HomeMy WebLinkAboutEngineers Cost Estimate EMERALD RIDGE
EMERGENCY ACCESS
COST ESTIMATE
Item I Qty I Unit I Description I Unit Cost I Total
Base Bid General Construction Items
1 1 LS Mobilization and project overhead (not to exceed 5% $1,500.00 $1,500.00
of work items)
2 275 LF Silt fence installation, maintenance, and removal $2.00 $550.00
General Construction Items Subtotal $2,050.00
3 2934 SY Base prime coat and one course surface treatment $ 6.00 $17,604.00
4 2934 SY 6" crushed limestone base $ 8.00 $23,472.00
5 44 LF 24" corrugated steel pipe $ 30.00 $1,320.00
6 1 AC Clearing and grubbing $ 2,000.00 $2,000.00
Subtotal General Construction Items $44,396.00
Total $46,446.00