Issue Date 8/03/04
Expiration Date . . . 9/03/04
Parcel Number 144500 - 0004 -0010
Property Address . . 405 CROSS ST
COLLEGE STATION TX 77840
Subdivision Name . . . BOYETT
Legal Description . . . BOYETT, BLOCK 4, LOT 1 -3 & 14-
16
Property Zoning . . . HISTORIC NORTHGATE
Owner
Contractor CAMDEN
713 354 -2500
Application number . . 03- 00003629 000 000
Description of Work . . RESIDENTIAL, 5+ UNITS NEW
Construction type . . . COMBUSTIBLE (PROTECTED)
Occupancy type . . . . RESIDENTIAL - MULTI - FAMILY
Flood Zone
Special conditions .
COMPLETE STREET REPAIRS
NEED BACKFLOW REPORT ON DOMESTIC WATER
NEED KNOX BOXES ON GATES / DOORS
GATES ON PARKING AREA MAY NOT BE CLOSED UNITL KNOX BOXES
ARE PROPERLY INSTALLED
SITE CLEAN AND FREE OF CONSTRUCTION DEBRIS, EQUIPMENT, JOB,
SHACKS, SAND DIRT, ETC.
DUMPSTER ENCLOSURE CLEANED OF ALL CONSTRUCTION DEBRIS
BIKE RACKS INSTALLED IN APPROVED LOCATION
GRATES ON SIDEWALK OPENINGS NEED TO BE INSTALLED
Approved C _A , � / C t_ �r•, nn
Buil I.- in Official
VOID UNLESS SIGNED BY BUILDING OFFICIAL
`) 5
Checklist for C.O.
P . lic Works: 1/4 �( � �
o mplete sidewalks �� �`� S(- v\- v �
Complete street repairs � < �� (Jd-
Straighten fire hydrant \'� C,
-place F/H valve box w/ adjustable box
Remove and replace handicapped ramp and approx. 200 sf stamped
walk, does not meet TAS
.complete relocation and installation of sewer main cleanout
(All of these items can be bonded and need not hold up the CO. Need cost estimate for these items so City
Engineer can review to determine bond amount. After 2 weeks the City must be able to cash in the bond
and contract for the remaining work to be completed.)
San
�Btr r�ipster enclosure gates must meet specs.
Utilities:
wed backflow reports on�omestic water fire sprinkler system, and
lawn irrigation.
" +oak_ ( cc( '
Fir
rm system needs to be up and running & final tested
'`Need final test and approval of dry sprinkler system
1%"1 ed final test and approval of wet sprinkler system
Need knox boxes on gates / doors
Fire lane through parking area
Building:
Final building inspection has not been requested or performed
Need one designated Handicapped unit
Pla Wing:
171,k
landscape installed (can be bonded with 150% of bid)
i e clean and free of construction debris, equipment, job shacks, sand,
dirt, etc.
Development, construction, finance signs removed
One way traffic flow marked on pavement
>ka •C 1 medil
Cii 0-q -,
ou.t_ I 0 a/td, 00" &
�� (
��
Checklist for C.O.
Public Works:
Complete sidewalks
Complete street repairs
Straighten fire hydrant
Replace F/H valve box w/ adjustable box
Remove and replace handicapped ramp and approx. 200 sf stamped
walk, does not meet TAS
Complete relocation and installation of sewer main cleanout
(All of these items can be bonded and need not hold up the Co. Need cost estimate for these items so City
Engineer can review to determine bond amount. After 2 weeks the City must be able to cash in the bond
and contract for the remaining work to be completed.)
Sanitation:
Dumpster enclosure gates must meet specs.
Utilities:
* *Need backflow reports on domestic water, fire sprinkler system, and
lawn irrigation
Fire:
* *Alarm system needs to be up and running & final tested
* *Need final test and approval of dry sprinkler system
* *Need final test and approval of wet sprinkler system
Need knox boxes on gates / doors
Fire lane through parking area
Building:
Final building inspection has not been requested or performed
Need one designated Handicapped unit
Planning:
Need landscape installed (can be bonded with 150% of bid)
Site clean and free of construction debris, equipment, job shacks, sand,
dirt, etc.
Development, construction, finance signs removed
One way traffic flow marked on pavement
INSPECTION CHECKLIST —
FOR CERTIFICATE OF OCCUPANCY
Multi - Family and Commercial Projects
Planning & Development Engineering Items (Exterior)
• All pavement must be in — especially around perimeter.
• All curbing must be installed, including edges of future phases.
• All parking spaces must be striped, including handicap spaces.
• Spot check dimensions of spaces and circulation aisles. (9'x18' with 2'
overhang or 9'x 20' without overhang; 2 -way circulation aisles must be 23'
wide; 1 -way can be 20'wide)
• All islands must be curbed raised, and either planted or bricked (decorative
pavers, stamped colored concrete O.K.) and located as shown on approved
plans.
• The Dumpster screening must be installed as shown on approved plans.
• The landscaping must be installed and appear to be similar to approved plan.
• The site must be clean and free of construction debris, equipment, job shacks,
sand, dirt, etc.
• The development, construction and finance signs must be removed.
• The adjacent lots disturbed during construction must be returned to original
conditions (graded, seeded or sodded, debris removed) .
• Handicap ramps must be installed.
• Handicap signs must be installed.
• Fire lanes must be painted in locations shown on approved plan.
• Detention with groundcover must be installed and located as shown on
approved plan. Look to see if water can get into and out of the pond per the
approved plans.
• If grass is the ground cover to be used for general landscape and detention
requirements, the sod must be installed or there must be evidence that the
area has been seeded or hydromulched.
IF ANY OF THE ITEMS HAVE NOT BEEN COMPLETED, PLEASE CONTACT THE
ASST. DEVELOPMENT MANAGER IN CHARGE OF THE PROJECT AT
979.764.3570
From: Mark Smith
To: Natalie Ruiz
Date: 7/29/2004 12:59:10 PM
Subject: Cross Street Warehouse
The following list was sent to me by John Logan.
complete sidewalks
complete street repairs
straighten fire hydrant
replace F/H valve box w/ adjustable box
remove and replace handicapped ramp and approx. 200 sf stamped walk, does not meet TAS
complete relocation and installation of sewer main cleanout
All of these items can be bonded and need not hold up the CO. I would like for the developer to provide
us with a cost estimate for these items so I can review it before the bond amount is determined. Also, I
think that there should be a time limit on the completion of these items. 2 weeks seems reasonable to
me. After 2 weeks the City must be able to cash in the bond and contract for the remaining work to be
completed.
Mark Smith
Director of Public Works
979 - 764 -3690
CC: Glenn Brown; John Logan
From: Anthony Hamilton
To: Mandi Alford
Date: 7/29/2004 10:38:48 AM
Subject: Re: Cross Street Warehouse
We will need the backflow reports on domestic water, fire sprinkler system, and lawn irrigation. The first
two being the most important.
»> Mandi Alford 7/29/2004 9:20:25 AM »>
405 Cross St
Wants to be ok'd for there ribbon cutting on exterior and partial first floor.
Any Issues???
Thanks
Mandi Alford
Customer Service Rep.
Development Services
City of College Station
www.cstx.gov
CC: Devel Service Front Counter; Jennifer Prochazka; Peter G Garcia
Page 1 of 1
Jennifer Prochazka - Re: Cross Street Warehouse
SSSr. "inESn`H & w'ti'm%. oYwm'Yad4Yb*vcS's °soh yfkwSa"d tP,` mal `5°.'i:% \i =x'R' N m_h:yx , ?s.- .t -, ?._` ' 1:.`. K .w.- ,+ ••.'... ..S ..as. ,;
NMIIMINSOMTMOOPM
From: Natalie Ruiz
To: Mandi Alford
Date: 7/29/2004 10:13 AM
Subject: Re: Cross Street Warehouse
CC: Jennifer Prochazka
Jennifer P.'s working on this one.
Natalie Thomas Ruiz, AICP
Development Manager
City of College Station
Phone (979) 764 -3570
Fax (979) 764 -3496
nru iz @csbcgov
www.cstx.gov
College Station. Embracing the Past, Exploring the Future.
»> Mandi Alford 7/29/2004 9:20:25 AM »>
405 Cross St
Wants to be ok'd for there ribbon cutting on exterior and partial first floor.
Any Issues ? ??
Thanks
Mandi Alford
Customer Service Rep.
Development Services
City of College Station
www.csbc.gov
file: / /C:\ Documents %20and %20Settings \jflanery \Local %20Settings \Temp \GW} 00002.HTM 7/29/2004
From: Bridgette George
To: JProchazka
Date: 7/29/2004 9:03:11 AM
Subject: Fwd: Re: Cross Street Warehouse Apts in NG
Bridgette George
Asst. Development Manager
City of College Station
P.O. Box 9960
College Station, TX 77842 -9960
979.764.3570
bgeorge @cstx.gov
www.cstx.gov
»> Anthony Hamilton 7/28/2004 11:30:24 AM »>
We will need three reports on backflow preventers
!. Fire line
2. Domestic water
3. Irrigation
I left info on general and fireline testers, they are working on the domestic and irrigation
»> Bridgette George 7/27/2004 2:54:20 PM »>
Good afternoon! They're getting close to requesting a CO, please let me know of any outstanding issues.
Thanks!
Bridgette George
Asst. Development Manager
City of College Station
P.O. Box 9960
College Station, TX 77842 -9960
979.764.3570
bgeorge(a cstx.gov
www.cstx.gov
From: Bridgette George
To: JProchazka
Date: 7/29/2004 9:02:52 AM
Subject: Fwd: Re: Cross Street Warehouse Apts in NG
Bridgette George
Asst. Development Manager
City of College Station
P.O. Box 9960
College Station, TX 77842 -9960
979.764.3570
bgeorge @cstx.gov
www.cstx.gov
»> John Logan 7/28/2004 7:47:41 AM »>
Good Morning, at this time the contractor is placing sidewalks. The street needs repairing as the damage
is getting worse. I estimate a week to finish the walks and 10 days total to finish all work needed for their
letter of completion.
From: Bridgette George
To: JProchazka
Date: 7/29/2004 9:02:39 AM
Subject: Fwd: Cross Street Warehouse Apts in NG.
Bridgette George
Asst. Development Manager
City of College Station
P.O. Box 9960
College Station, TX 77842 -9960
979.764.3570
bgeorge @cstx.gov
www.cstx.gov
»> Wally Urrutia 7/27/2004 4:52:47 PM »>
I met with the Superintendent at the location this morning to look at the enclosure gates.
They are not up to spec. and discussed with him on what needs to be done.
The enclosure gates are not wide enough for our vehicle, so they will be working on widening the gates for
us.
I will check back with them on Thursday and Friday this week and give you an update.
thanks,
"Keep Your Chin Up, Someone Cares About You"
Wally Urrutia
Solid Waste Foreman
Public Works
(979) 764 -3698