HomeMy WebLinkAboutConstruction Docs LetterHanle Engineering Company
P.O. Box 11995
College Station, Texas 77842
979.764.3900 office
979.764.3910
979.436.1559 mobile
March 12, 2010
Erika Bridges, EIT
Graduate Civil Engineer
Department of Public Works
1101 Texas Avenue
College Station, TX 77840
Re: Castle Rock Phase 5— Construction Drawings
Dear Ms. Bridges:
Attached are 1 copy of the revised construction drawings, my response to the staff comments, 2 copies of the
Drainage Report Addendum, 2 copies of the revised water exhibit, 1 copy of the revised final plat and a revised
Engineer's Estimate of the construction cost for the above referenced project. Please let me know if you want
me to have the revised drainage report pages inserted into your copies of the drainage report.
If you have any questions, please do not hesitate to call.
Very truly yours,
Harle Engineering Company
Joe Schu f ', P.E.
Civil Eng' , eer
Schultz Engineering, LLC,
P.O. Box 11995
College Station, Texas 77842
979.764.3900 office
979.764.3910
March 26, 2010
Erika Bridges
Graduate Civil Engineer
City of College Station
1101 Texas Avenue
College Station, TX 77840
Re: Castle Rock Phase 5 — Construction Drawings
Dear Ms. Bridges:
Attached are 6 copies of the construction drawings for the above referenced project. On Sheet 8 where the
waterline goes below the storm sewer line, there are no deflections of the pipe in this area. All of the horizontal
or vertical deflection occurs only in the bends, not in the pipe sections. Therefore, there are no radii used since
there are no curves in the pipe.
If you have any questions, please do not hesitate to call.
Very truly yours,
Schultz Engineering, LLC