HomeMy WebLinkAbout27 DP Gateway Retail Center 04-05 730 Earl Rudder FWY SDrainage Report, Water and Sewer Demand Analysis, Load Analysis For Gateway Retail Center College Station, Texas March 2004 Revised March 24, 2004 Developer: Todd Carnes College Station, Texas (979) 693-7835 Prepared By: Rhodes Architectural Industries P.O. Box 9389 College Station, Texas 77842 (979) 764-7150 OL\-c9-:A q :20~ 3 -c91...J -03 YYlA'1 ' ,-·~ Drainage Report for Gateway Retail Center College Station, Texas February 2004 Revised March 2004 Developer: Todd Carnes College Station, Texas (979) 693-7835 Prepared By: TEXCON General Contractors 1707 Graham Road College Station, Texas 77845 (979) 764-7743 CERTIFICATION I, Joseph P . Schultz, Licensed Professional Engineer No. 65889, State of Texas, certify that this report for the drainage design for the Gateway Retail Center in College Station, Texas, was prepared by me in accordance with the provisions of the City of College Station Drainage Policy and Design Standards for the owners hereof, with the exception that storm water runoff detention is not being required at this site since the site discharges directly into a storm sewer system which discharges into the existing detention facility for the entire Gateway Development. TABLE OF CONTENTS GATEWAY RETAIL CENTER CERTIFICATION ................................................................................................................................................................... 1 TABLE OF CONTENTS ........................................................................................................................................................ 2 LIST OF TABLES .................................................................................................................................................................. 2 INTRODUCTION ............................................................................................................................................................•...... 3 GENERAL LOCATION AND DESCRIPTION .................................................................................................................. 3 DEVELOPMENT DRAINAGE PATTERNS ....................................................................................................................... 3 DRAINAGE DESIGN CRITERIA ........................................................................................................................................ 3 . STORM WATER RUNOFF DETERMINATION ............................................................................................................... 4 STORM SEWER PIPE & INLET DESIGN ..................................................•...................................................................... 4 DETENTION FACILITY ...................................................................................................................................................... 5 CONCLUSIONS ..................................................................................................................................................................... 5 APPENDIX A .......................................................................................................................................................................... 6 Calculations EXHIBIT ..........................................................................................................•.................................................................... 11 Sheet S3 -Drainage and Grading Plan LIST OF TABLES TABLE 1-Rainfall Intensity &.RunoffData ..................................................................................................................... .4 TABLE 2 -Runoff Data ......................................................................................................................................................... 4 2 DRAINAGE REPORT GATEWAY RETAIL CENTER INTRODUCTION The purpose of this report is to provide the hydrological effects of the construction of th e infrastructure for the Gateway Retail Center project, and to show that the storm w ater runoff will be controlled in such a manner so as to have minimal offsite or downstream impact. GENERAL LOCATION AND DESCRIPTION The project is located on approximately 1.5 acres located in the Gateway Development in College Station, Texas. The site is a portion of Block 1, Lot 2R of the Phase 1 of the Gateway Subdivision . The project will be developed in 2 phases with approximately 0 .8 acres being developed in Phase 1. This site has previously been developed with the clearing and grading completed with the Home Depot project. In addition, the site has previously constructed driveways on all four sides , some of which are on this tract. The site falls appro x imately 6' in elevation from the west side to east side of the site . DEVELOPMENT DRAINAGE PATTERNS The storm water runoff from the site flows into an existing storm sewer inlet at the north comer of the site. The post development drainage area boundary for both phases is shown on Sheet S3, the Drainage and Grading Plan. The grading plan is based on elevations re lati ve to the site with the existing grate inlet top assum ed to be Elevation 95.3, as shown on the plans . This inlet is located near the existing driveway east of the site . The existing storm sewer inl et was constructed with the Home Depot development located to the north of this site. The Drainage/Detention Report for the Home Depot development was prepared in August 2002 by Bury+ Partners -SA, Inc. A review of this report shows that this site is part of Drainage Area 7, which had an area of 2 .5 acres, a "c" value of 0.85, and a time of concentration, Tc , va lue of 10 minutes. This area included a portion of Lot 2R to the east of this site, which is being developed separately and will have its own storm sewer system. DRAINAGE DESIGN CRITERIA The design parameters for the storm sewer are as follows : • The Rational Method is utilized to determine peak storm water runoff rates for the storm sewer design . • Desi gn Storm Frequency Storm sewer system • Runoff Coefficients 10 and 100 -year storms eve nt s Landscap e ar eas C = 0. 60 Imperv ious sur faces C = 0.90 • Rainfall Intensity equation s a nd valu e s for Braz o s Count y can be found in Ta bl e I . • Tim e of Con centration , tc -Fo r s ma ll er drain age a re a s, a minimum tc of I O minut es is use d to de te rmin e th e ra in fa ll int e nsit y valu es. , ' TABLE 1 -·R ai n fa ll Intensity & R u noff Data Rai nfall Intensity Va l ues (in/hr) Storm tc = Event 10 min Is 7 .693 110 8 .635 '2s 9 .861 lso 11-148 1100 11 .639 Brazos County: 51:'.ear storm 10 l:'.ear storm b = 76 b= 80 d= 8 .5 d= 8 .5 e= 0.785 e= 0 .763 I = b I (tc+d)e I = Rainfall Intensity (in/hr) tc = U(V*60) tc = Time of concentration (min) L = Length (ft) V = Velocity (ft/sec) 25 l:'.ear storm 50 l:'.ear storm 100 l:'.ear storm b= 89 b= 98 b= 96 d = 8.5 d = 8.5 d= 8.0 e = 0.754 e= 0-745 e= 0 .730 (Data taken from State Department of Highwal:'.s and Public Transportation Hl:'.draulic Manual, page 2-16) STORM WATER RUNOFF DETERMINATION The peak runoff values were determined in accordance with the criteria presented in the previous section for the I 0-and I 00-year storm ev ents. The runoff coefficients are based on the development of both phases o f this site . The drainage ar ea is shown on Sheet S3 , The Drainage and Grading Plan. Runoff conditions are summarized in Table 2. TABLE 2 -Runoff Data Area No. Area S iz e Co m posit e 110 010 1100 0100 (acres) c (in/h r ) (cfs) (i n /h r ) (cfs) 1 . 1 .18 0 .85 8 .64 8 .67 11.64 11.67 STORM SEWER PIPE & INLET DESIGN The existing private storm _sewer will collect the runoff from both phases of this project. A small portion of the project site will drain directly into the existing driveway along the northern boundary of the site . This runoff will eve ntually enter the public storm sewer system through the existing inlets located in the existing driveways . The grate for the existing storm sewer inlet is a 36" x 36 " V-57 36 grate manu fa ctured by Ea st Jordan Iron Works . Th e op en area fo r th e gra te is 6 93 square inch es, or 4.8 1 squ are fee t (sf). Assuming the grate is 50 % c lo gge d, th e ava ilabl e o pen area is 2.4 sf. T he d epth of water abo ve th e gra te is d ete rmin ed by th e o rifi ce equati o n: Q = 4 .82* A g * y 112 4 Therefore, for the 10-and 100-year storm events the following depths are calculated: Q1o = 8.67 cfs ~ y = 0 .56' = 6.74" Q1 00 = 11.67 cfs ~ y = 1.02' = 12 .2" The top of the grate is proposed to be at elevation 95.3, and the top of the berm around the inlet will be constructed to elevation 97.0. There will be 8" of freeboard during the 100- year storm event. The existing 30" diameter storm sewer pipe can adequately carry the runoff. The velocity in this pipe will be 6 .3 fps and 6.8 fps for the 10-year and 100-year storm events , respectively. DETENTION FACILITY No storm water detention is required for this site because the existing private and public storm sewer systems and the Home Depot detention pond were designed for the full development of the entire Gateway Subdivision development. The design of the facilities is provided in the aforementioned Drainage/Detention Report prepared by Bury + Partners . CONCLUSIONS The construction of this project will increase the storm water runoff from this site. However, the runoff will be carried through the proposed and existing storm sewer system and into the existing detention pond. No flood damage to downstream or adjacent landowners is expected as a result of this development. 5 APPENDIX A Calculations (J 10 -year.txt Manning Pipe calculator Given Input Data: shape .......................... . solving for .................... . Diameter ....................... . Flowrate ....................... . slope .......................... . Manning's n .................... . computed Results : Depth .......................... . Area ........................... . wetted Area .................... . Wetted Perimeter ............... . Perimeter ...................... . velocity ....................... . Hydraulic Radius ............... . Percent Full ................... . Full flow Flowrate ............. . Full flow velocity ............. . circular Depth of Flow 30.0000 in 8.6700 cfs 0.0100 ft/ft 0.0140 9.7322 in 4.9087 ft2 1. 3799 ft2 36.3587 in 94.2478 in 6. 2831 fps 5.4652 in 32.4406 % 38.0873 ·cfs 7.7591 fps Pa g e 1 . . . 100 -year.t xt Manning Pipe calcul a tor Given Input Data: shape .......................... . solving for .................... . Diameter ....................... . Fl owrate ....................... . s l ope .......................... . Manning's n .................... . computed Results: Depth .......................... . Area ........................... . wetted Area .................... . Wetted Perimeter ............... . Perimeter ...................... . velocity ........................ . Hydraulic Radius ............... . Percent Full ................... . Full flow Flowrate ............. . Full flow velocity ............. . circular Depth of Flow 30.0000 in 11.6700 cfs 0 .0100 ft/ft 0 .0140 11. 3955 in 4.9087 ft2 1. 7107 ft2 39.8436 in 94.2478 in 6.8217 fps 6.1828 in 37.9850 % 38.0873 .cfs 7.7591 fps Page 1 EXHIBIT Sheet 83 -Drainage and Grading Plan 11 I ,/ Gateway Retail Center Water Demand Analysis Irrigation -25 gpm -1" water meter Carnes Design Center Lavatory Shower Water Closet Urinal Service Sink Quantity 2 2 3 2 Fixture Unit 1 2 .0 4 .0 5.0 5 .0 3.0 38 Fixture Units -Demand= 25.7 gpm 2 -3/4" Water Meter 2 Rental Spaces Item ~ Fixture Unit 1 Lavatory 2 2 .0 Dishwasher 2 1.4 Water Closet 3 5 .0 Urinal 2 5 .0 Kitchen Sink 2 4 .0 Total Fixture Unit 4 .0 8.0 15 .0 5 .0 6 .0 38.0 Total Fixture Unit 4 .0 2 .8 15.0 10.0 8.0 39.8 39 .8 Fixture Units -Demand = 26 .3 gpm 2 -3/4" Water Meter for each Space Total Water Demand Irrigation Carnes Design Center Rental Spaces Quantity QQ!!l 25 .0 25 .7 2@26.3 103.3 gpm = 0.23 cfs 2" Waterline @ 0.23 cfs Headloss - 1 psi Velocity= 10 .5 fps 2" diameter Waterline is adequate for this development Sewer Demand Analysis Sewer Demand -90% of Water Use (exduding irrigation) 78.3 gpm x 0 .9 = 70.5 gpm -Peak Flow Average Daily Flow -25380 gpd 1. Table E1 0 1B • 2000 Intern ational Plumbing Code 2. Table E1 02 • 2000 Intern ational Plu mb in g Code . : i I I\ 'I I l• i! 1· ~ : APPENDIX E ., !, . TA BLE E1018 LOAD VALUES ASSIGNED TO FIXTURES 8 LOAD VALUES, IN WATER SUPPLY FIXTURE UNITS ( ' '• TYPE OF SUPPLY FIXTURE OCCUPANCY CONTROL Cold Hot Total Bathroom group Private Flush tank 2.7 1.5 3.6 ' Bathroom group Private Flush valve 6 .0 3 .0 8.0 Bathtub Private Faucet 1.0 1.0 1.4 -· Bathtub Public Faucet 3 .0 3 .0 4 .0 7-f. Bidet Private Faucet 1.5 1.5 2.0 . !:t :.~ Combination fixture Private Faucet 2 .25 2.25 3 .0 ' Dishwashing machin e Private Automatic .-1.4 1.4 ' Drinking fountain Offices , etc. 3/g" valve 0 .25 -0 .25 Kitchen sink Private Faucet 1.0 1.0 1.4 Kitchen sink Hotel, restaurant Faucet 3.0 3 .0 4.0 Laundry trays (1 to 3) Private Faucet 1.0 1.0 1.4 Lavatory Private Faucet 0.5 0 .5 0 .7 Lavatory Public Faucet 1.5 1.5 2.0 Service sink Offices, etc. Faucet 2.25 2 .25 3.0 Shower head Public Mixing valve 3.0 3 .0 4.0 Shower head Private Mixing valve 1.0 1.0 1.4 Urinal Public l" flush valve 10.0 -10.0 Urinal Public 3/4" flush valve 5 .0 -5.0 Urinal Public Flush tank 3.0 -3.0 Washing machine (8 lbs .) Private Automatic LO 1.0 1.4 Washing machine (8 lbs .) Public Automatic 2.25 2.25 3 .0 Washing machine (15 lbs .) Public Automatic 3 .0 3 .0 4.0 Water closet Private Flush valve 6.0 -6.0 Water closet Private Flush tank 2 .2 -2.2 Water closet Public Flush valve 10.0 -10.0 Water closet Public Flush tank 5.0 -5 .0 Water closet Public or private Flushometer tank 2.0 -2.0 For SI: l inch = 25.4 mm , l pound = 0.454 kg. a . For fix tures not li s ted, loads should be assumed by comparing the fixture to one listed using waterin similar quantities and at similar rates . The assigned loads for fixtures with both hot and cold water supplies arc given for separate hot and cold water loads and for total load, the separate hot and cold water loads being thrcc- fourths of the total load for the fixture in each case. 116 2000 INTERNATIONAL PLUMBING CODE® ' " ~ n l ,t ,._ t t -; APPENDIX E TABLE E102 TABLE FOR ESTIMATING DEMAND SUPPLY SYSTEMS PREDOMINANTLY FOR FLUSH TANKS SUPPLY SYSTEMS PREDOMINANTLY FOR FLUSH VALVES Load Demand Load Demand (Water supply (Water supply fixture units) (Gallons per minute) (Cubic feet per minute) fixture units) (Gallons per minute) (Cubic feet per minute) l 3.0 0.40104 --- 2 5.0 0 .6684 ---I 3 6.5 0 .86892 --- 4 8.0 l .06944 --- 5 9.4 1.256592 5 15 .0 2.0052 6 10.7 l.430376 6 17.4 2.326032 7 11.8 l.577424 7 19 .8 2.646364 8 12.8 l.711104 8 22 .2 2.967696 9 13 .7 l.831416 9 24 .6 3.288528 10 14.6 l.951728 10 27.0 3.60936 11 15.4 2.058672 11 27.8 3.716304 12 16 .0 2.13888 12 28 .6 3.823248 13 16.5 2.20572 13 29.4 3.930192 14 17 .0 2.27256 14 30 .2 4.037136 15 17 .5 2.3394 15 31.0 4.14408 16 18 .0 2.90624 16 31.8 4 .241024 17 18 .4 2.459712 17 32.6 4.357968 18 18 .8 2.513184 18 33.4 4.464912 19 19.2 2.566656 19 34 .2 4.571856 20 19 .6 2.620128 20 35 .0 4.6788 25 21.5 2.87412 25 38 .0 5.07984 30 23 .3 3.114744 30 42 .0 5.61356 35 24 .9' 3.328632 35 44 .0 5.88192 40 26,3 I 3.515784 40 46.0 6.14928 45 27 .7 3.702936 45 48.0 6.41664 50 29.l 3.890088 50 50.0 6.684 60 32.0 4 .27776 60 54.0 7.21872 70 35 .0 4.6788 70 58 .0 7.75344 80 38 .0 5.07984 80 61.2 8.181216 90 41.0 5.48088 90 64.3 8.595624 100 43.5 5.81508 100 67 .5 9.0234 120 48 .0 6.41664 120 73.0 9.75864 140 52.5 7.0182 140 77.0 10.29336 160 57 .0 7.61976 160 81.0 10.82808 180 61.0 8.15448 180 85.5 11.42964 200 65 .0 -8.6892 200 90.0 12.0312 225 70.0 9.3576 225 95.5 12.76644 250 75 .0 10.0260 250 101.0 13.50168 275 80.0 10.6944 275 104.5 13 .96956 300 85 .0 11 .3628 300 108 .0 14.43744 400 105 .0 14.0364 400 127 .0 16 .97736 500 124.0 16.57632 500 143 .0 19 .11624 750 170 .0 22 .7256 750 177.0 23.66136 1,000 208 .0 27 .80544 1,000 208 .0 27.80544 1,250 239 .0 31.94952 1,250 239 .0 31.94952 1,500 269 .0 35 .95992 1,500 269 .0 35 .95992 1,750 297 .0 39 .70296 1,750 297 .0 39 .70 296 (Co11tinu e d ) 2000 INTERNATIONAL PLUMBING CODE® 117 .. , ' 2 11 Waterline -Gateway Center Hazen-Williams Pipe Calculator Given Input Data: Shape .......................... . Solving for .................... . Diameter ....................... . Flowrate ....................... . Length ......................... . Coefficient .................... . Computed Results: Headless ....................... . Area ........................... . Perimeter ...................... . Velocity ....................... . Circular Headloss 2.0000 in 0.2300 cfs 10.0000 ft 150.0000 1.7894 ft 0.0218 ft2 6.2832 in 10.5424 fps Attn. John LOAD AN:J\'CYSIS GATEWAY RETAIL CENTER Gas Water Heater and Heating-System 120/208 Volt 3 Phase CENTER SPACE Builders Showroom 3;556 Square F~t CATEGORY Lighting General Receptacles l20v Lighting Display Pigs 120v (on ceiling) Motors-Exhaust Fans 120v {incl 1.25%) CONNECTED LOAD 8303w 6660w 8100w 4'800w DETAIL -8 Recessed X 120w= %0w 12 2X4FlourX l04w==l248w 6 Flour Strip X 55w= 330w 3 Exits X SSw= l6.5w 56 Gen Incaod X 100w=5600w Total =8303w 3 7 X UOw = 6660w 27 X 300w... 8100w 3 x r600 = 41UO"w Kit-Display Oven Pigs 208v 2polc HJOOOw #1 Heating {fan only) 120v #2 Heating (fan only.) f20v # 1 Cooling 208v 3 phase #2 Cooling 208v 3 phase HOUSE PANEL 1630w loSOW ttZSOw 11250w l x 1680w = 1680w I X 16BOw • 1:6BOw l X fl!S-Ow=ITT50w [ (25 running amps) X 1.25 %] 1 X ll 250w= 11 ZSOw [ (25 running amps) X I.2S-%} Total 6372Jw =177 Amps {I7.92w per Sq Ft) Total 8558w = 23 Amps 3-400w MH/47'W ea= 1434w 6-lSOw MH/104wea= 6I4w 20-lOOw Incud: IOOwu=-2UOUW 3-WP GF1 Pigs lSOOw ea= 4500w ONE SP ACE EACH SIDE 1977 Sq Ft each Empty Space-Not Yet Leased =Total 3954 Sq Ft Tofaf 708S5w =197 Amp$ Estiinateafoaa(&aseaon cemenpaceJ l 7.92w per Sq Ft= 708S5w UIEltt(dc 2SS M11rlno Rd PhOIK (fZ,> 778-JJ.f4) Total 143136w=398 Amps Conntcfed"Lolftf No Demand racfbr Drainage Report, Water and Sewer Demand Analysis, Load Analysis For Gateway Retail Center College Station, Texas March 2004 Revised March 24, 2004 Developer: Todd Carnes College Station, Texas (979) 693-7835 Prepared By: Rhodes Architectural Industries P.O. Box 9389 College Station, Texas 77842 (979) 764-7150 OL/-:J ~ q :20~ 3 -eiLl .. o~ ~ t " ..... Drainage Report for Gateway Retail Center College Station, Texas February 2004 Revised March 2004 Developer: Todd Carnes College Station, Texas (979) 693-7835 Prepared By: TEXCON General .Contractors 1707 Graham Road College Station, Texas 77845 (979) 764-7743 CERTIFICATION I, Joseph P. Schultz, Licensed Professional Engineer No . 65889, State of Texas , certify that this report for the drainage design for the Gateway Retail Center in College Station, Texas, was prepared by me in accordance with the provisions of the City of College Station Drainage Policy and Design Standards for the owners hereof, with the exception that storm water runoff detention is not being required at this site since the site discharges directly into a storm sewer system which discharges into the existing detention facility for the entire Gateway Development. TABLE OF CONTENTS GATEWAY RETAIL CENTER CERTIFICATION ............................................................................................................................................................•...... 1 TABLE OF CONTENTS ........................................................................................................................................................ 2 LIST OF TABLES .................................................................................................................................................................. 2 INTRODUCTION ................................................................................................................................................................... 3 GENERAL LOCATION AND DESCRIPTION .................................................................................................................. 3 DEVELOPMENT DRAINAGE PATTERNS ....................................................................................................................... 3 DRAINAGE DESIGN CRITERIA ........................................................................................................................................ 3 . STORM WATER RUNOFF DETERMINATION ............................................................................................................... 4 STORM SEWER PIPE & INLET DESIGN ......................................................................................................................... 4 DETENTION FACILITY ...............................................................................•...................................................................... 5 CONCLUSIONS ..................................................................................................................................................................... 5 APPENDIX A ...................................................................................................•...................................................................... 6 Calculations EXHIBIT ............................................................................................................................................................................... 11 Sheet SJ -Drainage and Grading Plan LIST OF TABLES TABLE 1 -Rainfall Intensity & Runoff Data ..................................................................................................................... .4 TABLE 2 -Runoff Data ........................................................................................................................................................ .4 DRAINAGE REPORT GATEWAY RETAIL CENTER INTRODUCTION The purpose of this report is to provide the hydrological effects of the construction of the infrastructure for the Gateway Retail Center project, and to show that the storm water runo ff will be controlled in such a manner so as to have minimal offsite or do w nstrea m impact. GENERAL LOCATION AND DESCRIPTION The project is located on approximately 1.5 acres located in the Gateway Development in College Station, Texas . The site is a portion of Block 1, Lot 2R of the Phase 1 of the Gateway Subdivision. The project will be developed in 2 phases with approximately 0.8 acres being developed in Phase 1. This site has previously been developed with the clearing and grading completed with the Home Depot project. In addition, the site has previously constructed driveways on all four sides, some of which are on this tract. The site falls approximately 6' in elevation from the west side to east side of the site . DEVELOPMENT DRAINAGE PATTERNS The storm water runoff from the site flows into an existing storm sewer inlet at the north comer of the site . The post development drainage area boundary for both phases is shown on Sheet S3 , the Drainage and Grading Plan. The grading plan is based on elevations relative to the site with the existing grate inl et top assum ed to be Elevation 95.3, as shown on th e plans. Thi s inlet is located near the existing driveway east of the site . The existing storm sewer inlet was constructed with the Home Depot development located to the north of this site. The Drainage/Detention Report for the Home Depot development was prepared in August 2002 by Bury+ Partners -SA, Inc . A review of this report shows that this site is part of Drainage Area 7, which had an area of2.5 acres, a "c" value of 0 .85, and a time of concentration, Tc, value of 10 minutes. This area included a portion of Lot 2R to the east of this site, which is being developed separately and will have its own storm sewer system. DRAINAGE DESIGN CRITERIA The design parameters for the storm sewer are as follows: • The Rational Method is utilized to determine peak storm water runoff rates for the storm sewer design . • Desi gn Storm Frequency Storm sewer system • Runo ff Coeffici e nt s 10 and 100-year storms eve nts Lands ca pe ar eas C = 0 . 60 Imp erv ious s ur faces C = 0 .90 • Rain fa ll Int ensit y equ ati o ns a nd va lu es for B raz o s Count y c an be fo und in Ta bl e I . • Tim e of Co nce ntration , t, -Fo r s ma ll e r drain age a rea s, a minimum tc of I 0 minut es is use d to d e te rmin e th ~ rain fa ll int e nsit y va lu es. , ' TABLE 1--Rainfall Intensity & Runoff Data Rainfall Intensity Values (in/hr) Storm le= Event 10 min Is 7 .693 110 8.635 '2s 9.861 lso 11 .148 1100 11 .639 Brazos County: 5 Y..ear storm 1 O Y..ear storm b= 76 b= 80 d= 8.5 d= 8.5 e= 0.785 e= 0.763 I = b I (tc+d)0 I = Rainfall Intensity (in/hr) tc = U(V*60) tc = Time of concentration (min) L = Length (ft) V = Velocity (ft/sec) 25 Y..ear storm 50 Y..ear storm 100 'l..ear storm b= 89 b= 98 b= 96 d= 8 .5 d= 8 .5 d= 8.0 e= 0.754 e= 0.745 e= 0 .730 (Data taken from State Department of HiqhwaY..S and Public Transportation HY..draulic Manual, page 2-16) STORM WATER RUNOFF DETERMINATION The peak runoff values were determined in accordance with the criteria presented in the previous section for the 10-and 100-year storm events . The runoff coefficients are based on the development of both phases of this site. The drainage area is shown on Sheet S3 , The Drainage and Grading Plan. Runoff conditions are summarized in Table 2 . TABLE 2 -Runoff Data Area No. Area Size Composite 110 010 1100 0100 (acres) c (in/hr) (cfs) (in/hr) (cfs) 1 . 1 .18 0.85 8 .64 8.67 11.64 11 .67 STORM SEWER PIPE & INLET DESIGN The existing private storm ~sewer will collect the runoff from both phases of this project. A small portion of the project site will drain directly into the existing driveway along the northern boundary of the site. This runoff will eventually enter the public storm sewer system through the existing inlets located in the existing driveways . The grate for the existing storm sewer inlet is a 36" x 36" V-5736 grate manu fa ctured by East Jordan Iron Works . The open area for th e grate is 693 square inches , or 4.81 squ are fee t (sf). Assuming the grate is 50 % clo gge d, th e ava ilabl e op en area is 2.4 sf. Th e depth o f w ater abo ve the grat e is dete rmin ed by th e orifi ce equ ati o n: Q = 4.8 2* Ag * y 112 4 Therefore, for the 10 -and 100-year storm events the following depths are calcul ated: Q1o = 8.67 cfs ~ y = 0.56 ' = 6.74" Q1 00 = 11.67 cfs ~ y = 1.02' = 12.2 " The top of the grate is proposed to be at elevation 95.3, and the top of the berm around the inlet will be constructed to elevation 97.0 . There will be 8" of freeboard during the l 00 - year storm event. The existing 30" diameter storm sewer pipe can adequately carry the runoff. The velocity in this pipe will be 6 .3 fps and 6 .8 fps for the 10-year and 100-year storm events , respectively. DETENTION FACILITY No storm water detention is required for this site because the existing private and public storm sewer systems and the Home Depot detention pond were designed for the full development of the entire Gateway Subdivision development. The design of the facilities is provided in the aforementioned Drainage/Detention Report prepared by Bury + Partners . CONCLUSIONS The construction of this project will increase the storm water runoff from this site. However, the runoff will be carried through the proposed and existing storm sewer system and into the existing detention pond. No flood damage to downstream or adjacent landowners is expected as a result of this development. 5 APPENDIX A Calculations 10 -year.txt Manning Pipe calculator Given Input Data: shape .......................... . solving for .................... . Diameter ....................... . Flowrate ....................... . slope .......................... . Manning's n .................... . computed Results: Depth .......................... . Area ........................... . Wetted Area .................... . wetted Perimeter ............... . Perimeter ...................... . velocity ....................... . Hydraulic Radius ............... . Percent Full ................... . Full flow Flowrate ............. . Full flow velocity ............. . circular Depth of Flow 30.0000 in 8.6700 cfs 0.0100 ft/ft 0.0140 9.7322 in 4.9087 ft2 1.3799 ft2 36.3587 in 94.2478 in 6.2831 fps 5.4652 in 32.4406 % 38.0873 ·cfs 7.7591 fps Pa g e 1 .. 100 -year.txt Manning Pipe calculator Given Input Data: shape .......................... . solving for .................... . Diameter ....................... . Flowrate ....................... . slope .......................... . Manning' s n .................... . computed Results: Depth .......................... . Area ........................... . wetted Area .................... . wetted Perimeter ............... . Perimeter ...................... . velocity ....... •.• .............. . Hydraulic Radius ............... . Percent Full ................... . Full flow Flowrate ............. . Full flow velocity ............. . circular Depth of Flow 30.0000 in 11.6700 cfs 0.0100 ft/ft 0.0140 11.3955 in 4.9087 ft2 1.7107 ft2 39.8436 in 94.2478 in 6.8217 fps 6.1828 in 37.9850 % 38.0873 'cfs 7.7591 fps Page 1 EXHIBIT Sheet 83 -Drainage and Grading Plan 11 Gateway Retail Center Water Demand Analysis irrigation -25 gpm -1" water meter Carnes Design Center Lavatory Shower Water Closet Urinal Service Sin k Quantity 2 2 3 1 2 Fixture Unit 1 2.0 4 .0 5 .0 5 .0 3 .0 38 Fixture Un its -Demand = 25 .7 gpm 2 -314 " Water Meter 2 Re ntal Spaces Item Quantity Fixture Unit 1 Lavatory 2 2 .0 Dishwasher 2 1.4 Water Closet 3 5.0 Urinal 2 5.0 Kitchen Sink 2 4 .0 Total Fixture Unit 4 .0 8.0 15 .0 5.0 6.0 38.0 Total Fixture Un it 4 .0 2.8 15 .0 10 .0 8.0 39.8 39 .8 Fixture Units -Demand = 26 .3 gpm 2 -314" Water Meter for each Space Total Water Demand Irrigation Carnes Des ign Center Rental Spaces Quantity 9.P!!l 25.0 25 .7 2@26 .3 103.3 gpm = 0.23 cfs 2" Waterline @ 0 .23 cfs Headless - 1 psi Velocity= 10 .5 fps 2" diamete r Waterline is adequate for th is development Sewer Demand Analysis Sewer Demand -90% of Water Use (excluding irrigation) 78 .3 gpm x 0 .9 = 70 .5 gpm -Peak Flow Average Dai ly Flow -25380 gpd 1. Table E1 01B -2000 Intern ational Plumbing Code 2 . Table E 102 -2000 International Plumbing Code : '."i • i-1 ! • ~ ·wan 'J' .-! ';I ·~ ::. ·1 f I . l I' I 1, APPENDIX E TABLE E1018 LOAD VALUES ASSIGNED TO FIXTURES 8 TYPE OF SUPPLY LOAD VA LUES, IN WATER SUPPLY FIXTURE UNITS(~ FIXTURE OCCUPANCY CONTROL Cold Hot Total ., Bathroom group Private Flush tank 2 .7 1.5 3 .6 =11 Bathroom group Private Flush valve 6 .0 3 .0 8 .0 Bathtub Private Faucet 1.0 1.0 1.4 ·~ Bathtub Public Faucet 3 .0 3 .0 4.0 ~ 1.5 ~ Bidet Private Faucet 1.5 2.0 1: Combination fixture Private Faucet 2.25 2 .25 3 .0 - Dishwashing machine Private Automatic .. -1.4 1.4 · - --Drinking fountain Offices, etc. 3/g" valve 0.25 0.25 ~ Kitchen sink Private Faucet 1.0 1.0 1.4 ~ Kitchen sink Hotel, restaurant Faucet 3 .0 3 .0 4.0 I Laundry trays (1 to 3) Private Faucet 1.0 1.0 1.4 .. _ Lavatory Private Faucet 0 .5 0.5 0 .7 Lavatory Public Faucet 1.5 1.5 2.0 Service sink Offices, etc. Faucet 2.25 2 .25 3 .0 Shower head Public Mixing valve 3.0 3 .0 4.0 Shower head Private Mixing valve 1.0 1.0 1.4 Urinal Public l" flush valve 10.0 -10.0 Urinal Public 3/4" flus h valve 5.0 -5.0 Urinal Public Flush tank 3.0 -3.0 Washing machine (8 lbs .) Private Automatic 1.0 1.0 1.4 Washing machine (8 lbs.) Public Automatic 2 .25 2 .25 3 .0 Washing machine (15 lbs .) Public Automatic 3 .0 3 .0 4.0 Water closet Private Flush valve 6 .0 -6.0 Water closet Private Flush tank 2 .2 -2 .2 Water closet Public Flush valve 10.0 -10.0 Water closet Public Flush tank 5 .0 -5.0 Water closet Public or private Aushometer tank 2 .0 -2 .0 For SI : I inch = 25.4 mm, I pound = 0 .454 kg . a. For fixtures not listed, loads should be assumed by comparing the fixture to one listed using water in similar quantities and at similar rates . The assigned loads for fixtures with both hot and cold water supplies are given for separate hot and cold waterloads and for total load, the separate hot and cold waterloads being three - fourths of the total load for the fixture in each case . 116 2000 INTERNATIONAL PLUMBING CODE® ~ .. .. .. t h • ' f t i. APPENDIX E TABLE E102 TABLE FOR ESTIMATING DEMAND SUPPLY SYSTEMS PREDOMINANTLY FOR FLUSH TANKS SUPPLY SYSTEMS PREDOMINANTLY FOR FLUSH VALVES Load Demand Load Demand (Water supply (Water supply fixture units) (Gallons per minute) (Cubic feet per minute) fixture units) (Gallons per minute) (Cubic feet per minute) 1 3 .0 0.40104 --- 2 5 .0 0 .6684 ---I 3 6 .5 0 .86892 --- 4 8 .0 1.06944 --- 5 9.4 1.256592 5 15 .0 2.0052 6 10.7 1.430376 6 17.4 2.326032 7 11.8 1.577424 7 19 .8 2.646364 8 12 .8 1.711104 8 22 .2 2.967696 9 13.7 1.831416 9 24.6 3 .288528 10 14.6 1.951728 10 27.0 3 .60936 11 15.4 2.058672 II 27.8 3.716304 12 16.0 2.13888 12 28 .6 3.823248 13 16.5 2.20572 13 29.4 3.930192 14 17 .0 2.27256 14 30.2 4 .037136 15 17.5 2.3394 15 31.0 4.14408 16 18.0 2.90624 16 31.8 4.241024 17 18.4 2.459712 17 32.6 4.357968 18 18 .8 2.513184 18 33.4 4.464912 19 19 .2 2.566656 19 34.2 4.571856 20 19 .6 2.620128 20 35 .0 4.6788 25 21.5 2.87412 25 38.0 5.07984 30 23 .3 3 .114744 30 42.0 5 .61356 35 24.9' 3.328632 35 44.0 5.88192 40 26) I 3.515784 40 46 .0 6.14928 45 27 .7 3.702936 45 48.0 6.41664 50 29.1 3.890088 50 50.0 6 .684 60 32.0 4.27776 60 54.0 7 .21872 70 35 .0 4.6788 70 58.0 7 .75344 80 38 .0 5.07984 80 61.2 8.181216 90 41.0 5.48088 90 64 .3 8.595624 100 43 .5 5 .81508 100 67 .5 9.0234 120 48.0 6 .41664 120 73.0 9 .75864 140 52.5 7.0182 140 77.0 10 .29336 160 57 .0 7.61976 160 81.0 10 .82808 180 61.0 8.15448 180 85 .5 11.42964 200 65 .0 8.6892 200 90.0 12 .0312 225 70.0 9.3576 225 95 .5 12 .76644 250 75 .0 10.0260 250 101.0 13.50168 275 80.0 10.6944 275 104 .5 13 .96956 300 85 .0 11.3628 300 108 .0 14 .43744 400 105 .0 14.0364 400 127 .0 16 .97736 500 124 .0 16.57632 500 143 .0 19.11624 750 170 .0 22 .7256 750 177 .0 23 .66136 1,000 208 .0 27 .80544 1,000 208.0 27.80544 1,250 239.0 31.94952 1,250 239 .0 31 .94952 1,500 269 .0 35 .95992 1,500 269 .0 35 .95992 1,750 . 297 .0 39.70296 1,750 297 .0 39 .70296 (Cor1ti11u ed) 2000 INTERNATIONAL PLUMBING CODE<' 117 2" Waterline -Gateway Center Hazen-Williams Pipe Calculator Given Input Data: Shape .......................... . Solving for .................... . Diameter ....................... . Flowrate ....................... . Length ......................... . Coefficient .................... . Computed Results: Headloss ....................... . Area ........................... . Perimeter ...................... . Velocity ....................... . Circular Headloss 2.0000 in 0.2300 cfs 10.0000 ft 150.0000 1. 7894 ft 0.0218 ft2 6.2832 in 10.5424 fps Attn. John LOAD ANALYSIS GATEWAY RETAIL CENTER Gas Water Heater and Heating-System 120/208 Volt 3 Phase CENTER SP ACE Builders Showroom 3;556 Square F-eet CATEGORY Lighting General Receptacles 120v Lighting Display Plgs 120v (on ceiling) Motors-Exhaust Fans 120v (incl 1.25%) CONNECTED LOAD 8303w 6600w 8l00w 4800w DETAIL .g ReeeMed X 120w= %0w 12 2X4 Flour X l04wcl248w 6 Flour Strip X 55w= 330w 3 Exits X SSw= 16.5w .56 Geo lncand X l0Qw=560Qw Total =83(J3w 3 7 x l&Ow = 6660w 27 X 300w... 8l00w 3 x r6oo-= 480ffw Kit-Display Oven Pigs 208v 2 pole HJOOOw 2 X SO<JOw"" 11JOOOw #1 Heating(fan only) l20v #2 Heating (fan only) f20v # 1 Cooling 208v 3 phase #2 Cooling 208v 3 phase HOUSE PANEL 16SOw t680W lm'Ow ll250w IX 1680w = 1680w IX I 680w • 1:680w ix n zs-ow.=-rr2s0w [ (25 running amps) X l .25 %] 1xl1250w=l 1250w [ (25 running amps) X I .2S-%J Total 63723w =177 AblpS (17.92w per Sq Ft) Total 8558w = 23 Amps 3-400w MH/473W ea= 14.34w 6-lSOw MW104wea= 6Z4w 20-lOOw Inamit IOOw-e&= 2UOOw 3-WP GF1 Pigs lSOOw ea= 4SOOw ONE SPACE EACH SIDE 1977 Sq Ft each Empty Spac.e-Not Yet Leased =Total 3954 Sq Ft Totaf 70855w =l97 Amps EstiinateaI:oruf (&ase<fon cen1en;paceJ l 7 .92w per Sq Ft= 7i>SS5w UIEl«trfc JSS Morino Rd Phol( ftW 778·31441 Total 143136w =3• Amps ConnecfedLolOf No Demand Factor ' J Drainage Report for Gateway Retail Center College Station, Texas February 2004 Developer: Todd Carnes College Station, Texas (979) 693-7835 Prepared By: TEXCON General Contractors 1707 Graham Road College Station, Texas 77845 (979) 764-7743 CERTIFICATION I, Joseph P. Schultz, Licensed Professional Engineer No . 65889, State of Texas , certify that this report for the drainage design for the Gateway Retail Center in College Station, Texas, was prepared by me in accordance with the provisions of the City of College Station Drainage Policy and Design Standards for the owners hereof, with the exception that storm water runoff detention is not being required at this site since the site discharges directly into a storm sewer system which discharges into the existing detention facility for the entire Gateway Development. TABLE OF CONTENTS GATEWAY RETAIL CENTER CERTIFICATION .................................................................................................................................................................. 1 TABLE OF CONTENTS ........................................................................................................................................................ 2 LIST OF TABLES .................................................................................................................................................................. 2 INTRODUCTION ................................................................................................................................................................... 3 GENERAL LOCATION AND DESCRIPTION .................................................................................................................. 3 DEVELOPMENT DRAINAGE PATTERNS ....................................................................................................................... 3 DRAINAGE DESIGN CRITERIA ........................................................................................................................................ 3 STORM WATER RUNOFF DETERMINATION .............................................................................................................. .4 STORM SEWER PIPE & INLET DESIGN ........................................................................................................................ .4 DETENTION FACILITY ...................................................................................................................................................... 5 CONCLUSIONS ..................................................................................................................................................................... 5 APPENDIX A .......................................................................................................................................................................... 6 Calculations EXHIBIT ............................................................................................................................................................................... 11 Sheet S3 -Drainage and Grading Plan LIST OF TABLES TABLE 1 -Rainfall Intensity & Runoff Data ..................................................................................... 4 TABLE 2 -Runoff Data ......................................................................................................................... 4 DRAINAGE REPORT GATEWAY RETAIL CENTER INTRODUCTION T he purpose of this report is to provide th e hydrolo g ical effect s of the construction of th e infras tructure for th e Gatew a y Re tail C enter proj ec t , and to sh o w that th e stonn w at er run off w ill be controlled in such a manner so as to have minimal offs it e or downstre a m impact. GENERAL LOCATION AND DESCRIPTION The project is located on approximately 1.5 acres located in the Gateway Dev e lopment in College Station, Texas . The site is a portion of Block 1, Lot 2R of the Phase 1 of the Gatew ay Subdivision. The project will be developed in 2 phases with approximately 0 .8 acres being developed in Phase 1. This site has previously been developed with the clearing and grading completed with the Home Depot project. In addition, the site has previously constructed driveways on all four sides, some of which are on this tract. The site falls approximately 6 ' in elevation from the west side to east side of the site . DEVELOPMENT DRAINAGE PATTERNS The storm water runoff from the site flows into an ex isting storm sewer inlet at the north comer of the site. The post development drainage area boundary for both phases is shown on Sh eet S3 , the Drainage and Grading Plan. The grading plan is based on elevations relative to the site with the existing grate Inlet No. 1 top assumed to be Elevation 100, as shown on the plans . This inlet is located in the existing driveway south of the site . The existing storm sewer inlet was constructed with the Home Depot development located to the north of this site . The Drainage/Detention Report for the Home Depot development was prepared in August 2002 by Bury + Partners -SA, Inc. A review of this report shows that this site is part of Drainage Area 7, which had an area of 2.5 acres , a "c" value of 0.85 , and a time of concentration, Tc , valu e of 10 minutes . This area included a portion of Lot 2R to the east of this site, which is be in g developed separately and will have its own storm sewer system. DRAINAGE DESIGN CRITERIA The design parameters for the storm sew er are as follows: • The Rational Method is utili z ed to determine peak storm water runoff rates for th e storm sewer design. • Desi gn Storm Frequency Stonn sewer s ystem • Runo ff Co e ffici ents 10 and 100 -ye ar storms eve nt s Landscap e areas C = 0 .60 Imp e rv ious s ur fa ces C = 0 .9 0 • Rain fa ll Int ensit y equati o ns and va lu es for Bra zos C ount y ca n be fo und in Ta bl e I . • Tim e o f C onc e ntrati o n, le -Fo r s ma ll e r drain age a reas , a minimum tc of I 0 minut es is use d to determin e th e ra in fa ll int e ns it y va lu es. ' ·' TABLE 1 -Rainfall Intensity & Runoff Data Rainfall Intensity Values (in/hr) Storm t c = Event 10 min Is 7 .693 110 8 .635 '2s 9 .861 lso 11 .148 1100 11.639 Brazos County: 5 year storm 10 year storm b= 76 b= 80 d= 8.5 d= 8 .5 e= 0.785 e= 0.763 I = b I {tc+d)e I = Rainfall Intensity (in/hr) tc = L/(V*60) tc = Time of concentration (min) L = Length (ft) V = Velocity (ft/sec) 25 year storm 50 year storm 100 year storm b= 89 b= 98 b= 96 d = 8.5 d = 8.5 d= 8.0 e= 0.754 e= 0.745 e= 0.730 (Data taken from State Department of Highways and Public Transportation Hydraulic Manual, page 2-16) STORM WATER RUNOFF DETERMINATION The peak runoff values were determined in accordance with the criteria presented in the previous section for the 10-and 100-year storm events. The runoff coefficients are based on the development of both phases of this site. The drainage area is shown on Sheet S3, The Drainage and Grading Plan. Runoff conditions are summarized in Table 2. TABLE 2 -Runoff Data Area Size Composite 110 010 acres C in/hr cfs) f--~~~--+-~'--~-'---+-~~~~-t----'-~-'---t~--'- Area No. 1. 01 0 .85 8 .64 7.42 STORM SEWER PIPE & INLET DESIGN 1100 (in/hr) 11 .64 0100 (cfs) 9 .99 The existing private storm sewer Inlet No. 2 will be relocated ap pro ximately 25 feet to the north of where it is currently located so that the proposed building can be constructed. A 30" diam eter storm sewer pipe will be constructed from the relocated inlet to the existing storm sewer junction box. This relocated storm sewer inlet (proposed storm sewer Inlet No. I) will collect the runoff from both phases of this project. The runoff from the Phase I building roof wi ll be collected by a roof gutter system and discharged at the inlet. Th e Phase 2 building and most of the parking lot will drain to a concrete flume that is located along the north side of the Phase I building . A portion of the project site will drain direct ly into the existing driveway a lon g the southern boundary of the site . This runoff wi ll eventua ll y enter the public storm se we r system thro ugh the ex ist in g inlets locat ed in th e ex istin g dri ve w ay s . ..j The grate for the existing storm sewer inlet is a 36" x 36" V-5736 grate manufactured by East Jordan Iron Works . The open area for the grate is 693 square inches, or 4 .81 square feet (sf). Assuming the grate is 50% clogged , the available open area is 2.4 sf. The depth of water above the grate is determined by the orifice equation : Q = 4.82* Ag * y 112 Therefore, for the 10-and 100-year storm events the following depths are calculated: Q1 0 = 7.42 cfs ~ y = 0.41' = 4.9" Qioo = 9.99 cfs ~ y = 0.75' = 9.0 " The top of the grate is proposed to be at elevation 2~8.5, and the top of the berm around the inlet will be elevation 100.0. There will be 9" of freeboard during the 100-year storm event. The proposed flume and storm sewer pipe design parameters and summaries are found in Appendix A. The flume will be 4' wide and have a 6" high curb on each side. The depth of flow for the flume is 4" and 4 .8" for the 10-year and 100-year storm events, respectively. The storm sewer pipe size was selected to be 30" diameter because.it is the same as the existing pipe diameter. The flowline into the existing junction box will match the existing pipe flow line. The velocity in this pipe will be 6 .0 fps and 6.5 fps for the 10- year and 100-year storm events, respectively. DETENTION FACILITY No storm water detention is required for this site because the existing private and public storm sewer systems and the Home Depot detention pond were designed for the full development of the entire Gateway Subdivision development. The design of the facilities is provided in the aforementioned Drainage/Detention Report prepared by Bury + Partners . CONCLUSIONS The construction of this project will increase the storm water runoff from this site . However, the runoff will be carried through the proposed and existing storm sewer system and into the existing detention pond. No flood damage to downstream or adjacent landowners is expected as a result of this development. 5 APPENDIX A Calculations Concrete Flume -10-yr Storm Channel Calculator Given Input Data: Shape .......................... . Solving for .................... . Flowrate ....................... . Slope .......................... . Manning's n .................... . Height ......................... . Bottom width ................... . Computed Results: Depth .......................... . Velocity ....................... . Flow area ...................... . Flow perimeter ................. . Hydraulic radius ............... . Top width ...................... . Area ........................... . Perimeter ...................... . Percent full ................... . Rectangular Depth of Flow 7.4200 cfs 0.0130 ft/ft 0.0130 6.0000 in 48.0000 in 3.9599 in 5.6213 fps 1.3200 ft2 55.9199 in 3.3991 in 48.0000 in 2.0000 ft2 60.0000 in 65.9991 % Concrete Flume -100-yr Storm Channel Calculator Given Input Data: Sha pe .......................... . Solving for .................... . Flowrate ....................... . Slope .......................... . Manning's n .................... . Height ......................... . Bot tom width ................... . Computed Results: Depth .......................... . Velocity ....................... . Flow area ...................... . Flow perimeter ................. . Hydraulic radius ............... . Top width ...................... . Area ........................... . Perimeter ...................... . Percent full ................... . Rectangular Dep th of Flow 9.9900 cfs 0.0130 ft /ft 0 .0130 8.0 000 in 48 .0000 in 4.7892 in 6.25 78 fps 1.5964 ft2 57 .5784 in 3.9925 in 48.0000 in 2.6667 ft2 64.0000 in 59.8651 % 30 11 Storm Sewer -10 -yr Storm Manning Pipe Calculator Given Input Data: Shape .......................... . Solving for .................... . Diameter ....................... . Flowrate ....................... . Slope .......................... . Manning' s n .................... . Computed Results: Depth .......................... . Area ........................... . Wetted Area .................... . Wetted Perimeter ............... . Perimeter ...................... . Velocity ....................... . Hydraulic Radius ............... . Percent Full ................... . Full flow Flowrate ............. . Full flow velocity ............. . Circular Depth of Flow 30 .0000 in 7.4200 cfs 0.0100 ft/ft 0.0 140 8.9759 in 4.9087 ft2 1.2339 ft2 34.7257 in 94.2478 in 6.0132 fps 5.1169 in 29.9195 % 38.0873 cfs 7.7591 fps 30" Storm Sewer Pipe -100-yr Storm Manning Pipe Calcula to r Given Input Data: Shape .......................... . Solving for .................... . Diameter ....................... . Flowrate ....................... . Slope .......................... . Manning's n .................... . Computed Results: Depth .......................... . Area ........................... . Wetted Area .................... . Wetted Perimeter ............... . Perimeter ...................... . Velocity ....................... . Hydraulic Radius ............... . Percent Full ................... . Full flow Flowrate ............. . Full flow velocity ............. . Circular Depth of Flow 30.0000 in 9.9900 cfs 0.0100 ft/ft 0.0140 10.4863 in 4.9087 ft2 1.5284 ft2 37.9543 in 94.2478 in 6.5363 fps 5.7988 in 34.9542 % 38.0873 cfs 7.7591 fps ' EXHIBIT Sheet 83 -Drainage and Grading Plan 11 I ~-ti DEVELOPMENT PERMIT PERMIT NO . 04-05 Project: GATEWAY RETAIL CENTER COLllC.l STATION FOR AREAS INSIDE THE SPECIAL FLOOD HAZARD AREA RE : CHAPTER 13 OF THE COLLEGE STATION CITY CODE SITE LEGAL DESCRIPTION: The Gateway Lots 2RA and 2RC DATE OF ISSUE: 04/14/04 OWNER: Baker and Carnes Investments c/o Todd Carnes 230 Southwest Parkway East College Station , Texas 77840 SITE ADDRESS: 730 Earl Rudder Freeway South DRAINAGE BASIN: Burton Creek VALID FOR 9 MONTHS CONTRACTOR: TYPE OF DEVELOPMENT: Full Development Permit SPECIAL CONDITIONS: All construction must be in compliance with the approved construction plans All trees required to be protected as part of the landscape plan must be completely barricaded in accordance with Section 7.5.E., Landscape/Streetscape Plan Requirements of the City's Unified Development Ordinance , prior to any operations of this permit. The cleaning of equipment or materials within the drip line of any tree or group of trees that are protected and required to remain is strictly prohibited . The disposal of any waste material such as , but not limited to , paint, oil , solvents, asphalt , concrete , mortar, or other harmful liquids or materials within the drip line of any tree required to remain is also prohibited . TCEQ PHASE II RULES IN EFFECT The Contractor shall take all necessary precautions to prevent silt and debris from leaving the immediate construction site in accordance with the approved erosion control plan as well as the City of College Station Drainage Policy and Design Criteria . If it is determined the prescribed erosion control measures are ineffective to retain all sediment onsite , it is the contractors responsibility to implement measures that will meet City , State and Federal requirements . The Owner and/or Contractor shall assure that all disturbed areas are sodden and establishment of vegetation occurs prior to removal of any silt fencing or hay bales used for temporary erosion control. The Owner and/or Contractor shall also insure that any disturbed vegetation be returned to its original condition , placement and state . The Owner and/or Contractor shall be responsible for any damage to adjacent properties , city streets or infrastructure due to heavy machinery and/or equipment as well as erosion , siltation or sedimentation resulting from the permitted work. In accordance with Chapter 13 of the Code of Ordinances of the City of College Station, measures shall be taken to insure that debris from construction , erosion , and sedimentation shall not be deposited in city streets , or existing drainage fac iliti es . I hereby grant this permit for development of an area inside the special flood hazard area . All development shall be in accordance with the plans and specifications submitted to and approved by the City Engineer in the development permit application for the above named project and all of the codes and ordinances of the City of College Station that apply . DL-}-JL/-D'-f Date Lf-)S--Ol( Owner/Agent/Contractor Date Drainage Report for Gateway Retail Center College Station, Texas February 2004 Developer: Todd Carnes College Station, Texas (979) 693-7835 Prepared By: TEXCON General Contractors 1707 Graham Road College Station, Texas 77845 (979) 764-7743 CERTIFICATION I, Joseph P. Schultz, Licensed Professional Engineer No. 65889, State of Texas, certify that this report for the drainage design for the Gateway Retail Center in College Station, Texas, was prepared by me in accordance with the provisions of the City of College Station Drainage Policy and Design Standards for the owners hereof, with the exception that storm water runoff detention is not being required at this site since the site discharges directly into a storm sewer system which discharges into the existing detention facility for the entire Gateway Development. JosI>:SChultz, P.E . TABLE OF CONTENTS GATEWAY RETAIL CENTER CERTIFICATION .................................................................................................................................................................. 1 TABLE OF CONTENTS ........................................................................................................................................................ 2 LIST O F TABLES .................................................................................................................................................................. 2 INTRODUCTION ................................................................................................................................................................... 3 GENERAL LOCATION AND DESCRIPTION .................................................................................................................. 3 DEVELOPMENT DRAINAGE PA TTERNS ....................................................................................................................... 3 DRAINAGE DESI GN C RITERIA ........................................................................................................................................ 3 STORM WATER R UN OFF DETERMINATION .............................................................................................................. .4 STORM SEWER PIPE & INLET DESIGN ........................................................................................................................ .4 DETENTION FACILITY ...................................................................................................................................................... 5 CONCLUSIONS ..................................................................................................................................................................... 5 APPENDIX A .......................................................................................................................................................................... 6 Calculations EXHIBIT ............................................................................................................................................................................... 11 Sheet S3 -Drainage and Grading Pla11 LIST OF TABLES TABLE 1 -Rainfall Intensity & Runoff Data ..................................................................................... 4 TABLE 2 -Runoff Data ......................................................................................................................... 4 DRAINAGE REPORT GATEWAY RETAIL CENTER INTRODUCTION The purpose of this report is to provide the hydrolo g ical effects of the construction of th e infrastructure for the Gateway Retail C enter project , and to show that th e stom1 water runoff will be controlled in such a manner so as to have minimal offsite or downstream impact. GENERAL LOCATION AND DESCRIPTION The project is located on approximately 1.5 acres located in the Gateway Development in College Station, Texas . The site is a portion of Block 1, Lot 2R of the Phase l of the Gateway Subdivision. The project will be developed in 2 phases with approximately 0.8 acres being developed in Phase 1. This site has previously been developed with the clearing and grading completed with the Home Depot project. In addition, the site has previously constructed driveways on all four sides , some of which are on this tract. The site falls approximately 6 ' in elevation from the west side to east side of the site. DEVELOPMENT DRAINAGE PATTERNS The storm water runoff from the site flows into an existing storm sewer inlet at the north corner of the site. The post development drainage area boundary for both phases is shown on Sheet S3 , the Drainage and Grading Plan . The grading plan is based on elevations relative to the site with the existing grate Inlet No. 1 top assumed to be E levation 100 , as shown on the plans . This inlet is located in the existing driveway south of the site. The existing storm sewer inlet was constructed with the Home Depot development located to the north of this site. The Drainage/Detention Report for the Home Depot development was prepared in August 2002 by Bury+ Partners -SA, Inc. A review of this report shows that this site is part of Drainage Area 7, which had an area of 2.5 acres, a "c" value of 0.85 , and a time of concentration, Tc , value of 10 minutes . This area included a portion of Lot 2R to the east of this site, which is being developed separately and will have its own storm sewer system. DRAINAGE DESIGN CRITERIA The design parameters for the storm sewer are as follows : • The Rational Method is utilized to determine peak storm water runoff rates for the stonn sewer design. • Design Storm Frequency Storm sewer system • Runoff Coefficients 10 and 100-year storms ev ents Landscap e ar eas C = 0 .60 [mperv ious s urfaces C = 0 .90 • Rainfall int ensit y equations and va lu es for Br az o s C ount y can be found in T a bl e I . • Tim e of C oncentration , tc -For s ma ll e r draina ge a reas, a minimum t, of I 0 minut es is use d to de termin e th e ra infall int e ns it y va lu es. ·' TABLE 1 -Rainfall Intensity & Runoff Data Rainfall Intensity Values (in/hr) Storm le= Event 10 min Is 7.693 110 8.635 hs 9.861 lso 11 .148 1100 11 .639 Brazos County: 5 year storm 10 year storm b= 76 b= 80 d= 8.5 d = 8.5 e= 0.785 e= 0 .763 I = b I (tc+d)e I = Rainfall Intensity (in/hr) tc = U(V*60) tc =Time of concentration (min) L = Length (ft) V = Velocity (ft/sec) 25 year storm 50 year storm 100 year storm b= 89 b= 98 b= 96 d= 8.5 d= 8.5 d= 8.0 e= 0.754 e= 0.745 e= 0.730 (Data taken from State Department of Highways and Public Transportation Hydraulic Manual, page 2-16) STORM WATER RUNOFF DETERMINATION The peak runoff values were determined in accordance with the criteria presented in the previous section for the 10-and 100-year storm events. The runoff coefficients are based on the development of both phases of this site. The drainage area is shown on Sheet S3 , The Drainage and Grading Plan. Runoff conditions are summarized in Table 2. TABLE 2 -Runoff Data Area Size Composite 110 acres C in/hr) t--~~~--+~~~-'--+-~~~~+-~~ Area No. 1.01 0 .85 8.64 STORM SEWER PIPE & INLET DESIGN 010 (cfs) 7.42 1100 (in/hr) 11.64 0100 (cfs) 9.99 The existing private storm sewer Inlet No. 2 will be relocated approximately 25 feet to the north of where it is currently located so that the proposed building can be constructed. A 30" diameter storm sewer pipe w ill be constructed from the relocated inlet to th e existing storm sewer junction box. This relocated storm sewer inlet (proposed storm sewer Inlet No. 1) will collect the runoff from both phases of this project. The runoff from the Phas e 1 building roof wi ll be collected by a roof gutter system and discharged at the inl et. The Phase 2 building and most of th e parkin g lot will drain to a co ncrete flume th at is lo cated a long th e north side of the Phase 1 building. A portion of the project site w ill drain directly into the existing dri ve way a lon g the southern bound a r y of th e site. This runoff w ill eventual ly enter the publ ic stom1 sewe r system through the ex istin g inl ets loca ted in the ex ist in g dri veways . -l The grate for the existing storm sewer inl et is a 36 " x 36" V-5736 grat e manu fa ctured by East Jordan Iron Works . The open area for the grat e is 693 square inch es, or 4 .81 square fe et (sf). Assuming th e grate is 50 % clo gge d , the av ailable op en area is 2.4 sf. T he depth of water above the grate is determined by the orific e equation : Q = 4 .82 * Ag * y 112 Therefore, for the 10-and 100-year storm events th e followin g depths are calcul ated: Q1 0 = 7.42 cfs ~ y = 0.41 ' = 4 .9" Qi oo = 9 .99 cfs ~ y = 0 .75 ' = 9.0 " T he top of the grate is proposed to be at elevation 298 .5, and the top of the berm around the inlet will be elevation 100 .0 . There will be 9" of freeboard during the 100-year storm event. The proposed flume and storm sewer pipe design parameters and summaries are found in Appendi x A. The flume will be 4' wide and have a 6" high curb on each side . The depth of flow for the flume is 4" and 4.8 " for the 10-year and 100-year storm events , respectively. The storm sewer pipe size was selected to be 30" diameter because .i t is the same as the existing pipe diameter. The flow line into the existing junction box will match the existing pipe flowline . The velocity in this pipe will be 6 .0 fps and 6 .5 fps for the 10- year and 100-year storm events, respecti v ely. DETENTIO N FACILITY No storm water detention is required for this site because the ex isting private and public storm sewer systems and the Home Depot detention pond were designed for the full development of the entire Gateway Subdivision development. The design of the facilities is provided in the aforementioned Drainage/Detention Report prepared by Bury+ Partners. CONCLUSI ONS The construction of this project will increase the storm water runoff from this site . However, the runoff will be carried throu gh the proposed and existing storm sewer system and into the existing detention pond. No flood damage to downstream or adj acent landowners is expected as a result of this developm ent. APPENDIX A Calculations Concrete Flume -1 0-yr Storm Channel Calculator Given Input Data: Shape .......................... . Solving for .................... . Flowrate ....................... . Slope .......................... . Manning's n .................... . Height ......................... . Bot tom width ................... . Computed Resul ts: Depth .......................... . Velocity ....................... . Flow area ...................... . Flow perimeter ................. . Hydraulic radius ............... . Top width ...................... . Area ........................... . Perimeter ...................... . Percent f ul 1 ................... . Rectangular Depth of Flow 7.4200 cfs 0.0130 ft/ft 0 .01 30 6.0000 in 48.0000 in 3 .959 9 in 5 .621 3 fps 1.3200 ft2 55 .91 99 in 3 .3991 in 48.0000 in 2.0000 ft2 60.0000 in 65.9991 % Concrete Flume -100-yr Storm Channel Calculator Given Input Data : Shape .......................... . Solving for .................... . Flowrate ....................... . Slope .......................... . Manning' s n .................... . Height ......................... . Bot torn width ................... . Computed Results: Depth .......................... . Velocity ....................... . Flow area ...................... . Flow perimeter ................. . Hydraulic radius ............... . Top width ...................... . Area ........................... . Perimeter ...................... . Percent full ................... . Rectangular Depth of Flow 9.9900 cfs 0 .01 30 ft/ft 0.0 130 8.0000 in 48.0000 in 4.7892 in 6.2578 fps 1.5964 ft2 57.5784 in 3.9925 in 48.0000 in 2.6667 ft2 64.0000 in 59.8651 % 30" Storm Sewer -10-yr Storm Manning Pipe Calculator Given Input Data: Shape .......................... . Solving for .................... . Diameter ....................... . Flowrate ....................... . Slope .......................... . Manning' s n .................... . Computed Results: Depth .......................... . Area ........................... . Wetted Area .................... . Wetted Perimeter ............... . Perimeter ...................... . Velocity ....................... . Hydraulic Radius ............... . Percent Full ................... . Full flow Flowrate ............. . Full flow velocity ............. . Circular Depth of Flow 30.0000 in 7.4200 cfs 0.0100 ft/ft 0.0140 8.9759 in 4.9087 ft2 1.2339 ft2 34.7257 in 94.2478 in 6.0132 fps 5.1169 in 29.9195 % 38.0873 cfs 7.7591 fps 30" Storm Sewer Pipe -100-yr Storm Manning Pipe Ca lculat or Given Input Data: Shape .......................... . Solving for .................... . Diameter ....................... . Flowrate ....................... . Slope .......................... . Manning's n .................... . Computed Results: Depth .......................... . Area ........................... . Wetted Area .................... . Wetted Perimeter ............... . Perimeter ...................... . Velocity ....................... . Hydraulic Radius ............... . Percent Full ................... . Full flow Flowrate ............. . Full flow velocity ............. . Circular Depth of Flow 30.0000 in 9.9900 cfs 0.0100 ft/ft 0.0140 10.4863 in 4.9087 ft2 1.5284 ft2 37.9543 in 94.2478 in 6.5363 fps 5.7988 in 34.9542 % 38.0873 cfs 7.7591 fps • 4 EXHIBIT Sheet S3 -Drainage and Grading Plan 11 FOR OFFICE USE ONLY P&Z CASE NO .: ----- SITE PLAN APPLICATION MINIMUM SUBMITTAL REQUIREMENTS . /Site plan application completed in full. -y;T $200.00 Application Fee . '7"" $200 .00 Development Permit Application Fee. DATE SUBMITTED: __ $600 .00 Public Infrastructure Inspection Fee if applicable . (This fee is payable if construction of a public waterline, sewerline, sidewalk, street or drainage facilities is involved.) V Eleven (11) folded copies of site plan · __ One (1) folded copy of the landscape plan. __ One (1) copy of building elevation required.for buildings with a footprint of 20,000 sq . ft . or greater __ A list of building materials for all facades that are visible from the public right-of-way . __ A copy of the attached site plan checklist with all items checked off or a brief explanation as to why they are not checked off. __ Parkland Dedication requirement approved by the Parks & Recreation Board, please provide proof of approval (if applicable). Date of Preapplication Conference: ______________________ _ NAME OF PROJECT C2:>q.\e~c) \<..e.,-\:.~.\ [<:CJ\.er ADDRESS ___ --:----------------------------- LEGAL 0EscR1rT10N Lo\ cl.\{ c_ b \ \z. \ APPLICANT/PROJECT MANAGER'S INFORMATION (Primary Contact for the Project): Name \. (__ ('(\.e~ Street Address ;;13,0 Sbv...~~e~\ State '\-X Zip Code 1 Jiyo Phone Number kf\3-:)i~ PROPERTY OWNER'S INFORMATION : a..rK~ ~\; City \Ci '"- E-Mail Address ~C...o.. t C\e. s ~tc._c ('\. \:v\<!. . <\e.. \- Fax Number lsf\~-'li~C\ Name ~ e_~ -.S:.'<'-~~\~c.1\-\s LL c_ StreetAddress 9-ZC ~~\AC<?.~\ 9o..rY,~ 1:_o...~\-City \\ene. ~\~\.\o" State '1:-J< Zip Code 71 &YD E-Mail Address ------------ Phone Number lo:\. ~-J 87:>S" Fax Number _lcB___,'-"~"---1....:....8=-'::f\-=-..J.__ ______ _ ARCHITECT OR ENGINEER'S INFORMATION: Name Rf\!::._ ~\~" Street Address ----------------- State "'\--"')( Zip Code 71~4 ~ E-Mail Address ------------ Phone Number _1_~_'4_-_'J~l_S'_D ___ _ Fax Number ------------- 6/13/03 I of6 "OTHER CONTACTS (Please specify type of contact, i.e . project manager, potential buyer, local contact , etc .) Name --------------------------------- Street Address -----------------City ---------- E-Mail Address State _____ Zip Code _____ _ ------------ Phone Number -----------Fax Number ____________ _ PRESENT USE OF PROPERTY -------------------------- PROPOSED USE OF PROPERTY VARIANCE(S) REQUESTED AND REASON(S) ------------------ #OF PARKING SPACES REQUIRED l._\S. la"-\ #OF PARKING SPACES PROVIDED l\lo MUL Tl-FAMILY RESIDENTIAL PARKLAND DEDICATION Total Acreage ____ _ # of Multi-Family Dwelling Units Floodplain Acreage __ _ ---x $452 = $ -------- Housing Units ____ _ _ __ # of acres in floodplain # of 1 Bedroom Units # of acres in detention ------ # of 2 Bedroom Units ---__ # of acres in greenways #of 3 Bedroom Units ---__ date dedication approved by Parks Board #of 4 Bedroom Units COMMERCIAL --- FOR 2 BEDROOM UNITS ONLY Total Acreage • ~~ \ ___ #Bedrooms= 132 sq . ft . Building Square Feet '6 a~ \ ___ # Bedrooms < 132 sq . ft. Floodplain Acreage _____ _ NOTE: Parkland Dedication fee is due prior to the issuance of a Building Permit. The applicant has prepared this application and certifies that the facts stated herein and exhibits attached hereto are true and correct. Signature of Owner, Agent or Applicant Date 6/13/03 2 of 6 .. SUPPLEMENTAL DEVELOPMENT PERMIT INFORMATION Application is hereby made for the following development specific site/waterway alterations: ACKNOWLEDGMENTS: I, ___ \_,_&1=-:=.....__(h~. ~(-~~~~3~-----' design engineer/owner, hereby acknowledge or affirm that: The information and conclusions contained in the above plans and supporting documents comply w ith the current requ irements of the City of College Station , Texas City Code , Chapter 13 and its associated Drainage Policy and Design Standards . As a condition of approval of this permit application, I agree to construct the improvements proposed in this ap 'cation accordi to these documents and the requirements of C ter of the llege Station City Code . Contractor CERTIFICATIONS: (for proposed alterations within designated flood hazard areas .) A.I , certify that any nonresidential structure on or proposed to be on this site as part of this application is designated to prevent damage to the structure or its contents as a result of flooding from the 100 year storm . Engineer Date B. I, certify that the finished floor elevation of the lowest floor , including any basement, of any residential structure , proposed as part of th is application is at or above the base flood elevation established in the latest Federal Insurance Administration Flood Hazard Study and maps, as amended . Engineer Date C . I, , certify that the alterations or development covered by this permit shall not diminish the flood-carrying capacity of the waterway adjoining or crossing this permitted site and that such alterations or development are consistent with requirements of the City of College Station City Code, Chapter 13 concerning encroachments of floodways and of floodway fringes . Eng ineer Date D. I, , do certify that the proposed alterations do not raise the level of the 100 year flood above elevation established in the latest Federal Insurance Administration Flood Hazard Study. Engineer Date Conditions or comments as part of approval : -------------------------- In accordance with Chapter 13 of the Code of Ordinances of the City of College Station, measures shall be taken to insure that debris from construction, erosion, and sedimentation shall not be deposited in city streets, or existing drainage facilities . All development shall be in accordance with the plans and specifications submitted to and approved by the City Engineer for the above named project. All of the applicable codes and ordinances of the City of College Station shall apply. 6/13103 3 of 6