Loading...
HomeMy WebLinkAboutStaff Commentst CITY OF COLLEGE STATION DEVELOPMENT SERVICES 1101 Texas Avenue South, PO Box 9960 College Station, Texas 77842 Phone 979.764.3570 / Fax 979.764.3496 MEMORANDUM February 2, 2004 TO: James H. Woods, Via fax 846.9133 FROM: Bridgette George, Assistant Development Manager SUBJECT: EDELWEISS BUSINESS CENTER (MP) - Final Plat Staff reviewed the above-mentioned final plat as requested. The following page is a list of staff review comments detailing items that need to be addressed. If all comments have been addressed and the following information submitted by Monday, February 9, 10:00 a.m., your project will be placed on the next available Planning and Zoning Commission meeting scheduled for, February 19, 2004, 7:00 p.m. in the City Hall Council Chambers, 1101 Texas Avenue. Two (2) copies of the revised final plat; One (1) Mylar original of the revised final plat; and One (1) copy of the digital file of the final plat on diskette or e-mail to nmanhart@ci.college-station.tx.us Upon receipt of the required documents for the Planning & Zoning meeting, your project will be considered formally filed with the City of College Station. Please note that if all comments have not been addressed your project will not be scheduled for a Planning & Zoning Commission meeting. Your project may be placed on a future agenda once all the revisions have been made and the appropriate fees paid. If you have any questions or need additional information, please call Carol Cotter or myself at 764.3570. Attachments: Staff review comments cc: Michael McClure, McClure Engineering Inc., Via fax 693.2554 i/ Case file #04-00500017 Home of Texas A&M University STAFF REVIEW COMMENTS NO. 1 Project: EDELWEISS BUSINESS CENTER (MP) - 04-00500017 ENGINEERING 1. Due to fire lane layout shown on the Site Plan for these lots, access easements will be required across portions of Lot 7R. This can be shown on the Plat or by separate easement. However, the Site Plan cannot be approved until the easement is filed. 2. Revise signage note to reflect Lots 7R and 8R. Reviewed by: January 30, 2004 Date: January 30, 2004 ELECTRICAL 1. Developer installs conduit per city specs and design. 2. Developer provides 30' of rigid conduit for riser poles. Developer installs first 10'. City installs remainder. 3. Developer pours transformer pad(s) per city specs and design. 4. Developer installs pull boxes as per city specs and design.(pull boxes provided by the city. 5. Developer provides digital AutoCAD 2002 version of plat and/or site plan. email to rbolin ,cstx.gov 6. Developer provides load data for project. 7. Developer provides temporary blanket easement for construction purposes. 8. Developer provides easements for electric infrastructure as installed for electric lines. 9. Developer provides electrical easement for all electric lines installed on property. Reviewed by: Ronnie Bolin Date: 1-29-04 NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out to the City, will constitute a completely new review. Page 2 of 2