HomeMy WebLinkAboutInfrastructure and Facilities INFRASTRUCTURE AND FACILITIES
Water: Domestic water and fire flow capacity is not available on the west
side of SH 6 in this area at this time. Extension of the City water system
would be by way of Greens Prairie Road at Arrington or by boring under
TxDOT ROW from the College Station Business Park.
Sewer: This area is in the City's 97 -02B Sewer Impact Fee Area.
Access to the public sewer system is across SH 6 to the east or south to
Nantucket.
Streets: Access is to Hwy 6 frontage road and to Arrington Road. Hwy
6 is designated as a Freeway on the Thoroughfare Plan, and the
frontage road is anticipated to be one -way in the future at the direction
of TxDOT. Arrington is designated as a Major Collector on the
Thoroughfare Plan. A recent Thoroughfare Plan amendment realigned
Arrington Road moving the intersection with Greens Prairie Road further
to the west. The existing Greens Prairie / Arrington intersection will be
closed in the future. Access will be maintained to the properties that
currently have frontage on Arrington Road and a turn around is planned
at the end of the current right -of -way.
Off -site Easements: Easements to obtain public water and sewer may
be required.
Drainage: Drainage is generally to a tributary of Alum Creek. The creek
crosses SH 6, Lakeway Drive and connects with the branch of Alum
Creek from Nantucket.
Flood Plain: The FEMA floodplain has not been mapped along this
creek on the west side of SH 6. The current FEMA study ends on the
east side of the highway.
Oversize request: None at this time.
Impact Fees: These properties fall within the 97 -02B Sewer Impact Fee
Area. The fee is currently $243.38 per living unit equivalent.
NOTIFICATION:
Legal Notice Publication(s): The Eagle; 4 -20 -04 and 5 -11 -04
Advertised Commission Hearing Dates(s): 5 -5 -04
Advertised Council Hearing Dates: 5 -27 -04
Number of Notices Mailed to Property Owners Within 200': 15
R: IHTLTRIPZLTRIPRODIPZ20041P0009482. DOC