HomeMy WebLinkAboutSTAFF REVIEW COMMENTS C__IiCITY OF COLLEGE STATION
DEVELOPMENT SERVICES
1101 Texas Avenue South, PO Box 9960
COLLEGE STATION College Station, Texas 77842
Phone 979.764.3570 / Fax 979.764.3496
MEMORANDUM
April 24, 2003
TO: Rick Jenkins, Main Street Homes, Via fax 512.478.5678
FROM: Bridgette George, Assistant Development Manager
SUBJECT: WESTFIELD ADDITION PH 2B (DP)
Staff reviewed the above - mentioned engineering documents as requested. The
following page is a list of staff review comments detailing items that need to be
addressed. Please address the comments and submit the following information
for further staff review and approval of the plans:
Two (2) sets of revised construction documents.
If you have any questions or need additional information, please call Spencer
Thompson or myself at 764.3570.
Attachments: Staff Review Comments
Cc: CSC Engineering & Environmental Consultants, Inc., Via fax 778.0820
Case file no.
Home of Texas A&M University
WESTFIELD ADDITION PH 2B (FP) - (03- 00500103)
ENGINEERING REVIEW
COMMENTS No. 1
1. In light of the fact that the water line along Springfield Drive is constructed
and the most logical place for a connection falls under the pavement, the
next best design would be to connect to the end of the line, parallel Graham
and extend the line along Meadow View to meet it.
2. Sheet C7. Silt fence appears to be on private property. Please adjust.
3. Sheet C9; Detail 1; should read POTABLE WATER LINE.
Reviewed by: Spencer Thompson Date: April 23, 2003
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must
be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on
these plans that have not been pointed out to the City of College Station will constitute a
completely new review.
Page 2 of 2
CITY OF COLLEGE STATION
`I DEVELOPMENT SERVICES
1101 Texas Avenue South, PO Box 9960
College Station, Texas 77842
COLLEGE STATION Phone 979.764.3570 / Fax 979.764.3496
MEMORANDUM
April 24, 2003
TO: Rick Jenkins, Main Street Homes, Via fax 512.478.5678
FROM: Bridgette George, Assistant Development Manager
SUBJECT: WESTFIELD ADDITION PH 2B (FP) - Final Plat
Staff reviewed the above - mentioned final plat as requested. The following page is a list
of staff review comments detailing items that need to be addressed. If all comments
have been addressed and the following information submitted by Monday, May 5, 2003,
10:00 a.m., your project will be placed on the next available Planning and Zoning
Commission meeting scheduled for, Thursday, May 15, 2003, 7:00 p.m. in the City Hall
Council Chambers, 1101 Texas Avenue.
Two (2) copies of the revised final plat;
One (1) Mylar original of the revised final plat; and
One (1) copy of the digital file of the final plat on diskette or e-mail to
nmanhart@ci.college- station.tx.us
Upon receipt of the required documents for the Planning & Zoning meeting, your project
will be considered formally filed with the City of College Station. Please note that if all
comments have not been addressed your project will not be scheduled for a Planning &
Zoning Commission meeting. Your project may be placed on a future agenda once all
the revisions have been made and the appropriate fees paid. If you have any questions
or need additional information, please call Spencer Thompson or myself at 764 -3570.
Attachments: Staff review comments
cc: CSC Engineering & Environmental Consultants, Inc.
Riley Engineering Co., Via fax 778.0820
Case file #03- 00500103
Home of Texas ABM University
STAFF REVIEW COMMENTS NO. 1
Project: WESTFIELD ADDITION PH 2B (FP) - 03- 00500103
ENGINEERING
1. Please replace Certificate for City Planner with Certificate for Planning and Zoning
Commission. This is not a Minor Plat.
2. Please remove Note 7.
3. Please correct Location Map. There is no Phase 4 and the other phases are not
shown correctly.
4. Label Block 1.
5. Title Block is incorrect. What kind of plat, Lots 1 thru ?, Block 1, etc....
6. Comments for construction drawings to be returned separately.
Reviewed by: Spencer Thompson Date: April 23, 2003
ELECTRICAL
1. Developer installs conduit per city specs and design.
2. Developer provides 30' of #4 rigid conduit for riser poles. Developer installs
first 10'. City installs remainder.
3. Developer pours transformer pad(s) per city specs and design.
4. Developer installs pull boxes as per city specs and design.(pull boxes
provided by the city.
5. Developer provides digital AutoCAD 14 version of plat and /or site plan.
email to rbolin @ci.college- station.tx.us
6. Developer provides load data for project.
7. Developer provides temporary blanket easement for construction
purposes.
8. Developer provides easements for electric infrastructure as installed for
electric lines (including street lights).
Reviewed by: Ronnie Bolin
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your
next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out
to the City, will constitute a completely new review.
Page 2 of 3