MEMORANDUM
June 11, 2003
TO: Donald Garrett, Garrett Engineering, Via fax 846.3094 t/
FROM: Bridgette George, Assistant Development Manager
SUBJECT: University Park Phase II
Staff reviewed the above - mentioned engineering documents as requested. The
following page is a list of staff review comments detailing items that need to be
addressed. Please address the comments and submit the following information
for further staff review and approval of the plans:
One (1) set of revised construction documents; and
Development Permit application and appropriate fees.
If you have any questions or need additional information, please call Spencer
Thompson or myself at 764.3570.
Attachments: Staff Review Comments
Cc: Rossco Holdings, Inc., Via fax 268.0956 J
Case file no.
Home of Texas ABM University
UNIVERSITY PARK PHASE II - (03- 00500144)
ENGINEERING REVIEW
COMMENTS No. 1
1. When doing a Plan /Profile, the plan view should match the profile view. Re-
align waterline.
2. If City details are not provided with construction drawings, state "Contractor to
have City Detail Sheets on -site during construction ".
3. The water line sizing is sufficient for platting. However, the engineer should
do a fire -flow analysis to determine that sufficient capacity is being provided
for the intended use. If a 3 -story hotel goes in on this site, will the 8" line
meet fire code? Will the 8" line need to be looped back to the 6" to the east?
4. According to City data, the downstream (180 -ft) manhole invert is at 294.97.
The upstream (420 -ft) manhole invert is at 303.90. Do you have field data
that differs?
5. Water and sewer plans must be submitted under the Development Permit
process. Please submit DP and applicable fees.
Reviewed by: Spencer Thompson Date: June 11, 2003
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must
be explained in your next transmittal letter and "bubbled" on your plans. Any additional changes on
these plans that have not been pointed out to the City of College Station will constitute a
completely new review.
Page 2 of 2
CITY OF COLLEGE STATION
DEVELOPMENT SERVICES
1101 Texas Avenue South, PO Box 9960
College Station, Texas 77842
COLLEGE STATION
Phone 979.764.3570 / Fax 979.764.3496
MEMORANDUM
June 11, 2003
TO: Donald Garrett, Garrett Engineering, Via fax 846.3094 i/
FROM: Bridgette George, Assistant Development Manager
SUBJECT: UNIVERSITY PARK PHASE II - Final Plat
Staff reviewed the above - mentioned final plat as requested but had to stop review due
to an incomplete submittal. The following page is a list of staff review comments
detailing items that need to be addressed. If all comments have been addressed and
the following information submitted by Monday, July 7, 10:00 a.m., your project will be
placed on the next available Planning and Zoning Commission meeting scheduled for,
July 17, 2003, 7:00 p.m. in the City Hall Council Chambers, 1101 Texas Avenue.
Two (2) copies of the revised final plat;
One (1) Mylar original of the revised final plat; and
One (1) copy of the digital file of the final plat on diskette or e-mail to
nmanhart@ci.college- station.tx.us
Upon receipt of the required documents for the Planning & Zoning meeting, your project
will be considered formally filed with the City of College Station. Please note that if all
comments have not been addressed your project will not be scheduled for a Planning &
Zoning Commission meeting. Your project may be placed on a future agenda once all
the revisions have been made and the appropriate fees paid. If you have any questions
or need additional information, please call Spencer Thompson or myself at 764.3570.
Attachments: Staff review comments
cc: Rossco Holdings, Inc., Via fax 268.0956 V
Case file #03- 00500144
Home of Texas A&M University
STAFF REVIEW COMMENTS NO. 1
Project: UNIVERSITY PARK PHASE II - 03- 00500144
Plat Comments. Engineering comments returned separately.
STOP REVIEW: This item is invalid as submitted. See comments below.
ENGINEERING
1. This is a replat of Lot 3B Block V. Lot 3B is 4.96 acres. You must show Original
Plat as originally platted. Plat can not be processed as submitted.
2. There is an existing 20 -ft PUE on the east property line of 3B. You are not showing
this existing easement. See plat.
3. Show easements adjacent to subject property.
4. Show lengths of all individual lot line segments.
5. Plat must be signed by all owners.
6. Remove all building lines. BL's are set by zoning ordinance.
Reviewed by: Spencer Thompson Date: June 11, 2003
ELECTRICAL
1. Developer installs conduit per city specs and design.
2. Developer provides 30' of #4 rigid conduit for riser poles. Developer installs
first 10'. City installs remainder.
3. Developer pours transformer pad(s) per city specs and design.
4. Developer installs pull boxes as per city specs and design. (pull boxes
provided by the city.
5. Developer provides digital AutoCAD 2000i version of plat and /or site plan.
email to rbolin(c�ci.college- station.tx.us
6. Developer provides load data for project.
7. Developer provides temporary blanket easement for construction
purposes.
8. Developer provides easements for electric infrastructure as installed for
electric lines.
9. Developer provides a 10' easement along eastside of property at s20d28'59 "e-
147.86.
Reviewed by: Ronnie Bolin Date: 6 -12 -03
NOTE: Any changes made to the plans, that have not been requested by the City of College Station, must be explained in your
next transmittal letter and "bubbled" on your plans. Any additional changes on these plans that have not been pointed out
to the City, will constitute a completely new review.
Page 2 of 2
MEMORANDUM
June 24, 2003
TO: Planning and Zoning Commission
FROM: Spencer Thompson
Email: sthompson @cstx.gov
SUBJECT: REPLAT for UNIVERSITY PARK PHASE II Lot 3B Block V
Item: Public hearing, discussion, and possible action on a Replat for University Park
Phase 11 Lot 3B Block V consisting of 4 lots on 5 acres generally located at 903
University Drive East.
Applicant: Garret Engineering for Jim Woods, Developer.
Staff Recommendations: Staff recommends approval of the plat as submitted.
Item Summary: The Applicant wishes to subdivide this commercial tract into 4 lots. All
lots will take access from University Drive via the platted access easement. Utilities are
to be extended to accommodate the subdivision. State Farm Insurance is currently
located on the adjacent Lot 3A. The tract was zoned C -B, however, that zoning
classification has been rolled into the C -1 class by the newly adopted UDO. A portion
of the subject property is in the Overlay District.
Comprehensive Plan Considerations:
Land Use Plan: Regional retail, zoned C -1.
Thoroughfare Plan: University drive is a major arterial.
Special Area Plans: University Dr. Study implemented the Overly District
Budgetary & Financial Summary: None
Attachments:
1. Area map
2. Application
MEMORANDUM
June 24, 2003
TO: Planning and Zoning Commission
FROM: Spencer Thompson
Email: sthompson @cstx.gov
SUBJECT: REPLAT for UNIVERSITY PARK PHASE II Lot 3B Block V
Item: Public hearing, discussion, and possible action on a Replat for University Park
Phase II Lot 3B Block V consisting of 4 Tots on 5 acres generally located at 903
University Drive East.
Applicant: Garret Engineering for Jim Woods, Developer.
Staff Recommendations: Staff recommends approval of the plat as submitted.
Item Summary: The Applicant wishes to subdivide this commercial tract into 4 lots. All
lots will take access from University Drive via the platted access easement. Utilities are
to be extended to accommodate the subdivision. State Farm Insurance is currently
located on the adjacent Lot 3A. The tract was zoned C -B, however, that zoning
classification has been rolled into the C -1 class by the newly adopted UDO. A portion
of the subject property is in the Overlay District.
Comprehensive Plan Considerations:
Land Use Plan: Regional retail, zoned C -1.
Thoroughfare Plan: University drive is a major arterial.
Special Area Plans: University Dr. Study implemented the Overly District
Budgetary & Financial Summary: None
Attachments:
1. Area map
2. Application
MEMORANDUM
June 24, 2003
TO: Planning and Zoning Commission
FROM: Spencer Thompson
Email: sthompson @cstx.gov
SUBJECT: REPLAT for UNIVERSITY PARK PHASE II Lot 3B Block V
Item: Public hearing, discussion, and possible action on a Replat for University Park
Phase II Lot 3B Block V consisting of 4 Tots on 5 acres generally located at 903
University Drive East.
Applicant: Garret Engineering for Jim Woods, Developer.
Staff Recommendations: Staff recommends approval of the plat as submitted.
Item Summary: The Applicant wishes to subdivide this commercial tract into 4 lots. All
lots will take access from University Drive via the platted access easement. Utilities are
to be extended to accommodate the subdivision. State Farm Insurance is currently
located on the adjacent Lot 3A. The tract was zoned C -B, however, that zoning
classification has been rolled into the C -1 class by the newly adopted UDO. A portion
of the subject property is in the Overlay District.
Comprehensive Plan Considerations:
Land Use Plan: Regional retail, zoned C -1.
Thoroughfare Plan: University drive is a major arterial.
Special Area Plans: University Dr. Study implemented the Overly District
Budgetary & Financial Summary: None
Attachments:
1. Area map
2. Application