WATER SYSTEM FIRE HYDRANT FLOW TEST REPORT
Date: 3 -22 -2012
Wellborn SUD
Water System Owner:
Development Project: Saddle Creek Subdivision
Flow Test Location: Martingale Court (between Lots 161 and 162)
Nozzle size (in.): 2.5 Discharge Coeff: (c) = 0.90
Pitot Reading (psi): 40 Flowrate Formula: Q= 29.84cd
1060 c = discharge coeff.
Flowrate (gpm): d = orifice size (in)
P = pitot pressure (psi)
Pressure Gauge Location:
on Stetson Dr. (@ Martingale intersection)
Static Pressure (psi):
82
Residual Pressure (psi): 65
Computed Discharge at 20 psi Residual Pressure: QR = 2131 e p m
54 0.54
Discharge Formula: QR = QF X (hr 0. /hf )
Note: The flow test and report were prepared in accordance with NFPA 291.
Report Prepared by: Ricky Flores
Deven Doyen, P.E.
Others Present: Clendan Adams
Britt Curless
.I
F -12327
SCHULTZ ENGINEERING. LLC.
Joe Schultz
From: Stephen Cast <wsud.sc @verizon.net>
Sent: Thursday, March 22, 2012 11:45 AM
To: Joe Schultz
Subject: Re: Saddle Creek - Phase 9
Joe,
Wellborn Special Utility District inspected and approved the water line construction for Saddle Creek, Phase 9.
Stephen Cast
General Manager
Wellborn Special Utility District
- - -- Original Messaae - - --
To: Stephen Last
Sent: Friday, March 09, 2012 2:48 PM
Subject: Saddle Creek - Phase 9
Stephen,
Please check with your guys to see if anything else needs to be done on the waterline for Phase 9 for your acceptance.
Thanks
Joe
Joe Schultz, P.E.
Schultz Engineering, LLC
2730 Longmire, Suite A
College Station, TX 77845
Office 979.764.3900
Page 1 of 1
Josh Norton - FW: Saddle Creek - Phase 9
From: "Joe Schultz" <joeschultz84 @verizon.net>
To: "'Josh Norton "' <Jnorton @cstx.gov>
Date: 3/22/2012 1:57 PM
Subject: FW: Saddle Creek - Phase 9
Attachments: Waterline Acceptance.pdf
Josh,
Here is acceptance by Wellborn and the flow test results
A copy is being dropped off at your office
Joe
From: Stephen Cast [mailto:wsud.sc @verizon.net]
Sent: Thursday, March 22, 2012 11:45 AM
To: Joe Schultz
Subject: Re: Saddle Creek - Phase 9
Joe,
Wellborn Special Utility District inspected and approved the water line construction for Saddle Creek, Phase 9.
Stephen Cast
General Manager
Wellborn Special Utility District
- - - -- Original Message - - - --
From: Joe Schultz
To: Stephen Cast
Sent: Friday, March 09, 2012 2:48 PM
Subject: Saddle Creek - Phase 9
Stephen,
Please check with your guys to see if anything else needs to be done on the waterline for Phase 9 for your
acceptance.
Thanks
Joe
Joe Schultz, P.E.