Staff reviewed the above - mentioned preliminary plat as requested. The following page
is a list of staff review comments detailing items that need to be addressed. If all
comments have been addressed and the following information submitted by Monday,
September 23, 10:00 a.m. your project will be placed on the next available Planning
and Zoning Commission meeting scheduled for October 3, 2002, 7:00 p.m. in the City
Hall Council Chambers, 1101 Texas Avenue.
Ten (10) copies of the revised preliminary plat; and,
One (1) Mylar original of the revised preliminary plat.
One (1) copy of the digital file of the preliminary plat on diskette or e-mail
to nmanhart @ci.college - station.tx.us
Please note that if all comments have not been addressed on your revised preliminary
plat, your project will be pulled from the scheduled Planning & Zoning Commission
agenda. Your project may be placed on a future agenda once all the revisions have
been made and the appropriate fees paid. Upon receipt of the required documents for
the Planning & Zoning meeting, your project will be considered formally filed with the
City of College Station. If you have any questions or need additional information, please
call me at 764 -3570.
Attachments: Staff review comments
cc: Southcorp Holdings I, L.P., via fax 713.355.4275
Case file #02 -190
Home of Texas A &M University
STAFF REVIEW COMMENTS NO. 1
Project: POR NADA SUBDIVISION (PP) - 02 -190
ENGINEERING
1. Please correct survey information along north boundary lines.
2. Please state utility information on plat. Water to be served...? Sewer to be
served...? Utilities will have to be "provided" for Final Plat.
3. Please see Zoning Ordinance, Table A for correct setbacks.
4. Please label topo for clarity.
5. Please provide utility easements per Subdivision Regulations.
Reviewed by: Spencer Thompson Date: September 4, 2002
PLANNING
1. Please continue the city limit line.
2. Please show the zoning district boundary.
Reviewed by: Molly Hitchcock Date: September 5, 2002
ELECTRICAL
1. Developer installs conduit as per city specs and design.
2. Developer provides 30' of #4 rigid conduit for riser pole. Developer installs first 10'.
City installs remainder.
3. Developer pours transformer pad(s) per city specs and design.
4. Developer installs pull boxes as per city specs and design (pull boxes provided by
the city).
5. Developer provides digital AutoCAD 2000i version of plat and /or site plan. Email to
rbolin(a�ci.college- station.tx.us.
6. Developer provides load data for project.
7. Developer provides temporary blanket easement for construction purposes.
8. Developer provides easements for electric infrastructure as installed for electric
lines.
Reviewed by: Ronnie Bolin Date:9 -4 -02
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your
next transmittal letter and 'bubbled" on your plans. Any additional changes on these plans that have not been pointed out
to the City, will constitute a completely new review.
2 of 2
10/02/02 08:51 From: Bridgette George 979 - 764 -3896 Page 2 of 3
CITY OF COLLEGE STATION
DEVELOPMENT SERVICES
1101 Texas Avenue South, PO Box 9960
COLLEGE STATION College Station, Texas 77842
Phone (979) 764 -3570 / Fax (979) 764 -3496
MEMORANDUM
October 1, 2002
TO: Lenwood Adams, via fax 693.4243
FROM: Bridgette George, Assistant Development Manager
SUBJECT: POR NADA SUBDIVISION (PP) - Preliminary Plat
Staff reviewed the above - mentioned preliminary plat as requested. The following page is a
list of staff review comments detailing items that need to be addressed. If all comments
have been addressed and the following information submitted by Monday, October 7, 10:00
a.m., your project will be placed on the next available Planning and Zoning Commission
meeting scheduled for October 17, 2002, 7:00 p.m. in the City Hall Council Chambers,
1101 Texas Avenue.
Ten (10) copies of the revised preliminary plat;
One (1) Mylar original of the revised preliminary plat; and
One (1) copy of the digital file of the preliminary plat on diskette or e-mail to
nmanhart @ci.college- station.tx.us
Please note that if all comments have not been addressed on your revised preliminary plat,
your project will be pulled from the scheduled Planning & Zoning Commission agenda. Your
project may be placed on a future agenda once all the revisions have been made and the
appropriate fees paid. Upon receipt of the required documents for the Planning & Zoning
meeting, your project will be considered formally filed with the City of College Station. If you
have any questions or need additional information, please call me at 764 -3570.
Attachments: Staff review comments
cc: Southcorp Holdings I, L.P., via fax 713.355.4275
Case file #02 -190
STAFF REVIEW COMMENTS NO. 2
Home of Texas A &M University
10/02/02 06:51 From: Bridgette George 979 - 764 -3896 Page 3 of 3
Project: POR NADA SUBDIVISION (PP) - 02 -190
ENGINEERING
1. In order for this property to be platted, the required utilities must be extended to and
across each resulting parcel. There is sufficient acreage that sewerage could be
provided by OSSF. You may state on the Preliminary Plat that sewerage will be
supplied by OSSF or other when available. However, fire protection must be provided to
the property in order to develop the property according to the current zoning. If water is
not extended to the property, then the property is not ready to develop at this time and a
plat is not needed. In order to get a preliminary plat approval you must show the required
utilities in order to meet minimum platting requirements.
2. In order to receive Final Plat approval you must provide construction documents for any
required utilities. The required utilities must be constructed and accepted or guaranteed
before the Final Plat will be filed.
Reviewed by: Spencer Thompson Date: October 1, 2002
NOTE: Any changes made to the plans, that have not been requested by the City of College Station,
must be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on
these plans that have not been pointed out to the City, will constitute a completely new review.