HomeMy WebLinkAboutWater System Analysis Report❑ „ Kimley -Horn
and Associates, Inc.
Water System Analysis
To: City of College Station
From: Michael J. Moore, P.E.
Date: April 15, 2010
Subject: Greens Prairie Elementary
KHA Project No. 066077400
Erika Bridges,
The proposed development consists of one building, approximately 85,254 GSF,
Type I113 construction, with an internal Fire Sprinkler System. The school is
designed for 650 students. The site will be served from an existing 12" water line
owned and operated by the Wellborn Special Utility District (WSUD).
Currently there are no fire hydrants located adjacent to, or in the vicinity of the
site. We are working with JF Fontaine, WSUD's engineer, to confirm adequate
fire flow can be obtained from the proposed design based in the water system
model prepared and maintained by JF Fontaine.
Due to the proprietary nature of the system model, and the construction schedule
necessary to have the school ready for students in August 2011, we request that
you allow the submittal to be reviewed and the Water System Analysis to be
submitted under separate cover as soon as it is completed.
Sincerely,
ael J. I4dore, P.E.
6,4 Reg
% c. , ..... � ... '4c 1
MICHAEL J. MOORE j
V• 68815 ' �''
•• LiISTE �-
•
Suite 105
111 University Drive East
College Station, Texas
77840