Loading...
HomeMy WebLinkAboutEngineers Cost Estimate • • Indian Lakes Subdivision, Phase XIII Engineer's Estimate MBESI NO. 1062 -0030 March 20, 2012 Item Estimated No. Description Unit Quantity Total Unit Price Paving Construction 1 Excavation ( +1- 2,779 CY Excavation) L.S. 1 # # # # # # ## $17,000.00 2 1.5" HMAC (including prime coat) S.Y. 4,618 $9.50 $43,871.00 3 6" Lime Stabilized Subgrade (6 %) S.Y. 6,411 $4.30 $27,567.30 4 6" Crushed Limestone Base S.Y. 6,049 $10.00 $60,490.00 Paving Subtotal $148,928.30 Water Line Construction 5 6" PVC CL 100-C900 Water Pipe, non - structural backfill L.F. 1,622 $19.00 $30,818.00 6 6" Gate Valve EACH 1 $850.00 $850.00 7 2" Blow -off Assembly EACH 1 $1,000.00 $1,000.00 Water Line Subtotal $32,668.00 Erosion Control Construction 8 4' Wide Erosion Control Blanket (as manufactured by North American Green) L.F. 900 $0.90 $810.00 9 Straw Bale Barrier EACH 17 $75.00 $1,275.00 10 Cellulose Fibermulch Seeding S.Y. 8,675 $0.50 $4,337.50 11 Construction Exit for Silt Control EACH 1 $1,500.00 $1,500.00 12 Silt Fence L.F. 175 $3.00 $525.00 Erosion Control Construction $8,447.50 TOTAL CONSTRUCTION COST $190,044 The above construction estimate is based on the engineer's preliminary opinion of probable construction costs. This estimate constitutes our best judgment at this time. Please note that the engineer does not have any control over contractor or supplier workloads and the degree to which inflation may affect project costs between now and the bid date. During construction, additional features may become apparent as the work progresses, which will result in an increase in cost. b� ' l � � � pl 1 } ., tt e �Jn r J ' Jeffery, , ` rtscin,'P.E. VI a te 1 v N =MARY L. ROBERT7C ii � 1 : 94745 k - � ' EN S