HomeMy WebLinkAboutLetter Re: Energy Transfer Kent Laza
From: Waterwall, Celeste [ Celeste .Waterwall @energytransfer.com]
Sent: Wednesday, April 27, 2011 4:16 PM
To: ' klaza @phillipsengineeringbcs.com'
Subject: Re: Castlegate II Section 200
Yes I did. Thanks so much. I had to go out of town & will be back Friday. I will look at them then.
Celeste Waterwall
Energy Transfer /Houston Pipe Line
Encroachment Supervisor
711 Louisiana Suite 900
Houston, Texas 77002
Office 832 - 668 -1222
Cell 832 - 693 -6468
From: Kent Laza J mailto: klaza @phillipsengineeringbcs.coml
Sent: Wednesday, April 27, 2011 04:11 PM
To: Waterwall, Celeste
Subject: Castlegate II Section 200
Celeste,
Did you received the file I sent yesterday with its attached drawings of our subdivision?
Kent M. Laza, P.E., Manager
Phillips Engineering
PROVIDING CIVIL ENGINEERING SERVICES TO COLLEGE STATION, BRYAN AND SURROUNDING COMMUNITIES
4490 Castlegate Drive
College Station, Texas 77845
(979) 690 -3141 office
(979) 220 -1957 cell
(979) 690 -1041 fax
klazaaphillipsengineeringbcs. com
��
1
Kent Laza
From: Kent Laza [ klaza @phillipsengineeringbcs.com]
Sent: Tuesday, April 26, 2011 11:40 AM
To: Celeste Waterwall ( celeste .waterwall @energytransfer.com)
Subject: Construction Plans for Castlegate II Section 200
Attachments: to Energy Transfer 4- 26- 11.zip
Celeste,
Attached is a zip file with several drawings in it for your review. It is a large file, so please respond and let me know if
you did or didn't get it all. These are the files I spoke to you about this morning regarding our planned construction of a
subdivision adjacent to a pipeline owned by Energy Transfer. The line extends along the north property line of our site
from Greens Prairie Road in a northwestward direction. We have worked with Mr. Gary Sawyer to get the line located,
but he was not able to give us specific depths on the line. At his suggestion, we have assumed a depth of 3.5 to 4 feet.
The attached drawings are not a complete set, but they include all those around the pipeline so you can see what we are
proposing. As I indicated on the phone, these are not yet approved for construction but we are hoping to have the city's
final review comments later this week.
We are referring to this as Section 200, which is the first of about 15 phases in the subdivision. Of those, about 5 will be
constructed adjacent to the pipeline. In most cases, there will be a roadway separating the pipeline from the residential
area. This first phase includes crossings for water, sewer, drainage and street extensions. Once this phase is completed,
there will be one other future phase involving a street extension that crosses the pipeline, but there are no other planned
crossings for drainage or utilities. There are some sidewalks planned within the pipeline easement in the future that are
similar to the one shown in this phase. If it will help, I can also send you a drawing of the overall subdivision to give a
larger perspective of the development.
Please call or e-mail me with any comments. Thank you.
Kent M. Laza, P.E., Manager
Phillips Engineering
PROVIDING CIVIL ENGINEERING SERVICES TO COLLEGE STATION, BRYAN AND SURROUNDING COMMUNITIES
4490 Castlegate Drive
College Station, Texas 77845
(979) 690 -3141 office
(979) 220 -1957 cell
(979) 690 -1041 fax
klaza(a,phillipsengineeringbcs. com
1