HomeMy WebLinkAboutSTAFF COMMENTS CITY OF COLLEGE STATION
I
DEVELOPMENT SERVICES
1101 Texas Avenue South, PO Box 9960
College Station, Texas 77842
COLLEGE STATION Phone 979.764.3570 / Fax 979.764.3496
MEMORANDUM
January 2, 2004
TO: Greg Taggart, Municipal Development Group, Via fax 693.4243
FROM: Bridgette George, Assistant Development Manager
SUBJECT: KRENEK CROSSING (FP) - Final Plat
Staff reviewed the above - mentioned final plat as requested but had to stop review due
to an incomplete submittal. The following page is a preliminary list of staff review
comments detailing items that need to be addressed. Please address the comments
and submit the following information by an established deadline to be scheduled for a
future Planning & Zoning Commission meeting:
Two (2) copies of the revised final plat; and,
Parkland Dedication in the amount of $26,132 must be submitted prior to
the filing of the final plat.
If you have any questions or need additional information, please call Carol Cotter at
764.3570.
Attachments: Staff review comments
cc: Stylecraft Builders, Inc., Via fax 690.0348
Lenwood Adams, P.E., Via fax 693.4243
Case file #03- 00500312
Home of Texas A&M University
STAFF REVIEW COMMENTS NO. 1
Project: KRENEK CROSSING (FP) - 03- 00500312
STOP REVIEW: This plat does not meet minimum platting requirements for numerous
reasons. This does not constitute a full review. Some items have been noted. Please
see comments below.
ENGINEERING
1. The storm sewer system prior to the detention basin is private and will need to be
removed from the PUE. You can relocate the line or reduce the PUE width.
2. Provide final grading plan for entire subdivision. The proposed roads are significantly
below or above the existing grade. How does the road transition into the existing
ground?
3. The water line is profiled off the existing grade. The design grade will be
significantly lower resulting in the water line will not meeting the 4' minimum bury
and possibly even being above ground. Show design grade.
4. Sanitary and storm sewers are also profiled off existing grades. Show design grade.
5. Refer to TCEQ requirements for water line /sewer line crossings. Pipe joints shall be
centered over crossing. Joint of pressure pipe and cement stabilized sand are
required for sanitary sewer line.
6. Provide gate valve detail.
7. The detention basin was shown in a different location on the Preliminary Plat. It is
now entirely within the PUE. I will need to get approval for this new location.
8. Drainage Report comments will be addressed under Development Permit
comments.
Reviewed by: Carol Cotter Date: January 02, 2004
ELECTRICAL
1. Developer installs conduit per city specs and design.
2. Developer provides 30' of rigid conduit for riser poles. Developer installs
first 10'. City installs remainder.
3. Developer pours transformer pad(s) per city specs and design.
4. Developer installs pull boxes as per city specs and design.(pull boxes
provided by the city.
5. Developer provides digital AutoCAD 2004 version of plat and /or site plan.
email to rbolin(c�cstx.gov
6. Developer provides load data for project.
7. Developer provides temporary blanket easement for construction
purposes.
8. Developer provides easements for electric infrastructure as installed for
electric lines (including street lights).
Reviewed by: Ronnie Bolin Date: 12 -18 -03
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your
next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out
to the City, will constitute a completely new review.
Page 2 of 2
Deborah Grace - Krenek Crossing Page 1
From: Spencer Thompson
To: Donald Harmon
Date: 2/9/2004 10:46:09 AM
Subject: Krenek Crossing
The property at Krenek Tap and Dartmouth is looking to file their Final Plat within the next few days. Mr.
French did sign the plat as the owner.
I am inquiring as to our role in filing or not filing the plat in regards to the Dartmouth Extension assessment
set on the property.
If it is paid....lf it is not paid....Yada, yada, yada
thx
st
Spencer G. Thompson, Jr.
Engineering Services
City of College Station
PO Box 9960
College Station, TX 77842
Ph. 979.764.3570 Fx. 979.764.3496
www.cstx.gov
CC: Brenda Godfrey; Carla Robinson; Carol Cotter; Deborah Grace; Mark McAuliffe