HomeMy WebLinkAboutStaff CommentsCITY OF COLLEGE STATION
DEVELOPMENT SERVICES
1101 Texas Avenue South, PO Box 9960
College Station, Texas 77842
Phone 979.764.3570 / Fax 979.764.3496
MEMORANDUM
June 30, 2004 /
TO: Alton E. Ofczarzak, via fax: 979.690.2504 V
FROM: Jennifer Prochazka, Staff Planner
SUBJECT: HORSE HAVEN ESTATES (MP)
Staff reviewed the above - mentioned master plan as requested. The following page is a
list of staff review comments detailing items that need to be addressed. If all comments
have been addressed and the following information submitted by Tuesday, July 6, 2004
at 10:00 a.m., your project will be placed on the next available Planning and Zoning
Commission meeting scheduled for July 15, 2004 at 7:00 p.m. in the City Hall Council
Chambers, 1101 Texas Avenue.
Ten (10) copies of the revised master plan; and,
One (1) Mylar original of the revised master plan.
One (1) copy of the digital file of the master plan on diskette or e-mail to
nmanhart@ cstx.gov
Upon receipt of the required documents for the Planning & Zoning meeting, your project
will be considered formally filed with the City of College Station. Please note that if all
comments have not been addressed, your project will be pulled from the scheduled
Planning & Zoning Commission agenda. Your project may be placed on a future agenda
once all the revisions have been made and the appropriate fees paid. If you have any
questions or need additional information, please call Spencer Thompson or myself at
979.764.3570.
Attachments: Staff Review Comments no. 1
cc: Virginia Herman, via fax: 979.680.0466 '
Michael Hester, P.E., via fax: 979.693.1075 ✓
Case file #04- 00500153
Home of Texas A &M University
STAFF REVIEW COMMENTS NO. 1
Project: HORSE HAVEN ESTATES (MDP) - 04- 00500153
ENGINEERING
1. Please title this document "Master Plan." We no longer have a "Master
Development Plan" in the UDO.
2. The only information that is required by the Subdivision Regulations to be on the
Master Plan is the following:
(a) proposed land uses, including, but not limited to street rights -of -way;
(b) proposed zoning changes;
(c) proposed drainage development;
(d) proposed public improvements, including, but not limited to parks, schools,
and other public facilities.
Please remove all other information, including easements, existing buildings, utilities,
etc. Topo lines may be helpful if they do not add to the confusion.
3. Please label the topo lines in shown.
4. The current submittal does not meet the Thoroughfare Plan. Appomattox is shown
as a minor collector on the plan. The Plan shows Appomattox connecting to Horse
Haven. The Master Plan must comply with the approved Thoroughfare Plan at this
time.
5. Please change "Future Residential Zoning" to "Future Residential Development ".
6. Please change the proposed zoning areas on the MP to reflect the changes made
with the zoning request.
7. Due to the fact that the area of development shown is different from the previous
Preliminary Plat, this item will need to go to the Parks Board for final approval. The
Board will need to know the number of lots and final layout.
8. Mr. Hester, it is my opinion that this plan shows much more floodplain than what is
shown on the FIRM. It is my opinion that what you show on this document should
be what is shown on the FIRM. If you feel the actual area of the 100 -year flooding
event is greater than that shown on the FIRM, please label as such, as Greenway or
other.
Reviewed by: Spencer Thompson & Jennifer Prochazka Date: 6 -28 -04
ELECTRICAL
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your
next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out
to the City, will constitute a completely new review.
2of3
1. Developer will be responsible for the installation of conduit per city design and
specs.
2. Developer will be responsible for the installation of street lighting per city design and
specs. (Streetlight poles to be DARK BRONZE in color.)
3. Developer will be responsible for providing all necessary easements for electric
infrastructure required to provide service to development.
4. If and when Appomattox Drive is extended through Switch Station Rd. the developer
will be responsible for the relocation of Switch Station Rd Gate.
Reviewed by: Tony Michalsky Date: 6 -23 -04
NOTE: Any changes made to the plans, that have not been requested by the City of College Station,
must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on
these plans that have not been pointed out to the City, will constitute a completely new review.
HORSE HAVEN (ROW -EASE) (04- 00500282)
Engineering Review
Comments No. 1
1. Provide signatures for TXU, Verizon and Cox Communication. These
abandonments of public ROW -OF- WAY /Easement can not be fully
reviewed by the city until all signatures are acquired.
2. Please provide letter or legal size exhibit for meets and bounds description
for E -1, R -1, D -1, P -1, and S -1 (exhibit for E -2 was already submitted).
3. Provide note for INSET "A" and INSET "B" (ie. ROW or Easement
Abandonment).
4. Please clarify or depict the access to Kolbe Property between abandonment
and filed plat of phase three, as well as during construction.
Reviewed by: JOSH NORTON Date: January 7, 2005
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be
explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans
that have not been pointed out to the City of College Station will constitute a completely new review.
Page 2 of 2