Loading...
HomeMy WebLinkAbout03-00500180- 00076187 03 8 0 �� - oe Westfield Village Phase 6 Engineering Review Comment Response The following is a reply to the engineering review of the construction plans for phase 6 of the Westfield Village Subdivision dated August 14, 2003. 1. All public utility construction must be in a dedicated PUE. The PUE must be submitted to the City prior to plan approval. A PUE for all utilities not in the ROW is being prepared and will be submitted to the City. c 2. Sheet 2: Sidewalk required with street. Extend to end of street construction. The sidewalk is being extended to the end of the boundary of Phase 6 as required. The additional portion of Victoria is being constructed as a temporary turn - around as required by the city. A street is currently being planned to intersect Victoria at Station 49 +78.81 in conjunction with a future section of Edelweiss Gartens. We have left the sidewalk off intentionally to avoid its removal when this street is built. 3. Sheet 3: Remove "Typical 40' Subgrade Section" There are no prohibitions for this type of work in the city regulations and we believe the diagram is necessary on this project. The soil being excavated from Mountain Breeze Way is being used as fill on other portions of the subdivision. This diagram is the only information the contractor will have for the earthwork along Mountain Breeze Way. 4. Sheet 3: Section A -A should show 7" flex base. Sidewalk is required with street construction. Since a turn - around is being required on Victoria, we have attempted to design a facility that will serve that purpose, but can still be used with the future extension of Victoria Avenue. Our concern is that any turning movements by heavy vehicles will damage the surface course and it will become necessary to replace the asphalt before the city will accept it in the future. We have designed the temporary turn - around with 5.5 " of base and 1.5" of HMAC. As you can see in the detail, the asphalt is being left 1.5 " below the lip of the gutter. An additional 1.5" of HMAC will be added to this portion of the street with future construction of Mountain Breeze Way. We believe 3" of HMAC on 5.5" of base is a superior section to 7" of base and 1.5" of HMAC. The sidewalk is addressed in #2 above. • 5. Sheet 4: Curved storm sewer along Night Rain Drive not in accordance with Drainage Policy and Design Standards (DPDS). The use of curved storm sewers was approved by the Director of Public Works for Phase 1 of this subdivision so long as the joint deflections fall within the manufacturer's guidelines. We are unaware of a change in this policy. 6. Sheet 5: Outlets for Storm Drain A and B. Riprap in channel as shown constitutes modification to natural watercourse. When placing riprap in lieu of energy dissipation structure, you must show that velocities are reduced before entering natural channel. To our knowledge, there is no prohibition to the modification of an ephemeral stream through the placement of rip -rap. We are simply installing an outfall from a development into a natural watercourse (Lick Creek Tributary A) as done on many other public and private projects. The rip -rap is intended to provide a short section of lined channel where the velocity in the pipe slows to the velocity in the receiving stream. Energy dissipation occurs in the swirls and eddies that form at that point. If the streambed is not lined in this area, it is subject to washouts immediately below the pipe headwall. Rip -rap has proven to effectively reduce these washouts on previous projects. It has been accepted by all of the area governments, including College Station, and it is unclear why this application is any different than those previous installations. Formal studies of Lick Creek Tributary A were conducted in the drainage reports from Alexandria Subdivision and Westfield Subdivision. Those reports included computer models of the stream in the area where this outfall is being proposed. The maximum water velocity for both the 100-yr and 25-yr storm events is 3 fps, which is less than the maximum allowable for grass - lined waterways in the College Station DPDS. Any runoff coming from outfalls like the one being proposed will immediately slow to the velocity in the natural watercourse. With the exception of some eddies in the stream, there are no erosive velocities to consider. Energy dissipaters at the base of the outfall will be completely ineffective because they will be submerged by water in the stream. In our opinion, this is not an appropriate application of energy dissipation devices as described in the College Station DPDS. The water velocity in the receiving stream will not be significantly changed by such devices if installed at this location. 7. Sheet 6: Manhole required at end of S -2 per TNRCC 317. The plans have been changed to show this revision. 8. Remove references to "existing" sewer where sewer does not exist. The plans have been changed to show this revision. 9. Sheet 7: Inset B. Cross not permitted as shown. Install additional valve or replace cross with tee. The cross is designed correctly with valves on three of the four legs. As indicated previously, a street is being planned at the Victoria/Mountain Breeze Way associated with a future phase of Edelweiss Gartens. The water line extension shown here is intended to serve that future development. 10. 2" sand cushion required on sidewalk/pathway detail. The plans have been changed to show this revision. Westfield Village Subdivision Phase 6 Engineer's Estimate July 24, 2003 Item Estimated Description Unit Quantity Total No. Unit Price Paving Construction 1 Mobilization Lump Sum 1 10,000.00 10,000 2 Clearing and Grubbing Acre 8.3 1,000.00 8,300 3 Excavation C.Y. 2,546 3.75 9,548 4 1.5" HMAC Surface Course S.Y. 7,672 3.80 29,154 5 6" Lime Stabilized Subgrade S.Y. 9,701 3.00 29,103 6 Extra Lime Ton 60 85.00 5,100 7 7" Crushed Limestone Base S.Y. 3,837 6.75 25,900 8 6" Crushed Limestone Base S.Y. 3,467 5.80 20,109 9 5.5" Crushed Limestone Base S.Y. 368 5.50 2,024 10 Curb and Gutter, all types L.F. 3,752 7.50 28,140 11 Concrete Apron S.Y. 663 35.00 23,205 12 4" Sidewalk S.F. 18,493 2.60 48,082 13 Sidewalk Ramps S.F. 546 9.00 4,914 Paving Subtotal 243,577 Drainage System Construction 14 18" Reinf. Concrete Pipe, Str. Backfill L.F. 190 35.00 6,650 15 21" Reinf. Concrete Pipe, Str. Backfill L.F. 449 37.00 16,613 16 24" Reinf. Concrete Pipe, Str. Backfill L.F. 241 42.00 10,122 17 27" Reinf. Concrete Pipe, Non -Str. Backfill L.F. 127 43.00 5,461 18 30" Reinf. Concrete Pipe, Str. Backfill L.F. 420 48.00 20,160 19 33" Reinf. Concrete Pipe, Str. Backfill L.F. 30 55.00 1,650 20 33" Reinf. Concrete Pipe, Non -Str. Backfill L.F. 37 52.00 1,924 21 10' Curb inlet EACH 4 2,900.00 11,600 22 5' Curb inlet EACH 5 2,200.00 11,000 23 Sloped Headwall for 33" RCP EACH 1 1,000.00 1,000 24 Sloped Headwall for 27" RCP EACH 1 950.00 950 25 Plug for 18" RCP EACH 1 75.00 75 26 Inlet Protection EACH 9 35.00 315 27 Silt Fence L.F. 1,080 2.00 2,160 28 Construction Exit S.Y. 67 5.00 335 29 Dry Rip Rap S.F. 206 5.00 1,030 30 Fibermulch Seeding S.Y. 11,000 0.60 6,600 31 Trench Safety (storm sewer) L.F. 1,494 1.00 1,494 Drainage System Subtotal 99,139 Page 1 of 2 Westfield Village Subdivision Phase 6 Engineer's Estimate July 24, 2003 Item Estimated Description Unit Quantity Total No. Unit Price Water System Construction 32 6" PVC, C900 Water Line, Str. Backfill L.F. 151 20.00 3,020 33 6" PVC, C900 Water Line, Non -Str. Backfill L.F. 257 14.00 3,598 34 8" PVC, C900 Water Line, Str. Backfill L.F. 1,840 23.00 42,320 35 12" PVC C900 Water Line, Str. Backfill L.F. 785 30.00 23,550 36 Fire Hydrant Assembly EACH 2 2,200.00 4,400 37 6" Gate Valve EACH 1 450.00 450 38 8" Gate Valve EACH 5 650.00 3,250 39 12" Gate Valve EACH 4 1,100.00 4,400 40 2" Blow -Off Assembly EACH 5 525.00 2,625 41 6 "x 11.25 degree Bend EACH 4 175.00 700 42 6" x 13" Anchor Coupling EACH 2 100.00 200 43 8 "x 60" Anchor Coupling EACH 4 200.00 800 44 8 "x 13" Anchor Coupling EACH 1 160.00 160 45 8 "x 8" Tee EACH 1 250.00 250 46 8" x 6" Tee EACH 1 230.00 230 47 8 "x 1" Tapped Tee EACH 1 150.00 150 48 12 "x 8" Cross EACH 2 600.00 1,200 49 12 "x 60" Anchor Coupling EACH 2 400.00 800 50 12 "x 13" Anchor Coupling EACH 2 300.00 600 51 1.5" Water Ser., (avg. length = ft.) EACH 15 750.00 11,250 52 1" Water Ser., (avg. length = ft.) EACH 2 550.00 1,100 53 Trench Safety (water) L.F. 3,033 1.00 3,033 Water System Construction 108,086 Sewer System Construction 54 6" PVC, D -3034, Str. Backfill L.F. 248 29.00 7,192 55 8" PVC, D -3034, Str. Backfill L.F. 460 31.00 14,260 56 8" PVC, D -2241, Str. Backfill L.F. 20 33.00 660 57 Standard Manhole, 0 -8.00 feet EACH 2 1,850.00 3,700 58 Standard Manhole, 8.01 -10.00 feet EACH 1 2,050.00 2,050 59 4" Sewer Service > 10 ft. EACH 7 1,000.00 7,000 60 Trench Safety (sewer) L.F. 728 2.00 1,456 Sewer System Subtotal 36,318 Total Construction Cost $487,120 Alias OP ket * - * A �- r, i J 6 65923 / 2 \ , " , �� 7 /z /U3 Page 2 of 2