HomeMy WebLinkAboutTCEQ - Exception Letter for Utility Easements7607 Eastmark Drive, Ste. 250-F <77840>
P.O. Box 9253, College Station, TX 77842
Off/Fax: (979) 764-0704
email: civil@rmengineer.com
January 6, 2011
David Loflin
Texas Commission of Environmental Quality
Water Supply Division
MC 153
P.O. Box 13087
Austin, TX 78711
RE: Randall's University Park, Lot 311-2 - College Station, TX
TCEQ Exception Letter for Utility Improvements
RME No. 220-0419
Mr. David Loflin:
The above referenced project will install the following improvements within the distribution
system of the City of College Station (CoCS):
❖ Approximately 106 linear feet of 4" PVC (C909, Class 200) water line;
❖ Applicable services, valves & fittings.
Design and construction of these improvements will be in accordance with the latest
Bryan/College Station Unified Water & Sewer Design Guideline Manual, Standard Details, and
Specifications and Chapter 290 of the TCEQ Rules & Regulations. This quantity of water line is
less than 10% of the total length of water line within the City's current distribution system.
Therefore, an exception for plan review is being requested for this project and its water system
improvements.
Please call should you have any questions or require assistance.
Sincerely, 1* ,:"NN'*XVk
i
PEE OF TEk~ 1
Rabon A. Metcalf, P E ,.T Q Q c Q
oow~ i
Texas Firm Registration No. F-4695 o CA
rabon@rmengineer.com
CENS
xc: Josh Norton, P.E. ~S~~•'~
•
Assistant City Engineer
City of College Station
1101 Texas Avenue South
College Station, TX 77840
CD 1-220-0419-L08.docx
Page 1 of 1
r
` PUBLIC WATER SYSTEM PLAN REVIEW SUBMITTAL FORM
(Complete and Attach to Submittal Package)
Date: January 6, 2011
TCEQ PWS Identification No.*: 0210002 CCN No. or Application No.**: 10169
Water System Name: City of College Station
Water System Owner: City of College Station Type of Entity: Municipality
Address: 13881, 13889 13909 Renee Ln. -College Station Phone: (979) 764-3660
Responsible Official: John Woody Title: Director of Public Utilities
County (system location) : Brazos County Subdivision Sec., Phase, Unit, etc. Randall's University Park - Replat of
Lot 3R-2 Mechanism & Source of Financing: Private
Engineer: Rabon A. Metcalf. P.E. Registration Number: 88583
Firm Name: Rabon Metcalf Engineering Phone: (979) 764-0704
Firm Address: P.O. Box 9253, College Station, TX 77842 Fax: (979) 764-0704
If no PWS Number exists, the owner must submit a business plan, if required, in accordance with §290.39(f) and (g).
" If a required CCN number does not exist, an acceptable application to obtain a CCN number must be made before a project submittal can be
technically reviewed. In addition, if a submittal is for a project located outside the CCN area, a CCN amendment application must be submitted before a
project may be reviewed for construction approval. Please refer to 30 TAC Chapter 291 for additional information regarding CCNs.
If this is a new (proposed) system, you must attach the following with this submittal: NOT APPLICABLE
❑ Attach a list of all water utilities within 'h mile of the proposed service area boundaries
❑ Copies of formal applications for service from each of the following
❑ any municipality if the system is within its ETJ;
❑ any district or other political subdivision whose corporate boundaries are within '/z mile of the proposed
service area boundaries
❑ any other water service provider whose certificated service area boundary is within '/z mile of the proposed
service area boundaries
❑ Documentation that all application requirements including payment of fees were complied with.
❑ Copies of written responses from each of the entities listed above.
❑ Business plan, if required by 30 TAC 290.39(D & (g). The business plan financial requirements for non-community
water systems must confirm capital availability to construct the system according to TCEQ requirements. This
would consist of a balance sheet that shows liabilities as well as assets, not just a bank confirmation of a deposit
account. Alternatively, if the project is being constructed with loan funds, then a loan commitment letter from the
lender specific to that project will suffice.
❑ Justification for constructing a separate system (unless none of the entities listed above exist)
❑ Plans and specifications with an engineering report all sealed by design engineer.
Type of Project (please check the appropriate boxes)
✓
Distribution System Modifications
❑
Storage Capacity Modifications
❑
Well completion data on previously approved well
❑
Water Well Construction, Proposed
❑
Pressure Maintenance Facilities Modifications
❑
Proposed Innovative Process Study
❑
Disinfection Facilities or Other Modifications
❑
Ground Water Treatment Plant, New
❑
Preliminary Engineering Report w/o plans
❑
Surface Water Treatment Plant, New
❑
Modification of Surface Water Treatment Plant
❑
Tex. Water Dev. Board Proj. No.
Other(PleaseExplain)
IF THIS SUBMITTAL IS A REVISION OF PREVIOUSLY SUBMITTED PLANS, PLEASE ENTER THE ASSIGNED TCEQ
LOG NUMBER: . Please call (512) 239-6960 if you have questions regarding this form. Your
rnnnP.rntinn will hi-In im nrnvirlp hpftpr cgryirp Arlrilitinnnl hplnfi d infnrmntinn nnrt nilpc nrp. avaiInhlp nt niir wphcitp-
http://www.tceq.state.tx. us/permittingAvaterperm/ud/planrev.html
of rE~q It,
I hereby certify that the above information is, to the best of my knowledge, true and correct. :41~ _
Rabon A. Metcalf. P.E. January 6, 2011 / Ra a. F
Printed Engineer's Name Date 88;8
U~-••.~CEN`
F • • \
Revised 9/12/02 ~l ~S~~NAt I A
C:\USERS\USER\RME\PROJECTS\220-0419 AJ-CHIMNEY HILL\ENGINEERING \TCEQ FORM 10233-WATER APPROVAL-