HomeMy WebLinkAboutCorrespondenceJennifer Reeves - C.O. @ 1001 Woodcreek, Our Saviors Lutheran Church Page 1J
From: Jennifer Reeves
To: Chris Haver; Gina Southerland
Date: 10/7/2005 10:04:05 AM
Subject: C.O. @ 1001 Woodcreek, Our Saviors Lutheran Church
I am ok for a 30 day temporary C.O. until we get established ground cover. Steve you may want to take a
look at the roll curb. I know you are ok with the curb for a temp. C.O., however if you have not seen how
they have fixed it, you might want to drop by.
Thanks,
Reeves
Jennifer Reeves
Staff Planner
City of College Station
jreeves@cstx.gov
(979) 764-3570
(979) 764-3496 FAX
CC: Carol Cotter; Steve Smith
Jennifer Reeves Re: Calling for C.O. @ 1001 Woodcreek Our Savior's Luthern Church Page 1 1
From: Steve Smith
To: Gina Southerland; Jennifer Reeves
Date: 10/4/2005 1:49:46 PM
Subject: Re: Calling for C.O. @ 1001 Woodcreek Our Savior's Luthern Church
I have talked to the GC and he still needs the roll-over curb, hood test and fire alarm test.
Jennifer Reeves 10/04/05 1:18 PM
Carol and I did a site inspection this morning and these are the following issues:
1. Will need established ground cover
2. Remove construction debris
3. Remove Development Signs
4. Many dead shrubs in the required buffer adjacent to the single family located at the rear of the property.
These will need to be replaced.
5. There is a note on the stamped approved landscape plan that states "30' wide buffer yard provided in
lieu of required 15' buffer with wall-dense existing native foliage to remain undisturbed-included 14 canopy
trees and very opaque undergrowth. All shall be protected during construction". There is a portable
building approximately 20x30 in area that has been placed in a cleared area in the middle of this above
mentioned required natural buffer. This portable building and location was not approved with the site plan.
Please explain.
6. A roll curb was shown on the stamped approved site plan for emergency vehicle access in the parking
lot adjacent to the front of the building. This was not constructed according to plans. This is a fire
department requirement. How will this be resolved?
Thanks,
Jennifer
Jennifer Reeves
Staff Planner
City of College Station
ireevesa-cstx.aov
(979) 764-3570
(979) 764-3496 FAX
Gina Southerland 09/29/05 10:31 AM
Are there any issues?
Bp# 04-2155
Gina Southerland
Customer Service Rep.
City Of College Station
1101 Texas Ave.
979-764-3570
glsoutherland(o)-cstx.gov
CC: Carol Cotter; Chris Haver; Jennifer Prochazka; Lance Simms
Jennifer Reeves - Re: Calling for C.O. @ 1001 Woodcreek Our Savior's Luthern Church Page 1
From: Jennifer Reeves
To: Gina Southerland
Date: 10/4/2005 1:18:08 PM
Subject: Re: Calling for C.O. @ 1001 Woodcreek Our Savior's Luthern Church
Carol and I did a site inspection this morning and these are the following issues:
1. Will need established ground cover
2. Remove construction debris
3. Remove Development Signs
4. Many dead shrubs in the required buffer adjacent to the single family located at the rear of the property.
These will need to be replaced.
5. There is a note on the stamped approved landscape plan that states "30' wide buffer yard provided in
lieu of required 15' buffer with wall-dense existing native foliage to remain undisturbed-included 14 canopy
trees and very opaque undergrowth. All shall be protected during construction". There is a portable
building approximately 20x30 in area that has been placed in a cleared area in the middle of this above
mentioned required natural buffer. This portable building and location was not approved with the site plan.
Please explain.
6. A roll curb was shown on the stamped approved site plan for emergency vehicle access in the parking
lot adjacent to the front of the building. This was not constructed according to plans. This is a fire
department requirement. How will this be resolved?
Thanks,
Jennifer
Jennifer Reeves
Staff Planner
City of College Station
jreeves@cstx.gov
(979) 764-3570
(979) 764-3496 FAX
Gina Southerland 09/29/05 10:31 AM
Are there any issues?
Bp# 04-2155
Gina Southerland
Customer Service Rep.
City Of College Station
1101 Texas Ave.
979-764-3570
glsoutherland(o)-cstx.gov
CC:
Com Flvk
nq - ~ 3q _50?
y 4.5
4,
6Z v Sk-Y.Te)
TO- -j~kV
Haver; Jennifer Prochazka; Lance Simms; Steve Smith
MCCLURE & BROWNE ENGINEERING/ SURVEYING, INC.
1008 Woodcreek Drive, Suite 103 • College Station, Texas 77840
(979) 693-3838 • Fax (979) 693-2554 • Email: mikem(c'tca.net
TRANSMITTAL LETTER
TO: Carol Cotter Date: 10/19/04 Proj.#
Development Services Dept. Project: Our Savior's Lutheran Church
CITY OF COLLEGE STATIOM
We are sending you the following: ® Attached ❑ Under Separate Cover Via:
❑ Invoice ❑ Prints ❑ Plans ❑ Contractor ❑ Bid Books ❑ Specifications ❑ Change Order
Invoice
❑ Contracts ❑ Other
Copies Date Description
1 Copy of signed Easement Agreement between Our Savior's
Lutheran Church & East Bypass Development Group
These are transmitted as follows:
❑ For Approval ❑ Approved as Submitted Sets to approved and returned to me
® For your use ❑ Approved except as noted Copies for your files
❑ As Requested ❑ Resubmitted after Revisions Corrected Prints
❑ For Review Comment ❑ Other:
REMARKS:
COPY TO: SIGNED: ~~W44( 1?1~ y
NT-T
chael R. Clure, P. R.P.L.S.
President
~l
n4-ilk
LETTER OF TRANSMITTAL
TO: Jennifer Prochazka WITH: C.O CS Devel. Serv.
FROM: Eva Read-Warden DATE: September 27, 2004
PROJECT: Our Saviour's Lutheran Church PROJECT NO: 0313
The following items are hereby transmitted for your usage, review and/or action
as noted.
Case File No. 04-00500118
Irv IL.;" kcjPC3 E?,Aqro]D 2 copies Sheet AU & A1.2: Site Plans
511 Unimsily Drive East Suite 201
College Sl.tine, Texas 77840 2 copies Sheet L1.1 & L1.2: Landscape Plans
Phone 979/260-2635
Tax 979/846-8224 6 full sets: Construction Documents
www.arkitex.com
Jennifer-
Do you need the spec book as well? If so, 6 copies? Let me know and we
will send those over.
Thanks-
260-2635
eva@arkitex.com
Co`t o
Irpu hJ Gpu.r-
. ~~S Nerd a- ,r.J
July 12, 2004
C01"i ~20 Ms. Jennifer Prochazka
City of College Station Development Services
1101 Texas Avenue South
College Station, Texas 77842
III Re: Our Saviour's Lutheran Church
Site Review
V
-
arkitex
Dear Jennifer:
"'r;` D r D
Enclosed please find our re-submittal for site review. We are resubmitting Sheet
ANCt-~1ZPORATED
A1.1 and L1.1, and also providing a new sheet L1.2. On this new sheet
further
511 Daaersity Drive Cast Suite 201
College Station. Texas 77840
n
,
information is provided about the landscaping to be provided around the entry
.1 979I260.267i
Fax 979!846-8224
plaza area at the main entrance to the building.
w w w. a r k i t e xx . c o m
We have made every effort to address your past comments. We now believe the
required notes have been added to the plans and that the landscape legend is
coordinated with the landscape point analysis. Please feel free to contact me
should you find anything unclear. Note that the points have been revised to
account for the new landscaping provided on Sheet L1.2.
McClure and Brown Engineering's submittal for the engineering portion of the
work is being submitted under separate cover. Concerning your curb comment,
we have asked the engineers to address this in their submittal.
Again, should you have any questions or require additional information, please
feel free to contact me.
Sincerely,
Eva M. Read-Warden, AIA
Associate Principal
July 9, 2004
MCCLLIRE & BROWNE ENGINEERING /SURVEYI , INC.
1008 Woodcreek Drive, Suite 103 . College Station, Texas 77845
(979) 693-3838 • Fax (979) 693-2554 • Email: mcclure@tca.net
Carol Cotter, E.I.T.
Graduate Civil Engineer
Development Services, City of College Station
College Station, TX 77840
Re.: Our Saviour's Lutheran Church - Site Plan
Revisions per City comments Summary Letter
Dear Ms. Cotter:
Attached please find two (2) sets of Civil Site Construction Plans revised per City review
comments. Below is the summary of the revisions made per review comments No. 2 dated
June 4, 2004. Please be aware that the planning comments will be addressed by the
architect with their submittal under separate cover.
ENGINEERING COMMENTS:
COMMENT #1: Show easements that are being required with platting.
ACTION: Revised per your request. (See Preliminary Plat re-submitted on
71212004)
COMMENT #2: Site Plan cannot be approved until property is platted.
ACTION: This property is in the platting process.
COMMENT #3: Architectural Site Plan needs to look like engineering plans.
ACTION: Architect to adjust site plan per engineering drawings.
COMMENT #4: Requested that the water report show the required fire flow based on
the size of the building and construction.
RESPONSE: The fire flow shown on the site plan is 1750 gpm. This figure
was developed by the MEP designer based on the building size
and construction as required by the International Fire Code. The
water report was developed using 2500 gpm as required in the
CS Design Guidelines for Commercial and Multifamily
developments. The larger figure was chosen for use because it
is the more conservative of the two figures. Even when using
the higher flowrate, the proposed system easily meets the City
requirements. The minimum pressure under fire flows (83 psi)
Our Savior's Lutheran Church Site Plan
Review Comments
7/9/2004
Page 2
is more than 4 times the required minimum (20 psi), and the
maximum velocity (8.9 fps) is substantially less than the
maximum allowable (12 fps).
COMMENT #5: Requested that the drainage from the detention pond have an off-site
drainage easement.
ACTION: The two property owners are currently working on an agreement
for the drainage issue.
COMMENT #6: Is all the flow in drainage basin EX2 actually going to study point?
ACTION: All of the flow from EX2 is not going to the detention pond. There is
a small portion of land just west of the detention pond, between the
drainage channel and property line that does not flow to the detention
pond. The flow through that area has been greatly reduced because
the majority of the runoff from the site is being captured and conveyed
to the detention pond via the drainage channel. The area that will
continue to sheet flow off of the property has been reduced in size
and no improvements will be made to this portion of property.
COMMENT #7: Requested that water line W-1 be C-909.
ACTION: Revised per your request.
COMMENT #8: Requested a P.U.E. for water line W-2.
ACTION. Revised per your request.
COMMENT #9: Requested Blow-Off Riser detail W3-03.
ACTION: The detail has been removed and reference is made to B/CS
Unified Design Guidelines, Specifications and Details.
COMMENT #10: Requested a check of the deflection of the water line bends and
fittings.
ACTION: Comment noted and no revision was required.
COMMENT #11: Requested a note stating that all water and sewer construction will be
in accordance with B/CS Unified Design Guidelines, Specifications
and Details.
ACTION: See note #2 in the general construction notes on sheet 1 of the
construction drawings.
COMMENT #12: Requested a verification that the sidewalk from the covered drop off
to the parking lot is not covered.
ACTION: The sidewalk from the covered drop off to the parking lot is not
Our Savior's Lutheran Church Site Plan Page 3
Review Comments
7/9/2004
covered.
COMMENT #13: Requested that sewer line in ROW be SDR 21 (ASTM D-2241).
ACTION: Revised per your request.
COMMENT #14: Will a temporary construction easement be needed from the property
owner at 9301 Amberwood Court?
ACTION: See note on sheet 3 of construction drawings stating that all
work shall be done within the R.O.W. of Woodcreek Drive or 10'
P.U.E.
COMMENT #15: Is Type 3 Curb (Sheet 2) the Beveled curb (Sheet 5)?
ACTION: The Type 3 Curb is the Beveled Curb. See detail Sheet 5.
COMMENT #16: What is Type 4 Curb?
ACTION: See detail Sheet 5 for Type 4 Curb.
Should you have any questions or need additional information, please do not hesitate to
call.
Very truly yours,
ichael R McClure, P.E., R. P. L. S.
President
MRM/mlm
attachment
xc: Ms. Eva Read-Warden
The Architex Studio
LETTER OF TRANSMITTAL
TO: Bridgette George WITH: City of College Station
FROM: Eva Read-Warden DATE: 10 March 2004
PROJECT: Our Saviour's Lutheran Church PROJECT NO: 0313
The following items are hereby transmitted for your usage, review and/or action
as noted.
Site Review Pre-Application Meeting Submittal:
2 prints: Our Saviour's Lutheran Church Site Plan
2 prints: Utility Layout and Demands
511 University Drive East Suite 201
College Station. Texas 77840
Phone 9791260-2635
Fax 9791846.8224
www.arkitex.com
3
rM
May 21, 2004
1008 Woodcreek Drive, Suite 103 • College Station, Texas 77845
(979) 693-3838 • Fax (979) 693-2554 • Email: mcclure@tca.net
Carol Cotter, E.I.T.
Graduate Civil Engineer
Development Services, City of College Station
College Station, TX 77840
Re.: Our Saviour's Lutheran Church - Site Plan
Revisions per City comments Summary Letter
Dear Mrs. Cotter:
Below is the summary of the revisions made per your comments.
COMMENT #1: Requested engineered plan and profile of public water line.
ACTION: Provided plan and profile of public water line.
COMMENT #2: Requested a water design report.
ACTION: Provided water design report.
COMMENT #3: Requested that the water line needs to be in a PUE.
ACTION: Revised per your request.
COMMENT #4: Requested the location of the domestic and irrigation meters be
shown within a PUE or ROW.
ACTION: Revised per your request.
COMMENT #5: Requested the size and slope of the private sanitary sewer service be
shown.
ACTION: Revised per your request.
COMMENT #6: Called attention to the drop structure requirements for the connection
to the manhole.
ACTION: The proposed manhole connection has been removed and replace
with a standard sewer service connection.
McCLURE & BROWNE I ,
ENGINEERING/SURVEYING, INC.
COMMENT #7: Requested the Development Permit Application.
ACTION: Application is being submitted. Payment was received with first
submittal.
COMMENT #8:
ACTION:
COMMENT #9:
ACTION:
COMMENT #10:
ACTION:
COMMENT #11:
ACTION:
Requested a Grading Plan.
Provided a Grading Plan.
Requested an Erosion Control Plan.
Provided an Erosion Control Plan.
Requested a Drainage Report.
Provided a Drainage Report.
Requested paving and curbing details.
Provided details.
Sincerely,
MCCLU & BRO NGINEERING/SURVEYING, INC.
Pat Penn, E.I.T.
McCLURE & BROWNE ENGINEERING/ SURVEYING, INC. 3 ;1
1008 Woodcreek Drive, Suite 103 • College Station, Texas 77840
(979) 693-3838 • Fax (979) 693-2554 • Email: mikem@tca.net
TRANSMITTAL LETTER
TO: Ms. Jennifer Prochazka, Staff Planner Date: 5/21/2004 Proj.#
City of College Station Project: Our Savior's Lutheran Church
Civil Site Design
We are sending you the following: ® Attached ❑ Under Separate Cover Via:
❑ Invoice ❑ Prints ❑ Plans ❑ Contractor ❑ Bid Books ❑ Specifications ❑ Change Order
Invoice
❑ Contracts ❑ Other
Co ies
Date
Description
2
Sets of Civil Site Design Construction Plans
2
Copies of Drainage Report
1
Development Permit (Fee was paid by Architect)
2
Copies of Water Report
1
Copy of Engineer's Estimate for Civil Site Improvements
1
Letter of Response to Engineering Comments from 5/10/04 Memo
These are transmitted as follows:
® For Approval ❑ Approved as Submitted Sets to approved and returned to me
® For your use ❑ Approved except as noted Copies for your files
❑ As Requested ❑ Resubmitted after Revisions Corrected Prints
❑ For Review Comment ❑ Other
REMARKS: Regarding the Memo Planning comment about platting: a preliminary plat for the site was submitted
5/90/2004 by our firm- If you have anv auestions. please do not hesitate to call. Thank You!
COPY TO: SIGNED: A " G
Michael R. McClure, P.E., R.P.L.S.