unit Hyd. Surmary •••••••••.•••• 3.0S
SB -2 EX-CON •.••• Dev100
SCS Unit Hyd. Surmary .•.••••••••••• 3.06
SB-I POST ••••.•• Dev •• 2
SCS Unit Hyd. Surmary .•.•••••••••.. 3.07
SB-I POST ••.•.•• Dev .. S
SCS Unit Hyd. Surmary •••••••.•.••.• 3.08
SB-I POST .•••••• Dev.10
SCS Unit Hyd. Surmary ..•••..••••••• 3.09
SB-I POST ••••••• Dev.2S
SCS Unit Hyd. Surmary •••••••••••••• 3.10
SB-I POST ••••••• Dev.SO
SCS Unit Hyd. Surmary ••••••••••...• 3.11
SB-I POST •..•.•• Dev100
scs Unit Hyd. Surmary •••••••.•••••• 3.12
Type •.•• Executive Surmary (Nodes)
Name •••• POST
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• TypeII 24hr Tag: Dev •• 2
NETUORK SUMMARY --NOOES
Page 1.01
Event: 2 yr
(Trun.= HYG Truncation: Blank=None; L=Left;.R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File,ID = BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Dev •• 2
Description: 2 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF TypeII 24hr
Storm Frequency = 2 yr
Total Rainfall Depth= .0000 in
Duration Multiplier = 1
Resulting Duration = -.1000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= -.1000 hrs
HYG Vol Cpeak Qpeak Max USEL
Node ID Type ac-ft Trun. hrs cfs ft
-----------------·-------------------------· ·--------
utfal l POINT OF EVAL. JCT 35.439 12.1500 312.96
SB-1 POST AREA 4.863 12.0000 75.53
SUB-2 EX-CON AREA 30.575 12.2000 289.36
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type .••• Executive SUllllary Clinks)
Name •••• POST
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev .• 2
NETWORK SUMMARY ·· LINKS
Page 1.02
Event: 2 yr
(UN=Upstream Node; DL=DNstream End of Link; DN=DNstream Node)
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS·24HR ALL
Storm Tag Name = Dev •• 2
Description: 2 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 2 yr
Total Rainfall Depth= .0000 in
Duration Multiplier = 1
Resulting Duration = ·.1000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= -.1000 hrs
HYG Vol Peak Time Peak Q
Link ID Type ac·ft Trun. hrs cfs End Points
----------------...................... ... -.......... -.. --------------·-
SB·1 POST ADD UN 4.863 12.0000 75.53 SB-1 POST
DL 4.863 12.0000 75.53
ON 35.439 12.1500 312.96 POINT OF EVAL.
SB-2 EX-COND ADD UN 30.575 12.2000 289.36 SUB-2 EX-CON
DL 30.575 12.2000 289.36
DN 35.439 12.1500 312.96 POINT OF EVAL.
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type .••• Executive SLrm1ary (Nodes)
Name •••• POST
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev •• 5
NETWORK SUMMARY --NODES
Page 1.03
Event: 5 yr
CTrun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS·24HR ALL
Storm Tag Name = Dev .. 5
Description: 5 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 5 yr
Total Rainfall Depth= .0000 in
Duration Multiplier= 1
Resulting Duration = -.1000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= -.1000 hrs
HYG Vol Qpeak Qpeak Max WSEL
Node ID Type ac-ft Trun. hrs cf s ft
-----------------·---------.......................... -----------------
POINT OF EVAL. JCT 52.929 12.1500 463.33
SB-1 POST AREA 7.075 12.0000 107.33
SUB-2 EX-CON AREA 45.854 12.2000 428.99
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08 -1998
Type •••• Executive Sl.ITIT1ary (Links)
Name •••• POST
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Oev •• 5
NETWORK SUMMARY --LINKS
Page 1.04
Event: 5 yr
(UN=Upstream Node; DL=DNstream End of Link; DN=DNstream Node)
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Dev .. 5
Description: 5 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 5 yr
Total Rainfall Depth= .0000 in
Duration Multiplier= 1
Resulting Duration = -.1000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= -.1000 hrs
HYG Vol Peak Time Peak Q
Link ID Type ac-ft Trun. hrs cfs End Points
----------·---· ··--------------·-----·------------
SB-1 POST ADD UN 7.075 12.0000 107.33 SB-1 POST
DL 7.075 12.0000 107.33
ON 52.929 12.1500 463.33 POINT OF EVAL.
B-2 EX -COND ADD UN 45.854 12.2000 428.99 SUB-2 EX-CON
DL 45.854 12.2000 428.99
ON 52.929 12.1500 463.33 POINT OF EVAL.
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type .••• Executive SU1111ary (Nodes)
Name •••• POST
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ..• Type!! 24hr Tag: Dev.10
NET~ORK SUMMARY --NOOES
Page 1.05
Event: 10 yr
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Dev.10
Description: 10 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 10 yr
Total Rainfall Depth= .0000 in
Duration Multiplier= 1
Resulting Duration = -.1000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= -.1000 hrs
HYG Vol Qpeak Qpeak Max ~SEL
Node ID Type ac-ft Trun. hrs cfs ft
--------------------·---------------................ ....................
tfal l POINT OF EVAL. JCT 68.726 12.1500 596.34
SB-1 POST AREA 9.055 12.0000 135.25
SUB-2 EX-CON AREA 59.671 12.2000 552.43
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type •••• Executive Sl.tllllary Clinks)
Name •••• POST
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm .•• Typell 24hr Tag: Oev.10
NETYORK SUMMARY ·· LINKS
Page 1.06
Event: 10 yr
(UN=Upstream Node; DL=DNstream End of Link; DN=DNstream Node)
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID = BRAZOS.RNQ SCS·24HR ALL
Storm Tag Name = Dev .10
Description: 10 YR · 24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Typell 24hr
Storm Frequency = 10 yr
Total Rainfall Depth= .0000 in
Duration Multiplier = 1
Resulting Duration = -.1000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= -.1000 hrs
HYG Vol Peak Time Peak Q
Link ID Type ac·ft Trun. hrs cfs End Points
_,.. _______ .................. ................................ ... ..................... ----------------
SB-1 POST ADD UN 9.055 12.0000 135.25 SB-1 POST
DL 9.055 12.0000 135.25
ON 68.726 12. 1500 596.34 POINT OF EVAL.
B-2 EX·COND ADD UN 59.671 12.2000 552.43 SUB-2 EX-CON
DL 59.671 12.2000 552.43
ON 68 .726 12. 1500 596.34 POINT OF EVAL.
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type •••• Executive Sl.lllllary (Nodes)
Name •••• POST
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Typell 24hr Tag: Dev.25
NETYORK SUMMARY --NODES
Page 1.07
Event: 25 yr
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File,ID = BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Dev.25
Description: 25 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Typell 24hr
Storm Frequency = 25 yr
Total Rainfall Depth= .0000 in
Duration Multiplier= 1
Resulting Duration = -.1000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= -.1000 hrs
HYG Vol Qpeak Qpeak Max YSEL
Node ID Type ac-ft Trun. hrs cfs ft
-----------------....................... ...................... .. ................ ---------
utfal l POINT OF EVAL. JCT 84.441 12.1500 726.73
SB-1 POST AREA 11.016 12.0000 162.57
SUB-2 EX-CON AREA 73.425 12.2000 673.42
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08 -1998
Type .••• Executive SU'llllary Clinks)
Name •••• POST
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm •.• Type!! 24hr Tag: Dev.25
NETYORK SUMMARY ·· LINKS
Page 1.08
Event: 25 yr
CUN=Upstream Node; DL=DNstream End of Link; DN=DNstream Node)
CTrun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File,ID = BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Dev.25
Description: 25 YR · 24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 25 yr
Total Rainfall Depth= .0000 in
Duration Multiplier=
Resulting Duration = -.1000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= -• 1000 hrs
HYG Vol Peak Time Peak Q
Link ID Type ac·ft Trun. hrs cfs End Points
----------------·----------------------------------
SB-1 POST ADD UN 11. 016 12.0000 162.57 SB-1 POST
DL 11.016 12.0000 162.57
DN 84.441 12.1500 726.73 POINT OF EVAL.
SB-2 EX·COND ADD UN 73.425 12.2000 673.42 SUB-2 EX-CON
DL 73.425 12.2000 673.42
ON 84.441 12.1500 726.73 POINT OF EVAL.
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type •••• Executive SLITlll8ry (Nodes)
Name •••• POST
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev.SO
NETWORK SUMMARY --NOOES
Page 1.09
Event: SO yr
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File,ID = BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Dev.SO
Description: SO YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = SO yr
Total Rainfall Depth= .0000 in
Duration Multiplier =
Resulting Duration = -.1000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= -.1000 hrs
HYG Vol Qpeak Qpeak Max WSEL
Node ID Type ac-ft Trun. hrs cf s ft
--------------------·---------------.................. --------·
utfal l POINT OF EVAL. JCT 102.010 12.1SOO 870.80
SB-1 POST AREA 13.201 12.0000 192.77
SUB-2 EX-CON AREA 88.808 12.2000 807 .07
S/N: HOMOL01203S6 KLING ENGINEERING & SURVEYING
Pond Pack Ver: S-OS-97 :050 Compute Time: 10:00:50 Date : 01-08-1998
Type •••• Executive Sllllllary Clinks)
Name •••• POST
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev.SO
NET\JORK SUMMARY --LINKS
Page 1. 10
Event: SO yr
(UN=Upstream Node; DL=DNstream End of Link; DN=DNstream Node)
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin St.orm Fi le, ID = BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Dev.SO
Description: SO YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = SO yr
Total Rainfall Depth= .0000 in
Duration Multiplier= 1
Resulting Duration = -.1000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= -.1000 hrs
HYG Vol Peak Time Peak Q
Link ID Type ac-ft Trun. hrs cfs End Points
---------------------------------------------------
SB-1 POST ADD UN 13.201 12.0000 192.n SB-1 POST
DL 13.201 12.0000 192.n
ON 102.010 12.1SOO 870.80 POINT OF EVAL .
SB-2 EX-COND ADD UN 88.808 12.2000 807.07 SUB-2 EX-CON
DL 88.808 12.2000 807.07
ON 102.010 12.1SOO 870.80 POINT OF EVAL.
S/N: HOMOL01203S6 KLING ENGINEERING & SURVEYING
Pond Pack Ver: S-OS-97 :OSO COfll>Ute Time: 10:00:SO Date: 01-08-1998
Type •••• Executive SlJllllary (Nodes)
Name •••• POST
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm .•• Type!! 24hr Tag: Dev100
NET~ORK SUMMARY --NODES
Page 1. 11
Event: 100 yr
CTrun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS -24HR ALL
Storm Tag Name = Dev100
Description: 100 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Typell 24hr
Storm Frequency 100 yr
Total Rainfall Depth= .0000 in
Duration Multiplier=
Resulting Duration = -.1000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= -.1000 hrs
HYG Vol Qpeak Qpeak Max ~SEL
Node ID Type ac-ft Trun. hrs cfs ft
-----------------............................ ... ........................ --------...........................
tfal l POINT OF EVAL . JCT 112.974 12.1500 960.00
SB-1 POST AREA 14.563 12.0000 211.48
SUB-2 EX-CON AREA 98.411 12.2000 889.81
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Ti me: 10:00:50 Date: 01 -08-1998
Type •••• Executive S1.11111ary (Links)
Name •••• POST
File •••• E:\HAESTAO\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev100
NET~ORK SUMMARY ·· LINKS
Page 1. 12
Event: 100 yr
(UN=Upstream Node; DL=DNstream End of Link; DN=DNstream Node)
(Trun.= HYG Truncation: Blank=None; L=Left; R=Rt; LR=Left & Rt)
DEFAULT Desgin Storm File, ID= BRAZOS.RNQ SCS-24HR ALL
Storm Tag Name = Dev100
Description: 100 YR -24 HR STORM
Data Type, File, ID= Synthetic Storm SCSTYPES.RNF Type!! 24hr
Storm Frequency = 100 yr
Total Rainfall Depth= .0000 in
Duration Multiplier=
Resulting Duration = -.1000 hrs
Resulting Start Time= .0000 hrs Step= .1000 hrs End= -.1000 hrs
HYG Vol Peak Time Peak Q
Link ID Type ac-ft Trun. hrs cfs End Points
----·------------------------·-----.................................
SB-1 POST ADD UN 14.563 12.0000 211.48 SB-1 POST
DL 14.563 12.0000 211.48
ON 112.974 12.1500 960.00 POINT OF EVAL.
SB-2 EX-COND ADD UN 98.411 12.2000 889.81 SUB-2 EX-CON
DL 98.411 12.2000 889.81
ON 112.974 12.1500 960.00 POINT OF EVAL.
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type •••• Runoff CN-Area
Name •••• SB-2-EX-CON
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Title ••• TOTAL SUB-BASIN 2 DRAINAGE AREA. EXISTING CONDITIONS
RUNOFF CURVE NUMBER DATA
Page 2.01
.......................................................................... ..........................................................................
TOTAL SUB-BASIN 2 DRAINAGE AREA. EXISTING CONDITIONS
Soil/Surface Description
HSG-0,FIELD GRASSES,BRUSH
HSG-0,DEVELOPED AREAS
HSG-D,DEVELOPED AREAS
COMPOSITE AREA & YEIGHTED CN --->
CN
80
89
89
Area
acres
---------
30.078
72.068
19.110
121.256
Impervious
Adjustment
xc ~c
-------.. --
Adjusted
CN
80.00
89.00
89.00
86. 77 (87) ........................................................................... ···········································································
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type •.•• Runoff CN-Area
Name •••• SB-! POST
File •••• E:\HAESTAD\PONDPACK\PPK6\AS HFORD\ASHFORDC.PPK
Title ••• SB-I POST-DEVELOPED
RUNOFF CURVE NUMBER DATA
Page 2.02
.......................................................................... ..........................................................................
SB-! POST-DEVELOPED
Soil/Surface Description
IMPERVIOUS
GRASSED
COMPOSITE AREA & WEIGHTED CN --->
CN
98
80
Area
acres _____ .........
10.818
6.237
17. 055
Impervious
Adjustment Adjusted
xc xuc CN
.. ---.. .. .. -.. -
98.00
80.00
91.42 (91) ........................................................................... . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type •••• scs Unit Hyd. Surrrnary
Name .••• SB·2 EX-CON Tag: Dev •• 2
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Title ••• SUB-BASIN 2 EXISTING CONDITIONS
Storm ••• Typell 24hr Tag: Dev •• 2
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 2 year storm
Page 3.01
Event: 2 yr
Duration = 24.0000 hrs Rain Depth = 4.4210 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Typell 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-2 EX-CON Dev •• 2
Tc = .5500 hrs
Drainage Area = 121.256 acres Runoff CN= 87
============================================
Computational Time Increment
Computed Peak Time
Computed Peak Flow
= .07333 hrs
= 12.1733 hrs
= 290.14 cfs
Time Increment for HYG File = .0500 hrs
Peak Time, Interpolated Output = 12.2000 hrs
Peak Flow, Interpolated Output 289.36 cfs
============================================
DRAINAGE AREA
ID:SB-2-EX-CON
CN 87
Area = 121.256 acres
S = 1.4943 in
0.2S = .2989 in
Cumulative Runoff
3.0254 in
30.571 ac -ft
HYG Volume •.. 30.575 ac-ft (a r ea under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc = .55000 hrs CID: None Selected)
Computational Iner, Tm= .07333 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising Limb)
K = 483.43/645.333, K = .7491 (also, K = 2/(1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 249.80 cfs
Unit peak time Tp = .36667 hrs
Unit receding limb, Tr = 1.46667 hrs
Total unit time, Tb = 1.83333 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type •••• SCS Unit Hyd. Sl.lml8ry
Name •••• SB-2 EX-CON Tag: Dev •• 5
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev •• 5
SCS UNIT HYDROGRAPH METHOO
STORM EVENT: 5 year storm
Page 3.02
Event: 5 yr
Duration = 24.0000 hrs Rain Depth = 6.0210 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-2 EX-CON Dev •• 5
Tc = .5500 hrs
Drainage Area= 121.256 acres Runoff CN= 87
============================================
Computational Time Increment = .07333 hrs
Computed Peak Time 12.1733 hrs
Computed Peak Flow 430.97 cfs
Time Increment for HYG File .0500 hrs
Peak Time, Interpolated Output 12.2000 hrs
Peak Flow, Interpolated Output 428.99 cfs
DRAINAGE AREA
ID:SB-2-EX-CON
CN 87
Area =
s
0.2S =
121.256 acres
1.4943 in
.2989 in
CllllUlative Runoff
4.5373 in
45.848 ac-ft
HYG Volume ••• 45.854 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc =
Computational Iner, Tm=
.55000 hrs (ID: None Selected)
.07333 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/(1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 249.80 cfs
Unit p~ak time Tp = .36667 hrs
Unit receding limb, Tr = 1.46667 hrs
Total unit time, Tb = 1.83333 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type ..•• SCS Unit Hyd. Sllllllary
Name •••• SB-2 EX-CON Tag: Dev.1D
File .••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev.10
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 10 year storm
Page 3.03
Event: 10 yr
Duration = 24.0000 hrs Rain Depth = 7.4390 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-2 EX-CON Dev.10
Tc = .5500 hrs
Drainage Area= 121.256 acres Runoff CN= 87
============================================
Computational Time Increment = .07333 hrs
Computed Peak Time
Computed Peak Flow
= 12.1733 hrs
555.55 cfs
Time Increment for HYG File = .0500 hrs
Peak Time, Interpolated Output 12.2000 hrs
Peak Flow, Interpolated Output = 552.43 cfs
============================================
DRAINAGE AREA
ID:SB-2-EX-CON
CN = 87
Area =
s
0.2S =
121.256 acres
1.4943 in
.2989 in
Cumulative Runoff
5.9045 in
59.663 ac-ft
HYG Volune ••• 59.671 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentrat i on, Tc = .55000 hrs CID: None Selected)
Computational Iner, Tm= .07333 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/(1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 249.80 cfs
Uni .t p.eak t.ime Tp = .36667 hrs
Unit receding limb, Tr = 1.46667 hrs
Total unit time, Tb = 1.83333 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type •••• scs Unit Hyd. Surrmary
Name •••• SB·2 EX-CON Tag: Dev.25
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev.25
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 25 year storm
Page 3.04
Event: 25 yr
Duration = 24.0000 hrs Rain Depth = 8.8360 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File · ID= ASHFORD.HYG · SB-2 EX-CON Dev.25
Tc = .5500 hrs
Drainage Area= 121.256 acres Runoff CN= 87
============================================
Computational Time Increment = .07333 hrs
Computed Peak Time 12.1733 hrs
Computed Peak Flow = 677.66 cfs
Time Increment for HYG File = .0500 hrs
Peak Time, Interpolated Output = 12.2000 hrs
Peak Flow, Interpolated Output 673.42 cfs
============================================
DRAINAGE AREA
ID:SB-2·EX·CON
CN 87
Area= 121.256 acres
s = 1.4943 in
0.2S = .2989 in
Cumulative Runoff
7.2655 in
73.415 ac·ft
HYG Volume .•• 73.425 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc = .55000 hrs CID: None Selected)
Computational Iner, Tm= .07333 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/(1+CTr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak,
Unit peak time
Unit receding limb,
Total unit time,
qp = 249.80 cfs
Tp = .36667 hrs
Tr= 1.46667 hrs
Tb= 1.83333 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08·1998
Type ..•• SCS Unit Hyd. Surrmary
Name ..•• SB·2 EX-CON Tag: Dev.SO
File •... E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev.SO
SCS UNIT HYDROGRAPH METHOO
STORM EVENT: SO year storm
Page 3.0S
Event: SO yr
Duration = 24.0000 hrs Rain Depth = 10.3880 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File ·ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB -2 EX-CON Dev.SO
Tc = .SSOO hrs
Drainage Area= 121.2S6 acres Runoff CN= 87
============================================
Computational Time Increment .07333 hrs
Computed Peak Time = 12.1733 hrs
Computed Peak Flow 812.S7 cfs
Time Increment for HYG File = .OSOO hrs
Peak Time, Interpolated Output = 12.2000 hrs
Peak Flow, Interpolated Output = 807.07 cfs
============================================
DRAINAGE AREA
ID:SB-2-EX-CON
CN = 87
Area= 121.2S6 acres
S = 1.4943 in
0.2S = .2989 in
Cunulative Runoff
8.7877 in
88.796 ac -ft
HYG Volume ••• 88 .808 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentrat i on, Tc = .SSOOO hrs CID: None Selected)
Computational Iner, Tm = .07333 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37 .46% under r ising limb)
K = 483.43/64S.333, K = .7491 (also, K = 2/C1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 249.80 cfs
Unit peak time Tp = .36667 hrs
Un i t receding limb, Tr = 1.46667 hrs
Total unit time, Tb = 1.83333 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: S-05-97 :050 Compute Time: 10:00:50 Date: 01 -08-1998
Type •••• SCS Unit Hyd. Sunmary
Name •••• SB-2 EX-CON Tag: Dev100
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev100
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 100 year storm
Page 3.06
Event: 100 yr
Duration = 24.0000 hrs Rain Depth = 11.3530 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File ·ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG · SB-2 EX-CON Dev100
Tc = .5500 hrs
Drainage Area= 121.256 acres Runoff CN= 87
============================================
Computational Time Increment
Computed Peak Time
Computed Peak Flow
.07333 hrs
12.1733 hrs
896.08 cfs
Time Increment for HYG File = .0500 hrs
Peak Time, Interpolated Output 12.2000 hrs
Peak Flow, Interpolated Output = 889.81 cfs
============================================
DRAINAGE AREA
ID:SB-2-EX·CON
CN = 87
Area =
s
0.2S =
121.256 acres
1.4943 in
.2989 in
Cumulative Runoff
9.7378 in
98.398 ac-ft
HYG Volume ••• 98.411 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc = .55000 hrs CID: None Selected)
Computational Iner, Tm = .07333 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/C1+CTr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 249.80 cfs
Unit peak time Tp = .36667 hrs
unit receding limb, Tr = 1.46667 hrs
Total unit time, Tb= 1.83333 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type •••• SCS Unit Hyd. Sl.fllllary
Name •••• SB-I POST Tag: Dev •. 2
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev •• 2
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 2 year storm
Page 3.07
Event: 2 yr
Duration = 24.0000 hrs Rain Depth = 4.4210 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-I POST Dev •• 2
Tc = • 1667 hrs
Drainage Area = 17.055 acres Runoff CN= 91
============================================
Computational Time Increment = .02223 hrs
Computed Peak Time = 11.9802 hrs
Computed Peak Flow = 76.49 cfs
Time Increment for HYG File = .0500 hrs
Peak Time, Interpolated Output = 12.0000 hrs
Peak Flow, Interpolated Output = 75.53 cfs
============================================
DRAINAGE AREA
ID:SB-1 POST
CN 91
Area = 17.055 acres
s .9890 in
0.2S = .1978 in
Cumulative Runoff
3.4218 in
4.863 ac-ft
HYG Volume ••• 4.863 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc= .16670 hrs CID: None Selected)
Computational Iner, Tm= .02223 hrs= 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/(1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 115.92 cfs
Unit pea~ .time Tp = .11113 hrs
Unit receding limb, Tr = .44453 hrs
Total unit time, Tb = .55567 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type •••• scs Unit Hyd. Sunmary
Name •..• SB-I POST Tag: Dev •• 5
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev •. 5
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 5 year storm
Page 3.08
Event: 5 yr
Duration = 24.0000 hrs Rain Depth = 6.0210 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-I POST Dev •• 5
Tc = . 1667 hrs
Drainage Area = 17.055 acres Runoff CN= 91
============================================
Computational Time Increment = .02223 hrs
Computed Peak Time = 11.9802 hrs
Computed Peak Flow = 108.93 cfs
Time Increment for HYG File .0500 hrs
Peak Time, Interpolated Output = 12.0000 hrs
Peak Flow, Interpolated Output 107.33 cfs
============================================
DRAINAGE AREA
ID:SB-1 POST
CN = 91
Area = 17.055 acres
S = .9890 in
0.2S = .1978 in
Cumulative Runoff
4.9n8 in
7.075 ac-ft
HYG Volume •.. 7.075 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc= .16670 hrs CID: None Selected)
Computational Iner, Tm= .02223 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/C1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 115.92 cfs
Unit peak time Tp = .11113 hrs
Unit receding limb, Tr = .44453 hrs
Total unit time, Tb = .55567 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Pond Pack Ver: 5-05-97 :050 Compute Time: 10:00:50 Date: 01-08-1998
Type .••. SCS Unit Hyd. Surrrnary
Name •.•• SB-I POST Tag: Dev.10
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev.10
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 10 year storm
Page 3.09
Event: 10 yr
Duration = 24.0000 hrs Rain Depth = 7.4390 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File · ID = ASHFORD.HYG • SB-I POST Dev.10
Tc = • 1667 hrs
Drainage Area = 17.055 acres Runoff CN= 91
============================================
Co11'4'utational Time Increment =
C011'4'Uted Peak Time
C011'4'uted Peak Flow =
Time Increment for HYG File =
Peak Time, Interpolated Output
.02223 hrs
11. 9802 hrs
137.41 cfs
.0500 hrs
12.0000 hrs
Peak Flow, Interpolated Output = 135.25 cfs
WARNING: The difference between calculated peak flow
and interpolated peak flow is greater than 1.50%
============================================
DRAINAGE AREA
-------------------
ID:SB·I POST
CN = 91
Area 17.055 acres
s = .9890 in
0.2S = .1978 in
Cumulative Runoff
6.3710 in
9 .055 ac·ft
HYG Volume ••• 9.055 ac·ft Carea under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc= .16670 hrs CID: None Selected)
Computational Iner, Tm= .02223 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/C1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 115.92 cfs
Unit peak time Tp = .11113 hrs
Unit receding limb, Tr = .44453 hrs
Total unit time, Tb = .55567 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Type •..• SCS Unit Hyd. SlJllll8ry
Name ..•• SB-I POST Tag: Dev.25
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm .•• Type!! 24hr Tag: Dev.25
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 25 year storm
Page 3.10
Event: 25 yr
Duration = 24.0000 hrs Rain Depth = 8.8360 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-I POST Dev.25
Tc • 1667 hrs
Drainage Area = 17.055 acres Runoff CN= 91
============================================
Computational Time Increment
Computed Peak Time
= .02223 hrs
= 11. 9802 hrs
165.28 cfs Computed Peak Flow
Time Increment for HYG File = .0500 hrs
Peak Time, Interpolated Output 12.0000 hrs
Peak Flow, Interpolated Output 162.57 cfs
~ARNING: The difference between calculated peak flow
and interpolated peak flow is greater than 1.50%
============================================
DRAINAGE AREA
-------------------
ID:SB-1 POST
CN = 91
Area = 17 .055 acres
s = .9890 in
0.2S = .1978 in
Cl.lllUlative Runoff
7.7508 in
11.016 ac-ft
HYG Volume •.• 11.016 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc =
Computational Iner, Tm =
.16670 hrs CID: None Selected)
.02223 hrs = 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/(1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 115.92 cfs
Unit peak time Tp = .11113 hrs
Unit receding limb, Tr = .44453 hrs
Total unit time, Tb = .55567 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Type •••• scs Unit Hyd. Surrrnary
Name •••• SB-I POST Tag: Dev.SO
Page 3.11
Event: SO yr
File .••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev.SO
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: SO year storm
Duration = 24.0000 hrs Rain Depth = 10.3880 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID= SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID = ASHFORD.HYG -SB-I POST Dev.SO
Tc • 1667 hrs
Drainage Area = 17.0SS acres Runoff CN= 91
============================================
Computational Time Increment = .02223 hrs
Computed Peak Time = 11.9802 hrs
Computed Peak Flow 196.07 cfs
Time Increment for HYG File =
Peak Time, Interpolated Output =
.OSOO hrs
12.0000 hrs
Peak Flow, Interpolated Output = 192.77 cfs
YARNING: The difference between calculated peak flow
and interpolated peak flow is greater than 1.SO%
============================================
DRAINAGE AREA
ID:SB-1 POST
CN 91
Area =
s =
0.2S =
17.055 acres
.9890 in
.1978 in
Cl.lllUlative Runoff
9.2887 in
13.202 ac-ft
HYG Volume •.• 13.201 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc= .16670 hrs CID: None Selected)
Computational Iner, Tm= .02223 hrs= 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/64S.333, K = .7491 (also, K = 2/C1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1. 6698 C solved from K = .7491)
Unit peak, qp = 115.92 cfs
Unit peak time Tp = .11113 hrs
Unit receding limb, Tr = .444S3 hrs
Total unit time, Tb = .SSS67 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
Type •••• SCS Unit Hyd. Surrmary
Name •••. SB-I POST Tag: Dev100
File •••• E:\HAESTAD\PONDPACK\PPK6\ASHFORD\ASHFORDC.PPK
Storm ••• Type!! 24hr Tag: Dev100
SCS UNIT HYDROGRAPH METHOD
STORM EVENT: 100 year storm
Page 3.12
Event: 100 yr
Duration = 24.0000 hrs Rain Depth = 11.3530 in
Rain Dir = J:\HAESTAD\PPK6\UTIL\
Rain File -ID = SCSTYPES.RNF -Type!! 24hr
Unit Hyd Type= Default Curvilinear
HYG Dir = E:\HAESTAD\PONDPACK\PPK6\ASHFORD\
HYG File -ID= ASHFORD.HYG -SB-I POST Dev100
Tc = .1667 hrs
Drainage Area = 17.055 acres Runoff CN= 91
============================================
Computational Time Increment
Computed Peak Time
= .02223 hrs
= 11.9802 hrs
= 215.15 cfs Computed Peak Flow
Time Increment for HYG File = .0500 hrs
Peak Time, Interpolated Output 12.0000 hrs
Peak Flow, Interpolated Output = 211.48 cfs
~ARNING: The difference between calculated peak flow
and interpolated peak flow is greater than 1.50%
============================================
DRAINAGE AREA
ID:SB·I POST
CN = 91
Area = 17.055 acres
s .9890 in
0.2S = .1978 in
Cumulative Runoff
10.2467 in
14.563 ac-ft
HYG Volume .•• 14.563 ac-ft (area under HYG curve)
***** UNIT HYDROGRAPH PARAMETERS *****
Time Concentration, Tc= .16670 hrs (ID: None Selected)
Computational Iner, Tm= .02223 hrs= 0.20000 Tp
Unit Hyd. Shape Factor= 483.432 (37.46% under rising limb)
K = 483.43/645.333, K = .7491 (also, K = 2/(1+(Tr/Tp))
Receding/Rising, Tr/Tp = 1.6698 (solved from K = .7491)
Unit peak, qp = 115.92 cfs
Unit peak time Tp = .11113 hrs
Unit receding limb, Tr = .44453 hrs
Total unit time, Tb = .55567 hrs
S/N: HOMOL0120356 KLING ENGINEERING & SURVEYING
APPENDIXS
HYDRAULIC CALCULATIONS
100 YR-WSEL ESTIMATE SECTION D-D
Worksheet for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e :\haestad\pi\ashford\ashford.fm2
CHANNEL SECTION D-D (SCS)
Irregular Channel
Manning's Formula
Solve For Water Elevation
Input Data
Channel Slope 0.019000 V : H
Elevation range: 270.00 ft to 276 .00 ft.
Station (ft) Elevation (ft)
-97.80 276 .00
0.00 274 .00
3.40 272.00
13.30 270.00
30.60 272.00
47.20 274.00
95.00 276 .00
Discharge 890.00 ft3/s
Results
Wtd. Mannings Coefficient 0.050
Water Surface Elevation 274 .81
Flow Area 163.81
Wetted Perimeter 107.24
Top Width 106.23
Depth 4.81
Critical Water Elev. 274 .31
ft
ft2
ft
ft
ft
ft
Start Station
-97 .80
Critical Slope 0.031009 V: H
Velocity 5.43 ft/s
Velocity Head 0.46 ft
Specific Energy 275.27 ft
Froude Number 0.77
Full Flow Capacity 2041.58 ft3/s
Flow is subcritical.
Kl ing Engineering & Surveying
End Station
95.00
Jan 8 , 1998
13:06:37 Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
Roughness
0 .050
FlowMaster v4 .1 c
Page 1 of 1
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Section Data
Cross Section D-D
Cross Section for Irregular Channel
e :\haestad\pi\ashford\ashford. fm2
CHANNEL SECTION D-D (SCS)
Irregular Channel
Manning's Formula
Water Elevation
Wtd. Mannings Coefficient
Channel Slope
0.050
0.019000 V : H
Water Surface Elevation
Discharge
276.0 ~
274.81 ft
890.00 ft3/s
~ ~ "--.. 275.0
274.0
2 -
c:
.Q 273.0 .... ca > Q)
jjj
272 .0
271 .0
270.0
" .......,.
~ ...
~
\ v·
-100.0 -80 .0 -60 .0 -40 .0 -20 .0 0.0 20.0
Station (ft)
Kling Engineering & Surveying
v
I
I
I
40.0 60 .0
Jan 8,1998
13:11 :55 Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
/
,..
/
I
80.0 100.0
FlowMaster v4.1 c
Page 1 of 1
100 YR -WSEL ESTIMATE SECT D-D-FILLED
Worksheet for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e :\haesta d\pi\ashford\ashford. fm2
CHANNEL SECTION D-D (FILLED)
Irregular Channel
Manning's Formula
Solve For Water Elevation
Input Data
Channel Slope 0.019000 V : H
Elevation range: 270.00 ft to 276.00 ft.
Station (ft) Elevation (ft)
-97 .80 276.00
0.00 275.50
10.50 272.00
16 .50 270.00
30 .60 272.00
47 .20 274.00
95 .00 276.00
Discharge 890.00 ft3/s
Results
Wtd. Mannings Coefficient 0.050
Water Surface Elevation 274.99 ft
Flow Area 138.48 ft2
Wetted Perimeter 70.47 ft
Top Width 69 .38 ft
Depth 4.99 ft
Critical Water Elev. 274 .59 ft
Critical Slope 0.029960 V : H
Velocity 6.43 ft/s
Velocity Head 0.64 ft
Specific Energy 275.63 ft
Froude Number 0.80
Flow is subcritical.
Start Station
-97.80
End Station
95.00
01/08198
03:47:44 PM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
Roughness
0.050
FlowMaster v5.12
Page 1 of 1
Cross Section D-D (FILLED)
Cross Section for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e :\ha estad\pi\ashford\ashford. fm2
CHANNEL SECTION D-D (FILLED)
Irregular Channel
Manning's Formula
Solve For Water Elevation
Section Data
Wtd. Mannings Coefficient
Channel Slope
Water Surface Elevation
Discharge
276 .0
275 .0
274 .0
c:
.Q 273.0 ... ca > Q) w
272 .0
271 .0
270.0
---
0.050
0.019000 V: H
274.99 ft
890.00 ft3/s
----r---r---
I
I
v
-100.0 -80 .0 -60 .0 -40.0 -20.0 0 .0 20.0
Station (ft)
~
'!F
I v
I
40.0 60.0
01/08/98
03:47:15 PM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
-
/
I
80.0 100.0
FlowMaster v5 .12
Page 1 of 1
100 YR-WSEL ESTIMATE SECTION d'-d'
Worksheet for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e :\haestad\pi\ashford\ashford. fm2
CHANNEL SECTION d'-d'
Irregular Channel
Manning's Formula
Solve For Water Elevation
Input Data
Channel Slope 0.005900 V : H
Elevation range: 269.20 ft to 276 .00 ft .
Station (ft) Elevation (ft)
0.00 274.00
92.88 272.00
128.38 270.00
131.20 269.20
135.62 270.00
161.43 272.00
185.74 274.00
255.79 276.00
Discharge 890 .00 ft3/s
Results
Wtd. Mannings Coefficient 0.050
Water Surface Elevation 273.69 ft
Flow Area 278.45 ft2
Wetted Perimeter 168.06 ft
Top Width 167.66 ft
Depth 4.49 ft
Critical Water Elev. 272.68 ft
Critical Slope 0.033694 V : H
Velocity 3.20 ft/s
Velocity Head 0.16 ft
Specific Energy 273 .85 ft
Froude Number 0.44
Flow is subcritical.
Start Station
0.00
End Station
255 .79
01/08/98
03:38:37 PM Haestad Methods, Inc . 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
Roughness
0.050
FlowMaster v5 .12
Page 1of1
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Section Data
Cross Section d'-d'
Cross Section for Irregular Channel
e:\haestad\pi\ashford\ashford.fm2
CHANNEL SECTION d'-d'
Irregular Channel
Manning's Formula
Water Elevation
Wtd. Mannings Coefficient
Channel Slope
0.050
0.005900 V : H
Water Surface Elevation
Discharge
273.69 ft
890.00 ff'/s
269 .0'--~~~~-'-~~~~--'~~~~~-'--~~~~--L~~~~~-"-~~~~_J
01/08/98
03:38:25 PM
0.0 50.0 100.0 150.0
Station (ft)
200.0
Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
250.0 300.0
FlowMaster v5 .12
Page 1 of 1
100 YR -WSEL EST. SECT. d'-d'-FILLED
W orksheet for Irreg ul ar Chan nel
Project Description
Project File
Worksheet
Flow Element
Method
e :\ha estad\pi\ashford\ashford. fm2
CHANNEL SECTION d'-d' (FILLED)
Irregular Channel
Manning's Formula
Solve For Water Elevation
Input Data
Channel Slope 0.005900 V : H
Elevation range: 269 .20 ft to 276.00 ft.
Station (ft) Ele vation (ft)
0.00 274 .00
78 .50 274 .25
92.88 272.00
128.38 270 .00
131.20 269.20
135.62 270 .00
161.43 272.00
185.74 274 .00
255 .79 276 .00
Discharge 890.00 ft3/s
Results
Wtd. Mannings Coefficient 0.050
Water Surface Elevation 273.76 ft
Flow Area 227 .73 ft2
Wetted Perimeter 101 .66 ft
Top Width 101 .13 ft
Depth 4.56 ft
Critical Water Elev. 272 .63 ft
Critical Slope 0.031588 V : H
Velocity 3.91 ft/s
Velocity Head 0.24 ft
Specific Energy 273 .99 ft
Froude Number 0.46
Flow is subcritical.
Start Station
0.00
End Station
255 .79
01 /08/98
03:57:11 PM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
Roughness
0.050
FlowMaster v5. 12
Page 1 of 1
Cross Section d'-d' (FILLED)
Cross Section for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Section Data
e:\haestad\pi\ashford\ashford.fm2
CHANNEL SECTION d'-d' (FILLED)
Irregular Channel
Manning's Formula
Water Elevation
Wtd. Mannings Coefficient
Channel Slope
0.050
0.005900 V : H
Water Surface Elevation
Discharge
276.0
275.
274.
£273. -
c:
0 :;:;
11' > Q,) ill 272 .
271 .
270.
0
-
0
0
0
0
0
273.76 ft
890.00 ft3/s
-,
\ ~
\ 'SF
,
\
\
I\
\/
I I
~
/
I
I
I
I
/
269 .
0 .0 50.0 100.0 150.0
Station (ft)
200.0
-V"
/
250 .0
01/08198
03:56:25 PM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
300.0
FlowMaster vS .12
Page 1 of 1
100 YR -WSEL ESTIMATE SECTION E-E (PRE)
Worksheet for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e:\haestad\pi\as hford\ashford.fm2
CHANNEL SECTION E-E (SCS}
Irregular Channel
Ma nni ng's For mul a
Solve For Water Elevation
Input Data
Channel Slope 0.006000 V : H
Elevation range: 266.00 ft to 273.00 ft.
Station (ft} Elevation (ft}
0.00 273.00
41 .60 272.00
66 .30 271.00
80 .00 271 .00
159.50 271.30
179.00 271 .00
194.00 270 .00
199.70 269 .00
220.50 268.00
221 .80 267 .00
223 .20 266.00
227.60 266 .00
228 .70 267 .00
229.80 268 .00
231 .00 269 .00
231 .90 270 .00
234.70 271 .00
259 .60 272.00
284.70 273 .00
Discharge 959 .30 ft3/s
Results
Wtd . Mannings Coefficient 0.050
Water Surface Elevation 272.16
Flow Area 329.23
Wetted Perimeter 231 .19
Top Width 228.58
Depth 6.16
Critical Water Elev. 271.42
ft
ft2
ft
ft
ft
ft
Start Station
0.00
Critical Slope 0.038030 V : H
Velocity 2.91 ft/s
Velocity Head · 0.13 ft
Specific Energy 272 .29 ft
Froude Number 0.43
Full Flow Capacity 1923.25 ft3/s
Kling Engineering & Surveying
End Station
284 .70
Jan 8 , 1998
13:01 :25 Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
Roughness
0.050
FlowMaster v4.1 c
Page 1of2
Cross Section E-E (PRE)
Cross Section for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Section Data
e :\ha estad\pi\ashford\ashford. fm2
CHANNEL SECTION E-E (SCS)
Irregular Channel
Manning's Formula
Water Elevation
Wtd. Mannings Coefficient
Channel Slope
0 .050
0.006000 V : H
Water Surface Elevation
Discharge
273.
272 .
271 .
£270. .......
c
0
~
nJ > Q) m 269.
n
0
0
0
0
268. 0
267. 0
0
~
"
272.16 ft
959.30 ft3/s
\
~
.. 7
;
~
"' \
\
266.
0.0 50.0 100.0 150.0
Station (ft)
200.0
Kling Engineering & Surveying
7
I
I
250.0
Jan 8 , 1998
13:01 :38 Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
"' I
300.0
FlowMaster v4.1 c
Page 1 of 1
100 YR -WSEL ESTIMATE SECT. E-E-FILLED
Worksheet for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e :\haestad\pi\ashford\ashford.fm2
CHANNEL SECTION E-E (FILLED)
Irregular Channel
Manning's Formula
Solve For Water Elevation
Input Data
Channel Slope 0.006000 V : H
Elevation range: 266 .00 ft to 273 .50 ft .
Station {ft) Elevation {ft)
0.00 273.00
159.50 273 .50
179.00 273 .50
182.00 271.50
183 .50 271 .00
194.00 270 .00
199.70 269 .00
220 .50 268.00
221 .80 267 .00
223.20 266 .00
227 .60 266 .00
228 .70 267 .00
229.80 268 .00
231.00 269 .00
231 .90 270 .00
234 .70 271 .00
259 .60 272 .00
284 .70 273 .00
Discharge 960 .00 ft3/s
Results
W t d . Mannings Coe ffi cient 0.050
Water Surface Elevati on 272 .64 ft
Flow Area 234.16 ft2
Wetted Perimete r 98 .52 ft
Top W idth 95.49 ft
Depth 6.64 ft
Critical Water Elev. 271 .01 ft
Critical Slope 0.029853 V : H
Velocity 4.10 ft/s
Velocity Head 0.26 ft
Specific Energy 272 .91 ft
Froude Number 0.46
Flow is subcritical.
Start Station
0.00
End Station
284 .70
01/08/98
04:09:30 PM Haestad Methods, Inc. 37 Brookside Road Waterbu ry, CT 06708 (203) 755-1666
Roughness
0.050
FlowMaster v5.12
Page 1 of 2
Cross Section E-E (FILLED)
Cross Section for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Section Data
e:\haestad\pi\ashford\ashford.fm2
CHANNEL SECTION E-E (FILLED}
Irregular Channel
Manning's Formula
Water Elevation
Wtd. Mannings Coefficient
Channel Slope
0.050
0.006000 V : H
Water Surface Elevation
Discharge
274.0
273. n
272 . 0
271 . 0
c ~ 270. 0
I'll > Q) w
269. 0
268 . 0
267. 0
266 .0
272.64 ft
960 .00 ft3/s
\
\
I\
0.0 50.0 100.0 150.0
Station {ft)
200.0
.,...,, -I v
I
250.0
01/08/98
04:09:14 PM Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
,....
/
300.0
FlowMaster v5 .12
Page 1 of 1
100 YR-WSEL ESTIMATE SECTION F-F (PRE)
Worksheet for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e:\haestad\pi\ashford\ashford.fm2
CHANNEL SECTION F-F (SCS)
Irregular Channel
Manning's Formula
Solve For Water Elevation
Input Data
Channel Slope 0.008000 V : H
Elevation range: 263.00 ft to 272.00 ft.
Station (ft) Elevation (ft)
-50.00 272.00
0.00 271 .00
21.00 270.00
30.80 269 .00
40.60 268.00
49.80 267 .00
51 .00 266 .00
52 .30 265.00
53 .50 264 .00
59 .20 263.00
59.90 263 .00
60 .60 264.00
61 .30 265 .00
61 .90 266 .00
62.80 267.00
71.60 268.00
80.60 269 .00
93.40 270 .00
193.40 272.00
Discharge 959 .30 ff'/s
Results
Wtd. Mannings Coefficient 0.050
Water Surface Elevation 270.85
Flow Area 244.42
Wetted Perimeter 136.23
Top Width 132.69
Depth 7.85
Critical Water Elev. 269.42
ft
ft2
ft
ft
ft
ft
Start Station
-50 .00
Critical Slope 0.031130 V: H
Velocity 3.92 ft/s
Velocity_ H~ad 0.24 ft
Specific Energy 271.09 ft
Froude Number 0.51
Full Flow Capacity 1841 .97 ff'/s
Kling Engineering & Surveying
End Station
193.40
Jan 8, 1998
13:03:48 Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
Roughness
0 .050
FlowMaster v4.1 c
Page 1 of 2
Cross Section F-F (PRE)
Cross Section for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e:\haestad\pi\ashford\ashford.fm2
CHANNEL SECTION F-F (SCS)
Irregular Channel
Manning's Formula
Solve For Water Elevation
Section Data
Wtd. Mannings Coefficient
Channel Slope
Water Surface Elevation
Discharge
272 .
271 .
270.
269.
~ ~268 .
c:
0 ;
l1l
~ 267.
iTI
266.
265.
264.
n
o~
0
0
0
0
0
0
0
0
0.050
0 .008000 V : H
270 .85 ft
959 .30 ft3/s
!'\.
""' \
\
\
\
~~
= v ~
I
I
I
263 .
-50.0 0 .0 50.0 100.0
Station (ft)
Kling Engineering & Surveying
~
_/
,/
150.0 200.0
Jan 8 , 1998
13:04:17 Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v4.1 c
Page 1 of 1
100 YR-WSEL ESTIMATE SECTION F-F -POST
Worksheet for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e:\haestad\pi\ashford\ashford.fm2
CHANNEL SECTION F-F (SCS)
Irregular Channel
Manning's Formula
Solve For Water Elevation
Input Data
Channel Slope 0.008000 V : H
Elevation range: 263 .00 ft to 272.00 ft.
Station (ft) Elevation (ft)
-50 .00 272.00
0.00 271.00
21 .00 270.00
30.80 269 .00
40 .60 268.00
49 .80 267.00
51.00 266 .00
52 .30 265 .00
53.50 264.00
59 .20 263 .00
59.90 263 .00
60 .60 264.00
61 .30 265 .00
61 .90 266 .00
62 .80 267 .00
71.60 268 .00
80.60 269.00
93.40 270 .00
193.40 272.00
Discharge 960 .00 ft3/s
Results
Wtd . Mann ing s Coefficient 0.050
Water Surface Elevation 270.85
Flow Area 244.59
Wetted Perimeter 136.32
Top Width 132.78
Depth 7.85
Critical Water Elev. 269.42
ft
ft2
ft
ft
ft
ft
Start Station
-50.00
Critical Slope 0.031128 V : H
Velocity 3.92 ft/s
Velocity Head 0.24 ft
Specific Energy 271.09 ft
Froude Number 0.51
Full Flow Capacity 1841.97 ft3/s
Kling Engineering & Surveying
End Station
193 .40
Jan 8 ,1998
13:04:47 Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
Roughness
0.050
FlowMastar v4.1c
Page 1 of 2
100 YR-WSEL ESTIMATE SECTION G-G (PRE)
Worksheet for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e:\haestad\pi\ashford\ashford.fm2
CHANNEL SECTION G-G (SCS}
Irregular Channel
Manning's Formula
Solve For Water Elevation
Input Data
Channel Slope 0.008500 V : H
Elevation range: 263 .05 ft to 269.20 ft.
Station (ft} Elevation (ft}
0.00 269.20
220.87 268.00
369.39 266.00
381.30 264 .00
386.97 263.05
392 .76 264 .00
403.44 266 .00
522.68 268.00
Discharge 959.30 ft3/s
Results
Wtd. Mannings Coefficient 0.050
Water Surface Elevation 267.75
Flow Area 314.87
Wetted Perimeter 268.54
Top Width 268.00
Depth 4.70
Critical Water Elev. 267.13
ft
ft2
ft
ft
ft
ft
Start Station
0.00
Critical Slope 0.037297 V : H
Velocity 3.05 ft/s
Velocity Head 0.14 ft
Specific Energy 267.89 ft
Froude Number 0.50
Full Flow Capacity 3414.47 ft3/s
Flow is subcritical.
Kling Engineering & Surveying
End Station
522.68
Jan 8 , 1998
13:05:14 Haestad Methods. Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
Roughness
0.050
FlowMaster v4.1 c
Page 1 of 1
Cross Section G-G (PRE)
Cross Section for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e:\haestad\pi\ashford\ashford.fm2
CHANNEL SECTION G-G (SCS)
Irregular Channel
Manning's Formula
Solve For Water Elevation
Section Data
Wtd. Mannings Coefficient
Channel Slope
Water Surface Elevation
Discharge
270.0
('-.
---~ 269.0
268.0
2267.0 ........
0 .050
0.008500 V : H
267 .75 ft
959 .30 ft3/s
~ ~ --"'-.
" ~
or-7
lllF
c:
0
+:l
Ill >
a.> jjj 266 .0
~ ~
265 .0
264.0
~
" / v
/
263.0
0.0 50.0 100.0 150.0 200.0 250.0 300.0 350.0 400.0 450.0 500.0 550.0
Station (ft)
Jan 8, 1998
13:05:24
Kling Engineering & Surveying
Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v4.1 c
Page 1 of 1
100 YR -W SEL ESTIMATE SECTION G-G -POST
Worksheet for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e :\haestad\pi\ashford\ashford. f m2
CHANNEL SECTION G-G (SCS)
Irregu lar Channel
Man ning's Formula
Solve For Water Elevation
Input Data
Channel Slope 0.008500 V : H
Elevation range: 263.05 ft to 269.20 ft.
Station (ft) Elevation (ft)
0.00 269.20
220 .87 268.00
369.39 266 .00
381.30 264.00
386.97 263.05
392.76 264.00
403.44 266.00
522.68 268.00
Discharge 960 .00 ft3/s
Results
Wtd. Mannings Coefficient 0.050
Water Surface Elevation 267.75
Flow Area 315.05
Wetted Perimeter 268.63
Top Width 268.09
Depth 4.70
Critical Water Elev . 267.13
ft
ft2
ft
ft
ft
ft
Start Station
0.00
Critical Slope 0.037294 V : H
Velocity 3.05 ft/s
Velocity Head 0.14 ft
Specific Energy 267 .89 ft
Froude Number 0.50
Full Flow Capacity 3414.47 ft3/s
Flow is subcritical.
Kling Engineering & Surveying
End Station
522.68
Jan 8, 1998
13:05:44 Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
Roughness
0.050
FlowMaster v4.1 c
Page 1 of 1
SOUTHSTREETSECTION10YREVENT
Worksheet for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e :\ha estad\pi\ashford\ashford. fm2
SOUTH STREET SECTION
Irregular Channel
Manning's Formula
Solve For Water Elevation
Input Data
Channel Slope 0.006000 V : H
Elevation range: 0.00 ft to 1.70 ft .
Station (ft) Elevation (ft)
0.00 1.70
6.00
6.50
6.50
20 .00
33.50
33.50
34.00
40.00
Discharge
Results
Wtd. Mannings Coefficient
Water Surface Elevation
Flow Area
Wetted Perimeter
Top Width
Depth
0 .50
0.50
0.00
0.50
0.00
0.50
0.50
1.70
81.60
0.013
0.78
14.93
31.86
30.78
0.78
0.90
ft3/s
ft
ft2
ft
ft
ft
ft Critical Water Elev.
Critical Slope
Velocity
0.002933 V : H
Velocity Head
Specific Energy
Froude Number
Full Flow Capacity
Flow is supercritical.
5.47
0.46
1.24
1.38
464.45
ft/s
ft
ft
ft3/s
Start Station
0.00
6.00
34.00
Kling Engineering & Surveying
End Station
6.00
34.00
40.00
Dec 24, 1997
09:36:28 Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
Roughness
0.030
0.013
0.030
FlowMaster v4.1 c
Page 1 of 1
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
Channel Slope
SOUTH STREET SECTION 25 YR EVENT
Worksheet for Irregular Channel
e :\ha estad\pi\ashford\ashfor d. fm2
SOUTH STREET SECTION
Irregular Channel
Ma nning's Formula
Water Elevation
0.006000 V : H
Elevation range: 0.00 ft to 1.70 ft .
Station (ft) Elevation (ft) Start Station
0.00
6 .00
34.00
0.00 1.70
6.00 0.50
6 .50 0.50
6 .50 0.00
20.00 0.50
33.50 0.00
33 .50 0.50
34.00 0.50
40 .00 1.70
Discharge 93.20 ft3/s
Results
Wtd. Mannings Coefficient 0.013
Water Surface Elevation 0.82 ft
Flow Area 16.25 ft2
Wetted Perimeter 32 .29 ft
Top Width 31.21 ft
Depth 0.82 ft
Critical Water Elev. 0.96 ft
Critical Slope 0.002860 V : H
Velocity 5.74 ft/s
Velocity Head 0.51 ft
Specific Energy 1.33 ft
Froude Number 1.40
Full Flow Capacity 464.45 ft3/s
Flow is supercritical.
Kling Engineering & Surveying
End Station
6.00
34.00
40 .00
Dec 24, 1997
09:37:09 Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
Roughness
0.030
0.013
0 .030
FlowMaster v4.1 c
Page 1 of 1
SOUTH STREET SECTION 100 YR EVENT
Worksheet for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e:\haestad\pi\ashford\ashford.fm2
SOUTH STREET SECTION
Irregular Channel
Manning's Formula
Solve For Water Elevation
Input Data
Channel Slope 0.006000 V : H
Elevation range: 0.00 ft to 1.70 ft.
Station (ft) Elevation (ft)
0.00 1.70
6.00
6.50
6.50
20 .00
33.50
33.50
34 .00
40.00
Discharae
Results
Wtd. Mannings Coefficient
Water Surface Elevation
Flow Area
Wetted Perimeter
Top Width
Depth
0 .50
0.50
0.00
0.50
0.00
0.50
0.50
1.70
110.00
0.013
0.88
18.08
32.88
31 .79
0.88
1.04
ft3/s ~
ft
ft2
ft
ft
ft
ft Critical Water Elev.
Critical Slope
Velocity
0.002776 V : H
6.09 ft/s
0.58 ft
1.45 ft
1.42
Start Station
0.00
6 .00
34.00
End Station
6.00
34.00
40 .00
Velocity Head
Specific Energy
Froude Number
Full Flow Capacity
Flow is supercritical.
464.45 ft3/s Q 0 \..1-J -to 'R 0 '-.-0
Dec 24, 1997
09:35:31
Kling Engineering & Surveying
Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
Roughness
0.030
0.013
0.030
FlowMaster v4.1 c
Page 1 of 1
SOUTH STREET SECTION 100 YR
Cross Section for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Section Data
e:\haestad\pi\ashford\ashford.fm2
SOUTH STREET SECTION
Irregular Channel
Manning's Formula
Water Elevation
Wtd. Mannings Coefficient
Channel Slope
0 .013
0.006000 V : H
Water Surface Elevation
Discharge
1 .8
()
1 .6
1.4
1 .2
~
:=, 1 .0
c
0 ;;
<ll
~ 0 .8
jjj
0 .6
\
\
\
\
\
\
' \
0.88 ft
110 .00 ft3/s
'<"t7
;~
\ / "" 0.4
0 .2 /
/
/
/ "" "'
0 .0
0.0 5.0 10.0 15.0 20.0 25.0
Station (ft)
Kling Engineering & Surveying
~ ~I
30.0
Oec 24, 1997
09:34:10 Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203} 755-1666
I)
J
I
I
I
I
I
I
I
J
35.0 40.0
FlowMaster v4.1 c
Page 1 of 1
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
Channel Slope
NE STREET SECTION 10 YR EVENT
Worksheet for Irregular Channel
e:\haestad\pi\ashford\ashford .fm2
NE STREET SECTION
Irregular Channel
Manning's Formula
Water Elevation
0.016600 V : H
Elevation range: 0 .00 ft to 1.70 ft.
Station (ft) Elevation (ft) Start Station
0.00
6.00
34.00
0.00 1.70
6 .00 0.50
6.50 0.50
6.50 0.00
20 .00 0.50
33 .50 0.00
33.50 0.50
34.00 0.50
40.00 1.70
Discharge 28.70 ft3/s
Results
Wtd. Mannings Coefficient 0.013
Water Surface Elevation 0.45 ft
Flow Area 5.42 ft2
Wetted Perimeter 25.10 ft
Top Width 24.19 ft
Depth 0.45 ft
Critical Water Elev. 0.58 ft
Critical Slope 0.003701 V : H
Velocity 5.30 ft/s
Velocity Head 0.44 ft
Specific Energy 0.88 ft
Froude Number 1.97
Full Flow Capacity 772.54 ft3/s
Flow is supercritica l.
Flow is divided .
Kling Engineering & Surveying
End Station
6.00
34.00
40 .00
Dec 24, 1997
09:47:08 Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
Roughness
0.030
0.013
0.030
FlowMaster v4. 1 c
Page 1 of 1
NESTREETSECTION10YR
Cross Section for Irregular Channel
Project Description
Project File
Worksheet
Flow Element
Method
e :\haestad\pi\ashford\ashford. fm2
NE STREET SECTION
Irregular Channel
Manning's Formula
Solve For Water Elevation
Section Data
Wtd. Mannings Coefficient
Channel Slope
Water Surface Elevation
Discharge
1 .8
(
1 .6
1.4
1.2
~
:t:.-1 .0
c
0 :;::: ca
~ 0 .8
[jj
0 .6
0.4
\
\
\
\
\
' \
\
0.013
0.016600 V : H
0.45 ft
28.70 ft3/s
..........
= /
/
/ ........
..........
........
....
0 .2
"'-/ ~
O.b
0 .0 5 .0
/
/
10.0 15.0 20 .0 25.0
Station (ft)
Kling Engineering & Surveyi ng
"-. ~
30.0
Dec 24, 1997
09:47:46 Haestad Methods, Inc. 37 Brookside Road . Waterbury, CT 06708 (203) 755-1666
(~
I
I
I
I
I
I
I
]
35.0 40.0
FlowMaster v4.1 c
Page 1 of 1
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Input Data
Mannings Coefficient
Channel Slope
Depth
Left Side Slope
Right Side Slope
Bottom Width
Results
Discharge
Flow Area
Wetted Perimeter
Top Width
Critical Depth
Critical Slope
Velocity
Velocity Head
Specific Energy
Froude Number
Flow is subcritical.
Dec 24, 1997
09:33:31
Swale A-A 100 year flow -no backwater
Worksheet for Trapezoidal Channel
e :\ha esta d\pi\ashford\ashford. fm2
SWALE TO CREEK
Trapezoidal Channel
Manning's Formula
Discharge
0.030
0.013000 V : H
1.50 ft
3.00 H: V
3.00 H : V
8.00 ft
110.93 ft3/s
18.75 ft2
17.49 ft
17 .00 ft
1.49 ft
0.013193 V: H
5.92 ft/s
0.54 ft
2.04 ft
0.99
Kling Engineering & Surveying
Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
FlowMaster v4.1 c
Page 1 of 1
Project Description
Project File
Worksheet
Flow Element
Method
Solve For
Section Data
Mannings Coefficient
Channel Slope
Depth
Left Side Slope
Right Side Slope
Bottom Width
Discharge
Cross Section Swale A-A
Cross Section for Trapezoidal Channel
e:\haesta d\pi\ashford\ashford. fm2
SWALE TO CREEK
Trapezoidal Channel
Manning's Formula
Discharge
0 .030
0 .013000 V : H
1.50 ft
3.00 H :V
3.00 H:V
8.00 ft
110.93 ft3/s
~ sz ~ ---~--_....__-~--=r1 .50ft
Dec 24, 1997
09:32:31
I. .I
8 .00 ft
Kling Engineering & Surveying
Haestad Methods, Inc. 37 Brookside Road Waterbury, CT 06708 (203) 755-1666
H 1
NTS
FlowMaster v4.1 c
Page 1 of 1
APPENDIX 6
REPLAT