Engineer's Opinion of Probable Construction Cost
ABEI No. 1044001
September 23, 2002
The following construction estimate is based on the engineer's opinion of probable
construction costs. This estimate constitutes our best judgement at this time. Please note
that the engineer does not have any control over contractor or supplier workloads and the
degree to which inflation may affect project costs between now and the bid date. During
construction, additional features may become apparent as the work progresses, which will
result in an increase in cost.
Item Description Estimated Estimated ESTIMATED
No. Quantity Unit Cost TOTAL COSTS
1.00 STREET
1.01 50' R.O.W. Preparation (includes 962 LF $14.00 $13,468
clearing and grubbing, cutting to rough
grade, etc.)
1.02 60' R.O.W. Preparation (includes 320 LF $16.50 $5,280
clearing and grubbing, cutting to rough
grade, etc.)
1.02 6" Lime Modified Subgrade (includes 5,092 SY $1.25 $6,365
subgrade preparation and incorporation
of lime into subgrade.)
1.03 Lime for Stabilization (5% by weight) 51 TN $100.00 $5,100
1.04 Curb and Gutter 2,600 LF $7.50 $19,500
1.05 6" Crushed Rock Base (Flexible Base) 5,092 SY $6.50 $33,098
TxDOT Type A, Grade 2
1.06 2" Hot Mix Asphaltic Concrete 4,237 SY $6.00 $25,422
TxDOT Type D (includes prime coat)
Subtotal Item 1.00 Streets: $108,233
2.00 WATER
2.01 6 "e AWWA C900 Class 200 PVC Pipe 866 LF $8.00 $6,928
(includes installation, testing, and
cleanup.) Non - structural
2.02 12 "e AWWA C900 Class 200 PVC Pipe 260 LF $12.00 $3,120
(includes installation, testing, and
cleanup.) Non - structural
Carroll Addition Estimate - Page 1 of 3
Item Description Estimated Estimated ESTIMATED
No. Quantity Unit Cost TOTAL COSTS
2.03 12 "e AWWA C900 Class 200 PVC Pipe 57 LF $20.00 $1,140
(includes installation, testing, and
cleanup.) Structural
2.04 Single Near Side Service 2 EA $100.00 $200
2.05 Double Near Side Service 5 EA $100.00 $500
2.06 Double Far Side Service 9 EA $200.00 $1,800
2.07 6" Gate Valve (includes installation and 2 EA $500.00 $1,000
cleanup.)
2.08 2" Blow -Off Valve Assembly With Valve 1 EA $750.00 $750
Box (includes installation and cleanup.)
2.09 DI Fittings (includes installation and 1.0 TN $4,200.00 $4,200
cleanup.)
2.10 Fire Hydrant Assembly (includes 1 EA $2,000.00 $2,000
installation and cleanup.)
Subtotal Item 2 - Water: $21,638
3.00 SEWER
3.01 8 "e SDR 26 PVC ASTM D3034 Sewer 1,116 LF $8.50 $9,486
Line (includes installation, testing, and
cleanup.)
3.02 8 "e SDR 26 PVC ASTM D2241 Sewer 18 LF $9.25 $167
Line (includes installation, testing, and
cleanup.)
3.02 0 - 5' Trenching & Backfill - Non- 39 LF $8.00 $312
Structural (includes backfill and
cleanup)
3.03 5' - 8' Trenching & Backfill - Non- 952 LF $10.00 $9,520
Structural (includes backfill and
cleanup) "
3.04 5' - 8' Trenching & Backfill - Structural 120 LF $14.00 $1,680
(includes backfill and cleanup)
3.05 8' - 10' Trenching & Backfill - Non- 23 LF $18.00 $414
Structural (includes backfill and
cleanup)
3.06 Single Far Side Service 6 EA $600.00 $3,600
3.07 Double Near Side Service 6 EA $800.00 $4,800
3.08 Double Far Side Service 6 EA $1,000.00 $6,000
3.09 Trench Safety 1,095 LF $1.00 $1,095
Carroll Addition Estimate - Page 2 of 3
Item Description Estimated Estimated ESTIMATED
No. Quantity Unit Cost TOTAL COSTS
3.10 4' Standard Manhole (0 - 6' Deep) 4 EA $1,750.00 $7,000
(includes installation, testing, and
cleanup.)
3.11 Additional depth for 4' dia. Standard 2 VF $100.00 $200
manhole
3.12 Cleanouts 1 EA $300.00 $300
Subtotal Item 3 - Sewer: $44,574
4.00 DRAINAGE
4.01 2' Pilot Channel 100 LF $8.00 $800
4.02 10' Drainage Channel 55 LF $35.00 $1,925
4.03 10' Inlet Box 1 EA $3,500.00 $3,500
4.04 Stone Riprap 4 CY $75.00 $300
Subtotal Item 4 - Drainage: $6,525
5.00 MISCELLANEOUS
5.01 Silt Fence 310 LF $4.00 $1,240
5.02 6' Sidewalk 1,505 LF $15.00 $22,575
5.03 Sidewalk Ramp Type 1 3 EA $150.00 $450
Subtotal Item 5 - Miscellaneous: $24,265
TOTAL PROJECT COST: $205,235
A
Prepared b . / /i i . ,%,
. Dale Browne Jr., •.E. t, .....
Ash & Browne Engineering t t - o• , 81890 ..4
t1 '�c�'•f'G /STE.. � 4
a 1 r
t ``‘ ..LN
Carroll Addition Estimate - Page 3 of 3