Estimate of Oversize Participation Costs
March 12, 2003
Sewer Trunk Line Construction for Ultimate Development south of Edelweiss Gartens
Item Description Unit Quantity Unit Cost Extension
1 15" PVC D 3034, Str. Backfill L.F. 480 70.00 33,600.00
2 12" PVC D 3034, Str. Backfill L.F. 2,390 45.00 107,550.00
3 12" DIP Class 350, 18" Steel Casing, Str. Backfill L.F. 60 120.00 7,200.00
4 10" PVC, D -3034, Str. Backfill L.F. 1,250 40.00 50,000.00
Estimated Construction Cost $198,350.00
Sewer Trunk Line Construction for Edelweiss Gartens Phases 5 & 6 Only
1 8" PVC, D -3034, Str. Backfill L.F. 4,120 31.00 127,720.00
2 8" DIP Class 350, 16" Steel Casing, Str. Backfill L.F. 60 76.00 4,560.00
Estimated Construction Cost $132,280.00
Oversize Participation by City of College Station $66,070.00