HomeMy WebLinkAboutStaff Report STAFF REPORT
Project Manager: Molly Hitchcock Date: June 17, 2004
Email: mhitchcock @cstx.gov
Item: Consideration, discussion, and possible action on a Preliminary Plat for the
Willams Gate Subdivision consisting of 82 single - family residential lots on 15.81
acres generally located on the north side of Rock Prairie Road West at the City
Limits line.
Applicant: Greg Taggart of MDG as agent for Robbie Robinson, Ltd.
Staff Recommendations: Staff recommends approval of the Preliminary Plat with
the condition that the plat be revised to address the attached Staff Review
Comments #2.
Comprehensive Plan Considerations: The Land Use Plan shows the area as
Single Family Medium Density (3-6 dwelling units /acre). The density of the
proposed development is 5.2 dwelling units /acre. The tract has access from Rock
Prairie Road West, which is a Minor Arterial on the Thoroughfare Plan.
Staff Comments #2 address utility issues. The design and construction of the water
system, even though it is served by another water utility company, must meet City
standards. The plat shows public sewer service to be provided by way of a lift
station. The area has been approved by the City Council to be a Sewer Impact Fee
Area. The Capitol Improvement Project (CIP) will provide a gravity sewer system to
the area and should be completed in the next 2 years.
Item Background: This property was annexed in 2002 and rezoned to R -1 Single
Family Residential by City Council on June 10, 2004.
Related Advisory Board Recommendations: The Parks Board agreed to a fee in
lieu of land dedication at their June 11, 2004 meeting.
Supporting Materials:
1. Location Map
2. Aerial
3. Application
4. Infrastructure and Facilities
5. Copy of Preliminary Plat
6. Staff Review Comments No. 2
INFRASTRUCTURE AND FACILITIES
Many of these comments are not required at the Preliminary Plat stage but will need
to be addressed at Final Plat.
Water required for plat: Water to be provided for domestic service and fire flow
capacity to the residential area. Provide an extension of the system to the north for
future use. Wellborn SUD will provide water to the development. The water supply
must be designed and constructed to City standards. The Applicant provided some
information in order not to design to City standards. The information provided was
inadequate to allow deviation from the minimum criteria outlined in the BCS Unified
Design Manual. Therefore the plat must reflect compliance with City standards.
Water Service: Required to provide domestic service to each platted lot.
Sewer required for plat: The project must prove a public sewer system to the area.
At the time of preparing this report, the final decision to construct the lift station as
private or public had not been officially made. The lift station is proposed to
discharge into the existing system along Rock Prairie Road and Wellborn. This will
require crossing the railroad tracks and Wellborn Road. If the system is to be owned
and maintain by the City, the design must reviewed and approved by City staff.
Sewer design information was provided. The information provided was inadequate
to show that the existing public sewer system has capacity for this development. A
revised sewer report will be required with sewer construction plans.
Sewer Service: Required to provide domestic service to each platted lot.
Street(s) required for plat: The street layout shown is required to provide access to
each platted lot. The City is also requiring the extension of the street system to the
adjacent tract to the north.
Streets /Access: The street access to Rock Prairie Road has been coordinated with
platted access points across the road on the Rock Prairie West Business Park.
Off -site Easements required for plat: If it is decided that the lift station is to be
privately owned and maintained, the owner is required to obtain easements from the
lift station to the public sewer system. Easements must be provided with the design
documents required for a Final Plat.
Drainage: Drainage flow is generally to the north. A detention pond is planned for
the HOA lot. There appears to be a small drainage swale on the adjacent tract that
will be the point of discharge. The development must comply with the City's drainage
policy.
Flood Plain: No FEMA floodplain onsite.
Oversize request: None requested.
Impact Fees: The sewer impact fee approved for the Steeplechase Impact Fee
Sewer Line is $300.00 per Living Unit Equivalent.
Parkland Dedication Fees:
Fee in Lieu of Land: $198 per dwelling unit.