CALLAWAY SUBDIVISION (PHASE 3)
PAVING IMPROVEMENTS
COLLEGE STATION, BRAZOS COUNTY, TEXAS
UNIT TOTAL
NO. DESCRIPTION QUANTITY UNIT COST COST
PAVING IMPROVEMENTS
1 Mobilization, Construction Staking, All Required 1 LS $1,000.00 $1,000.00
Testing by Contractor & Trench Safety
2 SWPP Measures (Seeding, Silt Fencing, 1 LS $500.00 $500.00
Construction Entrance)
3 In -Place Earthwork Excavation (Roadway, Alleys, 50 CY $5.00 $250.00
Drainage Channels, Sitework, etc )
4 In -Place Earthwork Embankment Finishing (Topsoil, Landsca 75 CY $8.00 $600.00
Berms & Miscellaneous) (Excavated On -Site)
5 4" Thick Reinforced Concrete Sidewalk (Includes 3,960 SF $4.50 $17,820.00
H/C Ramps & Drainage Flumes)
. SUB -TOTAL = $20,170.00
co e r z s 4 ; 0 %4 6 , � ESTIMATED CONSTRUCTION COST = $20,170.00
* P . 10% CONTINGENCY = $2,017.00
"" o# GRAND TOTAL = $22,187.00
0 FL: i 1 • . MET ALF
This Engineer's Cost Estimate was prepared in our
a . . 4000714"
2 / office, at the date shown, and is released for the
/ — t 3 , ( purposed of public infrastructure cost projections.
g
w l� A t o RME Consulting Engineers
a TEXAS FIRM REGISTRATION No. F -4695
�`''� POST OFFICE BOX 9253
•
COLLEGE STATION, TEXAS 77842
Cipti112181a14/i21 OFF/FAX: (979) 764 -0704
r t E -mail: civil @rmengineer.com
CD1- 178 - 0398- E01.xlsx 1 of 1