HomeMy WebLinkAboutCorrespondenceMEMORANDUM
To: City of College Station
From: Karl Nelson, TxDOT
Date: October 15, 2004
Subject: SITE DEVELOPMENT COMMENTS - -- October 11, 2004
NEW DEVELOPMENT IN COLLEGE STATION - WEEK OF 10 -11 - 04
1. Texas World Speedway (SH 6) (Preliminary Plan): Access driveways to
the SH 6 East Frontage Road for Tracts 7 — 10
must meet TxDOT's "Regulations for Access
Driveways to State Highways ". Access
regulations are primarily based on posted
speed limits and distances between proposed
& adjacent access points. For posted speed
limits of 50 MPH or greater a spacing of 425'
between driveways is required, which may
require shared /joint access. In addition, access
in the vicinity of an entrance ramp will be a
design consideration.
2. Duck Haven (Replat) : No Comment.
3. Agency Records Control (Replat): No Comment.
4. Kenny Cotten's BBQ (Site Plan) (FM 2818): No Comment.
See 8/20/04 Comments.
5. Pine Terrace (Preliminary Plat): No Comment.
6. Pine Terrace (Final Plat): No Comment.
7. Southwest Crossing Qa) Bee Creek (Site Plan): Access driveway on
FM 2154 (Wellborn Road) shall be shared, as
indicated, with the Schick Addition. Unless
existing, proposed driveway to the north (160'),
does not meet TxDOT's "Regulations for Access
Driveways to State Highways ". Access regulations
are primarily based on posted speed limits and
distances between proposed & adjacent access
points. For posted speed limits of 45 MPH a
spacing of 360' between driveways is required.
>>> "Mandl Alford" < MalfordO- cstx.gov
The following attachment is the list of new development projects
submitted to Development Services this week.
Mandl Alford
Staff Assistant
City of College Station
Development Services
1101 Texas Avenue
College Station, Tx 77840
(979) 764 -3570
Jen nifer Reeves - SD Page 1
MEMORANDUM
To: City of College Station
From: Karl Nelson, TxDOT
Date: October 15, 2004
Subject: SITE DEVELOPMENT COMMENTS ---October 11, 2004
NEW DEVELOPMENT IN COLLEGE STATION - WEEK OF 10 -11 - 04
1. Texas World Speedway (SH 6) (Preliminary Plan):
the SH 6 East Frontage Road for Tracts 7 —10
meet TxDOT's "Regulations for Access
Highways ". Access
primarily based on posted
distances between proposed
points. For posted speed
greater a spacing of 425'
is required, which may
access. In addition, access
vicinity of an entrance ramp will be a
2. Duck Haven (Replat) :
3. Agency Records Control (Replat):
4. Kenny Cotten's BBQ (Site Plan) (FM 2818):
Access driveways to
must
Driveways to State
regulations are
speed limits and
& adjacent access
limits of 50 MPH or
between driveways
require shared / joint
in the
design consideration.
No Comment.
No Comment.
No Comment.
See 8/20/04 Comments.
5. Pine Terrace (Preliminary Plat): No Comment.
6. Pine Terrace (Final Plat): No Comment.
7. Southwest Crossina 0- Bee Creek (Site Plan): Access driveway on
FM 2154 (Wellborn Road) shall be shared, as
indicated, with the Schick Addition. Unless
existing, proposed driveway to the north (160'), does
not meet TxDOT's "Regulations for Access
Driveways to State Highways ". Access regulations
are primarily based on posted speed limits and
distances between proposed & adjacent access
points. For posted speed limits of 45 MPH a
spacing of 360' between driveways is required.
>>> " Mandi Alford" < Malford cstx.gov
The following attachment is the list of new development projects
submitted to Development Services this week.
Mandi Alford
Staff Assistant
City of College Station
Development Services
1101 Texas Avenue
College Station, Tx 77840
(979) 764 -3570
Jennifer Re - Fwd: Texas World Speedway Revised Preliminary Plat Page . 1
From:
Mandi Alford
To:
Planners / Engineers
Date:
10/15/2004 1:23:07 PM
Subject:
Fwd: Texas World Speedway Revised Preliminary Plat
FYI
Mandi Alford
Staff Assistant
Planning and Development Services
City of College Station
www.cstx.gov
malford @cstx.gov
"Life is a book and you are its author. You determine its plot and pace and you - only you - turn the pages."
- Beth Mende Conny
>>> Gary Arnold <garnold @co.brazos.tx.us> 10/15/2004 2:20:24 PM >>>
Scale - Maximum 1"= 200'; Preferred 1"= 100' Statement On
Proposed Easements On The Property, These easements need to be shown on
the plans
Jenn ifer Reeves F wd: New Development -Week of 10 -11 -04 Page 1
From:
Mandi Alford
To:
Planners / Engineers
Date:
10/13/2004 3:50:15 PM
Subject:
Fwd: New Development -Week of 10 -11 -04
FYI
>>> Wally Urrutia 10/13/2004 3:37:37 PM >>>
Texas World Speedway: (04 -236) Sanitation is ok with this project.
Duck Haven: (04 -238) Sanitation is ok with this project.
Agency Records Control: (04 -240) Sanitation is ok with this project.
Kenny Cotten's BBQ: (04 -242) Sanitation is ok with this project.
Pine Terrace: (04 -243) Sanitation is ok with this project.
Pine Terrace: (04 -244) Sanitation is ok with this project.
Southwest Crossing @ Bee Creek: (04 -241) Dumpster enclosure by bldg. (A) needs to be rotated 10
degrees clockwise in order to give us a 45 degree angle.
On page 8 Potable Water Plan C3.2 by bldg. (B) is showing a double enclosure on the north east side. If
this is not an error, it is unacceptable.
From: Glenn Brown
To: Alan Gibbs; Harvey Cargill;
Mark Smith; Roxanne Nemcik
Date: 11/2/2004 11:11:28 AM
Subject: Re: Texas World Speedway
Jennifer Reeves; Joey Dunn; John Woody; Kim Foutz;
Alan,
Regarding point #1, 1 am only aware of one contract that we have entered into with Wellborn. In that case,
the customers are actually ours, and the contract provides that Wellborn lines bring the water to our
customers.
Anyway, the point I'm making is that it is not common practice for Wellborn to provide any service in our
CCN.
Thanks for all of your work on this, and hang in there.
Glenn
Glenn D. Brown
Assistant City Manager
City of College Station
PO Box 9960
College Station, TX 77842
979 764 -3510
gbrown @cstx.gov
>>> Alan Gibbs 11/2/2004 10:47:24 AM >>>
All,
Again, this Thursday the subject Preliminary Plat is on P &Z's agenda. Staff is recommending denial (Staff
Report attached) as the applicant requests to create new lots and serve with Wellborn water within our
CCN. This plat includes the lots for ARQ and HTRI and has been forwarded to them as well.
Based on a phone conversation with Dick Conole, he intends to speak at the meeting and will likely raise
several issues such as: the City changing positions on Wellborn Water Supply serving in our CCN and fire
flows, a request to allow Wellborn to serve, and the City's recent upgrading of the line from Venture Dr to
the Racetrack area.
My intent is to inform the P &Z Commissioners primarily in workshop that:
1. In the past the City (Council ?) has entered into agreements with Wellborn to allow them to serve within
our CCN until the time that the City line is extended such that service can be switched over. Due to recent
discussions with Wellborn, the City will not enter into such agreements any longer.
2. The Council also amended the Subdivision Ordinance on August 9, 2004 to require fire flows in the
ETJ with no variance procedure. Similarly, the Novemver 13, 2003 Council Resolution 11 -13- 2003 -9.17
states that annezation should be required as well. The motivation of these actions was to promote
development within the city limits and development conflicts in the ETJ were intended.
3. (1 am requesting more details of the recent line upgrade from John Woody.) There is approximately
8000 feet of 8" water from Venture Drive and about feet of 6 ". For extension of the line, meeting fire
t
flows and the guidelines would at a minimum require at the 6" be replaced with an 8 ".
4. The Council would be the body to direct further discussion of items 1 and 2.
Due to the sensitivity of the issues, I would appreciate any input.
Alan P. Gibbs, P.E.
Sr. Asst. City Engineer - Development
Public Works Department
From: Mark Smith
To: Alan Gibbs; Edwin Savage; John Woody
Date: 11/2/2004 11:23:31 AM
Subject: Re: Fwd: Fire hydrant at the Tx World Speedway
My understanding of this situation is that the because fire flow requirement was not met we required that
the building be sprinkled. This was an option that was available before the fire flow amendment was
implemented.
Mark Smith
Director of Public Works
979 - 764 -3690
>>> Alan Gibbs 11/2/2004 11:16:06 AM >>>
FYI - here is an email from Kim with some info on the 6" line and hydrant.
>>> Kim Foutz 10/28/2004 3:07:01 PM >>>
As I understand it, there has been a question raised of whether a fire hydrant had been previously installed
at the Race Track. Attached please find a letter that I sent in May 1999 to the Research Valley
Partnership requesting funding for water improvements for Kristen Distributing. As you will see, a fire
hydrant was part of the water project. The City of CS would have installed the hydrant either by contract
or its own crews at that time. Please let me know if you need additional information and I will spend more
time on it if needed.
CC: Bob Mosley; Glenn Brown; Joey Dunn; Kim Foutz; Roxanne Nemcik