HomeMy WebLinkAboutLetter Regarding Financial Guarantee\\ -SU
January 31, 2012
Josh Norton, P.E.
Assistant City Engineer
City of College Station
1101 Texas Avenue
College Station, TX 77840
Re: University Heights (FP) —11- 00500086
Dear Mr. Norton:
Attached is a Cashier's check for $12,200 payable to the City of College Station. Please accept this
as a financial guarantee for the construction completion of the HMAC pavement on Haverford
Drive from Station 9 +50 to Station 12 +50. An Engineer's cost estimate is also attached for this
work. The estimate provides for removing and replacing the section of pavement which is a greater
cost than wedge grinding the edge and overlaying the surface with 1" of HMAC. I anticipated the
Contractor will go with the overlay as requested by the City of College Station instead of removing
and replacing.
If you have any questions, please do not hesitate to call.
Very truly yours,
Schultz Engineering, LLC.
Joe Sch tz, P.E.
Civil E neer
P.O. Box 11995 • College Station, Texas 77842
schultzengineeringllc.com
Sch ultz Engineering, LLC
Office: 979.764.3900
Fax: 979.764.3910
Item
I Description
I Unit
Estimated
Quantity
I I
Unit Price
Total
I
Street Construction Items
1
Mobilization
LS
1,000
$ 1.00
$1,000
2
MILL & REMOVE HMAC - Type D Pavement, complete in place
SY
800
$ 4.00
$3,200
3
HMAC - Type D Pavement 2" thick - includes prime coat, complete in place
SY
800
$ 10.00
$8,000
Street Construction Items Subtotal
$12,200
SCHULTZ ENGINEERING, LLC.
2730 Longmire Drive, Suite A
College Station, Texas 77845
Firm No. 12327
University Heights Subdivision - Phase 1
HAVERFORD DRIVE PAVEMENT REPLACEMENT
Station 9 +50 to Station 12 +50
Engineer's Estimate of Construction Completion
January 30, 2012
Page 1 of 1
F -12327
SCHULTZ ENGINEERING, LLC,