HomeMy WebLinkAboutOVERSIZE PARTICIPATION REQ McCLURE ENGINEERING, INC.
September 30, 2003
Mr. Brett McCully
City of College Station
P.O. Box 9960
College Station, Texas 77842
Re: Westfield Village, Phases 2 & 3 — Oversize Participation Request
Dear Brett:
Accompanying this letter is an estimate of oversize participation costs associated
with the development of Westfield Village, Phases 2 & 3. Oversize participation is
estimated for two aspects of the development. The first is the construction of Victoria
Avenue, increasing its width from 39 feet to 48 feet as called for on the city's
Thoroughfare Plan. The estimated cost for this oversizing is $20,201.80.
The second is the increased water line sizes on Victoria Avenue and Barron Road
to match existing line sizes on those roadways. The Victoria Avenue line is increased
from an 8" to a 12" line and the Barron Road line is increased from 8" to 18 ". The
smaller line sizes were determined to be sufficient in the Water Report submitted with
Phase 1. The estimated cost for this oversizing is $43,714.00.
The total Oversize Participation cost being requested with this project is
$63,915.80. Please forward this request to the appropriate officials for consideration.
Thank you.
Sincerely,
/&
Kent Laza, P.E.
Project Administrator
xc: Randy French
attachment
1008 Woodcreek Drive, Suite 103 • College Station, Texas 77845
(979) 693 -3838 • FAX (979) 693 -2554 • email: mcclure @tca.net
WESTFIELD VILLAGE, PHASES 2 & 3
ENGINEER'S ESTIMATE OF OVERSIZE PARTICIPATION
September 30, 2003
Victoria Avenue Construction
Estimated
Item Description Unit Quantity Unit Price Total
No.
48 FT. WIDTH
1 Clearing and Grubbing ACRE 2.1 1,000.00 2,070.00
2 Excavation (Roadway and Channel) C.Y. 3,586 3.75 13,447.50
3 1.5" HMAC Surface Course S.Y. 6,312 3.80 23,985.60
4 6" Lime Stabilized Subgrade S.Y. 7,172 3.00 21,516.00
5 7" Crushed Limestone Base S.Y. 6,312 6.75 42,606.00
Subtotal $103,625.10
39 FT. WIDTH
1 Clearing and Grubbing ACRE 1.8 1,000.00 1,780.00
2 Excavation (Roadway and Channel) C.Y. 2,941 3.75 11,028.75
3 1.5" HMAC Surface Course S.Y. 5,021 3.80 19,079.80
4 6" Lime Stabilized Subgrade S.Y. 5,881 3.00 17,643.00
5 7" Crushed Limestone Base S.Y. 5,021 6.75 33,891.75
Subtotal $83,423.30
Oversize Participation (Victoria Avenue) $20,201.80
12" Water Line on Victoria Av. and 18" Water Line on Barron Road
Estimated
Item Description Unit Quantity Unit Price Total
No.
12" & 18" LINES
1 12" PVC, C900 Water Line, Str. Backfill L.F. 1,274 30.00 38,220.00
2 12" PVC, C900 Water Line, w/ 24" Steel Casing, bored (wet) L.F. 54 275.00 14,850.00
3 18" D.I.P., CL 250, Str. Backfill L.F. 543 60.00 32,595.00
4 12 "x 8" Tee EACH 1 500.00 500.00
5 12 "x 13" Anchor Coupling EACH 3 300.00 900.00
6 12" Gate Valve EACH 3 1,100.00 3,300.00
7 18 "x 12" Tee EACH 1 1,400.00 1,400.00
8 18" Butterfly Valve EACH 1 6,500.00 6,500.00
Subtotal $98,265.00
8" LINES
1 8" PVC, C900 Water Line, Str. Backfill L.F. 1,817 23.00 41,791.00
2 8" PVC, C900 Water Line, w/ 16" Steel Casing, bored (wet) L.F. 54 170.00 9,180.00
3 8 "x 8" Tee EACH 2 250.00 500.00
4 8 "x 13" Anchor Coupling EACH 3 160.00 480.00
5 8" Gate Valve EACH 4 650.00 2,600.00
Subtotal $54,551.00
OP
A ' ` 7 Oversize Participation (water line construction) $43,714.00