HomeMy WebLinkAbout26 USDA 04-55 1001 Holleman Dr E({~ DEVELOPMENT PERMIT
PERMIT NO. 04-55B
Project: USDA
COLllGl STATION FOR AREAS OUTSIDE THE SPECIAL FLOOD HAZARD AREA
RE: CHAPTER 13 OF THE COLLEGE STATION CITY CODE
SITE LEGAL DESCRIPTION:
USDA Subdivision
Block 1
Lot 1
DATE OF ISSUE: 02/01/05
OWNER:
Curtis Investments c/o Chris Curtis
5641 Yale Blvd, Suite 100
Dallas, Texas 75206
TYPE OF DEVELOPMENT:
SPECIAL CONDITIONS:
SITE ADDRESS:
1001 Holleman Drive East
DRAINAGE BASIN:
Wolf Pen Creek
VALID FOR 12 MONTHS
CONTRACTOR:
Full Development Permit
All construction must be in compliance with the approved construction plans
All trees required to be protected as part of the landscape plan must be completely barricaded in accordance with Section
7 .5.E., Landscape/Streetscape Plan Requirements of the City's Unified Development Ordinance, prior to any operations of
this permit. The cleaning of equipment or materials within the drip line of any tree or group of trees that are protected and
required to remain is strictly prohibited . The disposal of any waste material such as, but not limited to, paint, oil, solvents,
asphalt, concrete, mortar, or other harmful liquids or materials within the drip line of any tree required to remain is also
prohibited .
TCEQ PHASE II RULES IN EFFECT.
The Contractor shall take all necessary precautions to prevent silt and debris from leaving the immediate construction site
in accordance with the approved erosion control plan as well as the City of College Station Drainage Policy and Design
Criteria . If it is determined the prescribed erosion control measures are ineffective to retain all sediment onsite , it is the
contractors responsibility to implement measures that will meet City, State and Federal requirements . The Owner and/or
Contractor shall assure that all disturbed areas are sodden and establishment of vegetation occurs prior to removal of any
silt fencing or hay bales used for temporary erosion control. The Owner and/or Contractor shall also insure that any
disturbed vegetation be returned to its original condition, placement and state . The Owner and/or Contractor shall be
responsible for any damage to adjacent properties, city streets or infrastructure due to heavy machinery and/or equipment
as well as erosion, siltation or sedimentation resulting from the permitted work .
In accordance with Chapter 13 of the Code of Ordinances of the City of College Station, measures shall be taken to insure
that debris from construction, erosion, and sedimentation shall not be deposited in city streets, or existing drainage
facilities .
I hereby grant this permit for development of an area outside the special flood hazard area . All development shall be in
accordance with the plans and specifications submitted to and approved by the City Engineer in the development permit
application for the above named project and all of the codes and ordinances of the City of College Station that apply.
oz-oL-os
Owner/Agent/Contractor Date
~-~ DEVELOPMENT PERMIT
PERMIT NO. 04-55A
Project: USDA
COlllGl ~TAHON FOR AREAS OUTSIDE THE SPECIAL FLOOD HAZARD AREA
RE : CHAPTER 13 OF THE COLLEGE STATION CITY CODE
SITE LEGAL DESCRIPTION:
USDA Subdivision
Block 1
Lot 1
DATE OF ISSUE: 09/28/04
OWNER:
Curtis Investments c/o Chris Curtis
5641 Yale Blvd , Suite 100
Dallas, Texas 75206
TYPE OF DEVELOPMENT:
SPECIAL CONDITIONS:
SITE ADDRESS:
1001 Holleman Drive East
DRAINAGE BASIN:
Wolf Pen Creek
VALID FOR 6 MONTHS
CONTRACTOR:
Clearing and Grading Permit
All construction must be in compliance with the approved construction plans
All trees required to be protected as part of the landscape plan must be completely barricaded in accordance with Section
7 .5.E ., Landscape/Streetscape Plan Requirements of the City's Unified Development Ordinance, prior to any operations of
this permit. The cleaning of equipment or materials within the drip line of any tree or group of trees that are protected and
required to remain is strictly prohibited . The disposal of any waste material such as, but not limited to , paint, oil , solvents ,
asphalt, concrete, mortar, or other harmful liquids or materials within the drip line of any tree required to remain is also
prohibited .
TCEQ PHASE II RULES IN EFFECT .
The Contractor shall take all necessary precautions to prevent silt and debris from leaving the immediate construction site
in accordance with the approved erosion control plan as well as the City of College Station Drainage Policy and Design
Criteria . If it is determined the prescribed eros ion control measures are ineffective to retain all sediment onsite , it is the
contractors responsibility to implement measures that will meet City, State and Federal requirements . The Owner and/or
Contractor shall assure that all disturbed areas are sodden and establishment of vegetation occurs prior to removal of any
silt fencing or hay bales used for temporary erosion control. The Owner and/or Contractor shall also insure that any
disturbed vegetation be returned to its original condition, placement and state. The Owner and/or Contractor shall be
responsible for any damage to adjacent properties , city streets or infrastructure due to heavy machinery and/or equipment
as well as eros ion , siltation or sedimentation resulting from the permitted work .
In accordance with Chapter 13 of the Code of Ordinances of the City of College Station, measures shall be taken to insure
that debris from construction , erosion, and sedimentation shall not be deposited in city streets, or existing drainage
facil ities .
I hereby grant this perm it for development of an area outs ide the special flood hazard area . All development shall be in
accordance w ith the plans and specifications submitted to and approved by the City Engineer in the development permit
application for the above named project and all of the codes and ordinances of the City of College Station that app ly.
oq -d-6 -uf
Owner/ AgenUContractor
· ~ ill.Ii i: .i •iiiij·J· llllliil.11.1 1.6.!L_t _••_.··:.t_T .••.. •_•_:eo:_} .. •o••_,_••·_i/_:•s"."·T·u·iA_ .• •_~ T_.•· .. •···-···e•••·••sE·.·· .• i:.•o·.· •_.•.·e•·•_•·•.·e"F·•· .. iA_.N.•··_-•·_e _ ••. _:-r_ 1.•·_NM···_ F_.·e···.·F.:N··.··.·~.t i_:•.r.b.·::·· .... F~ ...• i.~.··.-4" ... ·o'_··.:··.Mm. ·.····.~.···.•~_.••_··.:u .. _F_1 •~_,._ .• •_u····•.•.:•R•·•.·.···e••.·•:·.;i_•·s:_::_.!u•_?_·a::_ •. _.o··._·:_~_:.·•,•·_l1"s_•·••••.••,·••_6_!!' .. ·.·N••• .. ·.•1i_i_•••••• ··: :::·i.•· j::i!:! :::: .. Ji
.. -:::::::========· . . . . . . '-~ ::•:: ::J:n :•:= n :n :•.=: :::•::: w. n .. :1:: t:v : -~rr:~ff::if ftf:fr::::::::::::::.
•:: ::. :: ........ • ::•E n••>· ·· : .... -.·-· ••: ..... __ .J.•·!.·~~~VY~.·m.'..·•.·•.·'.E.·.··•,il~§·~·:•·j:'··-.·•.••.•: ... _•:._ ......... ·;\ ...... ::::r:= ·==·<.-:;·:mt.· .::. <t t• ... :(? :: ::~{:)~:}~{:)~{\:ft }f ·:·:··-:-:-:-:-:-:-·-:-:-:-:.:-:;:;::::::/{:~::;::::::: :::::\\\\\;::::::::=·:-:-:-:-:·:· ff!{(( .·.·.·.·.·.·.·.·.· )}~:{ .;-:-:-:.:;::;::.:::::·:-:·:.·-·.·. ;:::::::;:;:;:;:::::;:::;::::::::; :::::::=::::;::::::::::·:·:·:-·.·.·.· .. .
. :•.• .. ·.•.: .. _._:_.•.•_·.···-· .. •.• .. •.• .. •.• .. •.· .. •.• .. •.• .. ·.• .. •.• .. •.• .. •.• .. •.•.·.·.• .. • .. • ... • .. • .. •.•_.•_.• .. •.•.·.··.•.-.•_ ::• : : . :: •r .. ·>.. .. A••·· · ...... : ...... ·:.··.•.·:.•·•.:.:.~.·• .... A.-... -..... :N .... -.. • ...•. P .. •.•· .... P..·• .••..•. R .... •·.···"······.·•.••.~.·· .• •.2.•.: ... ·.•.o ... ·.·.PA .... · .. : .. _ .. · .. _·_::.••-••-•·-••--•-•-••• .. •·t r••• J •·•-::: : •_:•_•:_•:_•:_::_:•_:•.••_-•_:•_•._. ·········································::.:·······················-·-·---..... ··· :::::~ :: =~= ~== ::::::{{:,::~:.:: ~:.:::_::: .. ::_•_:::.•_=~=.=·-····.:· •• _:· : . :· :·.·.·: ·:. :·: ·: .. ·:. :·; ·:·:·:. :· ... ·:· :·>: ·:·: ·:·:·:·:·:·:.: ·.·. · ..... ·. ·.· .· :;:::::::::::::::::::::::::::::::_·:.:: •. ::.::::::~: . . . ............... · .·• . .............. •, ·.·.·.·.·.·.· ..... . ::{{:~t~~tttt?f ~~{~~(~//~. :·:·=·=·:·=·=·=-=·=·=-:·=-:·:·>>=-=->=·=·:.:·:.:-: ::::::=: ::::::: /. rrrr~ -:::::~:~:~: ====:::=======:::;:<:=<·=·=· .. · ================: .·.·.·.·.·.·.·.· ............. ·.·.·.·.·.·.·.··=·=-:·=·=-:·=·=·=·=·=·:·::. ·=·:-:·'.·=·=·=-=·:-=.:-=·:·:-::.:·:·:·:·:·
===:::::::::::=:=:=:::=======:: l:::::=======:=========:::::========i·:J::::=:=:=:::::=:=:=======:::::::===i==::::: .. ;.;.;.;. =<·=-=·=···:·=·=·"=·===·::;::.:=:=:::::::=:::::=: .. :·: :~rt~r~t~~~fftff)]~~:}rf)::~=· =<:;:-:=::·.·==========·========:::::::=:==:=====:::::===:= :}(ff ~=~{{:~=~=~ =::::::::::::::: [::::===========:::::::::::::::::::::::=================:=:::::::::::::::::=: ,=======:::::::=:=========:::::=======::::========::::::::=:=::::::::::::::::
•. 1.ITE .•.•• N .•••••. O ....... :_ •.• _-•.:.-_.: .••.•..•. •_1.:.1_••.•a·.E·····~-·-····"·•···-····~-1.1_•.1.1.•• .1.1.•.•-•u•···.····N· ·_L.·_ .• _ ••.• _! .. ·.1.•.1.• 1.•.1·.•.i •. : •·rrEMPESCRJPTIQN&••erdde]t:J.•.vvokbst ......... ·_ ••.•• _.:,;•_· .• •_:.••_:.-·.•·.:_.1 .. •.-·.-• .• •.
0
....... •.• .•..•..• •.fJ ..... • .. ·····F··." .. •_._.J··· __ G:J_•·_-~·u ... ·~_·R·_._.PES·_···_e_•·_·!_:.:m .......... • .. ·.•_ ••.••.•..••.•.••.••.•• _.•.•_ ••. * .......... •.0
N·:·_ t_ .. _.•_ •. F•~_·•.·,··G:_.u•p!R.··_• __ ••.• E¢s•_-_··.E .•..•. • .• :.:.•·-•.•·_ •. _·_.• .•. · :1:::1.:1 1:1:=: ::~:~:~:~:;.:.:-:·:·:·:·:·:·:·:·:·:·:·:·:·:·:·'.·:·:·:·:·:·:·:·: .:·:::::·:::::::::::::::::::;:::::::::::::;:::::::;:;:;:;:::: :::::::::::::::::::::::::::: :.:·:·:·:·:·:·:·:·:·:···:·:·:·:·:·:·:·.·'.·:···:·:···:·:·:·:···:·=·=·=·=···:·:·:·:·:·:·:·:·:·:
WATER LINE
1 624
2 40
3 4
4 1
5
6 2
7
8 1
LF Furnish and Install 8" PVC Water Main (AVl/INA C-900,
Pressure Class 200) complete and in place
for Dollars
and __________ Cents per linear foot.
LF Furnish and Install 18" Schedule 80 PVC Waterline Casing to
include au necessary spacers, runners, end seals, & restraining
joint pipe glands complete and in place
for Dollars
and Cents per linear foot.
EA Furnish and Install 8" D.I., M.J. 45 deg Bend to include au
necessary thrust blocking complete and in place
for Dollars
and __________ Cents per each.
EA Furnish and Install 12"x8" D.I., M.J. Tee to include au necessary
thrust blocking complete and in place
for Dollars
and __________ Cents per each.
EA Furnish and Install Std. City of College Station Fire Hydrant
w/appurtenances including all necessary tees , valves and
blocking complete and in place
for Dollars
and Cents per each .
EA Furnish and Install 8" Gate Valve and Valve Box complete and
in place
for Dollars
and Cents per each .
EA Furnish and Install 8" M.J. Plug to include all necessary thrust
blocking complete and in place
for _______________ Dollars
and __________ Cents per each.
EA Furnish and Install 12" M.J. Plug to include all necessary thrust
blocking complete and in place
for Dollars
and __________ Cents per each.
$27.00 $16,848 .00
$35 .00 $1 ,400.00
$300 .00 $1,200.00
$700.00 $700 .00
$2,500.00 $2,500.00
$800.00 $1,600.00
$225.00 $225.00
$300.00 $300.00
'.
9
10 624
11 450
12
13 266
14 7
EA Connect to existing 12" waterline complete and in place
for Dollars
and __________ Cents per each.
LF Furnish and Install waterline Trench Safety (7' max depth)
complete and in place
for Dollars
and Cents per linear foot.
Furnish, Install, and Maintain Erosion & Sediment Control
LF Devices (Silt Fence) complete and in place
for Dollars
and Cents per linear foot.
Furnish, Install, and Maintain Traffic Control Devices complete
LS and in place
SY
SY
for Dollars
and Cents per lump sum .
Hot Mix Asphalt Concrete Pavement Replacement complete
and in place
for Dollars
and Cents per square yard .
Concrete Sidewalk Replacement complete and in place
for
and
Dollars
Cents per square yard .
WATER LINE· SUB-TOTAL 1
ltems(1-14)
15%~~ENCY: --~a, OF t~'''
TOTAL ESTIMATED C~· f*!~--~1~,~l
r.f ?.t--···--.---·~ ~~ B. J. KLING ~ ................... -.lll••·----
$500.00
$1 .50
$2 .00
$5,000.00
$16.00
$27.00
/
~i\ ~ 24705 ~~~; , ~.~.:_.~G'lstt.~~j ·· ·) .J ~ ..... 'L
"'\ N-S, ~ ••• ~ ·~:,r -v r ~' · \\,..tog.~;~\..~-..... ,~~<ii'
$500.00
$936.00
$900.00
$5,000.00
$4,256.00
$189.00
$36,554.00
$5 483.10
$42,037.10
Item No.
1
2
3
4
5
6
7
8
9
TABLE 1. ESTIMATE OF PUBLIC INFRASTRUCTURE CONSTRUCTION COST
PROPOSED UNITED STATES DEPARTMENT OF AGRICULTURE OFFICE BUILDING
HOLLEMAN DRIVE NEAR DARTMOUTH STREET; COLLEGE STATION, TEXAS
17TH NOVEMBER 2004
Descrigtion Estimated Quanti~ Unit Unit Price
PUBLIC WATER LINE {AND FIRE HYDRANT}
Mo bi I ization -Dem obi I ization 1 EA $1 ,000 .00
Connection to Existing 8" Line-Excavation/Connection 1 EA $800 .00
8" x 6" MJ DIP Tee Fitting (for connection to "existing" 8") 1 EA $450 .00
6" Water PVC AWWA C-909 CL200 DR14-non-structural backfill 222 LF $30 .00
6" Gate Valve (with box) 1 EA $500 .00
Fire hydrant assembly (with valve and fittings) 1 EA $2 ,500 .00
6" Water PVC AWWA C-909 CL200 DR14-non-structural backfill 22 LF $30 .00
6"x 6" MJ DIP Tee With Spools (for Fire Line) 1 EA $400 .00
6"x 6 " -45 degree MJ DIP Elbow fitting (to FH Assembly) 1 EA $375 .00
TOT AL CONSTRUCTION
~~~~~-r~\ Contingency @ 15%
TOTAL A-'~· * ··. \la
{
e*.· ·\u .t: .............. · ... ~ ,.
M F CONLIN, JR 2 ················rJt···~ • 44481 ... ~ ·~tf.E~S.~~,:~ \~ ~~.!.... € a., \\l .
~~ \\V
k'! \\
Page No . 1 of 1
Estimated Cost
$1 ,000 .00
$800 .00
$450 .00
$6 ,660.00
$500 .00
$2 ,500 .00
$660 .00
$400 .00
$375 .00
$13,345.00
$2,001.75
$15,346.75
..
DRAINAGE REPORT FOR
PROPOSED UNITED STATES
DEPARTMENT OF AGRICULTURE OFFICE
BUILDING
HOLLEMAN DRIVE NEAR DARTMOUTH STREET
COLLEGE STATION, TEXAS
A~''· K..1t. • * •. 0 '**-·· \\'I. ~····················~· Z M F CO NLIN , JR ~ ~ ....•............... ~ ~j ~·. 4 448 1 .. ,:; 't\o;..// CE N S ~~. • ·~ \\: s8'o'NAL°€.
~ • fi,l<P<'
\\ \
Senior Engineer
Prepared for
Curtis Investments, Ltd.
5641 Yale Boulevard, Suite I 00
Dallas , TX 75206
Submitted to
City of College Station
Development Services
1101 Texas Avenue
College Station, Texas 77842
Prepared by
CSC Engineering & Environmental Consultants , Inc .
3407 Tabor Road
Bryan, Texas 77808
November 2004
William R. Cullen, P.E.
Senior Engineer
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC.
Report of Drainage Study Proposed USDA O ffice Building: College Station, TX
TABLE O F C O NTENTS
Page
1.0 GENERAL DESCRIPTION OF SITE AND PROPOSED DEVELOPMENT ............................. 1
2.0 DESCRIPTION OF SITE AND PROPOSED DEVELOPMENT ................................................ 1
2.1 SITE LOCATION ............................................................................................................. l
2.2 EXISTING SITE CONDITIONS ...................................................................................... 1
2.3 PROPOSED SITE DEVELOPMENT SCHEME ............................................................... 2
3.0 LOCATION OF THE SITE WITHIN THE MAJOR DRAINAGE BASIN AND
EXISTING DRAINAGE PATTERNS IN THE AREA OF THE SUBJECT SITE ....................... 3
4.0 SCOPE OF REPORT AND DRAINAGE DESIGN CRITERIA ................................................ .4
5.0 STORM WATER RUNOFF COMPUTATIONS ....................................................................... .4
5.1 USE OF THE RATIONAL FORMULA. .......................................................................... .4
5.2 RUNO FF COEFFICIENTS (C) ........................................................................................ 5
5.3 TIME OF CONCENTRATION (Tc) ................................................................................. 6
5.4 RAINFALL INTENSITY (I) ............................................................................................ 6
5.5 AREA OF SITE (A) .......................................................................................................... 7
5.6 STORM WATER RUNOFF QUANTITIES ...................................................................... 7
6 .0 STORM WATER DETENTION ................................................................................................ 8
6 .1 REQUIREMENT FOR STORMW ATER DETENTION ................................................... 8
6.2 FLOOD LEVELS WITH RESPECT TO THE EXISTING SIT E ....................................... 8
7.0 EROSION CONTROL MEASURES .......................................................................................... 9
7.1 GENERAL CONSIDERATIONS ..................................................................................... 9
8.0 CERTIFICATION ...................................................................................................................... 9
9.0 REFERENCES .......................................................................................................................... 10
LIST O F T AB LES
Table 1. Summary of Determination of Runoff Coefficient (C) Values for Post-Development
Condit io ns for Entire Site .................................................................................................. 5
Table 2. Computed Rainfall Intensity Values for Defined Storm Return Period ............................... 7
Table 3. Calculation of Pre-and Post-Development Storm Water Runoff Quantities Using the
Rational Method ............................................................................................................... 7
II
CSC ENGINEERING & ENVIRONMENT AL CONSULT ANTS, INC .
Report of Drainage Study Proposed USDA Office Building: Co llege Sta tion, TX
Figure l.
Figure 2.
Figure 3.
Figure 4.
Figure 5.
Figure 6.
Figure 7 .
Figure 8.
LIST OF F IGURE S
Vicinity Map
Wolf Pen Creek Drainage Basin
Aerial Photograph (2002) of Subject Site and Surrounding Area
Pre-Development Site Conditions and Stormwater Runoff Flow Patterns
Proposed Site Development Scheme (Post-Development Conditions), Site Grading
Plan, and Surface Storm Water R unoff Flow Patterns
FIRM Flood Plain Map of Area of Subject Property
Types of Ground Cover Associated With Post-Development Scheme
Plan and Profile of Site Stormwater Discharge Piping Showing Relative
Elevations of 10-Year and 100-Year Flood
ll1
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC.
Report of Drainage Study Proposed USDA O ffi ce Building: College Sta tion, TX
1.0 GENERAL DESCRIPTION OF SITE AND PROPOSED DEVELOPMENT
This report documents the information used in the formulation of the storm water drainage system
for the proposed United States Department of Agriculture (USDA) Office Building development being
performed by Curtis Investments, LLC (Cl) in College Station, Texas.
2.0 DESCRIPTION OF SITE AND PROPOSED DEVELOPMENT
Information concerning the project was provided by Mr. Chris Curtis of CJ , the developer of the
project, and by Mr. Tim Risley , AJA , with the project architects , Risley & Associates.
2.1 SITE LOCATION
We understand that the proposed office building development will be situated on an existing
undeveloped tract of land that extends over approximately 1.63 acres . The subject tract of land is part of a
larger tract that will be developed by others at a later date. The subject tract is situated on the northern
side of Holleman Drive, approximately 800 to 900 ft east of the intersection with Dartmouth Street (see
Figure I -Vicinity Map in Appendix A ; all figures referenced in the report are in Appendix A). The site is
situated within the Wolf Pen Creek Drainage Basin (Figure 2 -Wolf Pen Creek Drainage Area). The
existing Post Oak Mall shopping center borders the subject property to the east, and the adjacent parent
tract land to the north and west of the subject property consists of undeveloped wooded pastureland (see
Figure 3 -Aerial Photograph (2002) of Subject Site and Surrounding Area).
2.2 EXISTING SITE CONDITIONS
The subject tract itself is heavily wooded . There are scattered large trees and significant brush
undergrowth present across the entire site (Figure 3). The subject site has a pronounced slope in a
southerly direction toward Holleman Drive and the predominant direction of stormwater surface runoff
flows follows the surface grade toward Holleman Drive (Figure 4 -Pre-Development Site Conditions and
Storm water Runoff Flow Patterns.) Surface grades vary somewhat across the site but average
approximately 2 percent. Wolf Pen Creek is situated on the southern side of Holleman Drive from the
1
CSC ENGINEERING & ENVIRONMENT AL CONSULT ANTS, INC.
Report of Drainage Study Proposed USDA O ffi ce Building; Coll ege Station, TX
site, and there is a small, unnamed tributary drainage swale to Wolf Pen Creek approximately 400 ft west
of the subject site. The unnamed drainage swale flows in a north to south direction through the previously
referenced "parent" tract and crosses beneath Holleman Drive through two 36-inch-diameter culverts
which tie-in to Wolf Pen Creek on the southern side of Holleman Drive.
2.3 PROPO SED SITE DEVE LOPMENT SCHEME
The proposed development will consist of a single-story office building and associated paved
driveway and parking areas as illustrated on Figure 5 -Proposed Site Development Scheme (Post-
Development Conditions), Site Grading Plan , and Surface Storm Water Runoff Flow Patterns . CSC
anticipates that the proposed office building structure will be situated in the south-central portion of the
previously described property. We further anticipate that the proposed development will have two parking
areas that will accommodate approximately a total of 54 parking spaces. One parking area for visitors will
be situated on the south side of the building facing Holleman Drive, and the second parking area will be
used for employees and will be located on the north side of the proposed building (Figure 5). We
anticipate that the paved drive and parking areas associated with the new building will be constructed of a
rigid pavement system with a Portland cement concrete (PCC) surface. Landscaping of the site will be
pursued in the areas around the office building, in the islands and areas bordering the parking lots, and
along the "streetscape" adjacent to Holleman Drive. It should be noted that some of the parking in front of
the office building was eliminated in an attempt to preserve some of the existing trees along Holleman
Drive.
We anticipate that the proposed Department of Agriculture Building will be a single-story office
building and will have a ground contact or footprint area of approximately 13 ,800 square feet. Although
we are not aware of the structural framing system planned for the proposed building, we anticipate that
the building will be a pre-engineered metal building with some light gauge steel stud walls that are non-
load bearing. We also anticipate that the building will have a steel joist roof framing system and a
standing seam metal panel roof system. We believe that the exterior of the structure will consist of a
combination of masonry walls , such as bricks or stone, and wood siding, along with metal-framed glass
window openings and combination wood and glass door openings. We also expect that the structural
interior of the building will consist of non-load bearing wood frame or light gauge metal frame walls with
drywall or gypsum panel covering.
The finished floor slab elevation of the building will be approximately at El. 272 .3. The fin ished
floor elevation will require some small volumes of fill to be added to the site in order to achieve final
grades in the building pad area. We anticipate that the fill heights will vary from 0.5 ft in the northwestern
2
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC.
Report of Drainage Stu dy Proposed USDA Office Building: Co llege Sta tion, TX
portion of the building pad to approximately 2.5 ft in the southeastern corner of the pad. Finally, we do
not anticipate that the building will have a basement or a storm shelter or other features that would require
structural excavations at the site.
We anticipate that the roadway system for the development will consist of a combination of one
major private access drive along the western boundary of the property and secondary feeder lanes within
the visitor and employee parking areas. The access drive is expected to have a Portland cement concrete
(PCC) curb and gutter section with back-to-back curb widths of approximately 27 ft. The secondary
feeder lanes are expected to be approximately 24 ft in width between the rows of parking spaces. We also
anticipate that the feeder lanes and parking areas will also have rigid pavement sections composed of
PCC.
3.0 LOCATION OF THE SITE WITHIN THE MAJOR DRAINAGE BASIN
AND EXISTING DRAINAGE PATTERNS IN THE AREA OF THE SUBJECT
SITE
As previously discussed, the subject 1.63-acre site is located in the lower reach or bottom half of
the Wolf Pen Creek drainage basin and is approximately 7,600 feet upstream from the point where Wolf
Pen Creek flows into Carters Creek (see Figure 6 -FIRM Flood Plain Map of Area of Subjec t Property).
The subject site is situated below the point where the three major tributaries of Wolf Pen Creek
(Tributaries A, B and C on the FIRM map) join the major Wolf Pen Creek channel to the west of
Dartmouth Street as illustrated on Figure 2.
T here are no distinct drainage channels across the ex isting site. The major portion of current
storm water runoff from the site appears to be by sheet-flow in a southerly or southeasterly direction
toward Holleman Drive. The stormwater runoff is collected within the Holleman Drive pavement section
where it is routed via the street gutters to existing storm sewer curb inlets. The stormwater collected in the
curb inlets is discharged through a system of storm sewer pipes into Wolf Pen Creek, which is situated
south of Holleman Drive.
3
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC.
Report of Drainage Study P roposed USDA O ffi ce Building: College Sta tion, TX
4.0 SCOPE OF REPORT AND DRAINAGE DESIGN CRITERIA
This report addresses the need for detention of drainage from the subject site following the
planned development of the office building site. The site and proposed development were evaluated in
accordance with the criteria outlined in the "Drainage Policy and Design Standards (DPDS)" manual of
the City of College Station, Texas. The DPDS manual is undated but contains a chapter on "Flood Ha:zard
Protection" that has a revision date of October l , 1990. This report also discusses general eros ion control
measures.
5.0 STORM WATER RUNOFF COMPUTATIONS
5.1 USE OF THE RATIONAL FORMULA
The Rational Formula was used to compute the volume of storm water runoff prior to and
following the planned development. Calculations based upon the Rational Formula were employed to
a ssess the quantity of storm water that must be detained to "offset" the increased runoff associated with
the new development. The generalized grading plan for the proposed development and the patterns of
post-development storm water runoff flows are illustrated on the accompanying Figure 5.
Us e of the Rational Formula is reasonable for this project since the contributory area of runoff is
less than 50 acres , a n area sometimes referenced in the literature as an upper limit for use of the Rational
Formula. In addition, the s ubject site is located wi t hin a Secondary Drainage System and not within a
Primary Drainage System. The Rational Formula is not recommended for use within a Primary Drainage
Sy stem . Therefore, the Rational Formula was used to determine the peak discharge for both pr e-and post-
development conditions.
T he general equation for the Rational Formula is well know n:
Q =CIA
w here
Q =discharge of storm water in units of cubic feet per second (cfs)
C = coeffi cient that represents the average runoff characteristics of the land cover within th e
drainage area of interest, i.e., the runoff coefficient, which is dimensionless
I =rainfall intensity in units of inches per hour (in/hr), and
4
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC.
Report of Drainage Study Proposed USDA Office Building: Coll ege Station, TX
A = area of the site that contributes to the storm water runoff in units of acres
The numbers for each of the values used to compute the storm water runoff at the subject site are
discussed in the following sections.
5.2 RUNOFF COEFFICIENTS (C)
The runoff coefficients or "C" values were computed for both pre-and post-development
conditions. Coefficients for the different types of surface covers were determined from Table III -1 of the
DPDS manual.
The coefficient for the pre-development condition was determined based upon the land cover
category listed in Tab le III-1 as a combination of "Natural Woodlands " and "Natural Grasslands " for
slopes in the range of 1 % to 3 .5%. A range of C-values of 0 .18 to 0.25 is listed in the referenced table for
the "Natural Woodlands" and a range of C-values of 0 .35 to 0.45 was given for "Natural Grasslands" for
the cited topographic conditions. Accordingly, an average value of 0.4 was selected for use for pre-
development cover of the entire 1.63-acre site .
The post-development C-values were determined from the referenced table for the specific types
of site cover associated with post-developed site conditions (Figure 7 -Types of Ground Cover Associated
With Post-Development Scheme). The specific types of post-development cover materials illustrated in
Figure 7 and the corresponding C-values from Table III-1 of the DPDS manual were used in the analysis
listed in Table 1 to compute an average C-value for the post-developed site. In general , a C-value of 0 .9
was used for building roof and concrete covered pavements and sidewalks and a C-value of 0.5 was used
for the landscaped or grassed areas.
Table I. Summary of Determination of Runoff Coefficient (C) Values for Post-Development
Conditions for Entire Site
Type of Ground Cover
Concrete (sidewalks, streets, etc .)
Building roof
Grassed or landscaped areas
Summation
Area of Coverage,
Square Feet
28 ,742
15 ,098
27 ,235
71,045
5
Typical
C-Values
0.90
0.90
0.50
Extended Multiplication of
C-Values X Area
25 ,868
13 ,588
13 ,618
53,074
'•
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC.
Report of Drainage Study Proposed USDA Office Building: College Station, TX
----~~~--~--~~~~~~~~~~~~~~~----
Transportation. The computed intensities calculated for storm events with "return periods " of 5, l 0, 25,
50, and 100 years are indicated in Table 2.
Table 2. Computed Rainfall Intensity Values for Defined Storm Return Period
Storm Return Period
(Years)
5.5 AREA OF SITE (A)
5
10
25
50
100
Rainfall Intensity
(Inches/Hour) ---'-----
7 .7
8 .6
9.9
I I. I
12.3
The area of the site used in the computation of storm water runoff is the original site area of 1.63
acres as indicated on Figure 4.
5.6 STORM WATER RUNOFF Q UANTITIES
Storm water runoff quantities were calculated using the Rational Formu la. Runoff quantities were
calculated for both pre-and post-development conditions for the I .63 -acre site for storm events with
recurrence intervals of 5, 10, 25, 50 and 100 years . The rainfall intensities used in the computations were
as discussed in Section 5.4. The results of the computations are presented in Table 3.
Table 3. Calculation of Pre-and Post-Development Storm Water Runoff Quantities Using the Rational
Method
PRE-POST-DIFFERE NC E
Storm Area_ Intensityc D EVELOPMENT D EVELOPME NT IN FLOWS
Event (acres) (inches
(year) /h r) Cp,/ Qp re Cpost 8 Qpost Qo
(dlessb) (cfs (dlessh) (cfs) (cfs)
5 1.63 7 .7 0.40 5.0 0 .75 9.4 4.4
10 1.63 8.6 0.40 5.6 0.75 10.5 4.9
25 1.63 9 .9 0.40 6.5 0.75 12.1 5.6
50 1.63 11.1 0.40 7.2 0.75 13.6 6.4
100 1.63 12.3 0.40 8.0 0.75 15 .0 7.0
•Average values ofC were obtained from Table Ill-I of the DPDS Manual
b dless = dimensionless
c Values obtained from Table 2 of this report
7
I
CSC ENGINEERING & ENVIRONMENT AL CONSULT ANTS, INC.
Report of Drainage Study Pro posed U SD A O ffi ce Building: Co ll ege Sta ti on, TX
6.0 STORM WATER DETENTION
6.1 REQUIREMENT FOR STORMWATER DETENTION
CSC has noted that the proposed site is relatively small and occupies an area of only 1.63-acres .
In addition, a significant portion of the site will remain as natural woodland or landscaped areas following
development. As can be seen from a review of Table 2 , approximately 38 percent of the site will still be
landscaped. Also, we have noted that the facility is situated within the lower reach of the Wolf Pen Creek
drainage basin. We also note that it is the policy of the City (as stated in the DPDS manual) "to encourage
the rapid conveyance of stormwater through and out of the City within the primary [drainage] system."
Since a significant percentage of the flows within the main Wolf Pen Creek channel in the vicinity of the
subject site are derived from the contributory drainage areas of the three upstream tributaries of the creek
(Tributaries A, B and C as illustrated in Figure 2 and 6), the time at which the peak flow will occur in the
channel in the vicinity of the subject site is believed to be relatively Jong. Further we anticipate that the
time at which peak flow will occur will certainly be in excess of the 10 minutes time of concentration that
it takes for the flows from the subject site to enter the main creek channel Therefore, we believe that the
flows from the subject site should be directed to the Wolf Pen Creek channel without delay, and therefore,
detention of stormwater runoff on the subject site is not desirable. Consequently, no separate stormwater
detention basin was included in the design of the stormwater drainage system for the proposed project.
6.2 FLOOD LEVELS WITH RESPECT TO THE EXISTING SITE
The flood elevations for the 10-year and 100-year recurrence intervals were also studied with
respect to the proposed site and planned drainage system. The flood elevations were determined from the
recently revised (March 12, 2001) FIRM Map Number 48041C0144 C for the area. This document
indicates a flood elevation of approximately EL. 363.3 for the 10-year event and an elevation of
approximately EL. 364.9 for the 100-year event. The relationship of these flood levels to the planned
drainage system discharge piping is illustrated on Figure 8 -Stormwater Discharge Pip e Plan and
Profile.
As can be seen from a review of Figure 8, the I 0-year flood level is essentially at the invert
elevation of the upstream (first box upstream of discharge point) drainage junction box for the site
stormwater drainage system and wi ll therefore not "back-up" into the drainage system for the proposed
8
CSC ENGINEERING & ENVIRONMENT AL CONSULT ANTS, INC.
Report of Drainage Stud y Proposed USDA Office Building: Co llege Station, TX
development. The flood leve l for the I 00-year event wi ll extend into t he lower portion of the proposed
site drainage system , but wi ll be below the finished grade elevation of the access roadway , below the
gutter flow line elevations of the curb inlets, and below the tops of the junction boxes present in the lower
portions of dra inage system. The 100-year flood elevations will not extend into the upper portions of the
site drainage system. Therefore, there should be no above-ground backwater associated with the 100-year
flood event with respect to the proposed developed site. The relatively steep grade (> I percent of the
proposed stormwater discharge pipe for the site drainage system, Figure 8) will produce sufficient
ve locities to remove sediments that may collect in the disc harge pipe due to flood backwaters.
7.0 E ROSI O N CONTROL MEA SURES
7.1 GENERAL C O NSIDERATIO NS
The erosion control measures proposed at the site will consist of a combination of silt fences, hay
bale barriers, and sedimentation traps. The locations of the proposed erosion control measures are
depicted on Sheet C 11 of the submitted construction plans.
8.0 C E R T I F ICATION
"I hereby certify that this drainage report for the 1.63-acre site of the proposed United States Department
of Agriculture Office Building located on the northern side of Ho ll eman Drive and east of Dartmouth
Street in College Station, Texas , was prepared under my supervision in accordance with the previsions of
the City of College Station "Drainage Policy and Design Standards (1990)" for the owners thereof."
?n, ~ C<mQ:.~.~-
M. Frederick Conlin, Jr., P.E.1
Registered Professional Engineer
State of Texas P.E. Number 44481
9
CSC ENGINEERING & ENVIRONMENT AL CONSULT ANTS , INC.
Report of Drainage Study Proposed USDA Office Building: College Station, TX
9.0 REFERENCES
Chow, Ven T., Maidment, David R ., and Mays, Larry W . 1988 . Applied Hydrology. McGraw-Hill Book
Company. New York, NY. 1988 .
City of College Station, Texas . 1990 . "Drainage Policy and Design Standards," part of the Stormwater
Management Plan for the City of College Station. October, 1, 1990.
Davis, Victor D., and Sorensen, Kenneth E. 1969. Handbook of Applied Hydraulics. McGraw-Hill Book
Company . New York, NY. 1969 .
Federal Emergency Management Agency. Flood Insurance Rate Map; Brazos County Texas and
Incorporated Areas; Panel 144 of250. FIRM Map Number 48041C0144 C, Effective Date: July 2, 1992;
Revised to Reflect LOMR: March 13, 2001.
Hann, C. T., Barfield, B. J., and Hayes , C. J . 1994. Design Hydrology and Sedimentology for Small
Catchments. Academic Press, Inc. San Diego, CA. 1994.
Mason, John M. and Rhombrerg, Edward L. 1980. On-Site Detention. Prepared for Texas Engineering
Extension Service, Texas A& M University. College Station, TX. 1980. Publication No. PWP : 03355-01.
McCuen, Richard H. A Guide to Hydrologic Analysis Using SCS Methods. Prentice-Hall , Inc .
Englewood Cliffs , NJ. 1982.
United States Department of Agriculture. 1975 . Urban Hydrology for Small Watersheds. Technical
Release No. 55. Engineering Division, Soils Conservation Service, U.S. Department of Agriculture.
January 1975.
Wanielista, Martin P . 1978 . Storm water Management Quantity and Quality. Ann Arbor Science. Ann
Arbor , MI. 1978.
Westaway , C.R. and Loomis, A. W. 1979. Cameron Hydraulic Data. (16th Edition). Ingersoll -Rand.
Woodcliff Lake, NJ. 1979.
10
I c
s
c
f .111:11u,,•r1111: c{ l .m·iro1111111nt11/
Co11s11/ta11ts, I n<.
CURTIS INVESTMENTS, LLC
VICINITY MAP
USDA BUILDING
COLLEGE STATION , TX
PROJECT: TX USDA
LOCATION : COLLEG E STATIO N TEXAS
APPR : MFC REV . DATE :
DRAWN BY: TOM SCALE : AS SHOWN
DATE : 07 26 2004 FIGUR E NO .:
..
l .ngi11eerini c( l .1wilonme11tal
Co1u11//f/11H. Inc.
CURTIS INVESTMENTS, LLC
WOLFPEN CREEK DRAINAGE BASIN
USDA BUILDING
COLLEGE STATION , TX
STATION TEXAS
APPR : MFC REV . DAT E:
DRAWN BY: TOM SCALE : AS SHOWN
DATE: 07 26 2004 FIGURE NO .: 2
·•
llifil
INFORMATION PRESENTED IN THIS DRAWING IS
FOR INFORMATIONAL PURPOSES ONLY AND NOT
INTENDED TO BE USED IN CONSTRUCTION .
KEY :
- - -PROPERTY LINE
GROUND COVER
b :~ ·· .. ;' ,j ~~~AP~Vl~~,742 FT2
f~'4
(OR 0.66 ACRES)
BUILDING LAYOUT
AREA = 15,098 FT2
(OR 0 .35 ACRES)
I c
s
c
J .11g111cen11~ & L.m·11011memal
Consultallfs. Inc
CURTIS INVESTMENTS, LLC
HOLLEMAN DRIVE
TYPES OF GROUND COVER ASSOCIATED WITH
POS~DEVELOPMENTSCHEME
COLLEGE STATION , TX
PROJECT: TXUSDA
LOCATION : COLLEGE STATION TEXAS
APPR : MFC REV . DATE :
DRAWN BY: TOM SCALE: AS SHOWN
DATE : 07 26 2004 FIGURE NO.: 7
Engineering & Environmental
Consultants, Inc.
November 18 , 2004
Ms. Jennifer Reeves, Project Manager
City of College Station
Development Services
1101 Texas A venue South
P. 0. Box 9960
College Station, Texas 77842
Re: Third Submittal of Revised Site Plan and Landscape Drawings and Construction Drawings for
Proposed United States Department of Agriculture Office Building
Holleman Drive near Dartmouth Road; College Station, Texas
Incorporating Revisions in Response to Staff Review Comments No. 2
Case File #04-00500093
Dear Ms. Reeves:
This letter transmits the revised site development documents outlined in your Memorandum dated
September 2 , 2004 for the proposed United States Department of Agriculture Office Building planned to
be located on Holleman Drive, east of the intersection with Dartmouth Road in College Station, Texas.
The submitted site development documents includes the following six (6) separate items:
(1) the revised site plan as prepared by CSC Engineering & Environmental Consultants, Inc.;
(2) the revised landscape plan as originally prepared by the project architect, Tim Risley &
Associates from Fort Smith, Arkansas (Risley) and later modified by CSC;
(3) one complete set of the site development construction documents prepared by CSC which
include the attached copies of the previously cited revised site and landscape plans;
( 4) a water demand report;
(5) a drainage report; and
(6) an engineering cost estimate for the domestic water line and fire line.
A listing of the construction drawings presented in the accompanying Table 1
The submitted site plan, landscape plan, and construction drawings have all been revised to address the
comments of the City of College Station staff as outlined in the previously referenced Memorandum. The
staff comments were designated as "Staff Review Comments No. 2" and are summarized in Table 2,
along with a description of how the responses to the comments were integrated into the previously
referenced site plan, landscape plan, and construction documents. The presently submitted construction
documents also reflect the changes discussed for the site plan and the landscape plan.
3407 Tabor Road
Bryan , Texas 77808 Phone (979) 778-2810
Fax (979) 778-0820
' ' ' Re-submittal of Revised Site and Landscape Plans and Submittal of Construction Documents
Submittal No. 3 Based Upon Staff Review comments No. 2
Proposed United States Department of Agriculture Office Building; College Station, Texas
Page2
Table 1. Listing of the Submitted Site Development Construction Drawings for the Proposed United
States Department of Agriculture Office Building
SHEET DRAWING REVISON DATE
NO. TITLE NO.
Cover Sheet
C-1 General Notes 0 11/ 15/04
C-2 Site Plan 0 11/15 /04
C-3 Dimension Control 0 11/15/04
C-4 Grading and Drainage 0 11/15/04
C-5 Utility Plan (WL, SS , Electrical and Nat. Gas) 0 11/15 /04
C-6 Water Line Plan and Profile 0 11/15/04
C-7 Paving and Drainage D etails 0 11/ 15 /04
C-8 Paving and Drainage D etails 0 11/ 15/04
C-9 Water and Waste Water Details 0 11/15 /04
C-10 Water and Waste Water Details 0 11115/04
C-11 Erosion Control Plan 0 11115 /04
We sincer ely appreciate your assistance in facilitating this submittal. Please do not hesitate to call should
any qu estions arise or if additional information is required .
Kind e st regards ,
CSC Engineering & Environmental Consultants, Inc.
M . Frederick Conlin, Jr. P .E ., JD
Senior Engineer
MFC :am
via: Hand Delivery
Attachme nts : (Listed in Body of Letter)
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC.
Re-submittal of Revised Site and Landscape Plans and Submittal of Construction Drawings
Submittal No. 3 Based Upon Staff Review comments No. 2
Proposed United States Department of Agriculture Office Building; College Station, Texas
Page 3
Table 2 . Summary of COCS Staff Review Comments No . land Adjustments to Drawings and Report to Incorporate Comments
C OMMENT ORIGINAL DESCRIPTIO N OF CHANGE T O DRAWING TO
NUMBER C O MMENT INC ORPORATE COMMENT
PLANNIN G
l Landscaping note #7 is to address disturbed areas from construction to Done. Two notes were added to the General Landscape and
assure that there will be an acceptable ground cover and not left as graded Irrigation System Notes on the Landscape Plan, Sheet L-1.
raw dirt . As previously commented, please provide a note stating: "Provide Note 5 states that All Ground Areas Disturbed by
a general note that all roof and ground-mounted mechanical equipment shall Construction Shall Be Sodded With Bermuda or St.
be screened from view or isolated so as not to be visible from any public Augustine Grass. Note 7 states All roof and ground-
right-of-way or residential district within 150 ' of the subject lot, measured mounted mechanical equipment shall be screened.from view
from a point five feet above grade. Such screening shall be coordinated or isolated so as not to be visible from any public right-of-
with the building architecture and scale to maintain a unified appearance .,. way or residential district within 150 ' of the subject lot,
measured from a point jive feet above grade . Such screening
shall be coordinated with the building architecture and scale
to maintain a un(fted appearance .
2 Per my phone conversation with Rick Conlin (CSC Engineering) 08/26/04: Done -see sheets SP-1, C -2 and C -5 which sho'v that
Please relocated the proposed fire hy drant located at the rear of the building relocated fire hydrant. and the relocated fire department
to the corner between the parking space and the proposed bike rack. (Per connection .
Steve Smith, Fire Marshall's Office).
..., FYI : The (F .D .C .) Fire Department Connection will need to be located on D one -see sheets SP-1 , C-2, and C -5 which show that .)
the rear side of the building facing the back parking lot (Per Steve Smith, relocated fire department connection to the back of the
Fire Marshall 's Office). building facing the back parking lot.
4 All paved areas must be curbed. It appears that the main drive isle that dead Done -see note on the Site Plan, Sheet SP-1 , and Sheet C-2
ends at the rear of the property is not showing curbing . where curbing is indicated at the end of the access road
paving .
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC .
Re-submittal of Revised Site and Landscape Plans and Submittal of Construction Documents
Submittal No . 3 Based Upon Staff Review comments No. 2
Proposed United States Department of Agriculture Office Building; College Station, Texas
Page4
Table 2. (Continued). Summary of COCS Staff Review Comments No. land Adjustments to Drawings to Incorporate Comments
C OMMENT ORIGINAL DESCRIPTIO N OF CHANGE T O DRAWING T O INCORPORATE
NU MB E R C OMMENT C OMMENT
ENGINEERING
l Site Plan cannot be stamped approved until the Final Plat is Understood . It is our believe the Kling Engineering & Surveying is
filed . The offsite easement for the water line is still needed submitting the Final Plan and that the owner/developer is taking care of the
in order to approve the construction plans required for the bonding requirement.
Plat. The water line will need to be constructed on bonded
before the Plat can be filed .
2 Add note that all ,\l·ater and seer construction to be in Done . See GENERAL PROJECT NOTES'.. Note B.l under City of College
accordance with BCS Unified Design Guidelines and Station Standards on Sheet C-1 .
specifications . The details you provided do not match
current approved details. You can cop y and include our
details or just provide the aforementioned note . (Contractor
may prefer details be included .)
..., Please relocate water line to east side of existing sevver . D one -water line relocated to existing Public Utility Easement. .)
There is not enough space between the building and the See Site Plan , Sheet SP-1 , Sheet C -2 , General Site Plan (Construction
existing sewer line to allow for any give in placement of Drawings), Sheet C-5 , Utility Plan (W, SS G + E), and Sheet C-6 , Domestic
water line. Water Line Plan and Profile .
4 Provide sealed engineer 's cost estimate for public (fire) line . Done . A cost estimate for installation of the domestic water line and fire
line accompanies this submittal.
5 No development permits can be issued until Development Done . The Development Permit Application, along v.1ith the appropriate fees
Pennit Application and fees and documents are submitted . and documents , have since been submitted by the general contractor for the
prqject -JaCody Construction.
6 Provide water design report and drainage report . Done . Those reports accompany this submittal.
·'
Re-submittal of Revised Site and Landscape Plans and Submittal of Construction Documents
Submittal No. 3 Based Upon Staff Review comments No. 2
Proposed United States Department of Agriculture Office Building; College Station, Texas
Page 5
Table 2 . (Continued). Summary of COCS StaffRevie'v Comments No. land Adjustments to Drawings to Incorporate Comments
COMMENT ORIGINAL DESCRIPTION OF CHANGE TO DRAWING TO INC ORPO RATE
NUMBER COMMENT COMMENT
ENGINEERIN G
7 Filed copies of the joint access easement and private It is our understanding the Kling Engineering & Surveying is submitting the
drainage easement will need to be provided prior to Site copies of the joint access easement and the private drainage easement to the
Plan approval . owner/developer who will file the documents .
8 Minimum curb return radius for a commercial driveway is Corrected . A minimum curb return radius of 20 feet has been added to the
20 feet. driveway entrance location on Holleman Drive . See Sheet C -3 , Dimension
Control Plan .
9 A drop manhole connection will be required for sanitary Understood . However, a different route is proposed for the sanitary sewer
sewer service line if it is more than 30 inches higher than service line . The existing alignment between the building and the MH would
the manhole invert . require crossing an area of existing trees that the developer is trying to
preserve . There is concern that the excavation for the sanitary sewer line '"rill
destroy the root system for the existing trees . Therefore, an alternate route
parallel to the front face of the proposed building, as illustrated on Sheet C-2
and on Sheet C-5, Utility Plan (W, SS G + E), is proposed . The proposed
alternate route would avoid the area of existing trees . Consequently, a drop
manhole is no longer needed and a deep sewer connection (existing line is
about 12 ft deep) detail has been added to Sheet C -10 , Water , Wastewater
and General Details, as Detail 6, replacing the former MH detail.
WATER DEMAND REPORT
(FIRE FLOW ANALYSIS
UNDER THE IFC 2000)
For:
United States Department of Agriculture (USDA)
Prepared By:
CSC Engineering & Environmental Consultants , Inc.
November, 2004
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC.
Water Demand (Fire Flow Analysis) Report
Proposed United States Department of Agriculture Office Building
Holleman Driv e Near Dartmouth Street
College Station Texas
SU MMARY OF FIRE FLOW ANALYSIS
(Co de A nalys is Per Inte rn ati ona l F ire Cod e 2000)
I. GENERAL DESC RIPTION OF PRO JECT
This report of fire flow analysis was prepared for the proposed United States Department of Agriculture
(USDA) office building planned at a 1.63-acre site on the northern side of Holl eman Drive,
approximately 800 to 900 feet east of the intersection with Dartmouth Street (see Figure 1 -Vicinity Map
in Appendix A of this report). The proposed building is a single story-structure that classifies as a
Building Type III B under the 2000 Edition of the International Fire Code (IFC). The bui lding will have
an area of approximately 13 ,800 square feet and will be sprinkled .
A schematic of the existing and proposed water lines in the vicinity of the proposed structure is illustrated
on Figure 2 -Schematic of Existing and Proposed Water Lines in Appendix A. As can be seen from a
review of F igure 2 , an 8-inch diameter water line with a fire hydrant is planned along the front or southern
portion of the building adjacent to Holleman Drive and the visitor parking of the planned office building
development. The fire hydrant will be within 100 ft of the building. In addition, a 6-inch diameter line
that is perpendicular to the referenced 8-inch line is planned along the eastern side of the building with a
fire hydrant in the rear. The rear fire hydrant wi ll be located within approximately 55 ft of the building.
In addition, a fire department connection will be situated on the rear (north) face of the building facing the
employee parking lot.
The following sections of this report contain more deta il ed building and IFC information concern ing the
project , as well as our determination of the fire flow demand for the proposed building. The concluding
sections of the report present our calculations of the public water system conditions in response to the fire
flow demand. Those calculations were based upon a specific fire hydrant flow test conducted by the City
of College Station.
In summary, the referenced calculations indicate that the proposed water system can supply the required
fire flows at or above the required minimum residual pressures .
l
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC .
Water Demand (Fire Flow Analy sis) Report
Proposed United States Department of Agriculture Office Building
Holleman Drive Near Dartmouth Street
College Station Texas
II. BUILDING INFORMATION
Buildin2 Type: IIIB
Number of Stories: One (1)
Buildin2 Fire Area: 13 ,800 square feet
Building Use: Office
Buildin2 Sprinkled: Yes
III. CODE ANALYSIS -REQUIRED FIRE FLOWS AND DURATION
Minimum Required Fire Flow and FIRE FLOW
Flow Duration for Buildings (gallons per
(Table B105.1 from IFC 2000) minute)
For Building Type III B of 13 ,800 square feet size 2,500
Reduction in required fire flow of up to 50 percent because 1,250
building is sprinkleda (1,500)b
Notes:
FLOW
DURATION
(Hours)
2
2
a. The IFC 2000 perm its a reduction of up to 75 percent but the City of College Station Fire Department limits the
reduction to 50 percent.
b. Resulting fire flow (from sprinkler reduction) shall not be le ss that 1,500 gallons per minute (Section B 105 .2 of
IFC 2000)
IV. CODE ANALYSIS -NUMBER AND DISTRIBUTION OF FIRE HYDRANTS
(Table Cl05.1 from IFC 2000)
Fire Minimum Average Minimum Distance
Flow Number Spacing from Any Point on
Requirement of Between Street or Road
(gallons per minute) Hydrants Hydrants Frontage to a
(feet) Hydrant (feet)
Fire Flow Requirement of 1 500 250
1,5 00 gpm (2 provided) ( <5 00 ft provided) ( < 250 ft provided)
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC.
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC.
Water Demand (Fire Flow Analysis) Report
Propos ed United States Department of Agriculture Office Building
Holl eman Drive N ear Dartmouth Street
Coll ege Station T exas
V. CALCULATION OF FIRE FLOW REQUIRED AT 20 PSI RESIDUAL PRESSURE
To calculate Fire F low required at 20 psi we used the following equations from the IFC ........ .
Q, =29.83cd D 2 JP:
and
( J
0.54
Q1 =Q, ~=~~
Where :
Qr = residual flow at the pitot pressure
Qr = F ire Flow
cd = friction los s
D = diameter of opening in inches
PP = pitot pressure
Pr = residual pressure
P s = static pressure
Equation No. 1
Equation No. 2
Values for the existing system that were used in the fire flow analysis were determined from a specific
flow test conducted on the nearest existing fire hydrant (FH) to the site. The flow test was conducted by
City of College Station personnel for the FH located on the south side of Holleman Drive in front of the
Sears Service Center east of the subject property. The referenced Fire Hydrant Flow Test Report provided
by Mr. Butch Willis of the City of College Station Water and Wastewater Division is presented in
Appendix B of this report. The values used for the referenced equation area as follows ...
Qr = residual flow at the pitot pressure -to be calculated
Qr = Fire Flow -to be calculated
cd =friction loss (usually 0 .9 for smooth 2 .5-in opening)
D = diameter of opening in inches (2.5 in most cases)
PP = pitot pressure -measured to be 90 psi
Pr= residual pressure-measured to be 98 psi
P s = static pressure -measured to be 102 psi
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC .
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC.
Water Demand (Fire Flow Analysis) Report
Proposed United States Department of Agriculture Office Building
Holleman Drive N ear Dartmouth Street
College Station Texas
Calculate Residual Flow at the Pitot Pressure using Equation No . 1
Q,. = 29 .83 (0 .9) (2 .5 inches)2 (90 psi)05
Q ,. = 1,592 gpm, which compares fa v orably with the measured test value of 1,590 gpm.
Calculate the available Fire Flow at 20 psi Residual Pressure from Equation No. 2 (Table 3)
Q r = 1,592 gpm [(102 psi -20 psi)/(102 psi-98 psi)]054
Q r = 8, 134 gpm at the required residual pressure of 20 psi .
Therefore, the available fire flow is well in excess of the required minimum flow of 1,500 gpm (from
Table III).
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC.
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC.
Water Demand (Fire Flow Analysis) Report
Proposed United States Department of Agriculture Office Building
Holleman Drive Near Dartmouth Street
College Station Texas
APPENDIX A
FIGURES
I c
s
c
l .11gineeri11g cC l .m·ilmmN'l11ol
Co11.511/ta11ts. Inc
U.S. DEPARTMENT
OF AGRICULTURE
VICINITY MAP
U.S. DEPARTMENT OF AGRICULTURE
COLLEGE STATION , TEXAS
PROJECT: TXUSDA
LOCATION : COLLEGE STAT ION TEXAS
APPR: MFC REV . DATE :
DRAWN BY: TOM SCALE : AS SHOWN
DATE : 07 26 2004 FIGURE NO .:
..
' .
CSC ENGINEERING & ENVIRONMENTAL CONSULTANTS, INC.
Water Demand (Fire Flow Analy sis) Report
Propos ed Unit ed States Department of Agriculture Office Building
Hollema n Drive N ear Dartmouth Street
College Station T exas
APPENDIXB
FIRE HYDRANT FLOW TEST REPORT
FROM THE CITY OF COLLEGE STATION
WATER AND WASTEWATER DIVISION
. .
' .
'
(.;UL~tat,; STA'l' l UN l'Ut!, l.ITL.
1601 GRAHAM ROAD
COLLEGE ST A TION TEXAS 77845
Date: 8 JULY 2004
Number pages including cover sheet - 1
Fax to: 778-0820
Attention: RICK CONL YN
Company: CSC
From: Butch Willis Water Wastewater Division
Phone: 979-764-3435 Fax: 979-764-3452
FLOW TEST REPORT
Nozzel size: 2., inch
Location: HOLLEMAN NEXT TO SEARS SERVICE CENTER
Flow hydrant number: E-056
Pitot reading: 90
(GPM): 1590
Static hydrant number: E-052
Static PSI: 102
Residual PSI: 98
\QI 001
·•
DEVELOPMENT PERMIT
FOR OFFICE USE ONLY
Case No .DU -55
Date Submitted C\ ~ 0.t -
MINIMUM SUBMITTAL REQUIREMENTS
$200 .00 d evelopme nt permit fee .
Draina ge and erosion contro l plan , with support ing Drainage Report two (2) copies each
Noti ce of Int ent (N .0.1 .) if disturbed area is grea ter tha n 5 acres-~ N~ ; ·
Date of *Required Preapplication Conference:
--------------------~ *(Required for areas of spec ial flood hazard)
Lot 1, Block 1, USDA Subdivision, a 1.68 acre tract,
Morgan Rector Survey, Abstract No. 46, as ~ecorded
LEGAL DESCRIPTION at Vol. 6081, Pg. 127
APPLICANT'S INFORMATION (Primary Contact for the Proje ct):
NameJacody, Inc. Attn: Wick McKeen
Street Address 1 0770 State Hwy. 30
City College Station State __ T_X _____ _ Zip Code 77845
Fa x Number ( 979) 774-5693 PhoneNumber (979) 774-5613
PROPERTY OWNER 'S INFORMATION :
Curtis Investments -College Station LLC
Name Attn: Chris Curtis E-Mail ccurtis@curtisinvestmentsllc.
StreetAddress 5641 Yale Blvd., Suite 100
City Dallas
Phone Number ( 21 4) 368-5091
ARCHITECT OR ENGINEER 'S INFORMATION:
CSC Engineering
Name Attn· Rick Conlin
Street Add re ss 3 4 o 7 Taylor Rd.
TX
com
Zip Code 75206
Fa x Number ( 214) 368-6067
City Bryan State TX Zip Code 7780_8 ____ _
PhoneNumber (979) 778-2810 Fa x Number (979) 778-0820
Application is hereby made for the following development specific site/waterway alterations:
ACKNOWLEDGMENTS:
I, __ , design on§iRQQr/owner , hereby acknowledge or affirm that:
The information and conclusions contained in the above plans and supporting documents comply with the
current requirements of the City of College Station , Texas City Code , Chapter 13 and its associated Drainage
Policy and Design Standards . C.... ... r--f>:S-.:Z:,v\f!Jt-"'"-1..Jf-.s-~ oller S+Jio,J,, l-~c_ --~K._,,..__' ~ fo
Property Owner( s) ff / / /' -1. 11 I f-A~e: (..-.h()°j G"'f'"~-' I (/\f..>;cJ,e,J
Development Pe rmit 07 /02 /03 1of 2
r . As a condition of approval of this permit application , I agree to construct the improvements proposed in this
application according to these documents and the requirements of Chapter 13 of the College Station City
Code
Contractor
CERTIFICATIONS:
A. I, __ , certify that any nonresidential structure on or proposed to be on this site as part of this
applicat ion is designated to prevent damage to the structure or its contents as a result of flooding from
the 100-year storm .
OCf /z7/0 4-
Date
B . I, ---=-· certify that the finished floor elevation of the lowest floor , including any basement , of any
residential structure , proposed as part of this application is at or above the base flood elevation
established in the latest Federal Insurance Administration Flood Hazard Study and maps, as amended .
Engineer Date
C . I, __ , certify that the alterations or development covered by this permit shall not diminish the flood-
carrying capacity of the waterway adjoining or crossing this permitted site and that such alterations or
development are consistent with requirements of the City of College Station City Code , Chapter 13
concerning encroachments of floodways ·and of floodways fringes .
flt~&~ . .,.fry.
Engineer
o'}/21/a4 •
Date
D . I , __ , do certify that the proposed alterations do not raise the level of the 100 year flood above
elevation established in the latest Federal Insurance Administration Flood Hazard Study.
Date
~· ............ .' ... · .. .
,., ~·. 44481 ··~
,,, o~J/ CE N S ~~-·, •""'~~-... \ '-'SStONA\_°f._~. 0
In accordance with Chapter 13 of the Code of Ordinances of the City of College Sta ~ures shall be
taken to insure that debris from construction , eros ion, and sedimentation shall not be deposited in city streets ,
or existing drainage facilities . All development shall be in accordance with the plans and specifications
submitted to and approved by the City Engineer for the above named project. All of the applicable codes and
ordinances of the City of College Station shall apply .
Developmen t Permit 07 /02/03 2 of 2