Falcon Point Water Line — Engineer's Opinion of Probable Construction Cost
5/4/2012
MBESI NO. 1000 -0208
Item Estimated Estimated Total
No. Description Estimated Quantity Unit Cost Cost
1.00 WATER LINE IMPROVEMENTS
1.01 8" AWWA C900, DR 14 (includes installation, testing, and clean- 756 LF $30.00 $22,680.00
up)
1.02 8 "x45 deg Bend 6 EA $250.00 $1,500.00
1.03 2" Blow -off 1 EA $1,000.00 $1,000.00
1.04 Connect to Existing Line 1 EA $500.00 $500.00
1.05 Remove Existing Blow -Off 1 EA $250.00 $250.00
Subtotal Item 1.00: $25,930.00
TOTAL CONSTRUCTION COST: $25,930.00
The above construction estimate is based on the engineer's opinion of probable construction costs. This estimate constitutes our best
judgment at this time. Please note that the engineer does not have any control over contractor or supplier workloads and the degree
to which inflation may affect project co between now and the bid date. During design and construction, additional features may
become apparent as the ork progress h will result in an increase or decrease in cost.